INTRODUCTION This document provides additional information and corrections to the
instructions provided in the Altivar
bulletin atv71e_installation_manual_en_v3 (module 1755849).
To facilitate cross referencing, the section headings in this bulletin match
the section headings in the Installation Manual. The page location of the
section headings are listed in the Contents of the Installation Manual.
Make the following changes to the Installation Manual.
IMPORTANT INFORMATION
®
71 Installation Manual, instruction
03/2008
Please Note
Replace the disclaimer note with the following:
Electrical equipment should be installed, operated, serviced, and
maintained only by qualified personnel. No responsibility is assumed by
Schneider Electric for any consequences arising out of the use of this
material.
1
Altivar® 71 Drive Controllers Errata to Bulletin atv71e_installation_manual_en_v3 30072-452-25
Before you begin 03/2008
BEFORE YOU BEGIN Read this document carefully and store it with the Installation Manual for
future reference.
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
• Read and understand this document and bulletin
atv71e_installation_manual_en_v3 before installing or operating the
Altivar 71 drive controller. Installation, adjustment, repair, and
maintenance must be performed by qualified personnel.
• The user is responsible for compliance with all international and national
electrical code requirements with respect to grounding of all equipment.
• Many parts of this drive controller, including the printed circuit boards,
operate at the line voltage. DO NOT TOUCH. Use only electrically
insulated tools.
• DO NOT touch unshielded components or terminal strip screw
connections with voltage present.
• DO NOT short across terminals PA/+ and PC/– or across the DC bus
capacitors.
• Before servicing the drive controller:
— Disconnect all power, including external control power that may be
present.
— Place a “DO NOT TURN ON” label on all power disconnects.
— Lock all power disconnects in the open position.
— WAIT 15 MINUTES to allow the DC bus capacitors to discharge.
Then follow the “Bus Voltage Measurement Procedure” on page 3 of
this bulletin to verify that the DC voltage is less than 42 V. The drive
LED is not an indicator of the absence of DC bus voltage.
• Install and close all covers before applying power or starting and
stopping the drive controller.
Failure to follow these instructions will result in death or serious
injury.
DANGER
UNINTENDED EQUIPMENT OPERATION
With regard to the connection diagrams for safety applications described
in the Altivar
• Refer to IEC 61508, Functional Safety of
Electrical/Electronic/Programmable Electronic Safety Related System,
Parts 1–7, 2000.
• Completely understand the applications and environment defined by
Safety Integrity Level 2 (SIL2) within IEC 61508.
• Do not exceed SIL2 ratings in the application of the product.
• The following terms are used in this document are used in the context
of Safety Integrity Level 2 of IEC 61508: power removal safety function,
safety-type signals, safely, and safe conditions.
Failure to follow these instructions can result in death, serious
injury, and equipment damage.
®
71 Installation Manual:
© 2008 Schneider Electric All Rights Reserved2
30072-452-25 Altivar® 71 Drive Controllers Errata to Bulletin atv71e_installation_manual_en_v3
03/2008 Preliminary Recommendations
PRELIMINARY RECOMMENDATIONS
Installing the AC choke on ATV71H•••Y
Insert the following safety message to this section.
drives
CAUTION
CONTROLLER DAMAGE
A 3–5% impedance input line reactor is required on all ATV71HC••Y drive
controller installations.
Failure to follow these instructions can result in equipment damage.
POSITION OF THE CHARGING LED Replace the Bus Voltage Measurement Procedure section with the
following:
Bus Voltage Measurement Procedure Before working on the drive controller, remove all power and wait 15
minutes to allow the DC bus to discharge. Then measure the DC bus
voltage between the PA/+ and PC/– terminals.
The DC bus voltage can exceed 1,000 Vdc. Use a properly rated voltagesensing device when performing this procedure. To measure the DC bus
voltage:
1. Disconnect all power.
2. Wait 15 minutes to allow the DC bus to discharge.
3. Measure the voltage of the DC bus between the PA/+ and PC/–
terminals to ensure that the voltage is less than 42 Vdc.
4. If the DC bus capacitors do not discharge completely, contact your local
Schneider Electric representative. Do not repair or operate the drive
controller.
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Read and understand the precautions in “Before you begin” on page 2 of
this Errata sheet before performing this procedure.
Failure to follow these instructions will result in death or serious
injury
© 2008 Schneider Electric All Rights Reserved