Mammoth V-Cube User Manual

V-Cube™
Floor-by-floor, Vertical Self-contained System
Installation, Operation and Maintenance Instructions Manual
Capacities: 9–150 tons
©2012 Venmar CES Inc.
Table of Contents
Nomenclature ......................................................................................................................................................................3
Safety Considerations .........................................................................................................................................................4
General Information ...........................................................................................................................................................4
Recommended Spare Parts ........................................................................................................................................... 4
Unit Application Limitations ........................................................................................................................................5
Installation ...........................................................................................................................................................................5
Unit Location Requirements .........................................................................................................................................5
Rigging, Lifting and Assembling .................................................................................................................................. 6
Suspended Unit Installation .......................................................................................................................................11
Electrical Connections ................................................................................................................................................. 11
Coil or Water Cooled Condenser (WCC) Piping Connections ................................................................................... 13
Condensate Drain Trap and Lines ..............................................................................................................................13
Start-up .............................................................................................................................................................................. 14
Start-up Procedure ...................................................................................................................................................... 15
Maintenance ......................................................................................................................................................................16
Long-term Storage Maintenance Procedures ............................................................................................................16
Maintenance Summary Chart .....................................................................................................................................16
Refrigerant Systems ....................................................................................................................................................17
Dampers .......................................................................................................................................................................18
FANWALL® Array .........................................................................................................................................................21
Coils ..............................................................................................................................................................................26
Troubleshooting ..........................................................................................................................................................27
Appendix A: Water Cooled Condenser (WCC) Piping Installation, Maintenance and Troubleshooting .....................28
Appendix B: Positive and Negative Pressure Trapping ................................................................................................... 32
Appendix C: V-Cube™ Start-up Report and Checklist ....................................................................................................33
Appendix D: HEPA Filter Installation ...............................................................................................................................40
Appendix E: Electric Heating Coil and Controls Information .........................................................................................42
Appendix F: Extended Dormant Unit Maintenance Procedure ......................................................................................44
Appendix G: V-Cube™ Maintenance Summary Chart ....................................................................................................45
Appendix H: Measuring and Adjusting V-belt Tension ..................................................................................................46
Appendix I: FANWALL® Inlet Cone Alignment ................................................................................................................47
Appendix J: Filter Resistance and Latches .......................................................................................................................48
Appendix K: Troubleshooting ..........................................................................................................................................49
Manufacturer reserves the right to discontinue or change specifications or designs without notice or obligation.
VCES-V-CUBE-IOM-1A
2

Nomenclature

VV Y
GSM
000 0
L
Model Indicator
ol Panel Location
V − V-Cube
Volume Control
V − Variable air volume C − Constant air volume
Condenser
N − No cooling X − Dx without WiSE coil W − Dx with WiSE coil Y − Chilled water cooling Z – Remote condenser A − Airside economizer
Nominal Tonnage
Number of Compressors
0 − Air handler T − Tandem compressors H − Heat pump
Voltage
F − 208-230/3/60 L − 220-240/3/60 G − 460-480/3/60 K − 575/3/60 J − 380-415/3/50
Heating Type
E − Electric H − Hot water S − Steam X − No heat
Frame Size
S − Small M − Medium L − Large T − Tall
Contr
L – Left handed unit R – Right handed unit
CES Group, LLC d/b/a Venmar CES furnishes equipment pursuant to its then-current Terms and Conditions of Sale and Lim­ited Warranty, copies of which can be found under the Terms & Conditions of Sale and Warranty link at www.ces-group.com. Extended warranties, if any, shall be as offered and acknowledged in writing by Venmar CES.
VCES-V-CUBE-IOM-1A
3

Safety Considerations

!
!
Warning, Caution and Important notes appear through­out this manual in specific and appropriate locations to alert Installing Contractors and maintenance or service personnel of potential safety hazards, possible equipment damage or to alert personnel of special procedures or in­structions that must be followed as outlined below.
WARNING
Identifies an instruction which if not followed, might cause serious personal injuries including possibility of death.
CAUTION
Identifies an instruction which if not followed, might se­verely damage the unit, its components, the assembly or final installation.
IMPORTANT
Indicates supplementary information needed to fully complete an instruction or installation.

General Information

This manual is designed to provide general information on the common operation of all standard and optional components that may have been installed in the unit. Note that some sections of this manual may not apply to your unit. This manual has been designed for a general purpose and describes all options offered by Venmar CES Inc. that could be included in the unit. Consult the manual from the component manufacturer if more detailed technical information about a specific component is required.
All documentation that was specifically designed for your unit has been included in the pocket of the control panel, including (and if applicable):
Hazards may exist within this equipment because it con­tains electrical and powerful moving components. Only qualified service personnel should install or service this equipment. Untrained personnel can perform basic main­tenance such as maintaining filters. Observe precautions marked in literature and on labels attached to the unit. Follow all safety codes.
WARNING
Disconnect the main power switch to the unit before per­forming service or maintenance. Electric shock can cause personal injury or death.
Warranties
Mechanical drawings
Unit nomenclature
Electrical schematics
Sequence of control
DDC controller documentation (when supplied) – Controller user’s manual – Communication protocol documentation – Hardware documentation – Keypad documentation

Recommended Spare Parts

Spare parts should be ordered at the time the installa­tion is accepted by the owner. Spare parts will reduce the down time in the event of a failure. The list of spare parts outlined below is considered minimal. Installation in remote locations or when the operation of heating equip­ment is essential may require more spare parts than listed. Please contact the service department at Venmar CES for recommendations.
VCES-V-CUBE-IOM-1A
Minimum spare parts include:
One matching set of fan belts (belt driven fans only)
One set of filters
One set of shell and tube condenser head gaskets
per condenser (water cooled units only)
4

Unit Inspection on Arrival

Inspect the equipment exterior and interior for any dam­age that may have occurred during unit shipment and for shipped loose parts. Ensure there is no damage to any protruding exterior components such as door handles, disconnect switch handle, etc. or to internal components such as fans, motors, heat exchanger, dampers and drains.

Unit Application Limitations

CAUTION
Venmar CES equipment is not designed to be used for temporary heating, cooling and/or ventilation during con­struction.
Using Venmar CES units for temporary ventilation dur­ing construction is subject to the unit warranty terms and should be reviewed carefully before proceeding, as this may void the standard warranty conditions.

Installation

Unit Location Requirements

File a claim with the shipping company if the unit is dam­aged. Check the packing slip against all items received. If any items are missing sign the carrier’s bill of landing with the notation “Shipment Received Less Item #_____.” Con­tact the factory immediately if damage is found. No return shipment will be accepted without authorization.
Fine dust, larger particulate matter, solvents, varnishes and other chemicals may cause filter clogging and elevated cabinet pressures, higher power consumption and possible irreparable damage to a variety of other key components that may be present in the system. Potential damages in­clude, but are not limited to, these examples.
Consult local building codes and electrical codes for spe­cial installation requirements and note additional require­ments listed in this manual. In choosing the installation location of the unit, consider the following factors:
The unit should be installed to allow easy access for maintenance and for systems operation.
Clearance around the unit should be per the recom­mended clearances indicated on the mechanical/sub­mittal drawings (varies per unit frame size) in order to allow easy access for maintenance and for system operation. For clearances to remove specific compo­nents, please consult factory.
Locate the unit in an area requiring the least amount of ductwork and direction changes to allow optimum performance, to reduce pressure loss and to use less electricity to achieve proper ventilation. Ductwork must be in accordance with ducting mechanical rules to prevent sound issues and system effects.
The unit should be mounted on a level foundation to allow condensation to flow into internal drains. The foundation must provide adequate continuous support to the full perimeter of the base and all cross members requiring support to minimize deflection of the unit base frame to not more than 1/16” [1.6 mm] over the entire length and width. In addition to these recommendations, a Structural Engineer must be involved to properly size supporting structural ele­ments.
Once the unit is in place within the mechanical equipment room, mount the unit on a housekeeping pad of sufficient height in order to allow for drain trap height and condensate lines to slope toward the building drain; install condensate pumps to reduce height of the housekeeping pads or drill holes in the concrete pad or mechanical room floor for sufficient trap height.
VCES-V-CUBE-IOM-1A
5

Rigging, Lifting and Assembling

IMPORTANT
Carefully read all the instructions contained herein. Before proceeding with any work, correlate these instructions with the information provided on the curb and equipment shop drawing for the specific project.
These instructions outline the suggested method of rigging, lifting and installing a Venmar CES unit. All local codes and fire regulations must be verified and adhered to by the Installing Contractor.
Before assembling, hoisting or setting any pieces of the supporting curbs or units, verify that the proper unit is being directed to the correct location, as des­ignated by the architectural and engineering design drawings.
Safety first: Ensure that all safety practices recom­mended by local safety associations are continu­ously in use.
If any questions arise during the installation proce­dure, please contact the factory.
The Installing Contractor is responsible for the unit being air and water-tight including all section joints on the unit.
All holes that have been made by the Installing or Electrical Contractor after receiving and installing the unit must be well sealed to prevent air and/or water infiltration.
All rigging equipment and labor (as applicable) is provided by the Installing Contractor as detailed below. It is highly recommended that extra quantities of all items listed be on hand. The rigging procedure and/or equipment used to lift the unit may differ depending on the physical dimen­sions of the unit, its location, the jobsite, the Installing Contractor and Crane Operator preferences.
Lifting crane of the appropriate capacity.
Adjustable spreader bars.
Cables (cables, chains or straps).
All tools required to pull the sections together (chains, chain blocks, chain type come alongs, etc.).
All construction equipment and labor required to complete the work according to local codes.
Condensate and/or P-trap piping hardware.
All tools and materials required for level unit installa­tion.
Installation and Assembly Materials for Multisection (Modular) Units
Polyvinyl gasket with adhesive strip (½” x 1½” [13 x 38 mm] x required length) applied between unit sec­tions (for split section joints and duct opening con­nections).
3/8” x 2½” Grade 5 full thread zinc plated bolts, with two washers and one nut each (to secure sec­tions together).
Adseal 1800 series (from Adchem Adhesives) clear silicone based sealant or equivalent (for side and top joints).
Rigging, Lifting and Assembling Instructions
Depending on size, the unit or unit sections of a multi-sec­tion (modular) unit will arrive at the jobsite on a standard flatbed or special low bed trailer. Each unit or unit section is identified with labels, as per the mechanical drawings. At ground level, ensure that any crating used for shipping purposes is removed if there is a possibility that it will in­terfere with the placing or assembling of the unit or unit sections on the structural steel or housekeeping pad.
Unit or unit sections shall be lifted by cables attached to all the lifting lugs. Consult the mechanical drawings located in the pocket of the control panel for the number of lift­ing lugs, number of sections and unit weight. For multi­section (modular) unit check for additional lugs located between split sections. Lifting lugs are factory bolted to the unit or unit section base.
CAUTION
All lifting lugs provided must be used when rigging units or unit sections. Rigging and lifting unit or unit sections without using all lifting lugs provided will compromise the structural integrity of the unit or unit section. Never lift, rig or ceiling suspend from the top of the unit or unit sections. Using a forklift or similar device for moving, lifting or rigging unit or unit sections is prohibited. The use of a forklift or other similar device is only allowed for modular unit sections that are mounted on wooden skids within the factory prior to shipment. The sections must be forklifted individually along its longest side only.
When lifting the unit or unit sections, use adjustable spreader bars, pulleys, cables (straps or chains) in order to properly distribute the load, applying an even vertical lifting force only at all the lifting lugs to prevent structural damage to the unit or unit section or prevent cables from rubbing against the cabinet (see Figure 1). Provide ad­ditional blocking and coverings (as required) to prevent damage to the unit finish and/or components. The adjust­able spreader bars are required to maintain a clearance between the cables and the unit or unit section of at least 12” [305 mm] beyond the sides. Venmar CES will not be responsible for any damage caused to the unit casing dur­ing the lifting process. Main areas where damage may occur are: electrical panels, filter gauges, roofing corners, door handles and paint finish. The lifting point must be at the center of gravity to ensure that the unit or unit section is level during hoisting and prior to setting. When com­mencing to hoist, take up the slack in the hoisting cables slowly and gradually increase the cable tension until the full unit or unit section weight is suspended. Avoid sud­den, jerking movements. Do not permit the unit or unit
VCES-V-CUBE-IOM-1A
6
section to be suspended by the lifting lugs for an extended
See Detail A
period of time. Once the unit or unit section leaves the trailer, ensure it is level at all times.
Adjustable spreader bars (typ.)
Pulleys (typ.)
Detail A
Use clevis and clevis pin to attach cable to lifting lugs.
12” 12”
Pulleys
Adjustable spreader bars
12” min.
6” max.
Figure 2: Set the next section approximately 6” [152 mm] from the first section.
3. Corner reinforcement brackets or angle bars may have been used to support multi-section (modular) unit walls during transportation, rigging and lifting at the split. The brackets shown in Figure 3 are for larger units. Simple angle bars are used for smaller units (not shown). The corner reinforcement brackets or angle bars are no longer required after rigging and lifting and must be removed.
IMPORTANT
After the corner reinforcement brackets or angle bars have been removed from the split section, set the screws along with the rubber washers that were holding the brackets or angle bars back in place for water-tightness.
Figure 1: Use adjustable spreader bars, pulleys and cables attached to all lifting lugs to apply an even lifting force.
Assembling a Multi-section (Modular) Unit
Special attention must be taken to ensure that a multi­section (modular) unit has an air and water-tight seal at every section split. Follow the next set of instructions for assembling a multi-section (modular) unit.
1. Remove the yellow lifting lugs located on the section joint (if any) once the first section is set in place.
IMPORTANT
Yellow lifting lugs located on the section joint (if any) must be removed once the first section is set in place to allow the next section to be pulled to the first.
2. Set the second section approximately 6” [152 mm] from the first section (see Figure 2). Remove the yellow lifting lugs located on the section joints (if any) from the second section to allow sections to be pulled together.
VCES-V-CUBE-IOM-1A
Figure 3: Corner reinforcement brackets or angle bars to be removed from the split section. Reset the screws with rubber washer in place for water-tightness.
4. Verify that these two sections are aligned square at the joint in all three directions.
7
5. For modular integrated water cooled units, the
acoustical butyl sealant
1½”
Detail at A
5b
½” x 1½” polyvinyl gasket
compressor/condenser section should first be mated to the coil section as outlined in Figure 2 prior to mounting the fan section. The internal water and re­frigerant piping must then be completed in the field by the Installing Contractor. Once the field piping is complete a bead of Adcoustik butyl sealer should be applied to the top of the condenser/compressor section as illustrated in Figure 4a. The fan/blower as­sembly should then be gently lowered on top of the compressor/condenser section as shown in Figure 4b. Finally the top and bottom sections should be joined together with bolts, nuts and washers as per Figure 4c. After reassembly, the unit will require pump down (evacuation) and refrigerant charging. Factory shall provide dry nitrogen “holding” charge only. Re­frigerant, additional copper piping and insulation for field connections shall be supplied by others. Filter drier shall be shipped loose for field installation.
½” [13 mm] bead of ADBOND 1465
Figure 4c: Secure the top and bottom sections together with bolts, nuts and washers. Do not over tighten.
6. Install the ½” x 1½” [13 x 38 mm] 6. polyvinyl gasket with adhesive strip directly on one side of the split section perimeter frames and middle interior parti­tions as shown in Figure 5a through Figure 5d.
Figure 4a: Apply a ½” bead of Adcoustik butyl sealer atop of the condenser/compressor section prior to placing the fan/blower section above it.
Figure 4b: Gently lower the fan/blower section atop of the compressor/condenser section.
1½”
A
5a & 5c
5d
Figure 5: General gasket layout
IMPORTANT
Make sure to have full contact between strips wherever a discontinuity is present, for air- and water-tightness.
¼”
Figure 5a: Install a polyvinyl gasket strip on each vertical outside wall ¼” [6.4 mm] from the outside side edge from top to bottom of the side joint. When compressed, a small gap will remain which will allow the Adseal 1800 series silicone based sealant or equivalent to seal the vertical side edges (explained in Figure 8).
VCES-V-CUBE-IOM-1A
8
Bottom of frame
Top of frame
7. Use tools (chains, chain blocks, 7. chain type come along, etc.) connected to the side lifting lugs (at­tached to the base) on both sides of the unit to pull the second or next section to the first end section evenly until both sections are ¼” [6.4 mm] apart on the full joint perimeter as in Figure 6. Remove any yellow side lifting lugs that interfere with the chains for pulling sections together. When joining sections together, always apply the pulling force to the lifting lugs attached to the unit structural base, never to the corner posts and pull uniformly from both sides of the unit section.
Figure 5b: Install two horizontal polyvinyl gasket strips along the base frame, one at the top and one at the bottom of the base frame between the two vertical side gasket strips so there is full contact between gasket strips for air- and water-tightness.
Figure 5c: Install one horizontal polyvinyl gasket strip along the top frame between the two vertical side gasket strips so there is full contact between gasket strips for air­and water-tightness.
IMPORTANT
Unit sections must be drawn together using the lifting lugs attached to the unit structural base only.
CAUTION
Do not use the vertical side casing framing or bolt holes to pull sections together as this may cause the corner posts to warp and break their air- and water-tight seal.
Displacement
Tools supplied by others
Figure 6: Use tools (chains, chain blocks, chain type come along, etc.) hooked to the unit lifting lugs attached to the structural base on both sides of the unit to pull the second or next section to the first section evenly.
Middle internal partition(s)/divider(s)
Figure 5d: Where two or more internal air tunnels/cor­ridors are present, install the gasket strips on the middle internal horizontal and/or vertical partition(s)/divider(s), between the perimeter gasket strips so there is full contact between gasket strips for air- and water-tightness.
VCES-V-CUBE-IOM-1A
8. With the sections pulled together, use the 3/8” x 2½” bolts, nuts and washers to secure the sections together along the sides as in Figure 7. Start at the bottom and gradually tighten all bolts to apply an even load along both sides and along the top (not at one place) until sections or gasket is compressed within ¼” [6.4 mm].
9
Figure 7: Secure the sections pulled together with bolts,
1/8” x 1” neoprene SOFT SEAL gasket
nuts and washers. Do not over tighten.
CAUTION
Do not over tighten the side bolts as this may cause the corner posts to warp and break their air- and water-tight seal.
9. After two sections are assembled, verify that the assembly is level and square. If an adjustment is re­quired, make certain to address it immediately, not at the end of the final assembly.
10. If multi-section unit has more than two sections fol­low Steps 1 through 9 for each additional section, always pulling the next section from the first end sec­tion.
11. Apply a generous bead of Adseal 1800 series clear silicone based sealant (or equivalent) to the exterior side frame joint seams to completely cover the sec­tion split gasket and in such a way that the silicone bead meets with both frames as in Figure 8. The bead of clear silicone based sealant should fill the ¼” gap, as shown in Figure 8.
12. All lifting lugs removed on the exterior of the base for pulling sections together must be returned or if not desired the bolts must be set back in place. Once removed the bolts must be returned and sealed with clear silicone based sealant for water-tightness. All other lifting lugs from the unit base may be removed if desired or left in place. When removing lifting lugs on the exterior of the base, set the bolts back in place and seal with clear silicone based sealant for water-tightness.
Bead of Adseal 1800 clear silicone based sealant
Figure 9: a) Install the gasket strips on the inside edges of the inside caps; b) Install caps in place with self-drilling screws; c) Apply a continuous bead of Adseal 1800 clear silicone based sealant (or equivalent) to the inside cap seams and partition(s)/divider(s).
Figure 8: Apply a continuous bead of Adseal 1800 clear silicone based sealant (or equivalent) to the exterior side frame joints and for indoor units along the top frame joints.
VCES-V-CUBE-IOM-1A
¼” bead Adseal 1800 clear silicone based sealant
10

Suspended Unit Installation

min.
!
To install units that will be permanently suspended, the units must be set on structural steel beams that are sup­ported by vertical rods. Venmar CES recommends beams under the full perimeter and all cross members requiring support. In addition to these recommendations, a Struc­tural Engineer must be involved to properly size the sup­porting structural elements. Note that the locations of the beams shall be coordinated with the location of access doors to prevent any interference (see Figure 10). Single section unit shown; for multi-sectional unit suspension, consult factory.

Field Fabricated Ductwork

Anchor
40”
Figure 10: Indoor suspended installation
40” min.
On indoor or indoor vertical duct connections, make con­nections to the casing by applying Adseal 1800 silicone based sealant or equivalent around the connection and screwing flanged ducts directly to the casing and/or flange with self-drilling sheet metal screws. It is important to seal all duct connections to prevent air leakage and system performance problems. Ductwork must be supported by the building structure.
For duct connection sizes, see the mechanical drawings. Insulate and weatherproof all external ductwork, joints and roof openings with counter-flashing and mastic in accordance with applicable codes. Ductwork running

Electrical Connections

WARNING
When installed, the unit must be electrically grounded in accordance with local codes or, in the absence of local codes, with the National Electrical Code, ANSI/NFPA70, and/or the Canadian Electrical Code CSA C22.1. Unit cabinet must have an uninterrupted, unbroken electrical ground to minimize the possibility of personal injury if an electrical fault should occur. Failure to follow this warning could result in the installer being liable for personal injury of others.
The unit is factory wired (unless otherwise specified) except for power connections, shipping split locations, shipped loose sensors/items or remote control options as indicated in the electrical schematics and sequence of control. The unit may or may not have an optional factory installed door interlocking disconnect in the control panel.
through roof decks must comply with local fire codes. Ducts passing through unconditioned spaces must be in­sulated and covered with a vapor barrier.
The ventilation system should be designed according to maximum airflow needs. To minimize noise level and loss of pressure, ducts should be designed for a maximum air velocity of 1,200 feet per minute, keeping the direction and transition changes to a minimum. To further reduce noise transmission, line the first 15 feet [4,572 mm] of duct with acoustic insulation. Elbows with a turning radius equal to or greater than 1, or 90º elbows with turning vvanes, should also be used.
If the unit control panel disconnect is not supplied the Electrical Contractor must provide and install disconnect outside of the unit as per local electrical codes and run the power supply wiring to the control panel.
For multi-section (modular) units, the Electrical Con­tractor must join the low voltage wiring between unit sections using quick connections supplied by Venmar CES and join the high voltage wiring between sec­tions at the junction boxes or extend coiled wiring.
Check nameplate for correct power supply require­ments.
See electrical schematics and sequence of control lo cated in the control panel pocket for field wiring of power connections, shipped loose sensors, items or remote control interlocks. The Electrical Contractor must locate, install and wire sensors, items or remote
VCES-V-CUBE-IOM-1A
11
control interlocks as per electrical schematics and se­quence of control.
Numbered terminals strips are included in the control panel for ease of connection and service.
All field wiring and components must comply with NEC and local requirements. In Canada, electrical connections must be in accordance with CSA C22.1 Canadian Electrical Code Part One.
Install copper wiring of proper size to handle current load.
Mounting of field provided components in the con­trol panel is allowed as long as their space was con­sidered during the submittal process. Non considered electrical components are not allowed in the control panel. It is the responsibility of the Control Contrac­tor to provide his own power source(s) for any field added electrical components. The control panel mounted transformers are not rated for external components power supply unless otherwise listed on the electrical schematics.
Electrical Field Connections
Shipped loose sensors, items or remote control wiring can be located next to the power feed cable provided it is inserted in shielded cable that will protect it from elec­tromechanical interference. Ensure the power feed cable ground is securely connected to the terminals located in the control panel.
Electrical Contractor must provide wiring for controls that are supplied optionally and shipped loose or field sup­plied. Mark the electrical schematic with the connections completed and leave them with the unit for start-up and service.
CAUTION
High voltage power lines, shipped loose sensors, items or remote control option field wiring entry points may only be field extended through the cabinet within des­ignated areas. The unit cabinet and/or floor must be wisely penetrated in order to keep their integrity. Access openings in the floor can only be cut or drilled for piping and wiring (high and low voltage) in the designated rect­angular areas within an upturned 1” [25.4 mm] flange as provided during the submittal process and located on the mechanical drawings. Access openings must be sized, field cut or drilled by the Installing Contractor within the rectangular flanged area then sealed air- and water-tight. If insulation was removed to create floor access openings, insulation must be put back in place to avoid condensa­tion. Do not cut or drill holes through floor of unit in non designated areas without consulting the factory first. The structural integrity of the floor may be compromised and possible leaks develop.
VCES-V-CUBE-IOM-1A
12

Coil or Water Cooled Condenser (WCC) Piping Connections

CAUTION
Internal coil (water, steam or non-integrated direct ex­pansion), WCC piping connections within the unit may only be field extended through the cabinet within desig­nated areas. Connections to the unit coil (water, steam or nonintegrated direct expansion, WCC) are by others. External supply and return piping connection, provision, design and all other safety (such as dielectric couplings or other), freeze protection or electrical control require­ments for system operation are the sole responsibility of the Installing Contractor and/or Design Engineer. Refer to ASHRAE handbooks and local building codes for correct piping and electrical control for proper installations. Refer to the mechanical drawings for coil performance design information.
Connections to the unit coil (water, steam or non-inte­grated direct expansion, WCC or humidifier) are by others. Refer to the mechanical drawings and the instructions on the casing for correct orientation of external piping. External supply and return piping connection, provision, design and all other safety, freeze protection or electrical control requirements for system operation are the sole responsibility of the Installing Contractor and/or Design Engineer. Refer to ASHRAE handbooks and local building codes for correct piping and electrical control for proper installations. Refer to the mechanical drawings for coil per­formance design information.
For WCC units, see Appendix A. See the piping schematics for optional piping components and sequence of opera­tion for electrical control options or interlocks supplied with the unit.
CAUTION
A water and glycol mixture is used for factory tests and to prevent any possibility of freezing during transit and/ or storage. In units that include factory installed water piping, some glycol may remain in the system. Flush the system in the field, prior to installation, if no glycol traces are desired. In low temperature applications, the water supply line and return line should be insulated to prevent condensate and an antifreeze solution should be used to protect water-to-refrigerant heat exchanger from freez­ing damage.
IMPORTANT
A hydrostatic test must be performed in the field by the Installing Contractor at 1.25 times the operating pressure on all equipment involving piping connections to verify that the installed unit and its connections to the network are free of leaks prior to the unit being set in operation. This test shall be performed after the unit is completely piped to the network and shall cover the connections between the unit and the network, as well as all internal components of the unit.

Condensate Drain Trap and Lines

Cooling coils, humidifiers or other options that can pro­duce condensation are provided with a drain pan with a 1¼” [32 mm] MPT (Male Pipe Thread) drain connection. A drain trap and condensate line of equal size must be field provided by the Installing Contractor on the drain connections and coupled to the building drainage system to prevent air or sewer gases from being pulled into the unit caused by the negative (suction) pressure and forcing water out of the pan into the unit or from air escaping into the drain caused by positive pressure. See Appendix
B for illustrations and dimensional information on positive
and negative pressure trapping height. Slope the drain lines downward in direction of flow not less than 1/8” per foot toward the building drainage system; otherwise, use a condensate pump. Refer to local codes for proper drain­age requirements. Installing a plug for cleaning of the trap is recommended. Fill the P-traps with water before starting the unit. Check and clear drains annually at start of cool­ing season. Drainage problems can occur should drains be inactive and dry out or due to reduced water flow caused by buildup of algae. Regular maintenance will prevent these from occurring.
VCES-V-CUBE-IOM-1A
13

Start-up

Pre Start-up Check

Before requesting start-up, check that the installation is complete and unit is ready. Complete the pre start-up below (if items are applicable) and the checklist in Appen-
dix C for each unit. For torque values on set screws, belt
tension, etc. check under Operation and Maintenance.
1. Check the electrical disconnect is in 1. the ‘Off’ posi­tion.
2. Check the split section joints are properly installed on multi-section units.
3. Check that all holes that have been made by the Installing Contractor after receiving the unit in the casing, partitions or floor have been well sealed to prevent air and/or water infiltration.
4. Check the unit for obstructive packaging, objects near or in fans, dampers, etc.
5. Remove all retaining bolts on fan bases. a. Check that the fan impellers are rotating freely. b. Check fan impeller and drive set screws. Tighten
if required.
c. Check the fan bearing set screws or locking col-
lars. Tighten if required.
d. Check fan belt alignment and tension.
6. Check that the air filters are installed and clean. Replace if necessary. See Appendix D for optional downstream high efficiency HEPA filter installation (if supplied). a. Check all face-mounted filters are attached with
four clips each.
b. Check each sliding filter has a retainer at the end
track and well attached blank-offs.
c. Check that the filter pressure differential gauges,
switches or sensors are free of dirt and set at a value satisfactory to the end user to trigger a fil­ter change.
7. Check coils if fins have been damaged in shipping, installation or building construction and are clean. Straighten fins with fin comb and clean coil if re­quired. a. Check all pipe connections are tight and that no
damage has occurred during shipping or instal­lation.
b. Check that the piping to the coils and WCC have
been completed, piping lines have been flushed, filled, vented and tested at 1.25 times the oper­ating pressure.
c. Refer to Appendix A for WCC piping installation
and check that it is complete.
8. Scroll compressor RIS vibration isolator bolts are fac­tory tightened to the correct torque setting for op­eration and do not require field adjustment. a. Check that refrigerant components and piping
are in good condition and have no damage or leaks from shipping or installation.
b. Check that the clearance around the water
cooled condenser (WCC) is in accordance with minimum recommended clearances.
9. Check motorized damper control arms, control rods and shafts for tightness. a. Check that non motorized dampers rotate freely.
10. Check that ductwork is connected, complete and free of obstructions.
11. Check that condensate drain connections have been trapped, installed correctly and filled.
12. Check that all shipped loose or field supplied compo­nents have been correctly installed and wired.
13. Check that the wiring diagram has been marked up accordingly and left with the unit.
14. Check that all power supplies and control wiring have been inspected and approved by the Local Au­thorities having jurisdiction.
15. Check all factory and field wiring connections for tightness. Tighten if necessary.
16. Check that all fuses are properly installed in holders.
17. Check the voltage at the disconnect switch against the nameplate and against phase-to-phase readings on three-phase. If the voltage is not within 10% of rated or 2% of phase-to-phase, have the condition corrected before continuing start-up.
18. Check that all field piping and venting installation and connections for the heating and cooling options have been completed and tested.
19. Set the heating and cooling enable switches to the ‘Off’ position.
VCES-V-CUBE-IOM-1A
14

Start-up Procedure

!
To ensure proper operation of each unit, qualified person­nel should perform the start-up as outlined below (based on options included with unit) and complete the Start-up Report and Checklist in Appendix C for permanent record. A completed report and checklist will provide valuable in­formation for personnel performing future maintenance.
IMPORTANT
A completed copy of the Start-up Report and Checklist must be sent back to the factory for war­ranty validation and for factory assistance.
General information on the factory installed and programmed DDC control system regarding the navigation and monitoring of the unit with the standard keypad are provided in separate docu­ments. For more specific information regarding the sequence of control, the different options of control or network communications, see these documents included with the unit in the control panel pocket.
If units are equipped with compressors, power must be turned on for 24 hours prior to a call for cooling, for the compressor crankcase heaters to be energiz­ing to prevent possible damage.
WARNING
Electric shock can cause personal injury or death.
Only qualified service personnel should install and service this equipment.
The keypad must be used to check operation ac­cording to sequence and to adjust setpoints while power is on for start-up and while performing ser­vice.
All units are factory run tested. Fans, compressors and condenser fans (if equipped and refrigerant pip­ing is not split for shipment) are set up to run correct when power is connected. If any one fan is running backwards or compressor is making loud noises, dis­connect power and switch two leads (on three-phase power) to ensure proper rotation and avoid damage. With multi-section units with split wiring connections check rotation of fans, compressors and condenser fans for correct rotation to ensure wiring connections are correct.
7. Recheck the voltage at the disconnect switch against the nameplate and against phase-to-phase readings on three-phase with all fans operating. If the voltage is not within 10% of rated or 2% of phase-to-phase have the condition corrected before continuing start­up.
8. Check amperage draw to each motor on each phase against motor nameplate FLA. If significantly differ­ent check ductwork static and/or take corrective ac­tion.
9. Feel the compressor crankcases. They should be warm if the disconnect has been on for at least 24 hours. This will assure that no refrigerant liquid is present in the crankcase which could cause compres­sor damage or failure to occur on start-up.
10. Before activating the compressor(s), ensure that any water shut-off valves are open and that water is circulating through the water-to-refrigerant heat ex­changer. Check the incoming line water pressure to ensure it is within design and acceptable limits.
11. Enable cooling and check that compressors and con­denser fans are rotating in the correct direction.
12. Check if the sound of the compressor is normal or if there is excessive vibration.
13. Check all field and factory refrigerant and water pip­ing connections for leaks and correct.
14. Check the operation of the control options provided on the unit.
15. Check the reference setpoints on the keypad opera­tion guide against the sequence of operation, adjust and record changes as required.
16. When unit has achieved steady state take measure­ments and complete the readings section of the start-up report in Appendix C.
17. Set the keypad to each mode of operation and check the operation according to sequence.
18. For recirculation scheduling mode the outside air and exhaust air dampers must be adjusted during start-up to achieve the required outside and exhaust air vol­umes. See Airflow Balancing for further information.
19. Send copy of the completed start-up reports to Ven­mar CES to validate warranty. Maintain a copy of the reports at the unit for future reference.
1. Before proceeding complete the Pre 1. Start-up Checklist.
2. Check that all access panels or doors are closed.
3. Open the access door to the main control panel to access the keypad interface device.
4. Bump-start the unit to verify that the fan wheel(s) are rotating in the correct direction.
5. Set the keypad to occupied mode with heating and cooling disabled and fan(s) enabled.
6. Check that dampers are operating properly.
VCES-V-CUBE-IOM-1A
15
Airflow Balancing
!
IMPORTANT
Before measuring supply and exhaust flows, the building must be in its normal state:
Hermetically close doors and windows.
Shut down hot air generators and combustion water heaters.
Install all ventilation system components: filters, grilles, diffusers, etc.
For proper performance the unit must operate at the spec­ified supply and exhaust flow rates as shown in the me­chanical drawings. Unit fan speed(s) and damper positions are theoretically set at the factory based on the ductwork static pressures and flow rates specified in the mechanical drawings. If conditions change or verification is required, airflow measurements should be taken using AMCA sug­gested methods. This would normally be a velocity traverse measurement or flow measuring station (FMS) installed in the ducts. Where space is limited in the outdoor air and exhaust air, pressure drop readings can be taken across the energy recovery heat exchanger (with economizer heat recovery bypass dampers closed, if equipped) and com-
pared to the submittal documents. Heat recovery perfor­mance is tested in accordance to AHRI Standard 1060 and is accurate to within +/− 5% if there is no dirt buildup in the heat recovery heat exchanger. Should flow rates need to be reset, adjust the outside air, exhaust air or mixed air dampers, variable speed sheaves, VFD fan speed setpoint positions or change the sheaves.
Flow measuring stations (FMS) and magnahelic gauges can also be used to measure supply and exhaust flow. It is im­portant to locate the FMS in the “warm side” ductwork to minimize the effect of differences in air density, especially when balancing during extremely cold outside conditions or to take temperature readings and make the necessary corrections if installed in the “cold side” ductwork. Air density variations can affect the FMS by more than 15%. The FMS should be located downstream in straight sec­tions of duct and not immediately after fans or obstruc­tions that will cause turbulent flow.
If the unit has been in operation before the air balancing, ensure the unit filters are clean or include pressure drop readings across the filter banks with the report.

Maintenance

Long-term Storage Maintenance Procedures

WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.

Maintenance Summary Chart

Please refer to Appendix G for a recommended list of routine maintenance items and time intervals. A more de­tailed description of maintenance items follows.
Please refer to Appendix F: Extended Dormant Unit Main­tenance Procedure and Checklist, for maintenance instruc­tions to follow if the unit is to be stored for a period of time exceeding one month. Following the instructions in this appendix will assist in preventing potential unit dam­age that may result from an extended storage period.
VCES-V-CUBE-IOM-1A
16

Refrigerant Systems

!
Distributor
application (optional)
Bulb clamp
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Compressors
Scroll-type compressors are the most common type of compressor used by Venmar CES. Other types of compres­sors are available upon request, if required. Maintenance and service on compressors must be completed by a li­censed service mechanic. Provincial or state regulations frequently require such qualifications for compressor main­tenance. If a compressor cycles, leaks or has any defects, contact Venmar CES as soon as possible.
Water Cooled Condensers
Shell and Tube Condensers
Most integrated water cooled units contain shell and tube condensers. Periodically, water tubes should be mechanically cleaned to ensure optimum condenser ef­ficiency. Frequency of cleaning will depend on individual water conditions, so a suitable cleaning schedule should be arranged based on experience and knowledge of the building or local water supply loop. Cleaning brushes are available from most refrigeration supply outlets. For better results, always remove both heads before cleaning water tubes.
Note that head gaskets do not require renewing at every maintenance operation. However, if the head gasket is physically disfigured or deteriorated in any way, the system will require new gaskets in order to retain the water-tight seal required for correct system operation.
Evaporator Section
The direct expansion coil is constructed of seamless cop­per tubing expanded into full collared aluminum fins. The tubes are arranged for a counter flow circuit and stag­gered to provide maximum heat transfer. A pressure type distributor with hot gas inlet port and a heavy duty copper suction header are included. Additional refrigerant circuit components include thermostatic expansion valves with external equalizer and hot gas bypass valves on the full face of the leaving side of the direct expansion coil (HGBP option is removed when optional digital scroll compressors are utilized).
Liquid line
Hot gas bypass line
Suction line
Expansion valve
Check valve on remote condensing
Evaporator coil
Figure 11: Direct expansion (Dx) coil
Thermostatic Expansion Valve
The thermostatic expansion valve (TXV) is a precision de­vice designed to meter the flow of refrigerant into the evaporator, thereby preventing the return of liquid refrig­erant to the compressor. By being responsive to the tem­perature of the refrigerant gas leaving the evaporator and the pressure in the evaporator, the thermostatic expansion valve can control the refrigerant gas leaving the evapora­tor at a predetermined superheat. Three forces that gov­ern the operation of the TXV are:
1. The pressure created by the remote bulb and power assembly (P1).
2. The evaporator pressure (P2).
3. The equivalent pressure of the superheat spring (P3).
Remote clamp
P
1
Diaphram
P
2
P
3
Figure 12: Thermostatic expansion valve (TXV)
External equilizer port
Components of a Direct Expansion (Dx) System
The evaporator is that part of the low pressure side of the refrigerant system in which the liquid refrigerant boils or evaporates, absorbing heat as it changes into a vapor.
VCES-V-CUBE-IOM-1A
17

Dampers

!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Units from Venmar CES may or may not incorporate the use of dampers. If dampers are present within the unit, the following maintenance should occur in order to pre­vent the unit from working under too much pressure and to prevent any other issues.
Dampers must be kept free of foreign matter that might impede normal free movement. Bearings between blades and frames are made of polymer and require no mainte­nance. Note that the damper shafts do not need lubrica-

Belt Driven Fans

Belt driven fan, motor and drive assemblies should be checked and inspected at regular intervals per the inspec­tion list and procedures below. Listen for vibrations or unusual sounds. Severe damage, premature failure and loss of airflow can be avoided by regular inspection and maintenance.
1. Check the fan, motor and bearing mounting bolts for tightness according to the bolt torque chart in Table 1 below at time of start-up, after 24 hours, then every three months.
Table 1: Minimum head bolt torque in lb-ft (Grade 5 bolts)
Size (Inches) Thread Designation Minimum Torque
1/4 –20 1/4–28 5/16–18 5/16–24 3/8–16 3/8–24 7/16–14 7/16–20 1/2–13 1/2–20 9/16–12 9/16–18 5/8–11 5/8–18 3/4–10 3/4–16 7/8–9 7/8–14 1–8 1–14
Soft metric conversions are not acceptable for screw and hex sizes.
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
UNC
UNF
6
7 14 16 24 28 42 45 69 83 99
118 150 176 254 301 358 422 500 602
tion. All Venmar CES dampers and linkages are assembled with non lubricating bearings.
Attachment mechanism linking motors to dampers should be checked for tightness.
Damper jackshafts (if provided) are fitted with grease nipples and should be lubricated once a year. Use a premium quality lithium based grease conforming to NLGI Grade 2 or 3 (examples are: Mobil Mobilith AW2, Chevron Amolith #2, Texaco Premium RB or Shell Alvania #2).
Dampers should be inspected for dirt; check the shaft, arms, bars and controls rod every three months.
Inspect the seals to ensure none have pulled loose or deteriorated. If a seal has been damaged, repair or replace it with the same seal or same seal material. Contact Venmar CES for replacement parts.
2. Check the fan wheel hub, bearings and drive sheave set screws for tightness according to the set screw torque chart in Table 2 below at time of start-up, after 24 hours of operation, monthly for the initial three months then every three months thereafter. If wheel or bearing set screws have worked loose, check the wheel for any signs of movement (inlet space clearance between the fan wheel and housing) or loose blades. If Loctite was used on any set screws that have come loose, the set screws must be re­moved and cleaned before re-tightening and Loctite must be re-applied.
Table 2: Wheel set screw torque in lb-ft
Set Screw Size
Diameter (Inches)
1/4 75 6.2
5/16 144 12.0
3/8 252 21.0
7/16 396 33.0
1/2 600 50.0 5/8 1,164 97.0 3/4 2,016 168.0 7/8 3,204 267.0
1 4,800 400.0
*Stainless steel set screws are not hardened and should not be tightened to more than half the values shown.
Carbon Steel Set Screw Torque*
lb-in lb-ft
VCES-V-CUBE-IOM-1A
18
!
WARNING
Lines must
Center lines
sheave
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Table 3: Bearing set screw torque in lb-in
Set Screw
Diameter
Link Belt
#10 40 35 35
1/4 90 65 50 85
5/16 185 125 165 165 160
3/8 325 230 290 290 275
7/16 460 350 350
1/2 680 500 620 600 5/8 1,350 1,100 1,325 1,200 3/4 2,350 2,000
Split pillow block bearings are fixed to the shaft with tapered sleeves and generally do not have set screws.
3. Check each V-belt tension and adjust 3. the motor base for correct amount according to the deflection outlined in the Measuring Belt Tension procedure below and in Appendix H for type of belt at time of start-up, daily for the first week until they should acquire their permanent set, then monthly. All belts should have approximately the same amount of de­flection. Be aware of mismatched or worn belt sets. If a belt must be changed, ensure to change all belts on the same drive at the same time. Never replace just one belt within a set.
Measuring Belt Tension
a. Measure the belt span with a span scale. b. Divide the belt span by 64 to determine the belt
deflection needed to check tension.
c. Set the O-ring on the span scale to the required
deflection value. d. Set the small O-ring at zero on the force scale. e. Place the scale end of the tension checker
squarely on one belt at the center of the belt
span. Apply force on the plunger until the bot-
tom of the large O-ring is even with the top of
the next belt or until it is even with a straight
edge laid across the sheaves. f. Read the force scale under the small O-ring to
determine the force required to give the needed
deflection. g. Compare the force scale reading in Step F above
with the correct value for the belt style and cross
section. The force scale reading should be be-
tween the minimum and maximum values shown
in Appendix H.
Manufacturer
Sealmaster SKF McGill Dodge
h. If the deflection value is below the minimum,
tighten the belts. If the deflection value is above the maximum, loosen the belts. The tension on new belts should be checked during the first day of operation, at the end of the first week and monthly thereafter.
4. Check the fan and motor sheave alignment using a straight edge along the outside edges of the sheaves for equal sized fixed sheaves as shown in Figure 13 and Figure 14 at time of start-up, after 24 hours of operation, monthly for the initial three months, then every three months thereafter. When properly aligned the straight edge should touch the full face of both sheaves. With one adjustable and one fixed sheave with unequal sizes, use a string placed at the center grove of both sheaves pulled tight to check alignment. Adjust sheaves for proper alignment and set screws to proper torque.
Figure 13: Equal sheave size alignment
must coincide
Fixed sheave
Adjustable
Figure 14: Unequal sheave size alignment
be parallel
Straight edge
5. Belt driven fan bearings are fitted with grease nipples for lubrication. The grease quantity and lubrication interval depends on bearing (fan size) and rpm and are indicated in Tables 4 and 5. Use a premium qual­ity lithium based grease conforming to NLGI Grade 2 or 3 (examples are: Mobil Mobilith AW2, Chevron Amolith #2, Texaco Premium RB, Shell Alvania #2 or Esso Beacon #325). Clean the grease nipple first, then rotate the fan shaft slowly by hand while add­ing grease. The lubrication intervals are theoretical and will depend on site conditions, hours of opera­tion and temperature. It is recommended to make periodic inspections of the bearings before these theoretical intervals.
VCES-V-CUBE-IOM-1A
19
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Table 4: Recommended Grease Quantity
Shaft Size
Inches Millimeters Ounces Kilograms
0.500–0.750 13–19 0.125 0.004
0.875–1.187 25–31 0.375 0.011
1.250–1.500 32–38 0.625 0.018
1.687–1.937 43–49 0.875 0.025
2.000–2.437 51–62 1.250 0.035
2.500–2.937 63–75 2.000 0.056
3.000–3.437 76–87 3.500 0.098
3.500–4.000 89–102 6.000 0.168
4.187–4.937 106–125 10.000 0.280
Maximum Grease Capacity
of Bearing Chamber
6. Fan, wheels, housings and drive assemblies 6. should be checked for dirt buildup annually and cleaned if necessary to keep them from becoming unbal­anced and to prevent loss of airflow. Clean with compressed air to reduce any dirt, dust, lint or larger particulates that have bonded to the fan impeller housing or drive assembly. Block dirt from entering the unit and ductwork if necessary or remove fan assembly from unit. Alternatively use low pressure steam, a degreaser and rag. If a sheave requires cleaning, detergent and water can also be used. En­sure the belt is dry before starting up the unit.
IMPORTANT
Be careful not to remove or dislodge balancing clips on the fan blades while cleaning.
Table 5: Generally Recommended Relubrication Frequency in Months
Operating
Speed (RPM)
up to 500 6 6 6 6 5 4
500–1,000 6 6 6 5 4 3 1,000–1,500 5 5 5 4 3 3 1,500–2,000 5 4 4 3 2 1 2,000–2,500 4 4 3 2 1 — 2,500–3,000 4 3 2 1 2 — 3,000–3,500 3 2 2 2 — 3,500–4,000 3 2 1 — 4,000–4,500 2 1 1 — 4,500–5,000 2 1
0.500–1.000” [13–35 mm]
1.125–1.500” [28–38 mm]
1.625–1.937” [41–49 mm]
2.000–2.500” [50–63 mm]
2.687–3.187” [68–81 mm]
3.437–3.937” [87–100 mm]
VCES-V-CUBE-IOM-1A
20
FANWALL® Array
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Maintenance Schedule
FANWALL array of multiple direct driven plenum fan and motor “cubes” are equipped with permanently sealed bearings and do not require lubrication. The following maintenance schedule is recommended.
1. Monthly a. Check the fan wheel to inlet cone alignment for
possible noise from the wheel rubbing against the inlet cone. See Fan Wheel/Cone Alignment below for instructions.
2. Every six months a. Check motor bearings for possible binding noise
or overheating.
b. Check fan wheels for dirt and grease accumula-
tion. Clean as necessary. Do not use any caustic cleaning solutions.
3. Annually a. Lightly lubricate damper and linkage bushings on
backdraft dampers (if equipped).
4. Every two years a. Examine fan housings and motor pedestal for
corrosion. Clean and touch up with paint as nec­essary.
Figure 16: Remove safety screen on motor end
3. Disconnect the four-wire electrical cable from the motor junction box. Make note of wire locations for reinstallation later (see Figure 17).
Figure 17: Remove electrical cable
4. Mark motor pedestal location on the motor pedestal mounting angles (both sides), then loosen and re­move (four) ½” bolts that retain the motor pedestal to the mounting angles (see Figure 18).
Figure 15: FANWALL array
Fan Wheel and Motor Removal
1. Disconnect power to the fan array control panel before maintenance. Follow all lockout and tag out procedures.
2. Remove the optional safety screen (if provided) on the motor end only of the cube in question by re­moving all four hex screws from the holding flange that retains the safety screen (see Figure 16).
VCES-V-CUBE-IOM-1A
Figure 18: Remove motor pedestal retaining bolts
21
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
5. After removing the motor pedestal 5. retaining bolts, slide the motor/fan/pedestal assembly out to the point where the motor lifting ring is clear of the cube frame enough to use. If a mechanical device is avail­able for use, attach it to the motor lifting ring. Lift and remove the motor pedestal with motor and fan wheel from the cube. The motor pedestal with motor and fan wheel can be turned 180º and slid back into the cube on the pedestal mounting angles or re­moved from unit for further disassembly.
6. Mark the location of the trans-torque bushing on the shaft and the fan. To remove the fan wheel from the motor shaft, remove the trans-torque bushing retain­ing hex nut using a 1” socket with a 12” extension by turning counter clockwise. Loosen progressively until the bushing is free from wheel hub and motor shaft. Remove fan wheel/hub assembly (see Figure 19).
Figure 19: Mark location and remove trans-torque bushing and fan wheel from motor.
7. If needed, the motor may now be removed for ser­vice by removing all (four) 3/8” motor retaining nuts and bolts. Be sure to mark the motor base pattern and bolt holes used on the motor pedestal. Rubber isolator pads between the motor base and the ped­estal are optional and if supplied be sure not to lose them (see Figure 20). If the motor is to be replaced, make sure to remove the shaft grounding ring off the front of the motor that is being replaced. Install the shaft grounding ring onto the new motor by drill­ing and taping mounting holes. Use a 7/64” or a #35 drill bit and #6-32 tap. Clean away any chips and shavings before installing the shaft grounding ring.
Figure 20: Remove motor retaining bolts; do not lose rub­ber isolator pads (if provided).
8. To reinstall the motor, fan wheel and fan wheel/ motor/pedestal assembly back into the cube, reverse the steps above noting the following: a. Insert the (four) 3/8” motor retaining bolts into
the holes in the motor pedestal from the under­side, make sure to use a standard washer on the bolt side, install the rubber isolator pads (if sup­plied) between the pedestal and motor base and only a locknut is required on the motor side.
b. Square the motor on the pedestal according to
markings and tighten the bolts. With rubber iso­lator pads tighten the bolts to 20 ft-lbs. Without rubber isolator pads tighten the bolts to 40 ft-lbs.
c. Install the fan wheel on the motor shaft with the
hub facing towards you. Line up the markings on the hub/trans-torque bushing/shaft. Make sure that the trans-torque bushing nut is flush to the hub. Tighten the bushing nut progressively to 80 ft-lbs turning clockwise.
9. Lift the motor pedestal with motor and fan wheel (turn 180º if placed on the pedestal mounting angles for disassembly) with the fan wheel inlet toward the inlet cone. Place motor pedestal into the cube on the pedestal mounting angles and slide the pedestal forward to the line that you previously marked. Line the four pedestal bolt holes up with the bolt holes on the mounting angles. Insert (four) ½” bolts into the holes, make sure to use a standard washer on the bolt side and a standard washer and lock washer on the nut side. Hand tighten the bolts for now.
10. Check the inlet cone alignment to the fan wheel. Fan wheel should not be rubbing against the fan inlet cone when rotated by hand. The fan wheel to inlet cone clearance should be approximately 1/16” gap and the overlap should be as indicated in Appendix
I for the fan wheel size. Adjust the overlap of the
wheel and cone by moving the motor pedestal for-
VCES-V-CUBE-IOM-1A
22
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
ward or backward. Fan wheel should not be rubbing on the inlet cone. If cone alignment is required see instructions for Fan Wheel/Cone Alignment below. Once alignment and overlap are correct tighten the (four) ½” pedestal mounting bolts to 90 ft-lbs.
sembly can be performed. Note the directions of the damper blades are running vertical. The damper is installed directly onto the FANWALL® cube inlet side panel and over the optional airflow straightener (if supplied).
Figure 22: Fan wheel/cone alignment – Step 2a
Figure 21: Check fan wheel/cone alignment and overlap.
11. Reconnect the four-wire electrical 11. cable from the motor junction box. Before operation, start the motor slowly to ensure the fan rotation is correct. If the fan wheel is not rotating correctly, check the motor leads for proper installation. a. Drive side – Clockwise rotation when looking at
motor end.
b. Inlet side – Counter clockwise rotation looking at
fan inlet.
IMPORTANT
Before restarting, re-balance the fan wheel once the motor rotation and alignment have been corrected be­fore placing the unit in operation.
Fan Wheel/Cone Alignment
1. To align fan wheel/cone, first disconnect power to the fan array control panel. Follow all lockout and tag out procedures.
2. If the optional backdraft damper is furnished on the inlet side of the fan it must be removed first. Remove all tek screws on all sides attaching the damper frame to the inlet side panel and remove it from the cube. The purpose of the damper is so that main­tenance staff can block the intake of a single fan to prevent back flow until service on an inoperative as-
Figure 23: Fan wheel/cone alignment – Step 2b
3. If the optional airflow straighteners are furnished on the inlet side of the fan it must be removed next. Re­move all tek screws on the airflow straightener panel frame and remove it from the cube.
Figure 24: Fan wheel/cone alignment – Step 3
VCES-V-CUBE-IOM-1A
23
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
4. Gently rotate the fan wheel to verify location of ad­justment required.
Figure 25: Fan wheel/cone alignment – Step 4
5. To make adjustment, loosen (do not remove) all the cone retaining fasteners.
7. Gently rotate the fan wheel to verify cone adjust­ment for proper clearance from wheel.
Figure 28: Fan wheel/cone alignment – Step 7a and Step 9a
Figure 26: Fan wheel/cone alignment – Step 5
6. Using a rubber mallet, gently tap around the cone until desired clearance is acquired between fan wheel and inlet cone.
Figure 29: Fan wheel/cone alignment – Step 7b and Step 9b
8. Tighten all the cone retaining fasteners.
Figure 30: Fan wheel/cone alignment – Step 8
9. Once again gently rotate the fan wheel to verify cone alignment.
10. To install the optional airflow straightener or back­draft damper reverse the steps above.
Figure 27: Fan wheel/cone alignment – Step 6
VCES-V-CUBE-IOM-1A
24
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Blank-off Plate (if applicable)
1. Optional blank-off plate(s) are available so that main­tenance staff can block the intake of a single fan to prevent back flow until service on an inoperative as sembly can be performed or it can be mounted on spare FANWALL® cube(s) until they are required to be put into service.
2. First disconnect power to the fan array control panel. Follow all lockout and tag out procedures.
3. The blank-off plate is fitted to the inlet side of the FANWALL cube on the optional airflow straight­ener panel frame (if supplied) or onto a matching “Z” frame. There are 12 pre-drilled holes which are located in the corners and middle of the airflow straightener panel frame or “Z” frame matching predrilled holes in the blank-off plate for fastening together with tek screws.
4. Place the blank-off plate over the optional airflow straightener panel frame (if supplied) or onto the matching “Z” frame and pre-drilled holes and fasten together with or remove tek screws.
Figure 32: Blank-off plate – Step 4
Figure 31: Blank-off plate – Step 3
VCES-V-CUBE-IOM-1A
25

Motors

!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Motors will operate effectively for years if they are kept clean, dry and properly lubricated. An excessive running current is a good indication of the overall condition of the motor. Check the following items every six months (unless otherwise indicated) for proper performance:
Motors must be cleaned with moderate air pressure (around 25 to 30 psi). Dirt must be blown away from vent fins and all other accessible areas. All areas sur­rounding the motor must be kept clear so air can circulate freely to cool the motor.
Ensure all connections are secure. Look for loose wires and loose contacts. Repair and tighten any de­fective connection.
Ensure the motor is operating at the current indi­cated on the nameplate. If not, a physical or electrical restriction is working against the motor and it must be repaired.
Ensure the motor is not vibrating too much. A signifi­cant vibration can come from a loose mounting bolt or an unbalanced impeller. If significant vibration has occurred, be sure to repair it and inspect the mount­ing base and the flexible duct connection for any damage.
Motor lubrication must occur once a year when grease nipples are provided with a premium quality lithium based grease conforming to NLGI Grade 2 or 3 (examples are Mobil Mobilith AW2, Chevron Amo­lith#2, Texaco Premium RB, Shell Alvania #2 or Esso Beacon #325). Clean the grease nipple first, then rotate the motor shaft slowly by hand while adding grease with a low pressure grease gun. Do not over lubricate!

Filters

Standard 2” [51 mm] and 4” [102 mm] prefilters are dis­posable and should be replaced every three months or sooner if the pressure drop across the filters is too great. High efficiency filters (optional) should be replaced when dirty. Venmar CES recommends that they be used only in combination with 2” [51 mm] or 4” [102 mm] prefilters in order to protect them from premature clogging and to increase their effective lifespan. The tables in Appendix J provide data relative to the pressure drop across clean fil-
Dirt on the surface of the coil reduces its ability to transfer heat which lowers the efficiency of the unit, resulting in poor air quality and expensive operating costs. Because of the condensate on the coil, the dirt often becomes wet and contributes to the growth of microbial organisms. Negligence in maintenance may result in serious health related indoor air quality problems. The coil should be kept clean for maximum performance. To achieve maxi­mum efficiency, clean the coil often during periods of high demand or when dirty conditions prevail. Venmar CES recommends cleaning the coil a minimum of once per year to prevent dirt buildup in the coil fins where it may not be visible.
ters and indicate the type of reading that should be given on the magnahelic gauge. The data relative to accurate pressure drop across the filters is available in the submit­tal. If the system is equipped with both prefilters and final filters, it is recommended that prefilters be changed twice as often as final filters. Running a unit with dirty and inef­ficient filters will lower the airflow and thus lower the air quality of the area.

Coils

CAUTION
Do not use acidic chemical coil cleaners. Do not use alka­line chemical coil cleaners with a PH value greater than
8.5 or lower than 6 (after mixing) without using an alu­minum corrosion inhibitor in the cleaning solution. Using these types of cleaners may result in unit damage. Coil fins can be cleaned by using steam with detergent, hot water spray or a commercial chemical coil cleaner. After cleaning the coil, be sure to rinse thoroughly.
VCES-V-CUBE-IOM-1A
26
!
WARNING
Many of the following steps need to be performed with the unit powered off and locked out. Disconnect the main power switch to the unit before performing service and maintenance procedures.
Cleaning Procedure
1. Shut down the unit by closing the main disconnect at the power inlet.
2. Open panels or doors to gain access to both sides of the coil section.
3. Remove soft debris from both sides of the coil with a soft brush.
4. Using a steam cleaning machine, clean the leaving air side of the coil first (going downward) then clean the entering air side. Use a block-off to prevent the steam from penetrating a dry section of the unit.
5. Allow the unit to dry thoroughly before restoring power.
6. Damaged coil fins should be straightened by using a fin comb.
7. Close all panels and doors once the coil is dry.
8. Restore electrical power to the unit.

Controls

General controls information regarding the navigation and monitoring of your unit with the standard keypad, DDC points list, ladder diagram and specific sequence of opera­tion or required network communication is included in the

Troubleshooting

See Appendix K for trouble shooting information.
documentation that is contained in the control panel of your unit. Please contact the factory if this information is missing or has been lost.
VCES-V-CUBE-IOM-1A
27
Appendix A: Water Cooled Condenser (WCC) Piping Installation,
Maintenance and Troubleshooting
Units have the WCC supply and return line internally coupled (manifold) and piped to the unit exterior. The WCC connections shall have copper IPS connections. See the submittal drawings for size, location, flow rate, type of fluid, pressure drop information and components included and factory installed for the supply and return connections.
Optional Water Piping Components
The following components may or may not be included and factory installed depending on the water conditions and/or options selected.
1. A two-way or three-way modulating 1. head pressure control valve may be included in the compressor or coil compartment to maintain stable operation of the refrigeration systems when operated on ground loop or cooler water systems when the design inlet water temperature is below 70ºF in the cooling mode. A re­frigerant pressure transducer is also included and fac­tory installed in the compressor compartment on the compressor discharge, which will modulate the water flow to the condenser using a 2 to 10 VDC signal to prevent the compressor discharge pressure from fall­ing below the compressor operating limit. The regu­lating valve may be factory installed or shipped loose for field installation depending on the unit configura­tion and/or options selected
2. A flow switch on the water return or leaving side of the condenser is factory provided and installed in the compressor or coil compartment to monitor the pres­ence or absence of flow, which will shut down the compressor operation if no flow is detected.
3. A water temperature sensor on the water supply or entering side of the condenser is factory provided and installed in the compressor or coil compartment to monitor the water temperature, which will shut down/disable the compressors if the entering water temperature drops below 70ºF. For units with wa­terside economizer coils (WiSE), the entering water temperature sensor shall be utilized to compare the unit entering water temperature to the unit entering air temperature and enable WiSE operation when ap­plicable.
4. A waterside economizer coil (WiSE) along with dual two-way modulating water economizer valves and a temperature sensor shall be supplied with the unit. The water temperature sensor is input to the DDC control system, which determines when to divert water to the economizer coil for energy conservation in cooling mode.
Water Piping Components Not Included
Water piping vibration eliminators, manual or automatic shut-off valves, pressure and temperature gauges, water strainer, vent valves or air vents, flow measuring and balancing valves, pressure relief valves or other safety or
control piping requirements are not available and must be field provided and installed outside of the unit.
IMPORTANT
WCC external water supply and return piping shall be in accordance with National and Local Codes. Line sizing, pressure limiting devices, backflow preventers, strainers, valves, flow temperature and pressure measuring, freeze protection, all other safety or control piping requirements for system operation are the sole responsibility of the Installing Contractor and/or Design Engineer. The water supply must be sized for the maximum flow as indicated on the submittals.
Recommended Piping, Components and Installation
Recommended and required WCC water line piping and components with a detailed functional description are out­lined below:
1. All WCC should be connected to supply and return piping in a two-pipe reverse return configuration. A reverse return system is inherently self-balancing and requires only trim balancing where multiple quanti­ties of heat pumps with different flow and pressure drop characteristics exist in the same loop.
2. The water line piping may be steel, copper or PVC. Avoid dissimilar metal fittings as they may corrode. The piping should be installed with a minimum number of bends and elevation changes for best per­formances. Size piping to minimize system pressure drop.
3. Water line piping should contain: a. Short sections of high pressure flexible hose or vi-
bration eliminators to reduce vibration and noise transmission .One end of the hose should have a swivel fitting to facilitate removal for service. Hard piping connections are not recommended due to the possibility of vibration that could dam­age piping connections, joints or transmit noise. Where hard piping is used unions should be provided in the supply and return lines for service and removal.
b. Manual shut-off valves in supply and return
water lines for isolation and service.
c. Pressure and temperature gauge connections in
the supply and return water lines to aid in start­up and service.
d. A water strainer (16–20 mesh minimum) or some
means of removing foreign matter from the water.
e. Manual vent valves and/or automatic air vents at
the high points of the system in the supply and return water lines to discharge non-condensable
VCES-V-CUBE-IOM-1A
28
air in order to avoid unexpected high head pres-
!
sure and poor cooling/heating performance.
f. A flow balancing valve in the return water line to
set the required flow rate.
g. A flow measuring valve or pressure gauge/con-
nections in the return water line to measure the required flow rate.
h. A two-way motorized on/off water shut-off valve
to isolate water flowing through both the econo­mizer coil (if equipped) and water-to-refrigerant condenser for conservation when the unit is off. The motorized water valve must open 90 seconds prior to compressor start-up and remain open five seconds after the compressor is shut off.
i. A relief valve in the water supply or inlet line if
the maximum pressure of components is less than the water supply pressure to prevent dam­age, injury or death due to instantaneous release of high pressure water.
WARNING
To prevent injury or death due to instantaneous release of high pressure water, provide relief valves on system water piping. This will also help prevent water pump damage or stoppage due to excessive system pressure.
4. WCC should not be connected to the incoming sup­ply and return piping until the water supply system has been cleaned and flushed completely. After the cleaning and flushing has taken place, the initial con­nection should have all valves wide open in prepara­tion for the water system flushing.
5. Automatic flow controlled devices must not be in­stalled prior to system cleaning and flushing.
Cleaning and Flushing
1. Prior to first operation of the WCC, the water circula­tion system must be cleaned and flushed of all con­struction dirt and debris by the Installing Contractor.
2. Short circuit connect the incoming supply line to the outgoing return line, prior to the factory installed piping at each connection point, before flushing to prevent the introduction of dirt into the unit from the supply line completed on site. This will prevent the introduction of dirt into the unit.
3. Fill the system at the city water makeup connection with all air vents open. After filling, close all air vents.
4. Start the main circulator with the pressure reducing valve open. Check vents in sequence to bleed off any trapped air to provide circulation through all compo­nents of the system.
5. While circulating water, check and repair any leaks in the piping. Drains at the lowest point(s) in the sys­tem should be opened for the initial flush and blow down, making sure city water fill valves are set to
make up water at the same rate. Check the pressure gauge at the pump suction and manually adjust the makeup to hold the same positive steady pressure both before and after opening the drain valves. Flush should continue for at least two hours or longer until clean drain water is visible.
6. Shut off the circulator pump and open all drains and vents to completely drain down the system. Short circuited supply and return lines coming to the unit should now be removed and supply and return lines connected to the unit supply and return connections. Do not use sealers at the swivel flare connections of the hose(s).
7. Install any automatic flow controlled devices that were removed for flushing.
8. Refill the system with clean water. Test the water using litmus paper for acidity, and treat as required to leave the water slightly alkaline (pH 7.5 to 8.5). The specified percentage of antifreeze may also be added at this time. Use commercial grade antifreeze designed for HVAC systems only. Do not use auto­motive grade antifreeze.
9. Once the system has been filled with clean water and antifreeze (if used), precaution should be taken to protect the system for dirty water conditions. Dirty water will result in system wide degradation of per­formance and solids may clog valves, strainers, flow regulators, etc. Additionally, the heat exchangers may become clogged which reduces compressor ser­vice life or causes premature failure.
10. Start the circulation pumps. After full flow has been established through all components, air vented, lines checked for leaks and loop temperatures stabilized, the WCC will be ready for check, start-up and water a. balancing.
General Maintenance
Recording of performance measurements of volts, amps, and water temperature difference (both heating and cool­ing) is recommended. A comparison of logged data with start-up and other annual data is useful as an indicator of general equipment condition.
Periodic lockouts almost always are caused by air or water problems. The lockout (shut-down) of the unit is a normal protective result. Check for dirt in the water system, water flow rates, water temperatures, airflow rates (may be dirty filters), and air temperatures. If the lockout occurs in the morning following a return from the night setback, enter­ing air below machine limits may be the cause.
Water treatment is important for proper condenser opera­tion. More frequent cleaning will be necessary if water is not properly treated. For water treatment instruction, con­sult your local water treatment specialist.
VCES-V-CUBE-IOM-1A
29
Monthly
!
Check water cooled condensers for scaling and pro­ceed with brushing and cleansing if necessary.
Quarterly
Check oil level in compressor (half site glass).
Semi-annually
Check operation of crankcase heaters.
Check for broken or loose pipe clamps.
Check moisture indicator of refrigerant site glass. A “Caution” or “Wet” condition requires changing fil­ter drier. If “Wet” condition does not improve, it will be necessary to evacuate system.
Yearly
Look for any sign of oil on all refrigeration compo­nents including coils, compressors, controls, tubing, etc. Oil would indicate a refrigerant leak.
Check water lines for leaks.
Check expansion valve bulb (properly attached to suction line, properly isolated).
Check the condensate drain pan and clean and flush as required.
Troubleshooting
Lubrication
R410a should be used only with polyolester (POE) oil. The HFC refrigerant components in R410a will not be compat­ible with mineral oil or alkylbenzene lubricants. R410a systems will be charged with the OEM recommended lu­bricant, ready for use with R410a.
Charging
Due to the zeotropic nature of R410a, it should be charged as a liquid. In situations where vapor is normally charged into a system, a valve should be installed in the charging line to flash the liquid to vapor while charging.
CAUTION
It is very important to make certain that the recycle or re­covery equipment used is designed for R410a. The pres­sure of R410a refrigerant is approximately 60% greater than that of R22. Pressure gauges require a range up to 800 psig high side and 250 psig low side. Recovery cylin­ders require a 400 psig rating.
IMPORTANT
Filter driers must be replaced each time a system is open to atmosphere (ex.: for a defective component replace­ment, refrigerant leak, etc.).
Compressor Burnout
When a motor burnout occurs in a compressor, the result­ing high temperature arc causes a portion of the refriger­ant/oil mixture to break down into carbonaceous sludge,
corrosive acid, and water. Such contamination resulting from a burnout can result in repeat failures if the contami­nants are allowed to reach and remain in the crankcase of the replacement compressor. This situation can be prevented by following proper cleanup procedures after a burnout.
To determine if a compressor burnout has actually oc­curred, run the proper electrical tests. This requires an ac­curate VOM Meter.
1. With all wires removed from the compressor termi­nals, measure resistance from each terminal to the compressor casing. If any terminal shows a direct ground (zero resistance), a failure has occurred. If not, continue.
2. With all wires removed from the compressor terminals, measure resistance from each compressor terminal. They should read the same. If two or more terminals show zero resistance between them, the compressor motor has failed (for actual resistance value, refer to the respective compressor manual or contact the Cus­tomer service Department at Venmar CES).
3. If steps 1 and 2 have not clearly identified a compres­sor failure, it will be necessary to meg the compres­sor motor (refer to the respective compressor manual or contact the Customer service Department at Ven­mar CES).
Compressor Burnout – System Cleanup
Any maintenance requiring refrigerant evacuation must be performed using proper recovery procedures.
1. In order to avoid losing refrigerant to the atmo­sphere, recover refrigerant using standard recovery procedures and equipment. Remove the inoperative compressor, and install the replacement.
2. Since the normal color of refrigerant oil varies from oil to oil, take a sample of oil from the replacement compressor and seal in a small glass bottle for com­parison purposes after the cleaning operation is com­plete. Suitable two ounce bottles are available at any drug store.
WARNING
Acid burns to the skin can result from touching the sludge in the burned out compressor. Rubber gloves should be worn when handling contaminated parts.
3. Inspect all system controls such as expansion valves, solenoid valves, check valves, reversing valves, con­tactors, etc. Clean or replace if necessary, remove all installed filter driers.
IMPORTANT
Before starting the new compressor, replace any ques­tionable components.
VCES-V-CUBE-IOM-1A
30
4. Install the recommended size suction 4. line filter drier and new size liquid line filter drier. Evacuate sys­tem using the triple evacuation method. Re-charge the system with new refrigerant (do not use the re­covered refrigerant). See unit’s nameplate for proper refrigerant charge.
5. Start the compressor and put the system in opera­tion. As the contaminants in the system are filtered out, the pressure drop across the suction line filter drier will increase. Observe the differential across the filter drier for a minimum of two hours. If the pres­sure drop exceeds the maximum limits for a tempo­rary installation, replace the filter drier and restart the system (see literature from filter drier’s manufacturer for pressure drop maximum limits.)
6. After the completion of Step 5, allow the unit to op­erate for 48 hours. Check the odor (warning – smell
cautiously) and compare the color of the oil with the sample taken in Step 2. Use of an Acid Test Kit is recommended to test for acid content. If the oil is discolored, has an acid odor, is acidic or if the mois­ture indicator indicates a high moisture content in the system, change the filter driers. The compressor oil can be changed if considered desirable. Allow the system to operate for an additional four hours, and recheck as before. Repeat until the oil remains clean, odor and acid free and the color approaches that of the original sample.
7. Replace the liquid line filter drier with one of the normally recommended size. Remove the suction line filter drier.
8. After the cleaning procedure is completed, recheck in approximately two weeks to ensure that the system condition and operation is completely satisfactory.
VCES-V-CUBE-IOM-1A
31

Appendix B: Positive and Negative Pressure Trapping

L = H + K + pipe diameter + insulation − X
L = H + J + pipe diameter + insulation − X
Positive Pressure Trapping
Removable plug
Cleanout
K = Minimum 0.5” [13 mm] H = 0.5” [13 mm] + maximum total static pressure X = 3.9375” [100 mm] if unit has a 6” [152 mm] tubular steel base
Negative Pressure Trapping
X
L
K
H
H = 1” [36 mm] (for each 1“ [25 mm] of maximum negative static pressure) + 1” [25 mm] J = Half of H X = 3.9375” [100 mm] if unit has a 6” [152 mm] tubular steel base
VCES-V-CUBE-IOM-1A
Removable plug
Cleanout
X
L
H
J
32

Appendix C: V-Cube™ Start-up Report and Checklist

IMPORTANT
Complete this form for each unit and email, fax or mail to Venmar CES immediately after start-up to validate warranty and to provide valuable informa­tion for personnel performing future maintenance or for factory assistance to address below.
Read the Installation, Operation and Maintenance Instructions Manual and the EPiC™ System Keypad Operation Guide and the Sequence of Operation before proceeding.
Leave a copy of this report with the owner and at the unit for future reference and permanent record.
To ensure proper operation of each unit, qualified personnel should perform the start-up, complete the checklist and report.
All units are functionally tested except when shipped in multiple pieces. Start-up adjustments may be required. If the unit is shipped as a single piece, blowers and compressors (if equipped) are set up to run correctly when power is connected. If any blower is running backwards or compressor is mak­ing loud noises, disconnect power and switch two leads (on three-phase power) to ensure proper rota­tion and avoid damage.
If units are equipped with compressors, power must be turned on for 24 hours prior to a call for cooling, for the compressor crankcase heaters to be energiz­ing to prevent possible damage.
The Bacview keypad located at the control panel will allow for manual override for start-up, mode of operation selection and includes an internal time clock if remote interlocks are not provided.
Venmar CES Inc. 200 Rue Carter St.-Léonard-d’Aston, QC Canada J0C 1M0
Email to tech support: venmarservice@venmarces.com Fax: 899-319-2612 Phone: 1-866-4-VENMAR
Unit Identification Information
Project ____________________________________________ Job Name _________________________________________ Job Address _______________________________________ Model Number _____________________________________ Serial Number ______________________________________ Tag ______________________________________________ Jobsite Contact ____________________________________ Email _____________________________________________ Telephone _________________________________________
Table C1: Pre Start-up Checklist
Checklist Item Yes N/A
1 Is the electrical disconnect set to the ‘Off’ position? 2 Have the split section joints been properly installed on multi-sectional units?
Have all holes made by the Installing Contractor in the casing, partitions or floor been well sealed
3
to prevent air and/or water infiltration? Have obstructive packaging, objects near or in fans, dampers, etc. been removed?
4
a. Has the inside of the unit been cleaned of all debris? Have all retaining bolts on fan bases been removed? a. Do all the fan impellers rotate freely? b. Are all fan impellers and drive set screws tight?
5
c. Are all the fan bearing set screws or locking collars tight? d. Are all fan belts aligned and have proper tension? e. Are the fan flexible joint connections well attached? Are all air filters installed and clean? a. Are all face-mounted filters attached with four clips each?
6
b. Do all sliding filters have a retainer at the end track and well attached blank-offs? c. Are the filter pressure differential gauges, switches or sensors free of dirt and set at a value
satisfactory to the end user to trigger a filter change?
VCES-V-CUBE-IOM-1A
33
Serial Number: _____________________________________
Table C1: Pre Start-up Checklist
Checklist Item Yes N/A
Have coils been checked for fin damage and dirt, straightened with a fin comb and cleaned? a. Are all pipe connections tight and have they been checked for damage that may have occurred dur-
7
ing shipping or installation? b. Has the piping to the coils and WSHP/WCC been completed and have the piping lines been flushed, filled, vented and tested at 1.2 times the operating pressure? Scroll compressor RIS vibration isolator bolts are factory tightened to the correct torque setting for operation and do not require field adjustment. a. Are the refrigerant components and piping in good condition and have no damage or leaks from shipping or installation? b. Are the refrigerant lines spaced at least 1” apart and from the compressor after shipping and
8
installation? c. Are the refrigerant line clamps still secure and have their rubber lining? d. Is the clearance around the air cooled condenser within minimum clearance and the discharge
clear from blockage? Are all motorized damper control arms, control rods and shafts tight?
9
a. Do all non motorized dampers rotate freely? 10 Is the ductwork connected, complete and free of obstructions? 11 Have all condensate drain connections been trapped, installed correctly and filled? 12 Are all shipped loose or field supplied components correctly installed and wired? 13 Has the wiring diagram been marked up accordingly and left with the unit? 14 Has the power supply and control wiring been inspected and approved by the Local Authorities? 15 Have factory and field wiring connections been checked and tightened?
Is voltage at the disconnect switch within 10% of nameplate and are phase-to-phase readings 16
within 2% of nameplate?
Have field piping and venting installation, connections for heating and cooling options been com­17
pleted and tested? 18 Are heating and cooling enable switches set to the ‘Off’ position?
19 Has the electric coil installation and pre start-up checks been completed per Appendix E? 20 Have all safety switches, overloads or other devices that are manual reset been checked and reset?
If units are equipped with compressors, has power been turned on for 24 hours prior to a call for 21
cooling?
VCES-V-CUBE-IOM-1A
34
Serial Number: _____________________________________
Table C2: Start-up Checklist
Checklist Item Yes N/A
1 Before proceeding, complete the Pre Start-up Checklist. 2 Close all access panels or doors. 3 Turn the main disconnect to the ‘On’ position.
The unit can be started by using the keypad and selecting the mode of operation from the Keypad Operation Guide and the Sequence of Operation. Run through the complete sequence of operation
4
of the unit, adjusting setpoints and documenting as required. Once completed, return the unit to the correct mode of operation and adjust the time clock if required.
5 Are dampers operating properly? 6 Are fans rotating in the correct direction? 7 Adjust the supply air fan motor VFD to the correct supply air.
For occupied recirculation mode, adjust outside air and exhaust air damper positioner to achieve
8
the required air volumes. Check amperage draw to each motor on each phase against motor nameplate FLA. If significantly
9
different, check ductwork static and/or take corrective action. Recheck the voltage at the disconnect switch against the nameplate and against phase-to-phase
10
readings on three-phase with all blowers operating. If the voltage is not within 10% of rated or 2% of phase-to-phase, have the condition corrected before continuing start-up. Feel the compressor crankcases. They should be warm if the disconnect has been on for at least
11
24 hours. This will assure that no refrigerant liquid is present in the crankcase which could cause compressor damage or failure to occur on start-up. Before activating the compressor on WSHP units, are water shut-off valves open and is water circu-
12
lating through the water-to-refrigerant heat exchanger? Check the incoming line water pressure to ensure it is within design and acceptable limits.
13 Enable cooling and check if the sound of the compressor is normal or if there is excessive vibration. 14 Check all field and factory refrigerant and water piping connections for leaks and correct.
On units with WSHP, after a few minutes of operation: a. Check the supply discharge temperature status on the keypad for cooling air delivery. Mea-
sure the temperature difference between entering and leaving water. In cooling mode, the temperature difference should be approximately 1.5 times greater than the heating mode temperature difference. For example, if the cooling temperature difference is 15ºF [8.3ºC], the heating temperature difference should be approximately 7ºF to 10ºF [3.9ºC to 5.6ºC]. Adjust the combination shut-off/balancing valve in the return line to a water flow rate which will
15
16
17
18 Enable heating options; see Start-up and check instructions in Appendix E for electric coil and complete.
19
20 Check the operation of the control options provided on the unit. 21 Check the setpoints on the DDC Points Reference, adjust and record changes as required. 22 Has air balancing been completed for both occupied and unoccupied operation?
23
VCES-V-CUBE-IOM-1A
result in the 7ºF to 10ºF [3.9ºC to 5.6ºC] difference. Alternatively, if a flow measuring valve or pressure gauge connections are included, take the flow reading or pressure drop compared to the submittal information and adjust the shut-off/balancing valve in the return line to the cor­rect flow/pressure drop reading.
b. Measure the temperature difference between entering and leaving air and entering and leav-
ing water. With entering water of 60ºF to 80ºF [15.6ºC to 26.7ºC], leaving temperature should rise through the unit (should not exceed 35ºF [19.4ºC]). If the air temperature exceeds 35ºF [19.4ºC], then the water flow rate is inadequate or the airflow rate may be low and a second
check may be required after airflow balancing. On units with integrated air cooled condensers, check condenser fans are rotating in the correct direction. Measure the temperature difference between entering and leaving air. On units with electric heating coils, check supply air proving interlock switch setting to ensure mini­mum supply airflow prior to operation.
For electric heating coil option, check the amp draw on each stage, the operation of the sequence or SCR controller and the coil for any hot spots.
When unit has achieved steady state, take measurements and complete readings section of start-up report!
35
Serial Number: _____________________________________
Nameplate voltage
Input voltage L1–L2 L2–L3 L1–L3
Table C3: Start-up Readings – Supply Fans
Fan 1
Fan 2
Fan 3
Fan 4
Fan 5
Fan 6
Fan 7
Fan 8
Fan 9
Fan 10
Fan 11
Fan 12
Rotation
Correct
Nameplate
Amps
Amp Draw
L1 L2 L3
Full
Load
Amps
O/L
Amp
Setting
RPM
Min.
Hertz
O/L Set at Min.
Hertz
Max.
Hertz
O/L Set at Min.
Hertz
Table C4: Start-up Readings – Exhaust Fans
Amp Draw
L1 L2 L3
Fan 1
Fan 2
Fan 3
Fan 4
Fan 5
Fan 6
Fan 7
Fan 8
Fan 9
Fan 10
Fan 11
Fan 12
Rotation
Correct
Nameplate
Amps
Full
Load
Amps
O/L
Amp
Setting
RPM
Min.
Hertz
O/L Set at Min.
Hertz
Max.
Hertz
O/L Set at Min.
Hertz
VCES-V-CUBE-IOM-1A
36
Table C5: Start-up Readings – Condenser Fans
Rotation
Correct
Fan 1
Fan 2
Fan 3
Fan 4
Fan 5
Fan 6
Fan 7
Fan 8
Fan 9
Fan 10
Fan 11
Fan 12
Fan 13
Fan 14
Fan 15
Fan 16
Nameplate
Amps
Serial Number: _____________________________________
Amp Draw
L1 L2 L3
Full Load Amps
O/L Amp
Setting
Table C6: Start-up Readings – Compressors
Amp Draw
Nameplate
Amps
Compressor 1
Compressor 2
Compressor 3
Compressor 4
Compressor 5
Compressor 6
Compressor 7
Compressor 8
Compressor 9
Compressor 10
Compressor 11
Compressor 12
Compressor 13
Compressor 14
Compressor 15
Compressor 16
L1 L2 L3
Full
Load
Amps
After compressor has been running for 15 minutes, check for the
Suction
Pressure
Discharge
Pressure
Super-
heat
following:
Liquid
Subcooling
Hot Gas
Bypass
Functioning
Outdoor Ambient
Temperature
During AC
Cooling
Start-up
(°F/°C)
VCES-V-CUBE-IOM-1A
37
Serial Number: _____________________________________
Table C7: Start-up Readings – Water Source Heat Pump (WSHP)/Water Cooled Condenser (WCC)
Waterside Cooling Mode Waterside Heating Mode
Entering
Temperature
(°F/°C)
Condenser 1
Condenser 2
Condenser 3
Condenser 4
Condenser 5
Condenser 6
Condenser 7
Condenser 8
Condenser 9
Condenser 10
Condenser 11
Condenser 12
Condenser 13
Condenser 14
Condenser 15
Condenser 16
Leaving
Temperature
(°F/°C)
Temperature
Difference
(°F/°C)
Table C8: Start-up Readings – Electric Heating Coil
Stage L1 Amps L2 Amps L3 Amps Check for Hot Pots
1
2
3
4
5
6
Entering
Temperature
(°F/°C)
Leaving
Temperature
(°F/°C)
Temperature
Difference
(°F/°C)
Entering Pressure
(PSI)
Leaving
Pressure
(PSI)
US GPM
Item Description Yes No
Is the unit stored indoors in a clean, dry environment?
1
2
3
Recommend Has a desiccant pouch been placed in the control panel?
VCES-V-CUBE-IOM-1A
Is the indoor storage facility temperature regulated to within 50ºF to 75ºF? Is the indoor storage facility humidity regulated to within 10% to 50% RH?
Is the unit mounted on a level surface along the perimeter of the base with weight evenly distributed? Has the plastic wrapping been removed from the unit to perform inspection and mainte­nance?
Has the plastic wrapping been saved for future use? Has the plastic wrapping been re-applied to the unit when the unit has been shipped to
jobsite?
38
Serial Number: _____________________________________
Item Description Inspection Date/Reading
Refrigerant pressure at storage
Compressor #1 Compressor #2
4
5
6
Compressor #3 Compressor #4 Compressor #5 Compressor #6 Compressor #7 Compressor #8
Refrigerant pressure every 3 months
Compressor #1 Compressor #2 Compressor #3 Compressor #4 Compressor #5 Compressor #6 Compressor #7 Compressor #8
Rotate blower impellers every 2 months
Supply Exhaust Other
Grease fan bearings as required
Supply Exhaust Other
Date PSIG
Date PSIG Date PSIG Date PSIG
Date Date Date Date Date Date
This unit has been checked out and started according with the above procedures and completed forms and is oper­ating satisfactorily. After 24 hours of satisfactory opera­tion shut-down the unit and check all foundation bolts, shaft bearings, drive set screws, valve train and terminals. Tighten where required.
Additional Comments: ______________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
VCES-V-CUBE-IOM-1A
Start-up
By _______________________________________________ Company Name ___________________________________ Date _____________________________________________ Email ____________________________________________ Telephone ________________________________________ Email to tech support: venmarservice@venmarces.com or Fax to: 819-399-2612.
39

Appendix D: HEPA Filter Installation

These instructions are for installing AAF HEPA filters (11½” depth) into AAF HEPA holding frames. The holding frames are available in multiple sizes and materials, but include the PN series of 30619XX-XXX, where the X’s vary with frame size and material. All frames, latches, extension legs and filters are sold separately. Please read the entire installation instructions before beginning the installation process.
Install filters into the HEPA holding frames only after the frames have been securely installed into existing ductwork or housing. Frames should be bolted or pop riveted to­gether into the permanent structure through the predrilled holes around the outside perimeter of the frames. Frames should be sufficiently caulked and sealed to prevent any air bypass or leakage.
Required tools for filter installation:
T-handle Hexkey, size 5/32”
Framing Components Required:
AAF HEPA holding frames – PN 30619XXXXX
Leg extensions, four per frame – PN 3061991- 00X
Latches, four per frame – PN 3062007-00X
Figure D3: Frame with leg extensions installed
Step 2
Insert the HEPA filter into the HEPA holding frame. The HEPA should be installed with the gasket side of the filter facing the frame. Insert the filter as far into the frame as possible, so that the gasket material is contacting the frame (see Figure D4 below).
Figure D1: Leg extensions and latches
Step 1
At the inside corner of each frame are four tabs, two per side. Place a leg extension over the four tabs as shown in Figure D2 below, then pull back on the leg extension lock­ing it into place.
Figure D2: Place leg extensions over the frame tabs, then pull back to lock the leg extension into place
Repeat Step 1 with each of the four corners. The frame with leg extensions should look like Figure D3.
VCES-V-CUBE-IOM-1A
Figure D4: Insert HEPA filter into frame, until the gasket comes in contact with the holding frame
The filter should now be resting inside of the holding frame as shown to the left. When installing the filters into
40
a frame bank of multiple frames, install the lower filters first so that the upper filters can rest on the lower filters.
Figure D5: Filter placed inside of frame
Step 3
Place a latch so that it overlaps the leg extension, as shown below in Figure D6. Align the latch’s cap screw with the threaded coupling on the end of the leg exten­sion and tighten using the hexkey. Tighten the cap screw until there is an approximately ¼” gap between the latch and the leg extension coupling as shown below in Figure D7. Repeat this step with all four corners.
Step 4
Once all four corner latches have been tightened within ¼” of the leg extension coupling, complete the installation by tightening each corner until the latch and leg extension coupling meet, as illustrated in Figure D8.
Figure D8: Tighten until latch and coupling meet
Once all four corners have been tightened, the filter should now be properly seated and sealed.
Figure D6: Latch overlapping leg extension
Figure D7: Tighten cap screw to ¼” of the coupling
VCES-V-CUBE-IOM-1A
Figure D9: Properly installed filter
Repeat the process with all remaining filters working from the bottom to the top.
41

Appendix E: Electric Heating Coil and Controls Information

This electric heating coil module covered by this appen­dix is a component of a “Listed” product, subject to the guidelines of application as designated by the Certifying Agency and outlined in the appliance Manufacturer’s In­stallation and Operation Instructions.
The information provided in this appendix applies to the electric heating coil module, installed in the appliance and to its operation, maintenance and service. Refer to the ap­pliance manufacturer’s instructions for information related to all other components.
1 – Mechanical Installation of Electric Coil Heaters
1.1 – Handling
1.1.1 Remove the shipping covers just before installation.
1.1.2 Inspect the heater carefully and report any dam­age to the manufacturer.
Do not install a damaged heater.
1.2 – Installation
Heater Position
1.2.1 The axis of the duct must always be perpendicular to the face of the heater.
1.2.2 The heating elements must always be installed horizontally.
Model SC or ST (Slip-in Type)
1.2.3 Cut an opening in the side of the duct.
1.2.4 Slip the heater into the duct until the hole is com­pletely covered by flanges around the heater.
1.2.5 Fasten the heater to the duct with sheet metal screws and seal openings with a suitable sealing compound.
1.2.6 If the heater is heavy, use additional hangers to support the heater.
Model FC or FT (Flanged Type)
1.2.7 Flange both ends of the duct outwards on three sides to match the heater’s flanges.
1.2.8 Fasten the heater to the duct with sheet metal screws (for heavy heaters, use nuts and bolts and additional hangers to support the heater).
1.2.9 Seal openings with a suitable sealing compound.
IMPORTANT
Do not install spray humidifiers upstream of duct. Install it downstream instead.
Do not cover the control box with thermal insulat­ing materials.
Use special air intake louvers of weatherproof con­struction for preheat duct heaters to avoid intake of water or snow particles.
Make sure that motorized damper blades are not blocked with snow or dirt. Inspect the dampers regularly to ensure a suitable airflow.
2 – Electrical Installation of Electric Coil Heaters
2.1 Disconnect all power sources before opening the control box and working within.
2.2 Read the nameplate carefully and consult wiring diagram before starting to wire.
2.3 – Supply Wires
Use only wires suitable for 167ºF [75ºC]. Wires shall be sized according to the Canadian Electrical Code require­ments. All wires must be brought in through knock-outs.
2.4 – Disconnecting Means
Install a disconnect switch close to the heater according to the code unless a disconnect switch is already built into the heater.
2.5 – Control Circuit Wiring
Use Class II wiring for control circuit connections to the duct heater.
2.6 – Magnetic Contactors
If magnetic contactors are mounted outside of the duct heater, use only contactors approved for:
250,000 operations when controlled by auto-reset thermal cut-out (A) and by other switching devices in series with this cut-out (thermostat, step controller, airflow switch, etc.).
100,000 operations when controlled by auto-reset thermal cut-out (A) alone.
100,000 operations when controlled by auto-reset thermal cut-out (A) plus manual reset cut-out in se­ries (A and M).
6,000 operations when controlled by manual reset cutout (M) alone.
2.7 – External Controls Ratings
Rating of external control devices shall be suitable for han­dling the VA ratings as marked on the nameplate; other­wise, a backup relay must be used.
2.8 – Airflow Interlock
Heaters are generally supplied with one extra terminal marked for fan interlock or air sensing device connection. Remove jumper between terminals I and C before con­necting the fan interlock. Select a suitable airflow sensing device of the differential pressure sensing type, with snap acting contacts. A slow make, slow brake device may cause undue cycling and in some instances chattering of the contactors. When fresh air dampers are used, make sure the heater is properly interlocked to prevent it from being energized before the damper is fully open.
VCES-V-CUBE-IOM-1A
42
3 – Operating Electric Coil Heaters
3.1 – Minimum Airflow
Ensure that sufficient airflow as marked on the nameplate is passing through the heater. Airflow should be evenly distributed across the entire face of the heater. Use air turning vane at duct elbows and splitter damper at duct branchoffs to streamline the airflow in the heater. Use suitable airflow sensing device or interlock the heater with fan. An insufficient airflow will lead to the opening of the autoreset thermal cut-out or damage to the heating ele­ments.
3.2 – Warning
The air flowing through the duct where the heater is in­stalled shall not contain any combustible particles, nor any flammable vapor or gas.
3.3 – Air Temperature
The air temperature should not exceed 120ºF [49ºC] at the heater outlet.
3.4 – Minimum Static Pressure and Air Direction
The heater is protected by a differential pressure switch. To keep the contact of this switch closed, it is necessary to maintain a minimum total pressure of 0.07” of water for a constant flow.
3.5 – Manual Reset Thermal Cut-out
This protection device is standard on all heaters of less than 300 volt and 30 kW and is optional on all other heat­ers. Please check the auto-reset thermal cut-out before resetting the manual thermal cut-out. If any defect has been detected in the auto-reset thermal cut-out, it will be necessary to replace it before resetting the manual reset thermal cut-out.
4.2 – Electrical Inspection
Two weeks after start-up, all electric connections to con­tactors should be checked and tightened up. Before each heating season, check the resistance between the heating elements and ground. It is also recommended to check the electrical connections to heating elements, magnetic contactors and main power lugs. This inspection is recom­mended monthly during the first four months of opera­tion. After that, two inspections per heating season are sufficient.
4.3 – Checkpoints
Check all fuses.
Check the resistance to ground for each circuit.
Check the resistance phase-to-phase for each circuit.
Check the tightening of connections at all contactors and heating elements.
Check all contactors.
4.4 – Off-season Maintenance
Where tubular heating elements are used, it is strongly recommended that you start the heating system from time to time. This precaution will prevent moisture from perco­lating through the terminal gaskets into the heating ele­ment and accumulating in the insulating powder. Should a heater be shut off for a long period, we recommend that you check carefully the resistance to ground for each circuit. It is important not to power a heater when too low a resistance to ground has been measured. It is also rec­ommended to pay attention to any other heater operating in normal conditions. Control components such as step controllers or modulating valves (SCR) should be main­tained and checked according to respective manufacturers instructions. Any defective components should be replaced only with identical original parts.
4 – Maintenance
All electric coil heaters have been designed to operate long term without problems. Those responsible for equip­ment and maintenance should be aware of the following suggestions.
4.1 – Visual Inspection
It is strongly recommended to complete a periodic inspec­tion. This precautionary step will help to keep your instal­lations operating well. Note these eventual first signs of problems:
Accumulation of dust on the heating elements.
Signs of overheating on the heater frame.
Traces of water or rust on the control box.
VCES-V-CUBE-IOM-1A
43

Appendix F: Extended Dormant Unit Maintenance Procedure

The following procedures must be applied to any unit which is stored for a period exceeding one month, which are required in order to maintain our warranty. Failure to comply with the procedures outlined below may result in damage and will void unit warranty.
1. Unit must be stored indoors in a clean, dry and tem­pered environment, heated in the winter and air cooled in the summer. Ambient air conditions should be from 50ºF to 75ºF with percentage RH from 10% to 50%. The unit needs to be stored in a warehouse (or some type of enclosure). Note that storing units outdoors is contraindicated and will void our war­ranty.
2. Unit must be stored on a level surface with the weight of the equipment evenly distributed through its base. The unit location must be free from exces­sive vibration and accidental impacts.
3. Once the unit has been unloaded in its resting loca­tion, the plastic wrapping must be removed from the unit by cutting along the corner edges in order to perform proper inspections and maintenance on the equipment. The plastic wrapping should be kept and re-applied to the unit when the unit will finally be shipped to the jobsite.
4. If applicable, a certified/qualified refrigeration techni­cian should record refrigerant pressures on all com­pressors at time of storage. Each compressor must maintain refrigerant pressure in the system.
5. If applicable, a certified/qualified refrigeration tech­nician should check refrigerant pressure in each compressor every three months. Refrigerant pressure must be maintained in the system. If zero pressure is found, this indicates a leak in the system. Leak(s) must be identified and repaired. A holding pressure must then be reinstalled.
6. Rotate blower impellers by hand every two months; grease fan bearings as required following proper practices. Do not over grease the bearings as this may rupture the seals and lead to premature bearing failure during operation.
7. Ensure that all unit doors are kept closed.
8. Continue above maintenance schedule until unit start-up.
For all checks listed above please complete the Extended Dormant Unit Maintenance Checklist below and send a copy to the Venmar CES service department every six months and when unit is put into service.
If the unit has been dormant for an extended period after initial start-up, all start-up checks should be repeated be­fore operating the unit. Refer to the V-Cube™ Start-up Report and Checklist in Appendix C and complete these checks. Failure to comply with the above recommenda­tions may result in component failure and surface corro­sion on the interior and exterior of the unit.
Please note that if the unit is being stored outdoors or remains dormant for an extended period after initial startup, this may result in condensation within the unit which could result in premature degradation of the unit and potential issues within the control panel. In this event, the installation of a desiccant pouch in the control cabinet is highly recommended, all ventilation ducts should be capped/covered to prevent chimney effect, all liquid pipes (water or glycol mixture) should be drained or capped off if necessary and all peripheral electrical penetrations should be properly sealed.
VCES-V-CUBE-IOM-1A
44

Appendix G: V-Cube™ Maintenance Summary Chart

Table G1: Maintenance Summary Chart – V-Cube
Item No. Description Monthly Quarterly
1 Inspect the general condition of the unit. x
General
Fans
Dampers
Air filters
Coils
Electric
Condenser fans
Cooling section
2 Remove any dirt or debris. x
3 Check for unusual noise or vibration. x
4 Lubricate the door latch mechanisms. x
5 Clean fans with stream of water. x
6 Align or replace belts and drives. x
7 Adjust belt tension. x
8 Check motor voltage and current. x
9 Lubricate the motor and shaft bearings. x
10 Lubricate motor base adjusting screws. x
11 Visual inspection for dirt or leakage. x
12 Lubricate damper linkage. x
13 Clean and replace prefilters. x
14 Clean and replace final filters. x
15 Inspect holding frames/sliding rack. x
16 Clean the coils. x
17 Winterize the water coil. x
34 Verify all electrical connections; tighten if necessary. x
35 Verify all fuse holders. x
36 Verify all motor overload settings. x
37 Inspect fan blades for cracks. x
38 Inspect for wear and tension. x
Look for oil on all refrigeration components (including coils,
39
compressors, etc.) to indicate a refrigerant leak.
40 Verify for proper superheat. x
Verify each circuit refrigerant site glass when the circuit is
41
operating under steady state, full load conditions. It should be full and clear. If not, look for refrigerant leaks.
x
x
Semi-
annually
Annually
VCES-V-CUBE-IOM-1A
45

Appendix H: Measuring and Adjusting V-belt Tension

Table H1: Measuring V-belt Tension
V-belt Cross Section
A
B
C
D
E
AX
BX
CX
3V
5V
8V
3VX
5VX
Small Sheave Diameter
Range (Inches)
3.00 to 3.40
3.60 to 4.20
4.60 to 6.00
4.60 to 5.40
5.60 to 7.40
8.60 to 9.40
7.00 to 8.50
9.00 to 12.00
13.00 to 16.00
12.00 to 15.50
16.00 to 18.00
22.00 to 27.00
17.70 to 23.60
23.70 to 31.50
31.60 to 39.60
2.10 to 3.40
3.60 to 4.20
4.60 to 6.00
3.70 to 5.40
5.60 to 7.40
8.60 to 9.40
5.80 to 8.50
9.00 to 12.00
13.00 to 16.00
2.65 to 3.35
3.65 to 4.12
4.50 to 5.60
6.00 to 10.60
7.10 to 8.50
9.00 to 11.80
12.50 to 16.00
12.50 to 16.00
17.00 to 20.00
21.00 to 24.80
2.20 to 3.35
3.65 to 4.12
4.50 to 5.60
6.00 to 10.60
4.40 to 8.50
9.00 to 11.80
12.50 to 16.00
Initial Installation
3.3
3.5
3.7
6.0
6.3
6.6
13.2
13.9
14.6
26.5
27.8
29.1
39.7
41.7
43.7
4.4
4.6
4.9
7.7
8.2
8.6
17.2
18.1
19.0
5.5
6.4
7.5
8.6
19.2
23.3
27.3
50.9
57.1
61.3
5.5
6.4
7.5
8.6
19.2
23.3
27.3
Recommended Deflection Force (lbs)
Retensioned
Maximum Minimum
2.9
3.1
3.3
5.1
5.5
5.7
11.5
12.1
12.6
22.9
24.3
25.6
34.4
36.2
37.9
3.7
4.0
4.2
6.6
7.1
7.5
15.0
15.7
16.5
4.8
5.7
6.6
7.5
16.7
20.3
23.8
44.3
49.8
53.3
4.8
5.7
6.6
7.5
16.7
20.3
23.8
2.2
2.4
2.5
4.0
4.2
4.4
8.8
9.3
9.7
17.6
18.7
19.6
26.5
27.8
29.1
2.9
3.1
3.3
5.1
5.5
5.7
11.5
12.1
12.8
3.9
4.4
5.1
5.7
13.0
15.6
18.5
34.4
38.6
41.4
3.9
4.4
5.0
5.7
13.0
15.6
18.5
Plunger with
deflection force scale (lbs)
Small O-ring Large O-ring
Figure H1: Belt tension adjustment
VCES-V-CUBE-IOM-1A
Body with deflection
distance scale (inches)
Belt Span
Deflection
Force
46

Appendix I: FANWALL® Inlet Cone Alignment

Table I1: FANWALL Wheel/Cone Alignment Dimensions (Inches)
Wheel Size Backplate OD Blade Width Backplate Extension Wheel/Cone Overlap
10 10.375 3.495 0.700 0.250
12 12.500 4.280 0.700 0.250
14 13.750 4.720 0.700 0.250
16 16.750 5.760 0.700 0.250
20 20.451 6.990 0.700 0.400
22 22.701 7.780 0.700 0.400
Blade width (100% wide)
Backplate extension
Figure I1: FANWALL inlet cone alignment
Wheel/cone overlap
Backplate OD
VCES-V-CUBE-IOM-1A
47

Appendix J: Filter Resistance and Latches

Table J1: Prefilters (MERV 8)
Depth Nominal Size
2” [51 mm]
4” [102 mm]
12” x 24” x 2” [305 x 610 x 51 mm] 24” x 24” x 2” [610 x 610 x 51 mm]
12” x 24” x 4” [305 x 610 x 102 mm] 24” x 24” x 4” [610 x 610 x 102 mm]
Table J2: 4” [102 mm] Final Filters
Filter Efficiency MERV Rating Nominal Size Capacities (CFM)
60–65% MERV 11
80–85% MERV 14
90–95% MERV 15
12” x 24” x 4” [305 x 610 x 102 mm] 24” x 24” x 4” [610 x 610 x 102 mm] 12” x 24” x 4” [305 x 610 x 102 mm] 24” x 24” x 4” [610 x 610 x 102 mm] 12” x 24” x 4” [305 x 610 x 102 mm] 24” x 24” x 4” [610 x 610 x 102 mm]
Table J3: 12” [305 mm] Final Filters
Filter Efficiency MERV Rating Nominal Size Capacities (CFM)
60–65% MERV 11
80–85% MERV 14
90–95% MERV 15
12” x 24” x 12” [305 x 610 x 305 mm] 24” x 24” x 12” [610 x 610 x 305 mm] 12” x 24” x 12” [305 x 610 x 305 mm] 24” x 24” x 12” [610 x 610 x 305 mm] 12” x 24” x 12” [305 x 610 x 305 mm] 24” x 24” x 12” [610 x 610 x 305 mm]
Capacities (CFM) Resistance @ Capacity (in. w.g.)
Medium High Medium High Final
600
1,250
600
1,200
1,000 2,000
1,200 2,400
0.12
0.12
0.12
0.12
1,000 2,000 1,000 2,000 1,000 2,000
1,000 2,000 1,000 2,000 1,000 2,000
0.23
0.23
0.27
0.27
Resistance (in. w.g.)
Initial Final
0.45 1.50
0.65 1.50
0.75 1.50
Resistance (in. w.g.)
Initial Final
0.39 1.50
0.53 1.50
0.58 1.50
1.00
1.00
1.00
1.00
Table J4: Filter Latches for Front Loading/Access
Final Filter Prefilter Latch Venmar PN
None 2” C-70 207312240
4” C-86 19516104
None C-86 19516104
4” nominal
12” HEPA
12” double header
2” Knock-on (4” + 2”) 500026048
4” Knock-on (4” + 4”) 500026049
None HEPA frame
2” VP-2 208290023
4” VP-4 19516310
None C-80 19516103
2” C-80/VP-2 19516103 / 208290023
4” C-80/VP-4 19516103 / 19516310
VCES-V-CUBE-IOM-1A
48

Appendix K: Troubleshooting

Table K1: Troubleshooting – V-Cube™
Symptom Possible Cause Corrective Action
General
Check filters and enthalpy wheel for blockage. Balance flow
Air supply too cold. Supply and exhaust air are unbalanced.
Blower wheel is rubbing on other parts. Adjust wheel or replace defective part.
Blower wheel is out of alignment. Remove the motor/blower assembly. Adjust the blower wheel.
Sheaves are out of alignment. Verify wheel alignment. Align belt using a straight edge.
Noisy unit.
Bearings wear down too quickly.
Poor airflow.
Fan motor overload.
Exhaust fan not working.
Filters are out of filter rack.
Water carryover from wet cooling coil onto the floor, motor or fan housing.
Water inside the unit.
Drain pan not properly draining.
Excessive belt tension causes bearings to screech. Adjust belt tension.
Low belt tension causes belts to squeal. Adjust belt tension.
Ducts are vibrating. Install flexible connections.
Unit is too close to occupants. Install a silencer.
Excessive vibration. Replace shaft and bearings. Verify wheel alignment.
Belt too tight. Adjust belt tension.
Fan wheel is turning the wrong direction.
Rotation speed is too low.
Filters are blocked. Replace filters.
Air leakage. Seal all leaks in ducts and unit walls.
Fan belt is slipping. Adjust belt tension.
Low static pressure.
Electric tension of motor is too low/high. Adjust tension.
Excessive fan speed. Reduce blower speed.
Low motor power. Install more powerful motors. Unit equipped with recirculation defrost system is in
defrost mode. A wire is disconnected. Connect the wire. Filters are too dirty and have been sucked into the
unit.
Filters are wet.
Filter rack is damaged. Repair filter racks and reinstall filters.
Some filter clips are missing. Order new clips from Venmar CES.
Airflow is too high. Lower airflow by adjusting the drive.
Drain pan not properly draining.
Coil bulkhead penetration. Be sure any field penetrations are sealed.
Missing or improper intermediate drain pan. Install or clean the intermediate drain pan.
Unit was not properly sealed when installed.
Electrical or piping conduits not properly sealed.
Trap is not properly installed. Revise trap installation and dimensions.
Unit is not installed on level. Revise the level of curbs.
Pressure exceeds the design.
Water Issues
of supply and exhaust air so that exhaust air is equal or greater than supply air. Install a post-heat module.
Reverse rotation or motor so that wheel turns in the direction of the arrows shown on the fan. Increase speed by increasing the diameter of motor sheave or installing a smaller fan sheave.
Verify presence of filters and other duct components. Set balancing damper so that it reduces the passage of air.
Wait until the defrost cycle is over.
Clean or change the filters and consider revising maintenance schedule. Water infiltration or condensation. See Water Issues section below.
Clean drain pan and ensure suction into the unit is not too high.
Seal all section joints. Sections under negative pressure require special attention to sealing. Inspect and seal any holes made for electrical wires or piping conduits.
Verify design pressure versus unit pressure and check the segment which houses the drain pan.
VCES-V-CUBE-IOM-1A
49
Table K1: Troubleshooting – V-Cube™
Symptom Possible Cause Corrective Action
Prefilter is wet.
Solenoid valve does not open.
Too much refrigerant is being fed to the evaporator and the superheat is too low (cannot be adjusted).
Compressors lockout on high head pressure or run at higher than design head pressure.
Condenser fan(s) short cycling.
Outside air hood is shipped loose and was not well sealed when installed. Airflow exceeds design conditions and sucks water into the unit.
Refrigerant Issues
No power to coil. Check circuit connections.
Defective solenoid coil. Replace solenoid coil. Dirt or foreign material lodged in thermostatic
expansion valve.
Defective thermostatic expansion valve. Replace thermostatic expansion valve.
Insufficient fluid flow across condenser coil.
Condenser fan failure.
High pressure control. Check for proper setting.
Service valve failure. Discharge valve fully back sealed.
Refrigerant overcharge.
Supply water temperature may be too high.
Water control valves not operating properly. Verify and repair water control valves.
Improperly set sequencing control. Set for correct pressure and differential.
Reinstall hood, ensuring the flange is properly sealed.
Redesign the hood or lower the cfm of the unit.
Disassemble valve, remove dirt and re-verify superheat.
Clean dirty condenser coil. Comb damaged fin surface with fin comb. Tighten loose fan belt(s). Verify fan rotation. Verify fan rpm. Check fuses. Verify overload. Check fan controls. Check for motor burnout.
Verify condenser subcooling (15ºF [−9ºC]). If above 15ºF [−9ºC], adjust charge based on maintaining suction pressure. Verify water temperature rise entering and leaving unit to determine if adequate water is flowing.
VCES-V-CUBE-IOM-1A
50
VCES-V-CUBE-IOM-1A
51
info@venmarces.com www.venmarces.com
Venmar CES Inc. has a policy of continuous improvement and reserves the right to change design and specifications without notice. FANWALL TECHNOLOGY and FANWALL® are trademarks of Huntair, Inc. Products in this literature are covered by one or more of the patents listed on www.ces-group.com/patents.
®
©2014 Venmar CES Inc.
VCES-V-CUBE-IOM-1A
February 2014
Loading...