TP 23 - G.C. Number 47-116-32
TP 30 - G.C. Number 47-116-33
Manufacturered by Merloni TermoSanitari spa - Italy
Country of destination: GB - IE
TABLE OF CONTENTS
USERS GUIDE
1.GENERAL INFORMATION
2.OPERATING INSTRUCTIONS
3.BOILER SHUTDOWN SITUATIONS
4.TIME CLOCK
INSTALLATION AND SERVICING
INSTRUCTIONS
5.GENERAL INFORMATION
5.1General Instructions
5.2Overall View
6.INSTALLATION
6.1Reference Standards
6.2Siting the Appliance
6.3Overall Dimensions
6.4Clearances
6.5Mounting the Appliance
6.6Electrical Connection
6.7Gas Connection
6.8Water Connections
6.9Flue Connection
6.10 Control Panel
6.11 Removing the front panel
6.12 Fitting the Time Clock
6.13 Room Thermostat Connection
6.14 Electrical/System Diagrams
6.15 Water Circuit Diagram
7.COMMISSIONING
7.1Initial Preparation
7.2Initial Start up
7.3Operational Adjustments
7.4Combustion Analysis
7.5Product of Combustion Discharge Monitoring
7.6Boiler Safety Systems
7.7Draining the System
7.8Completion
7.9Operational checks
7.10 Instructing the End User
8.GAS ADJUSTMENTS
8.1Changing the Type of Gas
8.2Adjusting the gas pressure
10. SERVICING INSTRUCTIONS
10.1Replacement of Parts
10.2To Gain General Access
10.2.1 Removing the Front Panel
10.2.2 Removing the Sealed Chamber Front Panel
10.2.3 Removing the Side Panels
10.3Access to the Combustion Chamber
10.3.1 Removing the Combustion Cover
10.3.2Removing the Burner and Jets
10.3.3 Removing the Electrodes
10.3.4 Removing the Main Heat Exchanger
10.3.5 Removing the Air Pressure Switch
10.3.6 Removing the Fan
10.4Access to the Gas Valve
10.4.1 Removing the Spark Generator
10.4.2 Removing the Gas Valve
10.5Access to the Water Circuit
10.5.1 Removing the D.H.W. (secondary) exchanger
10.5.2 Removing the Pump Pressure Switch
10.5.3 Removing the Safety Valve
10.5.4 Removing the Automatic Air Vent
10.5.5 Removing the Pump
10.5.6 Removing the Pressure Gauge
10.5.7 Removing the Expansion Vessel
10.5.8 Removing the Overheat Thermostat
10.5.9 Removing the Central Heating Temperature
Sensor (N.T.C.)
10.5.10Removing the D.H.W.Temperature Sensor (N.T .C .)
10.5.11Removing the D.H.W. Flow Switch
10.5.12Removing the Divertor Valve Actuator
10.6Access to the Control System
10.6.1 Checking the Fuses
10.6.2 Removing the Time Clock
10.6.3 Removing the P.C.B.
11. FAULT FINDING
11.1 Fault Finding Guide (Flow-chart)
12. SHORT SPARE PARTS LIST
9.MAINTENANCE
TECHNICAL INFORMATION
13.
2
A
B
C
DEFI HGK J
USERS GUIDE
1. General Information
This is a combined appliance for the production of central heating (C.H.) and domestic hot water (D.H.W.).This appliance mustbe used only for the purpose for which it is designed.The manufacturer declines all liability for damage caused by improper or
negligent use.
Do not allow children or inexperienced persons to use the appliance without supervision.
If you smell gas in the room, do not turn on light switches, use
the telephone or any other object which might cause sparks.
Open doors and windows immediately to ventilate the room.
Shut the gas mains tap (on the gas meter) or the valve of the gas
cylinder and call your Gas Supplier immediately.
If you are going away for a long period of time, remember to shut
the mains gas tap or the gas cylinder valve.
Before any intervention within the boiler it is first necessary
to cut off the electrical power supply by turning the external
switch to “OFF”.
Control Panel
LEGEND:
A - On/Off button
B - Central heating temperature adjustment
C - Domestic hot water temperature adjustment
D - Heating system pressure gauge
E - Time clock
F - Central heating selector
G - Central heating L.E.D. (green)
H - Flue sensor L.E.D. (yellow)
I - Ignition failure (lockout) and/or overheat reset button
J - Overheat and/or ignition failure (lockout) L.E.D. (red)
K - ON/OFF L.E.D. (green
)
2. Operating Instructions
Installation, star t-up, adjustments and maintenance must be
performed by a competent person only, in accordance with
the current Gas Safety (Installation & Use) Regulations and
the instructions provided. Improper installation may cause
damage or injury to individuals, animals and personal property, for which the manufacturer will not be held liable.
To ensure efficient and safe operation it is recommended
that the boiler is serviced annually by a competent person.
If it is known or suspected that a fault exists on the appliance, it must not be used until the fault has been corrected
by a competent person.
To get the most out of your boiler, we have provided you with
some useful advice on proper use and maintenance:
- Periodically check the system pressure
using the pressure gauge “D”, make sure
that the pressure is at 1.5 bar when the system is off and cool. If the pressure is below
the minimum recommended value.
Consult your installer for checking and refilling the system.
- The outer panels of the units case must only be cleaned with a
damp cloth. Do not use abrasive cleaners. The control panel
can be wiped with either a damp or dry cloth. Spray polishes
must not be used on the control panel surface or knobs. Care
must be taken in preventing any liquid entering the appliance.
- If the water is very hard, it is recommended that a water softener be added to the system so as to reduce the formation of
limescale in the heat exchanger. This will ensure that the efficiency of the unit remains the same over time, reducing gas
consumption and maintenance costs.
- If the boiler should be out of use for a prolonged period, it is
recommended that the electrical power supply be disconnected and that the external gas cock be closed. If low temperatures are expected, the boiler and system pipe work should be
drained in order to prevent frost damage.
- To improve comfort and take full advantage of the heat produced by the boiler, it is recommended that an external (room)
thermostat be installed.
- It is good practice to clean and service the appliance and central heating system every year.
Call an Authorised Service Centre.
Ignition Procedure
Press button “A”. The green L.E.D. “K” will
illuminate indicating that the boiler is ready to
operate. The centralised electronic control unit
will ignite the burner, upon demand for either
C.H. or D.H.W. If, after approximately 10 seconds, the burner has not ignited, the boiler
safety devices will shut off the gas and the red
L.E.D.“I” illuminates. To reset the ignition system, the reset “J” must be pressed and
released. Should the boiler fail to ignite a second time, check that the external gas cock is
open (see diagrams on the left). If the problem
persists, contact a local Service Agent.
D
K
A
I
IMPORTANT!! Always wait 2 minutes before
resetting each time.
3
J
3. Boiler Shutdown Situations
Winter and Summer Operating Modes
In the ‘winter operating mode’, the boiler will
produce both Central Heating and Domestic
Hot Water.In the ‘summer operating mode’, the
boile r w i ll p ro du c e only domestic hot water.
Press button “F” to select winter mode. The
green LED “G” will illuminate.
G
F
Adjusting the Heating
It is possible to set the temperature of the
heating system by adjusting the knob “B”.
By positioning the indicator somewhere
between MIN and MAX, a temperature may
be obtained which varies from approximately
42˚C to about 82˚C.
B
External (Room) Thermostat Control
If an external (room) thermostat is installed, it is recommended
that the temperature of the heating system be set by means of
the knob “B”, leaving it at MAX position in order to obtain the
best performance from the boiler and to allow the regulation of
the external temperature to function efficiently.
Setting the Hot Water for Domestic Use
Both in the winter and summer mode, the temperature of the
domestic hot water may be adjusted by rotating the knob “C”.A
delivery temperature for the water may be
selected between approx. 36˚C to 54˚C,
depending on the flow rate of the water and
the position of the knob between MIN and
MAX settings. NOTE: Should the Domestic
Hot Water not be hot enough, it may be
necessary to slow the flow rate from the
hot water outlet being used.
Turning Off the Central Heating
To tur n off the Central Heating, press the Central
Heating button “F”;the respective green LED “G”
will go off. The boiler will stay in summer mode,
only providing Domestic Hot Water
G
F
C
The boiler is equipped with safety devices that intervene in certain situations and shut it off.Most of these situations are communicated by means of the LED’s and at times the user may be able
to remedy them.
Shutdown Due To Ignition Failure
In the event that the automatic ignition of the
burner has failed, the red LED. “I” will illuminate. In order to reset the ignition, the button
“J” must be pressed and released. Should the
boiler fail to ignite a second time, check that the
external gas cock is open. If the problem persists, contact a local Service Agent.
IMPORTANT!! Always wait 2 minutes before
resetting each time.
I
J
Shutdown Due To Overheating
In the event that the safety limit is exceeded for
the temperature of the water in the boilers
exchanger, the thermostat shuts off the boiler
and the red LED “I” illuminates.
To remedy this situation, wait a few minutes to
allow the exchanger to cool down, then press
and release the reset button “J”.
If this situation occurs frequently, contact a
local Service Agent.
I
J
Temporary Shutdown Due To Defective
Discharge of Exhaust Fumes
The boiler is fitted with safety devices, which in the event of a
defective discharge of exhaust products, automatically interrupts
the gas supply, thereby shutting off the boiler.
The shut-off of the boiler is temporary and is indicated by the illumination of the yellow L.E.D.“H” for a period of about 15 minutes.
Once this time period has passed and the discharge state of
exhaust system has returned to normal, the boiler automatically
turns back on.
IMPORTANT!
If this situation occurs frequently , contact a local Service Agent so
that they may check that the exhaust fumes are being expelled
correctly, that the flue is installed correctly and that the area is
ventilated properly.
Turning Off the Boiler
To turn the boiler off, press the button “A”; the
respective green LED “K” will go off.
K
A
4
3. Boiler Shutdown Situations
Shutdown Due To Insufficient Circulation
If the boiler is off, one possible cause for this state is an insuffi-
cient pressure of water in the system.
Check the system pressure on the pressure
gauge “D” and if it is less than 0.5 bar, re-
pressurise the system as instructed by your
installer, should you be unsure some basic
instructions are provided hereafter;
Ensure that the filling loop hose is connected to the cold water
inlet pipe and to either the Central Heating flow or return
Open the handle/s or tap/s to allow water into the Central Heating
system
Once the needle on the pressure gauge reaches 1 Bar, close the
handle/s or tap/s and disconnect the filling loop hose
Should it still be unclear how to proceed, please consult your
installer.
If the boiler does not start up again, contact a local Service Agent.
If there are frequent drops in pressure within the system, have a
plumber check the heating system for possible water leaks.
D
4.Time clock
UT011Ap
Note: the time clock is for central heating control only.
The time clock is provided with 96 switches , called riders, each of
which covers a time interval of 15 minutes (four per hour).
When a rider is switched from the inside (off setting) to the outside of the clock border (on setting), the circuit is closed (switch
on) for a period of 15 minutes and then the boiler starts if the
room thermostat (if installed) or the heating thermostat require
heat (heating function on).
Anti-frost Device
The boiler is fitted with a device which, in the event that the water
temperature falls below 8
temperature of 18˚C is attained. In the event that the water temperature falls below
Hot Water and the burner fires and runs on minimum power until
a temperature of 33˚C is attained.
This device is only activated when the boiler is operating perf ectly and
- the system pressure is sufficient;
- the boiler is powered electrically;
- gas is being distributed.
˚C the pump activates and runs until a
3
˚C, the diverter valve switches to Domestic
EXAMPLE
To set the heating of your home in the time interval from 7.00
am to 9.30 am and from 7.00 pm to 10.00 pm every day:
- rotate the outer r ing of the clock in a clockwise direction until
the correct time of day (24h) lines up with the arrow on the
clock (at approx.2 o’clock position);
- under no circumstances should the minute hand bemoved manually;
- make sure all the switches, i.e. the riders, are placed on the
inside of the clock border;
- pull outward the riders for 7.00 am and 9.30 am, and then all
riders between these two;
- repeat this for 7.00 pm and 10.00 pm.
Other heating intervals may be set in the same way.
The timer has approximately 150 hours of battery back up for
power failure.
The clock is provided with a selector switch with three positions
(see figure):
1.Position “I” CONSTANT: in this position, the
clock circuit is always closed (switch on), therefore the boiler will constantly be on and will only
shut off upon the request of the room thermostat (if installed) or the heating thermostat;
2.
Position “O”HEATING OFF:in this position, the
UT014A
clock circuit is always open (switch off) and the
boiler will therefore never ignite for heating;
UT014A
3.
“Central” Position
PROGRAMMING ACTIVE:
in this position, the programming set by the user
is active.
5
UT014A
INSTALLATION AND SERVICING INSTRUCTIONS
5. GENERAL INFORMATION
5.1General Instructions
This manual is an integ
should be kept with the appliance so that it can be consulted by
the user and our authorised personnel.
Please carefully read the instructions and notices about the unit
contained in this manual, as they provide important information
regarding the safe installation, use and maintenance of the product.
For operating instructions please consult the separate Previous
User Guide.
Read the instructions and recommendations in these Installation
Instructions carefully to ensure proper installation, use and maintenance of the appliance.
Keep this manual in a saf e place.Y ou ma y need it f or y our own reference while our Servicing Centre technicians or your installer
may need to consult it in the future.
This is a combined appliance for the production of central heating
(C.H.) and domestic hot water (D.H.W.).
This appliance must be used only for the purpose for which it is
designed.
The man
improper or negligent use.
No asbestos or other hazardous materials have been used in the
fabrication of this product.
Before connecting the appliance, check that the information
sho
with the electric, water and gas mains of the property.You will find
the data plate on the reverse of the control panel.
The gas with which this appliance operates is also shown on the
label at the bottom of the boiler.
Do not install this appliance in a damp environment or close to
equipment which spr
Do not place objects on the appliance.
Do not allow children or inexperienced persons to use the appli-
ance without supervision.
If you smell gas in the room, do not turn on light switches, use
the telephone or an
Open doors and windows immediately to ventilate the room.
Shut the gas mains tap (at or adjacent to the gas meter) or the
valve of the gas cylinder and call your Gas Supplier immediately.
If you are going away for a long period of time, remember to shut
the mains gas tap or the gas cylinder valve.
Always disconnect the appliance either by unplugging it from the
mains or turning off the mains switch bef
ance or carrying out maintenance.
In the case of faults or failure, switch off the appliance and turn
off the gas tap.Do not tamper with the appliance.
For repairs, call your local A
request the use of original spare parts. For in-guarantee repairs
contact MTS (GB) Limited.
ufacturer declines all liability for damage caused by
wn on the data plate and the technical data section comply
ral and essential part of the product. It
ay water or other liquids.
y other object which might cause sparks.
ore cleaning the appli-
uthorised Servicing Centre and
Check the following at least once a year:
1 - Check the seals for the water connections; replace any
faulty seals.
2 - Check the gas seals; replace any faulty gas seals.
3 - Visual check of the entire unit.
4 - Visual check of the combustion process or analysis of com-
bustion by-products (see section 3.6) and cleaning of the
burner if needed.
5 - If called for by point.3, dismantling and cleaning of the com-
bustion
chamber.
6 -If called for by point.4, dismantling and cleaning of the burn-
er jets.
7 - Visual check of the primary heat exchanger:
- check for overheating in the blade assembly;
- clean the exhaust fan if needed.
8 - Adjustment of the flow rate of the gas: flow rate for lighting,
partial load and full load.
9 - Check of the heating safety systems:
- safety device for maximum temperature
(overheat thermostat);
- safety device for maximum pressure (safety valve).
10- Check of the gas safety systems:
- safety device for lack of gas or flame ionisation
(detection electrode);
- safety device for gas cock.
11- Check of the electrical connection (make sure it complies
with the instructions in the manual).
12- Check of domestic hot water production efficiency (flow rate
and temperature)
13- General check of the combustion by-products of the dis-
charge/ventilation system.
14- Check of the general performance of the unit.
OTE: THESE CHECKS ARE NOT EXHAUSTIVE, FURTHER HYDRAULIC,
N
MECHANICAL, ELECTRICAL AND OPERATIONAL CHECKS MAY BE
REQUIRED AS NECESSARY
.
6
General Information
27
26
25
21
20
24
23
22
9
10
8
13
14
12
15
6
5
4
3
2
1
28
1618 1917
11
7
5.2Overall View
Fig. 5.0
Legend:
1.Flue connector
2.Air intake for twin pipe flue systems
3.Fan
4.Combustion chamber hood
5.Heat exchanger
6.Safety thermostat
7.Combustion chamber
8.Combustion chamber insulation panel
9.Detection electrode
10. Ignition electrodes
11. Pump pressure switch
12. Main circuit temperature probe
13. Safety valve (3 bar)
14. Domestic hot water temperature probe
15. Secondary exchanger
16. Gas valve
17. Spar k generator
18. Domestic hot water inlet filter
19. D.H.W. flow switch
20. Drain valve
21. Circulation pump with automatic air release valve
22. Motor ised diver ter valve
23. Automatic By-pass
24. Bur ner
25. Expansion vessel
26. Air pressure switch tube
27. Air pressure switch
28. Combustion analysis points
7
6.INSTALLATION
6.1Reference Standards
The technical information and instructions provided herein below
are intended for the installer / Servicing Technician so that the
unit may be installed and serviced correctly and safely.
In the United Kingdom the installation and initial start up of the
boiler must be by a CORGI Registered Installer in accordance
with the installation standards currently in effect, as well as with
any and all local health and safety standards i.e.CORGI.
In the Republic of Ireland the installation and initial start up of the
appliance must be carried out by a Competent Person in accordance with the current edition of I.S.813 “Domestic Gas
Installations”, the current Building Regulations, reference should
also be made to the current ETCI rules for electrical installation.
This appliance must be installed by a competent installer in
accordance with current Gas Safety (installation & use)
Regulations.
The installation of this appliance must be in accordance with the
relevant requirements of the Local Building Regulations, the current I.E.E. Wiring Regulations, the bylaws of the local water
authority, in Scotland, in accordance with the Building Standards
(Scotland) Regulation and Health and Safety document No.635
“Electricity at work regulations 1989” and in the Republic of
Ireland with the current edition of I.S. 813, the Local Building
Regulations (IE).
C.O.S.H.H.
Materials used in the manufacture of this appliance are non-hazardous and no special precautions are required when servicing.
Installation should also comply with the following British Standard
Codes of Practice
6.2Siting the Appliance
The appliance may be installed in any room or indoor area,
although particular attention is drawn to the requirements of the
current I.E.E. Wiring Regulations, and in Scotland, the electrical
provisions of the Building Regulations applicable in Scotland,
with respect to the installation of the combined appliance in a
room containing a bath or shower, the location of the boiler in a
room containing a bath or shower should only be considered if
there is no alternative.
Where a room-sealed appliance is installed in a room containing a bath or shower the appliance and any electrical
switch or appliance control, utilising mains electricity
should be situated so that it cannot be touched by a person
using the bath or shower, specifically in accordance with
current IEE Wiring Regulations.
The location must permit adequate space for servicing and air
circulation around the appliance as indicated in Section 6.4.
The location must permit the provision of an adequate flue and
termination.
For unusual locations special procedures may be necessary.
BS 6798-1987 gives detailed guidance on this aspect.
A compartment used to enclose the appliance must be designed
specifically for this purpose. No specific ventilation requirements
are needed for the installation within a cupboard.
This appliance is not suitable for outdoor installation.
The type C appliances (in which the combustion circuit, air
vent intake and combustion chamber are air-tight with
respect to the room in which the appliance is installed) can
be installed in any type of room.
Secondary ventilation is not required with this boiler. The boiler
must be installed on a solid, non-combustible, permanent wall to
prevent access from the rear.
BS 7593:1992Treatment of water in domestic hot water
central heating systems
BS 5546:1990Installation of hot water supplies for
domestic purposes
BS 5440-1:2000 Flues
BS 5440-2:2000 Air supply
BS 5449:1990Forced circulation hot water systems
BS 6798:1987Installation of gas fired hot water boilers
of rated input not exceeding 60kW
BS 6891:1989Installation of low pressure gas pipe up to
28mm
BS 7671:2001IEE wiring regulations
BS 4814:1990Specification for expansion vessels
BS 5482:1994Installation of L.P.G.
8
Installation
6.3Overall Dimensions
FIG. 6.1
6.5 MOUNTING THE APPLIANCE
After removing the boiler from its packaging, remove the template
from the separate box containing the connection kit.
Note: Pa y particular attention to any test water that may spill from
the appliance.
QT002A
Legend:
A = Central Heating Flow (3/4”)
B = Domestic Hot Water Outlet (1/2”)
C = Gas Inlet (3/4”)
D = Domestic Cold Water Inlet (1/2”)
E = Central Heating Return (3/4”)
6.4Clearances
FIG. 6.2
In order to allow access to the interior of the boiler for maintenance
purposes, the boiler must be installed in compliance with the minimum clearances indicated in FIG.6.2
DM001B
FIG. 6.3
Place the template in the position the appliance is to be mounted
and after ensuring it is hanging squarely, use it to drill the holes
for the hanging bracket and flue pipe(s) NB: For further information relating to the flue installation please refer to Section 6.9 Flue
Connection. (If the appliance is to be fitted on a wall of combustible material, the wall must be protected by a sheet of fireproof material).
If the appliance is to be fitted into a timber framed building, guidance should be sought from the IGE document REF: IGE/UP/7.
9
F
G
Installation
6.7Gas Connection
6.5.1. Drill the wall and plug using those supplied with the con-
nections kit, position the bracket and secure with the wall
bolts supplied. Note: It is highly recommended that a spirit level be used to position the appliance to ensure that it is
perfectly level.
6.5.2. Position the appliance on the hanging bracket and connect
the isolating valves supplied in the connection kit as shown
on the wall template (see also Sections 6.7 Gas
Connections, 6.8 Water Connections & FIG. 6.3).
6.6Electrical Connection
For safety purposes, have a competent person carefully check
the electrical system in the property, as the manufacturer will not
be held liable for damage caused by the failure to earth the appliance properly or by anomalies in the supply of power. Make sure
that the residential electrical system is adequate for the maximum power absorbed by the unit, which is indicated on the rating
plate. In addition, check that the section of cabling is appropriate
for the power absorbed by the boiler.
The boiler operates with alternating current, as indicated in the
Technical Information table in Section 13, where the maximum
absorbed power is also indicated.Make sure that the connections
for the neutral and live wires correspond to the indications in the
diagram.The appliance electrical connections are situated on the
reverse of the control panel.
MPORTANT!
I
In the event that the pow er supply cord must be changed, replace
it with one with the same specifications.
Note: The diagrams for the electrical system are indicated in sec-
tion 6.13.
Warning, this appliance must be earthed.
External wiring to the appliance must be carried out by a competent person and be in accordance with the current I.E.E.
Regulations and applicable local regulations.
The appliance is supplied with a fly-lead already connected, this
must be connected to a 240v supply fused at 3A and must facilitate complete electrical isolation of the appliance, by the use of a
fused double pole isolator having a contact separation of at least
3 mm in all poles or alternatively, by means of a 3 A fused three
pin plug and unswitched shuttered socket outlet both complying
with BS 1363.
The point of connection to the Electricity supply must be readily
accessible and adjacent to the appliance unless the appliance is
installed in a bathroom when this must be sited outside the bathroom (see section 6.2).
Should external controls be required, the design of the external
electrical circuits should be undertaken by a competent person,
see section 6.12 for further information.
The local gas region contractor connects the gas meter to the
service pipe.
If the gas supply for the boiler serves other appliances ensure
that an adequate supply is available both to the boiler and the
other appliances when they are in use at the same time.
Pipe work must be of an adequate size. Pipes of a smaller size
than the boiler inlet connection should not be used.
6.8Water Connections
View of the Boiler Connections
Fig. 6.4
Legend:
A = Centr
B = Domestic Hot Water Outlet
C = Gas Inlet
D = Domestic Cold Water Inlet
E = Central Heating Return
F = Safety Valve Outlet
G = Drain Valve
Pipe Work:
Copper tubing to BS EN 1057:1996 is recommended for water
pipes. Jointing should be either with capillary soldered or compression fittings.
Where possible pipes should have a g r adient to ensure air is carried naturally to air release points and water flows naturally to
drain taps.
The appliance has a built-in automatic air release valve, however
it should be ensured as far as possible that the appliance heat
exchanger is not a natural collecting point for air.
Except where providing useful heat, pipes should be insulated to
prevent heat loss and avoid freezing.
Particular attention should be paid to pipes passing through ventilated spaces in roofs and under floors.
By-pass:
The appliance includes an automatic by-pass valve, which protects the main heat exchanger in case of reduced or interrupted
water circulation through the heating system, due to the closing
of thermostatic valves or radiators.
SYSTEM DESIGN:
This boiler is suitable for sealed systems only.
al Heating Flow
TE020E
10
Installation
E
A
B
D
C
FIG. 6.5
Drain Cocks:
These must be located in accessible positions to permit the draining of the whole system and should be fitted at all low points.The
taps must be at least 15mm nominal size and manufactured in
accordance with BS 2870:1980.
Safety Valve Discharge:
The discharge should terminate facing downward on the exterior
of the building in a position where discharging (possibly boiling
water & steam) will not create danger or nuisance, but in an easily visible position, and not cause damage to electrical components and wiring.
The discharge must not be over an entrance or a window or any
other type of public access.
Air Release Points:
These must be fitted at all high points where air naturally collects
and must be sited to facilitate complete filling of the system.
The appliance has an integral sealed expansion vessel to accommodate the increase of water volume when the system is heated.
It can accept up to 6 litres (1.3 gal) of expansion water. If the
heating circuit has an unusually high water content, calculate the
total expansion and add an additional sealed expansion vessel
with adequate capacity.This should be located on the return pipe
work as close as possible to the pump inlet.
Mains Water Feed - Central Heating:
There must be no direct connection to the mains water supply
even through a non-return valv e, without the approv al of the Local
Water Authority, therefore a temporary method for initially filling
the system and replacing lost water during servicing in accordance with current W ater Regulations and byla ws must be provided (FIG. 6.6).
Note: The installer should ensure that there are no leaks as fre-
quent filling of the heating system can lead to premature
scaling of the main exchanger and failure of h ydraulic com-
ponents.
Domestic Water:
The domestic water must be in accordance with the relevant recommendation of BS 5546:1990. Copper tubing to BS EN
1057:1996 is recommended for water carrying pipe work and
must be used for pipe work carrying drinking water, a scale
reducer should also be used to reduce the risk of scale forming
in the domestic side of the heat exchanger.
CENTRAL HEATING
Detailed recommendations are given in BS 6798:1987 and BS
5449-1:1990, the following notes are given for general guidance.
Residual Head of the Boiler
VR003A
∆
T=20°C
FIG. 6.6
11
Installation
6.9Flue Connections
FLUE SYSTEM
The provision for satisfactory flue termination must be made in
accordance with BS 5440-1.
The appliance must be installed so that the flue terminal is exposed
to outside air.
The terminal must not discharge into another room or space such
as an outhouse or lean-to.
It is important that the position of the terminal allows a free passage of air across it at all times.
The terminal should be located with due regard for the damage
or discolouration that might occur on buildings in the vicinity and
consideration must be given to adjacent boundaries.
In cold or humid weather water vapour may condense on leaving the
flue terminal. The effect of such “pluming”must be considered.
If the terminal is less than 2 metres above a balcony, above
ground or above a flat roof to which people have access, then a
suitable terminal guard must be fitted. When ordering a terminal
guard, quote the appliance model number.
A suitable terminal guard is available from:
TOWER FLUE COMPONENTS
Morle
y Road
Tonbridge
Kent TN9 1RA
The minimum acceptable spacing from the terminal to obstructions and ventilation openings are specified in F
IG. 6.7.
IMPORTANT!
For all flue systems, a restrictor may need to be inserted into the exhaust manifold, the siz e of the restrictor
and details of fitting requirements are shown in Table
6.1 (Page 18).
Ø 60/100 mm
FU003A
FIG. 6.7
T
ERMINALPOSITION
A -Directly below an openable window
or other opening300
B -Below gutters, solid pipes or drain pipes75
C - Below eaves200
D - Below balconies or car-port roof200
E -From vertical drain pipes and soil pipes150
F - From internal or external corners300
G -Above ground or balcony level300
H - From a surface facing a terminal600
I - From a terminal facing a terminal1200
J -From an opening in the car port
(e.g. door, window) into dwelling1200
K -Vertically from a terminal in the same wall1500
L -Horizontally from a terminal in the same wall300
M - Hor izontally from an opening window300
N - Fixed by vertical flue terminal
FU010ARev1
mm
FIG. 6.8
Fitting the Coaxial Flue (Horizontal)
(For Telscopic Instructions see page 13 and for Vertical Flue and
Twin Pipe Instr uctions see page 14)
Once the boiler has been positioned on the wall, insert the elbow
into the socket (FIG 6.8) and rotate to the required position. NOTE:
It is possible to rotate the elbow 360oon its vertical axis.
Using the flue clamps, seals and screws supplied (FIG 6.8)
secure the elbow to the boiler.
The 1 metre horizontal flue kit (705958) supplied is suitable for an
exact X dimension of 823mm, and the 750mm horizontal flue kit
(705785) is suitable for an exact X dimension of 573mm.
NOTE: THE FLUE MUST NOT TERMINATE IN A PLACE LIKELY TO CAUSE
NUISANCE
Measure the distance from the face of the external wall to the
12
Installation
25 mm
25 mm
25 mm
face of the flue elbow (X - FIG 6.8), add 22 mm to this measurement, you now hav e the total length of flue required (including the
terminal), this figure must now be subtracted from 860mm, you
now have the total amount to be cut from the plain end of the flue.
Cut the flue to the required length ensuring that the distance
between the inner and the outer flue is maintained (FIG 6.10).
e.g. X = 508mm + 22mm = 530mm
860 - 530 = 330mm (Length to be cut from the plain end
of the flue).
Once cut to the required length, ensure that the flue is free from
burrs and reassemble the flue.If fitting the flue from inside of the
building attach the grey outer wall seal to the flue terminal and
push through the flue through the hole, once the wall seal has
passed through the hole, pull the flue back until the seal is flush
with the wall. Alternatively, the flue can be installed from outside
of the building, the grey outer seal being fitted last.
The telscopic flue is suitable for use with an exact minimum X
dimension of 270mm and an exact maximum X dimension
470mm.
IMPORTANT!!
Do not extend the telescopic flue to an X dimension of more
than 470mm. If longer lengths are required use extension
pieces as necessary. Under no circumstances must the flue
be cut.
The wall must then be made good around the flue (ensuring a fall
of 1ois maintained away from the boiler to the flue terminal).
Once made good, place the inner (white) wall seal over the flue
and push up to the wall, secure the flue to the elbow by using the
clamp supplied.
For each additional 90oelbow 1 metre must be removed from the
total flue length (maximum 4 metres including the 1st elbow). For
each additional 45oelbow 0.5 metre must be subtracted from the
total flue length (FIG 6.13).
DETERMINE WHETHER
THE FLUE RESTRICTOR
IS REQUIRED
IT NOT BE NEEDED
THE RESTRICTOR WILL
NEED TO BE REMOVED
FROM THE FLUE GAS
COLLAR
. SHOULD
(FIG. 6.11).
,
The vertical flue kit is supplied with a specially designed weather
proof terminal fitted, it can be used either with a flat roof or a
pitched roof. (see FIGS 6.12, 6.13).
FIG 6.12
13
Installation
The Vertical flue kits maximum and minimum useable lengths
with both flat and pitched roof flashings are indicated in (Figs.
6.14 & 6.15).
Before proceeding to fit the flue, ensure that the maximum flue
length has not been exceeded and that all elbows and bends
have been taken into consideration, the maxim um flue length is 4
metres, for each additional 90oelbow 1 metre must be subtracted
from the total flue length, and for each 45o0.5 metres must be
subtracted from the total flue length (the offset and height of 2
x 45ocan be seen in Fig. 6.16).
Mark the position of the flue hole in the ceiling and/or roof (see
FIG. 6.14 for distance from wall to the centre of the flue).
Cut a 110mm diameter hole through the ceiling and/or roof and
fit the flashing plate to the roof.
Should it be necessary to cut the flue DO
ar inlet tube, cut the aluminium exhaust flue 6mm longer than the
outer white air tube when used at minimum length. DO NOT cut
more that 250mm from the inner aluminium exhaust flue.
To connect the vertical flue kit directly to the boiler, place the
adaptor (see FIG 6.12) (supplied with vertical flue kit) onto the
exhaust manifold and secure with the clamp, the vertical flue kit
must then be inserted through the roof flashing, this will ensure
that the correct clearance above the roof is provided as the terminal is a fixed height.
NOT cut the outer white
FIG 6.13
NOTE:MAX LENGTH = a+a+a +
b+b = a+a+a+0.5+0.5
COMBINED LENGTH NOT
TO EXCEED 4m
Should extensions be required, they are available in 1 metre
(Part No. 705786), 500mm (Part No. 705790) and 160mm
lengths (Part No.705812), they must be connected directly to the
boiler and secured with the clamp supplied before connecting the
adaptor to allow the vertical flue kit to be fitted. In the event that
extension pieces need to be shortened, they m
the male end and it must be ensured that the distance between
the inner and outer flue are kept (Fig. 6.10).
When utilising the vertical flue system, action must be taken to
ensure that the flue is supported adequately to prevent the weight
being transferred to the appliance flue connection.
When the flue passes through a ceiling or wooden floor, there
must be an air gap of 25mm between any part of the flue system
and any combustible material. The use of a ceiling plate will facilitate this. Also when the flue passes from one room to another a
fire stop must be fitted to prevent the passage of smoke or fire,
irrespective of the structural material through which the flue passes.
ust only be cut at
Fitting the Flue (Twin Pipe)
Where it is not possible to terminate the flue within the distance
permitted for coaxial flues, the twin flue pipe can be used by fitting a special adaptor to the flue connector and using the aperture for the air intake located on top of the combustion chamber.
FIG 6.14
Considerations necessary for twin flue installation;
It is most important to avoid any possible condense formation
entering the appliance.
14
Installation
According to Table 6.1 (Page 18) decide if condensation will form
within the flue. If yes, there are two options;
1) Where condense will form but can be negated with insulated
flue, install the insulated flue with a fall of 5mm in every metre
away from the boiler.
o
2) The exhaust flue will have a fall of 3
and a suitable trap will be fitted on the exhaust as close to the
boiler as possible, condense will then be suitably disposed of .
Where the flue runs through cold spots, i.e. loft areas, condense
is likely to be formed, therefore a fall back to the boiler and a trap
is required.
Always ensure that the flue is adequately supported, avoiding low
points. (MTS supply suitable clamps as Part No.705778).
To utilise the air intake it is necessary to:
Remove the ‘knoc k out’of the air intake by cutting it with a suitable
knife (FIG. 6.16).
Insert the elbow/flue pipe into the air intake until it stops.
back to the boiler
FIG 6.15
The twin flue pipes can be fitted with or without additional elbows
and need no clamps, simply ensure that the red o-ring is inserted in the female end of the flue pipe and push the extension piece
fully into the previous section of flue pipe or elbow, check that the
o-ring is not dislodged when assembling the flue.
Twin pipe can also be converted back to Coaxial flue to enable
vertical termination with a coaxial kit by using the pipe bridge
(Twin - Coaxial Adaptor - Part No. 705767). When running the
twin flue pipe vertically, a condense trap must always be used on
the exhaust pipe.
It is not recommended that the pipe bridge be used for horizontal
termination, however in the unlikely event that this proves to be a
necessity it is extremely important that the entire flue has a fall of
o
back to the boiler, is suitably trapped and where the 60mm
3
inner flue of the concentric terminal connects to the pipe bridge,
this point must be adequately sealed with silicone sealant to
avoid condense leakage at this point.
Note: Vertical twin flue installations must have a trap on the
exhaust. MTS supply a suitable condense trap with float
Part No. 705774 and recommend that this be used in the
event that the flue may not form condense.
When siting the twin flue pipe horizontally, the air intake and
exhaust terminals must terminate on the same wall, the centres
of the terminals m
imum of 500mm, the air intake must not be sited above the
exhaust terminal (refer to FIG. 6.19). The air intake pipe can be
run horizontally, however, the terminal and the final 1 metre of
flue must be installed with a fall away from the boiler to avoid rain
ingress.
ust be a minimum of 280 mm apart and a max-
WARNING
IT WILL BE NECESSARY TO CONSULT TABLE 6.1 ON PAGE
18 TO DETERMINE WHETHER THE FLUE RESTRICTOR IS
REQUIRED
WILL NEED TO BE REMOVED FROM THE FLUE GAS COLLAR
. SHOULD IT NOT BE NEEDED, THE RESTRICTOR
(FIG. 6.11).
Minimum offset distance when using 2x 45obends
It is also strongly recommended that the air intake pipe run be
constructed of insulated pipe to prevent condense forming on the
outside of the tube.
The maximum permissible flue length for twin flue is dependent
on the type of run used.
FIG 6.16
15
Installation
For flue runs with the intake and exhaust pipes under the same
atmospheric conditions (Type 4) the maximum length is 43
metres (80) and 28 metres (100), for runs with the terminals
under different atmospheric conditions (Type 5) the exhaust terminal must extend 0.5 metres above the ridge of the roof (this is
not obligatory if the exhaust and air intake pipes are located on
the same side of the building). For Type 5 also, the maximum permissible combined length is 40 metres (80) and 51 metres (100).
The maximum length is reached by combining the total lengths of
both the air intake and exhaust pipes. Therefore a maximum
length of 40 metres for example, will allow a flue run of 20 metres
for the air intake and 20 metres for the exhaust pipes, also for
each 90oelbow 1.3 metres must be subtracted from the total
length and for each 45oelbow 1 metre must be subtracted from
the total flue length.
Some of the acceptable flue configurations are detailed on below
(FIG. 6.19).
For further information relating to flue runs not illustrated, please
contact the Technical Department on 0870 2418180.
FIG 6.17
FIG 6.16
FIG 6.18
16
Installation
EXHAUST
AIR INTAKE
AIR INTAKE
AIR INTAKE MUST NOT BE
FITTED ABOVE THE EXHAUST
FIG. 6.19
Type 1
Type 4
Note: Drawings are indicative of flueing options only.
Type 2
Type 5
Type 3
17
FIG 6.20
Installation
TP 23
Coaxial
Systems
ø 60/100
Twin Pipe
Systems
ø 80/80
Exhaust
Type
TYPE 1
TYPE 2
TYPE 3
Exhaust
Type
TYPE 4
TYPE 5
Use the
ø 41 mm
Restrictor
Between
345 mm - 1 m
Use the
ø 43 mm
Restrictor
Up to 20 m
Up to 25 m
Do not use the
Restrictor
Between
1 m - 4 m
Do not use the
Restrictor
Between
20 m - 60 m
een
Betw
25 m - 59 m
Maximum
Flue
Length
4 m
Maximum
Flue
Length**
60 m
59 m
Risk of Condensation Forming
NOT APPLICABLE
NO
T APPLICABLE
Risk of Condensation Forming With:
Standard T win Pipe
After:
3 m*
with a
ø 41 mm
restrictor
3 m*
with a
ø 41 mm
restrictor
4 m*
with a
ø 41 mm
restrictor
4 m*
with a
ø 41 mm
restrictor
Insulated Twin Pipe
After:
3 m*
with a
ø 41 mm
restrictor
3 m*
with a
ø 41 mm
restrictor
Table 6.1
4 m*
with a
ø 41 mm
restrictor
4 m*
with a
ø 41 mm
restrictor
TP 30
Coaxial
Systems
ø 60/100
Twin Pipe
Systems
ø 80/80
Exhaust
Type
TYPE 1
TYPE 2
TYPE 3
Exhaust
Type
TYPE 4
TYPE 5
Use the
ø 42 mm
Restrictor
Between
345 mm - 1 m
Use the
ø 42 mm
Restrictor
Up to 4 m
Up to 11.5 m
Do not use the
Restrictor
Between
1 m - 4 m
Do not use the
Restrictor
Between
4 m - 47 m
Between
5 m - 42 m
11.
Maximum
Flue
Length
4 m
Maximum
Flue
Length**
47 m
42 m
Risk of Condensation Forming
NOT APPLICABLE
NOT APPLICABLE
Risk of Condensation Forming With:
Standard T win Pipe
After:
2 m*
with a
ø 42 mm
restrictor
7.4 m*
with a
ø 42 mm
restrictor
7.5 m*
without a
ø 42 mm
restrictor
7.4 m*
without a
ø 42 mm
restrictor
Insulated Twin Pipe
After:
2 m*
with a
ø 42 mm
restrictor
7.4 m*
with a
ø 42 mm
restrictor
7.5 m*
without a
ø 42 mm
restrictor
7.4 m*
without a
ø 42 mm
restrictor
Where there is no risk of condense forming (and, therefore no requirement for a condense collector), ensure a
*
minimum fall of 5mm per metre away from the appliance.
** Maximum Length = combined length of air intake and exhaust pipes (less any equivalent lengths for elbows).
Note: Under some circumstances, condense may form at the exhaust terminal, special attention m
possible condense dripping from the terminal.
18
ust be paid with regard to
Installation
A
B
C
DEFI HGK J
6.10Control Panel
LEGEND:
A - On/Off button
B - Central heating temperature adjustment
C - Domestic hot water temperature adjustment
D - Heating system pressure gauge
E - Time clock (knock out)
F - Central heating selector
G - Central heating L.E.D. (green)
H - Flue sensor L.E.D. (yellow)
I - Ignition failure (lockout) and/or overheat reset button
J - Overheat and/or ignition failure (lockout) L.E.D. (red)
K - ON/OFF L.E.D. (green
)
2
To dismantle the front casing panel it is necessar y to:
1 - Remove the two screws “B”;
2 - Move the front casing panel up and lift forward.
3
B
6.11Removing the Front Panel
In order to access the inside of the boiler, it is necessary to
unscrew the fastening screws “A”of the control panel located on
the lower part of the panel itself
The control panel moves downward and when pulled forward
rotates on two lateral hinges.
The panel stays in a semi-horizontal position, which allows
access to the inner parts of the boiler.
In order to increase the manoeuvering space, it is possible to
raise the control panel and rotate it to a fully horizontal position.
.
1
A
4
19
Installation
1
2
3B4
5
6
6.12 Fitting the Time Clock
To fit the mechanical time clock supplied with the boiler, it is necessary to proceed as follows:
1) Remove the fastening screws ‘A’ from beneath the boiler;
2) Rotate the control panel forward, if necessary , it is possib le to
lift the control panel up and rotate it to a fully horizontal position;
3) Using a suitable knife, remove the knock out ‘B’ for the time
clock;
4) Insert the clock into the control panel;
5) Secure the clock in place using the four screw provided;
6) Remove the two screws ‘C’ and remove the cover to allow
access to the Printed Circuit Board;
7) Plug the clock cable into the connector on the Printed Circuit
Board and conect the cables to the clock as indicated in Fig.
6.21
A
A
20
Installation
5
4
3
2
1
GREY
BLACK
RED
3
2
1
GREY
BLACK
RED
MECHANICAL
TIME CLOCK
DIGITAL
TIME CLOCK
6.12 Fitting the Time Clock (continued)
7
21
FIG. 6.21
Installation
6.13 Room Thermostat Connection
To connect a room ther mostat, it is necessar y to:
1. - Open the control panel as indicated in SECTION 6.11.
2.- Remove the link “A” from the terminal block on the reverse
of the control panel.
3. - Insert the ther mostat cable through the cable grommet and
fasten it by means of the cable-clamp provided.
4. - Connect the thermostat wires to the terminal block
(Diagram A).
5.- If a remote time clock is to be fitted, disconnect the integral
time clock from the P.C.B.
6. - Using a volt-free switching time clock, connect the switching
wires from the time clock following points 1-4 above
(Diagram B).
7. - If using an external time clock and room thermostat, these must
be connected in series as points 1-7 above (Diagram C).
Note: Only a low voltage room thermostat capable of volt
free switching must be used. Factory fitted integral
wiring must not be disturbed when wiring external
controls.
A
Important!!
DO NOT install 240v wires and low voltage switching wires in
the same cable/conduit, this may cause unwanted induced
voltages in the low voltage switching system.
22
FIG. 6.22
Installation
FUSE
FUSE
J
K
L
O
Q
R
T
S
MN
A
B
CN103
CN104
CN102
CN100
CN101
5
4
3
2
1
A
A
B
CN103
CN104
CN102
CN100
CN101
5
4
3
2
1
A
G
P
6.14ELECTRICAL/SYSTEM DIAGRAMS
FIG. 6.23
A - Jumper:
1 -Don’t move (jumper is factory set in position B)
2 -Anti-cycling Device Adjustment for Heating
Position A = 0 minsPosition B = 2 mins
3 -Don’t move (jumper is factory set in position B)
4 -Don’t move (jumper is factory set in position B)
5 -Fan/Pump over-run selector
Position A = OFFPosition B = ON
B - Central Heating Temperature Adjustment
C - Connector for Remote Control (Climate Manager)
D - Domestic Hot Water Temperature Adjustment
E - Soft-light Adjustment
F - Maximum Heating Adjustment
G - Time Clock Connector
H - On/Off Switch
I -Fume Sensor L.E.D.
J - Central Heating Selector
K - Ignition Failure (Lockout) L.E.D.
L - On/Off L.E.D.
M - Reset Button
N - Central Heating L.E.D.
O - Transformer
P - Spark Generator I.C.
Q - Motor ised diverter valve Relay
R - Gas Valve Relay
S - Circulation Pump Relay
T - Fan Relay
A01 - Circulation Pump
A02 - Fan
A03 - Spark Generator Supply
A04 - Gas Valve Supply
A05 - Motorised diverter Valve
A07 - Detection Electrode
A08 - Main Circuit Temperature Probe
A09 - Domestic Hot Water Temperature Probe
A10 - D.H.W. Flow switch
A11 - Pump Pressure Switch
A12 - Modulator
A13 - Air Pressure Switch
A14 - Safety Thermostat
A15 - External (Room) Thermostat
COLOURS:
Gr - Grey Bl - Blue
Bi - WhiteNr - Black
Rs - RedRo - Pink
Mr - Brown
23
Installation
3
4
8
7
10
9
16
15
17
18
19
20
21
12
1314
5
1
6
2
11
6.15Water Circuit Diagram
FIG. 6.24
Legend:
1.Fan
Heat Exchanger
2.
3.Overheat Thermostat
4.Burner
5.Detection Electrode
6.Ignition Electrodes
7.Main Circuit Temperature Probe
8.Pressure Gauge
9.Low Water Pressure Switch
10. Safety Valve
11. Domestic Hot Water Temperature Probe
12. Secondar y Exchanger
13. Gas Valve
14. D.H.W. Flow Switch
15. D.H.W. inlet filter
16. Drain Valve
17. Motor ised Diverter Valve
18. Automatic By-pass
19. Circulation Pump with Automatic Air Release Valve
20. Expansion Vessel
21. Air Pressure Switch
A. Central Heating Flow
B. Domestic Hot Water Outlet
C. Gas Inlet
D. Domestic Cold Water Inlet
E. Central Heating Return
24
7.COMMISSIONING
7.1Initial Preparation
Preliminary electrical system checks to ensure electrical safety
must be carried out by a competent person i.e.polarity , earth continuity, resistance to earth and short circuit.
FILLING THE HEATING SYSTEM:
Lower the control panel and remove the case panels (see
SECTION 6.11 for further information).
Open the central heating flow and return cocks supplied with
the connection kit (there are two isolation points on the return
connection).
Unscrew the cap on the automatic air release valve one full
turn and leave open permanently.
Close all air release valves on the central heating system.
Gradually open valve(s) at the filling point (filling-loop) connection to the central heating system until water is heard to flow,
do not open fully.
Open each air release tap starting with the lowest point and
close them only when clear water, free of air, is visible.
Purge the air from the pump by unscrewing the pump plug
anticlockwise, also manually rotate the pump shaft in the
direction indicated by the pump label to ensure the pump
is free.
Refit the pump plug.
Continue filling the system until at least 1.5 bar registers on the
pressure gauge.
Inspect the system for water soundness and remedy any leaks
discovered.
Filling of the D.H.W. System:
Close all hot water draw-off taps.
Open the cold water inlet cock supplied with the connection kit.
Open slowly each draw-off tap and close them only when clear
water, free of bubbles, is visible.
7.2Initial Start-up
THE CHECKS TO BE RUN BEFORE INITIAL START-UP ARE AS FOLLOWS:
1. Make sure that:
-the screw on the automatic air valv e has been loosened when
the system is full;
- If the water pressure in the system is below 1 bar, bring it up
to the appropriate level;
-Ensure that the gas cock is closed;
-Make sure that the electrical connection has been made
properly and that the earth wire is connected to an efficient
earthing system;
- Supply power to the boiler by pushing the On/Off button “A”
(see FIG. 6.16) - the L.E.D.“K” will illuminate.Then push the
button “F” in for central heating - the L.E.D.“G” will illuminate.This will start the circulation pump.After 7 seconds, the
boiler will signal a shutdown due to ignition failure.Leave the
boiler as it is until all of the air has been bled from the system.
-Loosen the cap on the head of the pump to eliminate any air
pockets;
-Repeat the procedure for bleeding the radiators of air;
-Open the taps for a brief period;
-Check the system pressure and, if it has dropped, open the
filling loop again to bring the pressure back up to 1 bar.
2. Make sure that all gate valves are open;
3. Turn on the gas cock and check the seals on the connections
with an approved soap solution and eliminate any leaks.
4. Press the reset button “I” for the lighting system; the spar k
will light the main burner.If the burner does not light the first
time, wait 1 minute and repeat the procedure.
5. Check the minimum and maximum burner pressure values;
adjust if needed using the values indicated in the table in
SECTION 4.
Gas Supply:
Inspect the entire installation including the gas meter, test for
tightness and purge the supply as described in BS 6891:1988.
Open the gas cock (supplied with the connection kit) to the
appliance and check the gas connections on the appliance for
leaks.
When the installation and filling are completed, flush the system
while cold, refill, turn on the Central Heating system (Section
7.2) and run it until the temperature has reached the boiler operating temperature.The system must then be immediately flushed
through.
The flushing procedure must be in line with BS 7593:1992 code
of practice for treatment of water in domestic hot water central
heating systems.
During this operation, we highly recommend the use of a central
heating flushing detergent (Fernox Superfloc or equivalent),
whose function is to dissolve any foreign matter that may be in
the system.
Substances different from these could create serious problems to the pump or other components.
The use of an inhibitor in the system such as Fernox MB-1 or
equivalent is strongly recommended to prevent corrosion
(sludge) damaging the boiler and system.
Failure to carry out this procedure may invalidate the appliance warranty.
7.3Operational Adjustments
To access the areas in which adjustments are made, it is necessary to open the control panel, as indicated in Section 6.11, then
remove the rear inspection cover by unscrewing the two screws.
Access is thereby provided to the P.C.B .and to the following components:
1. The power supply cable connector;
2. The fuses;
3. The soft-light potentiometer the setting for which can range
from the minimum thermal power to the maximum;
4. The maximum thermal heating power potentiometer
adjustable by the minimum to maximum power (already calibrated in the factory to 70% of the maximum thermal power);
5. The jumper for adjusting the ignition delay (anti-cycling) fea-
ture, which can be set from 0 to 2 minutes (set in the factory
at two minutes);
6.
Fan/Pump Over-run (Electrical Diagram). When the jumper is
set to position A the Fan and Pump over-run is activated. (The
jumper is factory set in position B)
7. The time clock connector.
25
Commissioning
7.4Combustion Analysis
The flue connector has two apertures, readings can be taken for the
temperature of the combustion by-products and of the combustion
air, as well as of the concentrations of O
To access these intakes it is necessary to unscrew the front
screw and remove the metal plate with sealing gasket.
It is possible to activate the flue test mode (maximum output) by
pressing and holding the RESET button “I” for 10 seconds, the
yello
w L.E.D.“H” will light.
tion after 5 minutes.The boiler can be returned to normal operation sooner by switching the boiler off and on again.
The boiler will return to normal opera-
2
and CO2, etc.
FU008A
7.5Product of Combustion Discharge
Monitoring
In the boiler, it is possible to monitor the correct operation of the
flue exhaust/air intake, checking for a loss of general pressure in
the system.Through the use of a differential manometer connected to the test points of the combustion chamber, it is possible to
detect the P of operation of the air pressure switch.
The value detected should not be less than 0.55 mbar (TP 23) -
0.90 mbar (TP 30) under conditions of maximum thermal power
in order for the boiler to function properly and without interruption.
7.6Boiler Safety Systems
The boiler is fitted with the following devices (see SECTION 6.10
for references).
1 - Ignition Failure:
This indicates ignition failure when a flame is not detected
within 7 seconds of starting an ignition sequence.The L.E.D.
“I” will illuminate to signal the shutdown status.
The system can be reset by pressing and releasing the button “J” after checking to make sure that the gas cock is
open.
2 - Insufficient System Pressure:
In the event of insufficient water pressure in the heating system, a safety device will shutdown the boiler. Check the system pressure on the pressure gauge “D” and if it is less
than 0.4 bar refill the system to 1.5 bar. Once the system
pressure is at the correct level the boiler will reset automatically.
3 - Overheating:
This control shuts off the boiler in the case where the primary circuit reaches a temperature in excess of 105°C.
The red L.E.D.“I” will illuminate to signal this shutdown status.
The system can be reset by waiting a few minutes for the
primary exchanger to cool down and then by pressing and
releasing the “J” button.
4.Anti-frost device:
The boiler is fitted with a device which, in the event that the
water temperature falls below 8
runs until a temperature of 18˚C is attained. In the event that
the water temperature falls below
switches to Domestic Hot Water and the burner fires and
runs on minimum power until a temperature of 33˚C is
attained.
This device is only activated when the boiler is operating
perfectly and
- the system pressure is sufficient;
- the boiler is powered electrically;
- gas is being distributed.
6.Exhaust Discharge Anomaly Shutdown:
The boiler is fitted with safety devices, which in the event of
defective discharge of e xhaust products, automatically interrupts the gas supply, thereby shutting off the boiler.
The shutdown of the boiler is temporary and is indicated by
the illumination of the yellow L.E.D.“E” for a period of about
15 minutes.
Once this time period has passed and the discharge state of
exhaust fumes has returned to normal, the boiler automatically turns back on.
7.Pump Protection:
To prevent the pump from seizing the boiler will activate the
pump for 20 seconds every 21 hours after it’s last operation.
˚C the pump activates and
3
˚C, the diverter valve
FU009A
26
Commissioning
7.7Draining the System
Draining the Heating System
The heating system must be drained as follows:
- Turn off the boiler;
- Attach a hose pipe and open the drain valve;
- Drain the system at the lowest points (where present).When
the heating system is unused for an extended period of time,
it is recommended that you add antifreeze with an ethylene
glycol base to the water in the heating pipe work and radiators if the ambient temperature drops below 0°C during the
winter.
This makes repeated draining of the entire system unnecessary.
Draining the Domestic Hot Water System
Whenever there is the danger of the temperature dropping below
the freezing point, the domestic hot water system must be
drained as follows:
- Turn off the general water valve for the household plumbing
system;
- Turn on all the hot and cold water taps;
- Empty the remaining water from the lowest points in the sys-
tem (where present).
7.8Completion
7.10Instructing The End User
1.Hand over the copy of the End User Instructions supplied
with the appliance, together with these instructions, and
explain how to use the timeclock and room thermostat if fitted.
2.Show the End User how to switch the appliance off quickly,
and indicate the position of the electric supply isolator.
3.Inform the End User of the location of all drains, isolating
valves and air vents.
4.Explain how to turn the appliance off for both short and long
periods and advise on the precautions necessary to prevent
damage in the event that the appliance is inoperative when
freezing conditions occur.
5.Finally advise the End User that, for continued safe and efficient operation, the appliance must be serviced by a competent person at least once a year.
For the Republic of Ireland it is necessary to complete a
“Declaration of Conformity” to indicate compliance to I.S. 813. An
example of this is given in the current edtion of I.S.813. In addition it is necessary to complete the Log Book.
7.9Operational Checks
1.The flue system must be visibly checked for soundness.
2.Run the Central Heating and manipulate the Central
Heating temperature control knob to check the gas pressures at high and low fire with a pressure guage/manometer, and adjust if necessary.
3.Range rate the thermal power for Central Heating, as
detailed in SECTION 8.2
4.Run the Domestic Hot Water, manipulate the Domestic Hot
Water temperature control knob to check the gas pressures
at high and low fire with a pressure guage/ manometer, and
adjust if necessary.
5.Balance the Central Heating system until all return temper-
atures are correct and equal.
6.Turn ON/OFF button OFF, disconnect the pressure Gauge,
retighten screw and re-light boiler.
7.Re-examine Central Heating, Domestic Hot Water and Cold
Water supplies for soundness.
8.Check the appearance of the gas flame to assess the ade-
quacy of the combustion air supply.
9.If external controls have been disconnected, reconnect and
Consumption (15°C; 1013mbar)m3/h
Consumption (15°C; 1013mbar)Kg/h
Gas Burner Pressure
max - minmbar
Consumption (15°C; 1013mbar)m3/h
Consumption (15°C; 1013mbar)Kg/h
Gas Burner Pressure
max - minmbar
45.67
20
20
1.25
2.80
----
11.3 - 2.0
1.35
3.49
---
11.5 - 2.2
8.1Changing the Type of Gas
The boiler can be converted to use either
methane (natural) gas (G20) or L.P.G. (G30
- G31) by an Authorised Service Centre.
The operations that must be performed are
the following:
1. Replace the jets on the main burner (seetable in section 8);
2. Adjust the maximum and minimum thermal capacity values for the boiler
(see table in section 8 and 8.2
Adjusting the Gas Pressures);
3. Adjust the maximum thermal power setting;
4. Adjust the soft-light feature (see tablebelow for recommended pressure);
5. Adjust the ignition delay feature for the
heating system by adjusting the
jumper 2 as shown in Section. 6.13 (can
be set from 0 to 2 mins.).
1
B
A
CATEGORY
II2H3+
Recommended
Soft-light
Pressure
(mbar)
Model
Microcombi
TP 2351212
TP 304.51212
8.2Adjusting the Gas Pressures
Setting the minimum and the maximum power of the boiler
1. Check that the supply pressure and dynamic pressure to the
gas v
2. To do this, loosen the screw “A”.
3. To check the pressure supplied by the gas valve to the burner,
4. Push the On/Off button to “ON” position -green light- and
alve is a minimum of 20 mbar for natural gas.
Fit the pipe of the pressure gauge to the inlet pressure connection of the gas valve “B” and check for the correct standing pressure
correct working pressure.
When you have completed this operation, replace the screw
“A” securely into its housing to seal off the gas (check for
tightness).
loosen the scre
pressure outlet test point of the gas valve “D”.
Disconnect the compensation pipe “D1” either from the gas
v
alve or from the sealed chamber.
ensure that the hot water temperature control knob is set to
maximum.
T
urn on the boiler by running a hot water tap.
Adjust the 10mm nut “E” on the modureg to set the maximum
gas pressure
wise to decrease the pressure until the required pressure is
achieved (see TABLE A page 28).
Liquid Butane Gas
G30
80.58
29
28
0.72
----
2.09
28.1 - 5.0
0.80
---
2.60
26.8 - 5.3
Methane Gas
G20
, then operate the appliance and check for the
w “C”.Fit the pipe of the pressure gauge to the
, turn the nut clockwise to increase and anti clock-
Butane Gas
Liquid Propane Gas
35.6 - 6.8
34 - 6.5
Liquid
Propane Gas
G30
G31
80.58
37
36
0.72
----
2.06
0.80
---
2.56
Liquid
G31
28
Gas Adjustments
2
D
C
3
E
4
5. To set the minimum power, disconnect a supply terminal “F1”
from the modureg and adjust screw “F” (ensure that the
10mm n
increase the pressure and anti-clockwise to decrease the
pressure (displayed on the pressure gauge) corresponding to
the minimum power (see TABLE
6. When you have completed the above operations, turn off the
hot w
on the gas valve, reconnect the compensation pipe and
replace the cap on the screw of the modureg.
Setting the maximum heating circuit power
7. To set the maximum heating circuit power, push the On/Off
b
utton to the “ON” position -green light- and push the Heating
button and set the time cloc
“ON” position -green light. Tur n the knob of the heating thermostat cloc
8. Remove the inspection panel of the P.C.B. and fit a small
cross-head scre
below). Turn clockwise to increase the pressure or counterclockwise to reduce the pressure. Adjust the setting to the
required heating pressure value (displayed on the pressure
gauge), as indicated in the charts shown on pages 28.
9. Turn off the boiler by placing the main switch to the "OFF"
position.
Setting the pressure for soft-light ignition.
Disconnect the detection electrode connection close to the
P.C.B. (F
Start the boiler and during the ignition sequence adjust the left
hand potentiometer until the gas pressure reads the required
gas pressure (see the table on pag
Once the gas pressure is set turn off the boiler and re-connect
the detection electrode to the P.C.B.
NB.: It may be necessary to reset the flame failure reset a
number of times during this operation.
ut is held in position). Turn the screw clockwise to
A page 28).
ater tap, reconnect the supply terminal to the modureg
k and any external controls to the
kwise to maximum.
wdriver in to the right hand potentiometer (see
IG. 6.13).
e 28).
10. Remove the pipe from the test point and tighten the scre w “C”
to the pressure test point in order to seal off the gas
11. Carefully check the pressure test points for gas leaks (valve
F
inlet and outlet).
IMPORTANT!
Whenev
tions, always check for leaks using a leak detection fluid.
er you disassemble and reassemble the gas connec-
.
Soft - Light
Adjustment
Max Heating
Adjustment
29
Gas Adjustments
TP 23 MFFI
2.80
20
10.3
2.0
1.16
2.09 Kg/h
0.87 Kg/h
28.1 mbar
5.0 mbar
28 mbar
14 x 0.7214 x 1.25
2.06 Kg/h
0.85 Kg/h
35.6 mbar
6.8 mbar
37 mbar
14 x 0.72
TP 30 MFFI
3.49
20
11.5
2.2
1.48
2.60 Kg/h
1.10 Kg/h
26.8 mbar
5.3 mbar
28 mbar
14 x 0.8014 x 1.35
2.56 Kg/h
1.09 Kg/h
34.0 mbar
6.5 mbar
37 mbar
14 x 0.80
model 23
model 30
model 23
model 30
34
36
38
40
model 23
model 30
TABLE A
Regulating the heating power for natural gas (G20)
CG010A
Regulating the heating power for propane gas (G31)
Regulating the heating power for butane gas (G30)
CG011A
30
9.MAINTENANCE
It is recommended that the following inspections be carried
out on the boiler at least once a year:
1 - Check the seals for the water connections;replace any
faulty seals
2 - Check the gas seals; replace any faulty gas seals.
3 - Visual check of the entire unit.
4 - Visual check of the combustion process or analysis of
combustion by-products (see section 3.6) and cleaning of
the burner if needed.
5 - If called for by point.3, dismantling and cleaning of the
combustion
chamber.
6 - If called for by point.4, dismantling and cleaning of the
burner jets.
7 - Visual check of the primary heat exchanger:
- check for overheating in the blade assembly;
- clean the exhaust fan if needed.
8 - Adjustment of the flow rate of the gas: flow rate for lighting,
partial load and full load.
9 - Check of the heating safety systems:
- safety device for maximum temperature
(overheat thermostat);
- safety device for maximum pressure (safety valve).
10- Check of the gas safety systems:
- safety device for lack of gas or flame ionisation
(detection electrode);
- safety device for gas cock.
11- Check of the electrical connection (make sure it complies
with the instructions in the manual).
12- Check of domestic hot water production efficiency (flow
rate and temperature)
13- General check of the combustion by-products of the dis-
charge/ventilation system.
14- Check of the general performance of the unit.
.
31
10. SERVICING INSTRUCTIONS
To ensure efficient safe operation, it is recommended that the
boiler is serviced annually by a competent person.
Before starting any servicing work, ensure both the gas and
electrical supplies to the boiler are isolated and the boiler is
cool.
Before and after servicing, a combustion analysis should be
made via the flue sampling point (please refer to SECTION 3.4 for
further details).
After servicing, preliminary electrical system checks must be carried out to ensure electrical safety (i.e. polarity, earth continuity,
resistance to earth and shor t circuit).
10.1Replacement of Parts
The life of individual components vary and they will need servicing or replacing as and when faults develop.
The fault finding sequence chart in SECTION 7 will help to locate
which component is the cause of any malfunction, and instructions for removal, inspection and replacement of the individual
parts are given in the following pages.
10.2To Gain General Access
All testing and maintenance operations on the boiler require the
control panel to be lowered.This will also require the removal of
the casing.
FIG. 10.3
2. The control panel moves downward and when pulled forward,
rotates on two lateral hinges; the panel stays in a semi-horizontal position, which allows access to the inner parts of the
boiler (FIG. 10.2);
3. In order to increase the manoeuvring space, it is possible to
raise the control panel and rotate it to a fully horizontal position (FIG. 10.3);
4. Remove the screws “B”from the front panel bottom lip
(FIG. 10.4);
5. Lift the front panel up and forward from the raised screws at the
the top of the casing (FIG.10.5).
FIG. 10.4
10.2.1 Removing the front panel
1. Loosen the fastening screws “A” of the control panel located
on the lower part of the panel itself. (FIG. 10.1);
FIG. 10.1
A
FIG. 10.2
B
32
FIG. 10.5
Servicing Instructions
10.2.2 Removing the sealed chamber front cover
1. Remove the screws “C”(FIG. 10.6);
2. Lift the sealed chamber front cover from the locating pins
(FIG. 10.7).
FIG. 10.6
C
FIG. 10.7
C
10.2.3 Removing the side panels
1. Remove the four screws “D” for each side panel (FIG.10.8);
2. Pull the panel away from the boiler at the base, then lift the
panel up and remove from the boiler (FIG.10.9).
FIG. 10.8
D
D
FIG. 10.9
D
D
33
Servicing Instructions
10.3Access to the Combustion Chamber
10.3.1 Removing the combustion cover
1. Remove the screws “E”(FIG. 10.10);
2. Lift off the combustion cover.
E
E
10.3.2 Removing the burner and jets
1. Remove the screws “F”from the burner (FIG. 10.11);
2. Remove the burner (FIG. 10.12);
3. Disconnect the electrodes (see SECTION 10.3.3);
4. Remove the jets using a No.7 socket spanner;
5. Replace in reverse order.
FIG. 10.11
E
E
FIG. 10.10
10.3.3 Removing the electrodes
Before carrying out this procedure, unscrew and slide the burner forward (see previous section).
1. Remove rubber gasket “G” (FIG. 10.13);
2. To remove the detection electrode disconnect the cable at its
connection point close to the P.C.B. (FIG. 10.14);
3. Remove screw “H” (FIG. 10.15);
4. Gently slide the electrode downward (FIG. 10.16).
FIG. 10.13
G
FIG. 10.14
FIG. 10.15
H
F
Fig. 10.12
F
FIG. 10.16
To replace, repeat the steps in
reverse order, paying particular
attention to the following:
a - Centre the electrode in the
positioning hole carefully,
otherwise the electrode may
break;
b - Ensure that the left hand and
right hand electrodes are
located the correct way
round (facing each other), to
give the correct spark gap;
c - Check that the cables have
been connected correctly;
d - Check that the rubber gasket
seals the cable/ electrode
connection point completely.
34
Servicing Instructions
10.3.4 Removing the main heat exchanger
1. Drain the boiler of water;
2. Remove the side panels (see 10.2.3)
3. Remove the overheat thermostat sensor “I”(FIG. 10.17);
4. Remove the clip “J” (FIG. 10.18);
5. Remove the “U” clip “K” (FIG. 10.19);
7. Pull down the pipe (FIG.10.20);
4. Pull it straight out (FIG.10.21).
Fig. 10.17
I
FIG. 10.18
FIG. 10.21
10.3.5 Removing the air pressure switch
1. Disconnect the electrical connections “L” and silicone pipes
“M” from their connection points (FIG. 10.22);
2. Remove screws “N” on the top of the sealed chamber (FIG.
10.23);
3. Lift out the air pressure switch (FIG.10.24);
4. Unscrew to remove the switch from the plate.
FIG. 10.19
FIG. 10.20
FIG. 10.22
J
J
L
M
M
FIG. 10.23
K
FIG. 10.24
N
35
N
Servicing Instructions
10.3.6 Removing the fan
1. Disconnect electrical connections “O” and silicone pipe “P”
(FIG.10.25);
2. Remove screw “Q” and remove the fan collar clamp “R” (FIG.
10.26);
3. Remove screws “S” (FIG. 10.27);
4. Remove fan and mounting plate (FIG. 10.28).
FIG. 10.25
O
O
FIG. 10.26
P
10.4Access to the Gas Valve
10.4.1. Removing the spark generator
1. Disconnect ignition leads “T”by pulling upward
(FIG. 10.29);
2. Remove the screw “U” (FIG. 10.30);
3. Remove the spark generator by pulling forward from the gas
valve (FIG.10.31).
FIG. 10.29
T
FIG. 10.27
FIG. 10.28
R
FIG. 10.30
Q
U
S
FIG. 10.31
S
S
36
Servicing Instructions
10.4.2 Removing the gas valve
Important! Before removing the gas valve, ensure the gas sup-
ply is turned off.
1. Disconnect all the cables from the solenoid and modureg;
2. Remove the spark generator (see previous section);
3. Release the nuts “V” (FIG. 10.32);
4. Remove the screws “W”from the bottom of the gas valve (FIG.
10.33);
5. Remove the gas valve (FIG.10.34).
FIG. 10.32
V
V
10.5Access to the Water Circuit
Important! Before any component is removed, the boiler
must be drained of all water.
10.5.1 Removing the D.H.W. (secondary) exchanger
1. Remove the screws “X” (FIG 10.35);
2. Disconnect the cable “Y” (FIG 10.36);
3. Push the exchanger towards the rear of the boiler, and
lift upwards and remove out of the front of the boiler
(FIG 10.37-10.38);
4. Before replacing the exchanger ensure that the O-rings
are in good condition and replace if necessary.
FIG. 10.35
FIG. 10.33
FIG. 10.34
W
W
FIG. 10.36
FIG. 10.37
X
X
Y
37
FIG. 10.38
10.5.2 Removing the pump pressure switch
1.Remove the pump pressure switch electrical connections “Z”
(FIG10.39);
2. Unscrew the pump pressure switch by
nut (FIG10.40);
3.Remove the pump pressure switch.
FIG. 10.39
using
a spanner on the
Z
10.5.3 Removing the safety valve
1. Disconnect the discharge pipe work from below the boiler;
2. Unscrew and remove the valve “A1” (FIG. 10.41).
A1
FIG. 10.41
10.5.4 Removing the automatic air vent
1. Remove the U-clip “B1” (FIG. 10.42);
2. Unscrew valve top and remove valve complete with float
(FIG 10.43).
FIG. 10.40
B1
FIG. 10.42
FIG. 10.43
38
Servicing Instructions
10.5.5 Removing the pump
1. Remove the electrical connection “ C1”(FIG. 10.44);
2. Remove the allen screw “D1” (FIG. 10.45);
3. Remove the pump (FIG.10.46).
C1
FIG. 10.44
D1
D1
10.5.6 Removing the pressure gauge
1. Remove the U-clip “E1” (FIG. 10.47)
2. Push the pressure gauge through the control panel from the
rear (FIG. 10.48).
FIG. 10.47
E1
FIG. 10.48
D1
D1
FIG. 10.45
FIG. 10.46
39
Servicing Instructions
10.5.7 Removing the expansion vessel
1. Release nuts “F1” and remove the gas pipe (FIG. 10.49);
2. Release nut “G1” (FIG. 10.50);
3. Remove back-nut “H1” (FIG. 10.51);
4. Remove the expansion vessel (FIG. 10.2).
FIG. 10.49
F1
FIG. 10.50
G1
F1
FIG. 10.51
10.5.8 Removing the overheat thermostat
1. Disconnect the ov erheat thermostat electrical connections “I1”
(FIG. 10.53);
2. Then remove the thermostat from its mounting by releasing
the securing clip (FIG. 10.54 /10.55).
FIG. 10.53
I1
FIG. 10.54
FIG. 10.55
H1
FIG. 10.52
10.5.9 Removing the heating temperature
sensor (N.T.C.)
1. Pull off the electrical connector and unscrew the sensor probe
using a suitable spanner (FIG. 10.56).
FIG. 10.56
40
Servicing Instructions
10.5.10 Removing the D.H.W. temperature
sensor (N.T.C.)
1. Pull off the electrical connector and unscrew the sensor probe
using a suitable spanner (FIG. 10.57).
FIG. 10.57
10.5.11 Removing the D.H.W. flow switch
1. Unplug the electrical connector “J1” (FIG. 10.58);
2. Unscrew the screws “K1” (FIG. 10.59);
3. Remove the D.H.W. flow switch.
6.5.12 Removing the divertor valve actuator
1. Unplug the electrical connector “L1” (FIG. 6.60);
2. Release the retaining clip “M1” and remove the divertor
valve actuator (FIG.6.61).
L1
FIG. 6.60
M1
FIG. 10.58
FIG. 10.59
FIG. 6.61
J1
K1
41
Servicing Instructions
10.6Access to the Control System
Important! Isolate the electrical supply to the boiler before
accessing the control panel.
10.6.1 Checking the fuses
1. Remove the inspection cover on the reverse of the control
panel (FIG. 10.62);
2. Remove the fuses (FIG. 10.63).
FIG. 10.56
10.6.2 Removing the P.C.B.
1. Isolate electricity;
2. Remove the inspection cover from the reverse of the control
panel;
3. Unplug all electrical connections from the P.C.B.
4. Remove the screws “N1”(FIG. 10.64);
5. Separate the facia panel from the rear of the control panel ;
6. Remove the screws “O1”and remove the P.C.B.
(FIG. 10.65).
FIG. 10.64
N1
N1
N1
FIG. 10.63
FIG. 6.65
O1
O1
42
11. FAULT FINDING
11.1Fault Finding Guide (Flow-charts)
These fault finding guides are not exhaustive. However, it is possible to detect and correct many defects by using the standard
fault finding diagrams described in this chapter, ensure these
guides are carried out in the set order.
To ensure that the external controls do not interfere with the fault
finding, disconnect the wires from the terminal block on the rear
of the control panel and provide a solid link between the terminals.
CE Certification
Heat Input max/min kW
Heat Outputmax/min kW
Efficiency of Nominal Heat Input%
Efficiency at 30% of Nominal Heat Input%
Heat Loss to the Casing (∆T=50°C)%
Flue Heat Loss with Burner Operating%
Flue Heat Loss with Burner Off%
Max Discharge of Products of Combustion
(G20)Kg/h
Residual Discharge Headmbar
3
Consumption at Nominal Capacity(G2 0)m
Gas Consumption after 10 Minutes*m
/h
3
(15°C, 1013 mbar) (G30-G31)Kg/h
Temp. of exhaust fumes at nominal capacity °C
2
Content%
CO
2
Content%
O
CO Contentppm
Minimum Ambient Temperature°C
Head Loss on Water Side (max) (∆T=20°C) mbar
Residual Head of Systembar
Heating Temperature max/min °C
Domestic Hot Water Temperature (approx)max/min °C
D.H.W. Flow Rate ∆T=35°Cl/min
D.H.W. Minimum Flow Ratel/min
Pressure of Domestic Hot Watermax/min bar
Expansion Vessel Capacityl
Expansion Vessel Pre-load Pressurebar
Maximum Water Content of Systeml
Maximum Heating Pressurebar
Nominal PressureNatural Gas (G20) mbar
LPG (G30-G31)mbar
Electrical SupplyV/Hz
Power ConsumptionW
Protection Grade of Electrical SystemIP
Internal Fuse Rating
WeightKg
TP 23 MFFI
0694BO0090
25.6/11.0
24.8/9.7
92.9
91.1
1.0
6.1
0.4
49.5
0.96
2.72
0.32/0.39
2.02/2.00
123
7.2
7.5
51.9
+5
200
0.25
82/42
56/36
9.7
2.6
8/0.2
6
1
130
3
20
30-37
230 / 50
110
X4D
FAST 2 AT
30
TP 30 MFFI
0694BO0090
36.6/15.5
30.6/12.1
83.4
80.9
1.7
5.7
0.4
63.73
1.6
3.49
0.41
2.60/2.56
121.2
7.19
7.8
53
+5
200
0.25
82/38
56/36
12.5
2.5
8/0.2
7
1
130
3
20
28-37
230/50
148
X4D
FAST 2 AT
32
G.C. Number47-116-3247-116-33
*Calculated at 70% maximum output
Manufacturer:Merloni T ermoSanitari S.p.A.
T
echnical Service Hot Line:0870 241 8180
Customer Service Help Desk:0870 241 8174
0 99 84 1869 000
52
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.