Siemens Mammomat Novation Installation Protocol

Welsing
MAMMOMAT Novation
Installation Protocol
System
SP
Service provider Installation Protocol
08380490
Print No.: Replaces: SPB7-250.813.03.01.02
SPB7-250.813.03.02.02
© Siemens AG
The reproduction, transmission or use of this document or its contents is not permitted without express written authority. Offenders will be liable for damages. All rights, including rights created by patent grant or registration of a utility model or design, are reserved.
English Doc. Gen. Date: 08.04
2004

2 Revision / Disclaimer

1Revision / Disclaimer
Document revision level
The document corresponds to the version/revision level effective at the time of system delivery. Revisions to hardcopy documentation are not automatically distributed.
Please contact your local Siemens office to order current revision levels.
Disclaimer
The installation and service of equipment described herein is to be performed by qualified personnel who are employed by Siemens or one of its affiliates or who are otherwise authorized by Siemens or one of its affiliates to provide such services.
Assemblers and other persons who are not employed by or otherwise directly affiliated with or authorized by Siemens or one of its affiliates are directed to contact one of the local offices of Siemens or one of its affiliates before attempting installation or service pro­cedures.
MAMMOMAT Novation SPB7-250.813.03.02.02 Siemens AG
08.04 CS SD 24
Page 2 of 12
Medical Solutions
Table of Contents 3
1- 0Table of Contents
1 _______ Scope of services _______________________________________________ 4
Delivery, installation, cabling and start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Room preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Delivery . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
System cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Other work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2 _______ Installation Protocol _____________________________________________ 6
Site data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Installation steps performed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Activity report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
General remarks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3 _______ Changes to previous version _____________________________________ 11
Siemens AG SPB7-250.813.03.02.02 MAMMOMAT Novation Medical Solutions
08.04 CS SD 24
Page 3 of 12

4 Scope of services

1Scope of services
2-

Delivery, installation, cabling and start-up 0

Room preparation 0

The following topics must be clarified with the project manager before the delivery date:
Building inspection by the service provider
Floor loading
Floor condition
Barriers, crane, tools.
The project manager must be on site for information on arrival of the service provider.
The orientation point is marked by the project manager.
The current project plan is handed over to the service provider on site.
Line voltage is available at the on-site system distributor.
The system emergency off is installed by the customer.
Cable ducts etc. must be installed.
All room preparations by the customer are completed and the room is swept clean.
Radiation protection partition is available.
To be able to install the covers, the system must be started up partially. This requires a
Siemens service engineer who connects and switches on the voltage to the MAMMO­MAT Novation
DR
.
Seal the joints of the unit base with silicone.
NOTE
All work must be performed in accordance with the supplied doc­uments.

Delivery 0

A long elevating truck is required for transporting the unit carrier on the pallet.
The system is brought into the room.
Unpacking and bringing in all system components of the unit.
Inspecting the components for damage.

Installation 0

Taking along all required tools, measuring and installation aids according to the tool list.
Positioning and aligning all system components according to the project plan or the
statements of the PM.
Installing accessories and options.
MAMMOMAT Novation SPB7-250.813.03.02.02 Siemens AG