SMA MLX 60, MLX 60 UL, MLX Series Design Manual

SMA Solar Technology AG
Solar Inverters
MLX Series
Design Guide
www.SMA.de
Contents
Contents
1.1 Introduction
1.2 List of Abbreviations
2 Inverter Overview
2.1 Product Label
2.2 Mechanical Overview of the Inverter
2.3 Description of the Inverter
2.3.1 System Overview 6
2.3.2 Functional Safety 8
2.3.3 Operation Modes 9
2.4 MPP Tracker and Derating
2.4.1 MPP Tracker 10
2.4.2 Inverter Derating 10
2.4.3 Power Reference 10
2.5 Grid Code
2.5.1 Grid Protection Settings 12
2.6 Grid Support (Ancillary Services)
3
3
3
5
5
5
5
10
11
12
2.6.1 Fault Ride Through 12
2.6.2 Reactive Power Management 13
2.6.3 Active Power Management 14
2.7 Functional Safety Settings
3 System Planning – Mechanical
3.1 Unpacking
3.2 Installation
3.2.1 Installation Conditions
3.3 Mounting the Inverter
3.3.1 How to Position the Inverter 18
3.3.2 Torque Specifications for Installation
3.4 Cable Specifications
4 System Planning – Electrical
4.1 Introduction
4.2 DC Side
4.2.1 Requirements for PV Connection 20
14
15
15
15
16
17
19
19
20
20
20
4.2.1.1 Maximum Open-circuit Voltage 20
4.2.1.2 MPP Voltage 20
4.2.1.3 Short-circuit Current 21
4.2.1.4 MPP Current 21
L00410648-02_02 / Rev. date: 2014-10-03 1
Contents
4.2.1.5 PV to Earth Resistance 21
4.2.1.6 Earthing 21
4.2.1.7 Parallel Connection of PV Arrays 21
4.2.1.8 PV Cable Dimensions and Layout 21
4.2.2 Determining Sizing Factor for PV Systems 22
4.2.3 Thin Film 22
4.2.4 Internal Surge Overvoltage Protection 22
4.2.5 Thermal Management 23
4.2.6 Simulation of PV 23
4.2.7 PV Field Capacitance 23
4.3 AC Side
4.3.1 Requirements for AC Connection 24
4.3.2 AC Connection Protection 24
4.3.3 Grid Impedance 25
4.3.4 AC Cable Considerations 25
5 Communication and System Planning, Inverter Manager
5.1 Ethernet Communication
5.1.1 System Overview 26
5.1.2 Inverter Manager 26
5.2 User Interfaces
5.3 I/O Box
5.4 Weather Station
6 Technical Data
6.1 Technical Data
6.2 Derating Limits
6.3 Norms and Standards
24
26
26
27
27
27
28
28
29
29
6.4 Mains Circuit Specifications
6.5 Auxiliary Interface Specifications
6.6 Ethernet Connections
2 L00410648-02_02 / Rev. date: 2014-10-03
30
30
31
Introduction
1Introduction
1
1
1.1 Introduction
The Design Guide provides information required for planning and dimensioning an installation. It describes requirements for use of the MLX series inverters in solar energy applications.
Illustration 1.1 MLX Inverter
Additional resources available:
Installation Guide, supplied with the inverter, for
information required to install and commission the inverter
Inverter Manager Installation Poster, for
information required to install the Inverter Manager
Inverter Manager Assembly Installation Guide, for
information required to install the Inverter Manager Assembly
Fan Installation Instruction, for information
required to replace a fan
SPD Installation Instruction, for information
required to replace Surge Protection Devices
These documents are available from the download area at www.sma.de, or from the supplier of the solar inverter.
Additional application-specific information is available at the same location.
1.2 List of Abbreviations
Abbreviation Description
ANSI American National Standards Institute AWG American Wire Gauge cat5e Category 5 twisted pair cable (enhanced) DHCP Dynamic Host Configuration Protocol DNO Distribution Network Operator DSL Digital Subscriber Line EMC (Directive) Electromagnetic Compatibility Directive ESD Electrostatic Discharge FCC Federal Communications Commission FRT Fault Ride Through GSM Global System for Mobile Communications HDD Hard Disk Drive IEC International Electrotechnical Commission IT Isolated Terra LCS Local Commissioning and Service LED Light-Emitting Diode LVD (Directive) Low Voltage Directive MCB Miniature Circuit Breaker MPP Maximum Power Point MPPT Maximum Power Point Tracking NFPA National Fire Protection Association P P is the symbol for active power and is
measured in Watts (W). PCB Printed Circuit Board PCC Point of Common Coupling
The point on the public electricity network to
which other customers are, or could be,
connected. PE Protective Earth PELV Protected Extra-Low Voltage PLA Power Level Adjustment P
NOM
POC Point of Connection
P
STC
PV Photovoltaic, photovoltaic cells RCD Residual-Current Device RCMU Residual Current Monitoring Unit R
ISO
ROCOF Rate Of Change Of Frequency Q Q is the symbol for reactive power and is
S S is the symbol for apparent power and is
Power [W], Nominal conditions
The point at which the PV system is connected
to the public electricity grid.
Power [W], Standard Test Conditions
Insulation Resistance
measured in reactive volt-amperes (VAr).
measured in volt-amperes (VA).
L00410648-02_02 / Rev. date: 2014-10-03 3
Introduction
1
Abbreviation Description
STC Standard Test Conditions SW Software THD Total Harmonic Distortion TN-S Terra Neutral - Separate. AC Network TN-C Terra Neutral - Combined. AC Network TN-C-S Terra Neutral - Combined - Separate. AC
Network
TT Terra Terra. AC Network
Table 1.1 Abbreviations
4 L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2 Inverter Overview
2.1 Product Label
Illustration 2.1 Product Label MLX 60
The product label on the side of the inverter shows:
Inverter type
Important specifications
Serial number, located under the bar code, for
inverter identification
2.2 Mechanical Overview of the Inverter
2
Illustration 2.2 Product Label MLX 60 UL
1 Cover for installation area 2Front cover 3 Die-cast aluminium heat sink 4Mounting plate 5 Display (read-only) 6 PV load switch (optional) 7Fans
Illustration 2.3 Mechanical Overview of the Inverter
2.3 Description of the Inverter
Inverter features:
IP65 enclosure/Type 3R
PV load switch
Ancillary service functionalities
Transformerless
3-phase
3-level inverter bridge with a high performance
Integrated residual current monitoring unit.
Insulation test functionality.
L00410648-02_02 / Rev. date: 2014-10-03 5
Inverter Overview
2
Extended fault ride through capabilities (to
support reliable power generation during grid faults) - depending on inverter configuration
Compliant with a wide range of international
grids
Adapted to local requirements and conditions via
grid code setting
2.3.1 System Overview
The MLX system draws on the advantages of both string inverters and central inverters, making it highly applicable in many commercial and utility scale plants.
The MLX system consists of the MLX inverter itself, a DC string combiner and the Inverter Manager.
The communication network of an MLX system is divided into 2 Ethernet networks; Plant network and inverter network. The plant network is the communication interface to the MLX plant and may be shared by several Inverter Managers as well as other IT equipment, while the inverter network is solely used for MLX inverters. The plant network
must have a DHCP server (router) as the Inverter Manager requires automatic IP assignment. It is recommended to use professional grade routers and switches. The Inverter Manager provides:
Control of up to 42 MLX inverters
Single point of access for each (up to) 2.5 MVA
plant for simple plant network deployment
Easy commissioning and service of the plant
using the Local Commissioning and Service (LCS) tool
Safe upload to data warehouse services, and
control of all local requirements and settings from the DNO
Open source Modbus TCP communication
protocol using SunSpec Alliance profile via Ethernet both for monitoring and control, making it easy to integrate in e.g. SCADA systems
Grid management interface through the optional
I/O box for PLA and reactive power commands
Easy integration of meteorological data using an
RS-485 SunSpec Alliance compliant weather station
6 L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2
1PV strings 2DC combiner 3MLX inverter 4MLX Inverter Manager 5Router 6LCS tool 7Portal 8SCADA system 9 Weather station 10 I/O box 11 Grid management 12 Transformer station
Illustration 2.4 System Overview
L00410648-02_02 / Rev. date: 2014-10-03 7
2
Inverter Overview
Illustration 2.5 Overview of Installation Area
PELV (Safe to touch)
2 Equipment grounding 7 Ethernet interface x 2 8 RS-485 interface (not in use)
Live Part
1 AC connection terminals 5 PV connection terminals
Other
3Surge Protection AC 4Surge Protection DC 6 PV load switch (optional)
2.3.2 Functional Safety
The inverter is designed for international use, with functional safety circuit design meeting a wide range of international requirements (see 2.5 Grid Code).
Single-fault Immunity
The functional safety circuit has a fully redundant built-in single-fault detection. If a fault occurs, the inverter disconnects from the grid immediately. The method is active and covers all circuitry within the residual current monitoring, both for continuous levels and sudden changes. All functional safety circuits are tested during start-up to ensure safe operation. If a circuit fails more than 1 out of 3 times during the self-test, the inverter enters fail safe mode. If the measured grid voltages, grid frequencies, or residual current during normal operation differ too much between the 2 independent circuits, the inverter ceases to energise the grid and repeats the self­test. The functional safety circuits are always activated and cannot be disabled.
Isolation
During the self-test, the inverter has an isolation measuring system that detects whether the isolation in the PV system is above the required level. This is done before the inverter
8 L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
starts to energise the grid. During grid connection, the inverter measures the continuous leakage current in the system. If this level is exceeded more than 4 times during 24 hours, the inverter stops operating due to safety hazards in the PV system.
NOTICE
Depending on the local legislation, a minimum earth-to­PV isolation resistance is defined. A typical value is 82 kΩ.
Self-test
The insulation resistance between the PV arrays and earth is also tested during the self-test. The inverter does not energise the grid if the resistance is too low. It then waits 10 minutes before making a new attempt to energise the grid.
Residual current
Residual current is continuously monitored. The inverter ceases to energise the grid when:
The cycle RMS value of the residual current
violates the trip settings for more than the duration of ‘clearance time’, or
A sudden jump in the residual current is detected
Grid Surveillance
Grid-related parameters are under constant surveillance when the inverter energises the grid. The following is monitored:
Grid voltage magnitude (instantaneous and 10
minute average)
Grid voltage and frequency
Loss of Mains (Islanding detection):
3-phase Loss of Mains (LoM) detection
Rate of Change of Frequency (ROCOF)
Frequency shift.
DC content of grid current
Residual current by means of RCMU
The inverter ceases to energise the grid if one of the parameters violates the grid code.
Status LEDs
Green
Off grid
Connecting
On grid
Internal inverter event
Fail safe
Table 2.1
Off grid (standby) (LEDs off)
#0-51. When no power has been delivered to the AC grid for more than 10 minutes, the inverter disconnects from the grid and shuts down. User and communication interfaces remain powered for communication purposes.
Connecting (Green LED flashing) #52-53. The inverter starts up when the PV input voltage reaches the minimum DC feed-in voltage. The inverter performs a series of internal self-tests, including measurement of the resistance between the PV arrays and earth. Meanwhile, it also monitors the grid parameters. When the grid parameters have been within the specifications for the required amount of time (depends on grid code), the inverter starts to energise the grid.
On grid (Green LED on) #60. The inverter is connected to the grid and energises the grid. The inverter disconnects when:
it detects abnormal grid conditions (dependent
on grid code), or
an internal event occurs, or
PV power is insufficient (no power is supplied to
the grid for 10 minutes)
The inverter then enters connecting mode or off grid mode.
- - - - - - - - - - - - - - - - -
Red
- - - - - - - - - - - - - - - - -
Green
▬██▬██▬██▬██▬██▬
Red
- - - - - - - - - - - - - - - - -
Green
Red Green
Red Green Red
██████████████████
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
- - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
2
2.3.3 Operation Modes
The inverter has 5 operation modes, indicated by LEDs.
L00410648-02_02 / Rev. date: 2014-10-03 9
Internal Inverter Event (Green LED flashing) #54 The inverter is waiting for an internal condition to become within limits (for example a too high temperature) before it will go back on grid.
Fail Safe (Red LED flashing) #70. If the inverter detects an error in its circuits during the self­test (in connecting mode) or during operation, the inverter goes into fail safe mode, disconnecting from grid. The
Inverter Overview
2
inverter will remain in fail safe mode until power has been absent for a minimum of 10 minutes, or the inverter has been shut down completely (AC+PV).
2.4 MPP Tracker and Derating
2.4.1 MPP Tracker
The Maximum Power Point Tracker (MPPT) is an algorithm, which is constantly trying to maximise the output from the PV array. The algorithm updates the PV voltage fast enough to follow rapid changes in solar irradiance. The MPPT will find the maximum power point while the PV voltage is within the specified MPP voltage range. At voltages below the minimum MPP voltage of the inverter, the MPPT moves away from the maximum power point (see Illustration 2.6) in order to maintain sufficient DC voltage to generate the required AC grid voltage.
AC power limitation by setting or external
command (PLA)
Each MLX inverter limits the AC output power according to the actual power reference, which will be the lowest of the following values:
Max AC power rating (60 kVA)
Fixed active/reactive power limit set by grid code
file
Active/reactive power reference from the Inverter
Manager
Power limit from internal temperature derating.
Derating due to temperature is a sign of excessive ambient temperature, a dirty heat sink, a blocked fan or similar. Refer to the MLX Instal- lation Guide regarding maintenance. The values shown in Illustration 2.7 are measured at nominal conditions cos(φ) = 1
Illustration 2.6 MPPT Behaviour at Low MPP Voltage
NOTICE
Due to the boosterless design of the MLX inverter, the minimum MPP voltage varies with the actual AC grid voltage.
2.4.2 Inverter Derating
In certain situations, the MPPT purposely moves away from the maximum power point. This behaviour is called derating and is a means of protecting the inverter against overload or a reduction of output power in order to support the grid. Reactive power (supporting the grid) has priority when the derate function is reducing the AC output power, meaning that first active power is reduced to zero where after reactive power is reduced. The MLX system is derating in the following situations:
Exceeding max AC power rating
Internal over temperature
Grid over voltage
Grid over frequency
Illustration 2.7 Derating as Function of Internal Overtem-
perature
NOTICE
The inverter can use the entire admissable DC voltage range up to 1000 V for derating. It is not restricted to the MPP voltage range.
2.4.3 Power Reference
The power reference for the individual MLX inverter is generated by the Inverter Manager based on the following functions. They are all deployed in the Inverter Manager and thus calculated on plant level.
Grid Overvoltage
When the grid voltage exceeds a DNO-defined limit U1, the inverter derates the output power. If the grid voltage increases and exceeds the defined limit 10 min mean (U2), the inverter ceases to energise the grid, in order to maintain
10 L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
power quality and protect other equipment connected to the grid.
U1 Fixed U2 Trip Limit
Illustration 2.8 Grid Voltage above Limit Set by DNO
Derating - Grid Over-frequency
The output power is reduced as a variable of the grid frequency. There are 2 methods for reducing the output power: ramp and hysteresis. The grid code setting determines which method is implemented in a specific installation.
Primary frequency control - hysteresis method
See Illustration 2.10. To support grid stabilisation, the inverter reduces output power if the grid frequency exceeds f1. Reduction occurs at a preconfigured rate, which is the ramp (R) shown in Illustration 2.10. The reduced output power limit is maintained until the grid frequency has decreased to f2. When the grid frequency has decreased to f2, the inverter output power increases again following a time ramp T. If the grid frequency continues to increase, the inverter disconnects at f3. When the frequency decreases below f2, the inverter reconnects to grid and ramps up power at the same rate as for the reduction.
2
Primary frequency control – ramp method
See Illustration 2.9. The inverter reduces output power if the grid frequency exceeds f1. Reduction occurs at a preconfigured rate, which is the ramp (R) shown in Illustration 2.9. When the frequency reaches f2, the inverter disconnects from grid. When the frequency decreases below f2, the Inverter reconnects to grid and ramps up power at the same rate as for the reduction.
Illustration 2.10 Primary Frequency Control – Hysteresis
Method
2.5 Grid Code
The MLX grid code file contains settings that determine both the behaviour of the single inverter and the entire plant. The grid code file is divided into 2 main sections:
Grid protection settings
Grid support (ancillary services)
The LCS tool used for commissioning the inverter is equipped with a range of default grid codes to meet national requirements. Changing these default grid code parameters requires a customised grid code file, supplied by SMA. See 2.7 Functional Safety Settings about how to apply for customised grid code parameters.
NOTICE
Obtain approval from the local distribution network operator (DNO) before connecting the inverter to the grid.
Illustration 2.9 Primary Frequency Control – Ramp Method
L00410648-02_02 / Rev. date: 2014-10-03 11
Inverter Overview
2
2.5.1 Grid Protection Settings
The grid protection settings are stored in each inverter. They ensure protection of the grid in case of certain grid events regardless of the connection to the Inverter Manager. The inverter continuously monitors the following grid values, and compares them to the disconnection values specified in the grid code. Example:
Voltage disconnection
Frequency disconnection
Reconnection
Loss of mains
Voltage and frequency disconnection
The cycle RMS values of the grid voltages are compared with 2 lower and 2 upper trip settings, for example overvoltage (stage 1). If the RMS values violate the trip settings for more than the duration of ‘clearance time’, the inverter ceases to energise the grid.
‘clearance time’, the inverters cease to energise the grid
Rate of change of frequency (ROCOF). The ROCOF
values (positive or negative) are compared to the trip settings. The inverter ceases to energise the grid when the limits are violated
Frequency shift. The inverter continuously tries to
‘push’ the grid frequency a bit, but the stability of the grid prevents this from happening
In an LoM situation, the stability of the grid is no longer present, and this makes it possible to change the frequency. As the frequency deviates from the operational frequency of the line, the inverter disconnects and ceases to energise the grid. If the inverter ceases to energise the grid due to grid frequency or grid voltage (not 3-phase LoM), and if the frequency or voltage is restored within a short time (short interruption time), the inverter can reconnect when the grid parameters have been within their limits for the specified time (reconnect time). Otherwise, the inverter returns to the normal connection sequence.
2.6 Grid Support (Ancillary Services)
Illustration 2.11 Overvoltage and Undervoltage Disconnect
Reconnection
During start-up or when the inverter has disconnected from grid due to for example overvoltage or frequency, the reconnection values determine under which grid conditions the inverter can reconnect to the grid and start injecting energy.
Loss of Mains (Islanding) disconnection
Loss of Mains (LoM) is detected by 3 different algorithms:
3-phase voltage surveillance (the inverter has
individual control of the 3-phase currents). The cycle RMS values of the phase-phase grid voltages are compared with a lower trip setting or an upper trip setting. If the RMS values violate the trip settings for more than the duration of
The ancillary services are comprised in 2 main categories:
Fault Ride Through (FRT).
Reactive and active power management.
2.6.1 Fault Ride Through
The grid voltage usually has a smooth waveform, but occasionally the voltage drops or disappears for several milliseconds. This is often due to short circuit of overhead lines, or caused by operation of switchgear or similar in the high-voltage transmission lines. In such cases, the inverter can continue to supply power to the grid using fault ride through (FRT) functionality. Continuous power supply to the grid is essential:
To help prevent a complete voltage blackout and
stabilise the voltage in the grid.
To increase the energy delivered to the AC grid.
There are 4 different behaviours to select from:
Zero Current
Reactive current only
Active current only
Full current – reactive priority
How FRT works
Illustration 2.12 shows the requirements that must be followed by FRT. The example is for German medium­voltage grids.
12 L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
Above line 1
Area A The inverter must not disconnect from grid for
Area B Right of line 2, a short-duration disconnection from
Below line 3
For voltages above line 1, the inverter must not under any circumstances disconnect from the grid during FRT.
voltages below line 1 and left of line 2. In some cases, the DNO permits a short-duration discon­nection, in which case the inverter must be back on grid within 2 s.
grid is always permitted. The reconnect time and power gradient can be negotiated with the DNO. Below line 3 there is no requirement to remain connected to grid.
Q(U) Reactive power injected as a function of the grid voltage. Q(P) Reactive power injected as a function of the active output
power.
Q(S) Reactive power injected as a function of the apparent
output power.
Q(T) Reactive power injected as a function of the ambient
temperature. PF(P) Power factor as a function of active output power. PF(T) Power factor as a function of the ambient temperature. PFext Power factor according to external signal either via
Modbus or the external I/O box (RS-485). Qext Reactive power injected according to external signal
either via Modbus or the external I/O box (RS-485).
Table 2.2 Reactive Power Management, Control Methods
NOTICE
Only 1 method can be used at a time. A mode selector determines which method to activate.
With the setpoint curve Q(U), the inverter controls reactive power as a function of the grid voltage U. The values for the setpoint curve are determined by the local utility company and must be obtained from them (see Illustration 2.13).
2
Illustration 2.12 German Example
When a short-duration disconnection from grid occurs:
The inverter must be back on grid after 2 s
The active power must be ramped back at a
maximum rate of 10% of nominal power per s
Active power management
The inverter can support the local grid by either static or dynamic limit of the plant output power. The different methods of control are:
Fixed Pref – maximum active power limit
Power Level Adjustment (PLA) – remotely
controlled maximum active power limit (requires I/O box)
2.6.2 Reactive Power Management
Reactive power management
The inverter can support the local grid voltage by injecting reactive power. The different control methods are:
Illustration 2.13 Q(U) Setpoint Curves - Reactive Power
When the grid voltage is below nominal, the inverter is configured to inject over-excited reactive power in order to help increase the grid voltage back up to nominal. When the grid voltage is above nominal, the inverter injects under-excited reactive power to help decrease grid voltage
L00410648-02_02 / Rev. date: 2014-10-03 13
Inverter Overview
2
and thus supports the grid by maintaining a more stable and healthy voltage.
Qext. and PFext
Control of a plant’s reactive power injection can be handled remotely with I/O box via RS-485 or via a 3 external signal via Modbus.
2
1
rd
-party
RS-485
3
I/O box
The I/O box monitors the relay state of the Ripple control receiver (supplied by the DNO) and transmits the state to the Inverter manager via RS-485. The Inverter Manager translates the relay state into the corresponding PLA value (max. plant output power) based on the grid code configu­ration.
180AA037.1
Ethernet
1 Ripple Control Receiver 2I/O Box 3 Inverter Manager 4MLX
Illustration 2.14
External signal (3rd party)
Modbus SunSpec control profile can be used to control the reactive power injected by the plant.
2.6.3 Active Power Management
Apparent power management
The inverter can support the local grid by setting a maximum apparent power limit.
Fixed Sref – maximum apparent power limit
Fallback
The inverters in the inverter network are controlled by a Qref and Pref from the Inverter Manager. If the connection to the Inverter Manager is lost, the inverter disconnects from grid after up to 40 seconds. If the connection is restored within this period the inverter will not disconnect from grid. When the connection is restored, the inverters reconnect to grid.
4
4
4
2.7 Functional Safety Settings
The inverter is designed for international use and it can handle a wide range of requirements related to functional safety and grid behaviour. Parameters for functional safety are predefined and do not require any alteration during installation. However, some grid code parameters may require alterations during installation to allow optimisation of the local grid. Contact SMA for a custom grid code.
14 L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3 System Planning – Mechanical
The aim of this section is to provide general information for planning the mechanical installation of the MLX inverter, including mounting and cable specifications.
3.1 Unpacking
Contents:
Inverter
Mounting plate
Accessories bag, containing:
6 wall plugs 8 x 50 mm
6 mounting screws 6 x 60 mm
1 M25 cable gland with sealing
grummet for Ethernet cables
2 conduit brackets (2 inches - only for
UL version)
1 equipment grounding bolt 6 x 12 mm
Installation guide, booklet format
Quick guide, poster format
3
Illustration 3.4 Ensure Adequate Air Flow
Illustration 3.5 Mount on Non-flammable Surface
3.2 Installation
Illustration 3.1 Avoid Constant Stream of Water
Illustration 3.2 Avoid Direct Sunlight
Illustration 3.6 Mount Upright on Vertical Surface. Tilt of up to
10 degrees is permitted
Illustration 3.7 Prevent Dust and Ammonia Gases
NOTICE
When planning the installation site, ensure that inverter product and warning labels remain visible. For details, refer to 6 Technical Data.
Illustration 3.3 Ensure Adequate Air Flow
L00410648-02_02 / Rev. date: 2014-10-03 15
3
System Planning – Mechanica...
3.2.1 Installation Conditions
Parameter Specification
Operational temperature range
Storage temperature Relative humidity 95% (non-condensing) Environmental class according to IEC
60721-3-4 Cooling concept Forced Air quality - general ISA S71.04-1985
Air quality - coastal, heavy industrial and agricultural zones Vibration 1G Enclosure rating ingress protection class IP65 UL 50E enclosure type Type 3R Max. operating altitude 2000 m (6500 ft) above sea level (derating may occur at an altitude over 1000 m). Installation Avoid constant stream of water.
25 °C – +60 °C (possible power derating above 45 °C) (−13 °F – 140 °F) (possible power
derating above 113 °F)
40 °C – +60 °C (−40°F – 140 °F)
4K4H/4Z4/4B2/4S3/4M2/4C2
Level G3 (at 75% RH) Must be measured and classified acc. to ISA S71.04-1985: G3 (at 75% RH)
Avoid direct sunlight. Ensure adequate air flow. Mount on non-flammable surface. Mount upright on vertical surface. Prevent dust and ammonia gases.
Table 3.1 Conditions for Installation
Parameter Condition Specification
Mounting plate Hole diameter 30 x 9 mm
Alignment
Table 3.2 Mounting Plate Specifications
Perpendicular
±
10° all angles
16 L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3.3 Mounting the Inverter
3
Illustration 3.8 Safe Clearances
NOTICE
Ensure 620 mm/24 inches base clearance for adequate airflow.
L00410648-02_02 / Rev. date: 2014-10-03 17
3
System Planning – Mechanica...
Illustration 3.10 Position the Inverter
Illustration 3.9 Mounting Plate
NOTICE
Use of the mounting plate delivered with the inverter is mandatory. If the inverter is mounted without the mounting plate, the warranty becomes void. It is strongly recommended to use all 6 mounting holes.
Important when mounting the mounting plate:
Mount in the defined environment
Use screws and rawl plugs that can safely carry
the weight of the inverter
Ensure that the mounting plate is correctly
aligned
Observe safe clearances when installing 1 or
more inverters, to ensure adequate airflow. Clearances are specified in Illustration 3.8 and the mounting plate label
Mounting multiple inverters in a single row is
recommended. Contact the supplier for guidelines when mounting inverters in more than 1 row
Ensure adequate clearance at the front, for
service access to the inverter
Illustration 3.11 Lifting Bolts
CAUTION
Refer to local health and safety regulations when handling the inverter.
3.3.1 How to Position the Inverter
Use M12 or ½ in lifting bolts and matching nuts (not supplied in the accessories bag) for mounting.
18 L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Mechanica...
3
3.3.2 Torque Specifications for Installation
Illustration 3.12 Overview of Inverter with Torque Indications
Parameter Tool Tightening Torque
1M63 cable gland
body
2Terminals on AC
terminal block 3 PE TX 30 3.9 Nm (35 in-lbf) 4 Terminal on DC TX 30 14 Nm (124 in-lbf) 5M32 cable gland
body 6M32 cable gland
compression nut 7M25 cable gland
body 8M25 cable gland
compression nut 9M6 equipment
bonding
Front screw (not
shown)
Wrench 65/68 mm TX 30 14 Nm (124 in-lbf)
Wrench 36 mm 6 Nm (53 in-lbf)
Wrench 36 mm 1.8 Nm (16 in-lbf)
Wrench 27 mm 10 Nm (89 in-lbf)
Wrench 27 mm 1.8 Nm (16 in-lbf)
TX 20 3.9 Nm (35 in-lbf)
TX 30 1.5 Nm (13 in-lbf)
6 Nm (53 in-lbf)
CAUTION
If the blind plugs are removed (see (7) in Illustration 3.12), use fittings with type rating: 3, 3S, 4, 4X, 6, 6P.
3
Table 3.3 Torque Specifications
3.4 Cable Specifications
Terminal Range Max. conductor
temperature
rating
AC + PE
PV
Table 3.4 Acceptable Conductor Sizes
16-95 mm 6-4/0 AWG 16-95 mm 6-4/0 AWG
90 ºC Al/Cu 37-44 mm
2
90 ºC Al/Cu 14-21 mm
2
Conductor
material
Cable
jacket
diameter
L00410648-02_02 / Rev. date: 2014-10-03 19
System Planning – Electrica...
4 System Planning – Electrical
4
4.1 Introduction
The aim of this section is to provide general information for planning integration of the inverter into a PV system:
PV system design, including earthing
AC grid connection requirements; including
choice of AC cable protection
Ambient conditions, e.g. ventilation
4.2 DC Side
4.2.1 Requirements for PV Connection
The specifications for PV connection are shown in Table 4.1.
Parameter MLX 60
MPP trackers/Inputs per MPPT 1/1 (external string combining) Maximum input voltage, open
dcmax
)
circuit (V Input voltage range 565–1000 V @ 400 Vac
Rated voltage DC 630 V @ 400 Vac
MPPT voltage range - rated power Max. MPPT current DC 110 A Max. short circuit current DC 150 A
Table 4.1 PV Operating Conditions
Illustration 4.1 Operating Range per MPP Tracker
1000 V
680–1000 V @ 480 Vac
710 V @ 480 Vac 570–800 V @ 400 Vac 685–800 V @ 480 Vac
To avoid damaging the inverter, observe the limits in Table 4.1 when dimensioning the PV generator for the inverter.
CAUTION
Always observe local requirements, rules, and regulations for the installation.
4.2.1.1 Maximum Open-circuit Voltage
The open-circuit voltage from the PV strings must not exceed the maximum open-circuit voltage limit of the inverter. Calculate the open-circuit voltage at the lowest PV module operating temperature expected for the location. If the module operating temperature is not well­defined, check local common practice. This calculation implies a maximum of 23–26 modules per string, for standard 60-cells c-Si modules. It depends on the local climate, module model, and installation conditions (for example ground based or flush mounted). Also check that the maximum system voltage of the PV modules is not exceeded. Special requirements apply to thin-film modules. See
4.2.3 Thin Film.
4.2.1.2 MPP Voltage
The string MPP voltage must be within the operational range of the inverter MPPT. Operational range is defined by:
Minimum voltage operation MPP:
570 V @ 400 V
-
685 V @ 480 V
-
Other grid voltages: Estimate by
-
‘√2 x grid voltage [V
Maximum voltage operating MPP (800 V), for the
temperature range of the PV modules
This requirement implies a minimum of 23–25 modules per string, for standard 60-cells c-Si modules. It depends on the location, module model, installation conditions, and grid voltage. If the input DC voltage is below the minimum MPP voltage for a period, the inverter will not trip but shift the operation up to the minimum voltage operation MPP, resulting in some yield losses.
MPP of the inverter can be below the minimum voltage operation MPP due to circumstances like:
High cell temperature
Partial shading conditions
ac
ac
]’
ac
20 L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Electrica...
4
Insufficient number of modules per string
High grid voltage
In general, the yield losses are minor for 400 V Yield losses can be minimised for 480 V
Increasing the number of modules per string
Reducing the grid voltage seen by the inverters
Grid voltage can be reduced by:
modifying the tap changer position in
-
the transformer station
moving the inverters to another location
-
modifying the AC cable sections
-
If the previous actions are insufficient for a particular project to minimise the yield losses due to MPP range at a low level, an auto-transformer 480–400 V can be installed in order to reduce the grid voltage.
ac
grids.
ac
grids by:
NOTICE
SMA can support you in the analysis of the yield losses due to MPP range for your particular project and in the selection of the best technical approach.
4.2.1.3 Short-circuit Current
The short-circuit current (Isc) must not exceed the absolute maximum that the inverter is able to withstand. Check the specification of the short-circuit current at the highest PV module operating temperature and the highest irradiance level expected. 125% of the module Isc at STC is used per string for the calculation, following the recommendations of the NEC and other regulations. This implies no more than 14 strings per inverter, for standard 60-cells c-Si modules.
4.2.1.4 MPP Current
The MLX inverter is able to provide full AC power even at its lower MPP range threshold. If the MPP current exceeds 110 A (due to high irradiance conditions or large number of strings per inverter), the inverter does not trip but shifts the operation point, resulting in some yield losses. In addition, the inverter limits the power intake by shifting the MPP when surplus PV power is available. For further information about PV over-sizing and related consequences, see 4.2.2 Determining Sizing Factor for PV Systems.
4.2.1.5 PV to Earth Resistance
Monitoring of the PV to earth resistance is implemented for all grid codes. Supplying energy to the grid with too low resistance could be harmful to the inverter and/or the PV modules. PV modules designed according to the IEC61215 standard are only tested to a specific resistance of minimum 40 MΩ*m
2
. Therefore, for an 84 kWp power
plant with a 14% PV module efficiency, the total area of the modules yields 600 m resistance of 40 MΩ*m must be within the required limit of the applied grid code. See 2.3.2 Functional Safety and 2.5 Grid Code.
2
. This yields a minimum
2
/600 m2 = 66.67 kΩ. The PV design
4.2.1.6 Earthing
It is not possible to earth any of the terminals of the PV arrays. However, it can be compulsory to earth all conductive materials, for example, the mounting system, to comply with the general codes for electrical installations. In addition, the PE terminal of the inverter must be always connected to earth.
CAUTION
It can be harmful to humans if not properly grounded.
4.2.1.7 Parallel Connection of PV Arrays
The MLX inverter has 1 input and 1 MPPT. An external string combiner is always required. Due to the number of strings in parallel, fusing of the strings in the string combiner is required. The recommendation is to place the string combiner close to the strings. The use of only 1 cable for each pole from the PV array to the inverter reduces the cable and installation costs.
4.2.1.8 PV Cable Dimensions and Layout
DC cabling is composed of 2 different cable segments:
The string cabling from the modules to the string
combiner (usually 4 mm
The combined line from the string combiner to
the inverter (recommended at least 50 mm (copper) or 70 mm2 (aluminium))
The cable section must be selected for each segment according to the current capacity of the cable and maximum DC cable losses according to local legislation.
Current capacity of the cable depends on the material of the wires (copper or aluminium) and the type of insulation (for example PVC or XLPE). Factors as for example high ambient temperature or grouping of cables produce derating of the current capacity of the cable. Follow the local legislation for correction factors calculation.
The maximum DC cable losses permitted also depend on the local legislation. Note that the limit must include both the losses in the strings and the combined line. Cable losses depend on the material of the wires (copper or aluminium), cross-section area and the cable length.
Take the following into account:
The total length for a string is defined as twice
the physical distance between the string and the
2
or 6 mm2)
2
4
L00410648-02_02 / Rev. date: 2014-10-03 21
System Planning – Electrica...
4
string combiner plus the length of the PV cables included in the modules
The total length for the combined line is defined
as twice the physical distance between the string combiner and the inverter
NOTICE
For the combined line, the maximum cable section connectable to the inverter (95 mm addressed in the system design. If the calculated cable section exceeds this limit, change the cable type, the sub-plant size, or the location of the string combiners/ inverters.
Avoid looping the DC cables as they can act as an antenna of radio-noise emitted by the inverter. Cables with positive and negative polarity must be placed side by side with as little space between them as possible. This also lowers the induced voltage in case of lightning and reduces the risk of damage.
4.2.2 Determining Sizing Factor for PV Systems
When determining the PV system size factor, a specific analysis is preferred, especially for large PV installations. Local rules of thumb for choosing the sizing factor can be determined, depending on local conditions, for example:
Local climate
Local legislation
System price level
To select the optimal configuration/sizing factor, an investment analysis must be made. Large sizing factors usually reduce specific investment costs (€/kWp) but could have lower specific yield (kWh/kWp) due to derating losses in the inverter (excessive DC power or overheating) and so, lower income. Small sizing factors result in greater investment costs. However, specific yield is potentially greater due to little or no derating loss.
2
/ AWG 4/0) must be
The MLX inverter supports different sizing factors, depending on the number of modules per string and number of strings per inverter. Any configuration that observes the varying conditions for different applications: the limits in Table 4.1 for short-circuit current and open-circuit voltage will be considered as valid and so covered by warranty.
4.2.3 Thin Film
The MLX inverter is a transformerless inverter without booster and so the PV voltage is distributed symmetrically to earth. Grounding of the minus pole is not allowed.
The use of transformerless inverters as MLX is
approved by many thin-film module manufac­turers not requiring grounding of the minus pole
The MLX inverter is not compatible with thin-film
modules with a requirement of minus pole grounding
NOTICE
It is important to get approval from the module manufacturer before installing thin-film modules with MLX inverters.
CAUTION
Module voltage during initial degradation can be higher than the rated voltage in the data sheet. This must be considered when designing the PV system, since excessive DC voltage can damage the inverter. Module current can also lie above the inverter current limit during the initial degradation. In this case, the inverter decreases the output power accordingly, resulting in lower yield. Therefore, when designing, take inverter and module specifications both before and after initial degradation into consideration.
4.2.4 Internal Surge Overvoltage Protection
Installations in regions with frequent irradiation levels over 1,000 W/m lations in regions with infrequent irradiance levels over 1000 W/m not expected during the irradiance peaks.
A lower sizing factor must also be considered for tracking systems, because they allow more frequent high irradiance levels. In addition, derating due to overheating of the inverter must be considered for tracking systems in hot climates. This can also reduce the recommended sizing factor further.
22 L00410648-02_02 / Rev. date: 2014-10-03
2
have lower levels of sizing factor than instal-
2
. In particular, if high ambient temperatures are
The MLX inverter includes high performance DIN-rail SPDs in both AC (type II+III, according to IEC 61643-11) and DC (type II) sides. The SPDs are easy to replace if damaged.
System Planning – Electrica...
4
The thermal management concept of the inverter is based on forced cooling with speed-controlled fans. The fans are electronically controlled and are only active when needed. The rear of the inverter is designed as a heat sink that removes the heat generated by the power semiconductors in the integrated power modules. Additionally, the magnetic parts are ventilated by force. At high altitudes, the cooling capacity of the air is reduced. The fan control attempts to compensate for this reduced cooling. At altitudes greater than 1000 m, consider derating of the inverter power when planning system layout, to avoid loss of energy.
4
1 SPD (AC) with 3 fuses.
Fuse to far right (green) does not require any replacement.
2 SPD (DC) with 2 fuses.
Fuse in the middle (green) does not require any replacement.
Illustration 4.2 Overview of Installation Area
Based in the combination of gas-filled spark gap and MOVs technologies, SPDs in MLX have the following advantages:
No leakage or operation current: no insulation
faults and tripping of the inverter, and no aging
No follow current: no tripping of the upstream
overcurrent protection during surge events
If the PV system is installed on a building with an existing lightning protection system, the PV system must also be properly included in the lightning protection system.
CAUTION
When mounting the inverter on a grounded metallic surface, ensure that the inverter’s earthing point and mounting plate are directly connected. Failure to do so can potentially result in material damage to the inverter, via arcing between the mounting plate and the inverter enclosure.
4.2.5 Thermal Management
All power electronics generate excess heat, which must be controlled and removed to avoid damage and to achieve high reliability and long life. The temperature around critical components like the integrated power modules is continuously measured to protect the electronics against overheating. If the temperature exceeds the limits, the inverter reduces output power to maintain temperature at a safe level.
Altitude Max. load of inverter 95%
Table 4.2 Compensation for Altitude
2000 m
NOTICE
PELV protection is effective up to 2000 m above sea level only.
Account for other altitude-related factors, such as increased irradiation.
Optimise reliability and lifetime by mounting the inverter in a location with low ambient temperature.
NOTICE
For indoor locations, consider a maximum airflow of 640
3
/h and a maximum heat dissipation of 1500 W per
m inverter.
4.2.6 Simulation of PV
Contact the supplier before connecting the inverter to a power supply for testing purposes, for example, simulation of PV. The inverter has built-in functionalities that can harm the power supply or the inverter.
4.2.7 PV Field Capacitance
PV fields have a small parasitic capacitance, which is directly proportional to the area and inversely proportional to the thickness of the modules. Depending on the weather conditions, a total capacity of about 50–150 nF/kW can be determined for a plant with crystalline modules. For standard thin-film modules (CdTe, CIS, and a­Si) similar values are expected. Under extreme conditions, stainless steel sheet-based thin-film modules can produce values near to 1 mF/kW.
The MLX inverter is designed to operate with a PV field capacitance up to 8.8 μF. If this limit is exceeded, the
L00410648-02_02 / Rev. date: 2014-10-03 23
System Planning – Electrica...
4
capacitive leakage current can provoke undesired tripping of the RCMU class B of the MLX inverter, and, as a result, the disconnection of the inverter from the grid.
WARNING
Plants with no grounding of the structure can be dangerous. If a grounded person touches the modules, a capacitive leakage current can flow through his body. It is especially important to ground the support structure of the modules when transformerless inverter having AC ripple on the DC side are installed in combination with high-capacity PV modules. This draws the capacitive leakage current to ground and prevents any bodily harm.
Observe the National Electric Code, ANSI/NFPA 70. Input and output circuits are isolated from the enclosure. System grounding is the responsibility of the installer.
4.3 AC Side
4.3.1 Requirements for AC Connection
CAUTION
Always follow local regulations.
Current sensitivity
20 A 2.5 Ω
Basic sensitivity
Medium sensitivity
High sensitivity ≤ 30 mA > 500 Ω
Table 4.4 Maximum Earth Resistance in TT Grids, Depending
on the Current Sensitivity of the RCD
10 A 5 Ω 5 A 10 Ω 3 A 17 Ω 1 A 50 Ω 500 mA 100 Ω 300 mA 167 Ω 100 mA 500 Ω
Maximum value of earth resistance
NOTICE
When using TN-C earthing to avoid earth currents in the communication cable, ensure identical earthing potential of all inverters.
4.3.2 AC Connection Protection
No consumer load can be applied between the mains circuit breaker/fuses and the inverters. An overload of the cable might not be recognised. Always use separate lines for consumer loads, protected against overcurrent and short circuit with proper fuses/circuit breakers.
The MLX inverters are designed with a 3-phased and protective earth (without neutral) AC grid interface for operation under the conditions described in Table 4.3.
Parameter Operation range
Grid interface 3P + PE (delta or WYE) Grid voltage, phase-phase 400 V or 480 V (+/- 10%) Grid frequency 50 Hz or 60 Hz (+/- 10%)
Table 4.3 AC Operating Conditions
When choosing grid code, the parameters in the above specification are limited to comply with the specific grid codes.
Earthing systems
The MLX inverters can operate on TN-S, TN-C, TN-C-S, and TT systems. Ungrounded delta systems are supported, but IT systems are not.
Where an external RCD is required in addition to the built­in RCMU, a type B RCD must be used. Consider a current sensitivity of 600 mA per inverter to avoid nuisance tripping. Table 4.4 shows the maximum values of the earth resistance in TT grids, depending on the sensitivity of the RCD to have lower values than 50 V of contact voltage, and so a proper protection.
Use circuit breakers/fuses with switch functionality for short-circuit protection and safe disconnection of the inverters. Threaded fuse elements like ‘Diazed’ (D-type) are not considered adequate as a switch. Fuse holder can be damaged if dismounted under load. ‘Neozed’ (D03-type, 100 A) can be installed in fuse-switch disconnection units adequate for switch purposes. NH fuses require an additional tool, a grip handle.
Dedicated circuit breakers/fuses for each individual inverter output line must be installed according to the specifi­cations in Table 6.4, in which it has been taken into account that derating of the circuit breakers/fuses can be necessary due to self-heating when installed in groups, or if exposed to heat. The maximum fuse size is 125 A.
For TN grids with no RCDs installed, check that the rating and curve of the circuit breakers/fuses selected are adequate for a proper residual current protection (tripping fast enough), considering the type of cable and cable length.
Consider the maximum short-circuit current in the location of the circuit breaker/fuses. Short-circuit currents can be as high as 60 kA, if the short-circuit current is produced inside a 2.5 MVA transformer station. This is the reason why only NH fuses or MCCBs, with higher breaking capacity, should be used in the main LV protection board integrated in the
24 L00410648-02_02 / Rev. date: 2014-10-03
System Planning – Electrica...
4
transformer station, and D0 fuses and MCBs, with lower breaking capacity, should only be used for AC combiners distributed in the plant.
AC combiners are not specifically required for AC distri­bution in ground-based plants with MLX inverters: the output line of each inverter can be directly protected with NH fuses in a main LV protection board integrated in the transformer station. If AC layout includes AC combiners and a main LV protection board, selective coordination of protection should be considered, in order to avoid tripping of protection in the main LV protection board in case of short circuit in an inverter line. This selective coordination can be particularly complicated when MCBs are used in the AC combiner and MCCBs in the main LV protection board.
Use the PV load switch to turn off the inverter before removing/replacing the fuse elements. For information about cable requirements, see 3.4 Cable Specifications.
4.3.3 Grid Impedance
Current capacity of the cable depends on the wire material (copper or aluminium) and insulation type (for example PVC or XLPE). Factors, such as high ambient temperature or grouping of cables, produce derating of the current capacity of the cable. Follow the local legislation for correction factors calculation.
The maximum AC cable losses permitted also depend on the local legislation. Cable losses depend on the wire material (copper or aluminium), the cable cross-section and the cable length.
In TN grids, due to the low impedance path for the fault loop, fault currents are high. This means that the short­circuit protection can also be used for residual current protection, if a tripping time lower than 0.4 s can be ensured, according to IEC 60364-4-41, table 41.1. This can be checked using the time/current curves of the fuses/ circuit breakers installed for the minimum short-circuit current (I
Initially consider a minimum AC cabling section of 35 mm (Cu) and 50 mm2 (Al).
) expected in the line they protect.
sc,min
4
2
The grid impedance must correspond to the power size of the application* in order to avoid unintended discon­nection from the grid or derating of the output power. Ensure that cable dimensions are correct, to avoid losses. Additionally the no load voltage at the connection point must be taken into account.
*The total system impedance is defined in per cent as: Ztotal = ZPCC + ZtrafoMVHV + ZtrafoLVMV [%], where:
ZPCC is the per cent short-circuit impedance of the
-
point of common coupling (PCC) calculated based on the short-circuit power available at the PCC (this data is typically provided by the DNO/TSO),
ZtrafoMVHV is the short-circuit impedance of the
-
MV/HV transformer unit as stated in the transformer datasheet (if non-existent then use 0),
ZtrafoLVMV is the short-circuit impedance of the
-
LV/MV transformer unit as stated in the transformer datasheet (if non-existent then use a default 6%).
For MLX 60 kVA inverter, the maximum total system impedance Ztotal value is 30%.
4.3.4 AC Cable Considerations
NOTICE
The maximum cable cross-section connectable to the inverter (95 mm system design. If the calculated cable cross-section exceeds this limit, either use AC combiners, change the cable type, the subplant size or the location of the inverters.
2
/ AWG 4/0) must be addressed in the
The cable cross-section must be selected according to the current capacity of the cable and the maximum AC cable losses according to local legislation. In TN grids, if no RCDs are installed, cable cross-section in combination with the short-circuit protection installed, should also ensure a proper residual current protection.
L00410648-02_02 / Rev. date: 2014-10-03 25
5
Communication and System Pl...
5 Communication and System Planning, Inverter Manager
PC with LCS software
5.1 Ethernet Communication
5.1.1 System Overview
The system consists of 4 components:
Router/DHCP for plant network
Inverter Manager
MLX inverters
Illustration 5.1 Commissioning of Inverters Using LCS Tool
1 LCS Tool 2Router/DHCP 3MLX Inverter Manager 4MLX inverter 5LAN 2 6LAN 1
This section describes how the system works and the function of the individual components.
The system is divided into 2 Ethernet networks; Plant network and inverter network (see Illustration 5.1). The plant network is the communication interface to the plant and can operate together with other IT equipment, while the inverter network must only be used for MLX series inverters.
The plant network must have a router/DHCP server as the Inverter Manager requires automatic IP assignment. It is recommended to use professional grade routers and switches.
NOTICE
When designing the plant network it is important to consider network security in order to ensure that only authorised personnel can access the plant network. This is especially important when the plant network is connected to the internet.
WARNING
SMA accepts no liability for damage or losses due to unauthorised access to the plant.
The inverters are equipped with a 2 port Ethernet switch allowing for daisy chaining. The Inverter Manager hosts the DHCP server for the up to 42 inverters that can be connected per Inverter Manager. In order to commission the plant, all inverters must be connected to the Inverter Manager. If the inverters loose connection they will disconnect from the grid. Plants requiring more than 42 inverters can use multiple Inverter Managers in the plant network.
5.1.2 Inverter Manager
The Inverter Manager separates the plant network and the inverter network and handles the following plant level tasks:
Allows access through SunSpec Modbus TCP
profile (acts as gateway to the inverters)
Distributed control of active and reactive power
(for example through reactive setpoint curves and Power Level Adjustment)
Portal upload to FTP server
Access to plant configuration and service through
LCS
26 L00410648-02_02 / Rev. date: 2014-10-03
Communication and System Pl...
5
Connection interfaces for external devices such as
I/O box (grid management) and weather stations
5.2 User Interfaces
The Local Commissioning and Service tool (LCS) is used to commission the Inverter Manager and inverters, enabling them to start injecting power into the grid. With the LCS Tool it is possible to:
Perform software update of the system
Read out inverter values (voltage, current, etc.)
Display inverter event logs
Load custom grid code file (information about
how to obtain custom grid file see 2.5 Grid Code)
Configure portal FTP upload
Access commissioning reports
Modbus gateway address list
Add/replace inverters
The MLX inverters and Inverter Managers must be commis­sioned via the Local Commissioning and Service Tool (LCS
Tool). Commissioning is required before the MLX inverters can connect to the AC grid and inject power.
The LCS Tool is available from the download area at www.sma.de.
The hardware requirements for the LCS Tool are:
PC running WindowsTM 7 and later
1 GB HDD
2 GB RAM
The LCS Tool must be installed on a local PC drive. The PC must be connected to the plant network of the Inverter Manager.
NOTICE
The Inverter Manager must have an IP address assigned by a DHCP server on the LAN 1 port. It is important that the PC running the LCS Tool is connected to the same IP subnet as the Inverter Manager. Port LAN 2 is intended for MLX inverters exclusively.
5
Illustration 5.2 Commissioning of Inverters Using LCS Tool
1LCS Tool 2Router/DHCP 3MLX Inverter Manager 4MLX inverter 5 LAN 2 (inverter network) 6 LAN 1 (plant network)
5.3 I/O Box
The I/O box is used for transmitting the relay state from a ripple control receiver, provided by the DNO, to the Inverter Manager over RS-485. An I/O box is required for each Inverter Manager.
L00410648-02_02 / Rev. date: 2014-10-03 27
5.4 Weather Station
Any SunSpec-compliant RS-485 weather station can be connected to the Inverter Manager.
6
Technical Data
6 Technical Data
6.1 Technical Data
Parameter MLX 60
AC
Rated apparent power
Rated active power
Reactive power range
1)
2)
1)
Rated grid voltage (voltage range) 3P + PE (delta or WYE) / 400-480 V (+/- 10%) Grounding schemes supported TT, TN Rated current AC 3 x 87 A Max. current AC 3 x 87 A AC current distortion (THD at nominal output power) < 1% Power factor default > 0.99 at rated power Power factor - regulated 0.8 over-excited, 0.8 under-excited Stand-by power consumption (comm. only) 3 W Rated grid frequency (frequency range) 50/60 Hz (+/- 10%)
DC
Input voltage range 565–1000 V @ 400 V
Rated voltage DC 630 V @ 400 V
MPPT voltage range - rated power 570–800 V @ 400 V
Max. voltage DC 1000 V Min. on grid power 100 W
Max. MPPT current DC
Max. short-circuit current DC
4)
4)
MPP tracker/Input per MPPT 1 / 1 (external string combining)
Efficiency
Max. efficiency EU/CEC 98.8% EU efficiency at 570 V CEC efficiency at 400/480 V
dc
ac
MPPT efficiency static 99.9%
Enclosure
Dimensions (H x W x D) 740 × 570 × 300 mm (29 × 22.5 × 12 in) Weight
Acoustic noise level 55 dB(A) (preliminary value)
60 kVA
60 kW
0–60 kVAr
680–1000 V @ 480 V
ac
710 V @ 480 V
ac
685–800 V @ 480 V
110 A
150 A
98.5%
98.0% / 98.5%
75 kg (165 lbs)
3)
ac
ac
ac
ac
Table 6.1 Specifications
1)
At rated grid voltage.
2)
At rated grid voltage, Cos(phi)=1.
3)
Depending on installed options.
4)
Under any conditions.
28 L00410648-02_02 / Rev. date: 2014-10-03
Technical Data
6
Parameter MLX series
Electrical
Electrical Safety
PELV on the communication and control card Class II
Functional
Functional Safety
Islanding detection - loss of mains
RCD compatibility
1)
IEC 62109-1/IEC 62109-2 (Class I, grounded – communication part
Class II, PELV)
UL 1741 with non-Isolated EPS Interactive PV Inverters
IEEE 1547
Voltage and frequency surveillance
DC content of AC current surveillance
Insulation resistance surveillance
Residual current monitoring
UL1998
Active frequency shift
Disconnection
3-phase monitoring
ROCOF/SFS
Type B, 600 mA
6
Table 6.2 Safety Specifications
1)
Depending on local regulations.
(Limit = rated value + tolerance).
6.2 Derating Limits
To ensure that the inverters can produce the rated power, measurement inaccuracies are taken into account when enforcing the derating limits stated in 2.4.2 Inverter Derating.
6.3 Norms and Standards
International standards MLX series
EU efficiency, Standard: EN50530
Efficiency
Directive LVD 2006/95/EC Directive EMC 2004/108/EC
Safety
Functional safety
EMC, immunity
EMC, emission
Utility interference EN 61000-3-12 CE
Test procedure: Performance Test Protocol for Evaluating Inverters Used in Grid-Connected
CEC efficiency, Standard: CEC guideline
Photovoltaic Systems (Draft): March 1, 2005
IEC 62109-1/IEC 62109-2
UL 1741
UL 508i
IEC 62109-2
UL 1741/IEEE 1547
EN 61000-6-1 EN 61000-6-2 EN 61000-6-3 EN 61000-6-4
CISPR 11 Class B
FCC Part 15
Yes
L00410648-02_02 / Rev. date: 2014-10-03 29
Technical Data
International standards MLX series
IEC 61727
Utility characteristics
Table 6.3 International Standards Compliance
EN 50160
IEEE 1547 UI
6
Approvals and certificates are available from the download area at www.sma.de.
NOTICE
Observe local regulations.
6.4 Mains Circuit Specifications
Parameter Specification
Maximum inverter current, I Recommended blow fuse type gL/gG (IEC 60269-1) Recommended blow fuse Class T (UL/USA) 125 A Recommended MCB type B or C 125 A Maximum fuse size 125 A
Table 6.4 Mains Circuit Specifications
acmax
87 A
100-125 A
6.5 Auxiliary Interface Specifications
Interface Parameter Parameter Details Specification
Ethernet Cable
RJ-45 connectors: 2 pcs RJ-45 for Ethernet
Galvanic interface insulation Yes, 500 Vrms Direct contact protection Double/Reinforced insulation Yes Short-circuit protection Yes Communication Network topology Star and daisy chain Cable Max. cable length between
Max. number of inverters Per Inverter Manager 42
Cable jacket diameter ( Cable type Shielded Twisted Pair (STP CAT 5e or
Cable characteristic impedance 100 Ω – 120 Wire gauge 24-26 AWG (depending on mating
Cable shield termination Via metallic RJ-45 plug
inverters
)
2 x 5-7 mm
SFTP CAT 5e)
metallic RJ-45 plug)
100 m (328 ft)
1)
Table 6.5 Auxiliary Interface Specifications
1)
For outdoor and/or burial use, ensure that the appropriate type of
Ethernet cable is used.
Illustration 6.1 Auxiliary Interfaces (Cutout of Inverter Installation Compartment)
30 L00410648-02_02 / Rev. date: 2014-10-03
Technical Data
6
6.6 Ethernet Connections
6
Illustration 6.2 RJ-45 Pinout Detail for Ethernet
Colour Standard
Pinout
Ethernet
1. RX+ Green/white Orange/white
2. RX Green Orange
3. TX+ Orange/white Green/white
4. Blue Blue
5. Blue/white Blue/white
6. TX- Orange Green
7. Brown/white Brown/white
8. Brown Brown
Table 6.6 RJ-45 Pinout Detail for Ethernet
Cat 5
T-568A
Cat 5
T-568B
6.6.1 Network Topology
The inverter has 2 Ethernet RJ-45 connectors enabling the connection of several inverters in a line topology as an alternative to the typical star topology.
NOTICE
Ring topology (C in Illustration 6.3) is only permitted if realised with Ethernet switch supporting spanning tree.
Illustration 6.3 Network Topology
A Linear daisy chain B Star topology C Ring topology (only if spanning tree is used) 1MLX inverter 2Ethernet switch
Table 6.7 Network Topology
Status of the LEDs next to the Ethernet port is explained in Table 6.8. There are 2 LEDs per port.
Status Yellow LED Green LED
Off Link speed 10 Mbit No link On Link speed 100 Mbit Link Flashing - Activity
Table 6.8 LED Status
L00410648-02_02 / Rev. date: 2014-10-03 31
SMA Solar Technology AG
Sonnenallee 1 34266 Niestetal Deutschland Tel. +49 561 9522-0 Fax +49 561 9522-100 www.SMA.de E-Mail: info@SMA.de
SMA Solar Technology AG can accept no responsibility for possible errors in catalogues, brochures and other printed material. SMA Solar Technology AG reserves the right to alter its products without notice. This also applies to products already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed. All trademarks in this material are property of the respective companies. SMA Solar Technology AG and the SMA Solar Technology AG logotype are trademarks of SMA Solar Technology AG All rights reserved.
Rev. date 2014-10-03 Lit. No. L00410648-02_02
Loading...