INTRODUCTION
AVC63-2.5 Voltage Regulators are intended for use on 50/60 Hz brushless generators. AVC63-2.5 features include frequency compensation, a solid-state buildup circuit, EMI filtering, and remote adjust capability.
WARNING!
To prevent personal injury or equipment damage, only qualified personnel should install, operate, or service this device.
ELECTRICAL SPECIFICATIONS
DC Output Power
Maximum Continuous: 2.5 Adc at 63 Vdc One-Minute Forcing: 3.97 Adc at 100 Vdc
(at 240 Vac input).
Exciter Field DC Resistance
25.2 minimum.
AC Power Input
Single phase, 50/60 Hz Operating range: 171 to 264 Vac, +10% Burden: 350 VA.
Sensing Input
Single phase, 50/60 Hz Operating Range: 171 to 264 Vac, +10% Burden: 350 VA.
Regulation Accuracy
Better than ±1.0% no-load to full-load.
EMI Suppression
Internal electromagnetic interference (EMI) filter
Voltage Buildup
Internal provisions for automatic voltage buildup from generator residual voltages as low as 10 Vac.
Terminations
¼ inch quick-connect terminals.
PHYSICAL SPECIFICATIONS
Temperature
Operating: –40 to 60°C (–40 to 140°F) Storage: –40 to 85°C (–40 to 185°F)
Vibration
Withstands 1.5 G at 5 to 29 Hz; 0.036" double amplitude at 29 to 52 Hz; and 5 G at 52 to 500 Hz.
Shock
Withstands up to 15 G in each of three mutually perpendicular axes.
Weight
3.8 oz (108 g)
FOR
VOLTAGE REGULATOR
AVC63-2.5
9318300106
FUSES
It is recommended that fuses with high interruption capability be installed per the interconnection diagram to protect wiring from faults before the regulator. See
Interconnection Drawings
Fuse must be installed per the interconnection diagrams to avoid interrupting the field current.
V/HZ "CORNER FREQUENCY" SELECTION AND ADJUSTMENT
The corner frequency is adjusted by the UF ADJ rheostat on the AVR. Clockwise
rotation raises the corner frequency (shifting the curve to the right). To set the UF rheostat:
1. Adjust the UF Rheostat fully CCW.
2. Start the generator and set at rated voltage.
3. Adjust the generator frequency to the desired kneepoint frequency.
4. Slowly adjust the UF ADJ rheostat clockwise (CW) until the generator voltage just begins to decrease.
Typical Frequency Compensation Curves
OPERATION
The following system operation procedures provide instructions for adjusting the AVC63-
2.5 voltage regulator. Symptoms resulting
from a faulty regulator and certain generator system problems are included, together with suggested remedies.
Complete the following steps before proceeding with system startup.
CAUTION
Meggers and high potential test equipment must not be used. Incorrect use of such equipment could damage the semiconductors contained in the regulator.
PRELIMINARY SETUP
1. Verify that the voltage regulator specifications conform with the generator system requirements.
2. Ensure the voltage regulator is correctly connected to the generator system.
3. Install the fuses as described in Fuses.
4. Set the regulator VOLT ADJ and external VOLT ADJ (if used) as follows:
.
NOTE
Regulator VOLT ADJ: Fully CCW Remote VOLT ADJ: Centered
SYSTEM STARTUP
1. Perform preliminary set-up as described in the above paragraphs.
NOTE
All voltage readings are to be taken with an average reading voltmeter.
2. Start prime mover and bring up to rated speed.
RESULT: Voltage should build up. If not, perform field flashing.
3. Slowly adjust the regulator VOLT ADJ CW until the generator output voltage reaches the nominal value. If used, adjust the remote VOLT ADJ to set the generator voltage to the exact value desired.
RESULT: Voltage should build up to rated value. If voltage does not build up to rated value, check generator for short or excessive load.
4. Check regulator under normal operating and loading conditions.
RESULT: Voltage regulation should be better than ±1.0% no-load to full-load. If regulation is not within this range, perform the following steps:
a. Voltage reduction under load may be
due to speed change from no load to full load, causing the frequency compensation (V/Hz) circuit to reduce voltage at lower frequencies.
b. Replace voltage regulator.
OPERATIONAL TEST
1. Connect the test setup as shown in the
Operational Test Connections
Do not apply power. Ensure that the light bulb is rated for 120 V and less than 100 W.
2. Adjust the regulator VOLT ADJ and/or remote VOLT ADJ to maximum CW.
3. Apply 240 V, 50/60 Hz power to the regulator. The light bulb should illuminate.
4. Slowly adjust the regulator VOLT ADJ control CCW. At the regulation point, the light bulb should extinguish.
The following notes apply to the intercon­nection diagrams:
1. If external pot is not used, short terminals 6 and 7.
2. Item not supplied by Basler Electric.
3. Select fuses with high interrupting capacity.
4. Excitation On/Off Switch (If Used).
illustration.
Publication
9318300991
Revision
B
First Printing: 01/98
Revised: 10/06
Copyright
AVC63-2.5 Dimensions, Top View
AVC63-2.5 Dimensions, Side View
Operational Test Connections
Interconnections, 277/480 V Nominal,
3-Phase, 4-Wire, Wye Connection
Interconnections, 120/240 V Nominal, 1-Phase, 3-Wire
Interconnections, 120/208 V Nominal,
3-Phase, 4-Wire, Wye Connection
Locations of Controls and Connectors
Page 2 First Printing: 01/98
Revised: 10/06
Revision
B
Publication
9318300991
Loading...