SMA MVPS 500SC-JP, MVPS 630SC-JP, MVPS 800SC-JP, MVPS 1000-1SC-JP, MVPS 1000-2SC-JP Transportation And Installation Requirements

...
!
SMA
Transportation and Installation Requirements
MEDIUM VOLTAGE POWER STATION 500SC-JP / 630SC-JP / 800SC-JP / 1000-1SC-JP / 1000-2SC-JP / 1250SC-JP / 1600SC-JP / 2000SC-JP
Table of Contents
1 Information on this Document..................................................................................................... 3
1.1 Validity ............................................................................................................................................................. 3
1.2 Target Group ................................................................................................................................................... 3
1.3 Additional Information..................................................................................................................................... 3
2 Product Overview ........................................................................................................................ 4
2.1 Design of the MV Power Station .................................................................................................................... 4
2.2 Option code..................................................................................................................................................... 5
2.3 Scope of Delivery ............................................................................................................................................ 9
2.4 External dimensions and weights ................................................................................................................... 11
3 Transport and Mounting.............................................................................................................. 13
3.1 Transport by truck, train or ship ...................................................................................................................... 13
3.2 Storage............................................................................................................................................................. 14
3.3 Requirements and Ambient Conditions .......................................................................................................... 14
3.4 Unloading ........................................................................................................................................................ 14
4 Information for Installation ......................................................................................................... 19
4.1 Minimum Clearances ...................................................................................................................................... 19
4.2 Supply Air and Exhaust Air............................................................................................................................. 19
4.3 Installation........................................................................................................................................................ 21
4.3.1 Design of the System with MV Power Station ................................................................................................ 21
4.3.2 Support surface ................................................................................................................................................ 22
4.3.3 Pea gravel ground ........................................................................................................................................... 22
4.3.4 Weight load ..................................................................................................................................................... 22
4.3.5 Mounting options ............................................................................................................................................. 22
4.3.5.1 Flagstones........................................................................................................................................................ 23
4.3.5.2 Pile-driven steel pillars ..................................................................................................................................... 23
4.3.5.3 Concrete pillar................................................................................................................................................. 24
4.3.5.4 Strip foundations ............................................................................................................................................. 24
4.3.5.5 Foundation plate ............................................................................................................................................. 25
4.3.6 Erecting the service platforms.......................................................................................................................... 26
4.3.7 Recesses in the Support Surface ..................................................................................................................... 28
4.4 Oil spill containment........................................................................................................................................ 31
4.4.1 Oil Spill Containment for the MV Power Station with One Inverter ............................................................. 31
4.4.2 Oil Spill Containment for the MV Power Station with Two Inverters ............................................................ 32
5 Electrical Connection .................................................................................................................... 34
5.1 Grounding Concept ........................................................................................................................................ 34
5.2 Cable Requirements ........................................................................................................................................ 34
5.3 Q at Night........................................................................................................................................................ 35
6 On-Site Services............................................................................................................................ 37
Table of Contents
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-202
1 Information on this Document
1.1 Validity
This document is valid for the following device types of the MVPowerStation with the inverters of the series SunnyCentral 500CP-JP/ 630CP-JP/ 800CP-JP / 1000CP-JP:
• Medium Voltage Power Station 500SC-JP (MVPS 500SC-JP)
• Medium Voltage Power Station 630SC-JP (MVPS 630SC-JP)
• Medium Voltage Power Station 800SC-JP (MVPS 800SC-JP)
• Medium Voltage Power Station 1000-1SC-JP (MVPS 1000-1SC-JP)
• Medium Voltage Power Station 1000-2SC-JP (MVPS 1000-2SC-JP)
• Medium Voltage Power Station 1250SC-JP (MVPS 1250SC-JP)
• Medium Voltage Power Station 1600SC-JP (MVPS 1600SC-JP)
• Medium Voltage Power Station 2000SC-JP (MVPS 2000SC-JP)
The production version is indicated on the type label.
Illustrations in this document are reduced to the essential and may deviate from the real product.
1.2 Target Group
The tasks described in this document must only be performed by qualified persons. Qualified persons must have the following skills:
• Knowledge of how the product works and is operated
• Training in how to deal with the dangers and risks associated with installing and using electrical devices and systems
• Training in the installation and commissioning of electrical devices and systems
• Knowledge of all applicable standards and directives
• Knowledge of and adherence to this manual and all safety precautions
1.3 Additional Information
Links to additional information can be found at www.SMA-Solar.com.
1 Information on this Document
SMA Solar Technology AG
Transportation and Installation Requirements 3MVPS22JP-TA-en-20
2 Product Overview
2.1 Design of the MVPowerStation
Figure 1: Design of the MVPowerStation
Position Designation Explanation
A Protective roof The roof protects the devices from direct solar irradiation.
B Service platform The elevated position of the service platform facilitates opera-
tion of the devices and is part of the cooling concept of the MVPowerStation.
C MV transformer The MV transformer converts the inverter output voltage to the
voltage level of the medium-voltage grid.
D Medium-voltage switchgear* The medium-voltage switchgear disconnects the MV trans-
former from the medium-voltage grid.
E Communit*
or
Control device for cascade control*
The Communit contains control and communication devices.
The order option "Cascade control" allows for staggered recon­nection of several medium-voltage switchgears after a grid fail­ure or maintenance work.
F Transformer for internal power supply* The transformer for internal power supply provides the supply
voltage for the MVPowerStation and its devices. It is con­nected to the low-voltage side of the MV transformer (see cir­cuit diagram).
2Product Overview
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-204
Position Designation Explanation
G Station subdistribution The station subdistribution contains fuse and switching elements
for the supply voltage.
H Sunny Central CP-JP The SunnyCentral is a PV inverter that converts the direct cur-
rent generated in the PV arrays into grid-compliant alternating current.
* optional
2.2 Option code
The MVPowerStation is available in different power classes. Depending on the specific power class, the MVPowerStation can be equipped with different inverters. An MVPowerStation can only be equipped with two inverters of the same device type.
MVPowerStation Available inverters
MVPowerStation 500SC-JP 1 x SC 500CP-JP
MVPowerStation 630SC-JP 1 x SC 630CP-JP
MVPowerStation 800SC-JP 1 x SC 800CP-JP
MVPowerStation 1000-1SC-JP 1 x SC 1000CP-JP
MVPowerStation 1000-2SC-JP 2 x SC 500CP-JP
MVPowerStation 1250SC-JP 2 x SC 630CP-JP
MVPowerStation 1600SC-JP 2 x SC 800CP-JP
MVPowerStation 2000-SC-JP 2 x SC 1000CP-JP
You can use the option code to select an MVPowerStation configuration which is tailored specifically to your project. However, not all order options can be combined with each other. Consult your SMA contact person if you have any questions.
Order option 0 1 2 3 4 5 6 7 8 9 10 Description
Power class 0 500kVA
1 630kVA
2 800kVA
4 1000kVA with 1 SC
5 1000kVA with 2 SC
6 1250kVA
7 1600kVA
9 2000kVA
2 Product Overview
SMA Solar Technology AG
Transportation and Installation Requirements 5MVPS22JP-TA-en-20
Order option 0 1 2 3 4 5 6 7 8 9 10 Description
Nominal voltage 1 10kV
2 11kV
3 12kV
4 12.5kV
5 13.2kV
6 13.8kV
7 15kV
8 20kV
9 22kV
A 23kV
B 30kV
C 33kV
Nominal fre­quency
0 50Hz
1 60Hz
Transformer vector group
0 Dy11*
1 Dy11y11**
2 YNd11*
3 YNd11d11**
MV transformer 2 Mineral oil with hermetical
protection
3 Organic oil with hermetical
protection
Oil spill contain­ment
0 Without
1 With (supplied as a separate
accessory)
Medium-voltage switchgear
0 Without
2 Ring (3-field), transformer
panel with 24kV circuit breaker
4 Ring (3-field), transformer
panel with 36kV circuit breaker
2Product Overview
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-206
Order option 0 1 2 3 4 5 6 7 8 9 10 Description
Accessory for medium-voltage switchgear
0 Without
3 Cascade control (control unit
for staggered reconnection of the medium-voltage switchgears via the center ca­ble panel following a grid fail­ure)
4 Spatial separation (between
medium-voltage switchgear and low-voltage devices)
5 Cascade control and spatial
separation
Low-voltage trans­former
0 Without
1 6kVA with EMC filtering de-
vice
Low-voltage meter 0 Without
1 For inverter (measurement via
two current transformers and two voltage converters per in­verter)
2 For transformer for internal
power supply (measurement via four combined instrument transformers)
3 For inverter and transformer
for internal power supply
Uninterruptible power supply
0 Without
* For the MVPowerStation 500SC-JP / 630SC-JP / 800SC-JP / 1000-1SC-JP
** For the MVPowerStation 1000-2SC-JP / 1250SC-JP / 1600SC-JP / 2000SC-JP
Continuation of the Option Code
Order option 11 12 13 14 15 16 17 18 19 20 Description
Packaging 1 Sea freight
Communit 0 Without
1 With
Ambient temperature 0 −25°C to +40°C
1 −25°C to +50°C / +55°C with
derating (achieved with addi­tional fans)
2 Product Overview
SMA Solar Technology AG
Transportation and Installation Requirements 7MVPS22JP-TA-en-20
Order option 11 12 13 14 15 16 17 18 19 20 Description
Installation altitude 0 0m to 1000m
1 1001m to 2000m
2 2001m to 3000m
Environment 0 Standard
1 Protection from chemically active
environment, for example, sea salt (achieved with special paint on the MV transformer and resin casting of the transformer for in­ternal power supply)
3 Protection from chemically active
environment and dust (supple­mentary dust protection of the medium-voltage switchgear and the transformer for internal power supply)
Additional equipment 0 Without
1 Seismic and storm qualification
(strengthening of the container design and delivery of special mounting feet for seismic activity and wind speeds of up to 56m/ s)
AC contactor 0 Without
1 With (additional voltage and fre-
quency monitoring relay on the low-voltage side)
Language EN English
Yes Japanese
2Product Overview
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-208
2.3 Scope of Delivery
Scope of Delivery of the Station Container
The scope of delivery of the station container is located in the compartment of the medium-voltage switchgear.
Figure 2: Scope of delivery of the station container
Position Quantity Designation
A 1 MVPowerStation
B 4 Support foot for the container corners
C 2 Support foot for the container sides
D 10 Support foot for the service platform
E 8 Protective roof bracket
F 1 Oil spill containment with oil drain valve*
G 1 Spare paint RAL 7004 for the container
H 1 Documentation, circuit diagram
* Optional Depending on the production version, the oil drain valve is mounted or not.
Scope of Delivery of the Medium-Voltage Switchgear
The scope of delivery of the medium-voltage switchgear is located in the compartment of the medium-voltage switchgear.
Figure 3: Scope of delivery of the medium-voltage switchgear
Position Quantity Designation
A 1 Actuation lever for grounding switch
2 Product Overview
SMA Solar Technology AG
Transportation and Installation Requirements 9MVPS22JP-TA-en-20
Position Quantity Designation
B 1 Actuation lever for disconnection unit, load-break switch and circuit
breaker
C 1 Double-bit key for the medium-voltage switchgear
D 1 Magnetic sign "Do not switch"
E 1 Magnetic sign "Earthed"
F 1 Documentation for the medium-voltage switchgear
Scope of Delivery of the Inverter
The scope of delivery of the inverter is located in the connection area of the inverter. The indicated number of the individual components differs depending on the number of mounted inverters in the MVPowerStation.
Figure 4: Scope of delivery of the inverter
Position Quantity Designation
A 1/2 LV/HRC fuse extractor
B 1/2 Non-woven abrasive
C 1/2 Desiccant bag
D 51/105* Bolt
54/108**
E 51/105* Nut
54/108**
F 102/210* Fender washer
108/216**
G 102/210* Spring washer
108/216**
H 1/2 Inverter key
I 80/160 Cable tie
K 1/2 Cable support sleeve (15mm to 16mm)
2Product Overview
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-2010
Position Quantity Designation
L 1/2 Cable support sleeve (17mm)
M 5/10 Cable support sleeves (9.5mmto13mm)
N 1/2 Touch-up stick RAL 7004
O 1/2 Touch-up stick RAL 9016
P 1 Circuit diagram
* With transformer for internal power supply
** Without transformer for internal power supply
2.4 External dimensions and weights
1550 mm
2438 mm
2250 mm
2726 mm 1480 mm
723 mm
6058 mm
755 mm
Figure 5: Dimensions of the MVPowerStation
Dimensions of the MVPowerStation without Platforms and Support Feet
Width Height Depth Weight
MVPowerStation 500SC-JP / 630SC-JP / 800SC-JP / 1000-1SC-JP
6058mm 2591mm 2438mm < 10 t
MVPowerStation 1000-2SC-JP / 1250SC­JP / 1600SC-JP / 2000SC-JP
6058mm 2591mm 2438mm < 14 t
2 Product Overview
SMA Solar Technology AG
Transportation and Installation Requirements 11MVPS22JP-TA-en-20
Dimensions of the MVPowerStation with platforms and support feet
Width Height Depth Weight
MVPowerStation 500SC-JP / 630SC-JP / 800SC-JP / 1000-1SC-JP
6938mm 2941mm 5598mm < 10 t
MVPowerStation 1000-2SC--JP / 1250SC­JP / 1600SC-JP / 2000SC-JP
6938mm 2941mm 5598mm < 14 t
The weight of the MVPowerStation may vary below the indicated weight depending on the selected voltage and power classes.
2Product Overview
SMA Solar Technology AG
Transportation and Installation RequirementsMVPS22JP-TA-en-2012
Loading...
+ 26 hidden pages