Introduction
Command Closing Coil:
Command Close coil is used to switch ON the
Power Circuit Breaker remotely. When energized,
it releases the spring charged mechanism thus
ensuring a rapid connection of the main contacts.
The Command Close coil offers an extended
functionality in addition to all the features of the
standard closing coil. Additional connections
allow it to be wired out through the trip unit and
can be accessed electrically through the
communications bus. It also has an extra round
‘ON’ push button that fits onto the breaker front
fascia, which can be locally operated manually to
close the breaker.
Table 1. Catalog Numbers and Ratings
Catalog No DC Voltage AC Voltage
GCCC024DR 24V
GCCC030DR 30V
GCCC048R 48V 48V
GCCC060DR 60-72V
GCCC120R 110-130V 110-130V
GCCC208AR 208V
GCCC240R 220-240V 220-240V
GCCC277R* 250V 250-277V
*Electrical close switch push button cannot be
used with GCCC277R
DEH-41418 Installation Instructions
EntelliGuard
Accessories
Command Closing Coil
®
G Circuit Breaker
WARNING: Before installing any accessories, turn the
breaker OFF, disconnect it from all voltage sources,
and discharge the closing spings.
AVERTISSEMENT: Avant d’installer tout accessoire,
mettre le disjoncteur en position OFF, le déconnecter
de toute tension d’alimentation , et décharger les
resorts d’armement
Inrush Power: 350VA
Steady state : 50VA
Use the following procedure to install the
Command Closing Coil accessory into the circuit
breaker.
1. Verify that the rating on the Command Closing
Coil identification plate matches the voltage
rating required for the application, as listed in
Table 1.
2. Turn the breaker off and discharge the closing
springs by depressing the OFF and ON buttons in
the sequence OFF-ON-OFF. Verify that the
breaker OFF-ON indicator shows OFF on a green
background and that the charge indicator shows
DISCHARGE on a white background. If installing
in a draw-out type breaker remove breaker from
adaptor (cassette) before continuing.
3. Loosen the 6 screws on front cover (fascia)
using a posidrive screw driver as shown in Fig 1.B
Rotate the charging handle down and slide the
front cover over the handle to remove the front
cover as shown in Fig. 1.C.
1

6. Tilt the device backwards until the rear hooks
engage in the slots on the mechanism top
support plate as shown in the Fig. 4.
Figure 1. (A) Front Cover (B) ScrewRemoval (C) Handle
Rotation
4. Place the coil on the mechanism top plate and
assemble the connector marked as CCC from the
Command closing coil to the connector marked
as CCC in the Trip unit harness as shown in Fig. 2.
Figure 2. Plug Assembly
5. Tilt the coil forward and engage the front
hooks into the mechanism top support plate as
shown in the Fig. 3.
Figure 4. Coil Assembly
7. After installing the closing coil on the
mechanism top plate, connect the input wire
assembly plug to the A9- A10-A11 locations
marked on the secondary disconnect as shown in
Fig. 5.
Figure 3. Coil Assembly
Figure 5. Close Coil Plug assembly
8. Ensure the plug is inserted properly by the snap
in the secondary disconnect.
9.
Place the ferrite from the coil assembly behind
the coil. Route the wire from the close coil to the
side of the PMU base for the connection with
Electrical close switch as shown in fig.6.
2

Figure 6. Close Coil wire routing
Installation of Electrical close switch:
10. Slide the switch assembly over the
mechanism side sheet and locate in the two
locating holes as shown in Fig. 7.
Figure 8. Screw assembly
12. Plug the connector from the EC switch
assembly to the connector from the command
closing coil beside the PMU base as shown in
Fig 9.
Figure 7. EC switch assembly
11. Assemble the screw with washer as shown in
Fig. 8. Tighten the screw to torque 1.2N-m (0.9 ftlbs).
Figure 9. Connector plug assembly
Installation of Push button on the fascia:
13. Remove the existing dummy button by
removing the screw as shown in fig 10.
Dummy button
Screw
Figure 10. Connector plug assembly
3

14. Insert the push button and the spring from the
front of the fascia. Assemble them to the fascia
with the screw & washer as shown in fig 11.
Fig 11. Push button assembly
15. To reinstall the cover, rotate the charging
handle down and slide the front cover over the
handle to assemble the front cover to housing as
shown in Fig. 12.
Figure 12.
16. Ensure the fascia is aligned properly with the
trip unit and the pad lock features of the breaker.
17. Fasten the 6 mounting screws of fascia with
the housing using a pozidrive screwdriver. Apply
torque of 6 Nm (4.42ft-lbs).
4

Reference:
Command Closing Coil Connection Scheme:
These instructions do not purport to cover all details or variations in equipment nor, to provide contingency to be met in connection
with installation, operation, or maintenance. Should further information be desired, or should particular problems arise which are not
covered sufficiently for the purchaser’s purposes, the matter should be referred to GE.
GE
41 Woodford Ave, Plainville, CT 06062
www.geelectrical.com
© 2009 General Electric Company
-