Xantrex Technology Inc. is a world-leading supplier of advanced power electronics and controls with products from
50 watt mobile units to 1.5 MW utility-scale systems for wind, solar, batteries, fuel cells, microturbines, and backup
power applications in both grid-connected and stand-alone systems. Xantrex products include inverters, battery
chargers, programmable power supplies, and variable speed drives that convert, supply, control, clean, and distribute
electrical power.
Trademarks
PV225S 225 kW Grid-Tied Photovoltaic Inverter is a trademark of Xantrex International. Xantrex is a registered
trademark of Xantrex International.
Other trademarks, registered trademarks, and product names are the property of their respective owners and are used
herein for identification purposes only.
UNLESS SPECIFICALLY AGREED TO IN WRITING, XANTREX TECHNOLOGY INC. (“XANTREX”)
(a) MAKES NO WARRANTY AS TO THE ACCURACY, SUFFICIENCY OR SUITABILITY OF ANY
TECHNICAL OR OTHER INFORMATION PROVIDED IN ITS MANUALS OR OTHER DOCUMENTATION.
(b) ASSUMES NO RESPONSIBILITY OR LIABILITY FOR LOSS OR DAMAGE, WHETHER DIRECT,
INDIRECT, CONSEQUENTIAL OR INCIDENTAL, WHICH MIGHT ARISE OUT OF THE USE OF SUCH
INFORMATION. THE USE OF ANY SUCH INFORMATION WILL BE ENTIRELY AT THE USER’S RISK.
Date and Revision
April 2005 Revision A
Part Number
152606 Rev A
Contact Information
Telephone:1 800 670 0707 (toll free North America)
1 360 925 5097 (direct)
Fax:1 800 994 7828 (toll free North America)
1 360 925 5143 (direct)
Email:customerservice@xantrex.com
Web:www.xantrex.com
About This Manual
Purpose
The purpose of this Planning and Installation Manual is to provide explanations
and procedures for planning and installing the PV225S 225 kW Grid-Tied
Photovoltaic Inverter.
Scope
The Manual provides safety guidelines, detailed planning and setup information,
and procedures for installing the inverter.
Audience
The Manual is intended for use by anyone who plans to construct or install a
system involving the PV225S 225 kW Grid-Tied Photovoltaic Inverter. Installers
must meet all local and state code requirements for licensing and training for the
installation of Electrical Power Systems with AC and DC voltage to 600 volts.
Organization
This Manual is organized into four chapters:
Chapter 1, “Introduction” provides information about the features and functions
of the PV225S 225 kW Grid-Tied Photovoltaic Inverter.
Chapter 2, “Planning” provides information to help plan the installation of the
PV225S 225 kW Grid-Tied Photovoltaic Inverter.
Chapter 3, “Installation” describes the procedures needed to install the PV225S
225 kW Grid-Tied Photovoltaic Inverter. This section includes unpacking and
moving instructions, mounting instructions, and cabling instructions.
Chapter 4, “Verification” provides a checklist to ensure the installation of the
PV225S is correct and complete.
152606 Rev Aiii
About This Manual
Conventions Used
The following conventions are used in this guide.
WARNING
Warnings identify conditions or practices that could result in personal injury or loss of life.
CAUTION
Cautions identify conditions or practices that could result in damage to the unit or other
equipment.
Important:
serious as a caution or warning.
These notes describe things which are important for you to know, but not as
Abbreviations and Acronyms
ANSIAmerican National Standards Institute
CCU2Converter Control Unit 2
CFMCubic Feet per Minute
CWClockwise
DSPDigital Signal Processor
FPGAField Programmable Gate Array
GUIGraphical User Interface
IEEEInstitute of Electrical and Electronics Engineers
IGBTInsulated Gate Bipolar Transistor
IPMIntelligent Power Module
kcmil1000 circular mils
LANLocal Area Network
LCDLiquid Crystal Display
NFPANational Fire Protection Association
PBXPrivate Branch Exchange
PSLPhase-Shift Loop
POTSPlain Old Telephone Service
PVPhotovoltaic
UFCUUniversal Frontpanel Control Unit
Related Information
You can find more information about Xantrex Technology Inc. as well as its
products and services at www.xantrex.com.
iv152606 Rev A
Important Safety Instructions
SAVE THESE INSTRUCTIONS - DO NOT DISCARD
This manual contains important safety instructions for the PV225S that shall be
followed during installation and maintenance procedures.
WARNING: Shock Hazard
Read and keep this Planning and Installation Manual for future reference. Before
installing the PV225S, read all instructions, cautionary markings, and all other appropriate
sections of this manual. Failure to adhere to these warnings could result in severe shock or
possible death. Exercise extreme caution at all times to prevent accidents.
WARNING: Shock Hazard
The PV225S enclosures contain exposed high-voltage conductors. The enclosure doors
should remain closed with the latches tightened, except during installation, maintenance
or testing. These servicing instructions are for use by qualified personnel who meet all
local and state code requirements for licensing and training for the installation of
Electrical Power Systems with AC and DC voltage to 600 volts. To reduce the risk of
electric shock, do not perform any servicing other than that specified in the installation
instructions unless you are qualified to do so. Do not open the cabinet doors if extreme
moisture is present (rain or heavy dew).
WARNING: Lethal Voltage
In order to remove all sources of voltage from the PV225S, the incoming power must be
de-energized at the source. This may be done at the main utility circuit breaker and by
opening the AC Disconnect and the DC Disconnect Switches on the PV225S. Review the
system configuration to determine all of the possible sources of energy. In addition, allow
5 minutes for the DC bus capacitors, located on the ceiling of the cabinet, to discharge
after removing power.
152606 Rev Av
Safety
General Safety Precautions
1. When installing the PV225S use only components recommended or sold by
Xantrex. Doing otherwise may result in a risk of fire, electric shock, injury to
persons, and will void the warranty.
2. Do not attempt to operate the PV225S if it has been dropped, or received more
than cosmetic damage during transport or shipping. If the PV225S is
damaged, or suspected to be damaged, see the Warranty for this unit in the
PV225S 225 kW Grid-Tied Photovoltaic Inverter Operation and Maintenance
Manual.
3. To reduce the risk of electrical shock, lock-out and tag the PV225S before
attempting any maintenance, service, or cleaning.
Personal Safety
Follow these instructions to ensure your safety while working with the PV225S.
Safety Equipment
Authorized service personnel must be equipped with standard safety equipment
including the following:
•Safety glasses
•Ear protection
•Steel-toed safety boots
•Safety hard hats
•Padlocks and tags
•Appropriate meter to verify that the circuits are de-energized
(600 Vac and DC rated, minimum)
Check local safety regulations for other requirements.
Wiring Requirements
1. All wiring methods and materials shall be in accordance with the National
Electrical Code ANSI/NFPA 70. When sizing conductors and conduits
interfacing to the PV225S, both shall be in accordance with the National
Electric Code ANSI/NFPA 70, as well as all state and local code
requirements.
2. Use copper conductors only with insulation rated for 90 °C.
3. The PV225S has a three-phase output. It is marked with this symbol:
4. The AC power conductor wiring interfacing with the AC terminals in the
Transformer Enclosure are located at T6-X1, T6-X2, and T6-X3. These
terminals should be tightened to a torque value of 420 in-lbs (47.5 Nm).
Conductors terminated to these terminals must use a crimp-on type ring
vi152606 Rev A
Safety
terminal or compression-type lug. The terminals can accommodate up to two
conductors per phase. See Figure 3-14 on page 3–15 for the location of these terminals.
5. The AC power conductor wiring interfacing with the AC terminals in the
Main Inverter Enclosure are located at TB5, TB6, and TB7. These terminals
are to be tightened to a torque value of 375 in-lbs (42.4 Nm). The terminals
will accept a conductor size of 350 kcmil and can accommodate up to six
conductors per phase. See Figure 3-15 on page 3–16 for the location of these
terminals.
6. The AC power conductor wiring interfacing with the AC terminals in the
AC Interface Enclosure are located at S1-2T1, S1-4T2, and S1-6T3. These
terminals should be tightened to a torque value of 310 in-lbs (35.0 Nm). See
Figure 3-16 on page 3–16 for the location of these terminals.
7. The AC neutral conductor from the utility is terminated in the AC Interface
Enclosure at the TB11 terminal. This terminal requires the use of a crimp-on
type ring terminal or compression-type lug and should be tightened to a
torque value of 228 in-lbs (25.7 Nm).See Figure 3-18 on page 3–18 for the
location of these terminals.
8. The DC power conductor wiring interfacing with the DC terminals at S2-6,
K2-6T3, and TB4 are to be tightened to a torque value of 600 in-lbs
(67.8 Nm). These terminals will accept a conductor size of 600 kcmil and can
accommodate up to four conductors per pole at S2-6 and K2-6T3 and up to
two conductors at TB4. Keep these cables together as much as possible and
ensure that all cables pass through the same knockout and conduit fittings,
thus allowing any inductive currents to cancel. See Figure 3-19 on page 3–19
for the location of these terminals.
9. This product is intended to be installed as part of a permanently grounded
electrical system per the National Electric Code ANSI/NFPA 70. A copper
ground rod must be installed within three feet of the PV225S enclosure. This
is the single point earth ground for the inverter system. The single point
ground for the system is to be made at the AC ground bus bar (TB12) in the
AC Interface Enclosure. This terminal requires the use of a crimp-on type ring
terminal or compression-type lug and should be tightened to a torque value of
420 in-lb (47.5 Nm).
10. The equipment grounds on the PV225S are marked with this symbol:
11. AC overcurrent protection for the utility interconnect (Grid-tie) must be
provided by the installers as part of the PV225S installation.
CAUTION: Fire Hazard
In accordance with the National Electrical Code, ANSI/NFPA 70, connect only to a circuit
provided with 400 amperes maximum branch circuit overcurrent protection for the
PV225S-480.
152606 Rev Avii
Safety
Operational Safety Procedures
Never work alone when servicing this equipment. A team of two is required until
the equipment is properly de-energized, locked-out and tagged, and verified deenergized with a meter.
Thoroughly inspect the equipment prior to energizing. Verify that no tools or
equipment have inadvertently been left behind.
Lockout and Tag
Safety requirements mandate that this equipment not be serviced while energized.
Power sources for the PV225S must be locked-out and tagged prior to servicing.
A padlock and tag should be installed on each energy source prior to
servicing.
WARNING: Shock Hazard
Review the system schematic for the installation to verify that all available energy sources
are de-energized. DC bus voltage may also be present. Be sure to wait the full 5 minutes to
allow the capacitors to discharge completely.
The PV225S can be energized from both the AC source and the DC source. To
ensure that the inverter is de-energized prior to servicing, lockout and tag the
PV225S using the following procedure.
1. Open, lockout, and tag the incoming power at the utility main circuit breaker.
2. Open, lockout, and tag the AC Disconnect Switch (S1) on the AC Interface
Enclosure. See Figure 1-4 on page 1–9 for the location of the AC Disconnect
Switch.
3. Open, lockout, and tag the DC Disconnect Switch (S2) on the DC Interface
Enclosure. See Figure 1-4 on page 1–9 for the location of the DC Disconnect
Switch.
4. Using a confirmed, accurate meter, verify all power to the inverter is deenergized. A confirmed, accurate meter must be verified on a known voltage
before use. Ensure that all incoming energy sources are de-energized by
checking the following locations.
a) Inverter Terminals: TB5, TB6, TB7 (Phase A, B, C)
See Figure 3-15 on page 3–16.
b) Utility Terminals: Bottom of S1-2T1, S1-4T2, S1-6T3
See Figure 3-16 on page 3–16.
c) PV Terminals: Bottom of S2-6, K2-6T3, TB4 (PV+, PV-, GND)
See Figure 3-19 on page 3–19.
viii152606 Rev A
De-Energize/Isolation Procedure
The following procedure should be followed to de-energize the PV225S for
maintenance.
WARNING
The terminals of the DC input may be energized if the PV arrays are energized. In
addition, allow 5 minutes for all capacitors within the main enclosure to discharge after
disconnecting the PV225S from AC and DC sources.
To isolate the PV225S:
Safety
1. Turn the O
2. Open the DC Disconnect Switch.
3. Open the AC Disconnect Switch.
4. Open the utility connection circuit breaker.
5. Install lockout devices on the utility connection circuit breaker and DC
Disconnect Switch.
N/OFF switch to the OFF position.
Interconnection Standards Compliance
The PV225S has been tested and listed by Underwriters Laboratories to be in
compliance with UL1741 Static Inverters And Charge Controllers For Use In
Photovoltaic Power Systems, as well as IEEE-929-2000 Recommended Practice
For Utility Interface of Photovoltaic (PV) Systems.
IEEE-929-2000 provides guidance regarding equipment and functions necessary
to ensure compatible operation of photovoltaic systems which are connected in
parallel with the electric utility.
UL1741 is the standard applied by Underwriters Laboratory to the PV225S to
verify it meets the recommendations of IEEE-929-2000.
Refer to both documents for details of these recommendations and test
procedures.
Table 1-1Electrical Specifications 1–4
Table 1-2Over/Under Voltage and Over/Under Frequency Ranges 1–4
Table 1-3Environmental Specifications 1–6
Table 3-1AC Terminal Wire Gauge, Bolt Size, and Torque Values 3–12
Table 3-2DC Terminal Wire Gauge, Bolt Size, and Torque Values 3–12
152606 Rev Axv
xvi
1
Introduction
Chapter 1, “Introduction” provides information about the features and
functions of the PV225S 225 kW Grid-Tied Photovoltaic Inverter.
Introduction
Description of the PV225S
The PV225S 225 kW Grid-Tied Photovoltaic Inverter is a UL 1741 Listed, utility
interactive, three-phase power conversion system for grid-connected photovoltaic
arrays with a power rating of 225 kW. Designed to be easy to install and operate,
the PV225S automates start-up, shutdown, and fault detection scenarios. With
user-definable power tracking that matches the inverter to the array and adjustable
delay periods, users are able to customize start up and shut down sequences.
Multiple PV225S inverters are easily paralleled for larger power installations.
The PV225S power conversion system consists of a pulse-width modulated
(PWM) inverter, switch gear for isolation and protection of the connected AC and
DC power sources, and a custom Wye/Wye isolation transformer. Housed in a
rugged NEMA-3R rated, powder-coated steel enclosure, the PV225S incorporates
sophisticated Intellimod
the main power switching devices. An advanced, field-proven, Maximum Peak
Power Tracker (MPPT) integrated within the PV225S control firmware ensures
the optimum power throughput for harvesting energy from the photovoltaic array.
The advanced design of the PV225S includes an EMI output filter and the main
AC contactor located electrically on the utility side of the isolation transformer.
The location of the main AC contactor, and the ability to de-energize the isolation
transformer during times of non-operation, greatly reduces the night-time tare
losses consumed by an idle isolation transformer. An integrated soft-start circuit
precludes nuisance utility-tie circuit breaker trips as the result of isolation
transformer inrush current.
(IPM) Insulated Gate Bipolar Transistors (IGBTs) as
Additionally, the PV225S integrated controller contains self-protection features
including over and under voltage and frequency safeguards. An integral
anti-island protection scheme prevents the inverter from feeding power to the grid
in the event of a utility outage. The PV225S includes a local user interface
comprised of an O
user-friendly, Graphic User Interface (GUI) provides a remote interface for
operator interrogation of PV225S system status, control, metering/data logging
and protective functions within the PV225S. The status, control, and logging
features are also supported by the data modem (included) and can be accessed
remotely.
The PV225S comes in two modules comprised of six enclosures to house the
electronics described above. The first module includes the Main Inverter
Enclosure, Inductor Enclosure, DC Interface Enclosure, and Communications
Enclosure. The second module includes the Transformer Enclosure and AC
Interface Enclosure. These components are identified in Figure 1-1 on page 1–3.
Figure 1-1 also shows the dimensions and locations of the various enclosures that
comprise the PV225S.
See “Layout Options” on page 2–6 for information on configuration options.
N/OFF switch, keypad, and 4-line, 80 character LCD display. A
1–2152606 Rev A
Front View
AC
Interface
Enclosure
Communications
Enclosure
Transformer
Enclosure
Main
Inverter
Enclosure
Inductor
Enclosure
Description of the PV225S
DC Interface
Enclosure
Back
Figure 1-1
Front
AC Interface
Enclosure
AC Side View
Dimensions (Not to scale)
Communications
Enclosure
Front
DC Interface
Enclosure
Back
Inductor
Enclosure
DC Side View
152606 Rev A1–3
Introduction
System Specifications
The PV225S has been designed for photovoltaic power systems, which operate
within the following specifications.
CAUTION: Equipment Damage
Operation of the PV225S in a manner other than specified in this manual may cause
damage to the PV225S and other system components and will void the terms of the
warranty.
Electrical Specifications
Table 1-1 provides the AC and DC specifications for the PV225S.
Table 1-1
SpecificationPV225S-480
Nominal AC Input Voltage
(+10% to -12% acceptable range)
Maximum AC Output Current271 A
Nominal AC Input Frequency
(+0.5 to -0.7 Hz acceptable range)
Output Power225 kW
Peak Power Tracking Window330 to 600 Vdc
Maximum Open Circuit Voltage600 Vdc
Maximum DC Input Current710 amps
Electrical Specifications
Over Voltage, Under Voltage and Frequency Ranges
Table 1-2 provides the over voltage, under voltage, over-frequency, and
under-frequency detection limits for the PV225S. These detection limits have
been factory tested and deemed to be in compliance with IEEE-292 and UL 1741
requirements for utility interaction.
Table 1-2
Vac Condition
(% of Nominal)
Vac < 50%Vac < 2406 cycles
50% <
88% < Vac <
110% < Vac < 137%528 < Vac < 6572 seconds
137% <
f < rated -0.7f < 59.36 cycles
f > rated +0.5f > 60.56 cycles
Over/Under Voltage and Over/Under Frequency Ranges
Voltage RangeTrip Time
Va c < 88%240 < Vac < 4222 seconds
110%422 < Vac < 528normal operation
Vac657 < Vac2 cycles
480 Vac
(422 to 528 Vac)
rms
60 Hz
(59.3 to 60.5 Hz)
PV225S-480
1–4152606 Rev A
System Ground Requirements
This product is intended to be installed as part of a permanently grounded
electrical system per the National Electric Code ANSI/NFPA 70. A copper ground
rod must be installed within three feet of the PV225S enclosures and connected to
the unit as described in “System Grounding” on page 3–12. The single-point
ground for the system is to be made at the AC ground bus bar (TB12) in the AC
Interface Enclosure.
System Neutral Requirements
The PV225S is designed to be installed as a 4-wire system. As required by the
UL 1741 listing, a neutral conductor from the utility-interconnect must be
terminated at TB11 within the AC Interface Enclosure to ensure that the AC
voltage sensing circuit can perform an individual phase voltage (line-to-neutral)
measurement. The function of the neutral connection is to provide a point of
reference for measurement purposes that is essentially at ground potential. No
power will flow through the neutral conductor.
Utility Side Isolation Transformer Requirements
The PV225S is supplied with a custom, high-efficiency, isolation transformer as
part of the AC Interface/Transformer assembly. The utility side windings of the
isolation transformer are configured Wye and must match the voltage at the utility
inter-tie. The PV225S is a balanced, three-phase, current-sourcing inverter and
only operates with the presence of a stable utility voltage. The transformer is also
supplied with a neutral connection on the utility interconnect. Connection of this
utility-side neutral does not affect the operation of the inverter, however
connection of the neutral on the inverter-side does affect the operation and must
be left floating or disconnected. Single-phase, grounded loads which may be
present between the transformer and utility, will maintain their existing ground
reference at the utility distribution transformer.
System Specifications
CAUTION: Equipment Damage
If the Isolation Transformer (T6-X0) neutral terminal is tied to ground, it will cause
irreparable damage to the PV225S. Check local regulations for their requirements
regarding the connection of the neutral.
WARNING: Lethal Voltage
Grounding the neutral of a Wye-wound transformer may create an “open delta” condition,
depending on the utility configuration. This condition may keep the PV225S from
detecting a loss of phase condition on the utility system, which may allow potentially
lethal voltage to be present on the open-phase wiring.
152606 Rev A1–5
Introduction
Environmental Specifications
The following environmental specifications are the same for both models of the
PV225S 225 kW Grid-Tied Photovoltaic Inverter.
Table 1-3
SpecificationValue
Environmental Specifications
Dimensions
Inverter and DC Interface
88.5 in H x 80 in W x 32 in D
(225 cm H x 203 cm W x 81 cm)
Transformer and AC Interface
49.5 in H x 61.5 in W x 35.5 in D
(126 cm H x 156 cm W x 90 cm D)
Overall System Footprint:
Layout Option A
14 ft W x 5 ft L (approximate)
(4.3 m x 1.5 m)
Layout Option B
10 ft W x 9 ft L (approximate)
(3 m W x 2.7 m L)
Weig ht
Inverter and DC Interface
Transformer and AC Interface
Overall Weight
15 ft (4.5 m)
Inverter Enclosure and AC
Interface/Transformer Enclosure
1–6152606 Rev A
Operator Interface Controls
Operator interface controls are located on the front door of the main inverter
enclosure. These controls include an O
keypad called the Universal Frontpanel Control Unit (UFCU). Additionally there
is an AC and DC Disconnect on the AC Interface Enclosure and the DC Interface
Enclosure Doors.
Communication
Enclosure
Operator Interface Controls
N/OFF Switch, 4-line LCD display and
DC Disconnect
Switch (S2)
AC
Disconnect
Switch (S1)
Figure 1-2
AC Interface Enclosure
(AC Side View)
PV225S Operator Interface Components
LCD
Display
Universal
Frontpanel
Control
(UFCP)
ON/OFF
Switch
(S3)
Main Enclosure Door Interlock Switch
The front door of the PV225Smain enclosure is equipped with an interlock switch
to preclude operation while the front door is open. Opening the door of the main
inverter enclosure will initiate an immediate controlled shutdown of the PV225S
and opens both the main AC and DC contactors. The main AC and DC contactors
cannot be closed unless the door’s interlock is in the engaged position. The
PV225S is prevented from being restarted until the door is again closed and the
switch is in the engaged position.
DC Interface
Enclosure
Main Inverter Enclosure
(Front View)
It is required that the PV225Smain enclosure door must be locked during normal
operation. The door interlock switch does NOT remove all hazardous voltages
from inside the inverter. Before attempting to service the PV225S, follow the
de-energize Lockout and Tag procedure on
152606 Rev A1–7
page viii.
Introduction
On/Off Switch
WARNING: Shock Hazard
Disengaging the main enclosure door interlock switch does NOT remove all hazardous
voltages from inside the inverter. Before attempting to service the PV225S, follow the
de-energize Lockout and Tag procedure on page viii.
The PV225Sincorporates a maintained position ON/OFF switch (S3) located on
the front door of the main enclosure. Under normal conditions, the O
is in the O
N position. Turning the switch to the OFF position will initiate an
N/OFFswitch
immediate controlled shutdown of the PV225Sand opens both the main AC and
DC contactors within the unit. The main AC and DC contactors cannot be closed
unless the switch is in the
restarted until the O
ON position. The PV225Sis prevented from being
N/OFFswitch is turned back to the ONposition.
WARNING: Shock Hazard
Turning the ON/OFF switch to the OFF position does NOT remove all hazardous voltages
from inside the inverter. Before attempting to service the PV225S, follow the de-energize
Lockout and Tag procedure on page viii.
Figure 1-3
ON/OFF Switch
(S3)
On/Off Switch (S3)
1–8152606 Rev A
AC and DC Disconnect Switches
Both AC and DC Interface Enclosures are equipped with lockout hasps for
personnel safety. The enclosure doors should not be opened while the PV225Sis
operating.
The switch handles and shafts provide a door interlock for both the AC and DC
Interface Enclosures. The doors cannot be opened when the switch is in the
position.
The DC Disconnect Switch (S2) is equipped with an auxiliary contact block
which enables the switch to be used as a load break DC disconnect. In the event
the DC Disconnect Switch is opened while the PV225Sis processing power from
the PV array, the early-break contact block will signal the CCU2 (Converter
Control Unit 2) to stop processing power prior to the opening DC Disconnect
Switch.
Additionally, opening the DC Disconnect Switch will cause the PV225S to
execute an immediate orderly shutdown, open both the main AC and DC
contactors, and report a PV disconnect fault on the LCD of the UFCU.
Communication Features
ON
DC Disconnect
Switch (S2)
AC Disconnect
Switch (S1)
AC Interface Enclosure
Figure 1-4
AC and DC Disconnect Switches (S1 and S2)
DC Interface Enclosure
Communication Features
The PV225S provides two types of information to the user:
•system status and/or fault information, and
•data logging information.
System status and fault information can be accessed using the Universal Front
Panel Control Unit (UFCU) or a personal computer using the Xantrex Solar
Graphic User Interface (GUI) software. Data logging requires the use of a PC
using the GUI software.
152606 Rev A1–9
Introduction
System Status and Fault Reporting
Basic system status and all fault conditions rising from within the PV225Sare
reported to the UFCU. The unit stores the time and details of all faults in
non-volatile memory. The 4-line LCD will display a hexadecimal value and a
brief text description of the fault.
This information can also be accessed using a personal computer using the GUI
software either directly or remotely.
Types of status information include:
•Current Operating State or Goal State
•Fault Code (if applicable)
•Inverter State
•Line Voltage and Current
•Inverter Matrix Temperature
•Inverter Power
•PV State
•PV Voltage and Current
•PV Power
•Grid Frequency
•Peak Power Tracker Enabled
Data Logging
The inverter stores data values and software metrics for debugging. These values
are stored within the CCU2 controller board in non-volatile memory. Data logging
requires the use of a PC connection using the Xantrex Solar Graphic User
Interface (GUI) software.
•The Data Logging features include:
•Operational Values
•Internal Metrics
•Data Log Acquisition
•Graphic Data Analysis
•Fault Log Acquisition
•Software Upgrade
•Accumulated Values
•Configurable Parameters
1–10152606 Rev A
Communication Methods
The PV225S communicates system status information to the user using the
following methods.
•The Front Panel Control Unit (UFCU) Display
•PC Connection (Direct or Remote) - Xantrex Solar Graphic User Interface
(GUI) Software required. Communication with a PC requires the selection of
one of the following options.
•Remote Connection -- This method has three options available. One of
these options will be field-installed prior to commissioning.
•POTS Connection
•Wireless Connection
•Ethernet LAN Connection
•Direct Connection -- This method is most commonly used by field
technicians for local connection and troubleshooting purposes.
Communication Methods
Important:
to support a PC connection. (i.e., making arrangements for an analog phone line, wireless
service or local area network.)
The customer is responsible for providing the appropriate support service
Universal Front Panel Control Unit (UFCU)
The UFCU keypad is located on the front of the Main Inverter Enclosure to
manipulate and view system operation and status.
The keypad is comprised of 20 touch-sensitive keys that provide a means to
navigate through the menus and alter user-changeable settings.
Communications Enclosure
LCD
Display
Universal Front Panel
Control Unit (UFCU)
Figure 1-5
LCD Display and UFCU Location
See the PV225S 225 kW Grid-Tied Photovoltaic Inverter Operation and
Maintenance Manual for details.
152606 Rev A1–11
Introduction
PC Connection Methods
Personal computers can be used to access the system status and programming
features of the PV225S. A computer can be connected either directly or remotely.
1. Remote Connect - uses one of the three kits below.
•POTS Kit - uses a MultiTech® 56K Modem, RS232/Fiber Optic
•Wireless Kit - uses a GSM Wireless Modem.
•Ethernet LAN Kit - uses a data communication device to enable the unit
2. Direct Connect - This method is used for troubleshooting. It uses a
RS232/Fiber Optic Converter (configured for a PC), a DB25-to-DB25 gender
changer, and a DB25-to-DB9 Serial Cable.
Software is included to provide a graphic user interface that relates important
system information. This software is called Xantrex Solar Graphic Interface
(GUI). See"Computer Communications with the PV225S" in the PV225S 225
kW Grid-Tied Photovoltaic Inverter Operation and Maintenance Manual for
additional information.
The GUI can dial up the inverter and receive fault report calls from it through a
standard Hayes-compatible, landline modem. When the GUI initiates a call
through the modem at the GUI computer, the inverter’s modem answers the call
and initiates a 9600 baud serial connection, effectively as if the GUI was
connected directly. Or, if the inverter experiences a fault, it will initiate a call to
the GUI and report the fault details.
Converter (configured for ethernet) and SA2 Surge Arrestor.
to connect to a local area network.
Communications
Enclosure
RS232/FO
Converter
MultiTech®
56K Modem
SA2 Surge
Arrestor
Figure 1-6
1–12152606 Rev A
PC Connections in the Communications Enclosure
POTS connection option shown.
POTS Access
Communication Methods
Figure 1-7 illustrates the PV225S connected remotely to a personal computer.
Figure 1-7
POTS Access
Wireless Access
Figure 1-8
Wireless Access
Figure 1-8 illustrates the PV225S connected directly to a personal computer using
a wireless network.
152606 Rev A1–13
Introduction
Ethernet LAN Access
The PV225S can be remotely accessed through a local area network.
Figure 1-9
Ethernet LAN Access
Direct Access
Figure 1-10
Figure 1-10 illustrates the PV225S connected directly to a personal computer.
Direct Access
1–14152606 Rev A
2
Planning
Chapter 2, “Planning” provides information to help plan the installation of
the PV225S 225 kW Grid-Tied Photovoltaic Inverter.
Planning
Overview of PV225S Installation
WARNING: Shock Hazard
Installations of this equipment should only be performed by qualified technicians.
Installers must meet all local and state code requirements for licensing and
training for the installation of Electrical Power Systems with AC and DC voltage
to 600 volts.
PlanningPlanning for a system requires complete understanding of all the components that
are involved to successfully install the PV225S to meet the required national,
state, and local codes.
DefinitionA power system (such as the PV225S) is a collection of devices designed to
supply AC power to the utility grid from a solar energy (PV) source.
ComponentsAll types of grid-tied inverter installations, residential or industrial, share common
components. This chapter describes each component and suggests the minimum
requirements for a safe installation.
LocationThe PV225S 225 kW Grid-Tied Photovoltaic Inverter is designed to be installed
in either an indoor or outdoor location. The PV225S must be anchored to a level,
concrete floor or pad.
Ideally the AC Interface Enclosure/Transformer Assembly is placed on the left
side of the Main Inverter Enclosure. The AC Interface Enclosure/Transformer
Assembly may be co-located adjacent to the left side of the Main Inverter
Enclosure up to, but not exceeding, 15 feet away.
ClearanceAdequate ventilation and service access must be taken into consideration when
installing the PV225S. See “Ventilation and Serviceability Requirements” on
page 2–3 for specific clearance requirements and ambient temperature
requirements.
Conduits and
Conductors
Given the flexibility to co-locate the AC Interface Enclosure/Transformer
Assembly to fit a desired system layout, the conduits and conductors are to be
supplied by the installer.
See “Conduit Penetration” on page 2–8 for recommendations on enclosure
penetration locations and conduit routing.
See “Conductor and Conduit Sizing” on page 2–11 for information on sizing the
conductors and conduits.
All interconnect wiring and power conductors interfacing to the PV225S must be
in accordance with the National Electric Code ANSI/NFPA 70 and any applicable
local codes.
2–2152606 Rev A
Large gauge wire must conform to the minimum bend radius specified in the
NEC, Article 373-6B, Ninth Edition.
Take care to keep the wire bundles away from any sharp edges which may damage
wire insulation over time.
All conductors should be made of copper and rated for 90 °C (minimum).
If the installation of the PV225S is to be outdoors, all interconnect conduit and
fittings must be NEMA-4 rated as required by the NEC.
PV Planning
To determine the number of photovoltaic panels that are required for the PV
power plant, please use the PV planning tool from the Xantrex website:
The following environmental conditions must be established and maintained to
ensure the safe and efficient operation and servicing of the PV225S. Adequate
space must be provided around the unit for ventilation and access during
servicing. If locating the unit indoors, ambient air temperature cannot exceed the
maximum temperature for which the unit is rated.
PV Planning
VentilationMaintain a minimum clearance of 12 inches on both sides and 6 inches behind the
Main Inverter Enclosure and the AC Interface Enclosure for proper cooling fan
operation.
Maintenance and
Serviceability
Indoor Temperature
Control
Maintain a minimum clearance of 36 inches in front of the Main Inverter access
door, the Transformer Enclosure access panel, and the AC Interface access door
for maintenance and serviceability.
See Figure 2-1 on page 2–6 and Figure 2-2 on page 2–7 for illustrations of these
clearance requirements.
If the PV225S is to be installed indoors and external air is used for ventilation, the
required cubic feet per minute (CFM) rate must be no less than 1000 CFM. This
assumes the temperature inside the building is allowed to rise only 10 °C above
the outside temperature. Therefore, the maximum allowable outside ambient
temperature is 50 °C (50 °C minus 10 °C equals 40 °C Maximum Ambient
Temperature).
If air conditioning is planned for an indoor installation, the heat load of the
PV225S is 42,000 BTU/Hour at full load.
152606 Rev A2–3
Planning
Ground Requirements
This product is intended to be installed as part of a permanently grounded
electrical system per National Electric Code ANSI/NFPA 70. A copper ground
rod must be installed within three feet of the PV225S enclosure. This is the single
point earth ground for the inverter system. The single point ground for the system
is to be made at the AC ground bus bar (TB12) in the AC Interface Enclosure.
System Neutral Requirements
The PV225S is designed to be installed as a 4-wire system. As required by the
UL 1741 listing, a neutral conductor from the utility-interconnect must be
terminated at TB11 within the AC Interface Enclosure to ensure that the
AC voltage sensing circuit can perform an individual phase voltage (line-toneutral) measurement. The function of the neutral connection is to provide a point
of reference for measurement purposes that is essentially at ground potential. No
power will flow through the neutral conductor.
Communication Requirements
The PV225S can accommodate any one of the following options for PC
Communication:
•POTS Connect Kit - uses a MultiTech® 56K Modem, RS232/Fiber Optic
Converter (configured for ethernet) and SA2 Surge Arrestor. A direct analog
phone line to the local phone service is required to use this feature. The phone
line used for PV225S communication cannot be routed through a Private
Branch Exchange (PBX) unless an analog PBX card is used.
•Wireless Connect - uses a GSM Wireless Modem.
•Ethernet LAN Connect - uses a data communication device to enable the
unit to connect to a local area network.
•Direct Connect Kit - uses a RS232/Fiber Optic Converter (configured for a
PC), a DB25-to-DB25 gender changer, and a DB25-to-DB9 Serial Cable.
Determine which communications options are required for the installation and
procure the appropriate service or phone access. The personal computer to be used
with this unit must have the appropriate hardware as well, such as a 56K modem
for dial up connection or a Network Interface Card (NIC) for a LAN connection.
2–4152606 Rev A
Utility Side Isolation Transformer Requirements
Utility Side Isolation Transformer Requirements
The PV225S is supplied with a custom, high-efficiency, isolation transformer as
part of the AC Interface/Transformer assembly. The utility side windings of the
isolation transformer are configured Wye and must match the voltage at the utility
inter-tie. The PV225S is a balanced, three-phase, current-sourcing inverter and
only operates with the presence of a stable utility voltage. The transformer is also
supplied with a neutral connection on the utility interconnect. Connection of this
utility-side neutral does not affect the operation of the inverter, however
connection of the neutral on the inverter-side does affect the operation and must
be left floating or disconnected. Single-phase, grounded loads which may be
present between the transformer and utility, will maintain their existing ground
reference at the utility distribution transformer.
CAUTION: Equipment Damage
If the Isolation Transformer (T6-X0) neutral terminal is tied to ground, it will cause
irreparable damage to the PV225S. Check local regulations for their requirements
regarding the connection of these neutrals.
WARNING: Lethal Voltage
Grounding the neutral of a Wye-wound transformer may create an “open delta” condition,
depending on the utility configuration. This condition may keep the PV225S from
detecting a loss of phase condition on the utility system, which may allow potentially
lethal voltage to be present on the open-phase wiring.
Electrical Diagrams and Schematics
Since installations vary widely, a sample electrical diagram of the PV225S is
provided in Figure A-1 on page A–3. This diagram is to be used for system
planning purposes only.
For more detailed information, refer to the schematic illustrations.
•Figure A-2, “PV225S-480 Schematic for Main Power Distribution
(152291 B1)” on page A–4
•Figure A-3, “PV225S-480 Schematic for Control Power Distribution
(152291 B2)” on page A–5
•Figure A-4, “PV225S-480 Schematic for Converter Control
Unit (152291 B3)” on page A–6
152606 Rev A2–5
Planning
Layout Options
The PV225S is shipped as two separate assemblies and can be arranged as shown
in Figure 2-1 or Figure 2-2.
The PV225S can be arranged in a number of different system layout options to fit
specific site requirements. The AC Interface/Transformer assembly may be colocated adjacent to the left side of (or behind) the Main Inverter Enclosure up to,
and not exceeding, 15 feet away.
Given the flexibility to co-locate the AC Interface/Transformer assembly to fit a
desired system layout, the interconnect AC power conductors and conduit
between the Main Inverter Enclosure and the AC interface/transformer assembly
are to be supplied by the installer. See Figure 2-1 and Figure 2-2, depicting two
options for locating the AC interface/transformer assembly adjacent to the main
inverter.
Minimum Dimension of Base:
Approximately 14 ft. by 5 ft. (4.3 m x 1.5 m)
Figure 2-1
2–6152606 Rev A
PV225S Layout Option A
Minimum Dimension of Base:
Approximately 10 ft by 9 ft (3 m x 2.7 m)
Layout Options
Figure 2-2
152606 Rev A2–7
PV225S Layout Option B
Planning
Conduit Penetration
The following illustrations show the recommended locations for electrical conduit
entry into the PV225S enclosures. These drawings are to be used for system
planning purposes, such that the shaded areas are representative of the maximum
allowable area and location in which electrical conduit may penetrate the
enclosures of the PV225S, see Figure 2-3 through Figure 2-8. Xantrex
recommends a standard trade-size conduit knock-out set for cutting/punching the
PV225S enclosures and panels for conduit entry.
AC Interface
Enclosure
AC side view
of PV225S
E
Transformer
Enclosure
B
A
AC Interface
Enclosure
C
Main Inverter
Enclosure
Inductor
Enclosure
Front view of PV225S
Figure 2-4 on page 2–9
A
B
Figure 2-5 on page 2–9
C
Figure 2-6 on page 2–10
Figure 2-7 on page 2–10
D
E
Figure 2-8 on page 2–10
DC Interface
Enclosure
D
Figure 2-3
Conduit Entry Figure Reference
2–8152606 Rev A
Conduit Penetration
5 ½" (15 cm)
1 ½" (4 cm)
18" (46 cm)
6" (15 cm)
Figure 2-4
Inductor Enclosure Conduit Entry, Left Side
1 ½" (4 cm)
5 ½" (15 cm)
18" (46 cm)
6" (15 cm)
Figure 2-5
152606 Rev A2–9
Transformer Enclosure Conduit Entry, Right Side
Planning
Backside of
Transformer
Enclosure
(partial view)
8"
(20 cm)
AC Disconnect Switch (S1)
10" (25 cm)
1" (2.5 cm)
12" (30 cm)
5" (13 cm)
Figure 2-6
Figure 2-7
AC Interface Enclosure Conduit Entry, Left Side
DC Interface Enclosure, Bottom Side
3" (8 cm)
1" (2.5 cm)
18"
(45 cm)
2" (5 cm)
10" (25 cm)
4" (10 cm)
10.5" (27 cm)
1" (2.5 cm)
Figure 2-8
2–10152606 Rev A
Communications Enclosure Conduit Entry, Bottom Side
Conductor and Conduit Sizing
All wiring methods and materials shall be in accordance with the National
Electrical Code ANSI/NFPA 70. When sizing conductors and conduits interfacing
to the PV225S, both shall be in accordance with the National Electric Code ANSI/
NFPA 70, as well as all state and local code requirements.
Large gauge wire must conform to the minimum bend radius dependent upon the
wire gauge(refer to the National Electric Code, Article 373-6B (Ninth Edition).
CAUTION: Equipment Damage
Be careful to keep the wire bundles away from any sharp edges which may damage wire
insulation over time.
The following provides information on sizing the conductors and conduits for the
system.
To calculate the proper conduit size:
1. Determine the required cable ampacity.
2. Determine the conduit length between the inverter and the transformer.
Conductor and Conduit Sizing
3. Determine the proper size for the cable according to the allowable ampacities
indicated by NEC Table 310.16 (Ninth Edition).
4. Determine the proper size for the conduit.
The following is an example of the steps outlined above. Assumptions were made
in this example which may not match your application, and the resulting design
may not comply with all code requirements. Consult a licensed electrician on
recommendations for specific installations.
Step 1. Determine the required cable ampacity.
AC Phase Cables from Inverter to Transformer:
225 kW / 208 Vac / 1.732 = 624.5 A
624.5 x 125% = 780.69 A (required ampacity)
Step 2. Determine the conduit length between inverter and transformer.
•If the conduit length between the inverter and the transformer is less than
24 inches, then the cable can be sized using the NEC Table 310.16
(in raceway) (Ninth Edition).
•If the conduit length is greater than 24 inches, then the cable must be sized
using NEC Table 310.16 (in Raceway) (Ninth Edition) and by using the
adjustment factors in NEC Table 310-15(b)(2)(a).
(full load current)
rms
152606 Rev A2–11
Planning
Step 3. Size the cable.
This example assumes that the conduit length is less than 24 inches. NEC
Table 310.16 (Ninth Edition) indicates the Temperature Correction Factor for
90 °C THHN cable in a 50 °C ambient is 0.82. With a required ampacity from
Step 1 above of 780.6 amps, it can be calculated that the required cable ampacity
at 50 °C in this application is 952 amps. (780.6 divided by 0.82)
In this example, four cables per phase termination are used, so from NEC Table
310.17 (Ninth Edition) it is apparent that the 90 °C THHN cable must be
262 kcmil or larger. Four each 262 kcmil conductors at 50°C have an allowable
ampacity of 984 amps (246 multiplied by 4).
Step 4. Size the conduit.
In this step, the cross sectional area of all the individual cables is first calculated.
Once calculated, the total cross sectional area of the cables is determined by
summing their values. In this example, 262 kcmil DLO, 2000 V cable is selected
for the AC Phase connections:
DLO 262 Phase Cable:
262 MCM DLO, 2000V, 90 °C per Phase
262 MCM has an O.D. of 0.973
0.973 x 0.973 x 12 x 0.7854 = 8.923 in²
Ground Cable:
1 Each #2 AWG (per NEC Table 250.122 (Ninth Edition),
using 400 A Breaker)
#2 AWG has an O.D. of 0.384 for THHN and 0.565 for DLO
2 runs of conduit between the Isolation Transformer (T6-X1, T6-X2, and T6X3) and the Main Inverter Enclosure (TB5, TB6, and TB7)
1st conduit run; 4.46 + 0.25 = 4.71 in²
2nd conduit run; 4.46 + 0.058 = 4.52 in²
2–12152606 Rev A
Using the "Over 2 Wires" column per NEC Chapter 9, Table 4, (Ninth Edition)
indicates that the following minimum permitted conduit trade size is acceptable
for the 21 wires in this exercise:
EMT = 3 ½" Trade size
IMC = 4" Trade size
RMC = 4" Trade size
Anchoring the PV225S
The PV225S is designed to be installed in either an indoor or outdoor location. It
must be placed on and anchored to a level concrete floor or pad. The concrete
floor or pad, upon which the PV225S is anchored, must be structurally designed to
meet any local, state, or national requirements for weight, seismic, and wind sheer
if applicable.
Four 5/8" holes are provided in the feet of the main inverter, and six 5/8" holes are
provided in the feet of the AC interface/transformer assembly for anchoring to the
floor or pad.
Figure 2-9 and Figure 2-10 depict the layout patterns of the anchoring holes for
both the PV225S main inverter and the AC interface/transformer assembly.
Anchoring the PV225S
23 ¼"
(59 cm)
Figure 2-9
(43 1/8”)
(110 cm)
Main Inverter Anchor Bolt Pattern (Not to scale)
5/8"
(1.5 cm)
(x4)
152606 Rev A2–13
Planning
(30”)
(76 cm)
17 ¼"
(43 cm)
(38”)
(97 cm)
¾" (1.9 cm)
(x6)
Figure 2-10
AC Interface/Transformer Anchor Bolt Pattern (Not to Scale)
The floor or pad should either be pre-drilled to accept masonry anchors or have
pre-installed anchoring bolts.
2–14152606 Rev A
3
Installation
Chapter 3, “Installation” describes the procedures needed to install
the PV225S 225 kW Grid-Tied Photovoltaic Inverter. This section
includes unpacking and moving instructions, mounting instructions,
and cabling instructions.
Installation
Equipment Required
The following is a list of required tools and equipment to aid in the installation of
the PV225S. This list is not a comprehensive list, but is intended to help identify
the minimum recommended tools and equipment used during the installation.
•Forklift (26" minimum fork span) and/or pallet jack
•Claw hammer or pry bar
•Standard and metric socket set
•Standard and metric wrench set
•Standard Allen
•Large slip-joint pliers
•Standard and Phillips screwdrivers
•Torque wrench with 0 - 600 in-lbs minimum range
•Appropriate voltage meter (600 Vac and DC rated, minimum)
•Phase rotation meter (600 Vac rated, minimum)
•Hammer drill and masonry bits
•Trade-size conduit knock-out set
®
Hex wrenches (5/16, 3/8, and 1/2)
Unloading
The PV225S is shipped partially assembled in two separate shipping crates and
one cardboard box.
❐ One crate is the main inverter and is marked "1-152287-01".
❐ The other crate is the AC Interface Enclosure and transformer assembly and is
marked "1-152448-01".
❐ The cardboard box contains one of the three remote connection kits:
•POTS Connection 1-152674-01,
•Wireless Connection 1-152659-01, or
•Ethernet Connection 1-152658-01.
WARNING: Heavy Equipment
The main inverter weighs approximately 2300 lbs. The AC Interface Enclosure and
transformer assembly weigh approximately 2350 lbs. Attempting to lift the equipment by
other than the recommended lifting points may damage the equipment or present a
personnel safety hazard and void the warranty. Keep all the doors closed and latched when
moving the enclosures. Leaving the door latches unsecured may result in damage to the
unit and void the warranty.
3–2152606 Rev A
Moving the PV225S
c
Unloading
CAUTION: Equipment Damage
To move the PV225S, use a forklift that has a sufficient lift capacity and has a 26" fork
span.
To move the PV225S while it is still inside the shipping crates:
1. Place the forks of the forklift below the shipping crate at the points specified
on the shipping crate.
2. Lift the main inverter and the AC Interface Enclosure and Transformer
Enclosure from beneath their shipping crates.
Figure 3-1
Moving the crated PV225S
Unpacking the PV225S
To unpack the main inverter and the AC Interface Enclosure and
transformer assembly from their shipping crates:
1. Using a claw hammer or pry bar, remove the crate’s wood top and side panels.
2. Remove the main inverter’s anchor hardware that attaches it to the shipping
pallet.
3. Remove the AC Interface Enclosure and transformer assembly anchor
hardware that attaches them to their shipping pallet.
152606 Rev A3–3
Installation
Removing the Pallet and Moving the PV225S
CAUTION: Equipment Damage
c
To move the PV225S, use a forklift that has a sufficient lift capacity and a26" fork span.
To move the PV225S using a forklift:
1. Place the forks of the forklift below the unit at the points specified in
Figure 3-2.
2. Lift the PV225S from beneath the respective enclosures.
Be sure to use a forklift with a 26" fork span.
3. Remove the pallet from beneath the unit.
4. Once the pallets are removed from the units, use the same lifting locations to
lift the units into the place where they are to be permanently located.
Lift Here
26" (66 cm)
fork span
Figure 3-2
3–4152606 Rev A
Forklift Lifting Locations - Underneath Unit
Lift Here
26" (66 cm)
fork span
Mounting and Anchoring the Units
Important:
of the components, conduit penetration locations, conductor and conduit sizing, and
method for anchoring the unit. Ensure adequate space is provided for clearance for
ventilation and serviceability. Review Chapter 2, “Planning” if necessary before
proceeding.
Before proceeding with the installation, determine the location and layout
Mounting and Anchoring the Units
To mount and anchor the PV225S:
1. Predrill the floor or pad to accept 1/2" diameter masonry anchors or ensure it
has pre-installed anchoring bolts that will fit the 5/8" mounting holes.
2. Lift the main inverter from beneath the lower enclosure with a forklift or
pallet jack as shown in Figure 3-2 on page 3–4. Move the Main Inverter
Enclosure into place.
3. Lift the AC Interface/Transformer assembly from beneath the enclosure with
a forklift or pallet jack as shown in Figure 3-2 on page 3–4. Move the AC
interface/transformer assembly into place.
4. Secure the Main Inverter Enclosure feet to the floor with a 1/2" diameter
anchor bolts.
5. Secure the AC Interface/Transformer assembly enclosure feet to the floor
with 1/2" diameter anchor bolts.
Mounting Holes for
securing and anchoring
the units.
Figure 3-3
152606 Rev A3–5
Mounting Hole Locations
Installation
Opening or Closing Access Doors
To lock or unlock the front door on the main inverter:
1. Use the 7 mm triangle key provided with the unit.
a) Insert the key in each lock and turn counterclockwise to open;
clockwise to lock.
b) Pull front door open from the right side.
Main Inverter Front Door Locks
Main Inverter Front Door Lock
Figure 3-4
3–6152606 Rev A
Inverter Enclosure Access Doors
Door Latches
Opening or Closing Access Doors
To Open Access Door:
1. Confirm that the AC Disconnect Switch
handle is placed in the OFF (Open)
position prior to opening the door.
2. Loosen the bolts on door latches and
slide away from the door.
3. Pull open from right side.
To Close Access Door:
1. Confirm that the AC Disconnect Switch
handle is placed in the OFF (Open)
position prior to closing the door.
2. Close the door and slide the latches
back over the edge of the door.
3. Tighten the bolts on door latches.
Figure 3-5
AC Interface Access Door
To Open Access Door:
1. Confirm that the DC Disconnect Switch
handle is placed in the OFF (Open)
position prior to opening the door.
2. Loosen the bolts on door latches and
slide away from the door.
3. Pull open from the left side.
To Close Access Door:
1. Confirm that the DC Disconnect Switch
handle is placed in the OFF (Open)
position prior to closing the door.
2. Close the door and slide the latches
back over the edge of the door.
3. Tighten the bolts on door latches.
Door Latches
Figure 3-6
152606 Rev A3–7
DC Interface Access Door
Installation
Transformer Access Panel
To Remove the Access Panel:
Loosen and remove the 1/4"
self-tapping sheet metal screws
(x9).
To Replace the Access Panel:
Replace and tighten the 1/4"
self-tapping sheet metal screws.
Figure 3-7
Transformer Access Panels
Main Inverter Front Door
Inductor Access Panel
To Remove the Access Panel:
Use a Phillips screwdriver to loosen
and remove the 1/4-20 Phillips
round-head bolts (x12).
To Replace the Access Panel:
Replace and tighten the 1/4-20
Phillips round-head bolts to 78 in-lb
(8.6 nm).
Figure 3-8
Inductor Access Panels
3–8152606 Rev A
Conduit Installation
Given the flexible nature of the system, conduit installation will be dependent
upon the final configuration of the system. Procurement and installation of the
conduit, therefore, is the responsibility of the installer. Since the layout will be
dependent upon the location available for the installation and the size of the
conductors used, specific conduit size and type must be pre-determined by the
installer before the actual installation. See “Conductor and Conduit Sizing” on
page 2–11 for instructions on how to determine the size of the conductors and
conduits to be used. Once the size of the conductors and conduits has been
determined, follow the instructions below for installing the conduits. Be sure to
consult the NEC Handbook and any local codes to ensure code compliance.
Conduit Installation
Important:
PV225S be NEMA-4 rated.
To install the conduits:
1. Determine the conduit penetration locations in the Main Inverter Enclosure
and the AC interface/transformer assembly. See Figure 2-3 on page 2–8
through Figure 2-5 on page 2–9.
2. Install appropriately sized conduit based upon system layout and required
codes between the main inverter and the AC interface/transformer assembly.
For ease of conduit installation, the access panels on both the main inverter
and the AC interface/transformer assembly can be removed.
3. Determine all remaining conduit penetration locations in the AC Interface
enclosure, DC Interface Enclosure, and Communication Enclosure. See
Figure 2-3 on page 2–8 through Figure 2-8 on page 2–10.
4. Install all remaining appropriately sized conduit interfacing for the AC
Interface Enclosure, DC Interface Enclosure, and Communication Enclosure
based upon system layout and required codes.
Outdoor installations require that all conduit fittings interfacing with the
Conduit
Figure 3-9
152606 Rev A3–9
Conduit Installation
Installation
Wiring - General
All wiring methods and materials shall be in accordance with the National
Electrical Code ANSI/NFPA 70. When sizing conductors and conduits interfacing
to the PV225S, both shall be in accordance with the National Electric Code
ANSI/NFPA 70, as well as all state and local code requirements.
WARNING: Shock Hazard
The PV225S enclosures contain exposed high-voltage conductors. The enclosure doors
should remain closed with the latches tightened, except during installation, maintenance
or testing. These servicing instructions are for use by qualified personnel who meet all
local and state code requirements for licensing and training for the installation of
Electrical Power Systems with AC and DC voltage to 600 volts. To reduce the risk of
electric shock, do not perform any servicing other than that specified in the installation
instructions unless you are qualified to do so. Do not open the cabinet doors if extreme
moisture is present (rain or heavy dew).
WARNING: Lethal Voltage
In order to remove all sources of voltage from the PV225S, the incoming power must be
de-energized at the source. This may be done at the main utility circuit breaker and by
opening the AC Disconnect and the DC Disconnect Switches on the PV225S. Review the
system configuration to determine all of the possible sources of energy. In addition, allow
5 minutes for the DC bus capacitors, located on the ceiling of the cabinet, to discharge
after removing power.
CAUTION: Equipment Damage
When connecting external AC wires to the PV225S, positive phasing sequence must be
maintained throughout the installation process. Refer to the system schematics in
Appendix A of this manual for proper phasing convention.
Important:
damage wire insulation over time. Consult the NEC ANSI/NFPA 70 Code Book to ensure
code compliance.
The model PV225S has a three-phase output. It is marked with this symbol:
Conductor size should have been pre-determined when the conduit was installed.
Prepare the appropriate length conductors for each connection.
3–10152606 Rev A
Take care to keep the wire bundles away from any sharp edges which may
Overcurrent Protection
AC overcurrent protection for the Utility Interconnect (Grid-tie) must be provided
by the installer as part of the PV225S installation.
CAUTION: Equipment Damage
In accordance with the NEC, ANSI/NFPA 70 (Ninth Edition) a 400 A maximum
branch-circuit overcurrent protection must be provided.
Conductor Termination
The PV225S has terminals and bus bars for making all wiring connections
required for the installation. All terminals used for making AC and DC
connections require the use of copper conductors with an insulation rating of
90 °C (or higher). For wire gauge, bolt size, and torque values for the AC
terminals, see Table 3-1. For wire gauge, bolt size, and torque values for the
DC terminals, see Table 3-2.
Wiring - General
Transformer
Enclosure
Main Inverter
Enclosure
AC Interface
Enclosure
DC Interface
Enclosure
The AC terminals in the Transformer Enclosure (T6-X1, T6-X2, and T6-X3)
require the use of crimp-on type ring terminals or compression-type lugs. The
terminals can accommodate up to two conductors per phase.
See Figure 3-14 on page 3–15 for the location of these terminals.
The AC terminals in the Main Inverter Enclosure (TB5, TB6, and TB7) have six
openings per phase. These terminals do not require the use of ring terminals or
compression lugs.
See Figure 3-15 on page 3–16 for the location of these terminals.
The AC line terminals in the AC Interface Enclosure (S1-2T1, S1-4T2, and
S1-6T3) are one bolt per phase. These terminals require the use of crimp-on type
ring-terminals or compression-type lugs.
See Figure 3-16 on page 3–16 for the location of these terminals.
The AC neutral terminal in the AC Interface Enclosure (TB11) has one bolt per
pole and requires the use of crimp-on type ring terminals or compression-type
lugs.
See Figure 3-18 on page 3–18 for the location of this terminal.
The DC terminals in the DC Interface Enclosure (S2-6, K2-6T3, and TB4) can
accommodate up to four conductors per pole at S2-6 and K2-6T3, and up to two
conductors at TB4. These terminals do not require the use of ring-terminals or
compression lugs.
See Figure 3-19 on page 3–19 for the location of these terminals.
Important:
pass through the same knockout and conduit fittings, thus allowing any inductive currents
to cancel.
152606 Rev A3–11
Keep these cables together as much as possible, and ensure that all cables
Installation
Wire Gauge and Torque Requirements
Table 3-1 provides acceptable wire gauges, bolt sizes, and torque values for AC
terminal connections.
Table 3-1
AC Terminal
Connections
TB1
(Chassis Ground)
TB12
(System Ground)
TB11 (Neutral)500MCM to #4 AWG (1 stud per pole)3/8-16228 in-lb (25.7 Nm)
S1-2T1, S1-4T2,
S1-6T3
T6-X1, T6-X2,
T6-X3
TB5, TB6, TB7350MCM to #4 AWG (6 openings per phase)3/8 Hex375 in-lb (42.4 Nm)
AC Terminal Wire Gauge, Bolt Size, and Torque Values
Acceptable Wire Size Range
(both models)
500MCM to #4 AWG (1 stud per pole)3/8-16420 in-lb (47.5 Nm)
500MCM to #4 AWG (1 stud per pole)3/8-16420 in-lb (47.5 Nm)
350MCM to #6 AWG (1 stud per phase)M10310 in-lb (35.0 Nm)
350MCM to #6 AWG (2 studs per phase)3/8-16420 in-lb (47.5 Nm)
Bolt (Hardware)
Size
Torque
Requirements
Table 3-2 provides acceptable wire gauges, bolt sizes, and torque values for DC
terminal connections.
Table 3-2
DC Terminal
Connections
S2-6, K2-6T3, TB4600MCM to #4 AWG (2 openings per pole)1/2 Hex600 in-lb (67.8 Nm)
DC Terminal Wire Gauge, Bolt Size, and Torque Values
Acceptable Wire Size Range
(both models)
Bolt (Hardware)
Size
Torque
Requirements
Grounding
System GroundingInstall a copper ground rod within three feet of the PV225S enclosures per the
National Electric Code ANSI/NFPA 70. The single-point ground for the system is
to be made at the AC ground bar (TB12) in the AC Interface Enclosure.
AC Ground Bar
(TB12) to be used
for the Single Point
Ground
AC Interface Enclosure
Figure 3-10
3–12152606 Rev A
Single-point Ground (TB12) Ground Bar
Wiring - General
Chassis GroundThe chassis ground is a copper bus bar in the Main Inverter Enclosure and has
3/8-16" bolts for terminating the AC ground. The ground conductor size depends
on the size of the main circuit breaker.
NEC Table 250.122 (Ninth Edition) requires that the ground conductor be at least
#3 AWG for a 400 A circuit breaker.
Torque connections to ground bar in the Main Inverter Enclosure to
420 in-lb (47.5 Nm).
The equipment ground on the PV225S is marked with this symbol:
Main Inverter Enclosure
Figure 3-11
Chassis Ground Bar (TB1)
DC Interface Enclosure
AC Ground Bar (TB1)
to be used for the
Chassis Ground
Array GroundingNEC Article 690-41/42 (Ninth Edition) requires the PV array to be earth
grounded.The PV225S chassis is also bonded to the PV safety ground terminal
block.
System Neutral Requirements
The PV225S is designed to be installed as a 4-wire system. As required by the
UL 1741 listing, a neutral conductor from the utility-interconnect must be
terminated at TB11 within the AC Interface Enclosure to ensure that the
AC voltage sensing circuit can perform an individual phase voltage
(line-to-neutral) measurement. The function of the neutral connection is to
provide a point of reference for measurement purposes that is essentially at
ground potential. No power will flow through the neutral conductor.
Utility Side Isolation Transformer Requirements
The PV225S is supplied with a custom, high-efficiency, isolation transformer as
part of the AC interface/transformer assembly. The utility side windings of the
isolation transformer are configured Wye and must match the voltage at the utility
inter-tie. The PV225S is a balanced, three-phase, current-sourcing inverter and
152606 Rev A3–13
Installation
only operates with the presence of a stable utility voltage. The transformer is also
supplied with a neutral connection on the utility interconnect. Connection of this
utility-side neutral does not affect the operation of the inverter, however
connection of the neutral on the inverter-side does affect the operation and must
be left floating or disconnected. Single-phase, grounded loads, which may be
present between the transformer and utility, will maintain their existing ground
reference at the utility distribution transformer.
CAUTION: Equipment Damage
If the Isolation Transformer (T6-X0) neutral terminal is tied to ground, it will cause
irreparable damage to the PV225S. Check local regulations for their requirements
regarding the connection of these neutrals.
WARNING: Lethal Voltage
Grounding the neutral of a Wye-wound transformer may create an “open delta” condition,
depending on the utility configuration. This condition may keep the PV225S from
detecting a loss of phase condition on the utility system, which may allow potentially
lethal voltage to be present on the open phase wiring.
Wiring - Specific
This section provides information for connecting the AC and DC conductors,
ground conductors, and AC Sense Harness.
AC Connections
To connect the main inverter to AC interface/transformer assembly:
1. Remove the access panels from the front of both the Main Inverter Enclosure
and the Transformer Enclosure. Additionally, open the front door to the Main
Inverter Enclosure.
2. Route the AC power conductors A, B, C phase cables and ground conductor
through the conduit between the main inverter to the AC interface/transformer
assembly (T6).
Route the AC cables from the Inverter
Enclosure through the conduits to the
Transformer Enclosure.
AC Sense Harness (partially
hidden below AC Cables)
Inductor Enclosure
Transformer Enclosure
Figure 3-12
3–14152606 Rev A
Route AC Cables through the Conduit
Wiring - Specific
3. In addition to the power conductors, route the AC Sense Harness assembly
(Xantrex P/N 1-152403-01) between the main inverter to the AC
interface/transformer assembly. Prior to completing the installation of the AC
Sense Harness, secure the harness to the AC power conductors with nylon
tie-wraps so it does not touch the surfaces of either the L1 or L2 inductor.
Failure to secure the AC Sense Harness away from these surfaces may cause
deformation of the harness insulation and possibly damage due to the
excessive heat generated by the L1 or L2 inductor
Prior to completing the installation
of the AC Sense Harness, secure
the harness to the AC power
conductors with nylon tie-wraps.
.
Figure 3-13
4. Connect the AC power conductors in the Transformer Enclosure at the T6-X1
AC Interface Enclosure
Tie-wraps on the AC Sense Harness
(A phase), T6-X2 (B phase), and T6-X3 (C phase) bus bars using
3/8-16" hardware. Connect the ground conductor in the AC
Interface/Transformer Enclosure at TB12. Cables to these terminals must use
a crimp-on type ring terminal or compression-type lug. Tighten these
connections to a torque value of 420 in-lb (47.5 Nm).
TB12 Ground Bar
Ground Cable
from Main
Inverter
Enclosure
T6-X3
T6-X2
T6-X1
Transformer Enclosure
Figure 3-14
152606 Rev A3–15
AC Terminal Connections in the AC Interface/Transformer Enclosure
Installation
5. Connect the AC power conductors in the Main Inverter Enclosure at TB5
(A phase), TB6 (B phase), and TB7 (C phase) with a box connector using a
3/8" Hex screw. This hardware should be tightened to a torque value of
375 in-lb (42.4 Nm). Connect the ground conductor to the TB1 terminal on
the ground bar on the right side of the enclosure. Torque this connection to
420 in-lb (47.5 Nm).
TB7
TB6
TB5
TB1
Figure 3-15
AC Interface Enclosure
AC Terminal Connections in the Main Inverter Enclosure
S1-2T1
(A phase)
S1-4T2
(B phase)
Enlargement of
Terminal Connectors
in the AC Interface
Enclosure
S1-6T3
(C phase)
Figure 3-16
AC Terminal Connections in the AC Interface Enclosure
3–16152606 Rev A
Wiring - Specific
6. The AC Sense Harness is pre-terminated within the AC interface/transformer
assembly and the opposite end is mated with its 9-pin plug to the
corresponding 9-pin jack within the Main Inverter Enclosure.
See Figure 3-17.
Figure 3-17
Connecting the AC Sense Harness
7. Replace the access panels on the front of both the main inverter Inductor
Enclosure and the Transformer Enclosure. Additionally, close the front door
to the Main Inverter Enclosure.
To connect the utility service to AC Interface Enclosure:
1. Remove the door clamps and open the door to the AC Interface Enclosure.
2. Route the AC power conductors A, B, C phase, neutral, and a neutral ground
cable through the conduit from the utility service to the AC Interface
Enclosure. See Figure 3-18 for the location of these terminals.
3. Connect the AC power conductors at the S1-2T1 (A phase), S1-4T2
(B phase), and S1-6T3 (C phase) terminals using the M10 hardware. Cables to
these terminals must use a crimp-on type ring terminal or compression-type
lug. Torque these connections to 310 in-lb (35.0 Nm). See Figure 3-18 for the location of these terminals.
4. Connect the neutral conductor at TB11. Connect the ground conductor at
TB12. Terminations for the neutral and ground conductors within the AC
Interface Enclosure at the TB11 and TB12 locations are made with 3/8-16"
hardware. Cables to these terminals must use a crimp-on type ring terminal or
compression-type lug. The terminal at TB11 should be tightened to a torque
value of 228 in-lb (25.7 Nm). The terminal TB12 should be tightened to a
torque value of 420 in-lb (47.5 Nm). See Figure 3-18 for the location of these
terminals.
5. Close the door to the AC Interface Enclosure and replace the door clamps.
152606 Rev A3–17
Installation
S1-2T1
(A Phase
terminal)
S1-4T2
(B Phase terminal)
TB11
Neutral
S1-6T3
(C Phase
terminal)
Ground TB12
Figure 3-18
AC Terminal Connections from the Utility
3–18152606 Rev A
PV Array Connections
To make the connections from the PV Array/combiner to DC Interface
enclosure:
1. Remove the door clamps and open the door to the DC Interface Enclosure.
2. Route the PV Array cables conductors POSitive (PV+), NEGative (PV-), and
3. The DC power conductor terminations are made at the S2-6 (POS/DC+), and
4. Terminations for the S2-6, K2-6T3, and TB4 terminals are made with box
5. Close the door to the DC Interface Enclosure and replace the door clamps.
Wiring - Specific
PV GND through the conduit to the DC Interface Enclosure, entering on the
underside.
K2-6T3 (NEG/DC-) and TB4 (PV Gnd) locations. See Figure 3-19.
connector using a 1/2" Hex Allen screw. The hardware should be tightened to
a torque value of 600 in-lbs (67.8 Nm).
PV POSitive (S2-6)
PV NEGative (K2-6T3)
PV GrouND (TB4)
Figure 3-19
152606 Rev A3–19
PV Array Cable Routing and Terminations
Installation
PC Communications
Personal computers can be used to access the system status and programming
features of the PV225S. A computer can be connected either directly or remotely.
1. Remote Connect - uses one of the three kits below.
•POTS Kit - uses a MultiTech® 56K Modem, RS232/Fiber Optic
•Wireless Kit - uses a GSM Wireless Modem to access wireless phone
•Ethernet LAN Kit - uses a data communication device to enable the unit
2. Direct Connect - This method is used for troubleshooting. It uses a
RS232/Fiber Optic Converter (configured for a PC), a DB25-to-DB25 gender
changer, and a DB25-to-DB9 Serial Cable.
Software is included to provide a graphic user interface that relates important
system information. This software is called Xantrex Solar Graphic Interface
(GUI). See "Computer Communications with the PV225S" in the PV225S 225
kW Grid-Tied Photovoltaic Inverter Operation and Maintenance Manual for
additional information.
The GUI can dial up the inverter and receive fault report calls from it through a
standard Hayes-compatible, landline modem. When the GUI initiates a call
through the modem at the GUI computer, the inverter’s modem answers the call
and initiates a 9600 baud serial connection, effectively as if the GUI was
connected directly. Or, if the inverter experiences a fault, it will initiate a call to
the GUI and report the fault details.
Converter (configured for ethernet) and SA2 Surge Arrestor and requires
access to a local analog phone line (Plain Old Telephone Service-POTS).
service.
to connect to a local area network.
PC Connection Methods
The personal computer can be connected to the PV225S the following ways.
Important:
Also ensure the personal computer to be used has the appropriate hardware to support the
installed feature, such as a phone line, wireless phone service, or local area network.
•POTS Connection
•Wireless Connection
•Ethernet LAN Connection
•Direct Connection
3–20152606 Rev A
Ensure the appropriate service has been established before proceeding.
Establishing a POTS Connection
PC Communications
Important:
feature. The phone line used for PV225S communication cannot be routed through a
Private Branch Exchange (PBX) unless an analog PBX card is used.
A direct analog phone line to the local phone service is required to use this
To connect a personal computer using the POTS Connection:
1. Ensure the personal computer to be used has a 56K modem installed.
2. Open the Communications Enclosure.
3. Plug the local phone line into the RJ11 port on the SA2 Surge Arrestor
marked "U
NPROTECTED".
SA2 Surge Arrestor
MultiTech 56K
Modem
Figure 3-20
Telephone Cable Routing
4. Install the GUI Software following the instructions in the PV225S 225 kW
Grid-Tied Photovoltaic Inverter Operation and Maintenance Manual.
5. Use a Terminal Emulation program on the PC to access the modem.
See the GUI Help Menu "Communication by Modem" for instructions on
setting up the Terminal Emulation program on the computer. See also,
"Connect to Telephone Number" and "Connect to Remote Inverter by
Modem" for additional information.
6. Use the GUI to setup the connection information.
a) From the GUI Main page, click on <T
OOLS>
b) Click on the inverter icon for the inverter to be setup.
c) Click on the <I
d) Click on the <C
e) Fill out the information required on the <G
<T
ELEPHONE FAULT CONFIGURATION> page, and the <TELEPHONE
C
ONFIGURATION> page.
152606 Rev A3–21
NVERTER DATA>
ONNECTION> tab.
ENERAL> page, the
Installation
Establishing Wireless Connection
Important:
provider before proceeding.
Ensure the Wireless service has been established with the local service
To connect a personal computer using the GSM Wireless modem:
1. Ensure the personal computer has the appropriate hardware installed to
support this feature.
2. Install the GUI Software following the instructions in the PV225S 225 kW
Grid-Tied Photovoltaic Inverter Operation and Maintenance Manual.
3. Use the GUI to setup the connection information.
a) From the GUI Main page, click on <T
b) Click on the inverter icon for the inverter to be setup.
c) Click on the <I
d) Click on the <C
e) Fill out the information required on the <G
ELEPHONE FAULT CONFIGURATION> page, and the <TELEPHONE
<T
C
ONFIGURATION> page.
Establishing an Ethernet LAN Connection
Important:
provider before proceeding.
To connect a personal computer using the Ethernet LAN Connection:
1. Ensure the personal computer has the appropriate hardware installed to
support this feature (i.e., Network Interface Card [NIC]).
2. Open the Communcations Enclosure and plug the LAN cable (CAT5 cable)
into the RJ45 Port of the SA2 Surge Arrestor marked "U
3. Install the GUI Software following the instructions in the PV225S 225 kW
Grid-Tied Photovoltaic Inverter Operation and Maintenance Manual.
4. Use the GUI to setup the connection information.
a) From the GUI Main page, click on the inverter icon for the inverter to be
b) Click on <C
c) Select "C
d) Fill in the IP address provided by the Internet Service Provider.
e) Click on the <C
f)Click on the <O
g) Repeat this procedure for each unit to be added to local area network.
Ensure the local area network has been established with the local service
setup.
ONNECTTO IP ADDRESS" in the drop-down menu.
OOLS>
NVERTER DATA>
ONNECTION> tab.
ENERAL> page, the
NPROTECTED".
OMMUNICATION>.
ONNECT> button.
K> button.
3–22152606 Rev A
Direct Connection
PC Communications
The direct connection provides the means to use the features of the GUI by
connecting a PC directly to the CCU. This allows field personnel to monitor and
control the inverter from a nearby laptop computer directly connected by a serial
cable. The computer connects to the inverter directly through one of its serial
COM ports running at 9600 baud.
The installed RS232/FO Converter will have to be removed and minor re-wiring
will be required.
The RS232/FO Converter kit (Xantrex p/n 1-152624-01) is required for this
connection to change the communication protocol from ethernet to serial in the
Communications Enclosure. A DB25-to-DB25 gender-changer adapter and
DB9/DB25 serial cable are provided with the RS232/FO Converter kit to
complete the connection.
If connecting the PC directly to the inverter:
1. Open the Communications Enclosure.
2. Disconnect the TX (transmit-orange) and RX (Receive-blue) wires from the
installed RS232/FO Converter in the Communications Enclosure.
3. Disconnect the power plug from the installed converter and plug it into the
new RS232/FO Converter.
4. Remove the installed converter. Replace with the new RS232/FO Converter.
5. Reconnect the TX (transmit-orange) and RX (Receive-blue) wires to the new
Converter in the Communications Enclosure.
6. Plug the DB25-to-DB25 Gender-changer Adapter into the Serial
Communications Port on the RS232/FO Converter. (Step not shown.)
7. Plug the DB25 connector on the serial cable into the gender-adapter and the
DB9 connector of the serial cable into the serial port on the computer. (Step
not shown.)
2
3
4
Modem Power Cord
(Do not Remove)
SA2 Surge Arrestor
MultiTech 56K Modem
Figure 3-21
152606 Rev A3–23
RS232/FO Converter Kit Installation
Installation
5
3
RE232/FO Converter
DB25-to-DB25 Gender Changer
Adapter
DB25/DB9 Serial Cable
Figure 3-22
Direct Connect Installation
3–24152606 Rev A
4
Verification
Chapter 4, “Verification” provides a checklist to ensure the
installation of the PV225S is correct and complete.
Verification
Verification Procedure Summary
WARNING: Electrocution Hazard
This chapter describes specific steps to ensure the installation of the PV225S 225 kW
Grid-Tied Photovoltaic Inverter is correct and complete. Failure to adhere to these
warnings could result in severe shock or possible death. Exercise extreme caution at all
times to prevent accidents. These installation instructions are for use by those familiar
and skilled with high voltage procedures.
WARNING: Shock Hazard
The PV225S enclosures contain exposed high-voltage conductors. The enclosure doors
should remain closed with the latches tightened, except during installation, maintenance
or testing. To reduce the risk of electric shock, do not perform any servicing other than
that specified in the installation instructions unless you are qualified to do so.
WARNING: Lethal Voltage
In order to remove all sources of voltage from the PV225S, the incoming power must be
de-energized at the source. This may be done at the utility main circuit breaker and by
opening the AC disconnect and the DC disconnect switches on the PV225S. Review the
system configuration to determine all of the possible sources of energy. In addition, allow
5 minutes for the DC bus capacitors, located on the ceiling of the cabinet, to discharge
after removing power.
The following procedures are intended to verify correct installation and proper
wiring of the PV225S. Prior to performing the following verification steps on the
PV225S, review all safety requirements and procedures outlined in this manual
and on any cautionary markings on the components within the system.
Inspect the following items prior to completion of the installation:
1. Visually inspect all the mechanical connections. This would include both
electrical conduit fittings, as well as enclosure anchoring and seismic bracing
if required.
2. Visually inspect the electrical connections and verify proper tightness of all
terminations.
3. Visually inspect the Isolation Transformer Wye/Wye connections and ensure
the T6-X0 neutral connection is left disconnected or floating.
4. Perform corrective actions if required.
4–2152606 Rev A
Visual Inspection of Mechanical Connections
Visual Inspection of Mechanical Connections
To perform a visual inspection of the PV225S mechanical connections:
1. Ensure that the AC and DC Disconnect Switches, as well as any utility
interconnect circuit breakers or main disconnect switches, are opened.
2. Ensure all anchor bolts and any required seismic bracing is properly
tightened and in place.
3. Remove the wiring access panels and front covers from the AC
Interface/Transformer assembly and Main Inverter Inductor Enclosure.
4. Remove the latches and open the doors of the Main Inverter Enclosure,
the AC and DC Interface Enclosures, and Communication Enclosure
and inspect.
5. Verify all wire conduit fittings and connections are properly tightened.❐
Visual Inspection of Electrical Connections
To perform a visual inspection of the PV225S electrical connections:
1. Ensure that the AC and DC disconnect switches, as well as any utility
interconnect circuit breakers or main disconnect switches, are opened.
2. Ensure all conductors and wiring connections interfacing with the
PV225S are tightened to the correct torque value.
For specific torque values, see Table 3-1, “AC Terminal Wire Gauge,
Bolt Size, and Torque Values” on page 3–12 and Table 3-2, “DC
Terminal Wire Gauge, Bolt Size, and Torque Values” on page 3–12.
❐
❐
❐
❐
❐
❐
3. Verify AC power conductors terminated at TB5, TB6, TB7 within the
Main Inverter Enclosure are terminated correctly and properly
sequenced.
4. Verify the AC power conductors terminated at S1-2T1, S1-4T2,
and S1-6T3 within the AC Interface Enclosure are terminated correctly
and properly sequenced.
5. Verify DC power conductors terminated at S2-6, K2-6T3, and TB4
within the DC Interface Enclosure are terminated correctly and properly
polarized.
152606 Rev A4–3
❐
❐
❐
Verification
Visual Inspection, Isolation Transformer Wye/Wye
To perform a visual inspection of the Isolation Transformer Wye/Wye:
1. Ensure that the AC and DC Disconnect Switches, as well as any utility
Interconnect circuit breakers or main disconnect switches, are open.
2. Verify all conductor and wiring connections interfacing with the
PV225S are tightened to the correct torque value.
For specific torque values, see Table 3-1, “AC Terminal Wire Gauge,
Bolt Size, and Torque Values” on page 3–12 and Table 3-2, “DC
Terminal Wire Gauge, Bolt Size, and Torque Values” on page 3–12.
3. Verify the AC power conductors terminated at T6-X1, T6-X2, and
T6-X3 within the Transformer Enclosure are terminated correctly and
properly sequenced.
4. Ensure the neutral on the inverter side (T6-X0) is left floating. If the
inverter side neutral is tied to ground, the inverter will not function
properly. Also, ensure that the neutral is not bonded to the isolation
transformer frame.
DateChecks Completed
❐
❐
❐
❐
Corrective Action
Perform after initial inspection (if required):
1. Correct any necessary repairs pertaining to the previous inspection steps.
2. Replace the wiring access panels to the AC interface/transformer assembly
and Main Inverter Enclosure.
3. Replace the latches and close the doors of the Main Inverter Enclosure, the
AC and DC Interface Enclosures, and communication enclosure.
4. Ensure that the AC and DC Disconnect Switches, as well as any utility
interconnect circuit breaker or main disconnect circuit breaker, are left open.
4–4152606 Rev A
A
Schematics
Appendix A contains useful schematics to aid with installation.
Schematics
This page intentionally left blank.
A–2152606 Rev A
Appendix ASchematics
Figure A-1
152606 Rev AA-3
Electrical Diagram (sample)
SchematicsAppendix A
Figure A-2
A-4152606 Rev A
PV225S-480 Schematic for Main Power Distribution (152291 B1)
Appendix ASchematics
Figure A-3
152606 Rev AA-5
PV225S-480 Schematic for Control Power Distribution(152291 B2)
SchematicsAppendix A
Figure A-4
A-6152606 Rev A
PV225S-480 Schematic for Converter Control Unit (152291 B3)