Hobart HL800 User Manual

INSTALLATION & SET-UP
HL800 MIXER
Procedures and Scope of work for installing an HL800 Mixer.
The HL800 Mixer is included in the Retail Installation Credit (WRN Claim) program.
SCOPE OF WORK GUIDE
SCOPE OF WORK
KROGER/GENERAL CONTRACTOR RESPONSIBILITIES:
Receive, Uncrate and Set in Place the HL800 Mixer Provide Electrical Outlet Under normal circumstances the mixer should not need to be anchored to the floor.
However, anchoring can keep mixer from ‘walking” under extreme conditions such as uneven or slippery floors. Contact the local Hobart office for instructions.
DAMAGED SHIPMENTS OR SHORTAGES
Any shortages and/or visible damage must be marked on the freight bill at the time of delivery. If damages are found, the local office of the carrier must be notified at once and an inspection requested. Also, notify Hobart Customer Service. If the delivery receipt is signed clear and concealed damage is found, the carrier must be notified and inspection requested within 15 days of delivery.
Hobart Corporation will take care of filing carrier claims for lost or damaged shipments. The local Hobart office can ascertain if the unit can be repaired in the field or at their location. Should replacement of unit(s) or parts be necessary, contact your Hobart representative or the Customer Service Department.
INSTALLING HOBART OFFICE RESPONSIBILITY:
Assemble and Install All Accessories Start Up Unit and Test Operation Customer Demo/Training*
o Demonstrate Controls, Cleaning and Maintenance Procedures to Tortilleria Personnel
* For details, refer to the Instruction Manual or Operator Training Video, available at www.Hobartcorp.com\Kroger