5 Communication and System Planning, Inverter Manager
5.1 Ethernet Communication
5.1.1 System Overview26
5.1.2 Inverter Manager26
5.2 User Interfaces
5.3 I/O Box
5.4 Weather Station
6 Technical Data
6.1 Technical Data
6.2 Derating Limits
6.3 Norms and Standards
24
26
26
27
27
27
28
28
29
29
6.4 Mains Circuit Specifications
6.5 Auxiliary Interface Specifications
6.6 Ethernet Connections
2L00410648-02_02 / Rev. date: 2014-10-03
30
30
31
Introduction
1Introduction
1
1
1.1 Introduction
The Design Guide provides information required for
planning and dimensioning an installation. It describes
requirements for use of the MLX series inverters in solar
energy applications.
Illustration 1.1 MLX Inverter
Additional resources available:
Installation Guide, supplied with the inverter, for
•
information required to install and commission
the inverter
Inverter Manager Installation Poster, for
•
information required to install the Inverter
Manager
Inverter Manager Assembly Installation Guide, for
•
information required to install the Inverter
Manager Assembly
Fan Installation Instruction, for information
•
required to replace a fan
SPD Installation Instruction, for information
•
required to replace Surge Protection Devices
These documents are available from the download area at
www.sma.de, or from the supplier of the solar inverter.
Additional application-specific information is available at
the same location.
1.2 List of Abbreviations
Abbreviation Description
ANSIAmerican National Standards Institute
AWGAmerican Wire Gauge
cat5eCategory 5 twisted pair cable (enhanced)
DHCPDynamic Host Configuration Protocol
DNODistribution Network Operator
DSLDigital Subscriber Line
EMC (Directive) Electromagnetic Compatibility Directive
ESDElectrostatic Discharge
FCCFederal Communications Commission
FRTFault Ride Through
GSMGlobal System for Mobile Communications
HDDHard Disk Drive
IECInternational Electrotechnical Commission
ITIsolated Terra
LCSLocal Commissioning and Service
LEDLight-Emitting Diode
LVD (Directive) Low Voltage Directive
MCBMiniature Circuit Breaker
MPPMaximum Power Point
MPPTMaximum Power Point Tracking
NFPANational Fire Protection Association
PP is the symbol for active power and is
measured in Watts (W).
PCBPrinted Circuit Board
PCCPoint of Common Coupling
The point on the public electricity network to
which other customers are, or could be,
connected.
PEProtective Earth
PELVProtected Extra-Low Voltage
PLAPower Level Adjustment
P
NOM
POCPoint of Connection
P
STC
PVPhotovoltaic, photovoltaic cells
RCDResidual-Current Device
RCMUResidual Current Monitoring Unit
R
ISO
ROCOFRate Of Change Of Frequency
QQ is the symbol for reactive power and is
SS is the symbol for apparent power and is
Power [W], Nominal conditions
The point at which the PV system is connected
to the public electricity grid.
Power [W], Standard Test Conditions
Insulation Resistance
measured in reactive volt-amperes (VAr).
measured in volt-amperes (VA).
L00410648-02_02 / Rev. date: 2014-10-033
Introduction
1
Abbreviation Description
STCStandard Test Conditions
SWSoftware
THDTotal Harmonic Distortion
TN-STerra Neutral - Separate. AC Network
TN-CTerra Neutral - Combined. AC Network
TN-C-STerra Neutral - Combined - Separate. AC
Network
TTTerra Terra. AC Network
Table 1.1 Abbreviations
4L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2 Inverter Overview
2.1 Product Label
Illustration 2.1 Product Label MLX 60
The product label on the side of the inverter shows:
Inverter type
•
Important specifications
•
Serial number, located under the bar code, for
•
inverter identification
2.2 Mechanical Overview of the Inverter
2
Illustration 2.2 Product Label MLX 60 UL
1Cover for installation area
2Front cover
3Die-cast aluminium heat sink
4Mounting plate
5Display (read-only)
6PV load switch (optional)
7Fans
Illustration 2.3 Mechanical Overview of the Inverter
2.3 Description of the Inverter
Inverter features:
IP65 enclosure/Type 3R
•
PV load switch
•
Ancillary service functionalities
•
Transformerless
•
3-phase
•
3-level inverter bridge with a high performance
•
Integrated residual current monitoring unit.
•
Insulation test functionality.
•
L00410648-02_02 / Rev. date: 2014-10-035
Inverter Overview
2
Extended fault ride through capabilities (to
•
support reliable power generation during grid
faults) - depending on inverter configuration
Compliant with a wide range of international
•
grids
Adapted to local requirements and conditions via
•
grid code setting
2.3.1 System Overview
The MLX system draws on the advantages of both string
inverters and central inverters, making it highly applicable
in many commercial and utility scale plants.
The MLX system consists of the MLX inverter itself, a DC
string combiner and the Inverter Manager.
The communication network of an MLX system is divided
into 2 Ethernet networks; Plant network and inverter
network. The plant network is the communication interface
to the MLX plant and may be shared by several Inverter
Managers as well as other IT equipment, while the inverter
network is solely used for MLX inverters. The plant network
must have a DHCP server (router) as the Inverter Manager
requires automatic IP assignment. It is recommended to
use professional grade routers and switches. The Inverter
Manager provides:
Control of up to 42 MLX inverters
•
Single point of access for each (up to) 2.5 MVA
•
plant for simple plant network deployment
Easy commissioning and service of the plant
•
using the Local Commissioning and Service (LCS)
tool
Safe upload to data warehouse services, and
•
control of all local requirements and settings
from the DNO
Open source Modbus TCP communication
•
protocol using SunSpec Alliance profile via
Ethernet both for monitoring and control, making
it easy to integrate in e.g. SCADA systems
Grid management interface through the optional
•
I/O box for PLA and reactive power commands
Easy integration of meteorological data using an
•
RS-485 SunSpec Alliance compliant weather
station
6L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2
1PV strings
2DC combiner
3MLX inverter
4MLX Inverter Manager
5Router
6LCS tool
7Portal
8SCADA system
9Weather station
10I/O box
11Grid management
12Transformer station
Illustration 2.4 System Overview
L00410648-02_02 / Rev. date: 2014-10-037
2
Inverter Overview
Illustration 2.5 Overview of Installation Area
PELV (Safe to touch)
2Equipment grounding
7Ethernet interface x 2
8RS-485 interface (not in use)
Live Part
1AC connection terminals
5PV connection terminals
Other
3Surge Protection AC
4Surge Protection DC
6PV load switch (optional)
2.3.2 Functional Safety
The inverter is designed for international use, with
functional safety circuit design meeting a wide range of
international requirements (see 2.5 Grid Code).
Single-fault Immunity
The functional safety circuit has a fully redundant built-in
single-fault detection. If a fault occurs, the inverter
disconnects from the grid immediately. The method is
active and covers all circuitry within the residual current
monitoring, both for continuous levels and sudden
changes. All functional safety circuits are tested during
start-up to ensure safe operation. If a circuit fails more
than 1 out of 3 times during the self-test, the inverter
enters fail safe mode. If the measured grid voltages, grid
frequencies, or residual current during normal operation
differ too much between the 2 independent circuits, the
inverter ceases to energise the grid and repeats the selftest. The functional safety circuits are always activated and
cannot be disabled.
Isolation
During the self-test, the inverter has an isolation measuring
system that detects whether the isolation in the PV system
is above the required level. This is done before the inverter
8L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
starts to energise the grid. During grid connection, the
inverter measures the continuous leakage current in the
system. If this level is exceeded more than 4 times during
24 hours, the inverter stops operating due to safety
hazards in the PV system.
NOTICE
Depending on the local legislation, a minimum earth-toPV isolation resistance is defined. A typical value is
82 kΩ.
Self-test
The insulation resistance between the PV arrays and earth
is also tested during the self-test. The inverter does not
energise the grid if the resistance is too low. It then waits
10 minutes before making a new attempt to energise the
grid.
Residual current
Residual current is continuously monitored. The inverter
ceases to energise the grid when:
The cycle RMS value of the residual current
•
violates the trip settings for more than the
duration of ‘clearance time’, or
A sudden jump in the residual current is detected
•
Grid Surveillance
Grid-related parameters are under constant surveillance
when the inverter energises the grid. The following is
monitored:
Grid voltage magnitude (instantaneous and 10
•
minute average)
Grid voltage and frequency
•
Loss of Mains (Islanding detection):
•
3-phase Loss of Mains (LoM) detection
•
Rate of Change of Frequency (ROCOF)
•
Frequency shift.
•
DC content of grid current
•
Residual current by means of RCMU
•
The inverter ceases to energise the grid if one of the
parameters violates the grid code.
StatusLEDs
Green
Off grid
Connecting
On grid
Internal inverter event
Fail safe
Table 2.1
Off grid (standby) (LEDs off)
#0-51.
When no power has been delivered to the AC grid for
more than 10 minutes, the inverter disconnects from the
grid and shuts down. User and communication interfaces
remain powered for communication purposes.
Connecting (Green LED flashing)
#52-53.
The inverter starts up when the PV input voltage reaches
the minimum DC feed-in voltage. The inverter performs a
series of internal self-tests, including measurement of the
resistance between the PV arrays and earth. Meanwhile, it
also monitors the grid parameters. When the grid
parameters have been within the specifications for the
required amount of time (depends on grid code), the
inverter starts to energise the grid.
On grid (Green LED on)
#60.
The inverter is connected to the grid and energises the
grid. The inverter disconnects when:
it detects abnormal grid conditions (dependent
•
on grid code), or
an internal event occurs, or
•
PV power is insufficient (no power is supplied to
•
the grid for 10 minutes)
The inverter then enters connecting mode or off grid
mode.
- - - - - - - - - - - - - - - - -
Red
- - - - - - - - - - - - - - - - -
Green
▬██▬██▬██▬██▬██▬
Red
- - - - - - - - - - - - - - - - -
Green
Red
Green
Red
Green
Red
██████████████████
▬
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
- - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
▬
2
2.3.3 Operation Modes
The inverter has 5 operation modes, indicated by LEDs.
L00410648-02_02 / Rev. date: 2014-10-039
Internal Inverter Event (Green LED flashing)
#54
The inverter is waiting for an internal condition to become
within limits (for example a too high temperature) before
it will go back on grid.
Fail Safe (Red LED flashing)
#70.
If the inverter detects an error in its circuits during the selftest (in connecting mode) or during operation, the inverter
goes into fail safe mode, disconnecting from grid. The
Inverter Overview
2
inverter will remain in fail safe mode until power has been
absent for a minimum of 10 minutes, or the inverter has
been shut down completely (AC+PV).
2.4 MPP Tracker and Derating
2.4.1 MPP Tracker
The Maximum Power Point Tracker (MPPT) is an algorithm,
which is constantly trying to maximise the output from the
PV array. The algorithm updates the PV voltage fast
enough to follow rapid changes in solar irradiance. The
MPPT will find the maximum power point while the PV
voltage is within the specified MPP voltage range. At
voltages below the minimum MPP voltage of the inverter,
the MPPT moves away from the maximum power point
(see Illustration 2.6) in order to maintain sufficient DC
voltage to generate the required AC grid voltage.
AC power limitation by setting or external
•
command (PLA)
Each MLX inverter limits the AC output power according to
the actual power reference, which will be the lowest of the
following values:
Max AC power rating (60 kVA)
•
Fixed active/reactive power limit set by grid code
•
file
Active/reactive power reference from the Inverter
•
Manager
Power limit from internal temperature derating.
•
Derating due to temperature is a sign of
excessive ambient temperature, a dirty heat sink,
a blocked fan or similar. Refer to the MLX Instal-lation Guide regarding maintenance. The values
shown in Illustration 2.7 are measured at nominal
conditions cos(φ) = 1
Illustration 2.6 MPPT Behaviour at Low MPP Voltage
NOTICE
Due to the boosterless design of the MLX inverter, the
minimum MPP voltage varies with the actual AC grid
voltage.
2.4.2 Inverter Derating
In certain situations, the MPPT purposely moves away from
the maximum power point. This behaviour is called
derating and is a means of protecting the inverter against
overload or a reduction of output power in order to
support the grid. Reactive power (supporting the grid) has
priority when the derate function is reducing the AC
output power, meaning that first active power is reduced
to zero where after reactive power is reduced. The MLX
system is derating in the following situations:
Exceeding max AC power rating
•
Internal over temperature
•
Grid over voltage
•
Grid over frequency
•
Illustration 2.7 Derating as Function of Internal Overtem-
perature
NOTICE
The inverter can use the entire admissable DC voltage
range up to 1000 V for derating. It is not restricted to
the MPP voltage range.
2.4.3 Power Reference
The power reference for the individual MLX inverter is
generated by the Inverter Manager based on the following
functions. They are all deployed in the Inverter Manager
and thus calculated on plant level.
Grid Overvoltage
•
When the grid voltage exceeds a DNO-defined
limit U1, the inverter derates the output power. If
the grid voltage increases and exceeds the
defined limit 10 min mean (U2), the inverter
ceases to energise the grid, in order to maintain
10L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
power quality and protect other equipment
connected to the grid.
U1 Fixed
U2 Trip Limit
Illustration 2.8 Grid Voltage above Limit Set by DNO
Derating - Grid Over-frequency
The output power is reduced as a variable of the grid
frequency. There are 2 methods for reducing the output
power: ramp and hysteresis. The grid code setting
determines which method is implemented in a specific
installation.
Primary frequency control - hysteresis method
See Illustration 2.10.
To support grid stabilisation, the inverter reduces output
power if the grid frequency exceeds f1. Reduction occurs
at a preconfigured rate, which is the ramp (R) shown in
Illustration 2.10. The reduced output power limit is
maintained until the grid frequency has decreased to f2.
When the grid frequency has decreased to f2, the inverter
output power increases again following a time ramp T. If
the grid frequency continues to increase, the inverter
disconnects at f3. When the frequency decreases below f2,
the inverter reconnects to grid and ramps up power at the
same rate as for the reduction.
2
Primary frequency control – ramp method
See Illustration 2.9.
The inverter reduces output power if the grid frequency
exceeds f1. Reduction occurs at a preconfigured rate,
which is the ramp (R) shown in Illustration 2.9. When the
frequency reaches f2, the inverter disconnects from grid.
When the frequency decreases below f2, the Inverter
reconnects to grid and ramps up power at the same rate
as for the reduction.
Illustration 2.10 Primary Frequency Control – Hysteresis
Method
2.5 Grid Code
The MLX grid code file contains settings that determine
both the behaviour of the single inverter and the entire
plant. The grid code file is divided into 2 main sections:
Grid protection settings
•
Grid support (ancillary services)
•
The LCS tool used for commissioning the inverter is
equipped with a range of default grid codes to meet
national requirements. Changing these default grid code
parameters requires a customised grid code file, supplied
by SMA. See 2.7 Functional Safety Settings about how to
apply for customised grid code parameters.
NOTICE
Obtain approval from the local distribution network
operator (DNO) before connecting the inverter to the
grid.
Illustration 2.9 Primary Frequency Control – Ramp Method
L00410648-02_02 / Rev. date: 2014-10-0311
Inverter Overview
2
2.5.1 Grid Protection Settings
The grid protection settings are stored in each inverter.
They ensure protection of the grid in case of certain grid
events regardless of the connection to the Inverter
Manager. The inverter continuously monitors the following
grid values, and compares them to the disconnection
values specified in the grid code. Example:
Voltage disconnection
•
Frequency disconnection
•
Reconnection
•
Loss of mains
•
Voltage and frequency disconnection
The cycle RMS values of the grid voltages are compared
with 2 lower and 2 upper trip settings, for example
overvoltage (stage 1). If the RMS values violate the trip
settings for more than the duration of ‘clearance time’, the
inverter ceases to energise the grid.
‘clearance time’, the inverters cease to energise
the grid
Rate of change of frequency (ROCOF). The ROCOF
•
values (positive or negative) are compared to the
trip settings. The inverter ceases to energise the
grid when the limits are violated
Frequency shift. The inverter continuously tries to
•
‘push’ the grid frequency a bit, but the stability of
the grid prevents this from happening
In an LoM situation, the stability of the grid is no longer
present, and this makes it possible to change the
frequency. As the frequency deviates from the operational
frequency of the line, the inverter disconnects and ceases
to energise the grid. If the inverter ceases to energise the
grid due to grid frequency or grid voltage (not 3-phase
LoM), and if the frequency or voltage is restored within a
short time (short interruption time), the inverter can
reconnect when the grid parameters have been within
their limits for the specified time (reconnect time).
Otherwise, the inverter returns to the normal connection
sequence.
2.6 Grid Support (Ancillary Services)
Illustration 2.11 Overvoltage and Undervoltage Disconnect
Reconnection
During start-up or when the inverter has disconnected
from grid due to for example overvoltage or frequency,
the reconnection values determine under which grid
conditions the inverter can reconnect to the grid and start
injecting energy.
Loss of Mains (Islanding) disconnection
Loss of Mains (LoM) is detected by 3 different algorithms:
3-phase voltage surveillance (the inverter has
•
individual control of the 3-phase currents). The
cycle RMS values of the phase-phase grid
voltages are compared with a lower trip setting
or an upper trip setting. If the RMS values violate
the trip settings for more than the duration of
The ancillary services are comprised in 2 main categories:
Fault Ride Through (FRT).
•
Reactive and active power management.
•
2.6.1 Fault Ride Through
The grid voltage usually has a smooth waveform, but
occasionally the voltage drops or disappears for several
milliseconds. This is often due to short circuit of overhead
lines, or caused by operation of switchgear or similar in
the high-voltage transmission lines. In such cases, the
inverter can continue to supply power to the grid using
fault ride through (FRT) functionality. Continuous power
supply to the grid is essential:
To help prevent a complete voltage blackout and
•
stabilise the voltage in the grid.
To increase the energy delivered to the AC grid.
•
There are 4 different behaviours to select from:
Zero Current
•
Reactive current only
•
Active current only
•
Full current – reactive priority
•
How FRT works
Illustration 2.12 shows the requirements that must be
followed by FRT. The example is for German mediumvoltage grids.
12L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
Above
line 1
Area AThe inverter must not disconnect from grid for
Area BRight of line 2, a short-duration disconnection from
Below
line 3
For voltages above line 1, the inverter must not
under any circumstances disconnect from the grid
during FRT.
voltages below line 1 and left of line 2. In some
cases, the DNO permits a short-duration disconnection, in which case the inverter must be back on
grid within 2 s.
grid is always permitted. The reconnect time and
power gradient can be negotiated with the DNO.
Below line 3 there is no requirement to remain
connected to grid.
Q(U) Reactive power injected as a function of the grid voltage.
Q(P) Reactive power injected as a function of the active output
power.
Q(S) Reactive power injected as a function of the apparent
output power.
Q(T) Reactive power injected as a function of the ambient
temperature.
PF(P) Power factor as a function of active output power.
PF(T) Power factor as a function of the ambient temperature.
PFext Power factor according to external signal either via
Modbus or the external I/O box (RS-485).
Qext Reactive power injected according to external signal
either via Modbus or the external I/O box (RS-485).
Table 2.2 Reactive Power Management, Control Methods
NOTICE
Only 1 method can be used at a time. A mode selector
determines which method to activate.
With the setpoint curve Q(U), the inverter controls reactive
power as a function of the grid voltage U. The values for
the setpoint curve are determined by the local utility
company and must be obtained from them (see
Illustration 2.13).
2
Illustration 2.12 German Example
When a short-duration disconnection from grid occurs:
The inverter must be back on grid after 2 s
•
The active power must be ramped back at a
•
maximum rate of 10% of nominal power per s
Active power management
The inverter can support the local grid by either static or
dynamic limit of the plant output power. The different
methods of control are:
Fixed Pref – maximum active power limit
•
Power Level Adjustment (PLA) – remotely
•
controlled maximum active power limit (requires
I/O box)
2.6.2 Reactive Power Management
Reactive power management
The inverter can support the local grid voltage by injecting
reactive power. The different control methods are:
Illustration 2.13 Q(U) Setpoint Curves - Reactive Power
When the grid voltage is below nominal, the inverter is
configured to inject over-excited reactive power in order to
help increase the grid voltage back up to nominal. When
the grid voltage is above nominal, the inverter injects
under-excited reactive power to help decrease grid voltage
L00410648-02_02 / Rev. date: 2014-10-0313
Inverter Overview
2
and thus supports the grid by maintaining a more stable
and healthy voltage.
Qext. and PFext
Control of a plant’s reactive power injection can be
handled remotely with I/O box via RS-485 or via a 3
external signal via Modbus.
2
1
rd
-party
RS-485
3
I/O box
The I/O box monitors the relay state of the Ripple control
receiver (supplied by the DNO) and transmits the state to
the Inverter manager via RS-485. The Inverter Manager
translates the relay state into the corresponding PLA value
(max. plant output power) based on the grid code configuration.
180AA037.1
Ethernet
1Ripple Control Receiver
2I/O Box
3Inverter Manager
4MLX
Illustration 2.14
External signal (3rd party)
Modbus SunSpec control profile can be used to control the
reactive power injected by the plant.
2.6.3 Active Power Management
Apparent power management
The inverter can support the local grid by setting a
maximum apparent power limit.
Fixed Sref – maximum apparent power limit
•
Fallback
The inverters in the inverter network are controlled by a
Qref and Pref from the Inverter Manager. If the connection
to the Inverter Manager is lost, the inverter disconnects
from grid after up to 40 seconds. If the connection is
restored within this period the inverter will not disconnect
from grid. When the connection is restored, the inverters
reconnect to grid.
4
4
4
2.7 Functional Safety Settings
The inverter is designed for international use and it can
handle a wide range of requirements related to functional
safety and grid behaviour. Parameters for functional safety
are predefined and do not require any alteration during
installation. However, some grid code parameters may
require alterations during installation to allow optimisation
of the local grid. Contact SMA for a custom grid code.
14L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3 System Planning – Mechanical
The aim of this section is to provide general information
for planning the mechanical installation of the MLX
inverter, including mounting and cable specifications.
3.1 Unpacking
Contents:
Inverter
•
Mounting plate
•
Accessories bag, containing:
•
6 wall plugs 8 x 50 mm
•
6 mounting screws 6 x 60 mm
•
1 M25 cable gland with sealing
•
grummet for Ethernet cables
2 conduit brackets (2 inches - only for
•
UL version)
1 equipment grounding bolt 6 x 12 mm
•
Installation guide, booklet format
•
Quick guide, poster format
•
3
Illustration 3.4 Ensure Adequate Air Flow
Illustration 3.5 Mount on Non-flammable Surface
3.2 Installation
Illustration 3.1 Avoid Constant Stream of Water
Illustration 3.2 Avoid Direct Sunlight
Illustration 3.6 Mount Upright on Vertical Surface. Tilt of up to
10 degrees is permitted
Illustration 3.7 Prevent Dust and Ammonia Gases
NOTICE
When planning the installation site, ensure that inverter
product and warning labels remain visible. For details,
refer to 6 Technical Data.
Illustration 3.3 Ensure Adequate Air Flow
L00410648-02_02 / Rev. date: 2014-10-0315
3
System Planning – Mechanica...
3.2.1 Installation Conditions
ParameterSpecification
Operational temperature range
Storage temperature
Relative humidity95% (non-condensing)
Environmental class according to IEC
60721-3-4
Cooling conceptForced
Air quality - generalISA S71.04-1985
Air quality - coastal, heavy industrial and
agricultural zones
Vibration1G
Enclosure rating ingress protection class IP65
UL 50E enclosure typeType 3R
Max. operating altitude2000 m (6500 ft) above sea level (derating may occur at an altitude over 1000 m).
InstallationAvoid constant stream of water.
−
25 °C – +60 °C (possible power derating above 45 °C) (−13 °F – 140 °F) (possible power
derating above 113 °F)
−
40 °C – +60 °C (−40°F – 140 °F)
4K4H/4Z4/4B2/4S3/4M2/4C2
Level G3 (at 75% RH)
Must be measured and classified acc. to ISA S71.04-1985: G3 (at 75% RH)
Avoid direct sunlight.
Ensure adequate air flow.
Mount on non-flammable surface.
Mount upright on vertical surface.
Prevent dust and ammonia gases.
Table 3.1 Conditions for Installation
ParameterConditionSpecification
Mounting plateHole diameter30 x 9 mm
Alignment
Table 3.2 Mounting Plate Specifications
Perpendicular
±
10° all angles
16L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3.3 Mounting the Inverter
3
Illustration 3.8 Safe Clearances
NOTICE
Ensure 620 mm/24 inches base clearance for adequate
airflow.
L00410648-02_02 / Rev. date: 2014-10-0317
3
System Planning – Mechanica...
Illustration 3.10 Position the Inverter
Illustration 3.9 Mounting Plate
NOTICE
Use of the mounting plate delivered with the inverter is
mandatory. If the inverter is mounted without the
mounting plate, the warranty becomes void. It is
strongly recommended to use all 6 mounting holes.
Important when mounting the mounting plate:
Mount in the defined environment
•
Use screws and rawl plugs that can safely carry
•
the weight of the inverter
Ensure that the mounting plate is correctly
•
aligned
Observe safe clearances when installing 1 or
•
more inverters, to ensure adequate airflow.
Clearances are specified in Illustration 3.8 and the
mounting plate label
Mounting multiple inverters in a single row is
•
recommended. Contact the supplier for
guidelines when mounting inverters in more than
1 row
Ensure adequate clearance at the front, for
•
service access to the inverter
Illustration 3.11 Lifting Bolts
CAUTION
Refer to local health and safety regulations when
handling the inverter.
3.3.1 How to Position the Inverter
Use M12 or ½ in lifting bolts and matching nuts (not
supplied in the accessories bag) for mounting.
18L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3.3.2 Torque Specifications for Installation
Illustration 3.12 Overview of Inverter with Torque Indications
If the blind plugs are removed (see (7) in
Illustration 3.12), use fittings with type rating: 3, 3S, 4,
4X, 6, 6P.
3
Table 3.3 Torque Specifications
3.4 Cable Specifications
Terminal RangeMax. conductor
temperature
rating
AC + PE
PV
Table 3.4 Acceptable Conductor Sizes
16-95
mm
6-4/0
AWG
16-95
mm
6-4/0
AWG
90 ºCAl/Cu37-44 mm
2
90 ºCAl/Cu14-21 mm
2
Conductor
material
Cable
jacket
diameter
L00410648-02_02 / Rev. date: 2014-10-0319
System Planning – Electrica...
4 System Planning – Electrical
4
4.1 Introduction
The aim of this section is to provide general information
for planning integration of the inverter into a PV system:
PV system design, including earthing
•
AC grid connection requirements; including
•
choice of AC cable protection
Ambient conditions, e.g. ventilation
•
4.2 DC Side
4.2.1 Requirements for PV Connection
The specifications for PV connection are shown in
Table 4.1.
ParameterMLX 60
MPP trackers/Inputs per MPPT1/1 (external string combining)
Maximum input voltage, open
dcmax
)
circuit (V
Input voltage range565–1000 V @ 400 Vac
Rated voltage DC630 V @ 400 Vac
MPPT voltage range - rated
power
Max. MPPT current DC110 A
Max. short circuit current DC150 A
Table 4.1 PV Operating Conditions
Illustration 4.1 Operating Range per MPP Tracker
1000 V
680–1000 V @ 480 Vac
710 V @ 480 Vac
570–800 V @ 400 Vac
685–800 V @ 480 Vac
To avoid damaging the inverter, observe the limits in
Table 4.1 when dimensioning the PV generator for the
inverter.
CAUTION
Always observe local requirements, rules, and
regulations for the installation.
4.2.1.1 Maximum Open-circuit Voltage
The open-circuit voltage from the PV strings must not
exceed the maximum open-circuit voltage limit of the
inverter. Calculate the open-circuit voltage at the lowest
PV module operating temperature expected for the
location. If the module operating temperature is not welldefined, check local common practice. This calculation
implies a maximum of 23–26 modules per string, for
standard 60-cells c-Si modules. It depends on the local
climate, module model, and installation conditions (for
example ground based or flush mounted). Also check that
the maximum system voltage of the PV modules is not
exceeded.
Special requirements apply to thin-film modules. See
4.2.3 Thin Film.
4.2.1.2 MPP Voltage
The string MPP voltage must be within the operational
range of the inverter MPPT. Operational range is defined
by:
Minimum voltage operation MPP:
•
570 V @ 400 V
-
685 V @ 480 V
-
Other grid voltages: Estimate by
-
‘√2 x grid voltage [V
Maximum voltage operating MPP (800 V), for the
•
temperature range of the PV modules
This requirement implies a minimum of 23–25 modules per
string, for standard 60-cells c-Si modules. It depends on
the location, module model, installation conditions, and
grid voltage. If the input DC voltage is below the minimum
MPP voltage for a period, the inverter will not trip but shift
the operation up to the minimum voltage operation MPP,
resulting in some yield losses.
MPP of the inverter can be below the minimum voltage
operation MPP due to circumstances like:
High cell temperature
•
Partial shading conditions
•
ac
ac
]’
ac
20L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Electrica...
4
Insufficient number of modules per string
•
High grid voltage
•
In general, the yield losses are minor for 400 V
Yield losses can be minimised for 480 V
Increasing the number of modules per string
•
Reducing the grid voltage seen by the inverters
•
Grid voltage can be reduced by:
modifying the tap changer position in
-
the transformer station
moving the inverters to another location
-
modifying the AC cable sections
-
If the previous actions are insufficient for a particular
project to minimise the yield losses due to MPP range at a
low level, an auto-transformer 480–400 V can be installed
in order to reduce the grid voltage.
ac
grids.
ac
grids by:
NOTICE
SMA can support you in the analysis of the yield losses
due to MPP range for your particular project and in the
selection of the best technical approach.
4.2.1.3 Short-circuit Current
The short-circuit current (Isc) must not exceed the absolute
maximum that the inverter is able to withstand. Check the
specification of the short-circuit current at the highest PV
module operating temperature and the highest irradiance
level expected. 125% of the module Isc at STC is used per
string for the calculation, following the recommendations
of the NEC and other regulations. This implies no more
than 14 strings per inverter, for standard 60-cells c-Si
modules.
4.2.1.4 MPP Current
The MLX inverter is able to provide full AC power even at
its lower MPP range threshold. If the MPP current exceeds
110 A (due to high irradiance conditions or large number
of strings per inverter), the inverter does not trip but shifts
the operation point, resulting in some yield losses. In
addition, the inverter limits the power intake by shifting
the MPP when surplus PV power is available. For further
information about PV over-sizing and related
consequences, see 4.2.2 Determining Sizing Factor for PVSystems.
4.2.1.5 PV to Earth Resistance
Monitoring of the PV to earth resistance is implemented
for all grid codes. Supplying energy to the grid with too
low resistance could be harmful to the inverter and/or the
PV modules. PV modules designed according to the
IEC61215 standard are only tested to a specific resistance
of minimum 40 MΩ*m
2
. Therefore, for an 84 kWp power
plant with a 14% PV module efficiency, the total area of
the modules yields 600 m
resistance of 40 MΩ*m
must be within the required limit of the applied grid code.
See 2.3.2 Functional Safety and 2.5 Grid Code.
2
. This yields a minimum
2
/600 m2 = 66.67 kΩ. The PV design
4.2.1.6 Earthing
It is not possible to earth any of the terminals of the PV
arrays. However, it can be compulsory to earth all
conductive materials, for example, the mounting system, to
comply with the general codes for electrical installations. In
addition, the PE terminal of the inverter must be always
connected to earth.
CAUTION
It can be harmful to humans if not properly grounded.
4.2.1.7 Parallel Connection of PV Arrays
The MLX inverter has 1 input and 1 MPPT. An external
string combiner is always required. Due to the number of
strings in parallel, fusing of the strings in the string
combiner is required. The recommendation is to place the
string combiner close to the strings. The use of only 1
cable for each pole from the PV array to the inverter
reduces the cable and installation costs.
4.2.1.8 PV Cable Dimensions and Layout
DC cabling is composed of 2 different cable segments:
The string cabling from the modules to the string
•
combiner (usually 4 mm
The combined line from the string combiner to
•
the inverter (recommended at least 50 mm
(copper) or 70 mm2 (aluminium))
The cable section must be selected for each segment
according to the current capacity of the cable and
maximum DC cable losses according to local legislation.
Current capacity of the cable depends on the material of
the wires (copper or aluminium) and the type of insulation
(for example PVC or XLPE). Factors as for example high
ambient temperature or grouping of cables produce
derating of the current capacity of the cable. Follow the
local legislation for correction factors calculation.
The maximum DC cable losses permitted also depend on
the local legislation. Note that the limit must include both
the losses in the strings and the combined line. Cable
losses depend on the material of the wires (copper or
aluminium), cross-section area and the cable length.
Take the following into account:
The total length for a string is defined as twice
•
the physical distance between the string and the
2
or 6 mm2)
2
4
L00410648-02_02 / Rev. date: 2014-10-0321
System Planning – Electrica...
4
string combiner plus the length of the PV cables
included in the modules
The total length for the combined line is defined
•
as twice the physical distance between the string
combiner and the inverter
NOTICE
For the combined line, the maximum cable section
connectable to the inverter (95 mm
addressed in the system design. If the calculated cable
section exceeds this limit, change the cable type, the
sub-plant size, or the location of the string combiners/
inverters.
Avoid looping the DC cables as they can act as an antenna
of radio-noise emitted by the inverter. Cables with positive
and negative polarity must be placed side by side with as
little space between them as possible. This also lowers the
induced voltage in case of lightning and reduces the risk
of damage.
4.2.2 Determining Sizing Factor for PV
Systems
When determining the PV system size factor, a specific
analysis is preferred, especially for large PV installations.
Local rules of thumb for choosing the sizing factor can be
determined, depending on local conditions, for example:
Local climate
•
Local legislation
•
System price level
•
To select the optimal configuration/sizing factor, an
investment analysis must be made. Large sizing factors
usually reduce specific investment costs (€/kWp) but could
have lower specific yield (kWh/kWp) due to derating losses
in the inverter (excessive DC power or overheating) and so,
lower income. Small sizing factors result in greater
investment costs. However, specific yield is potentially
greater due to little or no derating loss.
2
/ AWG 4/0) must be
The MLX inverter supports different sizing factors,
depending on the number of modules per string and
number of strings per inverter.
Any configuration that observes the varying conditions for
different applications: the limits in Table 4.1 for short-circuit
current and open-circuit voltage will be considered as valid
and so covered by warranty.
4.2.3 Thin Film
The MLX inverter is a transformerless inverter without
booster and so the PV voltage is distributed symmetrically
to earth. Grounding of the minus pole is not allowed.
The use of transformerless inverters as MLX is
•
approved by many thin-film module manufacturers not requiring grounding of the minus pole
The MLX inverter is not compatible with thin-film
•
modules with a requirement of minus pole
grounding
NOTICE
It is important to get approval from the module
manufacturer before installing thin-film modules with
MLX inverters.
CAUTION
Module voltage during initial degradation can be higher
than the rated voltage in the data sheet. This must be
considered when designing the PV system, since
excessive DC voltage can damage the inverter. Module
current can also lie above the inverter current limit
during the initial degradation. In this case, the inverter
decreases the output power accordingly, resulting in
lower yield. Therefore, when designing, take inverter and
module specifications both before and after initial
degradation into consideration.
4.2.4 Internal Surge Overvoltage Protection
Installations in regions with frequent irradiation levels over
1,000 W/m
lations in regions with infrequent irradiance levels over
1000 W/m
not expected during the irradiance peaks.
A lower sizing factor must also be considered for tracking
systems, because they allow more frequent high irradiance
levels. In addition, derating due to overheating of the
inverter must be considered for tracking systems in hot
climates. This can also reduce the recommended sizing
factor further.
22L00410648-02_02 / Rev. date: 2014-10-03
2
have lower levels of sizing factor than instal-
2
. In particular, if high ambient temperatures are
The MLX inverter includes high performance DIN-rail SPDs
in both AC (type II+III, according to IEC 61643-11) and DC
(type II) sides. The SPDs are easy to replace if damaged.
System Planning – Electrica...
4
The thermal management concept of the inverter is based
on forced cooling with speed-controlled fans. The fans are
electronically controlled and are only active when needed.
The rear of the inverter is designed as a heat sink that
removes the heat generated by the power semiconductors
in the integrated power modules. Additionally, the
magnetic parts are ventilated by force. At high altitudes,
the cooling capacity of the air is reduced. The fan control
attempts to compensate for this reduced cooling. At
altitudes greater than 1000 m, consider derating of the
inverter power when planning system layout, to avoid loss
of energy.
4
1 SPD (AC) with 3 fuses.
Fuse to far right (green) does not require any replacement.
2 SPD (DC) with 2 fuses.
Fuse in the middle (green) does not require any replacement.
Illustration 4.2 Overview of Installation Area
Based in the combination of gas-filled spark gap and MOVs
technologies, SPDs in MLX have the following advantages:
No leakage or operation current: no insulation
•
faults and tripping of the inverter, and no aging
No follow current: no tripping of the upstream
•
overcurrent protection during surge events
If the PV system is installed on a building with an existing
lightning protection system, the PV system must also be
properly included in the lightning protection system.
CAUTION
When mounting the inverter on a grounded metallic
surface, ensure that the inverter’s earthing point and
mounting plate are directly connected. Failure to do so
can potentially result in material damage to the inverter,
via arcing between the mounting plate and the inverter
enclosure.
4.2.5 Thermal Management
All power electronics generate excess heat, which must be
controlled and removed to avoid damage and to achieve
high reliability and long life. The temperature around
critical components like the integrated power modules is
continuously measured to protect the electronics against
overheating. If the temperature exceeds the limits, the
inverter reduces output power to maintain temperature at
a safe level.
Altitude
Max. load of inverter95%
Table 4.2 Compensation for Altitude
2000 m
NOTICE
PELV protection is effective up to 2000 m above sea
level only.
Account for other altitude-related factors, such as
increased irradiation.
Optimise reliability and lifetime by mounting the inverter
in a location with low ambient temperature.
NOTICE
For indoor locations, consider a maximum airflow of 640
3
/h and a maximum heat dissipation of 1500 W per
m
inverter.
4.2.6 Simulation of PV
Contact the supplier before connecting the inverter to a
power supply for testing purposes, for example, simulation
of PV. The inverter has built-in functionalities that can
harm the power supply or the inverter.
4.2.7 PV Field Capacitance
PV fields have a small parasitic capacitance, which is
directly proportional to the area and inversely proportional
to the thickness of the modules. Depending on the
weather conditions, a total capacity of about 50–150
nF/kW can be determined for a plant with crystalline
modules. For standard thin-film modules (CdTe, CIS, and aSi) similar values are expected. Under extreme conditions,
stainless steel sheet-based thin-film modules can produce
values near to 1 mF/kW.
The MLX inverter is designed to operate with a PV field
capacitance up to 8.8 μF. If this limit is exceeded, the
L00410648-02_02 / Rev. date: 2014-10-0323
System Planning – Electrica...
4
capacitive leakage current can provoke undesired tripping
of the RCMU class B of the MLX inverter, and, as a result,
the disconnection of the inverter from the grid.
WARNING
Plants with no grounding of the structure can be
dangerous. If a grounded person touches the modules, a
capacitive leakage current can flow through his body. It
is especially important to ground the support structure
of the modules when transformerless inverter having AC
ripple on the DC side are installed in combination with
high-capacity PV modules. This draws the capacitive
leakage current to ground and prevents any bodily
harm.
Observe the National Electric Code, ANSI/NFPA 70.
Input and output circuits are isolated from the enclosure.
System grounding is the responsibility of the installer.
4.3 AC Side
4.3.1 Requirements for AC Connection
CAUTION
Always follow local regulations.
Current sensitivity
20 A2.5 Ω
Basic sensitivity
Medium sensitivity
High sensitivity≤ 30 mA > 500 Ω
Table 4.4 Maximum Earth Resistance in TT Grids, Depending
on the Current Sensitivity of the RCD
10 A5 Ω
5 A10 Ω
3 A17 Ω
1 A50 Ω
500 mA 100 Ω
300 mA 167 Ω
100 mA 500 Ω
Maximum value of earth resistance
NOTICE
When using TN-C earthing to avoid earth currents in the
communication cable, ensure identical earthing potential
of all inverters.
4.3.2 AC Connection Protection
No consumer load can be applied between the mains
circuit breaker/fuses and the inverters. An overload of the
cable might not be recognised. Always use separate lines
for consumer loads, protected against overcurrent and
short circuit with proper fuses/circuit breakers.
The MLX inverters are designed with a 3-phased and
protective earth (without neutral) AC grid interface for
operation under the conditions described in Table 4.3.
ParameterOperation range
Grid interface3P + PE (delta or WYE)
Grid voltage, phase-phase400 V or 480 V (+/- 10%)
Grid frequency50 Hz or 60 Hz (+/- 10%)
Table 4.3 AC Operating Conditions
When choosing grid code, the parameters in the above
specification are limited to comply with the specific grid
codes.
Earthing systems
The MLX inverters can operate on TN-S, TN-C, TN-C-S, and
TT systems. Ungrounded delta systems are supported, but
IT systems are not.
Where an external RCD is required in addition to the builtin RCMU, a type B RCD must be used. Consider a current
sensitivity of 600 mA per inverter to avoid nuisance
tripping. Table 4.4 shows the maximum values of the earth
resistance in TT grids, depending on the sensitivity of the
RCD to have lower values than 50 V of contact voltage,
and so a proper protection.
Use circuit breakers/fuses with switch functionality for
short-circuit protection and safe disconnection of the
inverters. Threaded fuse elements like ‘Diazed’ (D-type) are
not considered adequate as a switch. Fuse holder can be
damaged if dismounted under load. ‘Neozed’ (D03-type,
100 A) can be installed in fuse-switch disconnection units
adequate for switch purposes. NH fuses require an
additional tool, a grip handle.
Dedicated circuit breakers/fuses for each individual inverter
output line must be installed according to the specifications in Table 6.4, in which it has been taken into
account that derating of the circuit breakers/fuses can be
necessary due to self-heating when installed in groups, or
if exposed to heat. The maximum fuse size is 125 A.
For TN grids with no RCDs installed, check that the rating
and curve of the circuit breakers/fuses selected are
adequate for a proper residual current protection (tripping
fast enough), considering the type of cable and cable
length.
Consider the maximum short-circuit current in the location
of the circuit breaker/fuses. Short-circuit currents can be as
high as 60 kA, if the short-circuit current is produced inside
a 2.5 MVA transformer station. This is the reason why only
NH fuses or MCCBs, with higher breaking capacity, should
be used in the main LV protection board integrated in the
24L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Electrica...
4
transformer station, and D0 fuses and MCBs, with lower
breaking capacity, should only be used for AC combiners
distributed in the plant.
AC combiners are not specifically required for AC distribution in ground-based plants with MLX inverters: the
output line of each inverter can be directly protected with
NH fuses in a main LV protection board integrated in the
transformer station. If AC layout includes AC combiners
and a main LV protection board, selective coordination of
protection should be considered, in order to avoid tripping
of protection in the main LV protection board in case of
short circuit in an inverter line. This selective coordination
can be particularly complicated when MCBs are used in
the AC combiner and MCCBs in the main LV protection
board.
Use the PV load switch to turn off the inverter before
removing/replacing the fuse elements.
For information about cable requirements, see 3.4 CableSpecifications.
4.3.3 Grid Impedance
Current capacity of the cable depends on the wire material
(copper or aluminium) and insulation type (for example
PVC or XLPE). Factors, such as high ambient temperature
or grouping of cables, produce derating of the current
capacity of the cable. Follow the local legislation for
correction factors calculation.
The maximum AC cable losses permitted also depend on
the local legislation. Cable losses depend on the wire
material (copper or aluminium), the cable cross-section and
the cable length.
In TN grids, due to the low impedance path for the fault
loop, fault currents are high. This means that the shortcircuit protection can also be used for residual current
protection, if a tripping time lower than 0.4 s can be
ensured, according to IEC 60364-4-41, table 41.1. This can
be checked using the time/current curves of the fuses/
circuit breakers installed for the minimum short-circuit
current (I
Initially consider a minimum AC cabling section of 35 mm
(Cu) and 50 mm2 (Al).
) expected in the line they protect.
sc,min
4
2
The grid impedance must correspond to the power size of
the application* in order to avoid unintended disconnection from the grid or derating of the output power.
Ensure that cable dimensions are correct, to avoid losses.
Additionally the no load voltage at the connection point
must be taken into account.
*The total system impedance is defined in per cent as:
Ztotal = ZPCC + ZtrafoMVHV + ZtrafoLVMV [%], where:
ZPCC is the per cent short-circuit impedance of the
-
point of common coupling (PCC) calculated based
on the short-circuit power available at the PCC (this
data is typically provided by the DNO/TSO),
ZtrafoMVHV is the short-circuit impedance of the
-
MV/HV transformer unit as stated in the transformer
datasheet (if non-existent then use 0),
ZtrafoLVMV is the short-circuit impedance of the
-
LV/MV transformer unit as stated in the transformer
datasheet (if non-existent then use a default 6%).
For MLX 60 kVA inverter, the maximum total system
impedance Ztotal value is 30%.
4.3.4 AC Cable Considerations
NOTICE
The maximum cable cross-section connectable to the
inverter (95 mm
system design. If the calculated cable cross-section
exceeds this limit, either use AC combiners, change the
cable type, the subplant size or the location of the
inverters.
2
/ AWG 4/0) must be addressed in the
The cable cross-section must be selected according to the
current capacity of the cable and the maximum AC cable
losses according to local legislation. In TN grids, if no RCDs
are installed, cable cross-section in combination with the
short-circuit protection installed, should also ensure a
proper residual current protection.
L00410648-02_02 / Rev. date: 2014-10-0325
5
Communication and System Pl...
5 Communication and System Planning, Inverter Manager
PC with LCS software
5.1 Ethernet Communication
5.1.1 System Overview
The system consists of 4 components:
•
Router/DHCP for plant network
•
Inverter Manager
•
MLX inverters
•
Illustration 5.1 Commissioning of Inverters Using LCS Tool
This section describes how the system works and the
function of the individual components.
The system is divided into 2 Ethernet networks; Plant
network and inverter network (see Illustration 5.1). The
plant network is the communication interface to the plant
and can operate together with other IT equipment, while
the inverter network must only be used for MLX series
inverters.
The plant network must have a router/DHCP server as the
Inverter Manager requires automatic IP assignment. It is
recommended to use professional grade routers and
switches.
NOTICE
When designing the plant network it is important to
consider network security in order to ensure that only
authorised personnel can access the plant network. This
is especially important when the plant network is
connected to the internet.
WARNING
SMA accepts no liability for damage or losses due to
unauthorised access to the plant.
The inverters are equipped with a 2 port Ethernet switch
allowing for daisy chaining. The Inverter Manager hosts the
DHCP server for the up to 42 inverters that can be
connected per Inverter Manager. In order to commission
the plant, all inverters must be connected to the Inverter
Manager. If the inverters loose connection they will
disconnect from the grid. Plants requiring more than 42
inverters can use multiple Inverter Managers in the plant
network.
5.1.2 Inverter Manager
The Inverter Manager separates the plant network and the
inverter network and handles the following plant level
tasks:
Allows access through SunSpec Modbus TCP
•
profile (acts as gateway to the inverters)
Distributed control of active and reactive power
•
(for example through reactive setpoint curves and
Power Level Adjustment)
Portal upload to FTP server
•
Access to plant configuration and service through
•
LCS
26L00410648-02_02 / Rev. date: 2014-10-03
Communication and System Pl...
5
Connection interfaces for external devices such as
•
I/O box (grid management) and weather stations
5.2 User Interfaces
The Local Commissioning and Service tool (LCS) is used to
commission the Inverter Manager and inverters, enabling
them to start injecting power into the grid. With the LCS
Tool it is possible to:
Perform software update of the system
•
Read out inverter values (voltage, current, etc.)
•
Display inverter event logs
•
Load custom grid code file (information about
•
how to obtain custom grid file see 2.5 Grid Code)
Configure portal FTP upload
•
Access commissioning reports
•
Modbus gateway address list
•
Add/replace inverters
•
The MLX inverters and Inverter Managers must be commissioned via the Local Commissioning and Service Tool (LCS
Tool). Commissioning is required before the MLX inverters
can connect to the AC grid and inject power.
The LCS Tool is available from the download area at
www.sma.de.
The hardware requirements for the LCS Tool are:
PC running WindowsTM 7 and later
•
1 GB HDD
•
2 GB RAM
•
The LCS Tool must be installed on a local PC drive. The PC
must be connected to the plant network of the Inverter
Manager.
NOTICE
The Inverter Manager must have an IP address assigned
by a DHCP server on the LAN 1 port.
It is important that the PC running the LCS Tool is
connected to the same IP subnet as the Inverter
Manager.
Port LAN 2 is intended for MLX inverters exclusively.
5
Illustration 5.2 Commissioning of Inverters Using LCS Tool
The I/O box is used for transmitting the relay state from a
ripple control receiver, provided by the DNO, to the
Inverter Manager over RS-485. An I/O box is required for
each Inverter Manager.
L00410648-02_02 / Rev. date: 2014-10-0327
5.4 Weather Station
Any SunSpec-compliant RS-485 weather station can be
connected to the Inverter Manager.
6
Technical Data
6 Technical Data
6.1 Technical Data
ParameterMLX 60
AC
Rated apparent power
Rated active power
Reactive power range
1)
2)
1)
Rated grid voltage (voltage range)3P + PE (delta or WYE) / 400-480 V (+/- 10%)
Grounding schemes supportedTT, TN
Rated current AC3 x 87 A
Max. current AC3 x 87 A
AC current distortion (THD at nominal output power)< 1%
Power factor default> 0.99 at rated power
Power factor - regulated0.8 over-excited, 0.8 under-excited
Stand-by power consumption (comm. only)3 W
Rated grid frequency (frequency range)50/60 Hz (+/- 10%)
DC
Input voltage range565–1000 V @ 400 V
Rated voltage DC630 V @ 400 V
MPPT voltage range - rated power570–800 V @ 400 V
Max. voltage DC1000 V
Min. on grid power100 W
Max. MPPT current DC
Max. short-circuit current DC
4)
4)
MPP tracker/Input per MPPT1 / 1 (external string combining)
Efficiency
Max. efficiency EU/CEC98.8%
EU efficiency at 570 V
CEC efficiency at 400/480 V
dc
ac
MPPT efficiency static99.9%
Enclosure
Dimensions (H x W x D)740 × 570 × 300 mm (29 × 22.5 × 12 in)
Weight
Acoustic noise level55 dB(A) (preliminary value)
60 kVA
60 kW
0–60 kVAr
680–1000 V @ 480 V
ac
710 V @ 480 V
ac
685–800 V @ 480 V
110 A
150 A
98.5%
98.0% / 98.5%
75 kg (165 lbs)
3)
ac
ac
ac
ac
Table 6.1 Specifications
1)
At rated grid voltage.
2)
At rated grid voltage, Cos(phi)=1.
3)
Depending on installed options.
4)
Under any conditions.
28L00410648-02_02 / Rev. date: 2014-10-03
Technical Data
6
ParameterMLX series
Electrical
Electrical Safety
PELV on the communication and control cardClass II
Functional
Functional Safety
Islanding detection - loss of mains
RCD compatibility
1)
IEC 62109-1/IEC 62109-2 (Class I, grounded – communication part
•
Class II, PELV)
UL 1741 with non-Isolated EPS Interactive PV Inverters
•
IEEE 1547
•
Voltage and frequency surveillance
•
DC content of AC current surveillance
•
Insulation resistance surveillance
•
Residual current monitoring
•
UL1998
•
Active frequency shift
•
Disconnection
•
3-phase monitoring
•
ROCOF/SFS
•
Type B, 600 mA
6
Table 6.2 Safety Specifications
1)
Depending on local regulations.
(Limit = rated value + tolerance).
6.2 Derating Limits
To ensure that the inverters can produce the rated power,
measurement inaccuracies are taken into account when
enforcing the derating limits stated in 2.4.2 InverterDerating.
6.3 Norms and Standards
International standardsMLX series
EU efficiency, Standard: EN50530
Efficiency
Directive LVD2006/95/EC
Directive EMC2004/108/EC
Safety
Functional safety
EMC, immunity
EMC, emission
Utility interferenceEN 61000-3-12
CE
Test procedure: Performance Test Protocol for Evaluating Inverters Used in Grid-Connected
CEC efficiency, Standard: CEC guideline
Photovoltaic Systems (Draft): March 1, 2005
IEC 62109-1/IEC 62109-2
UL 1741
UL 508i
IEC 62109-2
UL 1741/IEEE 1547
EN 61000-6-1
EN 61000-6-2
EN 61000-6-3
EN 61000-6-4
CISPR 11 Class B
FCC Part 15
Yes
L00410648-02_02 / Rev. date: 2014-10-0329
Technical Data
International standardsMLX series
IEC 61727
Utility characteristics
Table 6.3 International Standards Compliance
EN 50160
IEEE 1547 UI
6
Approvals and certificates are available from the download
area at www.sma.de.
NOTICE
Observe local regulations.
6.4 Mains Circuit Specifications
ParameterSpecification
Maximum inverter current, I
Recommended blow fuse type gL/gG (IEC
60269-1)
Recommended blow fuse Class T (UL/USA)125 A
Recommended MCB type B or C125 A
Maximum fuse size125 A
Table 6.4 Mains Circuit Specifications
acmax
87 A
100-125 A
6.5 Auxiliary Interface Specifications
InterfaceParameterParameter DetailsSpecification
EthernetCable
RJ-45 connectors:
2 pcs RJ-45 for Ethernet
Galvanic interface insulationYes, 500 Vrms
Direct contact protectionDouble/Reinforced insulationYes
Short-circuit protectionYes
CommunicationNetwork topologyStar and daisy chain
CableMax. cable length between
Max. number of invertersPer Inverter Manager42
Cable jacket diameter (
Cable typeShielded Twisted Pair (STP CAT 5e or
For outdoor and/or burial use, ensure that the appropriate type of
Ethernet cable is used.
Illustration 6.1 Auxiliary Interfaces (Cutout of Inverter Installation Compartment)
30L00410648-02_02 / Rev. date: 2014-10-03
Technical Data
6
6.6 Ethernet Connections
6
Illustration 6.2 RJ-45 Pinout Detail for Ethernet
Colour Standard
Pinout
Ethernet
1. RX+Green/whiteOrange/white
2. RXGreenOrange
3. TX+Orange/whiteGreen/white
4.BlueBlue
5.Blue/whiteBlue/white
6. TX-OrangeGreen
7.Brown/whiteBrown/white
8.BrownBrown
Table 6.6 RJ-45 Pinout Detail for Ethernet
Cat 5
T-568A
Cat 5
T-568B
6.6.1 Network Topology
The inverter has 2 Ethernet RJ-45 connectors enabling the
connection of several inverters in a line topology as an
alternative to the typical star topology.
NOTICE
Ring topology (C in Illustration 6.3) is only permitted if
realised with Ethernet switch supporting spanning tree.
Illustration 6.3 Network Topology
ALinear daisy chain
BStar topology
CRing topology (only if spanning tree is used)
1MLX inverter
2Ethernet switch
Table 6.7 Network Topology
Status of the LEDs next to the Ethernet port is explained in
Table 6.8. There are 2 LEDs per port.
StatusYellow LEDGreen LED
OffLink speed 10 MbitNo link
OnLink speed 100 MbitLink
Flashing-Activity
SMA Solar Technology AG can accept no responsibility for possible errors in catalogues, brochures and other printed material. SMA Solar Technology AG reserves the right to alter its products without notice.
This also applies to products already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed.
All trademarks in this material are property of the respective companies. SMA Solar Technology AG and the SMA Solar Technology AG logotype are trademarks of SMA Solar Technology AG All rights reserved.
Rev. date 2014-10-03 Lit. No. L00410648-02_02
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.