g EV Charging StationUser Manual & Installation Instructions
WALL-MOUNT
POLE-MOUNT
PEDESTAL
BACK TO BACK
NEMA EVSE CHARGING STATION
USER MANUAL & INSTALLATION INSTRUCTIONS
GE EV Charging Station User Manual 1 of 86
g EV Charging StationUser Manual & Installation Instructions
CONTENTS
1 Important Safety and Grounding Instructions ................................................................................................................................... 3
1.1 Safety and Compliance ....................................................................................................................................................................... 3
2.1 Before Installing ...................................................................................................................................................................................... 4
2.9.1 RFID .......................................................................................................................................................................................................... 33
2.9.4 Service Door ........................................................................................................................................................................................ 44
3 User Manual ..................................................................................................................................................................................................... 46
3.2 Basic User Instructions..................................................................................................................................................................... 47
3.3 Technical Data ..................................................................................................................................................................................... 51
4.3.2 Prepare Service Laptop or PC ..................................................................................................................................................... 59
4.3.3 EVSE Configuration Server Interface ....................................................................................................................................... 61
4.4 Recommended Network Designs for RFID Authentication ............................................................................................ 67
4.5 Setup without RFID Authentication ............................................................................................................................................ 82
4.6 Reset Controller to Factory Default ............................................................................................................................................ 83
g EV Charging StationUser Manual & Installation Instructions
1 Important Safety and Grounding Instructions
1.1 Safety and Compliance
WARNING:
Read all the instructions before using this product.
This device should be supervised when used around children.
Do not put fingers into the electric vehicle connector.
Do not use this product if the flexible power cord or EV cable are frayed, have broken insulation, or
any other signs of damage.
Do not use this product if the enclosure or the EV connector are broken, cracked, open, or show any
other indication of damage.
This document provides instructions for installation of EV Charging Station products listed in Table 11
in Section 3.3, and should not be used for any other product. Before installing the EVSE (Electric
Vehicle Supply Equipment), you should review this manual carefully and consult with a licensed
contractor, licensed electrician, or trained installation expert to ensure compliance with local building
codes, climate conditions, safety standards and state and local electrical codes.
The EVSE should be installed only by a licensed contractor, and/or a licensed electrician in accordance
with all applicable state, local and national electrical codes and standards. The EVSE should be
inspected by a qualified installer prior to initial use. Under no circumstances will compliance with the
information in this manual relieve the user of his/her responsibility to comply with all applicable codes
or safety standards.
1.2 Grounding Instructions
The EVSE must be connected to a grounded, metal, permanent wiring system, or an equipment
grounding conductor. This should be run with circuit conductors and connected to the equipment
grounding bar or lead on the EVSE. Connections to the EVSE shall comply with all applicable electrical
codes and ordinances.
GE EV Charging Station User Manual 3 of 86
g EV Charging StationUser Manual & Installation Instructions
SCREW SIZE
TORQUE
TORQUE TOL.
6-32 UNC
13 in-lb
+/- 2 in-lb
10-32 UNF
30 in-lb
+/- 5 in-lb
1/4-20 UNC
53 in-lb
+/- 7 in-lb
1/2-13 UNC
48 in-lb
+/- 7 in-lb
M6 x 1 LIGUIDTIGHT FITTING
30 in-lb
+/- 5 in-lb
FUSE BLOCK LUGS, 8 AWG
40 in-lb
+/- 5 in-lb
FUSE BLOCK LUGS, 6 AWG
45 in-lb
+/- 5 in-lb
GROUND TERM. SCREWS, 14-10 AWG
34 in-lb
+/- 5 in-lb
GROUND TERM. SCREWS, 8 AWG
38 in-lb
+/- 5 in-lb
3/4" LOCKNUT
HAND TIGHT + 1/4 TURN
n/a
2 Installation Instruction
2.1 Before Installing
Before any installation work is performed, study all drawings furnished by the supplier for the
particular installation.
These include arrangement drawings (front, end, and plan views), connections to the equipment that
may be required to meet any local codes (such as mats, screens, or railings) is not furnished.
2.2 Safety Requirements
Eye protection with appropriate glasses (especially when using the electrical drill).
In the installation be sure to not connect directly to power distribution network cables without
additional protection.
Ensure that at all times when working, no power is connected.
Use appropriate tools for each function.
2.3 Installation Overview and Specifications
This document describes how to install any EVSE charging station family.
It includes step-by-step instructions for installing the body assembly for the following stations:
To ensure that the EVSE is installed per Americans with Disabilities Act (ADA) Standards for Accessible
Design guidelines, refer to code of federal regulations document 28 CFR Part 36, sections 4.2 (Space
Allowance and Reach Ranges) and 4.4 (Protruding Objects).
EVSE Torque Specification Table
GE EV Charging Station User Manual 4 of 86
- Table 1 -
g EV Charging StationUser Manual & Installation Instructions
Type
Characteristics
Slotted Screwdriver
3/16” or ¼”
Phillips Screwdriver
#2
Socket
Socket sizes: 7/16”, ¾”
Electric Drill
Used in the wall mounted and pole mounted installations
Wire stripper, hammer, and wall anchors
ITEM
DESCRIPTION
QTY
1
Kiosk Pedestal Unit
1
2
Base Mounting Assembly
1
3
Kiosk Skirting
1
4
Base Mounting Template, NEMA 3R
1 5 Hex Nut, ½” SS
12 6 Star Washer, External Tooth, ½” SS
8
WARNING: Make sure power to the EVSE is
disconnected before performing any task
Tools
- Table 2 -
Field cable size: Single Pedestal, Wall Mount and Pole Mount:
Cu:8 AWG, minimum 75 C wire Al: 6 AWG, minimum 75 C wire
Double Pedestal:
Cu: 8 AWG, minimum 90 C wire
Al: 6 AWG, minimum 90 C wire
2.4 Pedestal
Bill of materials
GE EV Charging Station User Manual 5 of 86
- Table 3 -
g EV Charging StationUser Manual & Installation Instructions
Item 5 & 6
Item 1
Item 3
Item 4
Item 2
Procedure
Figure 1: Exploded pedestal base assembly
GE EV Charging Station User Manual 6 of 86
g EV Charging StationUser Manual & Installation Instructions
CONDUIT
MOUNTING TEMPLATE
BASE MOUNTING
CONCRETE
Figure 2
WARNING: Make sure power to the EVSE is
disconnected before performing any task
Figure 3
Locate area for pedestal location.
Install two conduits, one for power, and one for communication (if required). Allow approximately 5”
length for each conduit above the concrete level as shown in Figure 4. Cut as necessary to final
dimensions. Route power conduit and communication conduit through the center of the hole in the
mounting template, appropriately.
Install base mounting assembly plate securely over conduits with mounting template and four 1/2-13
nuts.
GE EV Charging Station User Manual 7 of 86
g EV Charging StationUser Manual & Installation Instructions
Figure 4
5.50
BASE MOUNTING ASSEMBLY – DURING CONCRETE POUR. ALLOW MIN. 5” CONDUIT LENGTH
ABOVE CONCRETE FLOOR LEVEL
Adjust (4) ½-13 nuts to position height as shown in Figure 4.
Pour concrete to level shown in Figure 4. Do not cover the ½-13 nuts with concrete. Remove
mounting template from threaded rods, after concrete has cured. Do not remove the ½-13 nuts as
they are used for leveling the skirt.
GE EV Charging Station User Manual 8 of 86
g EV Charging StationUser Manual & Installation Instructions
½-13 NUT, AND
STAR WASHER
KIOSK
CONDUIT
Figure 5
PEDESTAL SKIRT INSTALLATION, AFTER CONCRETE POUR
Install ½-13 nuts and star washers after lowering skirt over matching threaded rods over the ½-13
nuts. Use the bottom ½-13 nuts for leveling the skirt. Fasten nuts and skirt assembly to concrete
base, as shown in Figure 5. Torque nuts per specification Table 1
GE EV Charging Station User Manual 9 of 86
g EV Charging StationUser Manual & Installation Instructions
½-13 NUT AND ½”
STAR WASHER
CONCRETE LEVEL
Figure 6
Figure 7
Open the door by pressing the round button on the door latch. Insert the Kiosk from top and install ½13 nuts and star washers after lowering skirt over matching threaded rods as shown in the Figures 6
and 7.
Torque all the nuts as per the torque specification in Table 1 (recommended tool: 3/8” drive quick
release ratchet & 13/16 socket).
Connect L1 and L2 to the fuse block and ground wire to the ground bar shown in Figure 8.
IMPORTANT: EV Charging Station is rated for 208-240V power only. The EVSE must be connected to a
grounded, metal, permanent wiring system, or an equipment grounding conductor. This should be run
with circuit conductors and connected to the equipment grounding bar or lead on the EVSE.
Connections to the EVSE shall comply with all applicable electrical codes and ordinances.
In case of RFID sensor, the communication cable is connected to the Ethernet connector on the
controller as shown in Figure 9.
GE EV Charging Station User Manual 10 of 86
g EV Charging StationUser Manual & Installation Instructions
Fuse Block
Incoming Power
Ground Bar
Ground Bar
Fuse Block
Incoming Power Cables
Connect at Bottom
Terminals of Fuse Block
Ground Wire Connects to
Ground Bars
Figure 8 : Power Wire and Ground Wire Connections for Pedestal
GE EV Charging Station User Manual 11 of 86
g EV Charging StationUser Manual & Installation Instructions
ITEM
DESCRIPTION
QTY
1
Kiosk Pedestal Unit
1 2 Base Mounting Assembly
1 3 Kiosk Skirting
1
4
Base Mounting Template,
NEMA 3R
1
5
Hex Nut, ½” SS
12
6
Star Washer, External
Tooth, ½” SS
8
Figure 9 : Ethernet Connection to Controller for Pedestal
2.5 Double Pedestal (Back to Back)
Bill of materials
GE EV Charging Station User Manual 12 of 86
- Table 4 -
g EV Charging StationUser Manual & Installation Instructions
Item 5 & 6
Item 1
Item 3
Item 4
Item 2
Procedure
Figure 10: Exploded double pedestal base assembly
GE EV Charging Station User Manual 13 of 86
g EV Charging StationUser Manual & Installation Instructions
WARNING: Make sure power to the EVSE is
disconnected before performing any task
CONDUIT
MOUNTING TEMPLATE
BASE MOUNTING
CONCRETE
Figure 11
Figure 12
Locate area forpedestallocation
Locate area for double pedestal location.
Install conduits for power wire and communication wire (if required). Allow approximately 5” length for
each conduit above the concrete level as shown in Figure 13. Cut as necessary to final dimensions.
Route power conduit and communication conduit through the center of the hole in the mounting
template, appropriately.
Install base mounting assembly plate securely over conduits with mounting template and four 1/2-13
nuts.
GE EV Charging Station User Manual 14 of 86
g EV Charging StationUser Manual & Installation Instructions
Figure 13
5.50
BASE MOUNTING ASSEMBLY – DURING CONCRETE POUR. ALLOW MIN. 5” CONDUIT LENGTH
ABOVE CONCRETE FLOOR LEVEL
Adjust (4) ½-13 nuts to position height as shown in Figure 13.
Pour concrete to level shown in Figure 13. Do not cover the ½-13 nuts with concrete. Remove
mounting template from threaded rods after concrete has cured. Do not remove ½-13 nuts as they
are used for leveling the skirt.
GE EV Charging Station User Manual 15 of 86
g EV Charging StationUser Manual & Installation Instructions
½-13 NUT, AND
STAR WASHER
KIOSK SKIRT
CONDUIT
Figure 14
DOUBLE PEDESTAL SKIRT INSTALLATION, AFTER
DOUBLE PEDESTAL SKIRT INSTALLATION, AFTER CONCRETE POUR
Install ½-13 nuts and star washers after lowering skirt over matching threaded rods over the ½-13
nuts. Use the bottom ½-13 nuts for leveling the skirt. Fasten nuts and skirt assembly to concrete
base, as shown in Figure 14. Torque nuts per specification Table 1.
GE EV Charging Station User Manual 16 of 86
g EV Charging StationUser Manual & Installation Instructions
CONCRETE
LEVEL
Figure 15
Figure 16
½-13 NUT AND ½”
STAR WASHER
Open the door by pressing the round button on the door latch. Insert the Kiosk from top and install ½13 nuts and star washers after lowering skirt over matching threaded rods as shown in Figures 15
and 16.
Torque all the nuts as per the torque specification in Table 1 (recommended tool: 3/8” drive quick release ratchet and 13/16” socket)
Connect L1 and L2 of circuit 1 and 2 to the fuse block lugs 1 and 2 respectively. Connect ground wire
of circuit 1 and 2 to the ground bar 1 and 2 respectively as shown in Figure 17.
IMPORTANT: EV Charging Station is rated for 208-240V power only. The EVSE must be connected to a
grounded, metal, permanent wiring system, or an equipment grounding conductor. This should be run
with circuit conductors and connected to the equipment grounding bar or lead on the EVSE.
Connections to the EVSE shall comply with all applicable electrical codes and ordinances.
In case of RFID sensor, the communication cable is connected to the Ethernet connector on controller
1 and 2 as shown in Figure 18.
GE EV Charging Station User Manual 17 of 86
g EV Charging StationUser Manual & Installation Instructions
Incoming Power
Ground Bars
Fuse Blocks
Ground Bar 2
Fuse Block 2
Incoming Power Cables
Connect at Bottom
Terminals of Fuse Blocks
Ground Wires Connect to
Ground Bars
Fuse Block 1
Ground Bar 1
Figure 17 : Power Wire and Ground Wire Connections for Double Pedestal
GE EV Charging Station User Manual 18 of 86
g EV Charging StationUser Manual & Installation Instructions
ITEM
DESCRIPTION
CHARACTERISTICS
QTY
1
Kiosk Unit
Wall mounted
enclosure
1
2
Wall Bracket Assembly
(4) ¼”-20 Weld
Stud
1
3
Hex. Nuts ¼”-20
Zinc Plated Steel
4
4
Sealing Washer, ¼” dia.
Seals ¼” studs
4
5
Conduit Hub, ¾”
Attach to ¾”
conduits/enclosure
2
Figure 18: Ethernet Connection to Controller for Double Pedestal
Controller 1
Controller 2
WARNING: Make sure power to the EVSE is
disconnected before performing any task
2.6 Wall-Mounted
Bill of materials
- Table 5 -
Procedure
Drill 6 holes in the wall as illustrated in Figure 19. Use the supplied wall-mounting bracket to ensure
correct alignment. The height of the bottom hole from the floor should be between 19” to 25” to
GE EV Charging Station User Manual 19 of 86
g EV Charging StationUser Manual & Installation Instructions
Figure 19: Wall-Mount Bracket Holes
Figure 20: Wall-Mount Bracket
Min: 19”
Max: 25”
ensure meet UL and American Disability Act compliance. This will ensure the critical height shown in
Figure 21.
IMPORTANT: Exercise extreme caution when drilling holes in the wall. Make sure there are no electrical
cables.
Fasten the wall bracket to the wall. Refer to Table 6 for recommended wall mounting fasteners.
Supply two ¾” conduits (one for power cable and other one for communication cable) as per bracket
drawing dimensions and connect supplied ¾” conduit hubs to conduits. If the communication cable
and the corresponding conduit is not used, cover the hole with supplied NEMA 3R knockout plugs.
Optionally, the power wire can be run through the bottom of the enclosure. See page 24.
GE EV Charging Station User Manual 20 of 86
g EV Charging StationUser Manual & Installation Instructions
MIN: 18”
MAX: 24”
Figure 21: Wall Mount Installation, Critical Dimension
GE EV Charging Station User Manual 21 of 86
g EV Charging StationUser Manual & Installation Instructions
Wall Mount EVSE Mounting Fasteners
Fastener Type
Supplier
Part Number
Qty
Application
Image
3/8" x 1-7/8" Concrete Anchor
McMaster-Carr
96892A258
6
Concrete Wall
Pre-drill hole dia. 3/8"
3/8" x 1-3/4" Concrete Hex Screw
Tapcon
LDT38134
6
Concrete Wall
Pre-drill hole dia. 5/16"
3/8" x 2" Hex Head Lag Bolt
McMaster-Carr
95526A525
3
Stud Wall
Pre-drill hole dia. 3/8" Hardwood
(into wood stud)
Pre-drill hole dia. 1/4" Softwood
Hollow Wall Anchor
Cobra Anchors
TripleGrip
6
Drywall
Pre-drill hole dia. 3/8"
(into sheetrock)
GE EV Charging Station User Manual 22 of 86
- Table 6 –
g EV Charging StationUser Manual & Installation Instructions
WALL-MOUNT UNIT
¼-20 HEX NUT, ¼:
SEALING WASHER
SLEEVE STUD ANCHOR WITH
HEX NUT
WALL-MOUNT BRACKET
¾” CONDUIT HUB
(2) ¾” CONDUITS
The cables must extend 16” to 24” above the wall surface, or according to local codes.
Pull L1, L2 and ground wire into the enclosure assembly through the conduit hub. Similarly pull the
communication cable into the enclosure assembly through the second conduit.
IMPORTANT: EV Charging Station is rated for 208-240V power only. The EVSE must be connected to a
grounded, metal, permanent wiring system, or an equipment grounding conductor. This should be run
with circuit conductors and connected to the equipment grounding bar or lead on the EVSE.
Connections to the EVSE shall comply with all applicable electrical codes and ordinances.
Install the enclosure on the wall-mounting bracket. Insert the threaded portion of the conduit hub into
the hole of the enclosure. Fasten the conduit hub using the nut. Fasten the enclosure to the wallmounting bracket using the self-sealing washers and nuts from inside the enclosure as indicated in
Figure 22.
Torque all the nuts as per the torque specification in Table 1.
Connect L1, L2 to the fuse block and ground wire to the ground bar shown in Figure 23.
GE EV Charging Station User Manual 23 of 86
Figure 22: Wall-Mount Installation, Exploded View
g EV Charging StationUser Manual & Installation Instructions
Ground Bar
Fuse Block
Incoming Power Cables
Connect at Terminals of
Fuse Block
Ground Wire Connects to
Ground Bar
Figure 23: Power Wire and Ground Wire Connections for Wall Mount
In case of RFID sensor, the communication cable is connected to the Ethernet connector on the
controller, just like the pedestal as shown in Figure 9.
Field wiring entry from bottom:
If this option is preferred, remove the two knockouts at the bottom of the enclosure and fill in the
unused cable holes on the back of the enclosure using the spare NEMA 3R knockout plugs provided.
See Figure 24. Assemble the supplied conduit hub in the bottom and make the conduit arrangement.
GE EV Charging Station User Manual 24 of 86
g EV Charging StationUser Manual & Installation Instructions
ITEM
DESCRIPTION
CHARACTERISTICS
QTY
1
Kiosk Unit
Pole-Mounted
1
2
Pole-bracket Assembly
Bracket & ¾” Banding
1
3
Band Clamp
¾” Stainless Steel Clamp
2 4 Hex. Nuts ¼-20
Supplied with EVSE unit
4
5
Sealing Washers, ¼”
Seals ¼” studs
4
6
Conduit Hub, ¾”
Attach to ¾” conduits/enclosure
2
7
Conduit Nipple
(Installer supplied)
¾” pipe size, 1.05”OD, NPTXNPT
threaded both ends Nipple. Example:
Metallic - McMaster Carr part
7727K225 or similar suitable plastic
conduit nipple
g EV Charging StationUser Manual & Installation Instructions
WARNING: Make sure power to the EVSE is
disconnected before performing any task
Figure 25: Pole mount drilling dimension
Procedure
IMPORTANT: Possible pole diameters for these EVSE units are 8” to 12”.
Drill two holes of diameter 1 1/8” on the pole in the location shown in Figure 25. One hole is to bring
the power cables and the other for communication cable into the enclosure. If the communication
cable and the corresponding conduit is not used, cover the hole in the enclosure with the supplied
NEMA 3R knockout plug and do not drill the corresponding hole in the pole. The height of the holes
from the floor should be from 20” to 25” as shown in Figure 25 to meet UL and American Disability Act
compliance. This ensures the critical height shown in Figure 26.
IMPORTANT: Exercise extreme caution when drilling holes in the wall. Make sure there are no electrical
cables.
GE EV Charging Station User Manual 26 of 86
Loading...
+ 60 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.