1 Table of contents

Table of contents

1 General safety precautions 2

1.1 About the documentation .......................................................... 2
1.1.1 Meaning of warnings and symbols.............................. 3
1.2 For the installer.......................................................................... 3
1.2.1 General ....................................................................... 3
1.2.2 Installation site ............................................................ 3
1.2.3 Refrigerant .................................................................. 4
1.2.4 Brine............................................................................ 4
1.2.5 Water .......................................................................... 4
1.2.6 Electrical ..................................................................... 5
2 About the documentation 5
2.1 About this document.................................................................. 5
2.2 Installer reference guide at a glance ......................................... 6
3 About the box 6
3.1 Overview: About the box ........................................................... 6
3.2 Outdoor unit............................................................................... 6
3.2.1 To unpack the outdoor unit ......................................... 6
3.2.2 To handle the outdoor unit.......................................... 6
3.2.3 To remove the accessories from the outdoor unit....... 6
4 About the units and options 7
4.1 Overview: About the units and options...................................... 7
4.2 Identification .............................................................................. 7
4.2.1 Identification label: Outdoor unit ................................. 7
4.3 Combining units and options ..................................................... 7
4.3.1 Possible options for the outdoor unit........................... 7
5 Preparation 7
5.1 Overview: Preparation............................................................... 7
5.2 Preparing the installation site .................................................... 7
5.2.1 Installation site requirements of the outdoor unit ........ 7
5.2.2 Additional installation site requirements of the
outdoor unit in cold climates ....................................... 8
5.3 Preparing refrigerant piping....................................................... 8
5.3.1 Refrigerant piping requirements.................................. 8
5.3.2 Refrigerant piping insulation ....................................... 9
5.4 Preparing electrical wiring ......................................................... 9
5.4.1 About preparing electrical wiring................................. 9
6 Installation 9
6.1 Overview: Installation ................................................................ 9
6.2 Opening the units ...................................................................... 9
6.2.1 About opening the units .............................................. 9
6.2.2 To open the outdoor unit............................................. 9
6.3 Mounting the outdoor unit.......................................................... 10
6.3.1 About mounting the outdoor unit................................. 10
6.3.2 Precautions when mounting the outdoor unit.............. 10
6.3.3 To provide the installation structure............................ 10
6.3.4 To install the outdoor unit............................................ 10
6.3.5 To provide drainage.................................................... 10
6.3.6 To prevent the outdoor unit from falling over .............. 11
6.4 Connecting the refrigerant piping .............................................. 11
6.4.1 About connecting the refrigerant piping ...................... 11
6.4.2 Precautions when connecting the refrigerant piping... 11
6.4.3 Guidelines when connecting the refrigerant piping..... 12
6.4.4 Pipe bending guidelines.............................................. 12
6.4.5 To flare the pipe end................................................... 12
6.4.6 To braze the pipe end................................................. 12
6.4.7 Using the stop valve and service port......................... 13
6.4.8 To connect the refrigerant piping to the outdoor unit .. 13
6.4.9 To determine if oil traps are required.......................... 14
6.5 Checking the refrigerant piping ................................................. 14
6.5.1 About checking the refrigerant piping ......................... 14
6.5.2 Precautions when checking the refrigerant piping ...... 15
6.5.3 Checking refrigerant piping: Setup............................... 15
6.5.4 To check for leaks........................................................ 15
6.5.5 To perform vacuum drying ........................................... 15
6.6 Charging refrigerant ................................................................... 15
6.6.1 About charging refrigerant ........................................... 15
6.6.2 Precautions when charging refrigerant ........................ 16
6.6.3 To determine the additional refrigerant amount........... 16
6.6.4 To determine the complete recharge amount.............. 17
6.6.5 Charging refrigerant: Setup.......................................... 17
6.6.6 To charge additional refrigerant ................................... 17
6.6.7 To fix the fluorinated greenhouse gases label ............. 17
6.7 Connecting the electrical wiring.................................................. 17
6.7.1 About connecting the electrical wiring.......................... 17
6.7.2 About electrical compliance ......................................... 17
6.7.3 Precautions when connecting the electrical wiring ...... 18
6.7.4 Guidelines when connecting the electrical wiring ........ 18
6.7.5 Specifications of standard wiring components............. 18
6.7.6 To connect the electrical wiring on the outdoor unit..... 18
6.8 Finishing the outdoor unit installation ......................................... 20
6.8.1 To finish the outdoor unit installation ........................... 20
6.8.2 To close the outdoor unit ............................................. 20
6.8.3 To check the insulation resistance of the compressor. 20
7 Commissioning 20
7.1 Overview: Commissioning.......................................................... 20
7.2 Precautions when commissioning .............................................. 20
7.3 Checklist before commissioning................................................. 20
7.4 To perform a test run.................................................................. 21
7.5 Error codes when performing a test run ..................................... 21
8 Hand-over to the user 21
9 Maintenance and service 21
9.1 Overview: Maintenance and service .......................................... 22
9.2 Maintenance safety precautions................................................. 22
9.2.1 To prevent electrical hazards....................................... 22
9.3 Checklist for yearly maintenance of the outdoor unit ................. 22
10 Troubleshooting 22
10.1 Overview: Troubleshooting......................................................... 22
10.2 Precautions when troubleshooting ............................................. 22
11 Disposal 22
11.1 Overview: Disposal..................................................................... 22
11.2 About pump down ...................................................................... 22
11.3 To pump down............................................................................ 23
12 Technical data 24
12.1 Overview: Technical data ........................................................... 24
12.2 Service space: Outdoor unit ....................................................... 24
12.3 Piping diagram: Outdoor unit...................................................... 25
12.4 Wiring diagram: Outdoor unit ..................................................... 26
12.5 Information requirements for Eco Design ................................... 27
13 Glossary 27
1 General safety precautions

1.1 About the documentation

▪ The original documentation is written in English. All other
languages are translations.
▪ The precautions described in this document cover very important
topics, follow them carefully.
▪ The installation of the system, and all activities described in the
installation manual and in the installer reference guide MUST be performed by an authorised installer.
Installer reference guide
AZQS100~140B8V1B + AZQS100~140B7Y1B
Split system air conditioners
4P385529-1C – 2019.04
1 General safety precautions

1.1.1 Meaning of warnings and symbols

DANGER
Indicates a situation that results in death or serious injury.
DANGER: RISK OF ELECTROCUTION
Indicates a situation that could result in electrocution.
DANGER: RISK OF BURNING
Indicates a situation that could result in burning because of extreme hot or cold temperatures.
DANGER: RISK OF EXPLOSION
Indicates a situation that could result in explosion.
WARNING
Indicates a situation that could result in death or serious injury.
WARNING: FLAMMABLE MATERIAL
CAUTION
Indicates a situation that could result in minor or moderate injury.
NOTICE
Indicates a situation that could result in equipment or property damage.
INFORMATION
Indicates useful tips or additional information.
Symbol Explanation
Before installation, read the installation and operation manual, and the wiring instruction sheet.
Before performing maintenance and service tasks, read the service manual.
For more information, see the installer and user reference guide.

1.2 For the installer

1.2.1 General

If you are NOT sure how to install or operate the unit, contact your dealer.
NOTICE
Improper installation or attachment of equipment or accessories could result in electric shock, short-circuit, leaks, fire or other damage to the equipment. Only use accessories, optional equipment and spare parts made or approved by Daikin.
WARNING
Make sure installation, testing and applied materials comply with applicable legislation (on top of the instructions described in the Daikin documentation).
CAUTION
Wear adequate personal protective equipment (protective gloves, safety glasses,…) when installing, maintaining or servicing the system.
WARNING
Tear apart and throw away plastic packaging bags so that nobody, especially children, can play with them. Possible risk: suffocation.
DANGER: RISK OF BURNING
▪ Do NOT touch the refrigerant piping, water piping or
internal parts during and immediately after operation. It could be too hot or too cold. Give it time to return to normal temperature. If you must touch it, wear protective gloves.
▪ Do NOT touch any accidental leaking refrigerant.
WARNING
Provide adequate measures to prevent that the unit can be used as a shelter by small animals. Small animals that make contact with electrical parts can cause malfunctions, smoke or fire.
CAUTION
Do NOT touch the air inlet or aluminium fins of the unit.
NOTICE
▪ Do NOT place any objects or equipment on top of the
unit.
▪ Do NOT sit, climb or stand on the unit.
NOTICE
Works executed on the outdoor unit are best done under dry weather conditions to avoid water ingress.
In accordance with the applicable legislation, it might be necessary to provide a logbook with the product containing at least: information on maintenance, repair work, results of tests, stand-by periods,…
Also, at least, following information MUST be provided at an accessible place at the product:
▪ Instructions for shutting down the system in case of an emergency
▪ Name and address of fire department, police and hospital
▪ Name, address and day and night telephone numbers for
obtaining service
In Europe, EN378 provides the necessary guidance for this logbook.

1.2.2 Installation site

▪ Provide sufficient space around the unit for servicing and air
circulation.
▪ Make sure the installation site withstands the weight and vibration
of the unit.
▪ Make sure the area is well ventilated. Do NOT block any
ventilation openings.
▪ Make sure the unit is level.
Do NOT install the unit in the following places:
▪ In potentially explosive atmospheres.
▪ In places where there is machinery that emits electromagnetic
waves. Electromagnetic waves may disturb the control system, and cause malfunction of the equipment.
▪ In places where there is a risk of fire due to the leakage of
flammable gases (example: thinner or gasoline), carbon fibre, ignitable dust.
▪ In places where corrosive gas (example: sulphurous acid gas) is
produced. Corrosion of copper pipes or soldered parts may cause the refrigerant to leak.
AZQS100~140B8V1B + AZQS100~140B7Y1B Split system air conditioners 4P385529-1C – 2019.04
Installer reference guide
1 General safety precautions

1.2.3 Refrigerant

If applicable. See the installation manual or installer reference guide of your application for more information.
NOTICE
Make sure refrigerant piping installation complies with applicable legislation. In Europe, EN378 is the applicable standard.
NOTICE
Make sure the field piping and connections are NOT subjected to stress.
WARNING
During tests, NEVER pressurize the product with a pressure higher than the maximum allowable pressure (as indicated on the nameplate of the unit).
WARNING
Take sufficient precautions in case of refrigerant leakage. If refrigerant gas leaks, ventilate the area immediately. Possible risks:
▪ Excessive refrigerant concentrations in a closed room
can lead to oxygen deficiency.
▪ Toxic gas may be produced if refrigerant gas comes
into contact with fire.
DANGER: RISK OF EXPLOSION
Pump down – Refrigerant leakage. If you want to pump
down the system, and there is a leak in the refrigerant circuit:
▪ Do NOT use the unit's automatic pump down function,
with which you can collect all refrigerant from the system into the outdoor unit. Possible consequence: Self-combustion and explosion of the compressor because of air going into the operating compressor.
▪ Use a separate recovery system so that the unit's
compressor does NOT have to operate.
WARNING
ALWAYS recover the refrigerant. Do NOT release them directly into the environment. Use a vacuum pump to evacuate the installation.
NOTICE
After all the piping has been connected, make sure there is no gas leak. Use nitrogen to perform a gas leak detection.
NOTICE
▪ To avoid compressor breakdown, do NOT charge more
than the specified amount of refrigerant.
▪ When the refrigerant system is to be opened,
refrigerant MUST be treated according to the applicable legislation.
WARNING
Make sure there is no oxygen in the system. Refrigerant may only be charged after performing the leak test and the vacuum drying.
▪ In case recharge is required, see the nameplate of the unit. It
states the type of refrigerant and necessary amount.
▪ The unit is factory charged with refrigerant and depending on pipe
sizes and pipe lengths some systems require additional charging of refrigerant.
▪ Only use tools exclusively for the refrigerant type used in the
system, this to ensure pressure resistance and prevent foreign materials from entering into the system.
▪ Charge the liquid refrigerant as follows:
If Then
A siphon tube is present
(i.e., the cylinder is marked with "Liquid filling siphon attached")
A siphon tube is NOT present Charge with the cylinder upside
▪ Open refrigerant cylinders slowly.
▪ Charge the refrigerant in liquid form. Adding it in gas form may
prevent normal operation.
CAUTION
When the refrigerant charging procedure is done or when pausing, close the valve of the refrigerant tank immediately. If the valve is NOT closed immediately, remaining pressure might charge additional refrigerant. Possible consequence: Incorrect refrigerant amount.
Charge with the cylinder upright.
down.

1.2.4 Brine

If applicable. See the installation manual or installer reference guide of your application for more information.
WARNING
The selection of the brine MUST be in accordance with the applicable legislation.
WARNING
Take sufficient precautions in case of brine leakage. If brine leaks, ventilate the area immediately and contact your local dealer.
WARNING
The ambient temperature inside the unit can get much higher than that of the room, e.g. 70°C. In case of a brine leak, hot parts inside the unit can create a hazardous situation.
WARNING
The use and installation of the application MUST comply with the safety and environmental precautions specified in the applicable legislation.

1.2.5 Water

If applicable. See the installation manual or installer reference guide of your application for more information.
NOTICE
Make sure water quality complies with EU directive 98/83EC.
Installer reference guide
AZQS100~140B8V1B + AZQS100~140B7Y1B
Split system air conditioners
4P385529-1C – 2019.04

2 About the documentation

1.2.6 Electrical

DANGER: RISK OF ELECTROCUTION
▪ Turn OFF all power supply before removing the
switch box cover, connecting electrical wiring or touching electrical parts.
▪ Disconnect the power supply for more than 1minute,
and measure the voltage at the terminals of main circuit capacitors or electrical components before servicing. The voltage MUST be less than 50 V DC before you can touch electrical components. For the location of the terminals, see the wiring diagram.
▪ Do NOT touch electrical components with wet hands.
▪ Do NOT leave the unit unattended when the service
cover is removed.
WARNING
If NOT factory installed, a main switch or other means for disconnection, having a contact separation in all poles providing full disconnection under overvoltage category III condition, MUST be installed in the fixed wiring.
WARNING
▪ ONLY use copper wires.
▪ Make sure the field wiring complies with the applicable
legislation.
▪ All field wiring MUST be performed in accordance with
the wiring diagram supplied with the product.
▪ NEVER squeeze bundled cables and make sure they
do NOT come in contact with the piping and sharp edges. Make sure no external pressure is applied to the terminal connections.
▪ Make sure to install earth wiring. Do NOT earth the unit
to a utility pipe, surge absorber, or telephone earth. Incomplete earth may cause electrical shock.
▪ Make sure to use a dedicated power circuit. NEVER
use a power supply shared by another appliance.
▪ Make sure to install the required fuses or circuit
breakers.
▪ Make sure to install an earth leakage protector. Failure
to do so may cause electric shock or fire.
▪ When installing the earth leakage protector, make sure
it is compatible with the inverter (resistant to high frequency electric noise) to avoid unnecessary opening of the earth leakage protector.
CAUTION
When connecting the power supply, the earth connection must be made before the current-carrying connections are established. When disconnecting the power supply, the current-carrying connections must be separated before the earth connection is. The length of the conductors between the power supply stress relief and the terminal block itself must be as such that the current-carrying wires are tautened before the earth wire is in case the power supply is pulled loose from the stress relief.
NOTICE
Precautions when laying power wiring:
▪ Do NOT connect wiring of different thicknesses to the
power terminal block (slack in the power wiring may cause abnormal heat).
▪ When connecting wiring which is the same thickness,
do as shown in the figure above.
▪ For wiring, use the designated power wire and connect
firmly, then secure to prevent outside pressure being exerted on the terminal board.
▪ Use an appropriate screwdriver for tightening the
terminal screws. A screwdriver with a small head will damage the head and make proper tightening impossible.
▪ Over-tightening the terminal screws may break them.
Install power cables at least 1 metre away from televisions or radios to prevent interference. Depending on the radio waves, a distance of 1metre may not be sufficient.
WARNING
▪ After finishing the electrical work, confirm that each
electrical component and terminal inside the electrical components box is connected securely.
▪ Make sure all covers are closed before starting up the
unit.
NOTICE
Only applicable if the power supply is three‑phase, and the compressor has an ON/OFF starting method.
If there exists the possibility of reversed phase after a momentary black out and the power goes on and off while the product is operating, attach a reversed phase protection circuit locally. Running the product in reversed phase can break the compressor and other parts.
2 About the documentation

2.1 About this document

Target audience
Authorised installers
INFORMATION
This appliance is intended to be used by expert or trained users in shops, in light industry and on farms, or for commercial use by lay persons.
Documentation set
This document is part of a documentation set. The complete set consists of:
General safety precautions:
▪ Safety instructions that you MUST read before installing
▪ Format: Paper (in the box of the outdoor unit)
Outdoor unit installation manual:
▪ Installation instructions
▪ Format: Paper (in the box of the outdoor unit)
AZQS100~140B8V1B + AZQS100~140B7Y1B Split system air conditioners 4P385529-1C – 2019.04
Installer reference guide

3 About the box

21
ENERG
IJAY
IAIE
ENERG
IJAY
IAIE
2
3
1
a
b c
d
e
Installer reference guide:
▪ Preparation of the installation, reference data,…
▪ Format: Digital files on http://www.daikineurope.com/support-
and-manuals/product-information/
Latest revisions of the supplied documentation may be available on the regional Daikin website or via your dealer.
The original documentation is written in English. All other languages are translations.
Technical engineering data
▪ A subset of the latest technical data is available on the regional
Daikin website (publicly accessible).
▪ The full set of latest technical data is available on the Daikin
Business Portal (authentication required).

2.2 Installer reference guide at a glance

Chapter Description
General safety precautions
About the documentation What documentation exists for the
About the box How to unpack the units and remove
About the units and options
Preparation What to do and know before going
Installation What to do and know to install the
Commissioning What to do and know to commission the
Hand‑over to the user What to give and explain to the user
Maintenance and service How to maintain and service the units
Troubleshooting What to do in case of problems
Disposal How to dispose of the system
Technical data Specifications of the system
Glossary Definition of terms
Safety instructions that you must read before installing
installer
their accessories
▪ How to identify the units
▪ Possible combinations of units and
options
on‑site
system
system after it is installed

3.2 Outdoor unit

3.2.1 To unpack the outdoor unit

3.2.2 To handle the outdoor unit

CAUTION
To avoid injury, do NOT touch the air inlet or aluminium fins of the unit.
Carry the unit slowly as shown:
3 About the box

3.1 Overview: About the box

This chapter describes what you have to do after the box with the outdoor unit is delivered on-site.
It contains information about:
▪ Unpacking and handling the unit
▪ Removing the accessories from the unit
Keep the following in mind:
▪ At delivery, the unit MUST be checked for damage. Any damage
MUST be reported immediately to the claims agent of the carrier.
▪ Bring the packed unit as close as possible to its final installation
position to prevent damage during transport.
▪ Prepare the path along which you want to bring the unit inside in
advance.
Installer reference guide

3.2.3 To remove the accessories from the outdoor unit

AZQS100~140B8V1B + AZQS100~140B7Y1B
Split system air conditioners
4P385529-1C – 2019.04

4 About the units and options

a General safety precautions b Outdoor unit installation manual c Cable tie d Fluorinated greenhouse gases label e Energy label
4 About the units and options

4.1 Overview: About the units and options

This chapter contains information about:
▪ Identifying the outdoor unit
▪ Combining the outdoor unit with options

4.2 Identification

NOTICE
When installing or servicing several units at the same time, make sure NOT to switch the service panels between different models.

4.2.1 Identification label: Outdoor unit

Location

4.3 Combining units and options

4.3.1 Possible options for the outdoor unit

Demand adaptor kit
Can be used for the following:
▪ Low noise: To lower the operation sound of the outdoor unit.
▪ I-demand function: To limit the power consumption from the
system (example: budget control, limit power consumption during peak moments…).
Model Demand adaptor kit
AZQS_Y1 KRP58M51
AZQS_V1 SB.KRP58M51
For installation instructions, see the installation manual of the demand adaptor kit.
▪ Preparing the refrigerant piping
▪ Preparing the electrical wiring

5.2 Preparing the installation site

Do NOT install the unit in places often used as work place. In case of construction works (e.g. grinding works) where a lot of dust is created, the unit MUST be covered.
Choose an installation location with sufficient space for carrying the unit in and out of the site.

5.2.1 Installation site requirements of the outdoor unit

INFORMATION
Also read the following requirements:
▪ General installation site requirements. See the
"General safety precautions" chapter.
▪ Service space requirements. See the "Technical data"
chapter.
▪ Refrigerant piping requirements (length, height
difference). See further in this "Preparation" chapter.
▪ Select a place where rain can be avoided as much as possible.
▪ Take care that in the event of a water leak, water cannot cause
any damage to the installation space and surroundings.
▪ Choose a location where the hot/cold air discharged from the unit
or the operation noise, will NOT disturb anyone.
▪ Heat exchanger fins are sharp and injury is possible. Choose an
installation location where there is no risk for injury (especially in areas where children play).
Do NOT install the unit in the following places:
▪ Sound sensitive areas (e.g. near a bedroom), so that the
operation noise will cause no trouble. Note: If the sound is measured under actual installation conditions, the measured value might be higher than the sound pressure level mentioned in Sound spectrum in the data book due to environmental noise and sound reflections.
INFORMATION
The sound pressure level is less than 70dBA.
▪ In places where a mineral oil mist, spray or vapour may be
present in the atmosphere. Plastic parts may deteriorate and fall off or cause water leakage.
It is NOT recommended to install the unit in the following places because it may shorten the life of the unit:
▪ Where the voltage fluctuates a lot
▪ In vehicles or vessels
▪ Where acidic or alkaline vapour is present
Seaside installation. Make sure the outdoor unit is NOT directly exposed to sea winds. This is to prevent corrosion caused by high levels of salt in the air, which might shorten the life of the unit.

5 Preparation

5.1 Overview: Preparation

This chapter describes what you have to do and know before going on-site.
It contains information about:
▪ Preparing the installation site
AZQS100~140B8V1B + AZQS100~140B7Y1B Split system air conditioners 4P385529-1C – 2019.04
Installer reference guide
5 Preparation
b
c
a
a
b
c
d
c
d
a
b
c
b
a
b
c
c
d
t
Ø
Install the outdoor unit away from direct sea winds.
Example: Behind the building.
If the outdoor unit is exposed to direct sea winds, install a windbreaker.
▪ Height of windbreaker≥1.5×height of outdoor unit
▪ Mind the service space requirements when installing the
windbreaker.
b Prevailing wind direction c Air outlet
The outdoor unit is designed for outdoor installation only, and for ambient temperatures ranging:
Model Cooling Heating
AZQS –5~46°C –15~15.5°C

5.2.2 Additional installation site requirements of the outdoor unit in cold climates

Protect the outdoor unit against direct snowfall and take care that the outdoor unit is NEVER snowed up.
a Sea wind b Building c Outdoor unit d Windbreaker
Strong winds (≥18 km/h) blowing against the outdoor unit’s air outlet causes short circuit (suction of discharge air). This may result in:
▪ deterioration of the operational capacity;
▪ frequent frost acceleration in heating operation;
▪ disruption of operation due to decrease of low pressure or
increase of high pressure;
▪ a broken fan (if a strong wind blows continuously on the fan, it
may start rotating very fast, until it breaks).
It is recommended to install a baffle plate when the air outlet is exposed to wind.
It is recommended to install the outdoor unit with the air inlet facing the wall and NOT directly exposed to the wind.

5.3 Preparing refrigerant piping

5.3.1 Refrigerant piping requirements

▪ Foreign materials inside pipes (including oils for fabrication) must
be ≤30mg/10m.
a Snow cover or shed b Pedestal (minimum height=150mm) c Prevailing wind direction d Air outlet
INFORMATION
Also read the precautions and requirements in the "General safety precautions" chapter.
NOTICE
The piping and other pressure-containing parts shall be suitable for refrigerant. Use phosphoric acid deoxidised seamless copper for refrigerant.
Refrigerant piping material
Piping material: Phosphoric acid deoxidised seamless copper.
Flare connections: Only use annealed material.
Piping temper grade and thickness:
Outer diameter
(Ø)
6.4mm (1/4")
9.5mm (3/8")
12.7mm (1/2")
15.9mm (5/8") Annealed (O) ≥1.0mm
19.1mm (3/4") Half hard (1/2H)
Installer reference guide
a Baffle plate
Temper grade Thickness (t)
Annealed (O) ≥0.8mm
AZQS100~140B8V1B + AZQS100~140B7Y1B
Split system air conditioners
(a)
4P385529-1C – 2019.04

6 Installation

H1
L1
(a) Depending on the applicable legislation and the unit's
maximum working pressure (see "PS High" on the unit name plate), larger piping thickness might be required.
Refrigerant piping diameter
Use the same diameters as the connections on the outdoor units:
L1 liquid piping Ø9.5mm
L1 gas piping Ø15.9mm
Refrigerant piping length and height difference
The piping length and height difference must comply with the following requirements:
Total one‑way piping length:
5m≤L1≤50m (70m)
Height difference between the highest indoor unit and the outdoor unit:
H1≤30m
(a) Parenthesised figure represents the equivalent length. (b) For details about the combination of your outdoor and
indoor unit, see the engineering databook.
(a)(b)

5.3.2 Refrigerant piping insulation

▪ Use polyethylene foam as insulation material:
▪ with a heat transfer rate between 0.041 and 0.052W/mK (0.035
and 0.045kcal/mh°C)
▪ with a heat resistance of at least 120°C
▪ Insulation thickness
Ambient
temperature
≤30°C 75% to 80% RH 15mm
>30°C ≥80% RH 20mm
Humidity Minimum thickness

5.4 Preparing electrical wiring

5.4.1 About preparing electrical wiring

WARNING
▪ All wiring MUST be performed by an authorised
electrician and MUST comply with the applicable legislation.
▪ Make electrical connections to the fixed wiring.
▪ All components procured on-site and all electrical
construction MUST comply with the applicable legislation.
WARNING
ALWAYS use multicore cable for power supply cables.
6 Installation

6.1 Overview: Installation

This chapter describes what you have to do and know on-site to install the system.
Typical workflow
Installation typically consists of the following stages:
▪ Mounting the outdoor unit.
▪ Mounting the indoor units.
▪ Connecting the refrigerant piping.
▪ Checking the refrigerant piping.
▪ Charging refrigerant.
▪ Connecting the electrical wiring.
▪ Finishing the outdoor installation.
▪ Finishing the indoor installation.
INFORMATION
For installation of the indoor unit (mounting the indoor unit, connecting the refrigerant piping to the indoor unit, connecting the electrical wiring to the indoor unit …), see the installation manual of the indoor unit.
INFORMATION
Also read the precautions and requirements in the "General safety precautions" chapter.
INFORMATION
Also read "6.7.5 Specifications of standard wiring
components"on page18.
WARNING
▪ If the power supply has a missing or wrong N-phase,
equipment might break down.
▪ Establish proper earthing. Do NOT earth the unit to a
utility pipe, surge absorber, or telephone earth. Incomplete earthing may cause electrical shock.
▪ Install the required fuses or circuit breakers.
▪ Secure the electrical wiring with cable ties so that the
cables do NOT come in contact with sharp edges or piping, particularly on the high-pressure side.
▪ Do NOT use taped wires, stranded conductor wires,
extension cords, or connections from a star system. They can cause overheating, electrical shock or fire.
▪ Do NOT install a phase advancing capacitor, because
this unit is equipped with an inverter. A phase advancing capacitor will reduce performance and may cause accidents.

6.2 Opening the units

6.2.1 About opening the units

At certain times, you have to open the unit. Example:
▪ When connecting the refrigerant piping
▪ When connecting the electrical wiring
▪ When maintaining or servicing the unit
DANGER: RISK OF ELECTROCUTION
Do NOT leave the unit unattended when the service cover is removed.

6.2.2 To open the outdoor unit

DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF BURNING
AZQS100~140B8V1B + AZQS100~140B7Y1B Split system air conditioners 4P385529-1C – 2019.04