5 Communication and System Planning, Inverter Manager
5.1 Ethernet Communication
5.1.1 System Overview26
5.1.2 Inverter Manager26
5.2 User Interfaces
5.3 I/O Box
5.4 Weather Station
6 Technical Data
6.1 Technical Data
6.2 Derating Limits
6.3 Norms and Standards
24
26
26
27
27
27
28
28
29
29
6.4 Mains Circuit Specifications
6.5 Auxiliary Interface Specifications
6.6 Ethernet Connections
2L00410648-02_02 / Rev. date: 2014-10-03
30
30
31
Introduction
1Introduction
1
1
1.1 Introduction
The Design Guide provides information required for
planning and dimensioning an installation. It describes
requirements for use of the MLX series inverters in solar
energy applications.
Illustration 1.1 MLX Inverter
Additional resources available:
Installation Guide, supplied with the inverter, for
•
information required to install and commission
the inverter
Inverter Manager Installation Poster, for
•
information required to install the Inverter
Manager
Inverter Manager Assembly Installation Guide, for
•
information required to install the Inverter
Manager Assembly
Fan Installation Instruction, for information
•
required to replace a fan
SPD Installation Instruction, for information
•
required to replace Surge Protection Devices
These documents are available from the download area at
www.sma.de, or from the supplier of the solar inverter.
Additional application-specific information is available at
the same location.
1.2 List of Abbreviations
Abbreviation Description
ANSIAmerican National Standards Institute
AWGAmerican Wire Gauge
cat5eCategory 5 twisted pair cable (enhanced)
DHCPDynamic Host Configuration Protocol
DNODistribution Network Operator
DSLDigital Subscriber Line
EMC (Directive) Electromagnetic Compatibility Directive
ESDElectrostatic Discharge
FCCFederal Communications Commission
FRTFault Ride Through
GSMGlobal System for Mobile Communications
HDDHard Disk Drive
IECInternational Electrotechnical Commission
ITIsolated Terra
LCSLocal Commissioning and Service
LEDLight-Emitting Diode
LVD (Directive) Low Voltage Directive
MCBMiniature Circuit Breaker
MPPMaximum Power Point
MPPTMaximum Power Point Tracking
NFPANational Fire Protection Association
PP is the symbol for active power and is
measured in Watts (W).
PCBPrinted Circuit Board
PCCPoint of Common Coupling
The point on the public electricity network to
which other customers are, or could be,
connected.
PEProtective Earth
PELVProtected Extra-Low Voltage
PLAPower Level Adjustment
P
NOM
POCPoint of Connection
P
STC
PVPhotovoltaic, photovoltaic cells
RCDResidual-Current Device
RCMUResidual Current Monitoring Unit
R
ISO
ROCOFRate Of Change Of Frequency
QQ is the symbol for reactive power and is
SS is the symbol for apparent power and is
Power [W], Nominal conditions
The point at which the PV system is connected
to the public electricity grid.
Power [W], Standard Test Conditions
Insulation Resistance
measured in reactive volt-amperes (VAr).
measured in volt-amperes (VA).
L00410648-02_02 / Rev. date: 2014-10-033
Introduction
1
Abbreviation Description
STCStandard Test Conditions
SWSoftware
THDTotal Harmonic Distortion
TN-STerra Neutral - Separate. AC Network
TN-CTerra Neutral - Combined. AC Network
TN-C-STerra Neutral - Combined - Separate. AC
Network
TTTerra Terra. AC Network
Table 1.1 Abbreviations
4L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2 Inverter Overview
2.1 Product Label
Illustration 2.1 Product Label MLX 60
The product label on the side of the inverter shows:
Inverter type
•
Important specifications
•
Serial number, located under the bar code, for
•
inverter identification
2.2 Mechanical Overview of the Inverter
2
Illustration 2.2 Product Label MLX 60 UL
1Cover for installation area
2Front cover
3Die-cast aluminium heat sink
4Mounting plate
5Display (read-only)
6PV load switch (optional)
7Fans
Illustration 2.3 Mechanical Overview of the Inverter
2.3 Description of the Inverter
Inverter features:
IP65 enclosure/Type 3R
•
PV load switch
•
Ancillary service functionalities
•
Transformerless
•
3-phase
•
3-level inverter bridge with a high performance
•
Integrated residual current monitoring unit.
•
Insulation test functionality.
•
L00410648-02_02 / Rev. date: 2014-10-035
Inverter Overview
2
Extended fault ride through capabilities (to
•
support reliable power generation during grid
faults) - depending on inverter configuration
Compliant with a wide range of international
•
grids
Adapted to local requirements and conditions via
•
grid code setting
2.3.1 System Overview
The MLX system draws on the advantages of both string
inverters and central inverters, making it highly applicable
in many commercial and utility scale plants.
The MLX system consists of the MLX inverter itself, a DC
string combiner and the Inverter Manager.
The communication network of an MLX system is divided
into 2 Ethernet networks; Plant network and inverter
network. The plant network is the communication interface
to the MLX plant and may be shared by several Inverter
Managers as well as other IT equipment, while the inverter
network is solely used for MLX inverters. The plant network
must have a DHCP server (router) as the Inverter Manager
requires automatic IP assignment. It is recommended to
use professional grade routers and switches. The Inverter
Manager provides:
Control of up to 42 MLX inverters
•
Single point of access for each (up to) 2.5 MVA
•
plant for simple plant network deployment
Easy commissioning and service of the plant
•
using the Local Commissioning and Service (LCS)
tool
Safe upload to data warehouse services, and
•
control of all local requirements and settings
from the DNO
Open source Modbus TCP communication
•
protocol using SunSpec Alliance profile via
Ethernet both for monitoring and control, making
it easy to integrate in e.g. SCADA systems
Grid management interface through the optional
•
I/O box for PLA and reactive power commands
Easy integration of meteorological data using an
•
RS-485 SunSpec Alliance compliant weather
station
6L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
2
1PV strings
2DC combiner
3MLX inverter
4MLX Inverter Manager
5Router
6LCS tool
7Portal
8SCADA system
9Weather station
10I/O box
11Grid management
12Transformer station
Illustration 2.4 System Overview
L00410648-02_02 / Rev. date: 2014-10-037
2
Inverter Overview
Illustration 2.5 Overview of Installation Area
PELV (Safe to touch)
2Equipment grounding
7Ethernet interface x 2
8RS-485 interface (not in use)
Live Part
1AC connection terminals
5PV connection terminals
Other
3Surge Protection AC
4Surge Protection DC
6PV load switch (optional)
2.3.2 Functional Safety
The inverter is designed for international use, with
functional safety circuit design meeting a wide range of
international requirements (see 2.5 Grid Code).
Single-fault Immunity
The functional safety circuit has a fully redundant built-in
single-fault detection. If a fault occurs, the inverter
disconnects from the grid immediately. The method is
active and covers all circuitry within the residual current
monitoring, both for continuous levels and sudden
changes. All functional safety circuits are tested during
start-up to ensure safe operation. If a circuit fails more
than 1 out of 3 times during the self-test, the inverter
enters fail safe mode. If the measured grid voltages, grid
frequencies, or residual current during normal operation
differ too much between the 2 independent circuits, the
inverter ceases to energise the grid and repeats the selftest. The functional safety circuits are always activated and
cannot be disabled.
Isolation
During the self-test, the inverter has an isolation measuring
system that detects whether the isolation in the PV system
is above the required level. This is done before the inverter
8L00410648-02_02 / Rev. date: 2014-10-03
Inverter Overview
2
starts to energise the grid. During grid connection, the
inverter measures the continuous leakage current in the
system. If this level is exceeded more than 4 times during
24 hours, the inverter stops operating due to safety
hazards in the PV system.
NOTICE
Depending on the local legislation, a minimum earth-toPV isolation resistance is defined. A typical value is
82 kΩ.
Self-test
The insulation resistance between the PV arrays and earth
is also tested during the self-test. The inverter does not
energise the grid if the resistance is too low. It then waits
10 minutes before making a new attempt to energise the
grid.
Residual current
Residual current is continuously monitored. The inverter
ceases to energise the grid when:
The cycle RMS value of the residual current
•
violates the trip settings for more than the
duration of ‘clearance time’, or
A sudden jump in the residual current is detected
•
Grid Surveillance
Grid-related parameters are under constant surveillance
when the inverter energises the grid. The following is
monitored:
Grid voltage magnitude (instantaneous and 10
•
minute average)
Grid voltage and frequency
•
Loss of Mains (Islanding detection):
•
3-phase Loss of Mains (LoM) detection
•
Rate of Change of Frequency (ROCOF)
•
Frequency shift.
•
DC content of grid current
•
Residual current by means of RCMU
•
The inverter ceases to energise the grid if one of the
parameters violates the grid code.
StatusLEDs
Green
Off grid
Connecting
On grid
Internal inverter event
Fail safe
Table 2.1
Off grid (standby) (LEDs off)
#0-51.
When no power has been delivered to the AC grid for
more than 10 minutes, the inverter disconnects from the
grid and shuts down. User and communication interfaces
remain powered for communication purposes.
Connecting (Green LED flashing)
#52-53.
The inverter starts up when the PV input voltage reaches
the minimum DC feed-in voltage. The inverter performs a
series of internal self-tests, including measurement of the
resistance between the PV arrays and earth. Meanwhile, it
also monitors the grid parameters. When the grid
parameters have been within the specifications for the
required amount of time (depends on grid code), the
inverter starts to energise the grid.
On grid (Green LED on)
#60.
The inverter is connected to the grid and energises the
grid. The inverter disconnects when:
it detects abnormal grid conditions (dependent
•
on grid code), or
an internal event occurs, or
•
PV power is insufficient (no power is supplied to
•
the grid for 10 minutes)
The inverter then enters connecting mode or off grid
mode.
- - - - - - - - - - - - - - - - -
Red
- - - - - - - - - - - - - - - - -
Green
▬██▬██▬██▬██▬██▬
Red
- - - - - - - - - - - - - - - - -
Green
Red
Green
Red
Green
Red
██████████████████
▬
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
- - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - -
▬██▬██▬██▬██▬██▬
▬
2
2.3.3 Operation Modes
The inverter has 5 operation modes, indicated by LEDs.
L00410648-02_02 / Rev. date: 2014-10-039
Internal Inverter Event (Green LED flashing)
#54
The inverter is waiting for an internal condition to become
within limits (for example a too high temperature) before
it will go back on grid.
Fail Safe (Red LED flashing)
#70.
If the inverter detects an error in its circuits during the selftest (in connecting mode) or during operation, the inverter
goes into fail safe mode, disconnecting from grid. The
Loading...
+ 23 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.