Fuse ratings shown are maximum allowable to permit use of the transfer switch in application with
available fault current not exceeding that shown. Consideration must be given to fuse sizing when
fuses also provide overload protection.
PM062 REV 6 08/08/01 27 Thomson Technology
TS 870 TRANSFER SWITCH
16.2. INTERRUPTING CAPACITY CURRENT RATINGS (ALL MODELS WITH
INTEGRAL OVERCURRENT PROTECTION OPTION)
INTERRUPTING CAPACITY CURRENT RATING AMPS (RMS) 1
No Upstream Circuit Breaker Protection Required
@240V @480V @600V
BASIC MODEL
TS87xA-0100
TS87xA-0150
TS87xA-0200
TS87xA-0250
TS87xA-0400
TS87xA-0600
TS87xA-0800
TS88xA-1000/1200
MAX.
VOLTAGE
600 100 65,000 25,000 14,000
600 150 65,000 25,000 14,000
240 200 65,000 N/A N/A
600 250 65,000 35,000 22,000
600 400 65,000 50,000 25,000
600 600 65,000 50,000 25,000
600 800 65,000 50,000 25,000
600 1000/1200 65,000 50,000 50,000
RATED
CURRENT
(A)
1. Standard ratings only are shown. Consult Thomson Technology for versions with higher interrupting capacity current ratings.
2. For other model types not shown, contact Thomson Technology for further information.
17. GROUND FAULT SITE TEST REQUIREMENTS
Per NEC and UL1008, a ground fault protected system shall be performance tested when first
installed on site. A written record of this shall be made and be available to the authority having
jurisdiction. A form is provided at the back of this manual for this purpose – see Section 21.
Confirm and record actual trip setpoints in the form provided which is to be made available on
request by inspection authority.
17.1. PERFORMANCE TEST
Qualified Field Service technicians require a calibrated current injection test apparatus and
must be knowledgeable in breaker testing to provide primary neutral CT injection up to or
greater than the trip setpoint as selected by the responsible party. As indicated in the NEC,
the maximum setting of the ground fault protection shall be 1200 amps, and the maximum
time delay shall be 1 second for ground faults equal to or greater than 3000 amps.
The inspection authority should be contacted to confirm actual test requirements as these
may vary by region or local code requirements.
PM062 REV 6 08/08/01 28 Thomson Technology
TS 870 TRANSFER SWITCH
The interconnected system shall be evaluated to ensure compliance with the appropriate
schematic drawings. The proper location of sensors and power cabling shall be determined.
The grounding points of the system shall be verified to determine that ground paths do not
exist that would bypass the sensors. The use of high-voltage testers and resistance bridges
may be required. A simulated fault current is to be generated by a coil around the sensors.
The reaction of the circuit-interrupting device is to be observed for correct response. The
results of the test are to be recorded on the test form provided.
PM062 REV 6 08/08/01 29 Thomson Technology
TS 870 TRANSFER SWITCH
18. TROUBLESHOOTING
DANGER!!!!
Arc Flash and Shock Hazard. Will cause severe injury or death.
Do not open equipment until ALL power sources are disconnected
This equipment must be installed and serviced only by qualified electrical
personnel utilizing safe work practices and appropriate Personal Protective
Equipment (PPE). Failure to do so may cause personal injury or death
Note: An optional hand held, plug-in Service Display Module (SDM) is available for the TSC 80
Transfer Controller. The SDM module provides an LCD screen to display additional detailed
information on the operation and settings of the TSC 80 controller for simplified servicing/trouble
shooting procedures. For detailed information, refer to the separate SDM module instruction manual
(PM065). TSC 80e transfer controllers have a built-in LCD display and therefore do not require the
SDM unit.
Symptom Possible Causes
Will not re-transfer to utility source
upon restoration
Will not transfer to generator source
upon failure of utility source
- Isolation plug out
- Utility disconnect switch is in the de-energized position (Service
Entrance Rated ATS). Switch to the Energized position.
- A test mode has been activated (check TSC 80/TSC 80E
status LED)
- Utility voltage is below the pre-programmed limits (check utility
source for adequate voltage)
- A loose control connection
- Faulty motor limit switch
- Defective motor
- TSC 80 has incorrect voltage configuration jumper setting for
correct system voltage or TSC 80E has incorrect voltage
setting as set via software programming
- TSC 80/TSC 80E has “Transfer Fail” alarm activated as
indicated by flashing Load on Utility LED. Determine cause of
alarm and rectify before TSC 80/TSC 80E is reset
- Isolation plug out
- Generator set not producing enough voltage/frequency or
output circuit breakeropen
- TSC 80 has incorrect voltage configuration jumper setting for
correct system voltage or TSC 80E has incorrect voltage
setting as set via software programming
PM062 REV 6 08/08/01 30 Thomson Technology
TS 870 TRANSFER SWITCH
Transfer to generator source without a
power failure in the utility source
Generator does not start up or stop
when it should
No time delay when there should be
- Warm-up time delay function has not timed out yet (verify TSC
80/TSC 80E timer setting)
- TSC 80/TSC 80E has “Transfer Fail” alarm activated as
indicated by flashing Load on Generator LED. Determine
cause of alarm and rectify before TSC 80/TSC 80E is reset
-
A test mode has been activated (check TSC 80/TSC 80E
-
status LED)
Utility supply voltage is slightly below voltage sensing setpoints.
Verify TSC 80 has correct voltage configuration jumper setting
for system voltage or TSC 80E has incorrect voltage setting as
set via software programming
- Utility power switching devicehas tripped due to an over
current condition and TSC 80/TSC 80E “Transfer Fail” alarm
activated as indicated by flashing Load on Utility LED.
Determine cause of alarm and rectify before TSC 80/TSC 80E
is reset.
- Verify remote engine control panel is set for automatic mode
- Verify time delay setting of the TSC 80/TSC 80E controller
Power is not available at the load
terminals but the utility or generator
power switching deviceappears to be
closed to a live source
- Limit switch incorrectly adjusted
The transfer switch has completed a
transfer, but the motor has overheated and
the internal thermal protector has opened
- The power switching device's over current protection unit has
opened due to a fault on the system. Correct the fault, and
manually reset the power switching devicein the transfer
switch by moving it off and then on again with the manual
operating handle
-
Limit switch failure or improper adjustment has failed to
disconnect motor
-
Binding or jamming of the transfer mechanism
PM062 REV 6 08/08/01 31 Thomson Technology
TS 870 TRANSFER SWITCH
NOTE
There are no user serviceable components located on the
TSC 80/TSC 80E printed circuit board. If the TSC 80/TSC 80E
controller is deemed to be defective it must be returned to the
Thomson Technology Factory for repair or replacement.
Please refer to Product Return Policy section of this manual
further information on product return procedures required.
19. REPLACEMENT PARTS
Replacement parts are available for the transfer switch as follows:
NOTE
When ordering replacement parts please provide the
following information:
-Transfer Switch Model code (e.g. TS 873AA0200AS)
-Transfer Switch Serial Number (e.g. W-022345)
The above information can be found on the transfer
switch equipment rating plate located on the outside of
120VAC Auxiliary Plug-in Timer 001515 Must ensure coil voltage is correct
004929 Must install and adjust for proper
operation before use. Contact
Thomson Technology Service Dept
for installation/adjustment
procedures
007701 Motor is supplied with gear box
assembly. Contact Thomson
Technology Service Department for
installation procedures
007961 Motor is supplied with gear box
assembly. Contact Thomson
Technology Service Department for
installation procedures
001075 Motor is supplied with gear box
assembly. Contact Thomson
Technology Service Department for
installation procedures
001278 Must ensure coil voltage is correct
100VA Control Transformer 002159
For other parts not listed, please contact Thomson Technology.
20. PRODUCT RETURN POLICY
Thomson Technology uses a Return Material Authorization (RMA) process. Please complete the
Return Authorization Request Form (available on our web page) for return of goods, warranty
replacement/repair of defective parts, or credit consideration and fax to the appropriate department.
Returns only: Sales Fax (604) 888-5606
Warranty replacement/Warranty Repair: Service Fax (604) 888-3370.
Upon receipt of your request, Thomson Technology will confirm with a copy of our Order
Acknowledgement via fax advising the RMA number which should be used to tag the defective
controller prior to shipment.
PM062 REV 6 08/08/01 33 Thomson Technology
21. NOTES
TS 870 TRANSFER SWITCH
PM062 REV 6 08/08/01 34 Thomson Technology
TS 870 TRANSFER SWITCH
22. PERFORMANCE TEST FORM
This form should be retained by those in charge of the building electrical installation in order to be
available to the authority having jurisdiction.
Date Personnel Tests performed Comments
Interconnection evaluation
Grounding point evaluation
Fault current test:
Ground fault settings -
______________________________
Simulated current -
______________________________
Results -
______________________________
PM062 REV 6 08/08/01 35 Thomson Technology
APPENDIX “A”
THOMSON TECHNOLOGY
TYPICAL AUTOMATIC TRANSFER SWITCH
COMMISSIONING PROCEDURES Model Series TS 870
Note: The following commissioning procedures are provided for general information only
pertaining to typical site installations and applications. Contact the equipment supplier for
further information as may be required.
DANGER!!!!
Arc Flash and Shock Hazard. Will cause severe injury or death.
Do not open equipment until ALL power sources are disconnected
This equipment must be installed and serviced only by qualified electrical personnel
utilizing safe work practices and appropriate Personal Protective Equipment (PPE).
Failure to do so may cause personal injury or death
CAUTION
Commissioning procedures must be performed by qualified personnel only. Ensure the
Automatic Transfer Switch (ATS) Control Isolation Plug is disconnected prior to energizing the
supply sources. Manually place the transfer switch mechanism in the neutral position by
opening both Utility and Generator Power Switching devices prior to applying power.
NOTE: An optional hand held, plug-in Service Display Module (SDM) is available for the TSC
80Transfer Controller. The SDM module provides an LCD screen to display additional detailed
information on the operation and settings of the TSC 80 controller for simplified
servicing/trouble shooting procedures. For detailed information, refer to the separate SDM
module instruction manual (PM065). TSC 80e transfer controllers have a built-in LCD display
and therefore do not require the SDM unit.
Pre-Commissioning Checks Prior to Commissioning Agent On-Site (to allow
loads to be supplied prior to final commissioning)
1) Verify the system voltage of both sources (i.e. generator and utility) to be applied to the transfer
switch are of the correct nominal system value which matches the ATS drawings and the ATS
equipment label ratings. If the system voltage is correct, proceed to step 3. If system voltage is
incorrect for the rating of the ATS supplied, proceed to step 2.
CAUTION: FAILURE TO RE-CONFIGURE ATS VOLTAGE TO MATCH SYSTEM VOLTAGE
WILL RESULT IN EQUIPMENT MALFUNCTION AND DAMAGE.
NOTE: The factory default system voltage setting for multi-voltage TS 840/870 transfer switches is
480VAC, which will be indicated by a letter “Y” in the voltage code as shown on the ATS model code (e.g. TS 873A0250A1AY) and on a warning tag attached to the isolation plug.
APPENDIX “A”
THOMSON TECHNOLOGY
TYPICAL AUTOMATIC TRANSFER SWITCH
COMMISSIONING PROCEDURES Model Series TS 870
2) To re-configure the ATS for the correct system voltage prior to energization, refer to Appendix
B (as attached). For further information, refer to the TSC 80/TSC 80E controller manual
supplied with the transfer switch.
3) For 240V High Leg Delta systems refer to the ATS instruction manual for correct phasing
required and re-configuring procedures.
CAUTION: FAILURE TO OBTAIN THE CORRECT ATS PHASING WILL RESULT IN
EQUIPMENT MALFUNCTION AND DAMAGE.
4) Confirm cable size is correct for the lugs supplied in the transfer switch (line and load). Confirm
the cables were meggered by the electrical contractor to ensure no cross phase connections or
conduction to ground.
5) Confirm cable lugs are properly torqued. Confirm cable installation; ensure the cables do not
interfere with normal equipment operation or which may cause component damage.
6) Manually operate the transfer mechanism to the appropriate source of supply. Leave the
Isolation Plug disconnected until final Transfer Switch Commissioning is to be completed.
1) Verify installation of the Automatic Transfer Switch as per installation manual and verify wiring
(also see the Pre-Commissioning Checks). Confirm phase, neutral and grounding conductors
are installed as per electrical code requirements. Note: Confirm neutral conductors of both
sources are correctly installed and are solidly grounded for 3 phase 4 wire configurations.
2) Check for mechanical damage (shipping or installer).
3) Verify correct control wire interconnects to the engine/generator set auto start/stop circuitry.
Ensure the engine controller automatic start circuit does not draw more than 5.0 amps
(resistive) across the TSC 80/TSC 80E Engine Start contact. The TSC 80/TSC 80E Engine
Start contact is voltage free and the only voltage measured should result from the engine
controllers internal control logic. Note: The ATS Engine Start contact CLOSES to start the
engine and OPENS to stop the engine.
4) Place the generator engine controller in the "OFF" position and open the generator local circuit
breaker.
5) Ensure the ATS isolation plug is disconnected prior to application of voltage of the supply
sources.
6) Energize the utility supply and the generator supply sources and verify these meet the correct
voltage, phasing and phase rotation for the ATS and system. Once these have been confirmed
to be correct, de-energize both sources before installing the isolation plug.
7) Once the isolation plug is connected, the ATS and system load may be energized with utility
power once the site electrical contractor and or owner (as required) give authorization to
proceed.
8) If Utility power is within nominal limits, the ATS should transfer to the utility source. To
determine correct operation, observe the following on the TSC 80/TSC 80E faceplate:
i) Utility Source green LED is “ON”
APPENDIX “A”
THOMSON TECHNOLOGY
TYPICAL AUTOMATIC TRANSFER SWITCH
COMMISSIONING PROCEDURES Model Series TS 870
ii) Green LED above mimic bus for the Utility source is “ON”
iii) Green “Load” LED is “ON”
9) To verify all LED’s are operational, perform a “LAMP TEST” operation (lamp test is initiated by
pressing and holding the 2 push buttons on the TSC 80/TSC 80E faceplate simultaneously
“ON” until all the LED’s change state).
10) Prior to operating the generator, ensure it is ready to be energized and the site electrical
contractor and/or owner (as required) give authorization to proceed. In preparation for
operation, turn the generator’s engine control switch to the “Automatic” start position.
11) To transfer the generator on load, perform a load test by pressing the Utility Power Fail
Simulate pushbutton “ON” and holding it for approximately 5 seconds until the LED light above
the push button changes state. The engine should start following the 3-second engine start
delay period and the transfer switch will begin transferring to the generator supply once the 2second engine warm-up timer expires. Note: The engine warm-up timer will only begin timing
once the generator’s output rises above 85% nominal voltage and 90% nominal frequency.
Once the Utility power switching device opens, the transfer switch mechanism will pause in the
neutral position for the 3-second neutral delay period, then the mechanism will complete the
transfer and close the generator power switching device. To determine correct operation,
observe the following on the TSC 80/TSC 80E faceplate:
i) Generator Source green LED is “ON”
ii) Red LED above mimic bus for the generator source is “ON”
iii) Green “Load” LED is “ON”
iv) Utility Source green LED is “ON”
v) Utility Power Fail Simulate yellow LED is “ON”
vi) Green LED above mimic bus for the Utility source is “OFF”
12) To terminate the test, press the Utility Power Fail Simulate push button on the TSC 80/TSC 80E
faceplate again and hold until the LED above the pushbutton changes state. The transfer
switch will begin transferring to the utility supply following the 2-minute utility return delay
period. Note: the utility return delay timer will only begin timing if the utility voltage is above
85% nominal on all phases. Once the Generator power switching device opens, the transfer
switch mechanism will pause in the neutral position for the 3-second neutral delay period, then
the mechanism will complete the transfer and close the Utility power switching device to return
the load to the Utility source. Once the load has transferred onto the utility source, the engine
will continue to run for the 2-minute cool down time delay period and will then it will
automatically stop.
13) Perform a power outage test by opening the upstream utility feeder breaker. The TSC 80/TSC
80E controller Utility supply LED lights will de-energize; the generator set will start after the 3second engine start delay has expired. The generator should transfer on load as described in
item #12 above.
14) Return the transfer switch to utility power by re-closing the upstream utility breaker. The load
should re-transfer back to the utility supply and the engine should stop as described in item #13
above.
15) Repeat tests #12 through 14 two (or more) times to ensure correct operation.
APPENDIX “A”
THOMSON TECHNOLOGY
TYPICAL AUTOMATIC TRANSFER SWITCH
COMMISSIONING PROCEDURES Model Series TS 870
16) Automatic Plant Exercise Operation (OPTIONAL): If an automatic weekly plant exercise feature
is desired, press the GENERATOR EXERCISE Mode push button on the TSC 80/TSC 80E
faceplate. Hold the push button “ON” for approximately 5 seconds until the LED light changes
state. Once the mode is initiated, the engine will immediately start and the generator will
transfer on load as previously described. Note: The generator may or may not transfer on load,
which is dependent on the TSC 80/TSC 80E configuration setting. The factory default setting is
for a “Load Transfer” plant exercise test. The engine will remain operating on load until the
plant exercise time delay period expires, then the load will re-transfer back to the utility supply
following the 2-minute utility return timer. On ATS using TSC 80 controller, the engine will be
automatically re-tested on load every week (i.e.7 days) at the same time of day that the first test
was initiated. On ATS using TSC 80E controller, the engine will be automatically re-tested as
programmed in software. Refer to the TSC 80/TSC 80E manual for further information.
17) On completion of commissioning ensure all controls are left in automatic.
18) If required, forward document or drawing updates to the equipment supplier if revisions are
required and provide the end user with a set of marked-ups to be retained on site.