Emerson 610 User Manual

Liebert Series 610™ UPS
Installation Manual - 1000kVA, 60Hz, Three Phase Single-Module
AC Power For Business-Critical Continuity™

BATTERY CABINET PRECAUTIONS

Important Safety Instructions—page 1
Section 2.0 - Unloading and Handling
Section 5.0 - Battery Installation
WARNING
!
Internal battery strapping must be verified by manufacturer prior to moving a battery cabinet (after initial installation).
• Battery cabinets contain non-spillable batteries.
• Keep units upright.
• Do not stack.
• Do not tilt. Failure to heed this warning could result in smoke, fire or electric hazard.
Call 1-800-LIEBERT prior to moving battery cabinets (after initial installation).

CONTACTING LIEBERT FOR SUPPORT

To contact Liebert Global Services for information or repair service in the United States, call 1-800-LIEBERT (1-800-543-2378). Liebert Global Services offers a complete range of start-up services, repair services, preventive maintenance plans and service contracts.
For repair or maintenance service outside the 48 contiguous United States, contact Liebert Global Services, if available in your area. For areas not covered by Liebert Global Services, the autho­rized distributor is responsible for providing qualified, factory-authorized service.
For LGS to assist you promptly, please have the following information available:
Part numbers: _________________________________________________________________ Serial numbers:________________________________________________________________ Rating: _______________________________________________________________________ Date purchased: _______________________________________________________________ Date installed:_________________________________________________________________ Location:______________________________________________________________________ Input voltage/frequency:________________________________________________________ Output voltage/frequency: ______________________________________________________ Battery reserve time:___________________________________________________________
TABLE OF CONTENTS
BATTERY CABINET PRECAUTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INSIDE FRONT COVER
CONTACTING LIEBERT FOR SUPPORT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INSIDE FRONT COVER
IMPORTANT SAFETY INSTRUCTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.0 I
NSTALLATION CONSIDERATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.0 UNLOADING AND HANDLING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.0 INSPECTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
3.1 External Inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
3.2 Internal Inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.0 EQUIPMENT LOCATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
5.0 BATTERY INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8
5.1 Battery Safety Precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.2 Battery Safety Precautions in French Per CSA Requirements . . . . . . . . . . . . . . . . . . . . . . . . 9
5.3 Battery Cabinets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
5.4 Open-Rack Batteries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
6.0 CONFIGURING YOUR NEUTRAL AND GROUND CONNECTIONS . . . . . . . . . . . . . . . . . . . . . . .12
6.1 Preferred Grounding Configuration, Wye-Connected Service. . . . . . . . . . . . . . . . . . . . . . . . 13
6.2 Alternate Grounding Configuration, Wye-Connected Service. . . . . . . . . . . . . . . . . . . . . . . . 14
6.3 Preferred Grounding Configuration With Isolated Bypass . . . . . . . . . . . . . . . . . . . . . . . . . . 15
6.4 Alternate Grounding Configuration, Non-Isolated. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
6.5 Grounding Configuration, Corner-Grounded Delta or Impedance-Grounded Wye . . . . . . . 17
6.6 Preferred Grounding Configuration, Battery Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
7.0 WIRING CONSIDERATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
7.1 Power Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
7.2 Control Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
7.3 Battery Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
8.0 WIRING CONNECTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24
8.1 Specific Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
9.0 WIRING INSPECTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .26
10.0 INSTALLATION DRAWINGS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
A
PPENDIX A-SITE PLANNING DATA, 1000KVA, SINGLE-MODULE SYSTEMS . . . . . . . . . . . . . . . . 43
i
FIGURES
Figure 1 Preferred grounding configuration, wye-connected service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Figure 2 Alternate grounding configuration, wye-connected service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Figure 3 Preferred grounding configuration with isolated bypass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Figure 4 Alternate grounding configuration, non-isolated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Figure 5 Grounding configuration, corner-grounded delta . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Figure 6 Grounding configuration, impedance-grounded wye . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Figure 7 Preferred battery cabinet grounding configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Figure 8 Power single-line diagrams*. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Figure 9 Outline drawing, 1000kVA, front-access Single-Module UPS, 480V and 600V . . . . . . . . . . . . . . 29
Figure 10 Bussing details, 1000kVA, front-access Single-Module UPS, 480V and 600V . . . . . . . . . . . . . . . 30
Figure 11 Base mounting details, 1000kVA, Single- and Multi-Module rectifier and inverter sections . . . 31
Figure 12 Base mounting details, 1000kVA, Single- and Multi-Module control section . . . . . . . . . . . . . . . . 32
Figure 13 Shipping split detail, 1000kVA, Single- and Multi-Module UPS. . . . . . . . . . . . . . . . . . . . . . . . . . 33
Figure 14 Control connection location diagram, Single-Module system, 1000kVA . . . . . . . . . . . . . . . . . . . . 34
Figure 15 Wiring diagrams, Single-Module System, interconnect diagram. . . . . . . . . . . . . . . . . . . . . . . . . . 35
Figure 16 Control wire list, Single-Module System, external interconnection, Part 1 . . . . . . . . . . . . . . . . . 36
Figure 17 Control wire list, Single-Module System, external interconnection, Part 2 . . . . . . . . . . . . . . . . . 37
Figure 18 Control wire list, Single-Module System, external interconnection, optional internal modem . . 38 Figure 19 Control wire list, Single- and Multi-Module System, external interconnection,
optional battery temperature sensor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Figure 20 Control wire list, Single-Module System, external interconnection,
optional customer alarm interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
Figure 21 Outline drawing, single-breaker module battery disconnect,
1400AT/1600AT/2000AT/2500AT, 600VDC circuit breaker . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
Figure 22 Outline drawing, remote status panel, surface mount . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
TABLES
Table 1 Abbreviations for circuit breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Table 2 Power wiring terminals - factory supplied . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Table 3 Torque specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Table 4 Field-supplied lugs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Table 5 Table 310-16, National Electrical Code (Reprint) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Table 6 Site planning data—480V input. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Table 7 Site planning data—600V input. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
ii

IMPORTANT SAFETY INSTRUCTIONS

SAVE THESE INSTRUCTIONS
This manual contains important instructions that should be followed during installation of your Series 610 UPS and batteries.
WARNING
!
Exercise extreme care when handling UPS cabinets to avoid equipment damage or injury to personnel. The UPS module weight ranges from 16,700 to 17,550 lbs. (7575 to 7961kg), including input transformer. The battery cabinets weigh from 3060 to 5300 lbs. (1388 to 2404kg).
Locate center of gravity symbols and determine unit weight before handling each cabinet. Test lift and balance the cabinets before transporting. Maintain minimum tilt from vertical at all times.
Slots at the base of the modules and battery cabinets are intended for forklift use. Base slots will support the unit only if the forks are completely beneath the unit.
Follow all battery safety precautions when installing, charging or servicing batteries. In addition to the hazard of electric shock, gas produced by batteries can be explosive and sulfuric acid can cause severe burns.
In case of fire involving electrical equipment, use only carbon dioxide fire extinguishers or those approved for use in fighting electrical fires.
Extreme caution is required when performing maintenance. Be constantly aware that the UPS system contains high DC as well as AC voltages. Check for voltage with both AC and DC voltmeters prior to making contact.
Read this manual thoroughly, paying special attention to the sections that apply to your installation, before working with the UPS. Retain this manual for use by installing personnel.
WARNING
!
Under typical operation and with all UPS doors closed, only normal safety precautions are necessary. The area around the UPS system should be kept free of puddles of water, excess moisture and debris.
Special safety precautions are required for procedures involving handling, installation and maintenance of the UPS system and the battery. Observe all safety precautions in this manual before handling or installing the UPS system. Observe all precautions in the Operation and Maintenance Manual, before as well as during performance of all maintenance procedures. Observe all battery safety precautions before working on or near the battery.
This equipment contains several circuits that are energized with high voltage. Only test equipment designed for troubleshooting should be used. This is particularly true for oscilloscopes. Always check with an AC and DC voltmeter to ensure safety before making contact or using tools. Even when the power is turned Off, dangerously high potential electric charges may exist at the capacitor banks and at the batteries.
All power and control wiring should be installed by a qualified electrician. All power and control wiring must comply with the NEC and applicable local codes.
ONLY qualified service personnel should perform maintenance on the UPS system. When performing maintenance with any part of the equipment under power, service personnel and test equipment should be standing on rubber mats. The service personnel should wear insulating shoes for isolation from direct contact with the floor (earth ground).
One person should never work alone, even if all power is removed from the equipment. A second person should be standing by to assist and summon help in case an accident should occur.
1
CAUTION
!
This unit complies with the limits for a Class A digital device, pursuant to Part 15 Subpart J of the FCC rules and EN550022. These limits provide reasonable protection against harmful interference in a commercial environment. This unit generates, uses and radiates radio frequency energy and, if not installed and used in accordance with this instruction manual, may cause harmful interference to radio communications. Operation of this unit in a residential area may cause harmful interference that the user must correct at his own expense.
NOTE
Liebert Corporation neither recommends nor knowingly sells this product for use with life support or other FDA-designated “critical” devices.
2

1.0 INSTALLATION CONSIDERATIONS

Install your Series 610 UPS in accordance with the submittal drawing package and the following pro­cedures.
A Liebert authorized representative must perform the initial system check-out and start-up to ensure proper system operation. Equipment warranties will be voided unless system start-up is performed by a Liebert authorized representative. Contact your local Liebert sales representative or Liebert Global Services at 1-800-LIEBERT to arrange for system start-up.
CAUTION
!
Read this manual thoroughly before attempting to wire or operate the unit. Improper installation is the most significant cause of UPS start-up problems.
Do not install this equipment near gas or electric heaters. It is preferable to install the UPS in a restricted location to prevent access by unauthorized personnel.
1. Proper planning will speed unloading, location and connection of the UPS. Refer to Figures 9 through 22 and Appendix A.
2. Be certain that the floor at the final equipment location and along the route (inside the facility) to the installation site can support the cabinet weight and the weight of any moving equipment. The UPS modules can weigh from 16,700 to 17,550 lbs. (7575 to 7961kg). The battery cabinets weigh from 3060 to 5300 lbs. (1388 to 2404kg) each. Refer to Appendix A.
WARNING
!
Locate center of gravity symbols and determine unit weight before handling cabinet.
3. Plan the route to ensure that the unit can move through all aisleways and doorways and around corners without risking damage. If the modules and batteries must be moved by elevator, check the size of the door openings and the weight-carrying capacity of the elevator.
4. Refer to information later in this manual regarding the optional battery cabinet(s), Maintenance Bypass Cabinet and Transformer Cabinet. Observe all battery safety precautions when
working on or near the battery.
5. Use the shortest output distribution cable runs possible, consistent with logical equipment arrangements and with allowances for future additions if planned.
6. Recommended ambient operating temperature is 77°F (25°C). Relative humidity must be less than 95%, non-condensing. Note that room ventilation is necessary, but air conditioning may not be required. Maximum ambient operating temperature is 104°F (40°C) without derating. The batteries should not exceed 77°F (25°C). At elevations above 4000 ft. (1219m), temperature derating may be required for full power output—consult your Liebert sales representative or call 1-800-LIEBERT.
7. Even though your Liebert UPS unit is 92 to 94% efficient, the heat output is substantial. For more specific information, see Appendix A. Be sure environmental conditioning systems can accommodate this BTU load, even during utility outages.
8. The installer should attempt to balance the load between the three output phases. The UPS will operate safely with an unbalanced load, but will give optimum performance if the three output phases are loaded within 20 percent of each other.
9. During normal UPS operations, short-term overload current demand from the bypass source may reach 10x the UPS output current rating. This overload current demand may be caused by the magnetizing inrush current of one or more downstream transformers or faults on downstream branch circuits. The instantaneous trip point(s) of the upstream bypass feeder breaker(s) must be set to support these temporary overloads. The magnitude of short-term overload bypass current demand is typically six to eight times the UPS current rating, but must be determined by analysis on a per-site basis. This analysis, generally known as an End-to-End Fault Coordination Study, must be done by a Registered Professional Engineer experienced in this activity and familiar with local codes and related requirements.
NOTE
While Liebert can provide typical guidelines, the responsibility for the proper breaker trip settings outside of the Liebert-manufactured UPS equipment resides with the owner. Contact Liebert Global Services at 1-800-LIEBERT for further details.
Installation Considerations
3
Installation Considerations
10. A breaker coordination study should be performed to ensure proper handling of fault currents.
NOTE
The instantaneous trip setting of the breaker feeding the UPS bypass input should be high enough to accommodate short-duration overloads. The bypass static switch inside the UPS can draw up to 10 times the system’s rated current for up to three cycles.
4

2.0 UNLOADING AND HANDLING

UPS modules are shipped in split cabinets to allow ease of handling. Because the weight distribution in the cabinets is uneven, use extreme care during handling and transport. Your installation may also include battery cabinets and a System Control Cabinet.
WARNING
!
Exercise extreme care when handling UPS cabinets to avoid equipment damage or injury to personnel. The UPS module weight ranges from 16,700 to 17,550 lbs. (7575 to 7961kg). Battery cabinets weigh from 3060 to 5300 lbs. (1388 to 2404kg).
Locate center of gravity symbols before handling cabinet. Test lift and balance the cabinet before transporting. Maintain minimum tilt from vertical at all times.
Slots at the base of the unit and battery cabinets are intended for forklift use. Base slots will support the unit only if the forks are completely beneath the unit.
To reduce the possibility of shipping damage, cabinets are shored with 2x4 bracing, secured with screw-type nails. This shoring must be carefully removed prior to unloading.
CAUTION
!
Extreme care is necessary when removing shoring braces. Do not strike cabinet with hammers or other tools.
Unloading and Handling
5

3.0 INSPECTIONS

3.1 External Inspections

1. While the UPS system is still on the truck, inspect the equipment and shipping container(s) for any signs of damage or mishandling. Do not attempt to install the system if damage is apparent. If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact Liebert Global Services at 1-800-LIEBERT to inform them of the damage claim and the condition of the equipment.
2. Locate the bag containing the keys for the front access door. The bag is attached to the cabinet.
3. Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and to Liebert Global Services immediately.
4. Check the nameplate on the cabinet to verify that the model number corresponds with the one specified. Record the model number and serial number in the front of this installation manual. A record of this information is necessary should servicing become required.

3.2 Internal Inspections

1. Verify that all items have been received.
2. If spare parts were ordered, verify arrival.
3. Open doors and remove cabinet panels to check for shipping damage to internal components.
4. Check for loose connections or unsecured components in the cabinet(s).
5. Check for installation of circuit breaker line safety shields. There should be no exposed circuit breaker terminals when the cabinet doors are opened.
6. Check for any unsafe condition that may be a potential safety hazard.
7. UPS modules are shipped with internally mounted shipping brackets. The shipping brackets (painted orange) must be removed from the rear (remove rear panels). The installer must remove the orange shipping brackets before final equipment placement, particularly if rear access will be restricted.
Inspections
CAUTION
!
Failure to remove orange shipping brackets from transformers may cause restricted airflow within the UPS. This could cause overheating or reduction of UPS capacity. In some cases, it could cause damage to the UPS module, and such damage would not be covered under the factory warranty. If you foresee a situation where the UPS will be relocated in the near future, the brackets should be removed and stored elsewhere until they are needed.
6

4.0 EQUIPMENT LOCATION

1. Handle cabinet(s) in accordance with the safety precautions in this manual, especially in these sections:
Battery Cabinet Precautions—inside front cover
Important Safety Instructions—page 1
2.0 - Unloading and Handling—page 5
5.0 - Battery Installation—page 8
Use a suitable material handling device to move cabinet to its final location. Exercise extreme care because of the uneven weight distribution. Carefully lower the cabinet to the floor.
2. Verify that the UPS system is installed in a clean, cool and dry location.
3. Installation and serviceability will be easier if adequate access is provided on all sides of the equipment, but only front access is required.
a. Verify that there is adequate clearance to open cabinet doors—4 ft. (1.2m) is recommended.
NEC requires sufficient clearance in front of the equipment to fully open all doors without restriction. See drawings and local codes.
b. Verify that there is adequate area in front of circuit breakers to perform maintenance. Check
installation drawings for location of breakers. Check with local codes.
c. Verify that there is adequate clearance above all cabinets to allow exhaust air to flow without
restriction. The minimum clearance is 2 ft. (0.6m), unobstructed by conduit or any other items. Liebert recommends against using top-feed air conditioning systems.
4. Align the UPS cabinet, battery cabinets (if used) and optional transformer and maintenance bypass cabinets, as shown in the Outline Drawing (Figure 9) and your submittal package.
5. Connect the cabinets, internal cables and busbars, if applicable. Internal control connections should be left disconnected for later installation by Liebert LGS Customer Engineers.
Equipment Location
7

5.0 BATTERY INSTALLATION

5.1 Battery Safety Precautions

Servicing of batteries should be performed or supervised by personnel knowledgeable of batteries and the required precautions. Keep unauthorized personnel away from batteries.
Be sure to observe the grounding recommendations in 6.0 - Configuring Your Neutral and Ground Connections when installing batteries. When replacing batteries, use the same number and type of batteries.
CAUTION
!
Lead-acid batteries contain hazardous materials. Batteries must be handled, transported and recycled or discarded in accordance with federal, state and local regulations. Because lead is a toxic substance, lead-acid batteries must be recycled rather than discarded.
Do not open or mutilate the battery or batteries. Released electrolyte is harmful to the skin and eyes. It is toxic. Do not dispose of battery or batteries in a fire. The battery may explode.
Do not install any batteries that are cracked, leaking or show other signs of damage. Contact Liebert Global Services or your local Liebert representative.
A battery can present a risk of electrical shock and high short circuit current. The following precautions should be observed when working on batteries:
Battery Installation
• Remove watches, rings and other metal objects.
• Use tools with insulated handles.
• Wear rubber gloves and boots.
• Do not lay tools or metal parts on top of batteries.
• Disconnect charging source prior to connecting or disconnecting battery terminals.
• Determine if battery is inadvertently grounded. If inadvertently grounded, remove source of ground. Contact with any part of a grounded battery can result in electrical shock. The likelihood of such shock will be reduced if such grounds are removed during installation and maintenance.
Lead-acid batteries can present a risk of fire because they generate hydrogen gas. The following procedures should be followed:
• DO NOT SMOKE when near batteries.
• DO NOT cause flame or spark in battery area.
• Discharge static electricity from body before touching batteries by first touching a grounded metal surface.
• After replacing battery jars in a battery cabinet, replace the retaining straps that hold the jars in place on the shelves. This will limit accidental movement of the jars and connectors should the cabinet ever need to be repositioned or relocated. Regular maintenance of the battery module is an absolute necessity. Periodic inspections of battery and terminal volt­ages, specific gravity and connection resistance should be made. Strictly follow the proce­dures outlined in the battery manufacturer’s manual, available on the manufacturer’s Web site.
8

5.2 Battery Safety Precautions in French Per CSA Requirements

Instructions Importantes Concernant La Sécurité Conserver Ces Instructions

AVERTISSEMENT
!
Respecter toutes les consignes de sécurité applicables à l'installation, le chargement ou l'entretien des batteries. En plus du danger de chocs électriques, le gaz produit par les batteries peut exploser dégageant de l'acide sulfurique qui peut entraîner de très graves brûlures.
Toute opération d'entretien/réparation des batteries doit être exécutée ou supervisée par un personnel qualifié dans le domaine et en prenant toutes les précautions nécessaires. Tenir le personnel non autorisé à l’écart des batteries.
ATTENTION
!
Les batteries acide-plomb contiennent des substances toxiques dangereuses. Les batteries doivent être manipulées, transportées et recyclées ou jetées conformément à la réglementation en vigueur aux niveaux national et local. Le plomb étant toxique, les batteries acide-plomb doivent être recyclées et non jetées.
Ne pas ouvrir ni endommager la ou les batteries. Les électrolytes diffusés sont dangereux pour la peau et les yeux. Ils sont toxiques. Ne pas jeter la ou les batteries dans le feu. Risque d'explosion.
Ne jamais installer de batteries avec des cellules fissurées ou endommagées. Contacter Liebert Global Services ou le représentant agréé Liebert local.
Une batterie peut poser un risque de choc électrique et de courant élevé provoqué par un court-circuit. Respecter les précautions suivantes lors de travaux sur les batteries :
• Enlever montres, bagues ou autres objets métalliques.
• Utiliser des outils dont les poignées sont isolées.
• Porter des gants et des bottes en caoutchouc.
• Ne pas poser d'outils ou d'objets métalliques sur les batteries.
• Déconnecter la source de chargement avant de connecter ou de déconnecter les bornes de batterie.
• Vérifier que la batterie n'a pas été mise à la masse par inadvertance. Si elle est mise à la masse, éliminer la source de masse. Tout contact avec des composants de batterie mise à la masse peut entraîner un choc électrique. Éliminer le risque de chocs électriques potentiels en retirant les sources de masse avant l'installation et la maintenance.
Les batteries acide-plomb peuvent représenter un risque d'incendie puisqu'elles génèrent de l'hydrogène. Respecter les procédures suivantes :
• NE PAS FUMER près des batteries.
• NE PAS générer de flammes ou d'étincelles près des batteries.
• Éliminer l'électricité statique du corps avant de manipuler les batteries en touchant d'abord une surface métallique mise à la terre.
L’électrolyte est un acide sulfurique dilué qui est dangereux au contact de la peau et des yeux. Ce produit est corrosif et aussi conducteur electrique. Les procédures suivantes devront être observées :
• Porter toujours des vêtements protecteurs ainsi que des lunettes de protection pour les yeux.
• Si l’électrolyte entre en contact avec la peau, nettoyer immédiatement en rincant avec de l’eau.
• Si l’électrolyte entre en contact avec les yeux, arroser immédiatement et généreusement avec de l’eau. Demander pour de l’aide médicale.
• Lorsque l’électrolyte est renversée, la surface affectée devrait être nettoyée en utilisant un agent neutralisant adéquat. Une pratique courante est d’utiliser un mélange d’approxima­tivement une livre (500 grammes) de bicarbonate de soude dans approximativement un gal­lon (4 litres) d’eau. Le mélange de bicarbonate de soude devra être ajouté jusqu’à ce qu’il n’y ait plus apparence de réaction (mousse). Le liquide résiduel devra être nettoyé à l’eau et la surface concernée devra être asséchée.
Battery Installation
9

5.3 Battery Cabinets

Optional battery cabinets are available from Liebert and other qualified vendors. Consult your sub­mittal package for details.
Several models of optional battery cabinets with varying run times are available. Each model is 78" (1981mm) high and has forklift slots. Refer to the Battery Cabinet submittal drawings if a battery cabinet is to be used. The battery cabinet cells range from 90 to 150 ampere-hours. The same model battery cabinet may be paralleled in multiple cabinet strings for additional capacity. Battery capacity (in minutes) at your installation will depend on cabinet model, number of cabinets, and amount of critical load on the UPS.
1. Handling. The battery cabinet weighs from 3060 to 5300 lbs. (1388 to 2404kg). Forklift slots are provided for ease of handling.
2. Cabinet Inspection. Remove all panels and visually inspect the batteries, bus connections, and cabinet for any damage. If any foam blocks were placed between shelves to restrain movement during shipment, remove them now. Exercise caution—voltage is present within the battery cabinet even before installation. If there are signs of damage, do not proceed. Call Liebert Global Services at 1-800-LIEBERT.
3. Battery Storage. The batteries used in the battery cabinet retain their charge well. The batteries can be stored indoors in a temperature-controlled environment, for up to six months without any appreciable deterioration. Self-discharge rate of the batteries is approximately 3% per month when the batteries are stored in temperatures of 59°F to 77°F (15-25°C). If the battery cabinet must be stored for longer than six months, contact Liebert Global Services. The battery cabinet should never be stored outdoors or on a loading dock.
4. Installation. The battery cabinet(s) can be located conveniently next to the UPS module. The front-access-only-design eliminates side and rear service clearance requirements.
5. Reinstallation. If at any time it becomes necessary to move the battery cabinet to another location, contact Liebert Global Services to inspect the internal battery hold-down straps.
6. Environment. Locate the battery cabinet in a clean, dry environment. Recommended temperature range for optimum performance and lifetime is 68°F to 77°F (20-25°C).
7. Service Clearance. Allow front access to the battery cabinet at all times for maintenance and servicing. Electrical codes require that the battery cabinet be installed with no less than 3 ft. (1m) of clearance at the front of the cabinet when operating. Side and rear panels do not require service clearance.
8. Side Panels. To connect battery cabinets together, remove the protective side panels by removing the retaining screws that hold the side panels in place.
9. Cables. Multiple battery cabinets may be bolted together in a daisy-chain configuration. Cables for this setup may be run between paralleled battery cabinets through cutouts in the top of the cabinets, eliminating the need for external conduit runs. Route cables before moving cabinets into final position for bolting together. Low voltage control wiring must be kept separate from the power wiring. Remove top panels for access. No top or bottom entry cables are required, except for remotely located cabinets, which require conduits. Refer to your submittal drawings for instructions on wiring cabinets in parallel.
Battery Installation
NOTE
The 1000kVA UPS module is approximately 2 to 6 in. (51-152mm) deeper than the battery cabinet and is not designed to bolt directly to it.
10.
Grounding. The battery cabinets have ground studs near the busbar connections. Use an equipment grounding conductor to connect the lugs of the cabinets together and to connect the cabinets to the ground busbar in the UPS module.
10

5.4 Open-Rack Batteries

When batteries other than Liebert battery cabinets are used, a remote battery disconnect switch with overcurrent protection is required per the National Electrical Code. Refer to Required Battery Discon­nect Rating in the site planning data tables in Appendix A for recommended overcurrent protection ratings. Contact your Liebert sales representative for more information.
1. Install battery racks/cabinets and batteries per manufacturer’s installation and maintenance instructions.
2. Verify battery area has adequate ventilation and battery operating temperature complies with manufacturer’s specification. Installations using vented lead-acid batteries MUST have adequate ventilation to remove explosive gases per local and national codes.
3. Low voltage control wiring must be kept separate from power wiring and run in separate conduits.
4. Ensure that battery racks are properly grounded according to code requirements in your area.
If you have any questions concerning batteries, battery racks or accessories, contact your local sales representative or Liebert Global Services at 1-800-LIEBERT.
CAUTION
!
Cables between batteries and the UPS should be run in matched pairs, positive-with-negative, within each conduit or cable run. Grouping like-polarity cables together (i.e., positive-with-positive and negative-with-negative) can cause stress or damage to the cables, conduit or buswork.
Battery Installation
11
Configuring Your Neutral and Ground Connections

6.0 CONFIGURING YOUR NEUTRAL AND GROUND CONNECTIONS

Improper grounding is the largest single cause of UPS installation and start-up problems. This is not an easy subject, since grounding techniques vary significantly from site to site, depending on several factors. The questions you should ask are:
• What is the configuration of the input power source? Most of the recommended schemes for UPS grounding require grounded-wye service. The UPS system requires a bypass neutral for sensing and monitoring the quality of the bypass input. If the building service is ungrounded delta or cor­ner-grounded delta, contact your Liebert representative for details about Isolated Neutral kits.
A Power-Tie or distributed redundant system has different grounding requirements from stand­alone UPS modules. If using one of those systems, refer to Liebert’s Power-Tie configuration user manual, SL-30030.
• Does the system have a bypass isolation transformer? Systems with 480 VAC (or 600 VAC) input and 208 VAC output require a bypass isolation transformer. In some cases, it may be necessary to treat that transformer as a “separately derived source” with its own grounding electrode.
• What are the UPS input and output voltages? Systems with 480 VAC input and output have sig­nificantly different needs from systems with 480/208 VAC or 208/208 VAC.
• What is the connected load? Does the critical load consist of one or more Power Distribution Units (PDUs)? Do the PDUs have isolation transformers?
Proper grounding should be based on NEC Section 250, but safe and proper equipment operation requires further enhancements. The following pages detail Liebert’s recommendations for grounding various system configurations to ensure optimal UPS system performance.
NOTE
Some UPS modules are equipped with input isolation transformers. However, these transformers have no effect upon any system grounding considerations. These modules will be grounded exactly as shown in Figures 1 through 7.
CAUTION
!
The UPS ground lug must be solidly connected to the service entrance ground by an appropriately sized wire conductor per NEC Article 250. Each conduit or raceway containing phase conductors must also contain a ground wire, both for UPS input and output, which are solidly connected to the ground terminal at each termination point. Conduit-based grounding systems tend to degrade over time. Therefore, using conduit as a grounding conductor for UPS applications may degrade UPS performance and cause improper UPS operation.
12