Intel SE7501CW2 User Manual

Server Installation and Integration Guide
Using the Boxed Intel® Xeon Processor and Boxed Intel
®
Server Board SE7501CW2
Revision History
Date Revision Notes Product Code
9/25/03 1 First Draft
10/6/03 2 Second Draft
Disclaimers
The information contained in this document is provided for informational purposes only and represents the current view of Intel Corporation (“Intel”) and its contributors (“Contributors”) as of the date of publication. Intel and the Contributors make no commitment to update the information contained in this document, and Intel reserves the right to make changes at any time, without notice.
DISCLAIMER REPRESENTATIONS OF ANY KIND WITH RESPECT TO PRODUCTS REFERENCED HEREIN, WHETHER SUCH PRODUCTS ARE THOSE OF INTEL, THE CONTRIBUTORS, OR THIRD PARTIES. INTEL, AND ITS CONTRIBUTORS EXPRESSLY DISCLAIM ANY AND ALL WARRANTIES, IMPLIED OR EXPRESS, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES OF MERCHANTABILITY, FITNESS FOR ANY PARTICULAR PURPOSE, NON-INFRINGEMENT, AND ANY WARRANTY ARISING OUT OF THE INFORMATION CONTAINED HEREIN, INCLUDING WITHOUT LIMITATION, ANY PRODUCTS, SPECIFICATIONS, OR OTHER MATERIALS REFERENCED HEREIN. INTEL, AND ITS CONTRIBUTORS DO NOT WARRANT THAT THIS DOCUMENT IS FREE FROM ERRORS, OR THAT ANY PRODUCTS OR OTHER TECHNOLOGY DEVELOPED IN CONFORMANCE WITH THIS DOCUMENT WILL PERFORM IN THE INTENDED MANNER, OR WILL BE FREE FROM INFRINGEMENT OF THIRD PARTY PROPRIETARY RIGHTS, AND INTEL, AND ITS CONTRIBUTORS DISCLAIM ALL LIABILITY THEREFOR.
INTEL, AND ITS CONTRIBUTORS DO NOT WARRANT THAT ANY PRODUCT REFERENCED HEREIN OR ANY PRODUCT OR TECHNOLOGY DEVELOPED IN RELIANCE UPON THIS DOCUMENT, IN WHOLE OR IN PART, WILL BE SUFFICIENT, ACCURATE, RELIABLE, COMPLETE, FREE FROM DEFECTS OR SAFE FOR ITS INTENDED PURPOSE, AND HEREBY DISCLAIM ALL LIABILITIES THEREFOR. ANY PERSON MAKING, USING OR SELLING SUCH PRODUCT OR TECHNOLOGY DOES SO AT HIS OR HER OWN RISK.
Licenses may be required trademarks, copyrights or other intellectual proprietary rights covering subject matter contained or described in this document. No license, express, implied, by estoppels or otherwise, to any intellectual property rights of Intel or any other party is granted herein. It is your responsibility to seek licenses for such intellectual property rights from Intel and others where appropriate.
Limited License Grant internal distribution only. You may not distribute this document externally, in whole or in part, to any other person or entity.
LIMITED LIABILITY OTHER THIRD PARTY, FOR ANY LOST PROFITS, LOST DATA, LOSS OF USE OR COSTS OF PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES, OR FOR ANY DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES ARISING OUT OF YOUR USE OF THIS DOCUMENT OR RELIANCE UPON THE INFORMATION CONTAINED HEREIN, UNDER ANY CAUSE OF ACTION OR THEORY OF LIABILITY, AND IRRESPECTIVE OF WHETHER INTEL, OR ANY CONTRIBUTOR HAS ADVANCE NOTICE OF THE POSSIBILITY OF SUCH DAMAGES. THESE LIMITATIONS SHALL APPLY NOTWITHSTANDING THE FAILURE OF THE ESSENTIAL PURPOSE OF ANY LIMITED REMEDY.
Intel, Intel NetBurst, Intel Xeon, Intel i960, Intel Inside and the Intel logos are trademarks or registered trademarks of Intel Corporation or its subsidiaries in the United States and other countries.
Copyright © 2003, Intel Corporation. All rights reserved.
*
Other brands and names are the property of their respective owners.
. THIS DOCUMENT, IS PROVIDED “AS IS.” NEITHER INTEL, NOR THE CONTRIBUTORS MAKE ANY
. Intel, its contributors and others may have patents or pending patent applications,
. Intel hereby grants you a limited copyright license to copy this document for your use and
. IN NO EVENT SHALL INTEL, OR ITS CONTRIBUTORS HAVE ANY LIABILITY TO YOU OR TO ANY
2
Intel Server Board SE7501CW2 Installation and Integration Guide
Table of Contents
Introduction ......................................................................................5
Document Overview ................................................................................5
Target Audience ...................................................................................... 5
Thank you ............................................................................................... 5
Troubleshooting Guide ............................................................................ 6
Minimum Hardware Requirements ..........................................................6
Hardware Integration........................................................................7
Prepare for Assembly ..............................................................................7
Important Safety Information ................................................................. 8
Safety Instructions and Information...................................................... 8
Electrostatic Discharge (ESD) .............................................................. 8
Chassis Preparation and Server Board Installation ................................. 9
About the I/O Shield .......................................................................... 9
Attaching the Gasket to the I/O Shield .................................................. 9
Attaching the Label to the I/O Shield .................................................... 9
Installing the I/O Shield...................................................................... 9
Installing Chassis Standoffs ............................................................... 10
Installing the Rubber Bumper ............................................................ 10
Installing the Server Board................................................................ 10
Installing Memory ................................................................................. 11
Installing the Boxed Intel Xeon Processor......................................... 12
Choosing the Processor Socket .......................................................... 12
Opening the Socket Lever ................................................................. 12
Attaching the Processor .................................................................... 12
Installing the Retention Mechanism .................................................... 13
Applying Thermal Grease .................................................................. 13
Attaching the Heat Sink and Retention Clips ........................................ 13
Installing the Processor Wind Tunnel.................................................... 14
Attaching the Heat Sink Fan .............................................................. 14
Attaching the Fan/Intake Assembly .................................................... 14
Attaching the Wind Tunnel ................................................................ 15
Making Required Connections to the Server Board ................................ 16
3
Making Optional Connections to the Server Board................................. 17
Installing the Serial B Cable ..................................................................18
Cable Routing – Intel Server Chassis SC5200 ........................................ 19
IDE or SCSI Cables .......................................................................... 19
Floppy and Front Panel Cables ........................................................... 19
Installing the Access Cover ................................................................... 19
Installing the Chassis Feet (Pedestal Mode).......................................... 20
Installing into a Rack (Rack Mode)........................................................ 20
Finishing Up ..........................................................................................21
Software Installation.......................................................................22
Updating the BIOS................................................................................. 22
Installing the Operating System............................................................ 22
LANDesk* Client Manager ..................................................................... 23
Installing LANDesk Client Manager ....................................................... 23
LANDesk System Requirements ......................................................... 23
Administrator computers ..................................................................................23
Client computers ..................................................................................................23
Intel Server Maintenance and Reference Training Tool CD (Intel SMaRT
Tool)...................................................................................................... 24
Installing the Intel SMaRT Tool ............................................................. 24
4
Intel Server Board SE7501CW2 Installation and Integration Guide

Introduction

Document Overview

This guide outlines the procedures for integrating an
®
Intel
Server Platform using an Intel Server Board
SE7501CW2 and Intel Xeon processors.
This guide consists of the most essential information first-time server builders need to successfully assemble an Intel server solution. Your particular operating system’s installation guide will cover the installation of the server’s operating system.

Target Audience

Intel channel program members who are expanding their expertise to include server
platforms and current channel program members looking for a refresher on servers
System integrators deploying servers based on the boxed Intel Server Board
SE7501CW2
Our intent is to better enable system integrators, particularly first-time server builders, to meet the competitive challenges they face in the server market and to keep program members up-to-date on emerging server technologies. By following the steps outlined in this document, you will be able to integrate an Intel Server Board SE7501CW2 with an Intel Server Chassis SC5200 in a timely and effective manner.
The Intel Server Chassis SC5200 is used as an example and is recommended for ease of integration and compatibility; other reference chassis may be different. Expanded installation instructions and complete product information are available in the Intel Board SE7501CW2 Product Guide on the Resource CD. Unless otherwise noted, references to the Intel Server Chassis SC5200 include both the base version and the base redundant power version.
®
Server

Thank you

Thank you for buying Intel Server Products.
5

Troubleshooting Guide

In the unlikely event you do encounter issues, the troubleshooting guide will help you troubleshoot and identify possible areas of concern regarding the Intel Server Board SE7501CW2. It will also assist you in collecting the data needed to help you work through any concerns or issues that may arise The troubleshooting guide includes suggestions that may help you and a list of information that we will need to assist you should you need to call. The troubleshooting guide is available at:
http://support.intel.com/support/motherboards/server/SE7501CW2/ts_guide.htm
If you are unable to resolve a problem using this guide, please follow these steps:
1. Visit http://support.intel.com/support/motherboards/server/SE7501CW2/index.htm This Web site contains the latest information on known issues and their respective solutions. If you are still unable to resolve the issue, go to the next step.
2. Send e-mail, including as much information on the issue as possible, to Intel customer support, using the form available at this URL:
http://supportmail.intel.com/scripts-emf/welcome.asp?id=37
3. Channel customers can contact Intel customer support toll free at 1-866-655-6565. Non-channel customers should use one of the numbers listed at
http://www.intel.com/support/9089.htm
.

Minimum Hardware Requirements

Your system must meet the following minimum requirements to avoid integration difficulties and possible board damage:
Processor: Minimum of one Intel Xeon processor 1.8 GHz with 512K cache support in a 603-pin (400-MHz FSB) or 604-pin (533-MHz FSB) INT flip-chip micro pin-grid array (INT-mPGA). For a list of tested processors, visit
http://support.intel.com/support/motherboards/server/SE7501CW2/proc_supp.htm
Memory: Minimum of one 128-MB ECC DDR 266-compliant registered SDRAM 168-pin gold DIMM. For a list of tested memory, visit
http://support.intel.com/support/motherboards/server/SE7501CW2/tested_mem.htm
Power: Minimum of 450 W with 1.2A standby current which meets the SSI EPS 12V specification. Intel provides a power budgeting tool to help you determine the power needs of your server at
http://support.intel.com/support/motherboards/server/pwr_budget.htm
Additional resources and support for your server board, including tested chassis, qualified chassis components, specifications, and software updates, can be found at
http://support.intel.com/support/motherboards/server/SE7501CW2/index.htm
6
Intel Server Board SE7501CW2 Installation and Integration Guide

Hardware Integration

The following installation procedures enable you to prepare a chassis for integration, add the needed components to your server board, and install the server board. The procedures are condensed from the more comprehensive and detailed Product Guides for the Intel Server Board SE7501CW2 and Intel Server Chassis SC5200. To access the most current and complete Product Guides and for more information, visit Intel Support at:
http://support.intel.com/support/motherboards/server/SE7501C W2/index.htm

Prepare for Assembly

1. Gather tools needed:
Needle nose pliers
Flat blade screwdriver
Phillips head screwdriver
Antistatic wrist strap
2. Prepare a clean, static-controlled, level workstation.
3. Collect and organize all necessary hardware including the server board, memory, processor(s), and peripherals (hard drives, floppy disk drive, CD/DVD).
4. Verify that the components chosen for installation are listed as validated for use with the Intel Server Board SE7501CW2. This information is available from the Intel Support Web site: http://support.intel.com/support/motherboards/server/SE7501CW2/compat.htm
.
7

Important Safety Information

Safety Instructions and Information

To avoid personal injury or property damage, the following safety instructions apply whenever working inside the chassis:
1. Turn off all peripheral devices connected to this product.
2. Turn off the system by pressing the power button on the front of the product.
3. Disconnect the AC power by unplugging all AC power cords from the system or wall outlet.
4. Disconnect all cables and telecommunication lines that are connected to the system.
5. Retain all screws or other fasteners when removing access cover(s). When finished, refasten the access cover with original screws or fasteners.
6. Do not access the inside of the power supply. There are no serviceable parts in the power supply. If the power supply is malfunctioning, return it to the manufacturer for servicing.

Electrostatic Discharge (ESD)

CAUTION
Perform the procedures in this product guide only at an electrostatic discharge (ESD) workstation, because the server components are extremely sensitive to ESD. If no such workstation is available, you can reduce the risk of electrostatic discharge damage by doing the following:
Wear an antistatic wrist strap, and attach it to a metal part of the server.
Touch the metal on the server chassis before touching the server components.
Keep part of your body in contact with the metal server chassis to dissipate the static
charge while handling the components.
Avoid moving around unnecessarily.
Hold the server components (especially boards) only by the edges.
Place the server components on a grounded, static-free surface. Use a conductive foam
pad if available. Do not use the product packaging or wrapper as an antistatic surface.
Do not slide the components over any surface.