Introduction
These instructions describe the installation of TQD three-phase circuit breaker kit into an A-Series® II panelboard. These kits are for use in panelboards ordered with Un-Specified Space. The catalog number for six-pole TQD breaker kit is ASPP6QD6D
Parts List for ASPP6QD6D Table 1.
ITEM # DESCRIPTION PART # QTY
1 BRANCH BASE FOR B PHASE 139C5702BQDG1 1 2 BRANCH BASE FOR A PHASE 139C5702AQDG1 1 3 BRANCH BASE FOR C PHASE 139C5702CQDG1 1 4 (SPOOL) 315A7036P19 6 5 (SCREW-SPOOL) 315A7037P4 6 6 (WASHER-SPOOL) 75A105503P111 6 7 (SCREW-BUS) 315A7034P8 6 8 3P BRACKET 139C5500P81 2
9 SCREW, BKT TO RAIL N667P16008B6 8 10 SCREW, C/B TO BKT N80P150046B6 4 11 FILLER PLATE, TQD 139C5503P64 1 12 SCREWS , #10-32 X 3/8 N722P16006B6 4 13 NUT N210P16B6 6 14 CUP WASHER 254V644P1 4
Installation
WARNING: Before attempting to install one of these kits, remove all power from the
panelboard.
Use the following procedure to install a TQD circuit breaker kit. Call-out numbers in the illustrations and numbers in brackets in the text refer to the Item Numbers in Table 1. Installation of a three-pole kit is illustrated in Figure 1.
1. Remove the interior assembly from its packaging and verify that all parts are present, as given in the parts list.
2. Remove the 8 screws (600A and 800A panels) securing the dead front to panelboard interior. Lift off the dead front and place it and the screws aside.
3. Remove the circuit breaker kit from its packaging and verify that all parts are present, as given in the packing list.
DEH40152 Rev.No.02
1
Page 2
DEH40152
4. Refer Fig.no.1 to mount the breaker on interior. Place branch base for A phase [2] adjacent to crossbar [15] as shown in fig.1 and insert the screw [7] through slot provided to mount it to A phase main busbar. Similarly mount B phase branch base [1] to B phase main busbar adjacent to A phase branch base and C phase branch base [3] to C phase main busbar adjacent to B phase branch base. All phase branch bases should be clamped to main bus using screw [7] with 60 in-lb. Maximum.
Figure 1. Installation of a TQD circuit breaker kit, catalog number ASPP6QD6D, into an A-Series
®
II Panelboards.
5. Mount bracket [8] on the interior rail with two screws [9] with 27-36 in-lb at the location defined.
6. Place the conical washer [6] over the three ¼-28 x 1 3/8 screws [5] and insert the screws through the holes in the top of the circuit breaker. Secure the three spools [4] to the underside of the breaker terminals with the screws [5]. Take care to assemble the screws to the spools as shown in Figure 1, with the tapped end of the spool toward the breaker terminal.
7. Place the breaker assembled with spool over branch bases[1][2][3], align the spool [4] with protruded opening in branch bases and tighten the three ¼-28 X 1
3
/8 screws [5] installed in step 6 to 60 in-lb. Maximum.
DEH40152 Rev.No.02
2
Page 3
DEH40152
8. Insert two screws [10] into the holes in the circuit breaker and tighten to bracket [8] with 18-22 in-lb.
9. Remove the four screws [12] of existing filler plate from dead front where TQD breaker needs to be installed, as illustrated in Figure 2.
Figure 2. Removing the shield inserts from the shield for TQD breaker installation in A–Series® II Panelboards.
10. Place the filler plate [11] over the dead front so that the four same-size holes line up with the threaded holes of the dead front, as illustrated in Figure 3. Fasten filler plate to the dead front with four #10-32 x 3/8 screws [12] tightened to 27-36 in-lb.
11. Reattach the dead front to the interior with the 8 screws removed in step 2. Tighten the screws to 27-36 in-lb.
DEH40152 Rev.No.02
3
Page 4
DEH40152
Figure 3. Attaching the shield insert to the shield for TQD breaker installation in A-Series® II Panelboards.
12. If TQD breaker has to be installed after SG or SF/TFJ as shown in Figure 4 then gap between the breakers (dim A) has to be followed as mentioned in Table 2. Replace the subsequent blank filler of dead front with TQD filler plate given in kit ASPP6QD6D using steps 9 to 11.
13. If TQD breaker has to installed immediate after crossbar as shown in Figure 5 then gap between the breaker and crossbar has to be 0.0525inch.
DEH40152 Rev.No.02
4
Page 5
Figure 4. Distance between breakers
Gap with Breaker SG 0.582 SF/TFJ 1.875
A (in)
Table 2. Distance between breakers.
DEH40152
DEH40152 Rev.No.02
5
Page 6
DEH40152
Figure 5 Distance between the Crossbar and TQD breaker
These instructions do not cover all details or variations in equipment nor do they provide for every possible contingency that may be met in connection with installation, operation, or maintenance. Should further information be desired or should particular problems arise that are not covered sufficiently for the purchaser’s purposes, the matter should be referred to the GE Company.