g
GE
Lighting Solutions
GEH-5958E
INSTRUCTIONS
™
NUVATION
Industrial Luminaires, Installation and Maintenance
Electronically Ballasted
VBEUGE
READ THOROUGHLY BEFORE INSTALLING
SAVE THESE INSTRUCTIONS FOR FUTURE USE
WARNING
Risk of electric shock
• Turn power off before servicing
CAUTION
Risk of injury
• Wear safety glasses and gloves
during installation and servicing
CAUTION
Risk of burn
• Do not touch operating luminaire
GENERAL
This luminaire is designed for indoor applications only, and should
be installed and maintained according to these instructions.
The NuVation™ ballast is designed to operate 250W,300W, 320W,
350W and 400W pulse start and ceramic metal halide lamps with
line voltages from 208-277 volts.
See nameplate for more information.
OBEUTEUWE
NOTE: The maximum fixture ambient temperature rating is the
LESSER of the ratings indicated on the ballast and optical
assemblies.
NOTICE: There are no user serviceable parts inside this ballast
housing and there should not be a need to access the inside of
the ballast housing.
Minimum clearance of 3 feet must be maintained below
luminaire.
If the luminaire you ordered has a polycarbonate/acrylic refractor,
please pay particular attention to the following statement:
All -articles made from polycarbonates/acrylics, including
polycarbonate/acrylic resin, will yellow with time. The rate of
yellowing is determined by the specific material, any additives
and coatings, as well as the optical temperature and exposure to
Ultraviolet (UV) light.
This yellowing can reduce the light output and impact resistance
of products made from polycarbonate/acrylic resin. In no case
should the maximum lamp age, wattage rating, or ambient rating
listed for the luminaire be exceeded. Contact factory for more
information.
UNPACKING
This luminaire has been properly packed to avoid damage during
transit. Inspect the luminaire to confirm there is no damage. Do
not install a damaged luminaire or damaged luminaire
components.
UME
MBE
Any part damaged or broken during or after assembly or installation
should be replaced.
These instructions do not purport to cover all details or variations in equipment nor to provide for every possible contingency to be met in connection with installation, operation or
maintenance. Should further information be desired or should particular problems arise which are not covered sufficiently for the purchaser’s purposes, the matter should be referred
to GE Lighting Solutions.
NOTE: The NuVation luminaire is supplied with a Slide-On
Through Wire Box which may be included in the carton ready to
install.
INSTALLATION
Risk of fire
• Keep combustible materials away
from lens
• Use lamps specified on the
“luminaire fitting” nameplate
• Maintain a minimum of 3 feet
clearance below the luminaire
WARNING
WIRING BOX
THREADED
BOSS
WIRE BOX SLIDE
MOUNTING
BRACKET
CAUTION
Unit will fall if not installed properly
• Follow installation instructions
• Attach ONLY by threaded Boss
• Do not use Knockout Holes for
mounting.
CONDUIT (NOT SUPPLIED)
SET
THREADED
BOSS
WIRING BOX
Figure 1
CONDUIT MOUNTING
1. Remove the Wire Box End Cover by removing the two (2)
screws as shown in Figure 1.
1.A. For NuVation™ with Dimming Option, remove both wiring box
doors (Figure 2) for electrical connections and box removal.
WIRING BOX
END COVER
COVER SCREWS
Figure 3
NOTE: The Ballast Housing is not fully secure until the wire box
End Covers are reattached!
4. Connect the supply wires from mains to the Black and White
supply leads. Connect the Green Earth Ground Lead. Adhere
to the requirements defined the WIRING section below.
5. Replace the Wire Box End Covers. Insert and securely
retighten the End Cover Screws as shown in Figure 2.
The Ballast Housing is now secure.
FLEXIBLE MOUNTING
If flexible mounting accessories (hook or loop) are supplied
separately, thread the shaft into hanger hub/locking nut
assembly and follow the instructions above for conduit mounting.
CAUTION: If this instruction is not followed damage to the
mounting parts can occur causing the fixture to fall. When using
hook or loop fixture mounting, do not apply luminaire weight
when the mating parts are as shown in Figure 4. Do not apply any
twisting action to the hook and loop assembly. When properly
installed the hook and loop assembly is as shown in Figure 5.
Figure 2
2. Thread the Wiring Box onto the conduit. Secure the conduit
with the set screw provided. Ensure that the Wire Box cannot
turn on the conduit once Set Screw has been tightened.
3. Slide the Wiring Box onto the Mounting Bracket, which is preassembled on to the Upper Housing as shown in Figure 3.
Figure 4 Figure 5
WET LOCATION OPTION
When installing in a wet location, it is important to properly install
the Conduit with an appropriate water sealing material. The GE
Lighting Systems wet location wiring box and a GE Lighting
Systems wet location optical must be used.
WIRING
Make all electrical connections in accordance with the -National
Electrical Code and any applicable local code requirements.
Verify that the supply voltage is correct by comparing it to the
ballast’s “luminaire fitting” nameplate.