S19284H
Installation
S19284H (Eyewash)
S19284J (Eye/Face Wash)
Cabinet-Mounted Swing-Down Eyewash and
Eye/Face Wash
Table of Contents
Pre-Installation Information ........................... 2
S19284H Dimensions ............................... 3
S19284J Dimensions ............................... 3
Installation ........................................ 4
S19284H Assembly of Components .................... 5
S19284J Assembly of Components .................... 6
S19284H and S19284J Parts List...................... 7
S19284J
215-1741 Rev. B; ECN 13-05-014
© 2013 Bradley
Page 1 of 7 3/27/2013
P.O. Box 309, Menomonee Falls, WI USA 53052-0309
PHONE 800.BRADLEY (800.272.3539) FAX 262.251.5817
bradleycorp.com
S19284H, S19284J Installation
IMPORTANT
Installation
R
WI 53051
alls,
HENTLICH ZU
WEEK
WÖC
P.O. Box 309, Menomonee F
DAIRE
e(s) each week and sign
UNIT EACH
y malfunctions immediatel
hentlich im
TEST THIS
hrift. Jeglic
DIESES GERÄT 1ST
ESSAI HEBDOMA
Test-operate valv
Report an
Ventil(e) wöc
t immédiatement.
durch Untersc
Test le fonctionnement des v
signe en bas. S'il y à quelqu
un rappor
Date
Datum
Date
114-051
PRÜFEN.
Testbetrieb prüfen,
he Störung sofor
Signed
Unterschrift
below.
bestätigt
t melden.
y.
alves chaque semaine et
e chose qui ne v
Date Signed
Signe
THIS
SIDE
UP
a pas fait
Signed
Signed
Date
Date
P.O. BOX 309, MENOMONEE FALLS, WI 53052-0309 USA
TEL: 1-800-BRADLEY FAX: (262-251-5817)
http://www.bradleycorp.com
Read this installation manual completely to ensure proper installation, then file it
with the owner or maintenance department. Compliance and conformity to drain
requirements and other local codes and ordinances is the responsibility of the installer.
Separate parts from packaging and make sure all parts are accounted for before
Packing List
•
•
•
discarding any packaging material. If any parts are missing, do not begin installation
•
until you obtain the missing parts.
Flush the water supply lines before beginning installation and after installation is
complete. Test the unit for leaks and adequate water flow. Main water supply to the
eyewash should be “ON” at all times. Provisions shall be made to prevent unauthorized
shutoff.
The ANSI Z358.1 standard requires an uninterrupted supply of flushing fluid. Bradley
plumbed emergency fixtures require a minimum of 30 PSI (0.21 MPa) flowing pressure.
Flushing fluid should be tepid per ANSI Z358.1.
The inspection and testing results of this equipment should be recorded weekly to verify
proper operation. This equipment should be inspected annually to ensure compliance
with ANSI Z358.1.
Workers who may come in contact with potentially hazardous materials should be
trained regarding the placement and proper operation of emergency equipment per ANSI
Z358.1.
For questions regarding the operation/installation of this product, visit bradleycorp.com
or call 800.BRADLEY (800.272.3539).
Product warranties may also be found under ”Products” at bradleycorp.com.
Supplies Required:
• Piping to ½" NPT water supply inlet on unit
• Boltsforcabinetmounting
• Pipe sealant
• Sign-mounting hardware
Local codes may require the installation of a backflow prevention valve to complete proper installation. Compliance with
local codes is the responsibility of the installer. Valve must be tested annually to verify that it is functioning properly.
Backflow prevention valves are not included with the fixture and may be supplied by the contractor or purchased from
Bradley Corporation.
2
3/27/2013 Bradley • 215-1741 Rev. B; ECN 13-05-014
Installation S19284H, S19284J
S19284H Dimensions
1⁵⁄₈"
(41mm)
(395mm)
3⁹⁄₁₆"
(90mm)
15⁹⁄₁₆"
Alternate
Supply
Location
3⁵⁄₁₆"
(84mm)
3¹³⁄₁₆"
(97mm)
1¹³⁄₁₆"
(46mm)
6¹⁄₁₆"
(154mm)
1⁹⁄₁₆"
(40mm)
Ø ¼" mtg.
hole (qty. 4)
9¾"
(248mm)
23¼"–35¼"
(591mm–895mm)
to finished floor for
ANSI compliance
Alternate
Supply
Location
½" NPT
Supply
16³⁄₈"
(417mm)
22½"
(572mm)
6"
(152mm)
10⁷⁄₁₆"
(265mm)
S19284J Dimensions
1⁵⁄₈"
(41mm)
15⁹⁄₁₆"
(395mm)
3⁹⁄₁₆"
(90mm)
4¹⁄₁₆"
(103mm)
Alternate
Supply
Location
3⁵⁄₁₆"
(84mm)
3¹³⁄₁₆"
(97mm)
1¹³⁄₁₆"
(46mm)
(235mm)
1⁹⁄₁₆"
(40mm)
9¼"
Ø ¼" mtg.
hole (qty. 4)
(264mm)
22⁵⁄₈"–34⁵⁄₈"
(575mm–879mm)
to finished floor for
ANSI compliance
10³⁄₈"
Alternate
Supply
Location
½" NPT
Supply
16³⁄₈"
(417mm)
22½"
(572mm)
6"
(152mm)
10⁷⁄₁₆"
(265mm)
Bradley • 215-1741 Rev. B; ECN 13-05-014 3/27/2013