Flowserve VK 14 User Manual

Page 1
GESTRA
GESTRA Steam Systems
VK 14 VK 16
Installation Instructions 818577-00
Vaposcope Sightglass VK 14, VK 16
1
Page 2
Page
Important Notes
Usage for the intended purpose ............................................................................................................. 4
Safety note ............................................................................................................................................ 4
Danger ................................................................................................................................................... 4
Pressure Equipment Directive (PED) ...................................................................................................... 4
Explanatory Notes
Scope of supply ..................................................................................................................................... 5
Description ............................................................................................................................................ 5
Function................................................................................................................................................. 5
Technical Data
Corrosion resistance .............................................................................................................................. 6
Sizing..................................................................................................................................................... 6
Name plate / marking ............................................................................................................................ 6
Design
VK 14, VK 16.......................................................................................................................................... 7
Key ........................................................................................................................................................ 8
Installation
Danger ................................................................................................................................................... 9
VK 14, VK 16 .......................................................................................................................................... 9
Design with flanges ............................................................................................................................... 9
Design with screwed sockets ................................................................................................................ 9
Design with socket-weld ends............................................................................................................. 10
2
Page 3
Contents – continue –
Page
Commissioning
VK 14, VK 16........................................................................................................................................ 10
Operation
VK 14, VK 16........................................................................................................................................ 10
Maintenance
®
VK 14, DN 15, 20, 25: Replacing MAXOS
VK 14, DN 40, 50: Replacing MAXOS® safety sightglass ..................................................................... 11
VK 16, DN 15, 20, 25, 40, 50: Replacing MAXOS® safety sightglass ................................................... 11
Tools.................................................................................................................................................... 12
Torques ............................................................................................................................................... 12
A. F. ..................................................................................................................................................... 12
Spare Parts
Spare parts list .................................................................................................................................... 13
Decommissioning
Danger ................................................................................................................................................. 13
Disposal ............................................................................................................................................... 13
safety sightglass ............................................................... 11
Annex
Declaration of Conformity .................................................................................................................... 14
3
Page 4
Important Notes
Usage for the intended purpose
VK 14, VK 16 Use Vaposcope sightglass only as sight flow indicators for monitoring flow in pipes. Use this equipment only within the specified pressure and temperature ratings and check corrosion resistance and chemical suitability for the application in question.
Safety note
The equipment must onyl be installed and commissioned by qualified staff. Maintenance and service work must only be performed by adequately trained persons who have a
recognised level of competence.
Danger
The equipment is under pressure during operation. When loosening flanged connections or sealing plugs, hot water or steam may escape. This presents the danger of severe scalds to the whole body. The equipment becomes hot during operation. This presents the risk of severe burns to hand and arms. Installation and maintenance
work should only be carried out at room temperatures. Before servicing the equipment or loosening flanged connections or sealing plugs
make sure that all connected lines are depressurised (0 bar) and the equipment has cooled down to room temperature.
Sharp edges on internals present a danger of cuts to hands. Always wear industrial gloves for installation and maintenance work.
Pressure Equipment Directive (PED)
The equipment fulfills the requirements of the Pressure Equipment Directive PED 97/23/EC. For applications with fluids of group 2. With CE marking (apart from equipment according to section 3.3).
4
Page 5
Explanatory Notes
Scope of supply
VK 14
1 Vaposcope sightglass VK 14 1 Installation manual
VK 16
1 Vaposcope sightglass VK 16 1 Installation manual
Description
The GESTRA Vaposcope is a sight flow indicator specially designed for monitoring flow conditions in pipelines. If installed upstream of steam traps the Vaposcope can be used for checking the traps for steam loss or for banking up of condensate.
VK 14 sightglass PN 16
VK 16 sightglass PN 40
Function
The GESTRA Vaposcope has no moving parts. The sightglass permits visual inspection of condensate conditions. Condensate or steam (gas) are directed through the water seal by the deflector. As the specific gravity of steam is lower than that of condensate the steam passes over the condensate and depresses the condensate level.
5
Page 6
Technical Data
Corrosion resistance
When used for its intended purpose the safe functioning of the equipment will not be impaired by corrosion.
Sizing
The body must not be subjected to sharp increases in pressure. The dimensional allowances for corrosion reflect the latest state of technology.
Name plate / marking
For pressure and temperature ratings see indications on body or specifications on the name plate. For more information refer to GESTRA technical literature, such as data sheets and Technical Information.
According to EN 19 the following indications are stated on the name plate and the body:
Type designation
Pressure class PN or Class
Material number
Max. temperature
Stamp on body, e. g. specifies the quarter and the year of production
(Example: 4
th
quarter 2004).
4
04
Direction of flow
6
Size
Nominal pressure
{
Max. temperature
CE marking (if required)
Nominal pressure
Page 7
Design VK 14, VK 16
E
Fig. 1
VK 14, DN 15-25
A
B
C
B
D
Fig. 2
VK 14, DN 40, 50 VK 16, DN 15–50
A
B
F
C
B
G
H
7
Page 8
Key
Name plate
A
Sightglass gasket
B
MAXOS® safety sightglass
C
Spherical washer
D
Union nut
E
Mica disk (standard item with VK 16)
F
Flange
G
Hexagon-head cap screw
H
MAXOS® is a registered trademark of SCHOTT AG, Grünenplan, Deutschland
8
Page 9
Installation
Danger
Danger of severe injuries, death and destruction caused by the explosion of explosive gas-air mixtures.
An electrically insulated installation of the equipment between pipe flanges can cause static electricity. If the equipment is to be installed in explosive-risk areas, appropriate measures have to be taken in order to discharge static electricity (earthing)!
VK 14, VK 16
The Vaposcope should be installed in accordance with the flow direction arrow and upsteam of the steam trap with the deflector pointing downwards. The equipment can be used in horizontal or vertical pipelines without any modification.
Design with flanges
1. Take position of installation into account.
2. Observe the direction of flow. The flow arrow is on the name plate.
3. Consider space required for opening or servicing the equipment. When the Vaposcope is installed
a minimum space of 70 mm is required for replacing the sightglass
4. Remove plastic plugs. They are only used as transit protection.
5. Clean seating surfaces of both flanges.
6. Install Vaposcope.
C.
Design with screwed sockets
1. Take position of installation into account.
2. Observe the direction of flow. The flow arrow is on the name plate.
3. Consider space required for opening or servicing the equipment. When the Vaposcope is installed
a minimum space of 70 mm is required for replacing the sightglass
4. Remove plastic plugs. They are only used as transit protection.
5. Clean threads of screwed sockets.
6. Install Vaposcope.
C.
9
Page 10
Installation – continued –
Design with socket-weld ends
1. Take position of installation into account.
2. Observe the direction of flow. The flow arrow is on the name plate.
3. Consider space required for opening or servicing the equipment. When the Vaposcope is installed
a minimum space of 70 mm is required for replacing the sightglass
4. Remove plastic plugs. They are only used as transit protection.
5. Clean socket-weld ends.
6. Apply arc welding processes 111 and 141 in accordance with ISO 4063.
Attention
Only qualified welders certified e. g. according to EN 287-1 may weld the equipment
into pressurised lines.
It is not necessary to remove the sightglasses before welding the equipment in
place. Only if an annealing process is applied remove the sightglasses beforehand.
C.
Commissioning
Make sure that the flanged connections of the VK 14, VK 16 are tightly bolted and leakproof.
Operation
With some operating modes VK 14 and VK 16 must be serviced. For more information see section “Maintenance”.
10
Page 11
Maintenance
The GESTRA sightglass Vaposcope VK 14/VK 16 does not require special maintenance. However, if used in new installations which have not been rinsed the equipment should be checked and cleaned after the commissioning procedure.
VK 14, DN 15, 20, 25: Replacing MAXOS® safety sightglass
1. Observe danger note on page 4.
2. Carefully unscrew union nuts old safety sightglasses
3. Make sure that all old sightglass gaskets the body.
4. Remove dirt and deposits from the sightglass body.
5. Insert new sightglass gaskets
6. Insert spherical washers in the union nuts E.
7. Screw in union nuts
VK 14, DN 40, 50: Replacing MAXOS® safety sightglass
1. Observe danger note on page 4.
2. Unscrew hexagon-head cap screws safety sightglasses
3. Make sure that all old sightglass gaskets the body.
4. Remove dirt and deposits from the sightglass body.
5. Insert new sightglass gaskets
6. Apply heast-resistant lubricant to hexagon-head cap screws
7. Mount new sightglass gaskets hexagon-head cap screws
8. Screw in hexagon-head cap screws
E with a torque of 130 Nm.
C.
E and remove spherical washers D, old sightglass gaskets B and
C.
B are completely removed from the seating surfaces of
B in the body.
D, new sightglass gaskets B and new MAXOS
®
safety sightglasses C
H and remove flange G, old sightglass gaskets B and old
B are completely removed from the seating surfaces of
B in the body.
H (e. g. WINIX 2150).
B and new MAXOS
®
safety sightglasses C with flanges G and
H.
H with a torque of 55 Nm.
VK 16, DN 15, 20, 25, 40, 50: Replacing MAXOS® safety sightglass
1. Observe danger note on page 4.
2. Unscrew hexagon-head cap screws disks
F and old safety sightglasses C.
3. Make sure that all old sightglass gaskets the body.
4. Remove dirt and deposits from the sightglass body.
5. Insert new sightglass gaskets
6. Apply heast-resistant lubricant to hexagon-head cap screws
7. Mount new sightglass gaskets with flanges G and hexagon-head cap screws H.
8. Screw in hexagon-head cap screws torque of 55 Nm.
WINIX® 2150 is a registered trademark of WINIX GmbH, Norderstedt
H and remove flange G, old sightglass gaskets B, mica
B are completely removed from the seating surfaces of
B in the body.
H (e. g. WINIX 2150).
B, new mica disks F and new MAXOS
H A. F. 18 (19) with a torque of 30 Nm and A. F. 24 with a
®
safety sightglasses C
11
Page 12
Maintenance – continued –
Tools
Spanner A. F. 60, DIN 3113, form B
Spanner A. F. 24, DIN 3113, form B
Spanner A. F. 18, DIN 3113, form B
Torque spanner 25 – 130 Nm, ISO 6789
Torques in Nm
VK 14
metInoitangiseD5251ND0504ND
E
tunnoinU031
H
VK 16
metInoitangiseD5251ND0504ND
H
All torques are based at 20°C room temperature.
A. F.
VK 14
metInoitangiseD5251ND0504ND
E
tunnoinU06.F.A
H
VK 16
metInoitangiseD5251ND0504ND
H
swercspacdaeh-nogaxeH 06
swercspacdaeh-nogaxeH0306
swercspacdaeh-nogaxeH 42.F.A
swercspacdaeh-nogaxeH81.F.A42.F.A
12
Page 13
Spare Parts
Spare parts list
VK 14
metInoitangiseD
C, B, F
C, B
1
) Kit consisting of: 2 Sightglasses 45 x 10
4 Sightglass gaskets 35 x 46 x 1 2 Mica disks
2
) Kit consisting of: 2 Sightglasses 80 x 15
4 Sightglass gaskets 66 x 82 x 1
VK 16
metInoitangiseD
C, B, F
1
) Kit consisting of: 2 Sightglasses 45 x 10
2
) Kit consisting of: 2 Sightglasses 80 x 20
4 Sightglass gaskets 35 x 46 x 1 2 Mica disks
4 Sightglass gaskets 66 x 82 x 1 2 Mica disks
edockcotS 5251ND
steksag.lcnissalgthgiS
1
sksidacimdna
)
2
steksag.lcnissalgthgiS
) 884307
984307
edockcotS 5251ND
steksag.lcnissalgthgiS
sksidacimdna
1
984307
)094307
edockcotS
05,04ND
edockcotS
05,04ND
2
)
Decommissioning
Danger
Risk of severe burns and scalds to the whole body! Before loosening flanged connections or sealing plugs, make sure that all connected
lines are depressurised (0 bar) and cooled down to room temperature (20°C).
Disposal
Dismantel the equipment and separate the waste materials. For the disposal of the equipment observe the pertinent legal regulations concerning waste disposal.
13
Page 14
Annex
Declaration of Conformity
We hereby declare that the equipment VK 14 and VK 16 conform to the following European Directive:
EC Pressure Equipment Directive (PED) No. 97/23 of 29 May 1997 (apart from equipment
according to section 3.3) Applied conformity assessment procedure: Annex III, Module H, verified by the Notified Body 0525. This declaration is no longer valid if modifications are made to the equipment without consultation
with us.
Bremen, 2nd February 2004
GESTRA AG
Head of the Design Dept.
Uwe Bledschun
Academically qualified engineer
Quality Assurance Representative
Lars Bohl
Academically qualified engineer
14
Page 15
For your notes
15
Page 16
Agencies all over the world:
www.gestra.de
GESTRA
España
GESTRA ESPAÑOLA S.A.
Luis Cabrera, 86-88 E-28002 Madrid Tel. 00 3491 /51 52032 Fax 00 3491 /41 36 747; 51 52 036 E-mail: aromero@flowserve.com
Great Britain
Flowserve Flow Control (UK) Ltd.
Burrel Road, Haywards Heath West Sussex RH 16 1TL Tel. 00 44 14 44 / 31 44 00 Fax 00 44 14 44 / 31 45 57 E-mail: gestraukinfo@flowserve.com
Italia
Flowserve S.p.A.
Flow Control Division Via Prealpi, 30 l-20032 Cormano (MI) Tel. 00 39 02/66 32 51 Fax 00 3902 / 66 32 55 60 E-mail: infoitaly@flowserve.com
Polska
GESTRA POLONIA Spolka z.o.o.
Ul. Schuberta 104 PL - 80-172 Gdansk Tel. 00 48 58 /306 10 -02 od 10 Fax 00 48 58 /306 33 00 E-mail: gestra@gestra.pl
Portugal
Flowserve Portuguesa, Lda.
Av. Dr. Antunes Guimarães, 1159 Porto 4100-082 Tel. 0035122/6198770 Fax 0 0351 22/ 610 7575 E-mail: jtavares@flowserve.com
USA
Flowserve DALCO Steam Products
2601 Grassland Drive Louisville, KY 40299 Tel.: 00 15 02 / 4 95 01 54, 4 95 17 88 Fax: 00 15 02 / 4 95 16 08 E-Mail: dgoodwin@flowserve.com
GESTRA AG
P. O. Box 10 54 60, D-28054 Bremen Münchener Str. 77, D-28215 Bremen Tel. +49 (0) 421 35 03 - 0 Fax +49 (0) 421 35 03- 393 E-Mail gestra.ag@flowserve.com Internet www.gestra.de
818577-00/705c · © 2004 GESTRA AG · Bremen · Printed in Germany
16
Loading...