Model SCD-6/8
SECTION 2. INSTALLATION
2-1. INTRODUCTION This section provides the installation instructions for the
Henny Penny Rotisserie Display unit.
Installation of this unit should be performed only by a
qualified service technician.
Do not puncture the skin of the rotisserie display with
drills or screws as component damage or electrical
shock could result.
2-2. UNP ACKING
Figure 2-1 2. Tilt unit onto its side and install casters or legs onto unit,
The Henny Penny Rotisserie Display had been tested, inspected,
and expertly packed to ensure arrival at its destination in the best
possible condition. The cabinet rests on cardboard pads that sit
o n a wooden skid. The racks inside the cabinet are boxed
separately and the unit is packed inside a heavy cardboard carton
with sufficient padding to withstand normal shipping treatment.
1. Remove the racks, casters or legs, and drip pan, from their
box.
using a washer and lockwasher per bolt. Install the locking
casters on the control side of unit.
3. The side racks are hooked on the brackets at the top of the
interior of the unit. The bottom of the brackets rests on the
base of the unit. (Figure 2-1)
4. The shelves slide onto the side racks.
5. The drip pan slides into the bottom of the unit. (Figure 2-2)
Figure 2-2
2-3. ST ACKING
INSTRUCTIONS A stacking kit must be used to stack rotisseries, or to stack
a rotisserie on a display . This kit ensures 3 inches clearance
from a rear wall. The part numbers of the stacking kits are
02664, for use on the SCD-6 and SCR-6, and 02665 is used
on the SCD-8 and SCR-8.
203 2-1
Model SCD-6/8
2-3. ST ACKING INSTRUCTIONS 1. Lay unit on its side and bolt locking casters or legs, to the
(Continued) control side of unit.
2. Using the bolts provided for the non-locking casters, or
legs, bolt both the stacking spacer (provided in the kit)
and the non-locking caster, or legs, to the front side of the
unit. The stacking spacer should extend out the front of
the unit about three inches.
3. Carefully lift the rotisserie and place it on top of the display , or
place the display unit on top of the rotisserie, with the controls
on the same side.
T ake care when moving the unit to pr event personal
injury. The SCD-8 weighs approximately 400 lbs.
(180 Kg) and the SCD-6 weighs 315 lbs. (143 Kg).
4. Remove the three bottom side panel screws from the top
unit and remove the three top side panel screws from the
bottom unit (on both sides of the unit). Refer to Figure
2-3.
Figure 2-3 5. Mount the stacking brackets to each side of the units,
as shown in Figure 2-3, using the screws removed in step 4.
6. Unit is now ready for use.
For units being installed in Canada, proceed with the
following steps:
7. Remove the black plug button from the top of the upper unit.
8. Remove the screws from the channel assembly and take the
two parts apart.
2-2 203