fadini BARRI 88 Instruction Manual

1 - 12GB Instructions manual pages
Oil-hydraulic road barrier for 4 meters gateways
• Left- and right-handed versions
• Folding or fixed pedestal options
• Adjustable slowdown in opening and closing
• option with articulated arm
EN 13241 EN 12453 EN 12445
the gate opener
BARRI 88
GENERAL WARNINGS FOR PEOPLE SAFETY INTRODUCTION
This operator is designed for the specic scope of applications as indicated in this manual, it includes safety, control and signaling accessories as minimum required and FADINI equipment. Any applications not explicitly included in this manual may cause operation problems or damages to properties and people. Meccanica Fadini snc is not liable for damages caused by the incorrect use of the equipment, or for
English
applications not included in this manual or for malfunctioning resulting from the use of materials or accessories not recommended by the manufacturer. The manufacturer reserves the right to make changes to its products without prior notice. All that is not explicitly indicated in this manual is to be considered not allowed.
BEFORE INSTALLATION
Before commencing operator installation assess the suitability of the access, its general condition and the structure. Make sure that there is no risk of impact, crushing, shearing, conveying, cutting, entangling and lifting situations, which may prejudice people safety. □ Do not install near any source of heat and avoid contacts with ammable substances. Keep all the accessories able to turn on the operator (transmitters, proximity readers, key-switches, etc) out of the reach of the children. Transit through the access only with stationary operator. Do not allow children and/or people to stand in the proximity of a working operator. To ensure safety in the whole movement area of a gate it is advisable to install photocells, sensitive edges, magnetic loops and detectors. Use yellow-black strips or proper signals to identify dangerous spots. Before cleaning and maintenance operations, disconnect the appliance from the mains by switching o the master switch. If removing the actuator, do not cut the electric wires, but disconnect them from the terminal box by loosening the screws inside the junction box. in the near proximity or inside the installation accessories there aren’t any electromagnetic sources of disturbance, such that they can cover or aect the magnetic/electromagnetic detections of possible loop detectors as well as of all of the electronic units that command and control the system.
Oil-hydraulic road barrier with beam of 4 meters
Make sure that
During the rotation of the beam there must not be obstacles
or points of contact that interfere with the movement.
In case where the gate to automate is equipped with a
pedestrian entrance, it is appropriate to prepare the system in such a way to prohibit the operation of the engine when the pedestrian entrance is used. Apply safety nameplates with CE marking on the gate warning about the presence of an automated installation. The installer must inform and instruct the end user about the proper use of the system by releasing him a technical dossier, including: layout and components of the installation, risk analysis, test of safety accessories, test of impact forces and report of residual risks.
INFORMATION FOR END-USERS
The end-user is required to read carefully and to receive information concerning only the operation of the installation so that he becomes himself responsible for the correct use of it. The end-user shall establish a written maintenance contract with the installer/maintenance technician (on -call). Any maintenance operation must be done by qualied technicians. Keep these instructions carefully.
WARNINGS FOR THE CORRECT OPERATION OF THE INSTALLATION
To achieve a long lasting performance of system in compliance with the safety regulations, it is necessary that proper maintenance and monitoring of the entire installation be performed: including the automation, the electronic equipment and the cables connected to these. The entire installation must be carried out by qualied technical personnel, lling in the Maintenance Manual indicated in the Safety Regulation Book (to be requested or downloaded from the site www.fadini.net/supporto/downloads). Operator: maintenance inspection at least every 6 months, while for the electronic equipment and safety systems an inspection at least once every month is required. The manufacturer, Meccanica Fadini snc, is not responsible for non-observance of good installation practice and incorrect maintenance of the installation.
INSTALLATION
All installation operations must be performed by a qualied technician, in observance of the Machinery Directive 2006/42/CE and safety regulations EN 12453 - EN 12445. Verify the presence of a thermal-magnetic 0,03 A - 230 V - 50 Hz circuit breaker where the main electric source of power of the installation is located. Use appropriate objects to test the correct functionality of the safety accessories, such as photocells, sensitive edges, etc. Carry out a risk analysis by means of appropriate instruments measuring the crushing and impact force of the main opening and closing edge in compliance with EN 12445. Identify the appropriate solution necessary to eliminate and reduce such risks.
CE DECLARATION OF CONFORMITY of the manufacturer:
Meccanica Fadini snc (Via Mantova, 177/A - 37053 Cerea - VR - Italy) declares under own responsibility that: Barri 88 complies with the 2006/42/CE Machinery Directive, and also that it is sold to be installed in an “automatic system”, along with original accessories and components as indicated by the manufacturing company. An automatic gate operator is, by law, a “machinery” and therefore the installer must t the equipment with all of the applicable safety norms. The installer is also required to issue the installer’s Declaration of Conformity. The manufacturer is not liable for possible incorrect use of the product. The product complies with the following specic norms: analysis of the risks and subsequent action to cure them as per EN 12445 and EN 12453, Low Voltage Directive 2014/35/UE, Electromagnetic Compatibility 2014/30/UE. In order to certify the product, the manufacturer declares under own responsibility the compliance with the EN 13241-1 PRODUCT NORMS.
DISPOSAL OF MATERIALS
Dispose properly of the packaging materials such as cardboard, nylon, polystyrene etc. through specializing companies (after verication of the regulations in force at the place of installation in the eld of waste disposal). Disposal of electrical and electronic materials: remove and dispose through specializing companies, as per Directive 2012/19/UE. Disposal of substances hazardous for the environment is prohibited.
Meccanica Fadini s.n.c.
Director in charge
BARRI 88
Oil-hydraulic road barrier with beam of 4 meters
MAIN ACCESSORIES FOR THE INSTALLATION OF THE BARRIER
13
12
11
1
English
2
3
14
1. Miri 4 flasher with Birio A8 aerial (optional)
2. Braking adjustment
3. Oil-hydraulic actuator
4. Main assembly motor/pump/actuator
5. Pressure control valves
6. Balance spring
7. Anchoring base plate with hook bolts
8. Emergency release
9. Elpro 88 control board
10. Control board support arm
11. Beam limit switch assembly with adjustment screws
12. 80x30 L = 4 m beam
13. Folding pedestal
14. Fixed pedestal (optional)
IDENTIFYING BARRI 88 INTO RIGHT- OR LEFT-HANDED
10
4
9
5
6
8
7
Pic. 1
Barri 88
Left - Sx
Barri 88
Right - Dx
Entry side Entry side
Pic. 3Pic. 2
BARRI 88
SETTING THE ANCHORING BASE PLATE INTO THE GROUND FOUNDATION
The rst operation is xing the anchoring base plate on a at level into a concrete foundation; it is advised that, during this phase, one or two corrugated tubes, 30 mm of diameter, be laid in the foundation allowing for the electric cables to be driven through (electric power supply to the installation, command and safety accessories), as illustrated in Pic. 4.
Oil-hydraulic road barrier with beam of 4 meters
English
245 mm
~ 400 mm
245 mm
~ 400 mm
Ø 30Ø 30
65 mm
Two x M14 hook bolts
5 mm
0.0
Road level
~ 500 mm
Important: before cementing the anchoring base plate, drive the 2 bolts thoroughly out, to the end of the thread. Important: by means of a spirit level make sure the anchoring base plate be perfectly at in both directions; it is
!
also recommended that it be 5 mm higher than the road nish level (Pic. 4).
FITTING THE BEAM
1)
Pic. 4
3)
2)
Pic. 5