McQuay ALP-027C Installation Manual

Table of Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...3
Nomenclature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...3
Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...3
Installation
Rigging and moving units . . . . . . . . . . . . . . . . . . . . . ...3
Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...3
Refrigerant Piping
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4
Recommended line sizes . . . . . . . . . . . . . . . . . . . . . ...5
Hot gas bypass components. . . . . . . . . . . . . . . . . . ...6
Refrigerant piping connections . . . . . . . . . . . . . . . . . ...6
Holding charge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...6
Leak Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...6
Evacuation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...6
Charging the system . . . . . . . . . . . . . . . . . . . . . . . . . ...7
Refrigerant charge . . . . . . . . . . . . . . . . . . . . . . . . . . ...7
Pressure-vacuum equivalents . . . . . . . . . . . . . . . . . . ...7
Dimensional Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...7
Vibration isolators . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...8
Physical Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...9
Electrical Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...10
Field Wiring
Typical field diagram . . . . . . . . . . . . . . . . . . . . . . . . ...11
Control center layout and operation . . . . . . . . . . . . ...12
Recommended disconnect location . . . . . . . . . . . . ...12
Electrical legend . . . . . . . . . . . . . . . . . . . . . . . . . . . ...12
Electrical Hook-up . . . . . . . . . . . . . . . . . . . . . . . . . . . ...12
Normal Sequence of Operation
Start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...13
Pumpdown cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . ...13
Start-up&Shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
System Maintenance
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...14
Fan shaft bearings . . . . . . . . . . . . . . . . . . . . . . . . . ...14
Electrical terminals . . . . . . . . . . . . . . . . . . . . . . . . . ...14
Compressor oil level . . . . . . . . . . . . . . . . . . . . . . . . ...14
Condensers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...14
Refrigerant sightglass . . . . . . . . . . . . . . . . . . . . . . . ...14
Service
Thermostat expansion valve... . . . . . . . . . . . . . . . ...15
Filter driers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...15
Liquid line solenoid valve.... . . . . . . . . . . . . . . . . ...15
In-Warranty Return Material Procedure . . . . . . . . . ...15
Appendix: Standard Controls
High pressure control . . . . . . . . . . . . . . . . . . . . . . . ...16
Low pressure control . . . . . . . . . . . . . . . . . . . . . . . . ...16
Compressor lockout . . . . . . . . . . . . . . . . . . . . . . . . ...16
Compressor motor protector . . . . . . . . . . . . . . . . . . ...16
FanTrol head pressure control. . . . . . . . . . . . . . . . . ...16
Oil pressure safety control . . . . . . . . . . . . . . . . . . . ...16
Appendix: Optional Controls
SpeedTrol head pressure control . . . . . . . . . . . . . . ...17
Low ambient start . . . . . . . . . . . . . . . . . . . . . . . . . . ...17
High ambient control . . . . . . . . . . . . . . . . . . . . . . . . ...17
Part winding start . . . . . . . . . . . . . . . . . . . . . . . . . . ...17
Phase/voltage monitor . . . . . . . . . . . . . . . . . . . . . . . ...17
Hot gas bypass (field installed) . . . . . . . . . . . . . . . ...18
VAV direct expansion systems . . . . . . . . . . . . . . . . ...18
ALP Controls, Settings & Functions . . . . . . . . . . . . ...19
Troubleshooting Chart . . . . . . . . . . . . . . . . . . . . ...20.21
Product Warranty . . . . . . . . . . . . . . . . . . . . . . . . . . . ...22
‘“McQuay” and “SeasonCon” are registered tradenames of SnyderGeneral Corporation. “FanTrol” and “SpeedTrol” are tradenames of SnyderGenera! Corporation.
01994 SnyderGeneral Corporation. All rights reserved throughout the world.
“Bulletin illustrations cover the general appearance of SnyderGeneral Corporation products at the time of publication
and we reserve the right to make changes in design and construction at any time without notice.”
Page2/lM404
Introduction
Model type ALP air cooled condensing units are designed for outdoor installations and are compatible with either air handling or chilled water systems. Each unit is completely assembled and factory wired before evacuation, charg-
ing and testing. Each unit consists of an air cooled condenser with integral subcooler section with complete discharge pip­ing and suction and liquid connections for connection to any air or water cooling evaporator.
Inspection
When the equipment is received, all items should be carefully rier and a claim should be filed. The unit serial plate should checked against the bill of lading to insure a complete ship­ment. All units should be carefully inspected for damage upon arrival. All shipping damage should be reported to the car-
be checked before unloading the unit to be sure that it agrees with the power supply available.
Installation
Note: Installation and maintenance are to be performed only by qualified personnel who are familiar with local codes and regulations, and experienced with this type of equipment. Caution: Sharp edges and coil surfaces area potential injury hazard.
Avoid contact with” them.
Rigging and Moving Units The exact method of handling and setting the unit depends on available equipment, size of unit, final location, and other variables. It is therefore up to the judgment of the riggers and movers to determine the specific method of handling each unit.
All units are equipped with built-in skids for rigging and
moving.
Figure 1. Suggested rigging
Location Due to vertical condenser design, it is recommended that the unit is oriented so that prevailing winds blow parallel to the unit Iength, thus minimizing effects on condensing pressure. If it is not practical to orient the unit in this manner, a wind
deflector should be constructed.
Units are designed for outdoor application and may be mounted on a roof or concrete slab (ground level installation). Roof-mounted units should be installed level on steel chan­nels or an l-beam frame to support the unit above the roof.
The roof must be strong enough to support the weight of the unit. See Physical Data for unit weight. Concrete slabs used for unit mounting should be installed level and be pro­perly supported to prevent settling. A one-piece concrete slab with footings extended below the frost line is recommended.
Figure 2. Clearance around unit
t
5 Ft. Min. Clearance
For Air Inlet
&u
COND. COIL
Min. r- =
4 Ft.
Clearance ~ g
For Service
“o”
rcp
COND. COIL
Ft. Min. Clearance
5
For Air
COMP. Clearance
Inlet
6 Ft. Min.
For Service
NOTES
1. Minimum clearance between units is 12 feet.
2. Units must not be Installed in a pit that is deeper than the height of the unit.
3. Minimum clearance on each side is 12 feet when installed in a pit.
IM 404 I Page 3
Refrigerant Piping
General Piping design, sizing and installation information presented in ASHRAE Handbooks should, where applicable, be followed in the design and installation of piping. McQuay type ALP condensing units are adaptable to either chilled water or air handling air conditioning applications. The only restriction on applications is that the evaporator be selected for a system using refrigerant R-22.
Refrigerant Piping Piping between the condensing unit and the cooling coil must be designed and installed to minimize pressure drop, pre­vent liquid refrigerant carryover to the compressor and to assure a continuous return of compressor oil from the system. Piping sketches and tables are not intended to provide infor­mation on all of the possible arrangements.
Piping recommendations include:
1.
The use of type K or L clean copper tubing. All joints should be thoroughly cleaned and brazed with high temperature solder.
2.
Piping sizes should be based on temperature/pressure limitations as recommended in the following paragraphs. Under no circumstances should pipe size be based upon the coil or condensing unit piping connection size.
3.
Suction line piping pressure drop should not exceed the pressure equivalent of 2° F (3 psi) per 100 feet of equivalent pipe length. After the suction line size has been deter­mined, the vertical suction risers should be checked to verify that oil will be carried up the riser and back to the compressor. The suction line should be pitched in the direction of refrigerant flow and adequately supported. Lines should be free draining and fully insulated between the evaporator and the compressor. Table 3 shows pip­ing information for units operating at suction temperatures between 40F and 45F and a condenser entering air temperature of 95° F. If operating conditions are expected to vary substantially from these operating levels, the pipe sizing should be rechecked.
4.
Vertical suction risers should be checked using Table 1 to determine the minimum tonnage required to carry oil up suction risers of various sizes.
The Iiquid line should be sized for a pressure drop not to
5. exceed the pressure equivalent of 2° F (6 psi) saturated temperature. The liquid line on all units must include a liquid solenoid valve wired into the circuit as shown on the applicable unit wiring diagrams.
The control circuit for all compressors has been de-
signed to include a pumpdown cycle. The use of a liquid line solenoid is required for proper unit operation. In ad-.
dition, a filter-drier should be located between the liquid line service valve
and the solenoid valve and a combina-
tion moisture indicator/sightglass should be located in the liquid line ahead of the expansion valve.
Suggested piping arrangements are shown on page 5. The
6
figures shown are for an air handling installation, but all components shown are recommended for chilled water vessel installations except that a refrigerant distributor is not usually required for shell-and-tube evaporators.
If dual suction risers are used:
7
Double risers are sized so that the combined cross­sectional internal area will allow full load unit operation without excessive pressure drop (see notes, Table 3). Riser “A” is sized to provide adequate suction gas velocity for proper oil return at minimum load conditions. This riser becomes effective only when the trap shown in riser “B” fills itself with oil. It should be emphasized that the trap shown in riser “B” should be designed to contain a minimum internal volume to keep the total system oil re­quirements at a minimum. Table 3 gives recommended line sizes for both single and double suction lines and for Iiquid lines, a.
‘ The combined cross-sectional areas of the two risers
must be capable of maintaining adequate refrigerant velocity for oil return at full unit tonnage.
b.
The extra riser should be of a smaller diameter than the main riser. The extra riser must include its own trap at the bottom and should enter the main suction header at twelve o’clock. The trap serving the extra riser must be as short as fit-
c.
tings permit. A “U” fitting or the combination of a 90’ standard “L” and a 90° street-L is recommended.
d.
The suction line Ieaving the coil should also include a trap if the expansion valve control bulb is to be on the horizontal section leaving the coil outlet. See the pip­ing sketches on page 5.
Table 1. Minimum
tonnage (R-22) to carry oil up
suction riser at 40” F saturated suction.
Line Size OD 1%
Min. Tons 1.50 2.50 3,80
NOTE: When compressor minimum tonnage is less than shown in the above
table for a given line size. double suction risers will
1
7.60 13.10 20.4
21A 2% 3~/’E 378
1 ye
3/3
4y~
29.7 41.3
be required
Table 2. Equivalent feet of straight tubing for copper fittings and valves
7/8
0,9
1%
1.7
2.1 3.0 3.4
1.7
2.6 3.3
29
1.0 12
ELBOWS
900 Standard 90° Long Radius 900 Street 45o Standard
45” Street 180° aEND TEES
Full Size
Reducing VALVES
Globe Valve, Open
Gate Valve, Open
Angle Valve, Open
FITTING TYPE
5/8
I
1.6 2.0 2.6 3.3
1.0 1.4
2.5 3.2 4.1 5.6 6.3
0.6 0.9 1.3 1.7 2.1
1.3 1.5
2.5 .3.2 4.1 5.6 6.3 8.2
1.0 1.4
1.6 2,0
16 22
0.7
7.0 9.0
Page 4 I IM 404
1ye 1ya 2Y8
4.0
2.3 2,6 3.3
2.3 2.6 3.3
4.0 5.0 6.0
38 43 55
1.5 1.8 15 18
5.0
8.2
2.6 3.2
4.5 5.2
2.3 2.8 3.2 4.0 24 29 35 41
25A 3~/4
6.0
4.1 5.0
10.0 12.0 15.0 17.0
10.0
4.1 5.0
69 84 100
7.5
4.0
6.4 7.3 8.5
12.0
7.5
378
I
9.0
5.9
4.7 5.2
15.0
5.9
9.0
49A
10.0
6.7
17.0
6.7
10.0
I
120
4.5 47
.
I
Table 3. Recommended line eizes
ALP UNIT 0.0. COPPER
SIZE
!
027C 032C
037C 041C
)
NOTES: Recommended line sizes shown in the above table are based on the unit
operating conditions between 40° F and 45” F saturated suction temperature and condenser entering air temperature of 95” F, per 100 ft. equivalent length of tubing. When design conditions vary, the table values should be rechecked.
Liquid and suction lines based on a recommended equivalent pressure
1. drop of 2F (3 psi for suction line, 6 psi for liquid line) per 100 ft. of equivalent length. When refrigerant required to charge a circuit exceeds the pumpdown
2. capacity of that circuit the use of a separate refrigerant storage receiver will be required. The pumpdown capacity is based on the condenser full at 90iF (see Physical Data).
3.
Wherever vertical rise occurs in the suction piping, the minimum tonnage for oil entrainment should be checked and where necessary double suc­tion risers should be utilized. See Table 1.
4.
Wherever vertical rise occurs in the suction piping on a system with hot gas bypass, double suction risers may not be needed as the velocity of suction gas is increased at minimum load conditions.
5.
Total equivalent feet for a given piping layout must include the equivalent length of straight pipe for fittings, valves and specialties added to the total run of straight pipe. Piping design, sizing and installation information presented in ASHRAE
6. Handbooks should, ‘where applicable, be followed in the design and in­stallation of piping.
DOUBLE
A–B
134 — lye 21A
1% — 1% 2% 1~~
SINGLE
lye — 21A 2% lye — 21A 2’% 1ye
SUCTIONLINESIZE
LIQUID LINE
SIZE
O.D. COPPER
11A
l%
90%
Table 4. Weight of refrigerant R-22 in copper lines
(pounds per 100 feet of type L tubing)
0.0.
Vol.per
Line 100 Ft. Llquld
in Cu. Ft. r@lOO”F
Size
0.054 3.64
%
V2 0.100 7.12 .374
0.162 7.12 .605 .156
%
0.336
‘h
11A 0.573 40.8 2.14
Weight of Refrigerant, Lbe.
Hot Gas @120”F (Superheated to 65” F)
Cond. 20” F 40” F
.202
24.0 1.26
.052 .077
.096
.323
.550
Suction Gas
1% 0.672 62.1 3.26 .639 1.250
1% 1.237 86.0
2% 2.147 153.0 6.04 2.06 3.060 2% 3.312 236.0
3%
3y, 4j~ 6.313 592.0 31.1 8.00 11.190
t
4.726
6.398I456.0 24.0
I
336.0
4.62
12.4
17.7
1.190 1.770
3.16
4.55 6.750
6.15
.143 .232
.460 .620
4.720
9.140
I
Figure 3. Typical refrigerant piping diagram
Evaporator or cooler below condensing unit
AIR FLOW
Evaporator or cooler
ab
I
LEGEND
a Filter-drier b Solenoid valve c 8ightglass/moisture indicator d Thermal expansion valve e Suction line, pitched toward compressor
f Liquid line
g Vibration absorber
A & B Double suction riser (see Note 2)
NOTES:
1. All piping and piping components are by others.
2. Trap for double suction riser should be as small in the horizontal direc­tion as fittings will allow.
3. Cooler suction connection should always be top connection.
lM 404 I Page 5
Figure 4. Recommended liquid line piping
CONDENSING UNIT
SEALED CORE FILTER DRIER
LIQUID LINE
\/
BALL VALVES TO ISOLATE FILTER DRIER FOR SERVICE
Hot Gas Bypass Components Hot gas bypass kits are available for each ALP unit size. Each kit includes a solenoid valve, a hot gas bypass valve and in­struction drawing. See page 20 for hot gas bypass operation.
Table 5. Hot gas bypass kits
ALP UNIT
SIZE
027C
032C 037C 041 c 886-580898A-04
y.
KIT NUMbER
886-580898A-03 1ye
886-580898A-04 1ye 888-580898A-03 1ye
LINE SIZE
O.D. (IN.)
1ye
Refrigerant Piping Connections Refrigerant piping connections will be made at the com­pressor end of the unit. Suction and liquid lines should be routed through the compressor enclosure on the side of the unit.
Holding Charge The Model ALP condensing unit is shipped with a holding charge of refrigerant. At the time the unit was received a visual inspection of the unit piping should have been made to be sure no breakage had occurred or that fittings might have been loosened. A pressure check should indicate a positive pressure in the unit. If no pressure is evident, the unit will have to be leak tested and the leak repaired. This should be noted and reported to your sales representative or freight car­rier if the loss is due to shipping damage.
Leak Testing In the case of loss of the refrigerant holding charge, the unit should be checked for leaks prior to charging the complete system. If the full charge was lost, leak testing can be done by charging the refrigerant into the unit to build the pressure
to approximately 10 psig and adding sufficient dry nitrogen to bring the pressure to a maximum of 125 psig. The unit should then be leak tested with a Halide or electronic leak detector. After making any necessary repair, the system should be evacuated as described in the following para­graphs.
Caution: Do not use oxygen to build up pressure. A serious
explosion could be the result.
Evacuation After it has been determined that the unit is tight and there are no refrigerant leaks, the system should be evacuated. The use of a vacuum pump with a pumping capacity of ap­proximately 3 cu. ft./rein. and the ability to reduce the vacuum in the unit to at least 1 millimeter (1000 microns) is recom­mended.
LIQUID LINE
SOLENOID
AIR HANDLER
u
r “n\”
SIGHTGLASS
EXPANSION VALVE
1. A mercurv manometer, electronic or other type of micron gauge should be connected to the unit at a-point remote from the vacuum pump. For readings below 1 millimeter, an electronic or other micron gauge should be used.
2. The triple evacuation method is recommended and is par­ticularly helpful if the vacuum pump is unable to obtain the desired 1 millimeter of vacuum. The system is first evacuated to approximately 29 inches of mercury. Enough refrigerant vapor is then added to the system to bring the pressure up to O pounds.
3. Then the system is once again evacuated to 29 inches of vacuum. This procedure is repeated three times. This method can be most effective by holding system pressure at Opounds for a minimum of 1 hour between evacuations.
The first pull down will remove about 90% of the non­condensables, the second about 90% of that remaining from the first pull down and after the third only 1/10 of 1% noncondensables will remain.
Table 6 shows the relationship between pressure, microns,
atmospheres, and the boiling point of water.
Charging the System
After all refrigerant piping is complete and the system has
1. been evacuated, it can be charged as described in the paragraphs following. Connect the refrigerant drum to the gauge port on the liquid line and purge the charging line between the refrigerant cylinder and the valve. Then open the valve to the mid-position.
2.
If the system is under a vacuum, stand the refrigerant drum with the connection up and open the drum and break the vacuum with refrigerant gas.
3.
With a system gas pressure higher than the equivalent of a freezing temperature, invert the charging cylinder and elevate the drum above the condenser. With the drum in this position, valves open and liquid refrigerant will flow into the condenser. Approximately 75% of the total require­ment estimated for the unit can be charged in this manner.
After 75% of the required charge has entered the con-
4. denser, reconnect the refrigerant drum and charging line
to the suction side of the system. Again purge the con­necting line, stand the drum with the connection up, and place the service valve in the open position.
Important: At this point charging procedure should be in-
terrupted and prestart checks made before attempting to com-
plete the refrigerant charge (see start-up procedures).
Itis recommended that the total operating charge
Note:
be stamped on the with nameplate for future reference.
Page 6 I IM 404
Refrigerant Charge Each ALP condensing unit is designed for use with R-22. See
physical data for approximate refrigeration charges for opera­tion of the unit. Additional refrigerant will be needed for the system piping and evaporator. Estimated total operating charge should be calculated before charging system.
Table 6. Pressure-vacuum equivalents
ABSOLUTE PRESSURE ABOVE ZERO
MICRONS PSIA
o
50 0.001 759.95 100 0.002 150 0.003 759,85
200 0.004 300 0.006 759,70 500 0.009 759.50
1,000 0.019
0
2,000 0.039
4,000 0.078
VACUUM BELOW ONE ATMOSPHERE APPROXIMATE
MERCURY MERCURY FRACTION OF
(mm)
760,00
759.90 29.920
759.80 29.910
759.00 29.880
758.00 29.840
756.00 29.760
6,000 0.117 754.00
6,000 10,000 0.193 15,000 0.290
20,000 0.387 30,000 0.580 50,000 0.967
100,000 1.930 200,000 _—..­500,000 760,000 14.697
0.156
1
3.870 560.00
9.670
I
752.00 29.600
750.00 29.530
745.00
740.00 29130 1/38
730.00
710.00
660.00 25.960
260.00 10.240 0 0 1 Atmosphere
Caution: Tots/ operating charge shou/dnot exceed the
condenser pumpdown capacity plus the capacity of the liquid
Iine. A liquid receiver should be used if the unit operating
charge exceeds the pumpdown capacity. Refer to the ASHRAE Handbook for the design and installation of piping and components.
BOILING POINT
(Inches)
29.921
29.920 1/15,200
29.920
29.910 1/2,500 29,900
ONE ATMOSPHERE PRESSURE (’F)
.
1/7,600 — 40 1/5,100 — 33 1/3,800 — 28
1/1,520 — 12
OF H,O AT EACH
— 50
— 21
1/760 1 11380 15 1/189 29
29.690
I
29.330
28.740
27.950
22.050 1/4 157
1/127 39
1/95
I
1/76 52 1/50
I
1/25 64 1/15 101
2115 125
2/3 192
I
I
I
,
I
46
63
7? I
---
212
i
Figure 5.
ALP-027C thru 041 C
CONTROL POWER ENTRY KNOCKOUTS FOR
POWER ENTRY LOCATION
((
V,” CONOUI1
\\ -7r5”30
+ 4.60
4
57.50
1-
--F
Table 7.
I I
. , . ..---,
AI-F MW.JEL
027C 10.0 13.0 21.5 032C 10.0 13,0 21.5 037C 10.0 13.0 21.5 5.7 041C 10.0 13.0
A B
6.10
?ONNFCTION I CW!ATIC)N.Q I fY3NNFCTU3N n II llNCH~s)
c
w .. ..-.- . . . . . -= --- . . . . .
I I k ---- -... I
Dimensional Data
is-
c D LIQUID
21.5 5.7
T
1
5.7
5.7
1.75TV? SPACING FOR
DIA. ISOLATOR
1.093
MOUNTING HOLES (4)
“-------- . . . . ---- . . . . . . . .
~8
%
~8
%
nu I wm
aYPAss
11A 1 ya
11A 21A 6.94 86.40
11A
11A 21A
AIR
DISCHARGE
J
ISOLATOR LOCATIONS
SUCTION
21A 6.94 68.40
R T
6.94
6.94 8S.40
\ Ll&jlD
CONN.
88.40
IM 404 I Page 7
Loading...
+ 15 hidden pages