Tuesday 29 o£ Sep 1998. Faxination ->5123390477 Page 3 o£
Installation Procedures
I Remove line power from both appliances before
starting installation of the twinning kit.
2 Locale the Zl and Z2 connectic^s along one edge of
each control (see Figure 1). The demgnalions are
printed on top of the circuit board, and a black bar
shows the correct orientation of the metal body which
will be pust_ed in to make connection.
3 Remove furnace casing hole plugs and route the
[winning leads through bushings provided as required,
and lengthen if necessary by splicing. Be sure to
observe the polarity required so as lo match Z1 to Z1
and Z2 to Z2 (see Figure 2).
4. Push the terminal into the slot on the circuit board
edge. Be sure to align the body with the black bar to
line up the solder finger below the circuit board (see
Figure 1). The terminal will "bite into" the solder and
make the necessary connection. Repeat for each end
of both wires.
5 Locale and mount the isolation relay in the circulating
blower compartment on the same panel as the
electronic fen control in furnace #1 (see Figure 1).
6, Refer to single stage or two stage thermostat wiring as
noted below.
Single Stage Thermostat Operation
Reference Figure 3
1 Interconnect the thermostat wiring in parallel from the
thermostat to the terminaJ blocks on each fan control.
for the "G" and '+Y"connections only Interconnect the
winng from the "C" connections at the terminal blocks
on each fan control. Note: The "Y" connection ls not
required if air conditloning is not available.
2. Connect wire from "W" connection at the thermostat to
the "W" connection of the electronic fan control of
furnace #1
3 Connect wire from "R" connection at the thermoslat to
the "R" connection of the electronic fan control of
furnace #1.
4. Connect wire from the "W" connection of the electronic
fan control of furnace #1 to one side el the 24Vac coil of
the isolaUon relay (terminal #3)+ (Wire terminals for
connection to the isolation relay are provided in the kit)
5, Connect wire from the "C" connection of the electronic
fan control of furnace #1 to the other side of the 24Vac
coil of the isolation relay (terminal #1).
6. Connect one wire to each of the normally open
terminals of the isolation relay (terminals #2 and #4)
and connect to the "R" and "W" connections at the
electronic fan control of furnace #2.
7. -*S_t-the heat delay off timings on each control to the
same setting.
8. Set thermostat anticipator setting at 090
9. Recheck wiring connections, splices, and insulation
Re-apply line power to both appliances.
Two Stage Thermostat Operation
Reference Figure 3
1 Interconnect the Ihermostat wiring in parallel from the
thermostat to the terminal blocks on each fan control.
2,
for the "G' and 'Y' connections only. Interconnect [_,e
wir+ng from the C" connections at the terminal blocks
on each fan control. Note. The "'Y" connection _snot
reduired if air conditioning is not availab t=
Connect wire from "WI" of the thermostat to the W'"
connection of the electronic fan control of furnace Pl.
3. Connect wire from "W2" of the thermostat toone side
of the 24Mac coil of the isolation relay (terminal #3).
(VVire terminals for connection to the isolation relay are
provided in the kit)
4. Connect wire from'R" connection at the thermostat to
the "R" connection of the electronic fan control of
furnace #1.
5. Connect wire from the "C" connection of the electronic
fan control of furnace #1 to the other side of the 24Vac
coil of the isolation relay (terminal #1).
6. Connect one wire to each of the normally open
terminals of the isolation relay (terminal #2 and #4) and
connect to the 'R" and "W" connections at the
electronic fan control of furnace #2.
7. Set the heat delay off timings on each control Lothe
same setting.
8. Set thermostat anticipator setting at 0.75 for the tst
stage and 0.15 for the 2rid stage.
9. Recheck wiring connections, splices, and insulation.
Re-apply line power to both appliances.
Twinning+Kit Operation
1. Turn the heat/cool switching at the thermostat to
"OFF", or set so neither a call for heating nor cooling _s
being made.
2. Turn the fan switch to "ON" from "AUTO", or jumper
from '+R"to "G" at "furnace 1". Within several seconds,
the circulation blowers of each furnace will start at the
same speed connected to their respective 'heat =.
speed laps,
3. Turn the fan switch to ='OFF" from "AUTO" or remove
the jumper from "R" to"G". Both circulation blowers will
stop after several seconds.
4. Disconnect one wire from the high limit connection on
"furnace 1". Within several seconds, the circulation
blowers of each furnace will start at the same speed
connecled to their respective "heat" speed taps.
5. Re-connect the wire removed from the high limit
connection on "furnace 1". After the completion of the
heating "blower off" delay, both blowers will stop.
6. Repeat steps (4) and (5) with the limit connection in
"furnace 2" versus :furnace 1". The same operation
should result.
7.
8.
Operate the system through a normal call for heat,
burner on operation, and burner off operation. Each
furnace should fire and cycle both blowers, including
blower on and off delays, as in a normal single system.
Operate the system through a normal call for cooling.
The compressor operation should function normatiy.
with each furnace circulation blower operating at the
speeds connected to their respective "cool" speed
taps after cooling "blower on" delay. When the call for
cooling ends, Ihe circulation blowers will stop upon the
completion of the "cooling off" delay.