Legrand ALTP-2 User Manual

ALTP-2, ALTC-2 Series Pole
INSTALLATION INSTRUCTIONS
Installation Instruction No.: 42510R1 – Updated May 2004
Wiremold Electrical Systems conform to and should be installed and properly grounded in compliance with requirements of the current National Electrical Code, Canadian Electrical Code or codes administered by local authorities.
All electrical products may represent possible shock or fire hazard if improperly installed or used. Wiremold electrical products are UL Listed to U.S. and Canadian safety standards, made for interior use only, and should be installed in conformance with current local and/or the National Electrical Code.
Step 1 Remove ceiling tile at the poles
intended location. Position T-Bar Bracket as shown and secure by tightening clamping wing nut. Brace the bracket with a firmly anchored 3/8" drop rod or equal.
Step 2 Secure foot to floor. For carpeted
floors, install the carpet gripper to the bottom of foot and set in place. For hard floors, either use either double-sided tape or screws to attach to the floor.
Step 3 Place bottom of pole into
foot and loosely hold top of pole to the T-Bar Bracket with the U Bolt.
ALTP-2 INSTALLATION:
Step 4A Provide suitable power supply through KO into
entrance end fitting. Connect feed wires to leads provided and install cover.
Step 5A If communication cables are to be installed, feed
through the opening in top of pole. Unsnap pole cover as required to allow routing of cables. Cables may exit through the KO provided, or through openings created in the field. Close the pole cover and tighten T-Bar Bracket U Bolt.
Step 6A Replace ceiling tile
after carefully cutting a 3" [76mm] hole for pole. Install the trim plates to complete the installation.
ALTC-2 INSTALLATION:
Step 4B To install communication cables, feed through
the opening at the top of the pole. Unsnap pole cover as required to allow routing of cables. Cables may exit through the KO provided or through opening created in the file. Close pole cover and tighten T-Bar Bracket U Bolt.
Step 5B Replace ceiling tile after carefully cutting a
3" [76mm] hole for pole. Install the trim plates to complete the installation.
Drop Rod
T-Bar
Bracket
T-Bar
Foot
Assembly
Hard Floor
Carpet Gripper
U Bolt
Drop Rod
T-Bar
Bracket
U Bolt
Ceiling
Tile
Trim Plate
Pole Cover
End
Fitting
End Fitting
Cover
Drop Rod
T-Bar
Bracket
U Bolt
Ceiling
Tile
Trim Plate
Pole Cover
INSTALLATION:
The Wiremold Company
U.S. and International: 60 Woodlawn Street • West Hartford, CT 06110 1-800-621-0049 • FAX 860-232-2062 • Outside U.S.: 860-233-6251 Canada: 850 Gartshore Street • Fergus, Ontario N1M 2W8 1-800-741-7957 • FAX 519-843-5980
42510R1 – Updated May 2004 – For latest specs visit www.wiremold.com
© Copyright 2004 The Wiremold Company All Rights Reserved
Step 1 Remove cover. Remove clamps
that hold in wireway. Withdraw wireway from pole – do not remove entrance end fitting.
Step 2 Determine length “A” to be
removed from pole. Fold wires back and cut length “A” from shown ends of cover, base, and wireway.
Step 3 To re-assemble – Replace
wireway into the base with conductors inside. Replace and tighten down clamps. Snap cover onto pole.
Cover
Wireway
Base
Clamp
Length
“A”
Clamp
Entrance
End Fitting
TO SHORTEN ALTP POWER POLE BEFORE INSTALLATION:
Length
“A”
Length
“A”
NOTE: Tele-Power Pole must extend above hanger
clamp with Pole stanchion resting on floor.