The appliance must be connected to the 3A supply via a fused double-pole switch
having at least 3 mm (1/8 inch) contact separation in both poles, serving only the
boiler and the system controls.
The connection point to the mains supply should be readily accessible and
adjacent to the boiler, except for rooms containing a bath or a shower. Refer to
section 2.3 Position.
2.4.2 External Wiring & Controls
1. The boiler is designed so that all control wiring is external to the boiler.
2. A programmer may be used with zone valves to give independent control
of central heating and hot water.
2.5 BOILER SIZE SELECTION
The Celsius 25 will automatically adjust heat output and pump speed to match the system
requirements at any given time. Efficiency and combustion levels are maintained at
optimum levels throughout the possible output range. The Celsius 25 is therefore suitable
for all systems with a total heat load within the maximum range of the boiler.
2.6 GAS SUPPLY
A gas meter should be connected to the service pipe by the local gas region or their
contractor. An existing meter should be checked preferably by the gas region to ensure
that the meter is adequate to deal with the rate of gas supply required. Installation pipes
should be fitted in accordance with BS 6891.
Minimum/Maximum Gas Pressure:
Natural gas pressure before the gas valve must be maintained at between 18 mbar (7.2 in
WG) and 22 mbar (8.8 in) while the boiler is running.
LPG pressure must be maintained between 31.5 mbar (12.4 in w.g) and 37.6 mbar (14.8
in w.g) while the boiler is running.
Gas pressures above or below these levels will lead to problems associated with the gas
valve's internal pressure regulator.
Supply pipes to the boiler must not be sized less than the boiler inlet connection
(15 mm). Due consideration must be given to the supply pressure to other gas
appliances in the premises. Reduction in dynamic gas supply pressure will result in
intermittent ignition failures. Ensure gas supply pipe work is adequately sized for
the length of run from the meter to the boiler at a supply rate of 26.1 kW.
A gas cock is supplied loose with the boiler. This cock should be fitted in the gas line to
the boiler as close to the boiler as possible so that it is easily identified as the cock to
isolate the boiler.
2.7 WATER SYSTEMS
All piping must be installed in accordance with all applicable local and Water Supply
Bylaws for forced hot water heating systems.
Consideration must be given to pipe capabilities and pressure drop through the piping.
Water treatment must be carried out to BS 7593 : Treatment of Water in Hot Water
Central Heating Systems.
a The Celsius 25 is suitable for use on open, vented water systems with combined
feed and vent fitted to the boiler return.
b It is preferable for use on sealed water systems, provided the appropriate
components required (see Section 2.7.2 Sealed Systems) are included in the
system.
c Any system must be thoroughly flushed clean of grease, dirt and debris, prior to
connection with the boiler. A trap may be installed in the flow line to collect any
solder, or other debris, from the installation.
d All water systems must be constructed to comply with requirements of the Local
Water Authority.
e Always use a system complying with the requirements of BS 5449 and BS 6798.
WD209/1/2000 Chapter 2 - Boiler Connections The Keston Celsius 25 & 25P
Installation & Servicing Instructions Page : 7