Making final checks..........................................................................20
1
SUMMARY
Environmental conditions
• The higher the humidity in the place where the machine is installed,
the lower the insulation performance of its electric parts becomes.
This results in the premature degradation of the electric parts. Do
not install the machine in such a humid place.
• Where the ambient temperature is not higher than 5°C (41°F), keep
the machine and hydraulic unit energized during the day's work.
• Install the machine in a place where it is not subjected to dust, dirt,
and organic or corrosive gases.
• Keep the machine at least 10 m (33 ft) away from a welder or any
other equipment that may produce electric noise and magnetic fields.
Power supply
Power requirement: 200/230/400/460 V, AC, 3 phases, 50/60 Hz
Power cable: Composed of four conductors (including grounding
conductor) and thick enough to carry required power
Model Power voltage
200 V 230 V 400 V 460 V 200/230V 400 V 460 V
3512 37 A 32.2 A 18.5 A 15.9 A
5012 44 A 38.3 A 22 A 18.9 A
5020 44 A 38.3 A 22 A 18.9 A
8020 44 A 38.3 A 22 A 18.9 A
8025 44 A 38.3 A 22 A 18.9 A
1025 59 A 51.3 A 29.5 A 25.4 A
1030 59 A 51.3 A 29.5 A 25.4 A
1253
200/230/400
/460 V
59 A 51.3 A 29.5 A 25.4 A
Full load current
NOTICE
● Supply the machine from a power source independent of a welder or any
other equipment that may produce line voltage variations.
Power cable and ground
conductor (AWG)
2
2
2
2
2
2
2
2
5.5 mm2
(10)
2
8 mm
(8)
2
8 mm
(8)
2
8 mm
(8)
2
8 mm
(8)
14 mm
(6)
14 mm
(6)
14 mm
(6)
2
2
2
8 mm
(8)
14 mm
(6)
14 mm
(6)
14 mm
(6)
14 mm
(6)
22 mm
(4)
22 mm
(4)
22 mm
(4)
5.5 mm2
(10)
8 mm2
(8)
8 mm2
(8)
8 mm2
(8)
8 mm2
(8)
14 mm2
(6)
14 mm2
(6)
14 mm2
(6)
2
Machine installation
3
LOCATION
The place where the machine is to be installed must have an ample
floor space. Refer to the machine dimensions given in the table below.
Also take the following points into account:
• There must be no pillars and other obstacles in the area where the
tools are mounted and removed. (At least 835 mm (32.9 in.) long
tools must be able to be horizontally mounted and removed.)
• The ceiling must be at least 1000 mm (40 in.) from the top of the
machine.
• There must be an additional space to place a tool storage case and
an air compressor.
• There must be a work space where the worksheets can be easily
moved in and out and where maintenance and part quality check can
be smoothly performed. Especially, a work space of 1000 mm (40
in.) or more must be available at the rear of the machine, and an
enough space must be available for the door of the electrical
enclosure to be opened.
NOTICE
● Do not install the machine in a place where it is exposed to dust from such
operations as sandblasting and to direct sunlight, rain or wind.
When lifting the machine, apply the wire rope sling to the lifting ribs at
the top of the frame, slowly lift and carry the machine to the location,
and slowly lower the machine at the location. The wire rope sling must
be strong enough to carry the weight of the machine. (For the weight
of the machine, see the serial number plate attached to the machine.)
WARNING
● Carrying the machine is very dangerous.
Have a qualified contractor perform the
carrying work.
5
Using rollers
First jack up the front bottom of the machine under the left and right
main cylinders, and place rollers under the front feet of the machine.
Then slowly jack up the rear bottom of the machine, and place rollers
under the rear feet of the machine. Pay attention to the balance of the
machine when jacking up. Fix the rollers to the machine through the
anchor bolt holes. Slowly roll the machine to its location.
The shaft marked by an asterisk (✼) is used to connect the two rollers
at the right side of the machine. (Three rollers are shown in the
drawing.)
NOTICE
● Be sure to first jack up the front bottom of the machine under the main
cylinders.
● The machine has a center of gravity at its front. If the rear bottom of the
machine is jacked up without paying attention to its balance, the machine
may tip over, resulting in a very dangerous situation.
6
FOUNDATION
To maintain bending accuracy, install the machine on a flat concrete
floor that is strong enough to carry the weight of the machine and is not
likely to subside.
Unit: mm (in.)
CLEANING
Model A B
3512 2570 (101.26) 1990 (78.41)
5012 2570 (101.26) 1990 (78.41)
5020 3250 (128.05) 1985 (78.21)
8020 3290 (129.63) 2060 (81.17)
8025 3790 (149.33) 2060 (81.17)
1025 3790 (149.33) 2060 (81.17)
1030 4290 (169.03) 2060 (81.17)
1253 4310 (169.81) 2075 (81.76)
After the machine is installed on the foundation, clean it. Particularly,
remove all rust-preventive grease from the punch holders, the die
holders, and the top surface of the lower beam, using cleaning oil.
NOTICE
● Do not use a solvent or scraper that removes the paint of the machine.
7
SUPPLYING HYDRAULIC OIL
The hydraulic unit is located at the rear of the machine. Remove the
cover of the hydraulic unit, and pour the recommended hydraulic oil into
the hydraulic unit tank to slightly above the center mark of the oil gauge
when the lower beam is at the lower limit.
Model Tank capacity
3512, 5012, 5020, 8020, 8025 70 (18.4)
1025, 1030, 1253 90 (23.7)
Recommended oil
For use at normal temperature: Esso Teresso 46 and Shell Tellus Oil 46
(ISO VG56 Viscosity Index 113)
For use at lower temperature: Esso Spinesso 22 and Shell Tellus Oil
C22
Liters (US gal)
8
REMOVING SHIPPING BRACKETS
After the machine has been installed in place, remove the shipping
brackets securing the backgauge. The shipping brackets are each
fixed with two bolts. (Replace the bolts in their holes.)
9
SUPPLYING ELECTRIC POWER
WARNING
NOTE
● The machine needs a 200/230/400/460 V and 3-phase power supply.
● Use the power cable and grounding conductor that suit the power to be
handled.
● Have a qualified electrician perform all
electric work to prevent accidents and
damage.
● Before making the electrical connections,
be sure to turn off the shop circuit
breaker.
● Be sure to connect the grounding
conductor for safety.
● Use the shop circuit breaker and
grounding conductor exclusively for the
machine, and separate from those of other
equipment such as welders, drills,
sanders, and grinders.
Changing power supply parts
If the power supply voltage is different from the transformer and motor
connection voltage shown on the label affixed to the electrical
enclosure of the machine, the power supply parts must be changed.
For the wiring of each part, refer to the electric circuit diagram in the
appendix.
Change the power supply parts as described below.
1 Turn off the shop circuit breaker.
2 Open the door of the electrical enclosure at the left side of the
machine.
3 Turn off the circuit breaker QF1.
4 Turn off the motor circuit breaker QM1.
5 Change the following parts:
• Circuit breaker QF1
• Motor circuit breaker QM1
• Thermal relay FR1
• Fuses F1 and F2
• Varistors RV1 to RV3
10
6 Change the main motor power cables.
• When changing from 200/230 V to 400/460 V
Disconnect the three cables between the thermal relay and the
lower terminal block XT2, and install two jumper connectors at
the lower terminal block XT2.
• When changing from 400/460 V to 200/230 V
Remove the two jumper connectors from the lower terminal
block XT2, and connect the three cables between the thermal
relay and the lower terminal block XT2.
200/230 V connections
No.From Marker tube Length Marker tube To
1 FR1-2 U 350 Y XT2-Y (upper)
2 FR1-4 V 350 Z XT2-Z (upper)
3 FR1-6 W 350 X XT2-X (upper)
400/460 V connections
No.From Marker tube Length Marker tube To
1 XT2-X
(upper)
2 XT2-Y
(upper)
X 150 Y XT2-Y
Y 150 Z XT2-Z
(upper)
(upper)
11
7 Change the primary taps of the transformer TC1 as shown below.
8 Set the thermal relay FR1 at the values shown in the table below.
Model 3512 5012 5020 8020 8025 1025 1030 1253
Hydraulic pump motor
output: kW (HP)
200 V22.4 29.9 29.9 29.9 29.9 40.3 40.3 40.3
Thermal relay
setting: A
230 V19.5 26 26 26 26 35 35 35
400 V13.2 17.8 17.8 17.8 17.8 20.7 20.7 20.7
460 V11.5 15.5 15.5 15.5 15.5 18 18 18
5.5
(7.5)
7.5
(10)
7.5
(10)
7.5
(10)
7.5
(10)
11
(15)
11
(15)
11
(15)
12
Connecting power cable
Connect the power cable to the machine as described below.
1 Turn off the shop circuit breaker.
2 Open the door of the electrical enclosure at the left side of the
machine.
3 Turn off the machine circuit breaker.
4 Run the power cable from the shop circuit breaker through the
hole into the electrical enclosure.
5 Connect the power cable to the power input terminals L1, L2, and
L3 in the electrical enclosure.
6 Connect the grounding conductor to the ground terminal PE.
NOTE
● Use a grounding conductor of at least the same size as that of the
power cable conductors.
7 After the electric wiring connections are completed, check the
voltage with a tester.
When the power supply parts are changed, check the voltage with
a tester as described below.
(1) Turn off the shop circuit breaker.
(2) Change the machine to the following conditions:
• Turn off the circuit breaker QF1.
• Turn off the motor circuit breaker QM1.
• Remove the fuse FU3.
• Turn off the circuit protectors QF3 to QF5.
(3) Turn on the shop circuit breaker.
(4) Check the input voltage between the terminals L1 and L2, L2
and L3, and L1 and L3 at the lower terminal block.
(5) Check the input voltage between the terminals L1 and L2, L2
and L3, and L1 and L3 at the primary side (upper terminal
block) of the circuit breaker QF1.
(6) Turn on the circuit breaker QF1.
(7) Check the input voltage between the terminals L11 and L21,
L21 and L31, and L11 and L31 at the secondary side (lower
terminal block) of the circuit breaker QF1.
(8) Check the output voltage at the secondary side of the
transformer TC1.
(9) Check the input voltage between the terminals L11 and L21,
L21 and L31, and L11 and L31 at the primary side (upper
terminal block) of the motor circuit breaker QM1.
(10) Turn on the motor circuit breaker QM1.
13
(11) Check the input voltage between the terminals L12 and L22,
L22 and L32, and L12 and L32 at the secondary side (lower
terminal block) of the motor circuit breaker QM1.
(12) If the above voltage checks find no problems, turn off the
circuit breaker QF1.
(13) Return the machine to the following conditions:
• Replace the fuse FU3.
• Turn on the circuit protectors QF3 to QF5.
8 Replace the cover of the electrical enclosure.
14
Checking wiring connections
CAUTION
Check the wiring connections as described below.
1 Turn on the shop circuit breaker.
2 Turn on the machine circuit breaker, and check that the POWER
light comes on.
3 Turn the POWER ON/OFF switch to ON. When the initial NC
display is shown and a beep is heard, the hydraulic pump motor
can be started.
4 Press the HYDRAULIC ON button. The hydraulic pump motor
starts, and the HYDRAULIC ON button lights.
5 Check the rotational direction of the hydraulic pump motor. The
correct rotational direction is indicated by the arrow in the figure
below. If the hydraulic pump motor runs in the reverse direction,
immediately press the HYDRAULIC OFF button, turn off the
machine circuit breaker, and interchange two of the three
conductors connected to the terminals L1, L2, and L3.
● When turning on the power of the machine
for the first time as described below, keep
one hand at the POWER ON/OFF switch
so that you can turn off the power of the
machine as soon as possible.
NOTICE
● The hydraulic pump will fail if its motor is left to run in the reverse
direction for a long period of time. When the hydraulic pump motor is
found running in the reverse direction after the HYDRAULIC ON button
is pressed, immediately press the HYDRAULIC OFF button.
15
RE-ORIGIN
After the power of the machine is turned on, be sure to zero-return the
machine. Unless the zero-return is performed, each axis cannot
move.
Zero-return the machine as described below.
1 Touch the SETUP button shown on the screen.
2 Press and hold the UP foot pedal. Each axis zero-returns.
CONNECTING AIR COMPRESSOR
When the backgauge is equipped with optional flip-up stopper fingers,
compressed air must be supplied to the machine.
The air combination unit is located at the rear of the machine (inside the
right side frame). Fully connect the pipe or hose (inner diameter of
3/8 in.) from the air compressor to the air inlet (joint of 3/8 in.).
The required air pressure for the machine is 0.5 MPa (5 kg/cm
psi). The air compressor used should have a output of 0.75 kW (1
HP) or more.
2
, 70.97
NOTICE
● If a pipe or hose with an inner diameter of less than 3/8 in. is used, the air
flow will be limited and the air pressure will be reduced.
● Install the air compressor near the machine. If the air compressor is away
from the machine, the air pressure will be reduced.
Air combination unit
16
LEVELING
Level the machine as described below.
1 Turn the MODE SELECT switch to OFF with the HYDRAULIC ON
button lighted and the hydraulic pump motor running.
2 Place a spirit level on the lower beam.
3 Attach square spirit levels to the working surface at the rear of the
left and right side plates of the machine.
If square spirit levels are not available, place spirit levels at the left
and right edges of the top surface of the lower beam.
4 Turn the leveling bolts to level the machine to 0.03 mm/1m (0.001
in./1ft.) or less in the left-to-right and front-to-back directions.
17
PARALLELING UPPER AND LOWER BEAMS
Check that the upper and lower beams are parallel at the left edge D1
and right edge D2 as shown below. If not, parallel them as described
below.
1 Remove the punch holders at the left and right edges.
2 Turn the MODE SELECT switch to UPPER LOCK.
3 Raise the lower beam to 140 mm (5.52 in.), and measure the
dimensions D1and D2.
4 If the dimension D2 is greater than the dimension D1 (0.00), add
the difference to the grid shift of the dimension D1.
If the dimension D2 is smaller than the dimension D1, add the
difference to the grid shift of the dimension D2.
NOTE
● The grid shift is adjusted by changing the value of a system parameter.
For the method of displaying the system parameter, refer to the
adjustment specification.
5 Turn off the power and then back on, and repeat steps 1 to 3.
6 Repeat steps 1 to 5 so that the difference between the dimensions
D1and D2 becomes 0.01 mm (0.0004 in.).
7 When the paralleling of the upper and lower beams is completed,
check that the machine is level with the lower beam positioned
140 mm (5.52 in.). If not, level the machine again.
18
CHECKING MOVEMENT OF EACH AXIS
Be sure to check the movement of each axis. Manually move each
axis, and check that each axis moves free of trouble.
NOTE
● If the lower beam tilts or stops midway, lower the lower beam as described
below.
1 Turn the POWER ON/OFF switch to ON.
2 Press and hold the RAM DOWN button until the lower beam
reaches the bottom dead center.
3 Turn the POWER ON/OFF switch to OFF and then back to ON.
4 Re-origin the machine.
19
INSTALLING STOPPER FINGERS
WARNING
The machine is shipped with the stopper fingers removed. Install
them as described below.
1 Move the stoppers to the position where they can be reached
through the gap.
2 Turn the MODE SELECT switch to OFF.
3 Install a stopper finger of the same number as that marked on the
stopper as shown below.
● Never reach through the space between
the punches and dies to change the
stopper fingers. Turn the MODE SELECT
switch to OFF during the change.
MAKING FINAL CHECKS
• Interference of lower beam with cover
Move up the lower beam over a full stroke, and press the
EMERGENCY STOP button. Press the RAM DOWN button
intermittently to bring down the lower beam. When the lower beam
does not interfere with the cover, move up and down the lower beam
continuously, and check it for any interference with the cover.
• Oil leakage and air removal
Check for any oil leak. After tools are mounted, move up the lower
beam to apply pressure to the tools for a few seconds. This forces
air out of the hydraulic unit.
20
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.