Bosch LV009, LV012, LV007, LV018, LV024 Installation And Maintenance Manual

...
0 (0)
LV MODEL
Installation and Maintenance Manual
8733944336 (2016/09)
2 | LV Heat Pump Series
CONTENTS
Key to Symbols...................................................................3
Model Nomenclature...........................................................4
General Description............................................................5
Moving and Storage............................................................5
Installation.........................................................................5
Step1 Check Job Site....................................................5
Step 2 Check Unit.........................................................5
Step 3 Locate Unit...................... ...................................6
Step 4 Mount The Unit...................................................7
Hanging Bracket Kit.......................................................8
Step 5 Check Duct System......... .....................................9
Step 6 Install Condensate Drain................. ......................9
Step 7 Pipe Connections..............................................10
Step 8 Wire Power Supply............................................10
Step 9 Wire Field Controls............................................12
Unit Controls ECM-UPM....................................................12
ECM Interface Board...................................................12
Safety Devices and the UPM control..............................12
Safety Features..........................................................13
Freeze Sensor............................................................14
Intelligent Reset..........................................................14
Lockout reset.............................................................14
Pre- Start- Up..................... ...............................................15
Air Coil......................................................................15
Units Mounted Non-Fused Disconnect Switch.................22
Hot Gas Reheat..........................................................24
Hot Gas Bypass..........................................................25
Internal 2-Way Water Valve..........................................25
Economizer...............................................................25
Certified Performance Table.............................................26
Fan Motors Options...........................................................27
Permanent Split Capacitor Motors (PSC)........................27
Constant Torque Motors (ECM).....................................28
Constant Airflow Motors (ECM).....................................30
Standard Blower Motor................................................32
Constant Torque ECM Blower Motor..............................33
Constant CFM ECM Blower Motor..................................34
Troubleshooting...............................................................35
Temperature Pressure Table.............................................40
Waterside pressure Drop Table..........................................46
Compressor Characteristics..............................................47
Corner Weights (HZ).........................................................48
Water Coil Volume............................................................48
Wiring Diagrams...............................................................49
Dimensional Drawings......................................................56
Vertical............................................................................56
Horizontal........................................................................57
Start Up...........................................................................15
Operating Limits........................................................ 15
Environment..............................................................15
Power Supply.............................................................15
Unit Starting Conditions...............................................15
Scroll Compressor Rotation..........................................16
Sequence Of Operation UPM........................................17
Sequence Of Operation ECM.......... ...............................18
Unit Start Up Cooling Mode...........................................19
Unit Start Up Heating Mode................. ..........................19
Flow Regulation..........................................................19
Antifreeze..................................................................20
Application Considerations...............................................20
Well Water Systems....................................................20
Cooling Tower/Boiler Systems......................................21
Geothermal Closed Loop Systems.................................21
Open Well Water Systems............................................22
Water Quality...................................................................22
Water Quality Table..........................................................23
Condensate Connections..................................................23
Piping..............................................................................24
Options............................................................................24
Extended Range.........................................................24
Maintenance....................................................................59
Information On Decommissioning......................................59
Protecting The Environment..............................................59
Components..............................................................59
Refrigerant................................................................59
Terminology.....................................................................60
Unit Check Out Sheet........................................................61
Notes...............................................................................62
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Key to Symbols | 3LV Heat Pump Series
KEY TO SYMBOLS
Warnings
Warnings in this document are identified by a warning triangle printed against a grey background. Keywords at the start of the warning indicate the type and seriousness of the ensuing risk if measures to prevent the risk are not taken.
The following keywords are defined and can be used in this document:
DANGER indicates a hazardous situation which, if
not avoided, will result in death or serious injury.
WARNING indicates a hazardous situation which, if
not avoided, could result in death or serious injury.
CAUTION indicates a hazardous situation which, if
not avoided, could result in minor to moderate injury.
NOTICE is used to address practices not related to
personal injury.
Important Information
This symbol indicates important information where there is no risk to property or people.
SAFETY WARNINGS
IMPORTANT: Read the entire instruction
manual before starting installation.
DANGER: Improper installation, adjustment, alteration, service, maintenance, or use can cause explosion, fire, electrical shock or other conditions which may cause personal injury or property damage. Consult a qualified installer, service agency, or your distributor or branch for information or assistance. The qualified installer or agency must use factory­authorized kits or accessories when modifying this product. Refer to the individual instructions packaged with the kits or accessories when installing.
WARNING: Before performing service or maintenance operations on the system, turn off main power to the unit. Electrical shock could cause personal injury or death.
WARNING: When working on equipment, always observe precautions described in the literature, tags, and labels attached to the unit. Follow all safety codes. Wear safety glasses and work gloves. Use a quenching cloth for brazing, and place a fire extinguisher close to the work area.
NOTICE: To avoid the release of refrigerant into the atmosphere, the refrigerant circuit of this unit must be serviced only by technicians who meet local, state, and federal proficiency requirements.
NOTICE: All refrigerant discharged from this unit must be recovered WITHOUT EXCEPTION. Technicians must follow industry accepted guidelines and all local, state, and federal statutes for the recovery and disposal of refrigerants. If a compressor is removed from this unit, refrigerant circuit oil will remain in the compressor. To avoid leakage of compressor oil, refrigerant lines of the compressor must be sealed after it is removed.
NOTICE: To avoid equipment damage, DO NOT use these units as a source of heating or cooling during the construction process. Doing so may affect the unit’s warranty. The mechanical components and filters will quickly become clogged with construction dirt and debris, which may cause system damage.
WARNING: Installation and servicing of this equipment can be hazardous due to system pressure and electrical components. Only trained and qualified personnel should install, repair, or service the equipment.
8 733 905 683 (2016/09)LV Heat Pump Series
//9 97& )/738% ;; 6$0;; ; ; $;; ; ;; ; ; 6%$
       
GENERAL ELECTRICAL OPTIONS (UP TO 5 AVAILABLE PER UNIT)
A-EMS RELAY
B-BLOWER MONITOR RELAY
C-COMPRESSOR MONITOR RELAY
D-PHASE MONITOR
E-PUMP/VALVE RELAY
G-BOILERLESS CONTROL
H-FLOW PROVING SWITCH
J-DISCONNECT SWITCH
K-FIRE ALARM RELAY/DUAL POWER
M-WIRE TO 208 V
X-AS DEFAULT FOR NON USED ELECTRICAL CODES
VOLTAGE
0 115/60/1
1 208-230/60/1
2 277/60/1
3 208-230/60/3
4 460/60/3
5 575/60/3
8 220-240/50/1
A 380-420/50/1
SIZE
007, 009, 012, 015,
018, 024, 030, 036,
041, 042, 048, 060,
070
LV
CABINET CONFIGURATION
HZ-HORIZONTAL
VT-VERTICAL
CF-COUNTERFLOW
COAX OPTIONS
C-COPPER
N-CUPRO-NICKEL
WATER CONNECTIONS
F-FRONT
B-BOTTOM
M-MARINE
RETURN AIR CONFIGURATION
L-LEFT
R-RIGHT
DISCHARGE AIR CONFIGURATION
T-TOP
S-STRAIGHT
E-END
B-BOTTOM
FAN/MOTOR OPTIONS
P-STANDARD PSC
A- CONSTANT AI RFLOW ECM
T-CONSTANT TORQUE ECM
AIR COIL
U-UNCOATED
D-DUOGUARD
REVISION LEVEL
B-CURRENT
ELECTRIC HEAT
(SINGLE POINT)
X-NONE
A-5kW
B-7.5kW
C-10kW
CABINET CONSTRUCTION
A-GALVANIZED STEEL/1/2” STANDARD 1.5LB DUAL DENSITY FIBERGLASS
C-A-GALVANIZED STEEL/1/2” CLOSED CELL FOAM
D-A-GALVANIZED STEEL/1/2” STANDARD 1.5LB DUAL DENSITY FIBERGLASS, EXTRA QUIET
F-A-GALVANIZED STEEL/1/2” CLOSED CELL FOAM, EXTRA QUIET
APPLICATION
T-TXV OPTION
S-STANDARD RANGE
G-EXTENDED RANGE
AIR FILTRATION
1- STANDARD THROWAWAY FILTER W/4 SIDED FILTER RACK
4-MERV8-2” W/4 SIDED FILTER RACK
5-MERV13-2” W/4-SIDED FILTER RACK
REFRIGERATION CIRCUIT OPTIONS
X-NONE
H-HOT GAS REHEAT-ON OFF
B-HOT GAS BYPASS
C-HOT GAS BYPASS WITH HOT GAS REHEAT
S-STRAIGTH COOL
CONTROLS
X-NONE
M-DDC(MULTI PROTOCOL)(BACNET, MODBUS, N2
L-DDC-LONWORKS
WATER FLOW CONTROL OPTIONS
X-NONE
2-2 WAY SOLENOID VALVE
3-MEASURE FLOW (3GPM/TON)
4-2 WAY SOLENOID +MEASUREFLOW
6-WATER REGULATING VALVE CONNECTION
TRANSFORMER
4-40 VA
5-50 VA
7-75 VA
1-100 VA
STANDARD/SPECIAL
S-STANDARD
A-SPECIAL #1
B-SPECIAL #2
AGENCY OPTIONS
X-ETL (UL 1995)
C-CE (50 HZ ONLY)
E-ETL W/E-HEAT AND SINGLE POINT POWER
ECONOMIZER
X-NONE
E-ECONOMIZER WITH 3 WAY VALVE AND CONTROLS
CODE STRING LEVEL
CHANNEL
B-BOSCH
4 | Model Nomenclature LV Heat Pump Series
MODEL NOMENCLATURE
Not all Options are available on all models.
Figure # 1
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
General Description | 5LV Heat Pump Series
GENERAL DESCRIPTION
The LV series water-to-air heat pump provides an unmatched combination of performance, features and flexibility for both high performance new construction applications and replacement of existing water-to-air heat pumps. All units are certified by the Air conditioning, Heating and Refrigeration Institute (AHRI) to AHRI/ANSI/ASHRAE/ISO standard 13256-1 for water­to-air and brine-to-air heat pumps at both Water Loop Heat Pump and Ground Loop Heat Pump application points.
All Water-to-Air Heat Pumps conform to UL 1995 standard and are certified to CAN/CSA C22.2 No 236 by Intertek-ETL.
These units meet all current applicable requirements of ASHRAE 90.1. LV series units are designed to operate with entering fluid temperatures between 50°F and 100°F in cooling and 50°F and 80°F in heating with the base configuration. With the extended range option, LV series models can operate with entering fluid temperatures between 50°F and 110°F in cooling and between 20°F and 80°F in heating. LV units can accommodate a wide range of air temperatures, however, standard LV models should not be used for 100% outside air without consulting the factory applications group. 100% outside air routinely requires higher levels of dehumidification than is available from equipment designed for return air applications. LV series units are available in three basic configurations: vertical top supply air (VT), horizontal end supply air or straight through supply air (HZ) and counter flow down supply air (CF). Each of these configurations are available with either left or right hand return air. HZ models can have the supply air field converted from end discharge air to straight through with no extra parts required.
LV units are designed and rated for indoor installation only. LV units should not be installed in environments
that fall below freezing or exceed 100°F ambient. LV cabinets are constructed of heavy gauge G-90 galvanized steel and will resist most common types of corrosion for the life of the equipment.
LV series units are offered with a wide range of factory installed options including: PSC, constant torque ECM or constant air flow ECM fan motors; hot gas reheat; hot gas bypass; internal 2 way valves; tin plated air coils; 2“4-sided filter racks; MERV 13 filters (with constant airflow ECM motors); on board DDC controls; copper or cupro nickel water coils; water-side economizers and more refer to the unit model number for installed options..
Note that some options are offered in limited sizes and/or voltages.
On board safety features will protect the major unit components from damage under most foreseeable installation and operation problems.
MOVING AND STORAGE
If the equipment is not needed for immediate installation upon arrival at the job site, it should be left in its packaging and stored in a clean, dry area.
Units must be moved and stored in the normal upright position at all times. Use caution to avoid damage to filter racks and duct flanges when storing or handling units.
NOTICE: Never lift or move units by filter racks, external piping or attached options/ accessories.
NOTICE: Never stack units when transporting them.
NOTICE: When storing units: Do not stack units larger than 6 tons
capacity! Do not stack vertical or counter flow units
under 6 tons capacity more than 2 high Do not stack horizontal units 6 tons capacity
more than 3 high
INSTALLATION Step 1- Check Job Site
Installation, operation and maintenance instructions are provided with each unit. Before unit start-up, read all manuals and become familiar with unit and its operation. Thoroughly check out the system before operation. Complete the inspections and instructions listed below to prepare a unit for installation.
Horizontal Units
LV units are designed for indoor installation only. Be sure to allow adequate space around the unit for servicing.
Vertical Counter flow Units
LV Units are designed for indoor installations only. While vertical units are typically installed in a floor-level closet or a small mechanical room, the unit access guidelines for these units are very similar to those described for horizontal units.
Step 2- Check Unit
Upon receipt of shipment at the job site, carefully check the shipment against the bill of landing. Make sure all units have been received. Inspect each unit for damage. Ensure the shipping company makes proper notation of any shortages or damage on all copies of the freight bill.
Concealed damage not discovered during unloading must be reported to the shipping company.
Please inspect the product carefully for any defects or discrepancies. Should you identify any issue, contact the Bosch Wholesaler / Distributor you purchased the unit from.
8 733 905 683 (2016/09)LV Heat Pump Series
6 | Installation LV Heat Pump Series
1. Be sure that the location chosen for unit installation provides ambient temperatures maintained above freezing.
2. Be sure the installation location is isolated from sleeping areas, private offices and other acoustically sensitive spaces.
3. Be sure unit is mounted at a height sufficient to provide an adequate slope of the condensate lines. If an appropriate slope cannot be achieved, a field­supplied condensate pump may be required.
4. On horizontal units, allow adequate room below the unit for condensate drain trap and do not locate the unit above supply piping.
5. Provide sufficient space for duct connection. do not allow the weight of the duct work to rest on the unit.
6. Provide adequate clearance for filter replacement and drain pan cleaning. Do not allow piping, conduit, etc. To block filter access.
7. Provide sufficient access to allow maintenance and servicing of the fan and fan motor, compressor and coils. Removal of the entire unit from the closet should not be necessary.
8. Provide an unobstructed path to the unit within the closet or mechanical room. Space should be sufficient to allow return air to freely enter the space.
9. Provide ready access to water valves, fittings, and screwdriver access to unit side panels, discharge collar, and all electrical connections.
10. Where access to side panels is limited, pre-removal of the control box side mounting screws may be necessary for future servicing.
Protection
Once the units are properly positioned on the job site, cover them with either a shipping carton, vinyl film, or an equivalent protective covering. Cap opens ends of pipes stored on the job site. This precaution is especially important in areas where painting, plastering or spraying of fireproof material, etc. Is not yet complete. Foreign material that accumulates within the units can prevent proper start-up and require costly clean-up operations. Before installing any of the systems components, be sure to examine each pipe, fitting valves and remove any dirt or foreign material found in or on these components.
Inspect Unit
1. Compare the electrical data on the unit nameplate with ordering and shipping information to verify that the correct unit has been shipped.
2. Verify that the unit is the correct model for the entering water temperature of the job.
3. Do not remove the packaging until the unit is ready for installation.
4. Verify that the refrigerant tubing is free of kinks or dents, and that it does not touch other unit components.
5. Inspect all electrical connections. Be sure connections are clean and tight at the terminals.
6. Remove any blower support styrofoam from underneath the blower.
7. Remove any shipping brackets from the unit attached to the pallet.
Step 3- Locate the Unit
Locate the unit in an indoor area that allows easy access to the filter, front access panel and blower access panel, and has enough room for service personnel to perform maintenance and repair work. Provide sufficient room to make fluid, electrical and duct work connections. Locate the unit in conditioned space and avoid installation in corrosive environments. If the unit is installed in a confined space, such as a closet, provisions must be made for return air to freely enter the face of the unit’s air coil. Unit condensate drains are not internally trapped. Allow room below the unit base for horizontal and counter flow models for an adequate condensate trap.
NOTICE: These units are not approved for outdoor installation; therefore, they must be installed inside the structure being conditioned space. Do not locate in areas that are subject to freezing.
NOTICE: Do not locate the unit above supply piping. Do not locate the unit in areas subject to freezing or in areas subject to temperature or humidity extremes.
NOTICE: LV series packaged units are not approved for outdoor installation. Units must be installed in conditioned space that is not subject to extremes of temperature or humidity to avoid cabinet sweating and/or equipment damage.
NOTICE: Do not use LV series units for temporary heating, air conditioning or ventilation during construction, especially when plastering, sanding or painting. Care should be taken to avoid introduction of dust, paint or debris into the air coil.
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Installation | 7LV Heat Pump Series
Vibration Mounting Pad
Step-4 Mount The Unit
Duct Flanges
The Unit heat pump feature foldout return and supply air duct flanges. These fold-out flanges allow the heat pumps to more easily fit through doorways and other tight spaces, and also prevent damage in shipping and handling.
It is recommended that all fold-out flanges be folded out once the heat pump is installed to ensure that return and supply airflow is not obstructed. These Flanges can be easily folded using standard or duckbill pliers.Once folded out these flanges can be used to support light duct work loads.
Mounting Vertical Units
LV Series vertical and counter flow units should be mounted level on a vibration absorbing pad slightly larger than the unit base in order to minimize vibration transmission from the unit to the building structure. See Figure #2 It is generally not necessary to anchor the unit unless required by local code.
All major service access for the LV Series vertical and counter flow models is from the front side of the unit. When installing the unit in a confined space such as a closet, ensure that the service panel screws are accessible, that the filter can be replaced without damage and that water and electrical connections are accessible. For models with a unit mounted disconnect switch, make sure the switch can be easily seen and operated.
To reduce sound transmission, units should be installed using flexible electrical conduit and hose kits. Care should be taken to ensure that no part of the unit cabinet is touching part of the building structure. For ducted return applications, a flexible duct connection should be used.
Mounting Horizontal Units
While horizontal units may be installed on any level surface strong enough to hold their weight, they are typically suspended above a ceiling by threaded rods. The rods are usually attached to the unit corners by hanger bracket kits included with the unit.
NOTICE: Horizontal (HZ) units must be installed pitched toward the condensate drain connection 1/8” per foot.
Horizontal units installed above the ceiling must conform to all local codes. An auxiliary drain pan if required by code, should be at least four inches larger than the bottom of the heat pump. Plumbing connected to the heat pump must not come in direct contact with joists, trusses, walls, etc. Some applications require an attic floor installation of the horizontal unit. In this case the unit should be set in a full size secondary drain pan on top of a vibration absorbing mesh. The secondary drain pan prevents possible condensate overflow or water leakage damage to the ceiling. The secondary drain pan is usually placed on a plywood base isolated from the ceiling joists by additional layers of vibration absorbing mesh. In both cases, a 3/4” drain connected to this secondary pan should be run to an eaves at a location that will be noticeable.
NOTICE: If the unit is located in a crawl space, the bottom of the unit must be at least 4" above grade to prevent flooding of the electrical parts due to heavy rains.
Figure # 2 Mounting Vertical Units
8 733 905 683 (2016/09)LV Heat Pump Series
8 | Installation LV Heat Pump Series
Hanging Brackets Locations
Hanging Bracket Kit Installation instructions
All horizontal units come with Hanging Bracket Kit to facilitate suspended unit mounting using threaded
rod. Hanging Brackets are to be installed as shown in Figure#3
Figure # 3
This kit includes the following: (5) Brackets (5) Rubber Vibration Isolators (8) Screws # 10x1/2” (10) Bolts 1/4-28x1/2” hex Bolt (not used on this model) The following are needed and are to be field provided: Threaded rod (3/8” max dia) Hex Nuts Washers (1-3/4” min O.D.)
1. Remove and discard factory provided screws from location where Hanging Brackets will be installed shown in Figure#4
2. Mount 4 Brackets to unit corner post using the bolts
provided in the kit as shown on Figure # 5
WARNING: Do not re-use screws removed from the unit on step 1 to mount the hanging Brackets to the unit.
Figure # 5
WARNING: Follow all applicable codes
requirements when hanging this unit. Selecting threaded rod material, etc.
3. Install Rubber Grommet on the bracket as shown in
Figure# 6.
4. Hang the unit and assemble the field provided Thread
Rod, Nuts and Washers on to the Brackets as shown in Figure# 6.
DANGER: Rods must be securely anchored to the ceiling.
Figure # 4
Figure # 6
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Installation | 9LV Heat Pump Series
Step-5 Check Duct System
All units are provided with a return air duct flange and supply air duct connections. Refer to unit dimensional drawings (Page# 55).
A flexible duct connector is recommended for supply and return air duct connections on metal duct systems. All metal ducting should be insulated with a minimum of 1”inch duct insulation to avoid heat loss or gain and prevent condensate from forming during the cooling operation. Application of the unit to uninsulated duct work is not recommended as the unit’s performance will be adversely affected. If the unit will be installed in a new installation with new duct work, the installation should be designed using current ASHRAE procedures for duct sizing. If the unit will be connected to an existing duct system, a check should be made to assure that the duct system has the capacity to handle the air required for the unit application. If the duct system is too small, larger duct work must be installed. Be certain to check for existing leaks and repair. The duct system and all diffusers should be sized to handle the designed air flow quietly. To maximize sound attenuation of the unit blower, the supply and return air plenums should be insulated. There should be no direct straight air path through the air grill into the heat pump. The return air inlet to the heat pump must have at least one 90° turn away from the space return air grill. If air noise or excessive air flow are a problem, the blower speed can be changed to a lower speed to reduce air flow.
6. Turn the blower panel 180 support brackets are now at the bottom of the blower.
7. Insert the blower panel with the blower and motor into the desired location. Be careful not to damage the refrigerant coils or any other internal unit components. Screw the panel into place.
8. Replace the wires between the blower motor and electrical box. Make sure to connect wires to the proper speed taps.
9. Replace the blower access panel.
10. Reconnect power to the unit.
°
so that the blower
Step 6-Install Condensate Drain.
A drain line must be connected to the heat pump and pitched away from the unit a minimum of 1/8-inch per foot to allow the condensate to flow away from the unit. This connection must be in conformance with local plumbing codes. A trap must be installed in the condensate line to ensure free condensate flow. (Heat pumps are not internally trapped). A vertical air vent is sometimes required to avoid air pockets. (See figure # 7)
.
Do not connect discharge ducts directly to the blower outlet. Use ashrae guidelines for duct sizing
The factory filter rack should be left in place on a free return system.
Horizontal Supply Air Configuration Conversion
The supply air location on horizontal units can be quickly field converted from end blow to straight through or vice versa. To convert the supply air direction, follow the steps below:
1. If connected to power, shut off the unit and disconnect switch or circuit breaker.
2. Unscrew and remove the blower access panel.
3. Disconnect the wires from the unit electrical box to the blower motor. Note which speed taps are wired for units with PSC or constant torque motors.
4. Unscrew and carefully remove the blower panel with the blower and motor attached. Be careful not to damage the refrigerant coils or any other internal unit components.
5. Remove the blower support brackets from the bottom of the blower housing and relocate them to the top of the blower housing.
Figure # 7 Condensate Drain
The depth of the trap depends on the amount of positive or negative air pressure on the drain pan while the unit fan is operating. A second Trap must not be included. The Horizontal unit should be pitched approximately
1/4 inch towards the drain in both directions, to facilitate condensate removal.
(see figure # 8)
Figure # 8 Pitched Unit
8 733 905 683 (2016/09)LV Heat Pump Series
10 | Installation LV Heat Pump Series
Step 7-Pipe Connections
Depending on the application there are 3 types of WSHP piping systems to choose from: water loop, ground water-and ground loop.
All WSHP units use female pipe thread fittings for water connections. When making piping connections considered the following:
Insulation may be required on piping to avoid condensation in the case where fluid in loop piping operates at temperatures below dew point of surrounding air.
Piping systems that contains steel pipes or fittings may be subject to galvanic corrosion. Dielectric fittings may be used to isolate the steel parts of the system to avoid galvanic corrosion.
Water Loop applications
Water loop applications usually include a number of units plumbed to a common piping system. Maintenance of any of the units can introduce air into the system. Therefore, air elimination equipment comprises a major portion of the mechanical room plumbing. The flow rate is usually set between 2.25 and 3 GPM per ton of cooling capacity. For proper maintenance and servicing, pressure-temperature (P/T) ports are necessary for temperature and flow verification. In addition to complying with any applicable codes, consider the following for system piping:
Piping systems using water temperatures below
o
F require 1/2 inch closed cell insulation on all
50 piping surfaces to prevent pipe sweating.
Avoid all plastic to metal threaded fittings due to the potential for leaks.
Teflon tape thread sealant is recommended to seal pipe threads.
Use Backup wrench. Do not overtighten connections.
Route piping to avoid service access areas to unit.
Flush the piping system prior to operation to remove dirt and foreign materials from the system.
Ground Loop Applications
Temperatures between 20ºand 110ºF and a cooling capacity of 2.25 to 3 GPM of flow per ton is recommended. In addition to complying with any applicable codes, consider the following for system piping:
Limit piping materials to only polyethylene fusion in the buried sections of the loop.
Do not use galvanized or steel fittings at anytime due to corrosion.
Avoid all plastic to metal threaded fittings due to the potential for leaks. Use a flange fitted substitute.
Do not overtighten connections.
Route piping to avoid service access areas to unit.
Use pressure-temperature (P/T) plugs to measure flow and pressure drop.
Step 8 Wire Field Power Supply
High Voltage
All field-installed wiring must comply with the National Electric Code as well as all applicable local codes. Refer to the unit electrical data on the unit nameplate for wire and branch circuit protection sizing. Supply power voltage and phasing should match the required voltage and phasing shown on the unit nameplate. Operating the unit below the minimum voltage, above the maximum voltage or with incorrect phasing can result in poor system performance or damage to the heat pump. All field wiring should be installed by qualified and trained personnel. Refer to the unit wiring diagram for field connection requirements.
Power wiring to the heat pump should be enclosed in flexible conduit to minimize the transmission of vibration from the unit cabinet to the building. For heat pumps with unit mounted disconnect switches, field power should be connected to the marked terminals on the disconnect switch. For heat pumps without unit-mounted disconnect switches (except for 460-volt units noted below and units with dual power supply), power is connected to the line (L) side of the compressor contactor and the ground lug in the unit electrical box.
Units with Dual Power Supplies
For models with dual power supplies, one power supply feeds the compressor and a second power supply feeds the unit fan motor and control circuit. The compressor power supply should be connected to the line (L) side of the compressor contactor. The fan motor and control circuit power supply meets the voltage, amperage and phase requirements of its load. Refer to the unit name plates for requirements.
460-V Models with Constant Airflow Motors
The 460-V heat pumps with the constant airflow motor option require a properly sized neutral wire with the power supply wiring in addition to the three high voltage wires and the ground wire. These units employ a 265-V motor that requires power from one phase of the 460-V supply and the neutral wire.
CAUTION: The unit ground wire should never be used as a neutral wire
Transformer Settings for 208/230-V Units
As a factory built, all 208/230-V operation unless the wire for 208-v option is ordered. For Job sites with a 208-V power supply, the primary leads on the unit transformer will need to be changed from 240-V to 208­V. Refer to the unit wiring diagram for details.
NOTICE: All High voltage connections must be torqued as specified on contactor specifications to avoid the risk of overheating
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Installation | 11LV Heat Pump Series
Low Voltage
For heat pumps with PSC or constant torque fan motors, all thermostat wiring is connected to a terminal block located in the unit electrical box. For heat pumps with a constant airflow fan motor thermostat wiring is connected to a removal terminal strip located on the ECM (Electronically Commutated Motor) control board located in the electrical box. Refer to the unit wiring diagram for connection details.
CAUTION: Never route control wiring through the same conduit as power supply wiring.
Unless provided with DDC controls, the unit heat pump can be controlled by most commonly available single­stage heat pump thermostats. Note that the reversing valve on the unit is energized when the unit is in the cooling mode. Thermostats should be located on an interior wall away from supply ducts. Avoid locations subject to direct sunlight, drafts, external walls. Thermostat wiring should be 18AWG (American Wire Gage). refer to the installation instructions of the thermostats for further details.
NOTICE: Exceptionally long runs of thermostat wire should be avoided to prevent voltage drops in the control circuit.
See Table #1 and #2 for recommended length
Unit heat pumps are supplied with a 50VA control transformer as a standard. Models with DDC, hot gas reheat or an economizer are supplied with a 75 VA transformer. The 75 VA and 100 VA transformers are available as optional components for most models (size 018 and larger for 100 VA). The VA capacity of the transformer should be considered when connecting low voltage accessories to the heat pump such as thermostats or solenoid valves. Table # 3 shows the VA draw of factory mounted components in the low voltage heat pump. The total VA draw of the heat pump internal components plus attached accessories must be lower than the VA capacity of the unit control transformer.
NOTICE: Exceeding the transformer capacity can result in low control voltage, erratic unit operation or damage to the heat pump.
Thermostat to HVAC Equipment
The thermostat may not function properly if the total resistance of any of the thermostat to HVAC equipment wires exceeds 2.5 ohms. To ensure that wire length does not cause excess resistance, refer to Table # 1and ensure that the wires from the thermostat to the HVAC equipment are not too long.
Table 1: Copper wire size
22 AWG (0.33mm 2)
20 AWG (0.50mm 2)
18 AWG (0.75mm 2)
Maximum recommended
wire length
150 ft (46m)
240 FT (73m)
385 FT (117m)
Remote Sensor to Programmable Thermostat
Because remote temperature sensors measure resistance, very long cable runs can cause slight errors in the measurement. For the highest temperature reading accuracy, avoid exceeding the maximum recommended wire lengths show in Table # 2.
Table 2: Copper wire size
22 AWG (0.33mm 2)
20 AWG (0.50mm 2)
18 AWG (0.75mm2)
Maximum recommended
remote sensor wire length
1000 ft (300m)
1500 FT (450m)
2500 FT (750m)
Table 3: Low Voltage VA Draw
STANDARD CONSTRUCTION
Component VA Component VA Component VA
Blower Relay (PSC motors only)
Reversing Valve Solenoid
Compressor Contactor
UPM Board 2
Total VA draw 22-26 Total VA
6-7 Total from
8-9 Additional
6-8 Hot Gas
HOT GAS REHEAT OR ECONOMIZER
‘Standard’
Control Relays
Reheat Solenoid
draw
22-26 Monitor Relay
12-14 Internal 2
8-9 LED
42-49
OPTIONAL COMPONENTS
(VA draw per relay)
Way Motorized Valve
Annunciator
6-7
7
1
8 733 905 683 (2016/09)LV Heat Pump Series
12 | Installation LV Heat Pump Series
10
1
27
8
9
5
11
46
3
1
2 3 4
5
6
7
9
10
11
1213
17
14
15
16
8
Step 9- Wire Field Controls Units Controls ECM-UPM
ECM Interface Board
Thermostat wiring is connected to the 10 pin screw type terminal block on the lower center portion of the ECM Interface Board. In addition to providing a connecting point for thermostat wiring, the interface board also translates thermostat inputs into control commands for the Electronic Commutated Motor (ECM) DC fan motor and displays an LED indication of operating status. The thermostat connections and their functions are as
shown in figure # 9
Safety devices and the UPM control
Each unit is factory provided with a UPM board controller that controls the compressor operation and monitors the safety.
If the unit is being connected to a thermostat with a malfunction light, this connection is made at the unit malfunction output or relay.
Figure # 9
[1] Motor harness plug [2] Blower CFM adjustment [3] Motor settings [4] Dehumidification indication [5] Thermostat contact inputs [6] CFM count indicator [7] Thermostat input status indication [8] Reheat digital outputs [9] Thermostat outputs [10] 24 VAC [11] Hot gas Re-heat enable switch
Figure # 10
[1] Board Power Indicator [2] UPM Status LED Indicator [3] Water Coil Freeze Protection Temperature Selection [4] Air Coil Freeze Protection Temperature Selection [5] UPM Board Settings [6] Water Coil Freeze Connection [7] Air Coil Freeze Connection [8] LED Unit Display Connection [9] 24VAC Power Input [10] Compressor Contact Output [11] High Pressure Switch Connection [12] Call for Compressor Y1 [13] Low Pressure Switch Connection [14] 24VAC Power Common [15] Condensate Overflow Sensor [16] Dry Contact [17] UPM Ground Standoff
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Safety features includes the following:
High pressure switch located in the refrigerant discharge line and wired across the HPC terminals on the complete UPM board
Low pressure switch located in the unit suction line and wired across terminals LPC1 and LPC2 on the complete UPM Board
Complete UPM board dry contacts are normally open (NO).
Water side freeze protection sensor, mounted close to condensing water coil, monitors refrigerant temperature between condensing water coil and thermal expansion valve. If temperature drops below or remains at freeze limit trip for 30 seconds, the controller will shut down the compressor and enter a soft lockout condition. The default freeze limit trip is 26°F, however this can be changed to
°
F by cutting the R30 or Freeze1 resistor located
15 on top of DIP switch SW1. For resistor location. If unit is employing a fresh water system (no anti­freeze protection), it is extremely important to have the Freeze 1 R30 resistor set to 26
°
F in order to shut down the unit at the appropriate leaving water temperature and protect heat pump from freezing if a freeze sensor is included.
Evaporator freeze sensor, mounted between the thermal expansion device and the evaporator, monitors refrigerant temperature between the evaporator coil and thermal expansion valve. If temperature drops below or remains at freeze limit trip for 30 seconds, the controller will shutdown the compressor and enter into a soft lockout condition. The default freeze limit trip is 26
°
F See Figure # 10
The condensate overflow protection sensor is located in the drain pan of the unit and connected to the COND terminal on the complete UPM board.
Figure # 11 Water side Freeze Protection Sensor
NOTICE: If unit is employing a fresh water
system (no anti-freeze protection), it is extremely important to have the Freeze1
°
R30 resistor set to 26
F in order to shutdown the unit at the appropriate leaving-water temperature and protect your heat pump from freezing if a freeze sensor is included.
Installation | 13LV Heat Pump Series
Figure # 12
The UPM Board includes the following features:
ANTI-SHORT CYCLE TIMER: 5 minute delay on
break timer to prevent compressor short cycling.
RANDOM START: Each controller has a unique
random start delay ranging from 270 to 300 seconds on initial power up to reduce the chance of multiple units simultaneously starting at the same time after power up or after a power interruption, thus avoiding creating large electrical spike.
LOW PRESSURE BYPASS TIMER: If the compressor
is running and the low pressure switch opens, the controller will keep the compressor ON for 120 seconds. After 2 minutes if the low pressure switch remains open, the controllers will shutdown the compressor and enter a soft lockout. The compressor will not be energized until the low pressure switch closes and the anti-short cycle time delay expires. if the low pressure switch opens 2-4 times in 1 hour, the unit will enter a hard lockout power to the unit would need to be reset.
BROWNOUT/SURGE/POWER INTERRUPTION: The
brownout protection in the UPM board will shut down the compressor if the incoming power falls below 18 VAC. The compressor will remain OFF until the voltage is above 18 VAC and ANTI-SHORT CYCLE TIMER (300 seconds) times out. The unit will not go into a hard lockout.
MALFUNCTION OUTPUT: Alarm output is normally
open (NO) dry contact. If pulse is selected the alarm output will be pulsed. The fault output will depend on the on the dip switch setting for “ALARM”. If it is set to “CONST”, a constant signal will be produced to indicate a fault and the unit requires inspection to determine the type of fault. If is set to “PULSE”, a pulse signal is produced and a fault code is detected by a remote device indicating the fault. See LED fault indication for blink code explanation. The remote device must have a malfunction detection capability when the UPM board is set to “PULSE”.
8 733 905 683 (2016/09)LV Heat Pump Series
14 | Installation LV Heat Pump Series
If 24 VAC output is needed. R must be wired to ALR-COM terminal; 24 VAC will be available to the ALR-OUT terminal when the unit is in the alarm condition.
DISPLAY OUTPUT: The display output is a pulse
output connected to the Unit Diagnostics Display (UDD) and it pulses 24VAC when the unit is in an lockout alarm condition.
TEST DIP SWITCH: A test dip switch is provided to
reduce all time delays settings to 10 seconds during troubleshooting or verification of unit operation. In test mode the fault LED will flash 5 times in cooling or 3 times in heating for five minutes.
NOTICE: Operation of unit in test mode can lead to accelerated wear and premature failure of components. The “TEST” switch must be set back to “NO” after troubleshooting/servicing.
Table 4: UPM Fault Blink Codes
LED Blinks Fault Fault Criteria
All fault conditions
None None
1
High Pressure
2
3
4Condensate
5 Air Coil Freeze
6Brown Out
Low Pressure
Water Coil
Freeze
Condition
Overflow
Condition
UPM Board Factory Default Settings
TEMP 26°F LOCKOUT 2 RESET Y ALARM PULSE TEST NO
nominal
Refrigerant discharge
pressure has
exceeded 600 PSIG Refrigerant suction
pressure has fallen
below 40 PSIG
Refrigerant
temperature to the
water coil has fallen
below 26°F for 30
seconds
Condensate levels in
the unit drain pan are
too high
Refrigerant
temperature to the air
coil has fallen below 26°F for 30 seconds
Control voltage has
fallen below 18 VAC
Freeze Sensor
°
The default setting for the freeze limit trip is 26
F
(sensor number 1); however this can be changed to 15°F by cutting the R30 resistor located on top of the DIP
switch SW1, freeze limit trip should only be changed to 15°F when a closed loop system with appropriate antifreeze mixture is used.Since freeze sensor 2 is dedicated to monitor the evaporator coil it is recommended to leave the factory default setting on the board. The complete UPM controller will constantly monitor the refrigerant temperature with the sensor mounted close to the condensing water coil between the thermal expansion valve and water coil. If temperature drops below or remains at the freeze limits for 30 seconds. The controller will shut the compressor down and enter into a soft lockout condition. Both the status LED and the alarm contact will be active. The LED will flash three times the code associated with this alarm condition. If this alarm occurs 2 times (or 4 if DIP switch is set to 4) within an hour the complete UPM controller will enter into a hard lockout condition. It will constantly monitor the refrigerant temperature with the sensor mounted close to the evaporator between the thermal expansion valve and evaporator coil as shown in figure # 11 If temperature drops below or remains at the freeze limit trip for 30 seconds, the controller will shut the compressor down and enter into a soft lockout condition. Both the status LED and the alarm contact will be active. The LED will flash three times the code associated with this alarm condition. If this alarm occurs 2 times (or 4 if DIP switch is set to 4 within an hour the controller will enter into a hard lockout condition.
NOTICE: It is recommended to have a flow switch to prevent the unit from running if water flow is lost.
Intelligent Reset
If a fault condition is initiated, the 5 minute delay on break time period is initiated and the unit will restart after this delays expire and if the fault condition has been resolved. During this period the fault LED will indicate the cause of the fault. If the fault condition still exists or occurs 2 or 4 times (depending on 2 or 4 settings for lockout dip switch) before 60 minutes, the unit will go into a hard lockout and requires a manual lockout reset. A single condensate overflow fault will cause the unit to go into hard lockout immediately, and will require a manual lockout reset.
Lockout Reset
A hard lockout can be reset by turning the unit thermostat off and then back on. When the RESET dip switch is set to “Y” or by shutting off power at the circuit breaker when the RESET DIP switch is set to “R”.
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
THERMOSTAT OPTIONS Y1 First Stage Compressor Operation GFan O Reversing Valve (energized in cooling) W1 Auxiliary Electric Heat (runs in conjunction
with compressor)
Pre-Start-Up | 15LV Heat Pump Series
Air coil
To obtain maximum performance, clean the air coil before starting the unit. A 10% solution of dishwasher detergent and water is recommended for both sides of the coil. Rinse thoroughly with water.
START-UP
Use the procedure below to initiate a proper start-up
NC Transformer 24 VAC Common (extra
connection)
C1 Transformer 24 VAC Common (primary
connection) R Transformer 24 VAC Hot H Dehumidification Mode
UPM DIP SWITCH DEFAULT POSITION
lockout 42
reset
alarm
test
RY
Cont pulse
yes no
PRE-START-UP System Checkout
After completing the installation, and before energizing the unit, the following system checks should be made prior to initial startup:
1. Verify that the supply voltage to the heat pump is in accordance with the nameplate ratings.
2. Make sure that all electrical connections are tight and secure.
3. Check the electrical fusing and wiring for the correct size.
4. Verify that the low voltage wiring between the thermostat and the unit is correct.
5. Verify that the water piping is complete and correct.
6. Check that the water flow is correct, and adjust if necessary.
7. Check the blower for free rotation, and that it is secured to the shaft.
8. Verify that vibration isolation has been provided.
9. Unit is serviceable. Be certain that all access panels are secured in place.
10. Verify that the blower support has been removed.
11. Verify that duct work has been properly fastened to supply and return duct collars.
12. Make sure return air filters are positioned correctly in the filter rack if removed during installation.
NOTICE: This equipment is designed for indoor installation only
Operating Limits
Environment
This equipment is designed for indoor installation only. Extreme variations in temperature, humidity and corrosive water or air will adversely affect the unit performance, reliability and service life.
Power Supply
A voltage variation of
voltage is acceptable.
Unit Starting Conditions
Minimum ambient temperature for heating operation is 45°F. Minimum entering air for heating is 40°F. Minimum entering water temperature for heating with standard range units is 50°F and for extended range units is 20°F. Air and water flow rates must be within the cataloged range.
These operating limits are not suitable for continuous operating conditions. Assume that such start up conditions are for the purpose of bringing the building space up to occupancy temperature.
WARNING: When the disconnect switch is closed, high voltage is present in some areas of the electrical panel. Exercise caution when working with the energized equipment.
1. Restore power to system.
2. Turn thermostat fan position to ON. Blower should start.
3. Balance airflow at registers.
4. Adjust all valves to the full open position and turn on the line power to the heat pump unit.
5. Operate unit in the cooling cycle first, then the heating cycle. for unit operating limits. Allow 15 minutes between cooling and heating tests for pressure to equalize.
± 10% of nameplate utilization
8 733 905 683 (2016/09)LV Heat Pump Series
16 | Start-Up LV Heat Pump Series
Two factors determine the operating limits of a unit: entering air temperature and water temperature. Whenever any of these factors are at a minimum or maximum level, the other two factors must be at a normal level to ensure proper unit operation.
Scroll Compressor Rotation (4 and 5 Tons only)
It is important to be certain that the compressor is rotating in the proper direction. To determine whether or not compressor is rotating in the proper direction see as follows:
1. Connect services gases to suction and discharge pressure fittings.
2. Energize the compressor.
3. The suction pressure should drop and the discharge pressure should rise, as is normal on any start up.
If the suction pressure does not drop and the discharge pressure does not rise to normal levels:
1. Turn off power to the unit. Install disconnect tag.
2. Reverse any two of the unit power leads.
3. Reapply power to the unit and verify pressures are correct.
The suction and discharge pressure levels should now move to their normal start-up levels. When the compressor is rotating in the wrong direction, the unit makes more noise and does not provide cooling. After a few minutes of reverse operation, the scroll compressor internal overload protection will open, thus activating the unit lockout. This requires a manual reset. To reset, turn the thermostat on and then off.
There is a 5 minute time delay before the compressor will start.
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Sequence Of Operation
CC
LOCKOUT CAN BE SET
TO 4 VIA DIP SWITCH
BLINK CODE ON STATUS LED
SOFT LOCKOUT
RECORD ALARM
START COUNTER (IF APPLICABLE)
CC OUTPUT = ON
NO
YES
LPC
=CLOSED
FRZ >TEMP
LIMIT
Y1 = ON
TIME > 30
SEC
CON > 0
POWER/ SWITCHES/SENSOR
STATUS CHECK
START TIMER
NO
YES
NO
YES
NO
YES
T > ASC OR
RS SEC
YES
NO
NO
YES
START
ANTI SHORT CYCLE
INITIAL
POWER UP
YES
NO
START
RANDOM START UP
START
COUNTER NEEDED?
YES
COUNT = 2
OR
COUNT = 4
BLINK CODE ON STATUS LED
DISPLAY OUTPUT = PULSE
ALR OUTPUT = ON/PULSE
NO
YES
HARD
LOCKOUT?
CC OUTPUT = OFF
V > 18VAC
NO
YES
YES
NO
BLINK CODE
ON STATUS LED
NO
RESET ON
Y
CLEAR FAULTS
R = 24VAC
NO
YES
NO
YES
NO
YES
HPC =
CLOSED
RESET ON R
CC OUPUT=
ON
NO
YES
TIME >
120 SEC
START TIMER
NO
YES
CNT = CNT+1
Start-Up | 17LV Heat Pump Series
Figure # 13
8 733 905 683 (2016/09)LV Heat Pump Series
18 | Start-Up LV Heat Pump Series
Figure # 14
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Unit Start Up Cooling Mode
1. Adjust the unit thermostat to the warmest position. Slowly reduce the thermostat position until the compressor activates.
2. Check for cool air delivery at unit grille a few minutes after the unit has begun to operate.
3. Verify that the compressor is ON and that the water flow rate is correct by measuring pressure drop through the heat exchanger using P/T plugs. Check elevation and cleanliness of the condensate lines; any dripping could be a sign of a blocked line. Be sure the condensate trap includes a water seal.
4. Check the temperature of both supply and discharge water.
5. Check air temperature drop across the coil when compressor is operating. Air temperature drop should be between 15
o
and 25oF.
Unit Start Up Heating Mode
Oper
1. Turn thermostat to lowest setting and set
2. Slowly turn the thermostat to a higher temperature
3. Check for warm air delivery at the unit grille within a
4. Check the temperature of both supply and
5. Once the unit has begun to run, check for warm air
6. Check air temperature rise across the coil when
7. Check for vibration, noise and water leaks.
Operate the unit in heating cycle after checking the cooling cycle. Allow 5 minutes between tests for the pressure or reversing valve to equalize.
thermostat switch to HEAT position.
until the compressor activates.
few minutes after the unit has begun to operate.
discharge water. If temperature is within range, proceed. If temperature is outside the range, check the heating refrigerant pressures.
delivery at the unit grille.
compressor is operating. Air temperature rise should be between 20
°
F and 30°F after 15 minutes
load.
Start-Up | 19LV Heat Pump Series
WARNING: Open the disconnect switch and
secure it in an open position before flushing the system.
Flushing
Once the piping is complete, units require final purging and loop charging. A flush cart pump of at least 1.5 hp is needed to achieve adequate flow velocity in the loop to purge air and dirt particles from the loop. Flush the loop to purge air and dirt particles from the loop. Flush the loop in both directions with a high volume of water at a
high velocity. Follow the steps below to properly flush the loop:
1. Verify that the power is off.
2. Fill loop with water from the hose through flush cart before using flush cart pump to ensure an even fill. Do not allow the water level in the flush cart tank to drop below the pump inlet line to prevent air from filling the line.
3. Maintain a fluid level in the tank above the return tee to avoid entering back into the fluid.
4. Shutting off the return valve that connects into the flush cart reservoir it will allow 50 psig surges to help purge air pockets. This maintains the pump at 50 psig.
5. To purge, keep the pump at 50 psig until maximum pumping pressure is reached.
6. Open the return valve to send a pressure surge through the loop to purge any air pockets in the piping system.
7. A noticeable drop in fluid level will be seen in the flush cart tank. This is the only indication of air in the loop.
If air is purged from the system while using a 10 inch PVC flush tank, the level drop will only be 1 to 2 inches, since liquids are incompressible. If the level drops more than this, flushing should continue since air is still being compressed in the loop. If level is less than 1 to 2 inches, reverse the flow.
Flow Regulation
Flow regulation can be accomplished by two methods. Most water control valves have a flow adjustment built into the valve. By measuring the pressure drop through the unit heat exchanger, the flow rate can be determined. Adjust the water control valve until the desired flow is achieved. Since the pressure constantly varies, two pressure gages may be needed in some applications.
An alternative method is to install a flow control device. These devices are typically an orifice of plastic material designed to allow a specified flow rate that are mounted
on the outlet of the water control valve. Occasionally these valves produce a flow noise that can be reduced by applying some back pressure. To accomplish this, slightly close the leaving isolation valve of the well water setup.
8. Repeat this procedure until all air is purged.
9. Restore power.
Antifreeze may be added before, during or after the flushing process. However, depending on when it is added in the process, it can be wasted. refer to the Antifreeze section for more detail. Loop static pressure will fluctuate with the seasons. Pressures will be higher in the winter months than during the warmer months. this fluctuation is normal and should be considered when charging the system initially. Run the unit in either heating or cooling for several minutes to condition the loop to a homogenous temperature. When complete, perform a final flush and pressurize the loop to a static pressure of 40 to 50 psig for winter months or 15 to 20 psig for summer months.
8 733 905 683 (2016/09)LV Heat Pump Series
20 | Application Considerations LV Heat Pump Series
After pressurization, be sure to remove the plug from the end of the loop pump motor to allow trapped air to be discharged and to ensure the motor housing has been flooded. Be sure the loop flow center provides adequate flow through the unit by checking pressure drop across the heat exchanger.
Antifreeze
In areas where entering loop temperatures drop below 40°F or where piping will be routed through areas subject to freezing, antifreeze is needed. Alcohols and glycols are commonly used as antifreeze agents. Freeze protection should be maintained to 15
°
F below the lowest expected entering loop temperature. For example, if the lowest expected entering loop
temperature is 30°F, the leaving loop temperature would be 22°F to 25°F. Therefore, the freeze protection should be at 15
°
F (30°F-15°F=15°F).
NOTICE: All alcohols should be pre-mixed and pumped from a reservoir outside the building or introduced under water level to avoid build up of fumes.
1. Flex Duct Connection.
2. Low Voltage Control Connection
Figure # 15
3. Vibration Pad Antifreeze concentration should be checked from a well mixed sample using a hydrometer to measure specific gravity.
4. Ball Valves
5. Solenoid Valve Slow Closing
6. Condensate Drain Connection
7. Drain Valves Freeze Protection Selection
The 26°F FP1 factory setting (water) should be used to avoid freeze damage to the unit. Once antifreeze is selected. the (FP1 jumper) should be clipped on the control to select the low temperatures (antifreeze 15°F) set point to avoid nuisance faults.
8. Hose Kits (optional)
9. Pressure Tank (optional)
10. P/T Ports (optional)
11. Line Voltage Connection
12. Electric Heater Line Voltage Disconnect
13. Unit Line Voltage Disconnect
APPLICATION CONSIDERATIONS Well Water Systems
Copper is adequate for ground water that is not high in mineral content. Should your well driller express concerns regarding the quality of the well water available or should any know hazards exists in your area, we recommend proper testing to assure the well water quality is suitable for use with water source equipment. (See water quality table on page #21) in conditions anticipating moderate scale formation or in brackish water a cupro-nickel heat exchanger is recommended. In well water applications water pressure must always be maintained in the heat exchanger. This can be accomplished with a control valve or a bladder type expansion tank. When using a single water well to supply both domestic water and the heat pump care must be taken to ensure that the well can provide sufficient flow for both. In well water applications a slow closing solenoid valve must be used to prevent water hammer. Solenoid valves should be connected across Y1 and C1 on the interface board for all. Make sure that the VA draw of the valve does not exceed the contact rating of the thermostat.
LV Heat Pump Series8 733 944 336 (2016/09) Subject to change without prior notice
Loading...
+ 44 hidden pages