Danfoss Blind flange Installation guide

Installation guide
Blind flange for IPS 8
Closing the plant system's flange
Prior to disconnecting the IPS 8 purge unit from the ammonia plant it is important to follow these steps (see fig. 1):
1. Close all supply lines from the purge points of the ammonia system (a)
2. Restart the controller to force pump-down
148R9648
4. Stop the compressor by turning the compressor switch QM1 to the off position
5. Close the SVA shut-off valve in the drain line (located under the IPS 8 (b))
6. Release the remaining system pressure to ambient pressure by opening the SNV drain valve (c). This can also be done by attaching a permanent magnet on the AKVA 10 valve for forced opening
7. Close the SNV/AKVA 10 valve before removing the IPS 8 unit
148R9648
Fig. 1
c
SNV
NH₃ bypass for draining purger
Purge line to water tank
b
SVA
a
Blind flange (code 084H5053)
Enclosed gasket
Plant piping and flange
Enclosed bolts (x4) Torque: 60 Nm (44.3 ft lb) diagonal tension
Fig. 2
© Danfoss | DCS (ms) | 2019.08 AN31522724 4072-0 00101 | 1