HP NonStop S-Ser ies
Hardware Installation
and Fast Pa th Guide
Abstract
This guide is written for anyone qualified to install an HP NonStop™ S-series server.
This guide describes how to install and start a NonStop S-series server for the first
time. It includes information about installing server hardware, cabling system
enclosures, installing and starting NonStop system consoles, installing external system
devices, starting the server, and configuring the server after startup. This guide also
provides overview information about the I/O adapter module (IOAM) enclosure. A
quick reference to installing and configuring a two-processor or four-processor
NonStop S-series server in the Tetra 8 topology is included.
Product Version
N.A.
Supported Release Version Updates (RVUs)
This publication supports G06.28 and all subsequent G-series RVUs until otherwise
indicated by its replacement publication.
More About Groundstraps and Power Requirements1-23
Power-On Cables1-24
Hewlett-Packard Company—541880-001
i
Contents
1. Introduction (continued)
Emergency Power-Off Cables1-25
About EPO Cables1-25
EPO Cable Requirements1-25
System Organization1-26
Group, Module, and Slot Hierarchy for System Enclosures1-26
Group, Module, and Slot Hierarchy for IOAM Enclosures1-28
Server Numbering and Labeling1-31
ServerNet Cabling1-35
System Size1-35
Topologies1-36
Fabrics and S lots1-36
IOAM Enclosure Cabling1-37
ServerNet Cables1-37
The System Console1-45
1. Introduction (continued)
System Consoles1-45
The OSM Product1-46
The TSM Package1-46
Primary and Backup System Consoles1-47
Modems1-48
Preloaded and Supported Hardware and Software1-49
Software Connections1-54
System Startup1-55
Startup and Shutdown Files1-55
System Load Paths1-55
PMF CRU and IOMF CRU Power-On Self-Tests1-57
2. Installing Enclosures
Prepare to Install New Equipment2-2
1. Review the Documentation2-2
2. Prepare the Work Space2-3
3. Organize the Equipment2-4
Unpack the Enclosures2-6
Tools2-6
Unpack the Encl osures2-6
Connect the Groundstraps 2-13
Inventory the Enclosures2-16
Slot Assignments for NonStop S-Series Enclosures2-16
Inspect the Components2-23
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
ii
Contents
3. Cabling Enclosures
1. Connect Power-On Cables3-1
2. Connect EPO Cables 3-4
3. Connect ServerNet Cables3-5
4. Installing Service-Side Doors
5. Installing, Starting, and Testing a System Console
Unpacking and Assembling a System Console5-2
Installation Quick Reference5-2
Finding Documentation5-2
Finding the Quick Setup Reference Card5-2
Unpacking the System Console5-2
Assembling the System Console5-6
Starting and Testing a System Console5-8
3. Cabling Enclosures
Powering On a System Console5-8
Verifying Readiness5-9
Final Setup Step s5-9
Operational Considerations for OSM and TSM5-10
Connecting Multiple System Consoles5-11
System Console Function Keys5-12
6. Connecting a System Consol e
The Dedicated Service LAN6-2
Server Connection to a LAN6-2
System Console Connection to a Dedicated Service LAN6-3
System Console Connection to a Secure Operations LAN6-4
Ethernet Cables
Ethernet Switch Ports
Installing Ferrite Cores6-4
Installing the Ethernet Switch or Hub6-5
Connect the Ethernet Switch or Hub to the Server6-5
Connect the System Console to the Ethernet Switch or Hub6-6
6-4
6-4
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
iii
Contents
7. Installing External System Devices
Installing Tape Drives7-1
Installing a 5175 Open-Reel Tape Subsystem7-2
Installing a 519x Cartridge Tape Subsystem7-8
Installing Other Tape Devices 7-12
Installing Fibre Channel Tape Devices Using an IOAM Enclosure7-15
Attaching a SCSI Tape Drive to the NonStop S-Series Server7-15
Installing a SWAN or SWAN 2 Concentrator7-16
Installing an AWAN Server7-17
Installing Printers and Terminals7-17
8. Powering On and Starting the System
Starting a System for the First Time8-2
Startup Checklist8-2
Powering On External System Devices8-3
7. Installing External System Devices
Powering On the Primary System Console and Modem8-3
Powering On the Tape Subsystem8-3
Powering On the System8-5
Fault Tolerance and Access to Power Cutoffs8-5
Power-On Procedure Using AC Power Cords8-6
Status LEDs During a Power-On Procedure8-10
Troubleshooting Abnormal LED States8-12
Verifying Topology and System Components8-14
Starting the System8-18
Loading the System8-18
Completing the System Load8-21
Verifying the System Is Started8-21
9. Performi ng Po st-Startup Tasks
Testing the System9-1
Check Power Supplies9-2
Check System Enclosure Components9-2
Check Critical System Processes9-6
Check Disk Subsystem Status9-7
Test the Disk Drives9-8
Test the Communications Lines9-10
Check Tape Subsystem Status9-11
Test the Tape Subsystems 9-11
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
iv
Contents
9. Perf orming Post-Startup Tasks (continued)
9. Performi ng Po st-Startup Tasks (continued)
Completing Final Installation Steps9-12
System Configuration Changes and Verifications9-13
Restarting the Inspect Monitor Process9-14
Preparing for Daily Operations9-15
Reference Manuals 9-15
Configuring the OSM or TSM Environment9-16
Configuring the OSM Environment9-16
Configuring the TSM Environment9-16
10. Configurin g the System
Setup Configuration10-2
Procedure to Create the Setup Configuration10-2
Operating Configuration10-3
Create the Operating Configuration10-3
Add a System Console to the Operating Configuration10-6
Add a Server to the Operating Configuration10-8
Create a Cascading Ethernet Switch Configuration10-10
Add a System Console to the Cascading Ethernet Switches10-12
Add a Server to the Cascading Ethernet Switches10-12
Unattended Site Configuration10-13
Create the Unattended Site Configuration10-13
Add a Server to an Unattended Site Configuration10-14
Secure Operations LAN Configuration10-15
Construct a Secure Operations LAN Configuration10-15
11. Offline Configuratio n Tasks
Changes That Must Be Made Offline11-1
Application Reconfiguration11-2
Installing a New RVU11-2
Installing a Product Revision11-2
Changing System Name, System Number, or Time Attributes11-3
Changing the System Topology11-3
Changing the CONFTEXT File11-3
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
v
Contents
12. Online Configuration Tasks
SCF12-2
Initial CONFIG file12-2
Subsystems in G-Series RVUs12-3
Generic Processes12-4
Making Important Processes Persistent12-5
Types of System Configuration Files 12-6
KMSF12-8
Initial Configuration of KMSF Swap Files12-8
Changing the Configuration of KMSF Swap Files12-8
KMSF and the Operations Environment12-8
The OSM and TSM Packages12-9
Creating an Alternate System Disk12-10
1. Choose the Target Disk and Plan Its Space and Files12-11
2. Verify That the Target Disk Is Present12-12
12. Online Configuration Tasks
3. Stop Access to the Target Disk and Display Its Status12-12
4. Change the Label of the Target Disk12-13
5. Create a New System Volume and a System Image Tape (SIT)12-14
6. Install the Boot Millicode on the Target Disk12-14
7. Verify the Installation of Boot Millicode on the Target Disk12-15
8. Copy Subvolumes to the Target Disk12-16
Create a Command File12-17
13. Creating Startup and Shut down Files
Automating System Startup and Shutdown13-2
Startup13-2
Shutdown13-2
For More Information 13-2
Processes That Represent the System Console13-3
$YMIOP.#CLCI13-3
$YMIOP.#CNSL13-3
$ZHOME13-3
$ZHOME Alternative13-4
Example Command Files13-5
CIIN File13-6
Establishing a CIIN File13-6
Modifying a CIIN File13-7
If a CIIN File Is Not Specified or Enabled in OSM or TSM13-7
Example CIIN Files13-8
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
vi
Contents
13. Creating Startup and Shutdown
13. Creating Startup and Shut down Files (continued)
Tips for Startup Files13-9
How Process Persistence Affects Configuration and Startup13-9
Startup File Examples13-10
System Startup File13-10
Spooler Warm-Start File 13-12
TMF Warm-Start File13-12
TCP/IP Stack Configuration and Startup File13-12
CP6100 Lines Startup File13-15
ATP6100 Lines Startup File13-15
X.25 Lines Startup File13-15
Printer Line Startup File13-16
Expand-Over-IP Line Startup File13-16
Expand Direct-Connect Line Startup File13-16
Tips for Shutdown Files13-17
Files (continued)
Shutdown File Examples13-17
System Shutdown File13-18
CP6100 Lines Shutdown File13-19
ATP6100 Lines Shutdown File13-19
X.25 Lines Shutdown File13-19
Printer Line Shutdown File13-20
Expand-Over-IP Line Shutdown File13-20
Direct-Connect Line Shutdown File13-20
Spooler Shutdown File13-21
TMF Shutdown File13-21
Adding Super-Group User IDs13-21
14. Case Study: Installi ng and Configuring a System
About These Examples14-2
Background for Developers Inc.14-3
Hardware Configuration14-4
Installation Documents14-4
Case Study: Installation Document Checklist14-5
Case Study: System Equipment Inventory Form14-6
Case Study: Enclosure Arrangement Diagram14-7
Case Study: Floor Plan14-8
Case Study: Preinstalled I/O Device Cable Checklist14-9
Case Study: Group 01 System Enclosure Checklist14-10
Case Study: Group 01 Slot 50 PMF CRU Configuration Form14-11
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
vii
Contents
14. Case Study: Installing and Configuring a
System (continued)
14. Case Study: Installi ng and Configuring a System (continued)
Case Study: Group 01 Slot 55 PMF CRU Configuration Form14-12
Case Study: Group 01 Slot 53 E4SA Configuration Form14-13
Case Study: Group 01 Slot 54 E4SA Configuration Form14-14
Case Study: Group 02 System Enclosure Checklist14-15
Case Study: Group 02 Slot 50 PMF CRU Configuration Form14-16
Case Study: Group 02 Slot 55 PMF CRU Configuration Form14-17
Case Study: Group 02 Slot 53 E4SA Configuration Form14-18
Case Study: Group 02 Slot 54 E4SA Configuration Form14-19
System Configuration: CONFTEXT File14-20
LAN Environment at Developers Inc.14-20
Registry of IP Addresses14-20
Installing the System14-22
Customizing the Configuration14-22
Adding Ethernet 4 ServerNet Adapters (E4SAs)14-23
Adding ConMgr Process14-24
Configuring NonStop TCP/IP Stacks on E4SA Ports14-25
Adding Persistent CLCI TA CL, Expand Manager, and SCP Processes14-27
Starting the $ZEXP Expand Manager Process14-27
Adding a SWAN Concentrator14-28
Adding a SWAN 2 Concentrator14-28
Adding CP6100 Lines14-29
Adding an ATP6100 Line14-30
Adding a 5516 Printer14-31
Adding an X.25 Line14-32
Configuring and Starting the $NCP Network Control Process14-33
Adding an Expand-Over-IP Line14-33
Adding a Direct-Connect Line14-34
A. Part Numbers
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
viii
Contents
B. ServerNet Cabling
What ServerNet Cabling Diagrams MeanB-2
Maximum ServerNet ConfigurationsB-4
Maximum ServerNet Cabling TablesB-7
Shaded Areas in These TablesB-7
Tetra 8 Cabling TablesB-8
Tetra 16 Cabling TablesB-10
Small Tetra 8 SystemsB-14
About This InformationB-14
Tetra 8 Systems With One Processor EnclosureB-15
Tetra 8 Systems With Two Processor EnclosuresB-16
Tetra 8 Systems With Three Processor EnclosuresB-17
Tetra 8 Systems With Four Processor EnclosuresB-21
Small Tetra 16 SystemsB-25
About This InformationB-25
B. ServerNet Cabling
Tetra 16 Systems With Four Processor EnclosuresB-26
Tetra 16 Systems With Six Processor EnclosuresB-28
C. Power-On Cabling
D. Tr oubleshooting
ReferenceD-2
Power StatesD-2
Status LEDsD-4
Powering On the SystemD-5
System Does Not Appear to Be Powered OnD-6
Power Is Applied to Enclosure But Fans Are Not Turning
Any Green LED Is Not Lit
Any Amber LED Remains Lit After POSTD-9
Yellow ServerNet Port LEDs on SEBs or MSEBs Are Not LitD-9
Group Service LED on System Enclosure Is FlashingD-9
Correcting Topology AttributeD-9
D-6
D-8
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
ix
Contents
D. Tr oubleshooting (continued)
Starting the System D-10
Startup Event Stream and Startup TACL Windows Do Not AppearD-10
System Load Fails D-11
CIIN File Is Not Invoked During System StartupD-12
Reload FailsD-13
CPU Memory Test FailsD-14
System Load Path Test FailsD-14
Multifunction I/O Board (MFIOB) Test FailsD-15
Dumping Processor MemoryD-16
Dumping Processor Memory to Disk OnlineD-16
Dumping Processor Memory to Tape OfflineD-20
Expand-Over-IP ConnectionsD-22
Recovery Actions for the CONNECTING StateD-24
Recovery Actions for the WAIT StateD-24
D . Troubleshooting (continued)
Backing Out a Software RevisionD-26
PrerequisitesD-26
1. Start DSM/SCMD-26
2. Start and Log On to Target InterfaceD-27
3. Initiate Backout ActivityD-27
4. Monitor Backout ProcessD-28
5. Stop All ApplicationsD-28
6. Rename Software Files Using ZPHIRNMD-29
7. Stop SystemD-29
8. Load System From Saved ConfigurationD-30
9. Start ApplicationsD-30
System ConsolesD-31
Software Configuration ProblemsD-36
Software Corruption and Hard-Disk ProblemsD-37
Restoring Software on the Hard DiskD-38
Configuring a ProCurve 24-Port Ethernet SwitchD-48
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
x
Contents
E. FastPath Tasks: Required
1. Install HardwareE-3
1. Inventory ShipmentE-4
2. Collect T ools E-6
3. Unpack and Unload ServerE-6
4. Connect GroundstrapsE-10
5. Inventory and Inspect All ComponentsE-1 1
6. Connect the Power-On CablesE-11
7. Connect Emergency Power-Off (EPO) CablesE-13
8. Connect ServerNet CablesE-14
9. Install Service-Side Enclosure Doors If NecessaryE-15
10. Install Primary System ConsoleE-16
11. Create Emergency Repair Disk or Automated System Recovery DiskE-18
12. Install Ethernet SwitchE-18
13. Connect Ethernet Switch to Group 01E-18
E. FastPath Tasks: Required
14. Connect Primary System Console to Ethernet Switch E-19
15. Install Tape Drive E-19
2. Start the System E-22
1. Prepare for System StartupE-22
2. Power On External System DevicesE-23
3. Connect AC Po wer CordsE-24
4. Apply Power to ServerE-26
5. Verify TopologyE-27
6. Verify System ComponentsE-28
7. Start SystemE-28
3. Verify the System E-30
1. Verify ComponentsE-30
2. Verify Critical System ProcessesE-31
3. Verify Disk DrivesE-31
4. Verify Tape DriveE-32
5. Verify FirmwareE-32
6. Verify State of the Internal ServerNet FabricE-32
4. Configure the SystemE-33
1. Configure PasswordsE-34
2. Configure Kernel-Managed Swap FilesE-35
3. Configure OSM or TSM EnvironmentE-36
4. Configure System Attribute sE-37
5. Configure DSM/SCME-41
5. Install the Backup System ConsoleE-45
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xi
Contents
F. FastPat h Tasks: Optional
1. PrerequisitesF-2
1a. Verify Required Configuration ChangesF-2
1b. Review Initial System ConfigurationF-2
1c. Start Required ProcessesF-2
1d. Save Current System ConfigurationF-3
1e. If Your Server Will Be Part of a ServerNet ClusterF-3
2. Customize the System ConfigurationF-4
2a. Change SCFF-4
2b. Rename SCF Objects in the CONFIG FileF-5
2c. Add SCF Objects to the CONFIG FileF-6
3. Automate System StartupF-7
Modify Provided Startup FilesF-7
Create Startup FilesF-7
4. Automate System ShutdownF-8
F. FastPath Tasks: Optional
Tips for Shutdown FilesF-8
5. Configure a SWAN or SWAN 2 ConcentratorF-9
Access the WAN Wizard ProF-9
6. Configure an Expand-Over-IP LineF-10
PrerequisitesF-11
1. On the NonStop S-Series ServerF-12
2. On the NonStop K-Series ServerF-16
3. On the NonStop S-Series ServerF-18
4. On the NonStop K-Series ServerF-19
5. On Either NonStop ServerF-21
7. Install SoftwareF-22
Configuring Software With DSM/SCMF-23
Installing a Software Product Revision (SPR)F-25
Safety and Compliance
Glossary
Index
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xii
Contents
Examples
Example D-1.SCF STATUS LINE, DETAIL DisplayD-22
Example F-1.SCF LISTDEV TCP IP DisplayF-13
Example F-2.SCF LISTDEV TCP 6SAM DisplayF-14
Example F-3.SCF INFO SUBNET DisplayF-14
Example F-4.SCF STATUS PROCESS DisplayF-15
Example F-5.SCF LISTDEV TCP IP DisplayF-16
Example F-6.SCF INFO SUBNET DisplayF-16
Example F-7.SCF STATUS PROCESS DisplayF-17
Example F-8.COUP INFO CONTROLLER DisplayF-19
Example F-9.COUP INFO DEVICE DisplayF-19
Figure 1-3.Base and Stackable Enclosures1-16
Figure 1-4.SEBs in a Processor Enclosure Without a Power Shelf1-17
Figure 1-5.MSEBs in a Processor Enclosure With a Power Shelf1-18
Figure 1-6.Service Side of I/O Enclosure Without Power Shelf1-19
Figure 1-7.Service Side of I/O Enclosure With Power Shelf1-20
Figure 1-8.Rack with IOAM Enclosure (Front Side)1-21
Figure 1-9.Rack With IOAM Enclosure (Rear Side)1-22
Figure 1-10.Power-On Cable Connectors1-24
Figure 1-11.EPO Cable1-25
Figure 1-12.Port Numbers and Cable Connections on an MSEB1-39
Figure 1-13.SEB-to-SEB ECL Cable1-40
Figure 1-14.MSEB-to-MSEB ECL Cable1-40
Figure 1-15.SEB-to-MSEB ECL Cable1-40
Figure 1-16.Serial-Copper Cable1-41
Figure 1-17.Fiber-Optic Cable1-41
Figure 1-18.LC Connector for the 6780 Switch or ServerNet Switch Board1-42
Figure 1-19.SC Connector for MSEB1-42
Figure 1-20.ServerNet Cable Labeling1-43
Figure 1-21.Cable-Ma nagem ent Hardw ar e1-44
Figure 1-22.System Load Paths1-56
Figure 2-1.Cords, Cables, and Other Contents of Short Cartons2-5
Figure 2-2.Unpacking the Enclosures2-7
Figure 2-3.Tabs on Plastic Locking Clip of Shipping Package2-8
Figure 2-4.Loosen End Piece of Pallet by Turning Twist-Lock Handles2-8
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xiii
Contents
Figures (continued)
Figure 2-5.Removing End Piece of Pallet2-9
Figure 2-6.Velcro Strips on Loading Pallet2-9
Figure 2-7.Leveling Pads Must Be Raised Before Enclosure Is Moved2-10
Figure 2-8.Use Two People to Move an Enclosure Stack2-11
Figure 2-9.Lowering Legs of Base Enclosure2-12
Figure 2-10.Groundstrap Connecto r Locations2-13
Figure 2-11.Gr ound strap Connectio ns Between Enclo sures2-14
Figure 2-12.Examples of Groundstrap Locations Between Enclosures2-15
Figure 2-13.Appearance Side, Processor Enclosure2-17
Figure 2-14.Service Side: Processor Enclosure Without Power Shelf2-18
Figure 2-15.Service Side: Processor Enclosure With Power Shelf2-19
Figure 2-16.Service Side: I/O Enclosure Without Power Shelf2-20
Figure 2-17.Service Side: I/O Enclosure With Power Shelf2-21
Figure 2-18.Unlocking and Opening an Enclosure Door2-22
Figures (continued)
Figure 2-19.Reseating a Disk Drive2-23
Figure 2-20.Reseating a PMF CRU or IOMF CRU2-24
Figure 2-21.Reseating a SEB or MSEB2-25
Figure 2-22.Reseating a ServerNet Adapter2-26
Figure 3-1.Connecting and Securing Power-On Cables3-3
Figure 3-2.EPO Connector on a System Enclosure3-4
Figure 3-3.Securing ServerNet Cables With Cable Ties3-6
Figure 4-1.Securing the Frame to the Enclosure Using a Mounting Hole4-2
Figure 4-2.Inserting a Phillips Screw Into the Mounting Hole4-2
Figure 4-3.Tightening a Phillips Screw in a Mounting Hole4-3
Figure 4-4.Service-Side Door Installed on a System Enclosure4-4
Figure 5-1.Setup Configuration5-11
Figure 6-1.Processor Enclosure PM F CRU Ethernet Ports6-3
Figure 6-2.Connections for the Setup Configuration6-6
Figure 7-1.5175 Tape Subsystem7-2
Figure 7-2.Unloading a Tape Subsystem7-3
Figure 7-3.Removing the Shipping Restraints From a 5175 Tape Subsystem7-5
Figure 7-4.Installing the Top Panel and Corner Caps on a 5175 Tape
Subsystem7-6
Figure 7-5.Connecting a SCSI Cable to a 5175 Tape Subsystem7-7
Figure 7-6.AC Power Switch for 5175 Tape Drive CRU7-8
Figure 7-7.519x Tape Subsystem7-9
Figure 7-8.Connecting a SCSI Cable to a 519x Tape Subsystem7-10
Figure 8-1.AC Power Switch for 5175 Tape Drive8-4
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xiv
Contents
Figures (continued)
Figure 8-2.AC Power Switch for 519x Tape Drive8-5
Figure 8-3.AC Power Cord8-6
Figure 8-4.Connecting an AC Power Cord to an Enclosure With No Power
Shelf8-7
Figure 8-5.Connecting an AC Power Cord to an Enclosure With a Power
Shelf8-8
Figure 8-6.Management Window in OSM or TSM Low-Level Link8-15
Figure 8-7.Verifying the System Topology8-15
Figure 8-8.Entering Information in the System Startup Dialog Box8-19
Figure 8-9.Checking Processor Status8-22
Figure 9-1.Management Window in the OSM Service Connection9-3
Figure 9-2.Management Window in the TSM Service Application9-4
Figure 10-1.Setup Configuration10-2
Figure 10-2.Operating Configuration10-3
Figures (continued)
Figure 10-3.Connections for the Operating Configuration10-5
Figure 10-4.Operating Configuration With an Added System Console10-6
Figure 10-5.Adding a System Console to the Operating Configuration10-8
Figure 10-6.Operating Configuration With an Added Server10-9
Figure 10-7.Connections for Adding a Server to the Operating Configuration10-10
Figure 10-8.Cascading Ethernet Switch Configuration10-11
Figure 10-9.Connecting Cascading Etherne t Switches10-12
Figure 10-10. Unattended Site Configuration10-13
Figure 10-11. LAN Configurations: Operations and Dedicated10-16
Figure 12-1.Subsystems in G-Series RVUs12-3
Figure 12-2.Differences Among System Configuration Files12-7
Figure B-1.Correlation Between ServerNet Cable Diagram and One
EnclosureB-2
Figure B-2.
Correlation Between ServerNet Cable Diagram and Two
EnclosuresB-3
Figure B-3.Maximum Tetra 8 Topologies, X and Y FabricsB-4
Figure B-4.Maximum Tetra 16 Topology, X FabricB-5
Figure B-5.Maximum Tetra 16 Topology, Y FabricB-6
Figure B-6.Tetra 8 Cabling: Two Processor Enclosures, Two I/O EnclosuresB-17
Figure B-7.Tetra 8 Cabling: Three Processor Enclosures, Six I/O EnclosuresB-20
Figure B-8.Tetra 16 Cabling: Four Processor Enclosures, X FabricB-26
Figure B-9.Tetra 16 Cabling: Four Processor Enclosures, Y FabricB-27
Figure B-10.Tetra 16 Cabling: Six Processor Enclosures, X FabricB-28
Figure B-11.Tetra 16 Cabling: Six Processor Enclosures, Y FabricB-29
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xv
Contents
Figures (continued)
Figure C-1.Power-On Cabling: Single-High StacksC-2
Figure C-2.Power-On Cabling: Mixed Single-High and Double-High StacksC-3
Figure C-3.Po wer-On Cabling: Multiple-Row SystemsC-4
Figure C-4.Power-On Cable: One Processor EnclosureC-5
Figure C-5.Power-On Cables: One Processor Enclosure, One I/O EnclosureC-5
Figure C-6.Power-On Cables: One Processor Enclosure, Two I/O EnclosuresC-5
Figure C-7.Power-On Cables: Two Processor Enclosures, No I/O EnclosuresC-6
Figure C-8.Power-On Cables: Two Processor Enclosures, One I/O EnclosureC-6
Figure C-9.Power-On Cables: Two Processor Enclosures, Two I/O
EnclosuresC-6
Figure C-10.Power-On Cables: Three Processor Enclosures, No I/O
EnclosuresC-7
Figure C-11.Power-On Cables: Three Processor Enclosures, One I/O
EnclosureC-7
Figures (continued)
Figure C-12.Power-On Cables: Three Processor Enclosures, Two I/O
EnclosuresC-7
Figure C-13.Power-On Cables: Three Processor Enclosures, Three I/O
EnclosuresC-8
Figure C-14.Power-On Cables: Four Processor Enclosures, No I/O EnclosuresC-8
Figure C-15.Power-On Cables: Four Processor Enclosures, One I/O EnclosureC-8
Figure C-16.Power-On Cables: Four Processor Enclosures, Two I/O
EnclosuresC-8
Figure C-17.Power-On Cables: Four Processor Enclosures, Three I/O
EnclosuresC-9
Figure C-18.Power-On Cables: Four Processor Enclosures, Four I/O
EnclosuresC-9
Figure E-1.
Figure E-2.
Packaging of Enclosure StackE-6
Velcro Strips on Loading PalletE-8
Figure E-3.Rolling the Stack to the Installation AreaE-9
Figure E-4.Enclosure Stacks in Final PositionsE-9
Figure E-5.Lowering Legs of Base EnclosureE-9
Figure E-6.Groundstrap Connecto r LocationsE-10
Figure E-7.Power-On Cable ConnectorsE-11
Figure E-8.Power-On Cables: One Processor EnclosureE-11
Figure E-9.Power-On Cables: One Processor Enclosure, One I/O EnclosureE-11
Figure E-10.Power-On Cables: One Processor Enclosure, Two I/O
EnclosuresE-12
Figure E-11.Power-On Cables: Two Processor EnclosuresE-12
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xvi
Contents
Figures (continued)
Figure E-12.Power-On Cables: Two Processor Enclosures, One I/O
EnclosureE-12
Figure E-13.Power-On Cables: Two Processor Enclosures, Two I/O
EnclosuresE-12
Figure E-14.EPO CableE-13
Figure E-15.Connecting an Ethernet Switch to Group 01E-18
Figure E-16.Attaching SCSI Ca ble to PMF CRUE-20
Figure E-17.Adding a System Console to the Operating ConfigurationE-46
Tables
Table 1-1.Weights for Enclosure Shipping Packages1-10
Table 1-2.Maximum Processor and I/O or IOAM Enclosure Connections1-31
Table 1-3.Maximum Numbers of Enclosures for G06.03 and Later RVUs1-35
Table 1-4.ServerNet Cable Compatibilities With Components1-38
Figures (continued)
Table 1-5.Preloaded and Supported HP NonStop System Console
Software1-50
Table 1-6.Preconfigured IP Addresses for a NonStop S-Series Server1-52
Table 1-7.System Load Paths in Order of Use1-55
Table 2-1.Illustrations of Enclosures Including Slot Numbers2-16
Table 2-2.Slot Assignments: Tetra 8 Topology2-16
Table 2-3.Slot Assignments: Tetra 16 Topology2-17
Table 5-1.Contents of the Shipping Box5-3
Table 7-1.517x Firmware Requirements7-3
Table 8-1.Status LEDs and Their Functions8-10
Table 8-2.Troubleshooting Abnormal LED States8-12
Table 8-3.
Table 9-1.
Checking the Attributes of Selected System Components8-16
System Configuration Changes and Verifications9-13
Table B-1.Maximum Tetra 8 ServerNet Cabling, Processor EnclosuresB-8
Table B-2.Maximum Tetra 8 ServerNet Cabling, I/O EnclosuresB-9
Table B-3.Maximum Tetra 16 ServerNet Cabling, Processor EnclosuresB-10
Table B-4.Maximum Tetra 16 ServerNet Cabling, I/O EnclosuresB-11
Table B-5.Tetra 8 Cabling: One Processor Enclosure, One I/O EnclosureB-15
Table B-6.Tetra 8 Cabling: One Processor Enclosure, Two I/O EnclosuresB-15
Table B-7.Tetra 8 Cabling: Two Processor Enclosures, No I/O EnclosuresB-16
Table B-8.Tetra 8 Cabling: Two Processor Enclosures, One I/O EnclosureB-16
Table B-9.Tetra 8 Cabling: Two Processor Enclosures, Two I/O EnclosuresB-16
Table B-10.Tetra 8 Cabling: Three Processor Enclosures, No I/O EnclosuresB-17
Table B-11.Tetra 8 Cabling: Three Processor Enclosures, One I/O EnclosureB-17
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xvii
Contents
Tables (continued)
Table B-12.Tetra 8 Cabling: Three Processor Enclosures, Two I/O
EnclosuresB-18
Table B-13.Tetra 8 Cabling: Three Processor Enclosures, Three I/O
EnclosuresB-18
Table B-14.Tetra 8 Cabling: Four Processor Enclosures, No I/O EnclosuresB-21
Table B-15.Tetra 8 Cabling: Four Processor Enclosures, One I/O EnclosureB-21
Table B-16.Tetra 8 Cabling: Four Processor Enclosures, Two I/O EnclosuresB-22
Table B-17.Tetra 8 Cabling: Four Processor Enclosures, Three I/O
EnclosuresB-22
Table B-18.Tetra 8 Cabling: Four Processor Enclosures, Four I/O EnclosuresB-23
Table D-1.Troubleshooting the Expand Connection ProcedureD-22
Table D-2.Keyboard Is InoperativeD-32
Table D-3.Mouse Is InoperativeD-33
Table D-4.Monitor Screen Is BlankD-34
Tables (continued)
Table D-5.System Unit Is InoperativeD-35
Table D-6.Monitor Screen Is FrozenD-36
Table D-7.Application Fails Immediately When StartedD-37
Table D-8.Install Windows XP Professional Operating SystemD-39
Table D-9.Set Up Date and TimeD-43
Table D-10.Set Event Log SettingsD-44
Table D-11.Install Internet ExplorerD-46
Table E-1.ServerNet Cables for One Processor Enclosure, One I/O
EnclosureE-14
Table E-2.ServerNet Cables for Two Processor Enclosures, No I/O
EnclosuresE-14
Table E-3.ServerNet Cables for Two Processor Enclosures, One I/O
EnclosureE-14
Table E-4.
ServerNet Cables for Two Processor Enclosures, Two I/O
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xviii
What’s New in This Guide
Manua l In forma tion
HP NonStop S-Series Hardware Installation and FastPath Guide
Abstract
This guide is written for anyone qualified to install an HP No nStop™ S-series server.
This guide describes how to install and start a NonStop S-series server for the first
time. It includes information about installing server hardware, cabling system
enclosures, installing and starting NonStop system consoles, installing external system
devices, starting the server, and configuring the server after startup. This guide also
provides overview information about the I/O adapter module (IOAM) enclosure. A
quick reference to installing and configuring a two-processor or four-processor
NonStop S-series server in the Tetra 8 topology is included.
Product Version
N.A.
Supported Release Version Updates (RVUs)
This publication supports G06.28 and all subsequent G-series RVUs until otherwise
indicated by its replacement publication.
The glossary has been moved to NTL and is titled
NonStop System Glossary.
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xx
About This Guide
This guide describes how to install and bring up a NonStop S-series server for the first
time. It includes information about installing the server hardware, cabling system
enclosures, installing and starting system consoles, installing external system devices,
and starting the server. This guide is written for anyone who is qualified to install a
NonStop S-series server.
This guide assumes that you are using the HP NonStop Open System Management
(OSM) or Compaq TSM software to perform the OSM or TSM tasks described in this
guide.
Note. Throughout this guide, the term Sxx000 stands for NonStop S70000, S7200 0, S74000,
S76000 , S 78000, S86 000, S88000 s ervers.
Information in this guide also applies to NonStop S7x00 servers of model S7400 and higher.
Who Should Use This Guide
This guide is written for anyone who installs system equipment at a customer site. You
should be familiar with computers but do not need to be familiar with installing
mainframe computer systems. However, those who perform the hardware tasks
documented in this guide must have completed training courses on system support for
NonStop S-series servers.
Note. NonStop NS-series, NonS t op S-serie s, and NonStop K-s eries refer to h ardware
systems; H-series, G-series, and D-series refer to system software.
H-ser ies s of t wa re runs on NonStop NS-series se rvers.
•
G-series software runs on NonStop S-series servers.
•
D-ser ies s of t wa r e runs on No nStop K-series servers.
•
What’s in This Guide
SectionTitleContents (page1of3)
1
2
3
IntroductionThis section s ummarize s th e i nst allation pro cess a nd
Installing EnclosuresThis section describes how to u npac k new
Cabling EnclosuresThis section explains how to cable enclosures in
gives an overview of the NonStop S-series system.
equipment and install NonStop system enclosures.
NonStop S-series systems with power-on,
emergency power-off (EPO), and ServerNet ca ble s .
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxi
About This Guide
SectionTitleContents (page2of3)
What’s in This Guide
4Installing Service-Sid e
Doors
5
Installing, Starting, an d
Testing a System Console
6
Connecting a System
Console
7
Installing External System
Devices
8
Poweri n g On and St art i ng
the System
9
Perform ing Post-Startup
Tasks
10
Configu ring the Sys te mThis section describes how to configure system
This section describes how to install optional
service-side doors on NonStop S-series system
enclosu res t hat are alrea dy installed and c abled.
(New NonStop S-series system enclosures are
shipped with service-side doors installed.)
This section describes how to unpack, assemble,
start, and test a system console.
This section describes how to connect a primary
system console to the installed server and dedicated
service LAN by usin g Et hernet cables and an
Ethernet s w it c h or Ethernet hub.
This section describes how to install selected
peripheral devices such as tape subsystems.
This section describes how to p ow er on NonStop
S-series system enclosures, how to power on
external devices, and how to start the system.
This section describes the tasks that you must
perform after t he NonStop S-ser ies s erv er has been
powered up and starte d.
consoles and NonStop S-series servers in several
ways.
11
12
13
14
A
B
C
Off line Con f igur ation
Tasks
This section describes offline configuration tasks,
which change software or hardware configurations
and require the system to be shut down.
Online Configura tio n
Tasks
This section describes how to configure your system
online using the Subs y stem Contro l F ac ility (SCF),
Kernel- M anaged Sw ap Facility (KMSF), OSM , and
TSM, and how to create an alternate $SYSTEM disk.
Creating Startup and
Shutdow n F iles
This section describes command files that
automatically start and shut down a NonStop
S-series server.
Case Study: Installing and
Configu ring a Syste m
This section documents the instal lat ion and
configuration of a NonStop S7000 system for a
fictitious company.
Part NumbersPart numbers have been moved to the Support and
and tables for maximum Tetra 8 and Tetra 16
configu rat ions. It also co nta ins diagrams and tables
for selected smaller configurations.
Power-On CablingThis se ction provid es power-on ca bling diagram s f or
selected large and sm aller Serve rN et c onfigurations.
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxii
About This Guide
SectionTitleContents (page3of3)
DTroubleshootingThis appendix explains basic recovery tasks for the
What’s in This Guide
system and system console.
E
FastPath Tasks: RequiredThis appendix con tain s all t he ta s ks required to
install, start, and configure a two-pro ce ssor or fourprocessor NonStop S-series server in the Tetra 8
topology.
F
FastPath Tasks: OptionalThis append ix c ontains all optional configuration
tasks for a two-processor or four-processor NonStop
S-series s erv er in the Tetra 8 topolo gy.
Glossary
The Glossary has been moved to the NonStop
Technical Library (NTL).
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxiii
About This Guide
Where to Get More Information
Documentation
Manuals, Hotstuff messages, and other kinds of documentation are available in the
NonStop Technical Library (NTL) at http://techlibrary.cac.cpqcorp.net.ntl/.
For abstracts of the NonStop S-series manuals, see the NonStop S-Series Planning and Configuration Guide.
Support and Service Library
These NTL Support and Service library categories provide procedures, part numbers,
troubleshooting tips, and tools for servicing NonStop S-series and Integrity NonStop
NS-series systems:
Hardware Service and Maintenance Publications
•
Service Information
•
Service Procedures
•
Tools a nd Download Files
•
Troubleshooting Tips
•
Where to Get More Information
Within these categories, where applicable, content might be further categorized
according to server or enclosure type.
Authorized service providers can also order the NTL Support and Service Library CD:
Channel Partners and Authorized Service Providers: Order the CD from the SDRC
•
at https://scout.nonstop.compaq.com/SDRC/ce.htm.
HP employees: Subscribe at World on a Workbench (WOW). Subscribers
•
automatically receive CD updates. Access the WOW order form at
http://hps.knowledgemanagement.hp.com/wow/order.asp.
OSM Guided Replacement Procedures
Some of the procedures in this guide refer to the OSM guided replacement
procedures. These automated tools are integrated into the OSM Service Connection.
They guide you step-by-step through replacing many customer-replaceable units
(CRUs).
To launch OSM guided replacement procedures:
1.Log on to the OSM Service Connection.
2.In the tree pane, locate and select the CRU/FRU you want to replace.
3.Select Actions.
4.In the Actions dialog box, from the Available Actions list, select Replace.
5.Click Perform Acti on to launch the guided procedure.
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxiv
About This Guide
TSM Guided Replacement Procedures
TSM guided replacements procedures are launched by the Windows Start menu
(rather than integrated into the application).
Note. TSM does not su pport IOAM or F ibre Cha nnel di s k -drive enclosures. OSM should be
used to manage systems that inc lude these c om ponents.
These guided replacement procedures are currently available:
Replace IOMF
•
Replace PMF
•
Replace Power Supply
•
Replace SEB or MSEB
•
Replace SNDA
•
Replace Switch Component
•
Guided Replacement Toolkit (GRT)
•
TSM Guided Replacement Procedures
Note. The GRT is used to replace an IOM F, PMF, power supply, or 6760 ServerNet
device adapter (ServerNet/DA) in a system running TSM server T7945AAW (shipped with
the G06. 12 RVU) or earlier.
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxv
About This Guide
Notation Conventions
Notation Conventions
Hypertext Links
Blue underline is used to indicate a hypertext link within text. By clicking a passage of
text with a blue underline, you are taken to the location described. For example:
This requirement is described under Backup DAM Volumes and Physical Disk
Drives on page 3-2.
General Sy ntax Notation
This list summarizes the notation conventions for syntax presentation in this manual.
UPPERCASE LETTERS. Uppercase letters indicate keywords and reserved words; enter
these items exactly as shown. Items not enclosed in brackets are required. For
example:
MAXATTACH
lowercase italic letters. Lowercase italic letters indicate variable items that you supply.
Items not enclosed in brackets are required. For example:
file-name
computer type. Computer type letters within text indicate C and Open System Services
(OSS) keywords and reserved words; enter these items exactly as shown. Items not
enclosed in brackets are required. For example:
myfile.c
italic computer type. Italic computer type letters within text indicate C and Open
System Services (OSS) variable items that you supply. Items not enclosed in brackets
are required. For example:
pathname
Punctuation. Parentheses, commas, semicolons, and other symbols not previously
described must be entered as shown. For example:
error := NEXTFILENAME ( file-name ) ;
LISTOPENS SU $process-name.#su-name
Quotation marks around a symbol such as a bracket or brace indicate the symbol is a
required character that you must enter as shown. For example:
"[" repetition-constant-list "]"
Item Spacing. Spaces shown between items are required unless one of the items is a
punctuation symbol such as a parenthesis or a comma. For example:
CALL STEPMOM ( process-id ) ;
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxvi
About This Guide
Notation for Messages
If there is no space between two items, spaces are not permitted. In this example,
there are no spaces permitted between the period and any other items:
$process-name.#su-name
Line Spaci ng. If the syntax of a command is too long to fit on a single line, each
continuation line is indented three spaces and is separated from the preceding line by
a blank line. This spacing distinguishes items in a continuation line from items in a
vertical list of selections. For example:
ALTER [ / OUT file-spec / ] LINE
[ , attribute-spec ]…
Notation for Messages
This list summarizes the notation conventions for the presentation of displayed
messages in this manual.
Nonitalic text. Nonitalic letters, numbers, and punctuation indicate text that is displayed or
Change bars are used to indicate substantive differences between this edition of the
manual and the preceding edition. Change bars are vertical rules placed in the right
margin of changed portions of text, figures, tables, examples, and so on. Change bars
highlight new or revised information. For example:
The message types specified in the REPORT clause are different in the COBOL
environment and the Common Run-Time Environment (CRE).
The CRE has many new message types and some new message type codes for
old message types. In the CR E, the messa ge type S Y STEM incl udes all me ssages
except LOGICAL-CLOSE and LOGICAL-OPEN.
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxvii
About This Guide
Change Bar Notation
HP NonStop S-Series Hardware Installation and FastPath Guide —541880-001
xxviii
Loading...
+ 454 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.