AERCO BMK 1.5 LN User Manual June 2010

Page 1
AERCO INTERNATIONAL, Inc., Northvale, New Jersey, 07647 USA
Instruction
No.
Installation, Operation
& Maintenance Instructions
Benchmark 1.5LN Series Gas Fired Low NOx Boiler System
Condensing, Modulating
Forced Draft, Hot Water Boiler
1,500,000 BTU/H Input
Applicable for Serial Numbers G-10-1002 and above
Printed in U.S.A. REVISED JUNE 14, 2010
Page 2
Telephone Support
Direct to AERCO Technical Support (8 to 5 pm EST, Monday through Friday):
1-800-526-0288
AERCO International, Inc. 159 Paris Avenue Northvale, NJ 07647-0128
www.aerco,com
© AERCO International, Inc., 2010
The information contained in this installation, operation and mainte­nance manual is subject to change without notice from AERCO International, Inc.
AERCO makes no warranty of any kind with respect to this material, including but not limited to implied warranties of merchantability and fitness for a particular application. AERCO International is not liable for errors appearing in this manual. Nor for incidental or consequential damages occurring in connection with the furnishing, performance, or use of this material.
Page 3
CONTENTS
GF-120 - AERCO BENCHMARK 1.5LN GAS FIRED LOW NOx BOILER
Operating & Maintenance Instructions
FOREWORD A
Chapter 1 – SAFETY PRECAUTIONS 1-1
Para. Subject Page
1-1 Warnings & Cautions 1-1 1-2 Emergency Shutdown 1-2
Chapter 2 – INSTALLATION 2-1
Para. Subject Page
2.1 Introduction 2-1
2.2 Receiving the Unit 2-1
2.3 Unpacking 2-1
2.4 Site Preparation 2-1
2.5 Supply and Return Piping 2-3
2.6 Condensate Drains 2-3
2.7 Gas Supply Piping 2-4
2.8 AC Elec tric a l Po wer Wiring 2-5
Para. Subject Page
1-3 Prolonged Shutdown 1-2
Para. Subject Page
2.9 Modes of Operation and Field Control Wiring
2.10 I/O Box Connections 2-7
2.11 Auxiliary Relay Contacts 2-9
2.12 Flue Gas Vent Installation 2-9
2.13 Combustion Air 2-10
2-5
Chapter 3 – CONTROL PANEL OPERATING PROCEDURES 3-1
Para. Subject Page
3.1 Introduction 3-1
3.2 Control Panel Description 3-1
3.3 Control Panel Menus 3-4
3.4 Operating Menu 3-5
3.5 Setup Menu 3-5
Para. Subject Page
3.6 Configuration Menu 3-6
3.7 Tuning Menu 3-7
3.8 Combustion Cal Menu 3-8
3.9 Start Sequence 3-8
3.10 Start/Stop Levels 3-10
Chapter 4 – INITIAL START-UP 4-1
Para. Subject Page
4.1 Initial Startup Requirements 4-1
4.2 Tools and Instruments for Combustion Calibration
4.3 Natural Gas Combustion Calibration
4-1 4-2
Para. Subject Page
4.4 Unit Reassembly 4-5
4.5 Over-Temperature Limit Switches
4-6
i
Page 4
CONTENTS
Chapter 5 – MODE OF OPERATION 5-1
Para. Subject Page
5.1 Introduction 5-1
5.2 Indoor/Outdoor Reset Mode 5-1
5.3 Constant Setpoint Mode 5-2
5.4 Remote Setpoint Mode 5-2
5.5 Direct Drive Modes 5-3
Para. Subject Page
5.6 Boiler Management System (BMS)
5.7 Combination Control System (CCS)
5-4 5-5
Chapter 6 – SAFETY DEVICE TESTING PROCEDURES 6-1
Para. Subject Page
6.1 Testing of Safety Devices 6-1
6.2 Low Gas Pressure Fault Test 6-1
6.3 High Gas Pressure Test 6-2
6.4 Low Water Level Fault Test 6-2
6.5 Water Temperature Fault Test 6-2
6.6 Interlock Tests 6-3
6.7 Flame Fault Test 6-4
Para. Subject Page
6.8 Air Flow Fault Test 6-4
6.9 SSOV Proof of Closure Switch 6-5
6.10 Purge Switch Open During Purge
6.11 Ignition Switch Open During Ignition
6.12 Safety Pressure Relief Valve Test
6-5 6-6 6-6
Chapter 7 – MAINTENANCE REQUIREMENTS 7-1
Para. Subject Page
7.1 Maintenance Schedule 7-1
7.2 Ignitor-Injector 7-2
7.3 Flame Detector 7-3
7.4 Combustion Calibration 7-3
7.5 Safety Device Testing 7-3
7.6 Burner Assembly Inspection 7-3
Para. Subject Page
7.7 Condensate Drain Trap 7-5
7.8 Shutting the Boiler Down For An Extended Period of Time
7.9 Placing The Boiler Back In Service After A Prolong ed Shutdown
7-5 7-5
Chapter 8 – TROUBLESHOOTING GUIDE 8-1
Para. Subject Page
8.1 Introduction 8-1
Para. Subject Page
Chapter 9 - RS232 COMMUNICATION 9-1
Para. Subject Page
9.1 Introduction 9-1 9-2 RS232 Communication Setup 9-1
Para. Subject Page
9-3 Menu Processing Utilizing
RS232 Communication
9-4 Data Logging 9-2
9-1
ii
Page 5
CONTENTS
APPENDICES
App Subject Page
A Boiler Menu Item Descriptions A-1 B Startup, Status and Fault
Messages
C Temperature Sensor Resistance
Chart
D Indoor/Outdoor Reset Ratio
Charts
B-1 C-1 D-1
WARRANTIES W-1
App Subject Page
E Boiler Default Settings E-1 F Dimensional and Part Drawings F-1 G Piping Drawings G-1 H Wiring Schematics H-1 I Recommended Periodic Testing
Checklist
J Benchmark Control Panel Views J-1 K Recommended Spare Parts K-1
I-1
iii
Page 6
Page 7

FOREWORD

Foreword
The AERCO Benchmark 1. 5LN Boiler is a m odulating unit. It represents a true industry advance that meets the needs of today's ener gy and environmental concerns. Designed for application in any closed loop hydronic system, the Benchmark's modulating capability relates energ y input directly to fluctuating system loads. The Benchmark 1.5, with its 20:1 turn down ratio and condensing capability, provides extremely high efficiencies and makes it ideally suited for modern low temperature, as well as, conventional heating systems.
The Benchmark 1.5 operates at inputs ranging from 75, 000 BTU/hr. to 1,500,000 BTU/hr. The output of the boiler is a f unction of the unit’s firing rate and return water temperat ure. Output ranges from 74,250 BT U/hr. to 1,450,000 BTU/hr . , depending on operating conditions.
When installed and operated in accordance with this Instruction Manual, the Benchmark 1.5 Boiler complies with the NOx emission standards outlined in:
South Coast Air Quality Management District (SCAQMD), Rule 1146.2
Whether used in singular or modular arrangements, the Benchmark 1.5 offers the maximum flexibility in venting with minimum installation space requirements. The Benchmark 's advanced electronics are available in several selectable modes of operation offering the most efficient operating methods and energy manag em ent system integration.
For service or parts, contact your local sales represent at ive or AERCO I NTERNATIONAL.
NAME: ORGANIZATION: ADDRESS: TELEPHONE: INSTALLATION DATE: _____________________________________________
A
Page 8
Page 9
SAFETY PRECAUTIONS
CHAPTER 1 SAFETY PRECAUTIONS
1.1 WARNINGS & CAUTIONS
Installers and operat ing personnel MUST, at all times, observe all safety regulations. The following warnings an d cautions are gener al and must be given the same attention as specific precautions included in these instructions. In addition to all the requirements included in this AERCO Instruction Manual, the installation of units MUST conform with local building codes, or, in the absence of local codes, ANSI Z223.1 (National Fuel Gas Code Publ ication No. NFPA-
54). Where ASME CSD-1 is required by local jurisdiction, the installation must conform to CSD-1.
Where applicable, the equipment shall be installed in accordance with the current Installation Code for Gas Burning Appliances and Equipment, CGA B149, and applicable Provincial regulat io ns f or th e c las s; which should be carefully followed in all cases. Authorities having jurisdiction should be consulted before installations are made.
IMPORTANT
This Instruction Manual is an integral part of the product and must be maintained in legible condition. It must be given to the user by the installer and kept in a safe place for future reference.
WARNINGS!
MUST BE OBSERVED TO PREVENT SERIOUS INJURY.
WARNING!
BEFORE ATTEMPTING TO PER­FORM ANY MAINTENANCE ON THE UNIT, SHUT OFF ALL GAS AND ELECTRICAL INPUTS TO THE UNIT.
WARNING!
DO NOT USE MATCHES, CANDLES, FLAMES, OR OTHER SOURCES OF IGNITION TO CHECK FOR GAS LEAKS.
WARNING!
FLUIDS UNDER PRESSURE MAY CAUSE INJURY TO PERSONNEL OR DAMAGE TO EQUIPMENT WHEN RELEASED. BE SURE TO SHUT OFF ALL INCOMING AND OUTGOING WATER SHUTOFF VALVES. CAREFULLY DECREASE ALL TRAPPED PRESSURES TO ZERO BEFORE PERFORMING MAINTENANCE.
WARNING!
ELECTRICAL VOLTAGES UP TO 120 VAC MAY BE USED IN THIS EQUIPMENT. THEREFORE THE COVER ON THE UNIT’S POWER BOX (LOCATED BEHIND THE FRONT PANEL DOOR) MUST BE INSTALLED AT ALL TIMES, EXCEPT DURING MAINTENANCE AND SERVICING.
CAUTIONS!
Must be observed to prevent equipment damage or loss of operating effectiveness.
CAUTION!
Many soaps used for gas pipe leak testing are corrosive to metals. The piping must clean water after leak checks have been completed.
be rinsed thoroughly with
WARNING!
THE EXHAUST VENT PIPE OF THE UNIT OPERATES UNDER A POSITIVE PRESSURE AND THERE­FORE MUST BE COMPLETELY SEALED TO PREVENT LEAKAGE OF COMBUSTION PRODUCTS INTO LIVING SPACES.
CAUTION!
DO NOT use this boiler if any part has been under water. Call a qualified service technician to inspect and replace any part that has been under water.
1-1
Page 10
SAFETY PRECAUTIONS
1.2 EMERGENCY SHUTDOWN
If overheating occurs or the gas supply fails to shut off, close the manual gas shutoff valve (Figure 1-1) located external to the unit.
IMPORTANT
The Installer must identify and indicate the location of the emergency shutdown manual gas valve to operating personnel.
MANUAL GAS SHUTOFF VALVE
VALVE OPEN
VALVE CLOSED
1.3 PROLONGED SHUTDOWN
After prolonged shutdown, it is recommended that the startup proce dures in Chapter 4 and the safety device test procedures in Chapter 6 of this manual be performed, to verify all system­operating param eters. If ther e is an em ergenc y, turn off the electrical power supply to the AERCO boiler and close the manual gas valve located upstream the unit. The installer must identify the emergency shut-off device.
Figure 1-1
Manual Gas Shutoff Valve
IMPORTANT – FOR MASSACHUSETTS INSTALLATIONS ONLY
Boiler Installations within the Commonwealth of Massachusetts must conform to the following requirements:
Boiler must be installed by a plumber or a gas f itter who is licens ed within the Commonwealth of Massachusetts.
Pr ior to unit operation, the complete gas train and all connections must be lea k tested using a non-corrosive soap.
If a glycol solution is used as anti-freeze protection, a backflow preventer must be installed upstream of the Fill/Makeup Valve.
The vent termination must be located a minimum of 4 feet above grade le vel.
If side-wall venting is used, the installation m us t conform to the following r equirem ents ext racted
from 248 CMR 5.08 (2):
(a) For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or structure used in whole or in part for residential purposes, including those owned or operated by the Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above finished grade in the area of the venting, including but not limited to decks and porches, the following requirements shall be satisfied:
1-2
1. INSTALLATION OF CARBON MONOXIDE DETECTORS side wall horizontal vented gas fueled equipment, the installing plumber or gasfitter shall observe that a hard wired carbon monoxide detector with an alarm and battery back-up is installed on the floor level where the gas equipment is to be installed. In addition, the installing plumber or gasfitter shall observe that a battery operated or hard wired carbon monoxide detector with an alarm is installed on each additional level of the dwelling, building or structure served by the side wall horizontal vented gas fueled equipment. It shall be the responsibility of the property owner to secure the services of qualified licensed professionals for the installation of hard wired carbon monoxide detectors.
. At the time of installation of the
Page 11
Extracted Information From 248 CMR 5.08 (2) – Continued
a. In the event that the side wall horizontally vented g as fueled equ ipment is installed in a crawl space or an attic, the hard wired carbon monoxide detector with alarm and battery back-up may be installed on t he next adj ac ent floor le ve l.
b. In the event that the requirements of this subdivision can not be met at the time of completion of installation, the owner shall have a period of thirty (30) days to comply with the above requirements; provided, however, that during said thirty (30) day period, a battery operated carbon monoxide detector with an alarm shall be installed.
SAFETY PRECAUTIONS
2. APPROVED CARBON MONOXIDE DETECTORS. required in accordance with the above provisions shall comply with NFPA 720 and be ANSI/UL 2034 listed and IAS certified.
3. SIGNAGE of the building at a minimum height of eight (8) feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment. The sign shall read, in print size no less than one-half (1/2) inch in size, "GAS VENT DIRECTLY BELOW.
KEEP CLEAR OF ALL OBSTRUCTIONS".
4. INSPECTION equipment shall not approve the installation unless, upon inspection, the inspector observes carbon monoxide detectors and signage ins ta l led in acc or dance with the pr ov isi on s of 248 CMR
5.08(2)(a)1 through 4.
(b) EXEMPTIONS
1. The equipment listed in Chapter 10 entitled "Equipment Not Required To Be Vented" in the most current edition of NFPA 54 as adopted by the Board; and
2. Product Approved side wall horizontally vented gas fueled equipment installed in a room or structure separate from the dwelling, building or structure used in whole or in part for residential purposes.
(c) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM PROVIDED. the manufacturer of Product Approved side wall horizontally vented gas equipment provides a venting system design or venting system components with the equipment, the instructions provided by the manufacturer for installation of the equipment and the venting system shall include:
1. Detailed instructions for the installation of the venting system design or the venting system components; and
2. A complete parts list for the venting system design or venting system.
. A metal or plastic identification plate shall be permanently mounted to the exterior
. The state or local gas inspector of the side wall horizontally vented gas fueled
: The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4:
Each carbon monoxide detector as
When
(d) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM NOT PROVIDED. When the manufacturer of a Product Approved side wall horizontally vented gas fueled equipment does not provide the parts for venting the flue gases, but identifies "special venting systems", the following requirements shall be satisfied by the manufacturer:
1. The identification of each "special venting system" shall include the listing of either the website, phone number or manufacturer’s address where the venting system installation instructions can be obtained, and
2. The "special venting systems" shall be Product Approved by the Board, and the instructions for that system shall include a parts list and detailed installation instructions.
(e) A copy of all installation instructions for the Product Approved side wall horizontally vented gas fueled equipment and all the venting instructions, parts lists and/or design instructions for the venting system shall remain with the appliance or equipment at the completion of the installation.
_______________________________ [End of Extracted Information From 248 CMR 5.08 (2)]
1-3
Page 12
Page 13
INSTALLATION
CHAPTER 2 INSTALLATION
2.1 INTRODUCTION
This Chapter provides the descriptions and procedures necessary to unpack, inspect and install the AERCO Bench mark 1.5 Boiler. Brief descriptions are also pr ovided f or each avai lable mode of operation. Detailed procedures for implementing these modes are provided in Chapter 5.
2.2 RECEIVING THE UNIT
Each Benchmark 1.5 System is shipped as a single crated unit. The shipping weight is approximately 1551 pounds. The unit must be moved with the proper rigging equipment for safety and to avoid equipment dam age. The unit should be complete ly inspected for evidence of shipping damage and ship ment com pleteness at the time of receipt from the carrier and before the bill of lading is signed.
NOTE
AERCO is not responsible for lost or damaged freight.
Each unit has a Tip-N-Tell indicator on the outside of the crate. T his indic ates if the un it has been turned on its side during shipment. If the Tip-N-Tell indicat or is trip ped, do not s ign for the shipment. Note the information on the carrier’s paperwork and request a freight claim and inspection by a claims adjuster before proceeding. Any other visual damage to the packaging materials s hould also be made clear to the delivering carrier.
2.3 UNPACKING
Carefully unpack the unit taking care not to damage the unit enclosure when cutting away packaging materials
The following accessories come standard with each unit and are either packed separately within the unit’s pack ing container or are fac tory installed on the boiler:
Pressure/Temperature Gauge
Spare Spark Ignitor-Injector
Spare Flame Detector
ASME Pressure Relief Valve
Condensate Drain Trap
1-1/2” Gas Supply Shutoff Valve
When ordered, optional accessories may be packed separately, packed within the boiler shipping container, or may be installed on the boiler. Any standard or optional accessories shipped loose should b e identified and s tored in a safe place until ready for installation or use.
2.4 SITE PREPARATION.
Ensure that the site selected for installation of the Benchmark 1.5 Boiler includes:
Access to AC Input Power at 120 VAC, 1­Phase, 60 Hz @ 20
Access to Natural Gas line at a minimum pressure of 4 inches W.C.
2.4.1 Installation Clearances
The unit must be installed with the prescribed clearances for service as shown in Figure 2-1. The minimum AERCO, are listed below. However, if Local Building Codes require additional clearances, these codes shall supersede AERCO’s requirements. Minimum acceptable clearances required are:
clearance dimensions , requir ed by
A close inspection of the unit s hould be made to ensure that there is no evidence of dam age not indicated by the T ip-N-Tell indicator. The f reight carrier should be notified immediately if any damage is detected.
IMPORTANT
After unpacking, take off the unit top panel and remove the strap and packing material at the top of the h eat exchanger. The packing material is located in the area of the ignitor-injector and staged ignition solenoid on the burner assembly.
Sides: 24 inches
Front : 24 inches
Rear: 30 inches
Top: 18 inches
All gas piping, water piping and el ec tric al c on du it or cable must be arranged so that they do not interfere with the removal of any panels, or inhibit service or maintenance of the unit.
2-1
Page 14
INSTALLATION
44.5"
4" HIGH PAD
18"
79"
101"
Figure 2-1 Benchmark 1.5 Boiler Clearances
WARNING
KEEP THE UNIT AREA CLEAR AND FREE FROM ALL COMBUSTIBLE MATERIALS AND FLAMMABLE VAPORS OR LIQUIDS
.
CAUTION
While packaged in the shipping container, the boiler must be moved by pallet jack or forklift from the FRONT ONLY.
FOR MASSACHUSSETTS ONLY:
For Massachusetts installations, the boiler must be installed by a plumber or gas fitter who is licensed within the Commonwealth of Massachusetts. In addition, the installation must comply with all requirements specified in Chapter 1 (Safety Precautions), pages 1-2 & 1-3.
2.4.2 Setting the Unit
The unit must be installed on a 4 inch to 6 inch housekeeping pad to e nsure proper conde nsate drainage. If anchoring the unit, refer to the dimensional drawings in Appendix F for anchor locations. Two lifting t abs ar e provided a t the top of the heat exchanger. Figure 2-2 shows the location of the tab on the top-left side. The second tab is located on t he top-ri ght side of the heat exchanger. USE THESE TWO TABS TO LIFT AND MOVE THE UNIT. Remove the top panel from the unit to provide access to the lifting tabs. Remove the four (4) lag screws
2-2
24"
30" 24"
24"
REAR
securing the unit to the shipping skid. Lift the unit off the shipping sk id and position it on the 4 inch to 6 inch housekeeping concrete pad (required) in the desired location.
FRONT
WARNING
WHEN LIFTING OR MOVING THE BOILER:
DO NOT MANIPULATE THE BOILER USING THE GAS TRAIN OR BLOWER
WHEN USING THE LIFTING TABS, ENSURE THERE IS NO LOAD PLACED ON THE GAS TRAIN OR BLOWER
LIFTING TAB
(2 PLACES)
PART OF GAS TRAIN
DO NOT
LIFT HERE
BLOWER
AIR/FUEL
VALVE
Figure 2-2
Partial Top View Showing Lifting Tab
Location
Page 15
INSTALLATION
In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient space for piping connections and future service/maintenance requirements must also be taken into cons ider ation. All pipin g m ust include ample provisions for expansion.
If installing a Combina tion Control Panel (CCP) system, it is important to identify the Combination Mode B oilers in adv ance and plac e them in the proper physical location. Refer to Chapter 5 for inform ation on Combination Mode Boilers.
2.5 SUPPLY AND RETURN PIPING
The Benchmark 1.5 Boiler utilizes 3” 150# flanges for the water system supply and return piping connectio ns. The physical location of the supply and return p iping connections are on the rear of the unit as shown in Figure 2-3. Ref er to Appendix F, Drawing AP-A-832 for additional dimensional data.
BOILER SUPPLY
3" – 150# FLANGED
CONNECTION
1-1/2”
GAS INLET
CONNECTION
The procedure to install and connect the condensate drain is provided in paragraph 2.6.1.
EXHAUST
MANIFOLD
CONDENSATE DRAIN CONNECTION
PARTIAL REAR VIEW
BOILER RETURN
Figure 2-4
Condensate Drain Connection Location
2.6.1 Exhaust Manifold Condensate Drain
The exhaust manifold drain pipe connection shown in Figure 2-4, must be connected to a condensate drain trap external to th e unit. Refer to Figure 2-5 and install the trap as follows:
SHELL DRAIN
VALVE
EXHAUST
MANIFOLD
REAR VIEW
BOILER RETURN 3" – 150# FLANGED CONNECTION
Figure 2-3
Supply and Return Locations
2.6 CONDENSATE DRAIN
The Benchmark 1.5 Boiler is designed to condense water vapor from the flue products. Therefore, the insta llation must have provisions for suitable condensate drainage or collection.
The condensate drain pipe located on the exhaust manifold (Figure 2-4) must be connected to a condens ate trap which is packed separately within the unit’s shipping container.
1. Install 3/4” NPT nipples in the tapped inlet and outlet of the condensate trap (part no.
24060).
2. Install a third 3/4” NPT nipple in the tapped condensate outlet of the exhaust manifold.
3. Connect the exhaust manifold nipple to the condensate trap inlet using a female union.
4. install a suitable support under the condensate trap and ens ure that the trap is level.
5. Connect a length of 1” I.D. polypropylene hose (part no. 91030) to the nipple on the outlet side of the condensate trap and secure it with a hose clamp.
6. Route the hose on the trap outlet to a nearby floor drain.
If a floor drain is not available, a condensate pump can be used to remove the condens ate to drain. The max imum condensate flow rate is 2 0 GPH. The condensate drain trap, associated fittings and drain lines must be removable for routine maintenance.
2-3
Page 16
INSTALLATION
EXHAUST
HOUSEKEEPING
PAD
MANIFOLD
UNION
3/4" NPT NIPPLES
PARTIAL RIGHT SIDE VIEW
CONDENSATE
TRAP
SUPPORT
3/4" NPT
NIPPLE
FLOOR
1" I.D.
HOSE &
CLAMP
TO
DRAIN
Figure 2-5
Condensate Trap Installation
2.7 GAS SUPPLY PIPING
The AERCO Benchmark 1.5 Gas Components and Supply Design Guide, GF-4030 must be consulted prior to des ignin g or installi ng an y gas supply piping.
WARNING
NEVER USE MATCHES, CANDLES, FLAMES OR OTHER SOURCES OF IGNITION TO CHECK FOR GAS LEAKS
Many soaps used for gas pipe leak testing are corrosive to metals. There­fore, piping must be rinsed thoroughly with clean water after leak checks have been completed.
All gas piping m ust be arranged so that it does not interfere with removal of any covers, inhibit service/maintenance, or restrict access between the unit and walls, or another unit.
A 1-1/2 inch gas inlet connection is located on the rear of the unit as shown in Figure 2-3.
Prior to installation, all pipes should be de­burred and internally clear ed of any scale, m etal chips or other foreign particles. Do Not install any flexible connectors or unapproved gas fittings. Piping must be s upported from the floor, ceiling or walls onl y and must not be supported by the unit.
2-4
.
CAUTION
NOTE
A suitable piping compound, approved for use with natural gas, should be used. Any excess must be wiped off to prevent clogging of components.
To avoid unit damage whe n pres sur e tes ting gas piping, isolate the unit from the gas supply piping. At no time should the gas pressure applied to the unit exceed 2 psi. Leak test all external piping thoroughly using a soap and water solution or suitable equivalent. The gas piping used must meet all applicable codes.
2.7.1 Gas Supply Specifications.
The gas supply input specifications to the unit for Natural Gas are as follows:
The maximum static pressure to the unit must not exceed 2 psi. The gas supply press ure to the unit must be of sufficient capacity to provide 1500 cfh while maintaining the gas pressure at
4.0 inches W.C. for FM, or 4.2 inc hes W.C. for
IRI gas trains.
2.7.2 Manual Gas Shutoff Valve
A manual shut-off valve must be installed in th e gas supply line upstream of the Boiler as shown in Figure 2-6. M aximum allowable gas pressure to the Boiler is 2 psi
NOTE
Paragraph 2.7.3 applies only to bolier installations within the Commonwealth of Massachusetts.
2.7.3 External Gas Supply Regulator
For Massachusetts installations, a mandatory external gas suppl y reg ul at or must be positioned as shown in Figure 2-6. The gas supply regulator must be properly vented to outdoors. Consult the local gas utility for detailed requirements concerning venting of the the supply gas regulator.
NOTE
The external regulator must be c apable of regulating 1,500,000 BTU/HR of natural gas while maintaining a gas pressure of
4.0” W.C. to the boiler.
CAUTION
A lock-up style regulator MUST be used when gas supply pressure will exceed 14” W.C.
Page 17
INSTALLATION
NATURAL
GAS
SUPPLY
1-1/2” MANUAL GAS SHUTOFF
VALVE
GAS PRESSURE
REGULATOR
(REQUIR ED FOR
MASSACHUSETTS
INSTALALTIONS
ONLY)
DIRT
TRAP
Figure 2-6
Manual Gas Shut-Off Valve Location
2.7.4 IRI Gas Train Kit
The IRI gas train is an optional gas train configuration which is r e qui red i n s ome areas for code compliance or for insurance purposes. The IRI gas train is factor y pre-piped and wired. See Appendix F, Drawing AP- A-830 f or details.
2.8 AC ELECTRICAL POWER WIRING
The AERCO Benchmark 1.5 Electrical Power Wiring Guide, GF-40 60, must be co nsulted prior to connecting any AC power wiring to the unit. External AC power connect ions are made to the unit inside the Power Box on the front panel of the unit. Remove the front door of the unit to access the Power Box mounted directly above the Control Box. Loosen the four Power Box cover screws and remove cover to access the AC terminal connections inside the Power Box (Figure 2-7).
TERMINAL BLOCK
UPPER RIGHT CORNER OF FRONT PANEL
Figure 2-7
AC Input Terminal Block Location
2.8.1 Electrical Power Requirements
The AERCO Benchmark 1.5 Boiler accepts 120 VAC, single-phase, 60 Hz @ 20 A. The Power Box contains a terminal block as shown in Figure 2-8. In addition, a wiring diagr am showing the required AC power connections is provided on the front cover of the Power Box.
Each Benchmark 1.5 Boil er must be connected to a dedicated electrical circuit. NO OTHER DEVICES SHOULD BE ON THE SAME ELECTRICAL CIRCUIT AS THE BENCHMARK BOILER. A means for disconnecting AC power from the unit (such as a ser vice switch) mus t be installed near th e unit for normal operation and maintenance. All electrical connections should be made in accordance with the National Electrical Code and/ or with any applicable local codes.
For electrical power wiring diagrams, see the AERCO Benchmark 1.5 Electrical Power W iring Guide, (GF-4060).
120 VAC, 1 PHASE
GND
NEU
NOTE
All electrical conduit and hardware must be installed so that it does not interfere with the removal of any un it cover s, inh ibit service/maintenance, or prevent access between the unit and walls or another unit.
L1
Figure 2-8
AC Terminal Block Configurations
2-5
Page 18
INSTALLATION
2.9 MODES OF OPERATION AND FIELD CONTROL WIRING
The Benchmark 1.5 B oiler is available in severa l different modes of operation. W hile each unit is factory configured and wired for its intended mode, some additional field wiring may be required to complete th e installation. This wir ing is typically connected to the Input/Output (I/O) Box located on the lower por tion of the unit fr ont panel (Figure 2-9) behind the removable front door.
To access the I/O Box terminal strips shown in Figure 2-10, loosen the four cover screws and remove the cover. All field wiring is installed from the rear of the panel by routing the wires through one of the four bushings provided.
Refer to the wiring diagram provided on the cover of the I/O Box (Figur e 2-10) when making all wiring connections.
Brief descriptions of each mode of operation, and their wiring requirements, are provided in the following paragr aphs. Additional information concerning field wiring is prov ided in paragr aphs
2.9.1 through 2.9.9. Refer to Chapter 5 for detailed information on the available modes of operation.
TERMINAL
STRIPS
LOWER RIGHT CORNER
OF FRONT PANEL
Figure 2-9.
Input/Output (I/O) Box Location
2-6
Figure 2-10. I/O Box Terminal Strip
Page 19
INSTALLATION
2.9.1 Constant Setpoint Mode
The Constant Setpoi nt Mode is used when it is desired to have a fixed setpoint that does not deviate. No wiring connections, other than AC electrical power connections, are required for this mode. However, if desired, fault monitor ing or enable/disable in terlock wiring c an be utilized (see paragraphs 2.9.9.1 and 2.9.10).
2.9.2 Indoor/Outdoor Reset Mode
This mode of operation increases supply water temperature as outdoor te mperatures decrease. An outside air temperatur e sensor (AERCO Part No. 122790) is requ ired. The sensor MUST BE wired to the I/O Box wiring term inals (see Figure 2-10). Refer to paragraph 2.10.1 for additional information on outside air temperature sensor installation.
2.9.3 Boiler Management System Mode NOTE
BMS Model 168 can utilize either pulse width modulation (PWM) or RS485 Modbus signaling to the Boiler. BMS II Model 5R5-384 can utilize only RS485 signaling to the Boiler.
When using an AERCO Boiler Management System (BMS), the field wiring is connected between the BMS Panel and each Boiler’s I/O Box terminal strip (Figure 2-10). Twisted shielded pair wire f rom 18 to 22 AWG must be utilized for the connections. The BMS Mode can utilize either pulse width modulation (PWM) signaling, or RS485 Modbu s s ignaling. F or PWM signaling, connections are made from the AERCO Boiler Management System to the B.M.S. (PWM) IN terminals on the I/O Box terminal strip. For RS485 Modus signaling, connections are made from the BMS to the RS485 COMM term inals on the I/O Box ter minal strip. Polarity m ust be maintain ed and the shie ld must be connected only at the AERCO BMS. The boiler end of the shi eld m ust be left f loating. For additional instructions, refer to Chapter 5, paragraph 5.6 in t his manual. Also, ref er to GF­108M, BMS -Operations Guide.
2.9.4 Remote Setpoint and Direct Drive
Modes
The Benchmark 1.5 Boiler can accept several types of signal formats from an Energy Management System (EMS), Building Automation System (BAS) or other source, to control either the setpoint (Remote Setpoint Mode) or air/fuel valve position (Direct Drive Mode) of the Boiler. These formats are:
4 to 20 mA/1 to 5 VDC
0 to 20 mA/0 to 5 VDC
PWM – (Pulse W idth Modulated signal. See
para. 2.10.4)
Network (RS485 Modbus. See para. 2.10.7) While it is possible to c ontrol a boiler or boilers
using one of the previously described m odes of operation, it ma y not be the method best suited for the application. Prior to selecting one of these modes of operation, it is recommended that you consult with your local AERCO representative or the factory for the mode of operation that will work best with your application. For m ore information on wir ing the 4 to 20 mA / 1to 5VDC or the 0 to 20 m A / 0 to 5 VDC, see paragraph 2.9.3.
2.9.5 Combination Mode
With a Combination Mode unit, field wiring is between the unit’s I/O Box wiring terminals, the CCP (Combination Contr ol Panel), an d the BMS (Boiler Management System). The wiring must be accomplished using twisted-shielded pair wire from 18 to 22 AWG. Polarity must be maintained. For further instructions and wiring diagrams, refer to the GF-108 Boiler Management System Operations Guide and the CCP-1 data sheet.
2.10 I/O BOX CONNECTIONS
The types of input and output signals and devices to be connecte d to the I/O Box terminals shown in Figure 2-10 are described in the following paragraphs.
CAUTION
DO NOT make any connections to the I/O Box terminals labeled “NOT USED”. Attempting to do so may cause equipment damage.
2.10.1 OUTDOOR SENSOR IN
An outdoor air temperature sensor (AERCO Part No. 122790) will be required primarily for the Indoor/Outdoor reset m ode of operation. It can also be used with anoth er m ode if it is desired to use the outdoor sensor enable/disable feature. This feature allows the boiler to be enabled or disabled based on the outdoor air temperature.
The factory default for the outdoor sensor is DISABLED. To enable the sensor and/or select an enable/disable o utdoor temperature, see the Configuration menu in Chapter 3.
The outdoor sensor m ay be wired up t o 200 feet from the boiler. It is connected to the OU T D OO R
2-7
Page 20
INSTALLATION
SENSOR IN and SENSOR COMMON terminals in the I/O Box (see Figures 2- 9 and 2-10). Wire the sensor using a twisted shielded pair wire from 18 to 22 AWG. There is no polarity to observe when terminating these wires. The shield is to be connected only to the terminals labeled SHIELD in the I/O Box. The sensor end of the shield must be left free and ungrounded.
When mounting the sensor, it must be located on the North side of the building where an average outside air temperature is expected. The sensor must be shield ed f r om dir ect sunli ght as well as impingement by the elements. If a shield is used, it must allow for free air circulation.
2.10.2 AIR SENSOR IN
The AIR SENSOR IN is connected to the AUX SENSOR IN and SENSOR COMMON terminals on the I/O board. The AIR SENSOR measures the temperature of the air input to the Air/Fuel Valve. This temperature reading is one of the components used to calculate the rotational speed of the blower used in the combustion Calibration process (Chapter 4).
made using twiste d shiel ded pa ir wire fr om 18 to 22 AWG, such as Belden 9841 (see Figure 2-10). Polarity mu st be maintained. The shi eld must be connected only at the source end and must be left floating (not connected) at the Boiler’s I/O Box.
Regardless of whether volt age or curr ent is used for the drive signal, the y are linearly mapped to a 40°F to 240°F s etpoint or a 0% to 100% v alve position. No scaling for these signals is provided
2.10.4 B.M.S. (PWM) IN NOTE
Only BMS Model 168 can utilize Pulse Width Modulation (PW M), not the BMS II (Model 5R5-384).
These terminals are used to connect the AERCO Boiler Management System (BMS) to the unit. The BMS utilizes a 12 millisecond, ON/OFF duty cycle. This duty cycle is Pulse Width Modulated (PWM) to control valve position. A 0% va lve position = a 5% ON pulse and a 100% valve position = a 95% ON pulse.
The AUX SENSOR IN terminals can b e used to add an additional temperature sensor for monitoring purposes. This input is always enabled and is a view-only input that can be seen in the Operating Menu. The sensor must be wired to the AUX S ENSOR IN and SENSOR COMMON terminals and must be similar to AERCO BALCO wire se nsor Part No. 124 49. A resistance chart for this sensor is provided in Appendix C.
2.10.3 ANALOG IN
The ANALOG IN + and – terminals are used when an external signal is used to drive the air/fuel valve position (Direct Drive Mode) or change the setpoint (R emote Setpoint Mode) of the Boiler.
Either a 4 to 20 mA /1 to 5 VDC or a 0 t o 20 mA / 0 to 5 VDC signal may be used to vary the setpoint or valve position. The factory default setting is for 4 to 20 mA / 1 to 5 VDC, however this may be changed to 0 t o 20 mA / 0 to 5 VDC using the Configuration Menu described in Chapter 3. If voltage rather than current is selected as the dr ive signal, a DIP switch mus t be set on the PMC Board located inside the Control Box. Contact the AERCO factory for information on setting DIP switches.
All of the supplied signals must be floating (ungrounded) signals . Connectio ns bet ween the signal source and the Boiler’s I/O Box must be
2-8
2.10.5 SHIELD
The SHIELD terminals are us ed to terminate any shields used on sensor wires connected to the unit. Only shields m ust be connected to these terminals.
IMPORTANT
DO NOT USE the mA OUT output to remotely monitor Set point, O utlet Tem p or Fire Rate Out.
2.10.6 mA OUT
These terminals provide a 4 to 20 mA output to the VFD (if so equip ped) to control th e rotationa l speed of the blower. T his function is enable d in the Configuration Menu (Chapter 3, Table 3-4).
2.10.7 0 – 10V OUT
These terminals pro vide a 0 to 10 volt o utput to control the rotational speed of the blower. This function is enabled in the Configuration Menu (Chapter 3, Table 3-4).
2.10.8 RS-485 COMM
These terminals are used for RS-485 MODBUS serial communication between the unit and an external “Master” suc h as a Boiler Management System (BMS), Energy Management System (EMS), Building Automation System (BAS) or other suitable device.
Page 21
INSTALLATION
2.10.9 EXHAUST SWITCH IN
These terminals permit an external exhaust switch to be connected to the exhaust manifold of the boiler. The exhaust switch should be a normally open t ype s witc h (such as AERCO Par t No. 123463) that closes (trips) at 500°F.
2.10.10 INTERLOCKS
The unit offers two interlock circuits for interfacing with Energy Management Systems and auxiliary equipment such as pumps or louvers. These interlock s are called the Rem ote Interlock and Delayed Interlock (Figure 2-10). The wiring terminals for these interlocks are located inside the I/O Box on the unit front panel. The I/O Box cover contains a wiring diagram which s hows th e ter m inal str ip locat ions for these interlocks (REMOTE INTL’K IN and DELAYED INTL’K IN). Both interlocks, described below, are fac tory wired in the closed position.
NOTE
Both the Delayed Interlock and Remote Interlock MUST be in the closed position to allow the unit to fire.
2.10.10.1 REMOTE INTERLOCK IN
The remote interlock circuit is provided to remotely start (enable) and stop (disable) the Boiler, if desired. T he circuit is labeled REMO TE INTL’K IN and is located inside the I/O Box on the front panel. The circuit is 24 VAC and is factory pre-wired in the closed (jumpered) position.
2.10.10.2 DELAYED INT ER LOCK IN
The delayed interlock is typically used in conjunction with the aux iliary relay described in paragraph 2.11. This interlock circuit is located in the purge section of the start string. It can be connected to the proving device (end switch, flow switch etc.) of an auxiliary piece of equipment started b y the Boiler’s a uxiliary rela y. The delayed interlock must be closed for the boiler to fire.
If the delayed interl ock is connec ted t o a pr oving device that requir es tim e to clos e (mak e), a tim e delay (Aux Start On Dly) that holds the start sequence of the boiler lon g enoug h for a proving switch to make can be progr amm ed. Should the proving switch not prove within the programm ed time frame, the boiler will shut down. The Aux Start On Dly can be progr ammed from 0 to 120 seconds. This option is locate in the Configuration Menu (Chapter 3, Table 3-4).
2.10.11 FAULT RELAY
The fault relay is a single pole double throw (SPDT) relay having a normally open and normally closed set of relay contacts that are rated for 5 amps at 12 0 VAC and 5 amps at 30 VDC. The relay energizes when any fault condition occurs and remains energized until the fault is cleared and the CLEAR button is depressed. The fault relay connections are shown in Figure 2-10.
2.11 AUXILIARY RELAY CONTACTS
Each Boiler is equipped with a single pole double throw (SPDT) relay that is energized when there is a demand for heat and de­energized after the dem and for heat is satisf ied. The relay is prov ided for the control of auxiliary equipment, such as pumps and louvers, or can be used as a Boiler status indictor (firing or n ot firing). Its contacts are r ated for 120 VAC @ 5 amps. Refer to Figure 2- 10 to locate the AUX RELAY terminals for wiring connections.
2.12 FLUE GAS VENT INSTALLATION
The minimum allowable vent diameter for a single Benchmark 1.5 Boiler is 6 inches.
The AERCO Benchmark Venting and Combustion Air Guide, GF-2050, must be consulted before any flue gas vent or inlet air venting is designed or installed. U/L listed, positive pressure, watertight vent materials as specified in AERCO’s GF-2050, must be used for safety and code com pliance. S ince the u nit is capable of dischar ging low temperature ex haust gases, horizontal sections of the flue vent system must be pitched back to the unit a minimum of 1/4 inch per foot to avoid condensate pooling and allow for proper drainage.
The combined pressure drop of vent and combustion air systems must not exceed 140 equivalent feet of 6 inc h ducting. Fittings as we ll as pipe lengths must be calculate d as part of the equivalent length.
For a natural draf t installation the draf t must not exceed ±0.25 inch W .C. These factors must be planned into the vent installation. If the maximum allowabl e equivalent lengt hs of piping are exceeded, the unit will not operate properly or reliably.
For Massachusetts boiler installations, the Heatfab Division of the Selkirk Corporation provides vent systems which conform to all applicable requirements within the Common­wealth of Massachusetts. Contact information for this supplier is as follows:
2-9
Page 22
INSTALLATION
Selkirk Corporation Heatfab Division 130 Industrial Blvd. Turners Falls, MA 01376 Phone: 1-800-772-0739
www.heat-fab.com
2.13 COMBUSTION AIR
The AERCO Benchmark Venting and Combustion Air Guide, GF-2050 MUST be consulted before any flue or com bustion supply air venting is designed or implemented. Combustion air supp ly is a direct r equirem ent of ANSI 223.1, NFPA-54, and local codes. These codes should be consulted before a permanent design is determined.
The combustion air must be free of chlorine, halogenated hydrocarbons, or other chemicals that can become ha zardous when used in gas­fired equipment. Common sources of these compounds are swimming pools, degreasing compounds, plastic proc essing and refrigerants. Whenever the env ironment c ontains thes e t ypes of chemicals, combustion air must be supplied from a clean area outdoors for the protection and longevity of the equipment.
The AERCO Benchm ark 1.5 Boiler is UL listed for 100% sealed combustion. It can also be installed using room air, provided there is an adequate supply. (See paragraph 2.13.3 for more information conc erning sealed com bustion air). If the sealed combustion air option is not being used, an inlet screen will be attached at the air inlet on the top of the unit
The more common methods of supplying combustion air are outlined below. For more information concerning combustion air, consult the AERCO Benchmark Venting and Combustion Air Guide, GF-2050.
2.13.1 Combustion Air From Outside the Building
Air supplied from outside the building must be provided through two perm anent openings. Each opening must have a free area of not less than one square inch for each 4000 BTU/H boiler input. The free area must take into account restrictions such as louvers and bird screens.
one square inch per 1000 BTU/H of total boiler input. The free area must take into ac count any restrictions such as louvers.
2.13.3 Sealed Combustion
The AERCO Benchm ark 1.5 Boiler is UL listed for 100%-sealed combustion. For sealed combustion installations, the screen on the air inlet duct of the unit m ust be removed. T he inlet air ductwork must then be attached directly to the unit’s air inlet.
In a sealed combustion air application, the combustion air ducting pre ssure losses must be taken into account when calculating the total maximum allowable venting run. See the AERCO Benchmark Venting and Combustion Air Guide, GF-2050 . When using th e boiler in a sealed combustion air configuration, each unit must have a minimum 6 inch diameter connection at the unit.
2.13.4 Temporary Combustion Air
Filtering During Construction
When the Benchmark 1.5 Boiler is used to provide heat temporar ily during ongoing bu ilding construction, accum ulated dr ywall dust, sa wdust and similar particles can ac cum ulate in th e unit’s combustion air intake filter and block com bus tion air flow. In these situations, AERCO recom­mends that a disposable air intake filter be installed, temporarily, above the boiler combustion air inlet.
AERCO recommends that the temporary air filter be cut from a McMaster- Carr part no. 2122K3 15 Polyester Air Filter Roll Tackfield, ½” thick, 16” wide, or equivalent. Cover the Benchmark 1.5 air inlet with the blue side of the filter material facing outward to hold the dust on the outside surface. Maximize the surface area of the filter covering the 8" diameter opening by creating a dome out of the filter material.
Cover the flared duct op ening with the b lue side facing outward. During construction check the filter for dust accumulation and replace it when the accumulation becomes noticeable.
2.13.2 Combustion Air From Inside The Building
When combustion air is provided f rom within the building, it must be supplied through two permanent openings in an interior wall. Each opening must have a free area of not less than
2-10
Page 23
CONTROL PANEL OPERATING PROCEDURES
CHAPTER 3 CONTROL PANEL OPERATI NG PROCEDURES
3.1 INTRODUCTION
The information in this Chapter provides a guide to the operation of the Benchmark 1.5 Boiler using the Control Panel mounted on the front of the unit. It is imperative that the initial startup of this unit be performed by factory trained personnel. Operation prior to initial startup by factory trained personnel will void the equipment warranty. In addition, the following WARNINGS and CAUTIONS must be observed at all times.
2
CAUTION
All of the installation procedures in Chapter 2 must be completed before attempting to start the unit.
WARNING
ELECTRICAL VOLTAGES IN THIS SYSTEM MAY INCLUDE 460, 208 AND 24 VOLTS AC. IT MUST BE SERVICED ONLY BY FACTORY CERTIFIED SERVICE TECHNICIANS
WARNING
DO NOT ATTEMPT TO DRY FIRE THE BOILER. STARTING THE UNIT WITHOUT A FULL WATER LEVEL CAN SERIOUSLY DAMAGE THE UNIT AND MAY RESULT IN INJURY TO PERSONNEL OR PROPERTY DAMAGE. THIS SITUATION WILL VOID ANY WARRANTY.
12
11
10
9
1
3
4
5
6
7
8
3.2 CONTROL PANEL DESCRIPTIO N
The Benchmark 1.5 Control Panel shown in Figure 3-1 contains all of the controls, indicators and displays necessary to operate, adjust and troubleshoot the Benchmark 1.5 Boiler. These operating controls, indicators and displays are listed and described in Table 3-1. Additional information on these items are provided in the individual operating procedures provided in this Chapter.
Figure 3-1.
Control Panel Front View
3-1
Page 24
CONTROL PANEL OPERATING PROCEDURES
Table 3-1 Operating Controls, Indicators and Displays
ITEM
NO.
CONTROL, INDICATOR
OR DISPLAY
1 LED Status Indicators Four Status LEDs indicate the current operating status as
follows:
COMM
MANUAL
REMOTE
DEMAND
OUTLET
2
TEMPERATURE
Display
3 VFD Display Vacuum Fluorescent Display (VFD) consists of 2 lines each
Lights when RS-232 communication is occurring
Lights when the unit is being controlled using the front panel keypad.
Lights when the unit is being controlled by an external signal from an Energy Management System
Lights when there is a demand for heat.
3–Digit, 7–Segment LED display continuously displays the
outlet water temperature. The °F or °C LED next to the
display lights to indicate whether the displayed temperature is
in degrees Fahrenheit or degrees Celsius. The °F or °C blinks
when operating in the Deadband Mode.
capable of displaying up to 16 alphanumeric characters. The information displayed includes:
Startup Messages
Fault Messages
FUNCTION
Operating Status Messages
Menu Selection
RS-232 Port
4
FAULT Indicator Red FAULT LED indicator lights when a boiler alarm
5
CLEAR Key Turns off the FAULT indicator and clears the alarm message
6
READY Indicator
7
ON/OFF Switch
8
LOW WATER LEVEL
9
TEST/RESET Switches
Port permits a Laptop Computer or External Modem to be connected to the unit’s Control Panel.
condition occurs. An alarm message will appear in the VFD.
if the alarm is no longer valid. Lockout type alarms will be latched and cannot be cleared by simply pressing this key. Troubleshooting may be required to clear these types of alarms.
Lights ON/OFF switch is set to ON and all Pre-Purge
conditions have been satisfied.
Enables and disables boiler operation.
Allows operator to test operation of the water level monitor.
Pressing TEST opens the water level probe circuit and
simulates a Low Water Level alarm.
Pressing RESET resets the water level monitor circuit. Pressing the CLEAR key (item 6) resets the display.
3-2
Page 25
CONTROL PANEL OPERATING PROCEDURES
Table 3-1 Operating Controls, Indicators and Displays – Continued
ITEM
NO.
10 MENU Keypad Consists of 6 keys which provide the following functions for
CONTROL, INDICATOR
OR DISPLAY
the Control Panel Menus:
MENU
BACK
▲ (UP) Arrow When in one of the main menu categories (Figure 3-2),
▼ (DOWN) Arrow When in one of the main menu categories (Figure 3-2),
CHANGE
Steps through the main menu categories shown in Figure 3-
2. The Menu categories wrap around in the order shown.
Allows you to go back to the previous menu level without changing any information. Continuously pressing this key will bring you back to the default status display in the VFD. Also, this key allows you to go back to the top of a main menu category.
pressing the arrow key will select the displayed menu
category. If the CHANGE key was pressed and the menu
item is flashing, pressing the arrow key will increment the selected setting.
pressing this key will select the displayed menu category. If
the CHANGE key was pressed and the menu item is
flashing, pressing the arrow key will decrement the selected setting.
Permits a setting to be changed (edited). When the
CHANGE key is pressed, the displayed menu item will begin
to flash. Pressing the or arrow key when the item is flashing will increment or decrement the displayed setting.
FUNCTION
11
12
ENTER
AUTO/MAN Switch
VALVE POSITION
Bargraph
Saves the modified menu settings in memory. The display will stop flashing.
This switch toggles the boiler between the Automatic and
Manual modes of operation. When in the Manual (MAN)
mode, the front panel controls are enabled and the
MANUAL status LED lights. When in the Automatic (AUTO) mode, the MANUAL status
LED will be off and the front panel controls disabled.
20 segment red LED bargraph continuously shows the Air/Fuel Valve position in 5% increments from 0 to 100%
3-3
Page 26
CONTROL PANEL OPERATING PROCEDURES
3.3 CONTROL PANEL MENUS
The Control Panel incorporates an extensive menu structure which permits the operator to set up, and configure the unit. The menu structure consists of five major menu categories which are applicable to this manual. These categories are shown in Figure 3-2. Each of the menus shown, contain options which permit operating parameters to be viewed or changed. The menus are protected by a password levels to prevent unauthorized use.
Prior to entering the correct password, the options contained in the Operation, Setup, Configuration and Tuning Menu categories can be viewed. However, with the exception of Internal Setpoint Temperature (Configuration Menu), none of the viewable menu options can be changed.
Once the valid level 1 password (159) is entered, the options listed in the Setup. Configuration and Tuning Menus can be viewed and changed, if desired. The Combustion Cal Menu is protected by the level 2 password which is used in Chapter 4 to perform combustion calibration prior to service use.
available menu options in the Top-Down sequence. Pressing the arrow key will display the options in the Bottom-Up sequence. The menu options will wrap­around after the first or last available option is reached.
6. To change the value or setting of a
displayed menu option, press the CHANGE
key. The displayed option will begin to flash. Press the or arrow key to scroll through the available menu option choices for the option to be changed. The menu option choices do not wrap around.
7. To select and store a changed menu item,
press the ENTER key.
3.3.1 Menu Processing Procedure
Accessing and initiating each menu and option is accomplished using the Menu Keys shown in Figure 3-1. Therefore, it is imperative that you be thoroughly familiar with the following basic steps before attempting to perform specific menu procedures.
1. The Control Panel will normally be in the Operating Menu and the VFD will display the current unit status. Pressing the or arrow key will display the other available data items in the Operating Menu.
2. Press the MENU key. The display will show
the Setup Menu, which is the next menu category shown in Figure 3-2. This menu contains the Password option which must be entered if other menu options will be changed.
3. Continue pressing the MENU key until the
desired menu is displayed.
4. With the desired menu displayed, press the or arrow key. The first option in the selected menu will be displayed.
5. Continue to press the or arrow key until the desired menu option is displayed. Pressing the arrow key will display the
3-4
Figure 3-2. Menu Structure
Page 27
CONTROL PANEL OPERATING PROCEDURES
NOTE
The following paragraphs provide brief descriptions of the options contained in each menu. Refer to Appendix A for detailed descriptions of each menu option. Refer to Appendix B for listings and descriptions of displayed startup, status and error messages.
3.4 OPERATING M ENU
The Operating Menu displays a number of key operating parameters for the unit as listed in Table 3-2. This menu is “Read-Only” and does not allow personnel to change or adjust any displayed items. Since this menu is “Read-Only”, it can be viewed at any time without entering a password. Pressing the arrow key to display the menu items in the order listed (Top-Down). Pressing the arrow key will display the menu items in reverse order (Bottom-Up).
3.5 SETUP MENU
The Setup Menu (Table 3-3) permits the operator to enter the unit password (159) which is required to change the menu options. To prevent unauthorized use, the password will time-out after 1 hour. Therefore, the correct password must be reentered when required. In addition to permitting password entries, the Setup Menu is also used to enter date and time, units of temperature measurements and entries required for external communication and control of the unit via the RS-232 port. A view-only software version display is also provided to indicate the current Control Box software version.
NOTE
The Outdoor Temp display item shown with an asterisk in Table 3-2 will not be displayed unless the Outdoor Sensor function has been enabled in the Configuration Menu (Table 3-4).
Table 3-2. Operating Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Status Message
Active Setpoint 40°F 240°F
AIR Temp -70°F 245°F
Outdoor Temp* -70°F 130°F
Valve Position In 0% 100% Valve
Position
Flame Strength 0% 100%
Run Cycles 0 999,999,999
Run Hours 0 999,999,999
Fault Log 0 19 0
3-5
Page 28
CONTROL PANEL OPERATING PROCEDURES
Table 3-3. Setup Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Passsword 0 9999 0
Language English English
Time 12:00 am 11:59 pm
Date 01/01/00 12/31/99
Unit of Temp Fahrenheit or Celsius Fahrenheit
Comm Address 0 127 0
Baud Rate 2400, 4800, 9600, 19.2K 9600
Software Ver 0.00 Ver 9.99
3.6 CONFIGURATION MENU
The Configuration Menu shown in Table 3-4 permits adjustment of the Internal Setpoint (Setpt) temperature regardless of whether the valid password has been entered. Setpt is required for operation in the Constant Setpoint mode. The remaining options in this menu require the valid password to be entered, prior to changing existing entries. This menu contains a number of other configuration settings which may or may not be displayed, depending on the current operating mode setting.
Table 3-4. Configuration Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Internal Setpt Lo Temp Limit Hi Temp Limit 130°F
Unit Type KC Boiler, KC Boiler LN,
BMK Boiler, BMK Boiler LN,
BMK Boiler Dual, KC Water
Heater, KC Water Heater LN,
Water Heater 2010
Unit Size 0.5 MBTU, 1.0 MBTU
1.5 MBTU, 2.0 MBTU
3.0 MBTU, 3.5 MBTU
4.0 MBTU, 5.0 MBTU
Fuel Type Natural Gas, Propane Natural Gas
Boiler Mode Constant Setpoint,
Remote Setpoint,
Combination
Outdoor Reset
NOTE
The Configuration Menu settings shown in Table 3-4 are Factory-Set in accordance with the requirements specified for each individual order. Therefore, under normal operating conditions, no changes will be required.
BMK Boiler
LN
1.5 MBTU
6.0 MBTU
Constant
Setpoint
Direct Drive
3-6
Page 29
CONTROL PANEL OPERATING PROCEDURES
Table 3-4. Configuration Menu - Continued
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Remote Signal (If Mode = Remote Setpoint, Direct Drive or Combination)
Bldg Ref Temp (If Mode = Outdoor Reset)
Reset Ratio (If Mode = Outdoor Reset)
Outdoor Sensor Enabled or Disabled Disabled
System Start Tmp (If Outdoor Sensor = Enabled)
Setpt Lo Limit 40°F Setpt Hi Limit 60°F
Setpt Hi Limit Setpt Lo Limit 220°F 200°F
Temp Hi Limit 40°F 240°F 210°F
Max Valve Position 40% 100% 100%
Pump Delay Timer 0 min. 30 min. 0 min.
Aux Start On Dly 0 sec. 120 sec. 0 sec.
Failsafe Mode Shutdown or Constant Setpt Shutdown
4 – 20 mA/1 – 5V
0 -20 mA/0 – 5V
PWM Input (BMS)
Network
40°F 230°F 70°F
0.1 9.9 1.2
30°F 100°F 60°F
4 – 20 mA,
1-5V
*Analog Output
(See CAUTION at end of Table 3-4 )
Low Fire Timer 2 sec. 600 sec. 2 sec.
Setpt Limiting Enabled or Disabled Disabled
Setpt Limit Band 0°F 10°F 5°F
Network Timeout 5 Sec 999 Sec 30 Sec
HI DB Setpt EN 0% 100% 30%
Demand Offsert 0 25 10
Deadband High 0 25 2
Deadband Low 0 25 2
*CAUTION:
DO NOT CHANGE the Analog Output Menu Item from its Default setting (Valve Position 0-10V).
Off, Setpoint, Outlet Temp,
Valve Position 4-20 mA,
Valve Position 0-10V
*Valve
Position
0-10V
3-7
Page 30
CONTROL PANEL OPERATING PROCEDURES
3.7 TUNING MENU
The Tuning Menu items in Table 3-5 are Factory set for each individual unit. Do not change these menu entries unless specifically requested to do so by Factory-Trained personnel.
3.8 COMBUSTIO N CAL MENU
The Combustion Cal (Calibration) Menu items in Table 3-6 are used to vary the speed of the unit’s blower motor based on air temperature and air density at prescribed Air/Fuel Valve
Table 3-5. Tuning Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Prop Band 1°F 120°F 70°F
Integral Gain 0.00 2.00 1.00
Derivative Time 0.0 min 2.00 min 0.00 min
Reset Defaults? Yes, No, Are You Sure? No
Table 3-6. Combustion Cal Menu
positions (% open). This is accomplished by providing a DC drive voltage to the motor which adjusts the rotational speed of the blower to maximize combustion efficiency and ensure the unit conforms to the Nitrogen Oxide (NOx) and Carbon Monoxide (CO) emissions specified in Chapter 4. The valve positions (%) and default drive voltages are listed in Table 3-6.
Available Choices or Limits
Menu Item Display Minimum Maximum Default
CAL Voltage 16% .25 8.20 1.80v
CAL Voltage 30% .25 8.20 3.20v
CAL Voltage 45% .25 8.20 3.70v
CAL Voltage 60% .25 8.20 3.80
CAL Voltage 80% .25 8.20 4.60
CAL Voltage 100% .25 8.20 6.00
SET Valve Position 0% 100% 0%
Blower Output Monitor Blower Output Voltage .00
3.9 START SEQUENCE
When the Control Box ON/OFF switch is set to
the ON position, it checks all pre-purge safety switches to ensure they are closed. These switches include:
Safety Shut-Off Valve Proof of Closure
(POC) switch
Low Water Level switch
High Water Temperature switch
High Gas Pressure switch
Low Gas Pressure switch
Blower Proof switch
If all of the above switches are closed, the
READY light above the ON/OFF switch will light
and the unit will be in the Standby mode.
When there is a demand for heat, the following events will occur:
NOTE
If any of the Pre-Purge safety device switches are open, the appropriate fault message will be displayed. Also, the appropriate fault messages will be displayed throughout the start sequence, if the required conditions are not observed.
3-8
Page 31
CONTROL PANEL OPERATING PROCEDURES
1. The DEMAND LED status indicator will light.
2. The unit checks to ensure that the Proof of Closure (POC) switch in the downstream Safety Shut-Off Valve (SSOV) is closed. See Figure 3-3 for SSOV location.
MANUAL
SHUT-OFF
VALVE
TO
AIR/FUEL
VALVE
SSOV
GAS
INLET
Figure 3-3.
SSOV Location
3. With all required safety device switches closed, a purge cycle will be initiated and the following events will occur:
(b) The igniter relay is activated and
provides ignition spark.
(c) The gas Safety Shut-Off Valve (SSOV)
is energized (opened) allowing gas to flow into the Air/Fuel Valve.
Figure 3-4.
Air/Fuel Valve In Purge Position
(a) The Blower relay energizes and turns
on blower.
(b) The Air/Fuel Valve rotates to the full-
open purge position and closes purge position switch. The dial on the Air/Fuel Valve (Figure 3-4) will read 100 to indicate that it is full-open (100%).
(c) The VALVE POSITION bargraph will
show 100%.
4. Next, the blower proof switch on the Air/Fuel Valve (Figure 3-5) closes. The display will
show Purging and indicate the elapsed time
of the purge cycle in seconds. The normal (default) time for the purge cycle is 7 seconds.
5. Upon completion of the purge cycle, the Control Box initiates an ignition cycle and the following events occur:
(a) The Air/Fuel Valve rotates to the low-
fire ignition position and closes the ignition switch. The dial on the Air/Fuel Valve (Figure 3-6) will read between 25 and 35 to indicate that the valve is in the low-fire position.
Figure 3-5.
Blower Proof Switch
3-9
Page 32
CONTROL PANEL OPERATING PROCEDURES
8. With the unit firing properly, it will be controlled by the temperature controller
circuitry. The boiler’s VALVE POSIT ION will
be continuously displayed on the front panel bargraph.
Once the demand for heat has been satisfied, the Control Box will turn off the dual SSOV gas valves. The blower relay will be deactivated and
the Air/Fuel Valve will be closed. Standby will
be displayed.
3.10 START/STOP LEVELS
The start and stop levels are the Air/Fuel Valve positions (% open) that start and stop the unit, based on load. These levels are Factory preset as follows:
Figure 3-6.
Air/Fuel Valve In Ignition Position
6. Up to 7 seconds will be allowed for ignition to be detected. The igniter relay will be turned off one second after flame is detected.
7. After 2 seconds of continuous flame, Flame Proven will be displayed and the flame
strength will be indicated. After 5 seconds, the current date and time will be displayed in place of the flame strength.
Table 3-7.
Relationship Between Air/Fuel Valve Position and Energy Input For Unit Running On Natural Gas
Start Level: 20%
Stop Level: 16%
Normally, these settings should not require adjustment.
Note that the energy input of the boiler is not linearly related to the Air/Fuel Valve position. Refer to Table 3-7 for the relationship between the energy input and Air/Fuel Valve position for a unit running on natural gas.
3-10
Air/Fuel Valve
Position (% Open)
0% 0 0
10% 0 0
16%
(Stop Level)
20% 157,000 10%
30% 310,000 21%
40% 534,000 36%
50% 783,000 52%
60% 970,000 65%
70% 1,140,000 76%
80% 1,240,000 83%
90% 1,370,000 91%
100% 1,500,000 100%
Energy Input
(BTU/Hr)
75,000 5.0%
Boiler Energy Input (% of Full Capacity)
Page 33
CHAPTER 4 INITIAL START-UP
INITIAL START-UP
4.1 INITIAL START-UP REQUIREMENTS
The requirements for the initial start-up of the Benchmark 1.5 Boiler consists of the following:
Complete installation
Perform combustion calibration
Set proper controls and limits
Set up mode of operation (see Chapter 5)
Test safety devices (see Chapter 6)
Installation should be fully completed before performing initial start-up; and the start-up must be complete prior to putting the unit into service. Starting a unit without the proper piping, venting, or electrical systems can be dangerous and may void the product warranty. The following start-up instructions should be followed precisely in order to operate the unit safely and at a high thermal efficiency, with low flue gas emissions.
Initial unit start-up is to be performed ONLY by AERCO factory trained start-up and service personnel. After following the steps in this chapter, it will be necessary to perform the Mode of Operation settings in Chapter 5, and the Safety Device Testing procedures in Chapter 6 to complete the initial unit start-up.
An AERCO Gas Fired Startup Sheet, included with each Benchmark Boiler, must be completed for each unit for warranty validation and a copy must be returned promptly to AERCO at:
AERCO International, Inc.
159 Paris Ave. Northvale, NJ 07647
CAUTION
All applicable installation procedures in Chapter 2 must be completed before attempting to start the unit.
4.2 TOOLS AND INSTRUMENTATION FOR COMBUSTION CALIBRATION
To properly perform combustion calibration, the proper instruments and tools must be used and correctly attached to the unit. The following paragraphs outline the necessary tools and instrumentation as well as their installation.
4.2.1 Required Tools & Instrumentation
The following tools and instrumentation are necessary to perform combustion calibration of the unit:
Digital Combustion Analyzer: Oxygen accuracy to ± 0.4%; Carbon Monoxide (CO) and Nitrogen Oxide (NOx) resolution to 1PPM.
16 inch W.C. manometer or equivalent gauge and plastic tubing.
1/8 inch NPT-to-barbed fittings for use with gas supply manometer or gauge.
Small and large flat blade screwdrivers.
Tube of silicone adhesive
4.2.2 Installing Gas Supply Manometer
The gas supply manometer is installed in the gas train as follows:
1. Close the main manual gas supply shut-off valve upstream of the unit.
WARNING
DO NOT ATTEMPT TO DRY FIRE THE BOILER. STARTING THE UNIT WITHOUT A FULL WATER LEVEL CAN SERIOUSLY DAMAGE THE UNIT AND MAY RESULT IN INJURY TO PERSONNEL OR PROPERTY DAMAGE. THIS SITUATION WILL VOID ANY WARRANTY.
2. Remove the front door and left side panels from the boiler to access the gas train components.
3. Remove the 1/8 inch NPT pipe plug from the leak detection ball valve on the downstream side of the Safety Shut Off Valve (SSOV) No. 1 as shown in Figure 4-1.
4. Install a NPT-to-barbed fitting into the tapped plug port.
4-1
Page 34
INITIAL START-UP
5. Attach one end of the plastic tubing to the barbed fitting and the other end to the 16 inch W.C. manometer.
MANUAL
SHUT-OFF
VALVE
HIGH GAS
PRESSURE
SWITCH
TO
GAS
INLET
AIR/FUEL
VALVE
LEAK DETECTION BALL VALVE
SSOV
MANOMETER HERE)
1/8" NPT PLUG
(INSTALL
LOW GAS
PRESSURE
SWITCH
Figure 4-1.
1/8 Inch Gas Plug Location
4.2.3 Accessing the Vent Probe Port
The unit contains NPT plug on the exhaust manifold at the rear of the unit as shown in Figure 4-2. Prepare the port for the combustion analyzer probe as follows:
1. Remove the plug from the probe port on the right side of the exhaust manifold.
left or
2. If necessary, adjust the stop on the
combustion analyzer probe so that it will extend mid-way into the flue gas flow. DO NOT install the probe at this time.
UNIT
CONDENSATE DRAIN
CONNECTION
EXHAUST
MANIFOLD
VENT PROBE
PORT
PARTIAL TOP VIEW
FRAME
Figure 4.2
Analyzer Probe Hole Location
4.3 NATURAL GAS COMBUSTION CALIBRATION
The Benchmark 1.5LN Boiler is combustion calibrated at the factory prior to shipping. However, recalibration as part of initial start-up is necessary due to changes in the local altitude, gas BTU content, gas supply piping and supply regulators. Factory Test Data sheets are shipped with each unit. These sheets must be filled out and returned to AERCO for proper Warranty Validation.
It is important to perform the following procedure as outlined. This will keep readjustments to a minimum and provide optimum performance.
1. Open the water supply and return valves to the unit and ensure that the system pumps are running.
2. Open the natural gas supply valve(s) to the unit.
3. Set the control panel ON/OFF switch to the OFF position.
4. Turn on external AC power to the unit. The
display will show LOSS OF POWER and the
time and date.
5. Set the unit to the Manual Mode by pressing
the AUTO/MAN key. A flashing Manual Valve Position message will be displayed with the present rate in %. Also, the MANUAL LED will light.
6. Adjust the air/fuel valve position to 0% by pressing the arrow key.
7. Ensure that the leak detection ball valve down-stream of the SSOV is open.
8. Set the ON/OFF switch to the ON position.
9. Change the valve position to 29% using the arrow key. The unit should begin its start sequence and fire.
10. Next, verify that the gas pressure downstream of the SSOV is 3” W.C. for both FM and IRI gas trains. If gas pressure adjustment is required, remove the brass hex nut on the downstream SSOV actuator (IRI gas train) to access the gas pressure adjustment screw (Figure 4-3). Make gas pressure adjustments using a flat-tip screwdriver to obtain 3” W.C.
4-2
Page 35
INITIAL START-UP
BRASS HEX
HEAD CAP
(REMOVE TO
ACCESS GAS
PRESSURE
ADJUSTMENT
SCREW)
TYPICAL SSOV ACTUATOR WITH REGULATOR
Figure 4-3
Gas Pressure Adjustment Screw
Location
11. Increase the valve open position to 100% and verify that the gas pressure downstream of the SSOV remains at 3” W.C. Readjust pressure if necessary.
12. With the valve position at 100%, insert the combustion analyzer probe into the flue probe opening and allow enough time for the combustion analyzer to settle.
13. Compare the measured oxygen level to the oxygen range for the inlet air temperature shown in Table 4-1. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Table 4-1
Combustion Oxygen Levels for a 100%
Air/Fuel Valve Position
Inlet Air
Temp
>100°F 4.8 % <100 ppm <30 ppm
90°F 5.0 % <100 ppm <30 ppm 80°F 5.2 % <100 ppm <30 ppm
<70°F 5.3 % <100 ppm <30 ppm
14. If necessary, adjust the iris air damper shown in Figure 4-4 until the oxygen level is within the range specified in Table 4-1.
Oxygen %
± 0.2
Carbon
Monoxide NOx
15. Once the oxygen level is within the specified range at 100%, lower the valve position to 80%.
AIR/FUEL
VALVE
AIR INLET
A
A
IRIS AIR
DAMPER
FRONT
USE 1/2" WRENCH TO INCREASE (CW) OR DECREASE (CCW) INLET AIR
IRIS ADJUSTMENT
VIEW A - A
Figure 4-4
Iris Air Damper Location/Adjustment
NOTE
The remaining combustion calibration steps are performed using the
Combustion Cal Menu included in the C-
More Control System. The combustion calibration control functions will be used to adjust the oxygen level (%) at air/fuel valve positions of 80%, 60%, 45%, 30% and 16% as described in the following steps. These steps assume that the inlet air temperature is within the range of 50°F to 100°F.
16. Press the MENU Key on the front panel of the C-MORE and access the Setup menu.
Enter password 6817 and then press the
ENTER key.
17. Press the MENU Key on the front panel of the C-MORE until Combustion Cal Menu
appears on the C-More display.
18. Press the arrow key until SET Valve Position appears on the C-MORE display.
4-3
Page 36
INITIAL START-UP
19. Press the CHANGE key. SET Valve Position
will begin to flash.
20. Press the arrow key until the SET Valve Position reads 80%. Press the ENTER key.
21. Next, press the
CAL Voltage 80% is displayed.
down (▼) arrow key until
22. Press the CHANGE key and observe that CAL Voltage 80% is flashing.
23. The oxygen level at the 80% valve position should be as shown below. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Combustion Oxygen Level at
80% Valve Position
Oxygen %
± 0.2
6.0 % <100 ppm <30 ppm
24. If the oxygen level is not within the specified range, adjust the level using the and arrow keys. This will adjust the output voltage to the blower motor as indicated on the display. Pressing the arrow key increases the oxygen level and pressing the down arrow key decreases the oxygen level.
25. Once the oxygen level is within the specified
range at 80%, press the ENTER key to store
the selected blower output voltage for the 80% valve position.
Carbon
Monoxide
NOx
NOTE
The remaining steps basically repeat the procedures in steps 18 through 25 for valve positions of 60%, 45%, 30% and 16%. However, since oxygen levels vary, these steps are repeated in their entirety. When performing these steps, also ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown for each valve position.
26. Press the arrow key until SET Valve Position appears on the C-MORE display.
27. Press the CHANGE key. SET Valve Position
will begin to flash.
28. Press the arrow key until the SET Valve Position reads 60% and press the ENTER
key.
29. Press the
Voltage 60% is displayed.
down arrow key until CAL
30. Press the CHANGE key. CAL Voltage 60%
will begin to flash.
31. The oxygen level at the 60% valve position should be as shown below. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Combustion Oxygen Level at
60% Valve Position
Oxygen %
± 0.2
6.3 % <50 ppm <30 ppm
32. If the oxygen level is not within the specified range, adjust the level using the and arrow keys. This will adjust the output voltage to the blower motor as indicated on the display. Pressing the arrow key increases the oxygen level and pressing the arrow key decreases the oxygen level.
33. Once the oxygen level is within the specified
range at 60%, press the ENTER key to store
the selected blower output voltage for the 60% valve position.
34. Press the arrow key until SET Valve Position appears on the C-MORE display.
35. Press the CHANGE key. SET Valve Position
will begin to flash.
36. Press the arrow key until the SET Valve Position reads 45%, then press the ENTER
key.
37. Press the
▼ arrow key until CAL Voltage
45% is displayed.
38. Press the CHANGE key. CAL Voltage 45%
will begin to flash.
39. The oxygen level at the 45% valve position should be as shown below. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Carbon
Monoxide
NOx
Combustion Oxygen Level at
45% Valve Position
Oxygen %
± 0.2
7.0 % <50 ppm <30 ppm
Carbon
Monoxide
NOx
4-4
Page 37
INITIAL START-UP
40. If the oxygen level is not within the specified range, adjust the level using the and arrow keys. This will adjust the output voltage to the blower motor as indicated on the display. Pressing the arrow key increases the oxygen level and pressing the arrow key decreases the oxygen level.
41. Once the oxygen level is within the specified
range at 45%, press the ENTER key to store
the selected blower output voltage for the 45% valve position.
42. Press the arrow key until SET Valve Position appears on the C-MORE display.
43. Press the CHANGE key. SET Valve Position
will begin to flash.
44. Press the arrow key until the SET Valve Position reads 30%, then press the ENTER
key.
45. Press the
30% is displayed.
▼ arrow key until CAL Voltage
46. Press the CHANGE key. CAL Voltage 30%
will begin to flash.
47. The oxygen level at the 30% valve position should be as shown below. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Combustion Oxygen Level at
30% Valve Position
Oxygen %
± 0.2
7.0 % <50 ppm <30 ppm
48. If the oxygen level is not within the specified range, adjust the level using the and arrow keys. This will adjust the output voltage to the blower motor as indicated on the display. Pressing the arrow key increases the oxygen level and pressing the arrow key decreases the oxygen level.
49. Once the oxygen level is within the specified
range at 30%, press the ENTER key to store
the selected blower output voltage for the 30% valve position.
50. Press the arrow key until SET Valve Position appears on the C-MORE display.
51. Press the CHANGE key. SET Valve Position
will begin to flash.
Carbon
Monoxide
NOx
53. Press the
16% is displayed.
▼ arrow key until CAL Voltage
54. Press the CHANGE key. CAL Voltage 16%
will begin to flash.
55. The oxygen level at the 16% valve position should be as shown below. Also, ensure that the carbon monoxide (CO) and nitrogen oxide (NOx) readings do not exceed the values shown.
Combustion Oxygen Level at
16% Valve Position
Oxygen %
± 0.2
8.0 % <50 ppm <30 ppm
56. If the oxygen level is not within the specified range, adjust the level using the and arrow keys. This will adjust the output voltage to the blower motor as indicated on the display. Pressing the arrow key increases the oxygen level and pressing the arrow key decreases the oxygen level.
57. Once the oxygen level is within the specified
range at 16%, press the ENTER key to store
the selected blower output voltage for the 16% valve position.
58. This completes the natural gas combustion calibration procedure.
Carbon
Monoxide
NOx
4.4 UNIT REASSEMBLY
Once the combustion calibration adjustments are properly set, the unit can be reassembled for service operation.
1. Set the ON/OFF switch in the OFF position.
2. Disconnect AC power from the unit.
3. Shut off the gas supply to the unit.
4. Remove the manometer and barbed fittings and reinstall the NPT plug using a suitable pipe thread compound.
5. Remove the combustion analyzer probe from the vent hole. Replace the NPT plug in the vent hole using a suitable pipe joint compound.
6. Replace the unit’s side panels and front door.
52. Press the arrow key until the SET Valve Position reads 16%, then press the ENTER
key.
4-5
Page 38
INITIAL START-UP
4.5 OVER- TEMPER ATURE LIMIT
SWITCHES
The unit contains both automatic and manual reset over-temperature limit switches. These switches are mounted on a plate next to the VFD as shown in Figure 4-6. The switches can be accessed by opening the front panel door of the unit. The manual reset switch is not adjustable and is permanently fixed at 210°F. This switch will shut down and lock out the boiler if the water temperature exceeds 210°F. Following an over-temperature condition, it must be manually reset by pressing the RESET button before the boiler can be restarted. The automatic reset over-temperature switch is adjustable and allows the boiler to restart, once the temperature drops below its temperature setting. Set the automatic over-temperature switch to the desired setting.
4-6
Figure 4-6
Over Temperature Limit Switch
Locations
Page 39
MODE OF OPERATION
CHAPTER 5 MODE OF OPERATION
5.1 INTRODUCTION
The boiler is capable of being operated in any one of six different modes. The following paragraphs in this Chapter provide descriptions of each of these operating modes. Each boiler is shipped from the factory tested and configured for the ordered mode of operation. All temperature related parameters are at their factory default values which work well in most applications. However, it may be necessary to change certain parameters to customize the unit to the system environment. A complete listing and descriptions of the temperature related parameters are included in Appendix A. Factory defaults are listed in Appendix E. After reading this chapter, parameters can be customized to suit the needs of the specific application.
5.2 INDOOR/OUTDOOR RESET MODE
This mode of operation is based on outside air temperatures. As the outside air temperature decreases, the supply header temperature will increase and vice versa. For this mode, it is necessary to install an outside air sensor as well as select a building reference temperature and a reset ratio.
5.2.3 Outdoor Air Temperature Sensor Installation
The outdoor air temperature sensor must be mounted on the North side of the building in an area where the average outside air temperature is expected. The sensor must be shielded from the sun's direct rays, as well as direct impingement by the elements. If a cover or shield is used, it must allow free air circulation. The sensor may be mounted up to two hundred feet from the unit. Sensor connections are made at the Input/Output (I/O) Box on the front of the boiler. Connections are made at the terminals labeled OUTDOOR SENSOR IN and SENSOR COMMON inside the I/O Box. Use shielded 18 to 22 AWG wire for connections. A wiring diagram is provided on the cover of the I/O Box. Refer to Chapter 2, paragraph 2.9.1 for additional wiring information.
5.2.4 Indoor/ Outdoor Startup
Startup in the Indoor/Outdoor Reset Mode is accomplished as follows:
1. Refer to the Indoor/Outdoor reset ratio charts in Appendix D.
5.2.1 Reset Ratio
Reset ratio is an adjustable number from 0.1 to
9.9. Once adjusted, the supply header temperature will increase by that number for each degree that the outside air temperature decreases. For instance, if a reset ratio of 1.6 is used, for each degree that outside air temperature decreases the supply header temperature will increase by 1.6 degrees.
5.2.2 Building Reference Temperature
This is a temperature from 40°F to 230°F. Once selected, it is the temperature that the system references to begin increasing its temperature. For instance, if a reset ratio of 1.6 is used, and we select a building reference temperature of 70°F, then at an outside temperature of 69°F, the supply header temperature will increase by
1.6° to 71.6°F.
2. Choose the chart corresponding to the desired Building Reference Temperature.
3. Go down the left column of the chart to the coldest design outdoor air temperature expected in your area.
NOTE
A design engineer typically provides design outdoor air temperature and
header temperature data
supply
4. Once the design outdoor air temperature is chosen, go across the chart to the desired supply header temperature for the design temperature chosen in step 3.
5. Next, go up that column to the Reset Ratio row to find the corresponding reset ratio.
6. Access the Configuration Menu and scroll
through it until the display shows Bldg Ref Temp. (Building Reference Temperature).
5-1
Page 40
MODE OF OPERATION
7. Press the CHANGE key. The display will begin to flash.
8. Use the ▲ and ▼ arrow keys to select the desired Building Reference Temperature.
9. Press ENTER to save any changes.
10. Next, scroll through the Configuration Menu
until the display shows Reset Ratio.
11. Press the CHANGE key. The display will begin to flash.
12. Use the and arrow keys to select the Reset Ratio determined in step 5.
13. Press ENTER to save the change.
Refer to paragraph 3.3 for detailed instructions on menu changing.
5.3 CONSTANT SETPOINT MODE
The Constant Setpoint mode is used when a fixed header temperature is desired. Common uses of this mode of operation include water source heat pump loops, and indirect heat exchangers for potable hot water systems or processes.
5.4 REMOTE SETPOINT MODES
The unit’s setpoint can be remotely controlled by an Energy Management System (EMS) or Building Automation System (BAS). The Remote Setpoint can be driven by a current or voltage signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Remote Setpoint mode is 4 - 20 mA/1 - 5 Vdc. With this setting, a 4 to 20 mA/1 to 5 Vdc signal, sent by an EMS or BAS, is used to change the unit's setpoint. The 4 mA/1V signal is equal to a 40°F setpoint while a 20 mA /5V signal is equal to a 240°F setpoint. When a 0 to 20 mA/0 to 5 Vdc signal is used, 0 mA is equal to a 40°F setpoint.
In addition to the current and voltage signals described above, the Remote Setpoint mode can also driven by a RS485 Modbus Network signal from an EMS or BAS.
The Remote Setpoint modes of operation can be used to drive single as well as multiple units.
No external sensors are required to operate in this mode. While it is necessary to set the desired setpoint temperature, it is not necessary to change any other temperature-related functions. The unit is factory preset with settings that work well in most applications. Prior to changing any temperature-related parameters, other than the setpoint, it is suggested that an AERCO representative be contacted. For descriptions of temperature-related functions and their factory defaults, see Appendices A and E.
5.3.1 Setting the Setpoint
The setpoint temperature of the unit is adjustable from 40°F to 240°F. To set the unit for operation in the Constant Setpoint Mode, the following menu settings must be made in the Configuration Menu:
MENU OPTION SETTING
Boiler Mode Constant Setpoint
Internal Setpt Select desired setpoint
using and arrow keys (40°F to 240°F)
NOTE
If a voltage, rather than current signal is used to control the remote setpoint, a DIP switch adjustment must be made on the CPU Board located in the Control Panel Assembly. Contact your local AERCO representative for details.
In order to enable the Remote Setpoint Mode, the following menu setting must be made in the Configuration Menu:
MENU OPTION SETTING
Boiler Mode Remote Setpoint
Remote Signal 4-20mA/1-5V,
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for detailed instructions on changing menu options.
Refer to paragraph 3.3 for detailed instructions on changing menu options.
5-2
Page 41
MODE OF OPERATION
If the Network setting is selected for RS485 Modbus operation, a valid Comm Address must be entered in the Setup Menu. Refer to Modbus Communication Manual GF-114 for additional information.
While it is possible to change the settings of temperature related functions, the unit is factory preset with settings that work well in most applications. It is suggested that an AERCO representative be contacted, prior to changing any temperature related function settings. For descriptions of temperature-related functions and their factory defaults, refer to Appendices A and E.
5.4.1 Remote Setpoint Field Wiring
The only wiring connections necessary for the Remote Setpoint mode are connection of the remote signal leads from the source to the unit’s I/O Box. The I/O Box is located on the front panel of the boiler. For either a 4-20mA/0-5V or a 0-20mA/0-5V setting, the connections are made at the ANALOG IN terminals in the I/O Box. For a Network setting, the connections are made at the RS-485 COMM terminals in the I/O Box. The signal must be floating, (ungrounded) at the I/O Box and the wire used must be a two wire shielded pair from 18 to 22 AWG. Polarity must be observed. The source end of the shield must be connected at the source. When driving multiple units, each unit’s wiring must conform to the above.
5.4.2 Remote Setpoint Startup
Since this mode of operation is factory preset and the setpoint is being externally controlled,
no startup instructions are necessary. In this
mode, the REMOTE LED will light when the external signal is present.
To operate the unit in the Manual mode, press the AUTO/MAN switch. The REMOTE LED will go off and the MANUAL LED will light.
To change back to the Remote Setpoint mode, simply press the AUTO/MAN switch. The REMOTE LED will again light and the MANUAL LED will go off.
5.5 DIRECT DRIVE MODES
The unit’s air/fuel valve position (% open) can be changed by a remote signal which is typically sent from an Energy Management System (EMS) or from a Building Automation System (BAS). The Direct Drive mode can be driven by a current or voltage signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Direct Drive mode is 4-20 mA/1-5 Vdc. With this setting, a 4 to 20 mA signal, sent by an EMS or BAS is used to change the unit’s valve position from 0% to 100%. A 4 mA/1V signal is equal to a 0% valve position, while a 20 mA /5V signal is equal to a 100% valve position. When a 0-20 mA/0-5 Vdc signal is used, zero is equal to a 0% valve position.
In addition to the current and voltage signals described above, the Direct Drive mode can also driven by a RS485 Modbus Network signal from an EMS or BAS.
When in a Direct Drive mode, the unit is a slave to the EMS or BAS and does not have a role in temperature control. Direct Drive can be used to drive single, or multiple units.
NOTE
If a voltage, rather than current signal is used to control the remote setpoint, a DIP switch adjustment must be made on the CPU Board located in the Control Box Assembly. Contact your local AERCO representative for details.
To enable the Direct Drive Mode, the following menu setting must be made in the Configuration Menu:
MENU OPTION SETTING
Boiler Mode Direct Drive
Remote Signal 4-20mA/1-5V,
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for instructions on changing menu options.
5-3
Page 42
MODE OF OPERATION
If the Network setting is selected for RS485 Modbus operation, a valid Comm Address must be entered in the Setup Menu. Refer to Modbus Communication Manual GF-114 for additional information.
5.5.1 Direct Drive Field Wiring
The only wiring connections necessary for Direct Drive mode are connection of the remote signal leads from the source to the unit’s I/O Box. For either a 4-20mA/0-5V or a 0-20mA/0-5V setting, the connections are made at the ANALOG IN terminals in the I/O Box. For a Network setting, the connections are made at the RS-485 COMM terminals in the I/O Box. The signal must be floating, (ungrounded) at the I/O Box and the wire used must be a two wire shielded pair from 18 to 22 AWG. Polarity must be observed. The source end of the shield must be connected at the source. When driving multiple units, each unit’s wiring must conform to the above.
5.5.2 Direct Drive Startup
Since this mode of operation is factory preset and the valve position is being externally
controlled, no startup instructions are necessary.
In this mode, the REMOTE LED will light when the signal is present.
To operate the unit in manual mode, press the AUTO/MAN switch. The REMOTE LED will go off and the MANUAL LED will light.
To change back to the Direct Drive mode, simply press the AUTO/MAN switch. The REMOTE LED will again light and the MANUAL LED will go off.
5.6 BOILER MANAGEMENT SYSTEM
(BMS)
NOTE
BMS Model 168 can utilize either pulse width modulation (PWM) or RS485 Modbus signaling to the Boiler. BMS II Model 5R5-384 can utilize only RS485 signaling to the Boiler.
The BMS mode of operation is used in conjunction with an AERCO Boiler Management System. The BMS mode is used when it is desired to operate multiple units in the most efficient manner possible. For this mode of operation, a BMS Header Sensor must be installed between 2 and 10 feet downstream of the LAST boiler in the boiler plant's supply water
header. The BMS can control up to 40 boilers; 8 via pulse width modulation (PWM) and up to 32 via Modbus (RS485) network communication. For BMS programming, operation, and Header Sensor installation details, see GF-108M (BMS Model 168) and GF-124 (BMS II Model 5R5-
384), BMS Operations Guides. For operation via an RS485 Modbus network, refer to Modbus Communication Manual GF-114.
To enable the BMS Mode, the following menu settings must be made in the Configuration Menu:
MENU OPTION SETTING
Boiler Mode Direct Drive
Remote Signal BMS (PWM Input)
or Network (RS485)
Refer to paragraph 3.3 for instructions on changing menu options.
5.6.1 BMS External Field Wiring
Wiring connections for BMS control using PWM signaling are made between connector JP2 on the BMS panel (boilers 1 through 8), and the B.M.S. (PWM) IN terminals in the I/O Box on the front of the boilers. Refer to the wiring diagram provided on the cover of the I/O Box.
Wiring connections for RS485 Modbus control are made between connector JP11 on the BMS (boilers 9 through 40) and the RS485 COMM terminals in the I/O Box on the front of the boilers.
Wire the units using shielded twisted pair wire between 18 and 22 AWG. Observe the proper polarity for the B.M.S. (PWM) IN and/or RS485 COMM wiring connections. Shields should be terminated only at the BMS and the boiler end must be left floating. Each unit’s wiring must conform to the above.
5.6.2 BMS Setup and Startup
This mode of operation is factory preset and the AERCO BMS controls the firing rate (air/fuel valve % open position). There are no setup instructions for each individual unit.
To operate the unit in manual mode, press the AUTO/MAN switch. The REMOTE LED will go off and the MANUAL LED will light
5-4
Page 43
MODE OF OPERATION
To change back to the BMS mode, simply press the AUTO/MAN switch. The REMOTE LED will again light and the MANUAL LED will go off.
5.7 COMBINATION CONTROL SYSTEM
(CCS)
NOTE
Only BMS Model 168 can be utilized for the Combination Mode, not the BMS II (Model 5R5-384).
A Combination Control System (CCS) is one that uses multiple boilers to cover both space­heating and domestic hot water needs. An AERCO Boiler Management System (BMS) Model 168 and a Combination Control Panel (CCP) are necessary to configure this system. Typically, an adequate number of boilers are installed to cover the space-heating load on the design day, however one or more units are used for the domestic hot water load.
The theory behind this type of system is that the maximum space-heating load and the maximum domestic hot water load do not occur simul­taneously.+ Therefore, boilers used for the domestic hot water are capable of switching between constant setpoint and BMS modes of operation. These boilers are the combination units and are referred to as the combo boilers. The combo boilers heat water to a constant setpoint temperature. That water is then circulated through a heat exchanger in a domestic hot water storage tank.
When the space-heating load is such that all the space-heating boilers are at the 100% valve position, the BMS will then ask the Combination Control Panel for the domestic boilers to become space-heating boilers. Provided the domestic hot water load is satisfied, the combo (hot water) boilers will then become space­heating boilers. If the domestic hot water load is not satisfied, the combo boiler(s) remain on the domestic hot water load. If the combo boilers switch over to space heating, but there is a call for domestic hot water, the CCP switches the combo units back to the domestic load.
When the combo units are satisfying the domestic load they are in constant setpoint mode of operation. When the combo units switch over to space heating, their mode of operation changes to the BMS mode. For more information concerning the operation of the
Combination Control Panel see the AERCO CCP-1 literature.
5.7.1 Combination Control System Field Wiring
Wiring for this system is between the BMS Model 168 panel, the CCP and the B.M.S. (PWM) IN terminals in the I/O Box. Wire the units using a shielded twisted pair of 18 to 22 AWG wire. When wiring multiple units, each unit’s wiring must conform to the above. For a complete CCP system-wiring diagram see the AERCO CCP-1 literature.
5.7.2 Combination Control System Setup and Startup
Setup for the Combination Mode requires entries to be made in the Configuration Menu for boiler mode, remote signal type and setpoint. The setpoint is adjustable from 40°F to 240°F.
Enter the following settings in the Configuration Menu:
MENU OPTION SETTING
Boiler Mode Combination
Remote Signal BMS (PWM Input)
Internal Setpt 40°F to 240°F
Refer to paragraph 3.3 for instructions on changing menu options.
While it is possible to change other temperature­related functions for combination mode, thes functions are preset to their factory default values. These default settings work well in most applications. It is suggested that AERCO be contacted prior to changing settings other than the unit’s setpoint. For a complete listing of temperature related function defaults, see Appendix E.
To set the unit to the manual mode, press the AUTO/MAN switch. The MANUAL LED will light.
To set the unit back to the auto mode, press the AUTO/MAN switch. The MANUAL LED will go off and the REMOTE LED will light.
When the boiler is switched to BMS mode, the AERCO BMS controls the valve position. There are no setup requirements to the boiler(s) in this mode.
5-5
Page 44
Page 45
SAFETY DEVICE TESTING
CHAPTER 6 SAFETY DEVICE TESTING
6.1 TESTING OF SAFETY DEVICES
Periodic safety device testing is required to ensure that the control system and safety devices are operating properly. The boiler control system comprehensively monitors all combustion-related safety devices before, during and after the start sequence. The following tests check to ensure that the system is operating as designed.
Operating controls and safety devices should be tested on a regular basis or following service or replacement. All testing must conform to local codes such as ASME CSD-1.
NOTE
MANUAL and AUTO modes of operation are required to perform the following tests. For a complete explanation of these modes, see Chapter 3.
NOTE
It will be necessary to remove the front door and side panels from the unit to perform the following tests.
4. Place the unit in Manual Mode and adjust the air/fuel valve position (% open) between 25 and 30%.
5. While the unit is firing, slowly external manual gas shut-off valve.
6. The unit should shut down and display a
LOW GAS PRESSURE fault message at approximately 2.6” W.C. The FAULT indi-
cator should also start flashing.
close the
WARNING
ELECTRICAL VOLTAGES IN THIS SYSTEM MAY INCLUDE 120 AND 24 VOLTS AC. POWER MUST BE RE­MOVED PRIOR TO PERFORMING WIRE REMOVAL OR OTHER TEST PROCEDURES THAT CAN RESULT IN ELECTRICAL SHOCK.
6.2 LOW GAS PRESSURE FAULT TEST
Refer to Figure 6-1 and ensure that the leak detection ball valve located at the high gas pressure switch is closed.
1. Remove the 1/8 “ plug from the ball valve at the low gas pressure switch shown in the lower portion of Figure 6-1.
2. Install a 0 – 16 “ W.C. manometer or a W.C. gauge where the 1/8" plug was removed.
3. Slowly open the ball valve near the low gas pressure switch.
Figure 6-1
Low & High Gas Pressure Testing
7. Fully open the external manual gas shut-off
valve and press the CLEAR button on the
Control Box.
8. The fault message should clear and the
FAULT indicator should go off. The unit
should restart.
9. Upon test completion, close the ball valve and remove the manometer. Replace the 1/8 “ plug removed in step 1.
6-1
Page 46
SAFETY DEVICE TESTING
6.3 HIGH GAS PRESSURE TEST
To simulate a high gas pressure fault, refer to Figure 6-1 and proceed as follows:
1. Remove the 1/8“ plug from the leak detection ball valve shown in Figure 6-1.
2. Install a 0 – 16” W.C. manometer (or W.C. gauge) where the 1/8” plug was removed.
3. Slowly open the leak detection ball valve
4. Start the unit in Manual mode at a valve position (firing rate) between 25 and 30%.
5. Slowly increase the gas pressure using the adjustment screw on the SSOV.
6. The unit should shut down and display a
HIGH GAS PRESSURE fault message
when the gas pressure exceeds 4.7” W.C.
The FAULT indicator should also start
flashing.
7. Reduce the gas pressure back to 3.0” W.C.
8. Press the CLEAR button on the Control Box
to clear the fault.
shut the unit off immediately and refer fault to qualified service personnel.
7. Close the drain and pressure relief valve used in draining the unit.
8. Open the water shut-off valve in the return piping to the unit.
9. Open the water supply shut-off valve to the unit to refill.
10. After the shell is full, press the LOW WATER LEVEL RESET button to reset the
low water cutoff.
11. Press the CL EAR button to reset the FAULT LED and clear the displayed error
message.
12. Set the ON/OFF switch to the ON position.
The unit is now ready for operation.
6.5 WATER TEMPERATURE FAULT
TEST
A high water temperature fault is simulated by adjusting the automatic over-temperature switch. This switch is accessible from the front of the unit as shown in Figure 6-2.
9. The fault message should clear and the
FAULT indicator should go off. The unit
should restart.
10. Upon test completion, close the ball valve and remove the manometer. Replace the 1/8“ plug removed in step 1.
6.4 LOW WATER LEVEL FAU LT TEST
To simulate a low water level fault:
1. Set the ON/OFF switch to the OFF position
2. Close the water shut-off valves in the supply and return piping to the unit.
3. Slowly open the drain valve on the rear of the unit. If necessary the unit’s relief valve may be opened to aid in draining.
4. Continue draining the unit until a LOW WATER LEVEL fault message is displayed and the FAULT indicator flashes.
5. Place the unit in the Manual Mode and raise the valve position above 30%.
1. Start the unit in the normal operating mode. Allow the unit to stabilize at its setpoint.
2. Lower the adjustable over-temperature switch setting to match the displayed OUTLET TEMPERATURE.
3. Once the adjustable over-temperature switch setting is approximately at, or just below, the actual outlet water temperature,
the unit should shut down. The FAULT indicator should start flashing and a HIGH WATER TEMP SWITCH OPEN fault
message should be displayed. It should not be possible to restart the unit.
4. Reset the adjustable over-temperature switch to its original setting.
5. The unit should start once the adjustable temperature limit switch setting is above the actual outlet water temperature.
6. Set the ON/OFF switch to the ON position. The READY light should remain off and the
unit should not start. If the unit does start,
6-2
Page 47
SAFETY DEVICE TESTING
6.6 INTERLOCK TESTS
The unit is equipped with two interlock circuits called the Remote Interlock and Delayed Interlock. Terminal connections for these circuits are located in the I/O Box (Figure 2-9) and are labeled REMOTE INTL’K IN and DELAYED INTL’K IN. These circuits can shut down the unit in the event that an interlock is opened. These interlocks are shipped from the factory jumpered (closed). However, each of these interlocks may be utilized in the field as a remote stop and start, an emergency cut-off, or to prove that a device such as a pump, gas booster, or louver is operational.
6.6.1 REMOTE INTERLOCK
1. Remove the cover from the I/O Box and locate the REMOTE INTL’K IN terminals.
2. Start the unit in the Manual Mode and set the valve position between 25% and 30%.
3. If there is a jumper across the REMOTE INTL’K IN terminals, remove one side of the jumper. If the interlock is being controlled by an external device, either open the interlock via the external device or disconnect one of the wires leading to the external device.
Figure 6-2
Temperature Limit Switch Setting
6. Once the adjustable over-temperature switch setting is approximately at, or just below, the actual outlet water temperature,
the unit should shut down. The FAULT indicator should start flashing and a HIGH WATER TEMP SWITCH OPEN fault
message should be displayed. It should not be possible to restart the unit.
7. Reset the adjustable over-temperature switch to its original setting.
8. The unit should start once the adjustable temperature limit switch setting is above the actual outlet water temperature.
4. The unit should shut down and display
INTERLOCK OPEN.
5. Once the interlock connection is
reconnected, the INTERLOCK OPEN
message should automatically clear and the unit should restart.
6.6.2 DELAYED INTERLOCK
1. Remove the cover from the I/O Box and locate the DELAYED INTL’K IN terminals.
2. Start the unit in the Manual Mode at a valve position between 25% and 30%.
3. If there is a jumper across the DELAYED INTL’K IN terminals, remove one side of the jumper. If the interlock is connected to a proving switch of an external device, disconnect one of the wires leading to the proving switch.
4. The unit should shut down and display a
DELAYED INTERLOCK OPEN fault message. The FAULT LED should be
flashing.
5. Reconnect the wire or jumper removed in step 3 to restore the interlock.
6-3
Page 48
SAFETY DEVICE TESTING
6. Press the CLEAR button to reset the fault
7. The unit should start.
6.7 FLAME FAULT TES TS
Flame faults can occur during ignition or while the unit is already running. To simulate each of these fault conditions, proceed as follows:
1. Set the ON/OFF switch to the OFF position.
2. Place the unit in the Manual Mode and set the valve position between 25% and 30%.
3. Close the manual gas shutoff valve located between the Safety Shut-Off Valve (SSOV) and the Air/Fuel Valve (see Figure 6-3).
4. Set the ON/OFF switch to the ON position to
start the unit.
5. The unit should shut down after reaching the
Ignition cycle and display FLAME LOSS
DURING IGN.
6. Open the valve previously closed in step 3
and press the CLEAR button.
Figure 6-3
Manual Gas Shut-Off Valve Location
6.8 AIR FLOW FAULT TESTS
These tests check the operation of the Blower Proof Switch and Blocked Inlet Switch shown in Figure 6-3.
7. Restart the unit and allow it to prove flame.
8. Once flame is proven, close the manual gas valve located between the SSOV (Figure 6-
3) and the Air/Fuel Valve.
9. The unit should shut down and execute an
IGNITION RETRY cycle by performing the
following steps:
(a) The unit will execute a shutdown purge
cycle for a period of 15 seconds and
display WAIT FAULT PURGE.
(b) The unit will execute a 30 second re-
ignition delay and display WAIT RETRY PAUSE.
(c) The unit will then execute a standard
ignition sequence and display WAIT IGNITION RETRY.
10. Since the manual gas shutoff valve is still closed, the unit will shut down and display
FLAME LOSS DURING IGNITION following the IGNITION RETRY cycle.
11. Open the valve previously closed in step 8.
12. Press the CLEAR button. The unit should
restart and fire.
1. Disable the blower output drive voltage as follows:
(a) Press the MENU key until CONFIGUR-
ATION MENU is displayed.
(b) Press the ▲ arrow key until the ANA-
LOG OUTPUT function is displayed, then press the CHANGE key.
(c) Press the ▼ arrow key until OFF is
displayed, then press the ENTER key.
2. Start the unit in the Manual Mode at a valve position between 25% and 30%.
3. The unit should shut down and execute an
IGNITION RETRY cycle by performing the
following steps:
(a) The unit will execute a 30 second re-
ignition delay and display WAIT RETRY PAUSE.
(b) The unit will then execute a standard
ignition sequence and display WAIT IGNITION RETRY.
4. The unit should perform two IGNITION RETRY cycles and then shut down on the
third successive ignition attempt. The unit
will display AIRFLOW FAULT DURING PURGE.
6-4
Page 49
SAFETY DEVICE TESTING
5. Re-enable the blower output drive voltage by performing the following steps:
(a) Press the MENU key until CONFIGUR-
ATION MENU is displayed.
(b) Press the ▲ arrow key until the ANA-
LOG OUTPUT function is displayed, then press the CHANGE key.
(c) Press the ▲ arrow key until VALVE
POSITION 0-10V is displayed, then press the ENTER key.
6. Once the unit has proved flame, turn off the blower by going to the Configuration Menu,
Analog Output menu item and select OFF.
7. The Blower Proof Switch will open and the blower should stop. The unit should shut
down and display AIRFLOW FAULT DURING RUN.
8. Go to the Configuration Menu, Analog
Output item and select VALVE POSITION 0­10v.
9. Press the CLEAR button. The unit should
restart.
10. Next, check the Blocked Inlet Switch by first noting the current position of the Iris Air Damper and then closing the Damper to position 8.
6. The unit should fault and display SSOV SWITCH OPEN.
7. Replace wire #148 and press the CLEAR
button.
8. Set the ON/OFF switch to ON to start the
unit.
9. Remove the wire again when the unit
reaches the purge cycle and PURGING is
displayed.
10. The unit should shut down and display
SSOV FAULT DURING PURGE.
11. Replace the wire on the SSOV and press
the CLEAR button. The unit should restart.
SSOV
ACTUATOR
COVER
ACTUATOR
COVER
SCREW
11. .The unit should shut down and again
display AIRFLOW FAULT DURING RUN.
12. Return the Iris Air Damper to its previous setting.
13. Press the CLEAR button. The unit should
restart.
6.9 SSOV PROOF OF CLOSURE SWITCH
The SSOV shown in Figure 6-1 contains the proof of closure switch. The proof of closure switch circuit is checked as follows:
1. Set the unit’s ON/OFF switch to the OFF
position.
2. Place the unit in Manual Mode and set the valve position between 25% and 30%
3. Refer to Figure 6-1 and locate the SSOV.
4. Remove the cover from the SSOV by loosening the screw shown in Figure 6-4. Lift off the cover to access the terminal wiring connections.
5. Disconnect wire #148 from the SSOV to “open” the proof of closure switch circuit.
Figure 6-4
SSOV Actuator Cover Location
6.10 PURGE SWITCH OPEN DURING PURGE
The Purge Switch (and Ignition Switch) is located on the Air/Fuel Valve. To check the switch, proceed as follows:
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and set the valve position between 25% and 30%.
2. Remove the Air/Fuel Valve cover by rotating the cover counterclockwise to unlock it and then lift up (see Figure 6-5).
3. Remove one of the two wires (#171 or #172) from the Purge Switch (Figure 6-6).
4. Initiate a unit start sequence.
6-5
Page 50
SAFETY DEVICE TESTING
5. The unit should begin it’s start sequence,
then shut down and display PRG SWITCH OPEN DURING PURGE.
6. Replace the wire on the Purge Switch and
depress the CLEAR button. The unit should
restart.
6.11 IGNITION SWITCH OPEN DURING IGNITION
The Ignition Switch (and the Purge Switch) is located on the Air/Fuel Valve. To check the switch, proceed as follows:
1. Set the unit’s ON/OFF switch to the OFF
position.
2. Place the unit in Manual Mode and set the valve position between 25% and 30%.
3. Remove the Air/Fuel Valve cover (Figure 6-5) by rotating the cover counterclockwise to unlock and lift up to remove.
4. Remove one of the two wires (#169 or #170) from the Ignition Switch (Figure 6-6).
5. Initiate a unit start sequence.
9
6
1
0
7
1
1
7
2
1
7
1
Figure 6-6
Air/Fuel Valve Purge and Ignition Switch
Locations
6. The unit should begin it’s start sequence
and then shut down and display IGN SWITCH OPEN DURING IGNITION.
7. Replace the wire on the Ignition Switch and
press the CLEAR button. The unit should
restart.
6.12 SAFETY PRESSURE RELIEF VALVE TEST
Test the safety Pressure Relief Valve in accordance with ASME Boiler and Pressure Vessel Code, Section VI.
6-6
AIR/FUEL VALVE COVER (ROTATE CCW TO REMOVE)
Figure 6-5
Air/Fuel Valve Cover Location
Page 51
MAINTENANCE
CHAPTER 7 MAINTENANCE
7.1 MAINTENANCE SCHEDULE
The unit requires regular routine maintena nce to keep up efficiency and reliability. For best operation and life of the unit, the following routine maintenance procedures should be performed in the tim e periods specified in Table 7-1. See Appendix I for a complete CSD-1 inspection check list.
In order to perform the maintenance tasks specified in Table 7-1, the following maintenance kits are available through your local AERCO Sales Representative:
Annual Maintenance Kit, Part No. 58025-01
24-Month Waterside/Fireside Inspection Kit,
Part No. 58025-05 (See NOTE below)
NOTE
The 24-Month W aterside/Fireside Inspec­tion Kit also includes the items contained in the Annual Maintenance Kit. Therefore, only Kit Part No. 58025-05 is required when performing the waterside/fireside inspections.
Appendix K contains recommended spare parts lists for maintenance of the boiler.
WARNING
TO AVOID PERSONAL INJURY, PRIOR TO SERVICING ENSURE THAT THE FOLLOWING GUIDE­LINES ARE STRICTLY OBSERVED:
DISCONNECT THE AC SUPPLY BY TURNING OFF THE SERVICE SWITCH AND AC SUPPLY CIRCUIT BREAKER.
SHUT OFF THE GAS SUPPLY AT THE MANUAL SHUT-OFF VALVE PROVIDED WITH THE UNIT
ALLOW THE UNIT TO COOL TO A SAFE WATER TEMPERATURE TO PREVENT BURNING OR SCALDING
Table 7-1 - Maintenance Schedule
PARAGRAPH ITEM 6 Mos. 12 Mos. 24 Mos.
7.2
7.3
7.4
7.5
Ignitor-Injector
(58023)
Flame Detector
(66006)
Combustion
Calibration
Testing of
Safety Devices
*Inspect Inspect Replace 15 mins. *Inspect Inspect Replace 15 mins.
*Check Check 1 hr.
See CSD-1
Chart in
20 mins.
Appendix I
7.6 Burner Inspect 2 hrs.
7.7
* Only performed after initial 6 month period after initial startup.
Condensate
Drain Trap
*Inspect
Inspect &
Clean
30 mins.
Labor
Time
7-1
Page 52
MAINTENANCE
7.2 IGNITOR-INJECTOR
The ignitor-injector ( part no . 58023) is loc a ted on the burner plate at the top of the boiler. In addition to providing the ignition spark required to light the burner, the ignitor-injector also contains a gas injector tube which connects to the staged ignition assem bly. Figure 7-1 shows the complete burner ass embly removed f r om the boiler and indicates the location of the ignitor­injector flame detector and other related components.
The ignitor-injector may be hot, therefore, care should be exercised to a void burns. It is easier to remove the ignitor-injec tor from the unit after the unit has cooled to room temperature.
AIR/FUEL
VALVE
FLAME DETECTOR
BURNER
PLATE
IGNITOR-
INJECTOR
BLOWER
4. Refer to the partial exploded view in Figure 7-2. Using a 7/16” open-end wrench, disconnect the compression nut securing the gas injector tube of the ignitor- injector to th e elbow of the staged ignition assembly. Disconnect the staged ignition assembly from the ignitor-injector.
Figure 7-2
Ignitor-Injector & Flame Detector
Mounting Details
5. Next, loosen and remove the ignit or-injector from the burner plate using a 1" open-end wrench.
BURNER
STAGED
IGNITION
ASSEMBLY
Figure 7-1
Benchmark 1.5LN Burner Assembly
(Shown Removed from Boiler)
To inspect/replace the Ignitor:
1. Set the ON/OFF switch on the control pa nel, to the OFF position. Disconnect AC power from the unit
2. Remove the side and top panels from the unit.
3. Disconnect the cable from the ignitor-injector (Figure 7-1).
6. Check the ignitor-injector for evidence of erosion or carbon build-up. If there is evidence of substantial erosion or carbon build-up, the ignitor-injector should be replaced. If carbon buil d-up is pres ent, clean the component using fine emery cloth. Repeated carbon build-up is an indication that the combustion settings of the unit should be checked. Refer to Chapter 4 for combustion calibration procedures.
7. Prior to reinstalling the ignitor-injector, a high temperature, conductive, anti-seize com­pound must
be applied to the threads.
NOTE
If a replacement ignitor-injector (part no.
58023) is being installed, a compression nut containing a built-in ferrule will be included with the replacement part. If needed, 3 indexing washers are also included These washers may be needed to properly position the gas injector tube of the ignitor-injector within the 120 ° angle range shown in Figure 7-3.
7-2
Page 53
IGNITOR-
INJECTOR
BURNER
PLATE
BLOWER
0
2
1
GAS
INJECTOR
TUBE
Figure 7-3
Ignitor-Injector Orientation
8. Reinstall the ignitor-injector in the burner plate. Torque to 15 ft-lbs. Do not over tighten.
9. Connect the staged ignit ion assembly to the gas injector tube of the ignitor-injector by securing the compression nut to the elbow of the staged ignition assembly.
10. Reconnect the ignitor-injector cable.
11. Reinstall the side and top panels on the unit.
7.3 FLAME DETECTOR
The flame detector (part no. 66006) is located on the burner plate at the top of the unit (see Figures 7-1 and 7-2). T he f lame detector may be hot. Allow the unit to cool sufficiently before removing the flame detector.
MAINTENANCE
6. Thoroughly inspect the flame detector. If eroded, the detector should be replaced. Otherwise clean the detector with a fine emery cloth.
7. Reinstall the flame detector and flame detector gasket.
8. Reconnect the flame detector lead wire.
9. Reinstall the side and top panels on the unit.
7.4 COMBUSTION CALIBRATION
Combustion settings must be checked at the intervals shown in Table 7-1 as part of the maintenance requirem ents. Refer to Chapter 4 for combustion calibration instructions.
7.5 SAFETY DEVICE TESTING
Systematic and thorough tests of the operating and safety devices should be performed to ensure that they are operating as designed. Certain code requirements, such as ASME CSD-1, require that t hese tests be perform ed on a scheduled basis. Test schedules must conform to local jurisdictions. The results of the tests should be recorded in a log book. See Chapter 6-Safety Device Testing Procedures.
7.6 BURNER ASSEMBLY INSPECTION
The burner assem bly (part no. 24012) is loc ated at the top of the unit's heat exchanger. The burner assembly may be hot. Therefore, allow the unit to cool sufficiently before removing the burner assembly. It should be noted that the complete burner assembly also includes the blower and air/fuel valve assemblies for the unit.
To inspect or replace the flame detector:
1. Set the ON/OFF s witch on the c ontr ol panel , to the OFF position. Disconnect AC power from the unit.
2. Remove the side and top panels from the unit.
3. Disconnect the flame detector lead wire.
4. Remove the two (2) screws securing the flame detector to the plate (Figure 7-2 on previous page). The flame detector is secured to the burner plat e with o ne ( 1) #1 0­32 screw and one (1) #8-32 screw.
5. Remove the flam e detector and gask et from the burner plate.
The following parts will be required for reassembly after burner inspec tio n:
Part No. Description
81063 Burner Gaskets (Qty=2) 81048 Flame Detector Gasket 81064 Blower Gasket
To inspect or replace the burner assembly:
1. Set the ON/OFF switch on the con trol pa nel, to the OFF position. Disconnect AC power from the unit and turn off the gas supply.
2. Remove the side and top panels from the unit.
3. Disconnect the lead wire from the flame detector installed on the burner plate. See Figure 7-4.
7-3
Page 54
MAINTENANCE
Figure 7-4
Burner Assembly Mounting Details
4. Remove the two (2) screws securing the flame detector to the plate. The flame detector is secured to th e burner plate with one (1) #10-32 screw and one (1) #8-32 screw.
5. Remove the flam e detector and gask et from the burner plate.
6. Disconnect the cable from the ignitor­injector.
7. Using a 7/16” open-end wrench, discon nect the compression nut securing the gas injector tube of the ignitor-injector to the elbow of the staged ignition assembly (see Figure 7-2). Disconnect the staged ignition assembly from the ignitor-injector.
8. Next, loosen and remove the ignit or-injector from the burner plate using a 1" open-end wrench.
9. Disconnect the unit wiring harness connectors from the air/fuel valve and blower motor.
13. Disconnect the flex hose from the air/fuel valve by loosening the hose clamp.
14. Remove the four (4) 5/16-18 hex head screws securing the blower to the burner plate (Figure 7-5).
15. Remove the blower and air/fuel valve from the burner plate by lifting straight up. Also, remove the blower gasket.
16. Remove the eight (8) 3/8-16 nuts from the burner flange (Figure 7-4) using a 9/16” wrench.
NOTE
The burner assembly is heavy, weighing approximately 25 pounds.
17. Remove the burner assembly from burner flange by pulling straight up.
18. Remove and replace the two (2) burner gaskets.
NOTE
During reassembly, apply high-tempera­ture, anti-seize lu bricant to the threads of the ignitor-injector and grounding screw. Also, ensure that the ignitor-injector is properly positioned as indicated in Figur e 7-3. Torque the ignitor-injector to 15 ft-lbs.
19. Beginning with the burner assembly removed in step 17, reinstall all the components in the reverse order that they were removed.
20. Ensure that the ignitor-injector and flame detector cutouts in the burner plate are properly aligned with the heat exc hanger to p flange.
10. Disconnect the wire leads connected to the blower proof switch and b locked inlet switch (Figures 7-4 & 7-5).
11. Remove the 10-32 x 1/2" long. grounding screw from the burner plate (Figures 7-4 and 7-5).
12. Disconnect the gas train from the air/fuel valve by removing t he four (4) 1/2” bolts and nuts (Figure 7-4).
7-4
Page 55
MAINTENANCE
B
gasket and float in the condensat e trap and replace the trap cover.
8. Reassemble all piping and hose connections to the condensate trap inlet and outlet. Reconnect trap to exhaust manifold drain.
O-RING
GASKET
FLOAT
ORIFICE GASKET
3/4 NPT
PORT
COVER
THUM
SCREWS
(4)
INLET
3/4 NPT
PORT
Figure 7-4
Burner Assembly Exploded View
7.7 CONDENSATE DRAIN TRAP
The Benchmark 1.5 Boiler contains a condensate trap as shown in Chapter 2, Figure 2-5. The trap is located exter nal to the unit and attached to the drain pipe from the exhaust manifold. This trap should be inspected and, if necessary, cleaned to e nsure proper operation. To inspect and clean the trap, proceed as follows:
1. Disconnect the external condensate trap b y loosening the union pipe connection between the trap and the exhaust manifold drain pipe.
2. Remove the connections on the inlet and outlet sides of the condensate tr ap shown in Figure 7-5.
3. Loosen the four (4) thumbscrews securing the cover on the condensate trap. Remove the cover.
4. Remove the float from the condensate trap.
5. Remove the orifice gasket from the trap.
6. Thoroughly clean the trap, f loat and gasket. Also inspect the drain pipin g for blockage. If the trap cannot be thoroughly cleaned, replace the trap.
7. After the above items have been inspected and thoroughly cleaned, replace the orifice
OUTLET
Figure 7-5
External Condensate Trap
7.8 SHUTTING THE BOILER DOWN FOR AN EXTENDED PERIOD OF TIME
If the boiler is to be taken out of s ervice for an extended period of tim e (one year or more), the following instructions must be followed.
1. Set ON/OFF s witch on the f ront panel to the OFF position to shut down the boiler’s operating controls.
2. Dis c onnect AC po wer fr om the unit.
3. Close the water supply and return valv es to isolate boiler.
4. Close external gas supply valve.
5. O pen relief valve to vent water pressure.
7.9 PLACING THE BOILER BACK IN
SERVICE AFTER A PROLONGED SHUTDOWN
After a prolonged shutdo wn (one year or more), the following procedures must be followed:
1. Review installation requirements inc luded in Chapter 2.
2. Inspect all piping and connections to the unit.
3. Inspect exhaust vent, air duct (if applicable).
4. Perform initial startup per Chapter 4.
5. Perf orm s afet y device tes ting a nd sche duled maintenance procedures per Chapters 6 and 7 of this manual.
7-5
Page 56
Page 57

Chapter 8- TROUBLESHOOTING GUIDE

8.1 INTRODUCTION
This troubleshooting guide is intended to aid service/maintenance personnel in isolating the cause of a fault in a Benchm ark 1.5 Boiler. The troubleshooting procedures contained her ein are presented in tabular form on the f ollowing pages. These tables are comprised of three columns labeled: Fault Indication, Probable Cause and Corrective Action. The numbered items in the Probable Cause and Corrective Ac tion columns correspond to each other. For example, Probable Cause No. 1 corresponds to Corrective Action No. 1, etc.
NOTE:
The front panel of the C-More Control Box contains an RS232 port which can be interfaced to a laptop computer or other suitable device. This RS232 communication feature permits service personnel to view menu item s and data logs which can be useful in isolating faults. Refer to Chapter 9 of this manual for detailed RS232 communication set-up and procedures.
TROUBLESHOOTING
When a fault occurs in the Benchmark Boiler, proceed as follows to isolate and correct the fault:
1. Observe the fault m essages dis played in the Control Box display.
2. Refer to the Fault Indication column in Troubleshooting Table 8-1 which f ollows and locate the Fault that best describes the existing conditions.
3. Proceed to the Probable Cause column and start with the first item (1) lis ted for the Fault Indication.
4. Perform the c hecks and procedures listed in the Corrective Action column for the first Probable Cause candidate.
5. Continue checking each additional Probable Cause for the existing fault until the fault is corrected.
6. Paragraph 8.2 and Table 8-2 contain additional troubleshooting information which may apply when no fault message is displayed.
7. If the fault cannot be corrected using the information provided in the Troubleshooting Tables, contact your local AERCO Representative.
8-1
Page 58
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
AIRFLOW FAULT
DURING IGNITION
1. Blower stopped running due to thermal or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked Blower proof switch
4. Blocked blocked-air inlet switch
5. Defective Blower proof switch
6. Defective blocked-air inlet switch
7. Loose temperature to AUX connection in I/O Box
8. Defective temperature sensor
9. Loose wire connection between the 0-10V
signal from I/O box to the Blower Motor input
10. Defective I/O box
11. Wrong 0-10V output selection on the
control box
12. Defective Air-Fuel Valve potentiometer
1. Check combustion blower for signs of excessive heat or high current drain that may trip thermal or current overload devices.
2. Inspect the inlet to the combustion blower including any ductwork leading up to the combustion blower for signs of blockage.
3. Remove the Blower proof switch and inspect for signs of blockage, clean or replace as necessary.
4. Remove the blocked-air inlet switch and inspect for signs of blockage, clean or replace as necessary.
5. Measure the Blower proof switch for continuity with the combustion blower running. If there is an erratic resistance reading or the resistance reading is greater than zero ohms, replace the switch.
6. Measure the blocked-air inlet switch for continuity with the combustion blower running. If there is an erratic resistance reading or the resistance reading is greater than zero ohms, replace the switch.
7. Check the actual inlet air temperature and measure voltage at AUX input in the I/O Box. Verify that the voltage conforms to the values shown in the tabular listing provided in Appendix C.
8. Refer to CORRECTIVE ACTION 7 and verify that the voltage conforms to the values shown in Appendix C.
9. Check wire connection from I/O Box 0-10V signal to the Blower Motor.
10. Measure voltage at the I/O box 0-10V output. A voltage of
8.2V equates to a 100% open valve position.
11. Check the Analog Out option on the C-More Configuration Menu. Valve Position 0-10V should be selected.
12. Check Air/Fuel Valve position at 0%, 50% and 100% open positions. The positions on the VALVE POSITION bargraph should match the dial readings on the Air/Fuel Valve dial.
8-2
Page 59
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
AIRFLOW FAULT
DURING PURGE
AIRFLOW FAULT
DURING RUN
1. Blower not running or running too slow
2. Defective Air Flow Switch
3. Blocked Air flow Switch
4. Blocked Blower inlet or inlet ductwork.
5. No voltage to switch from control box.
PROBABLE CAUSES from 3 to 16
6. for AIRFLOW FAULT DURING IGNITION applies for this fault
1. Blower stopped running due to thermal or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked airflow switch
4. Defective airflow switch
5. Combustion oscillations
6. PROBABLE CAUSES from 3 to 16 for AIRFLOW FAULT DURING IGNITION applies for this fault
1. Start the unit. If the blower does not r un check the blower solid state relay for input and output voltage. If the relay is okay, check the blower.
2. Start the unit. If the blower runs, check the airflow switch for continuity. Replace the switch if there is no continuity.
3. Remove the air flow switch and inspect for signs of blockage, clean or replace as necessary.
4. Inspect the inlet to the combustion blower including any ductwork leading up to the combustion blower for signs of blockage.
5. Measure for 24 VAC during start sequence from eac h side of the switch to ground. If 24VAC is not present refer to qualified service personnel.
6. See
1. Check combustion blower for signs of excessive heat or high
2. Inspect the inlet to the combustion blower including any ductwork
3. Remove the airflow switch and inspect for signs of blockage,
4. Measure the airflow switch for continuity with the combustion
5. Run unit to full fire. If the unit rumbles or runs rough, perform
6. See CORRECTIVE ACTIONS from 3 to 16 for AIRFLOW
CORRECTIVE ACTIONS from 3 to 16 for AIRFLOW
FAULT DURING IGNITION.
current draw that may trip thermal or current overload devices.
leading up to the combustion blower for signs of blockage.
clean or replace as necessary.
blower running. If there is an erratic resistance reading or the resistance reading is greater than zero ohms, replace the switch.
combustion calibration.
FAULT DURING IGNITION.
8-3
Page 60
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
DELAYED
INTERLOCK OPEN
DIRECT DRIVE SIGNAL FAULT
FLAME LOSS
DURING IGN
1. Delayed Interlock Jumper not installed or removed.
2. Device proving switch hooked to interlocks is not closed
1. Direct drive signal is not present: Not yet installed. Wrong polarity. Signal defective at source. Broken or loose wiring.
2. Signal is not isolated (floating).
3. Control Box signal type selection switches not set for correct signal type (voltage or current).
1. Burner Ground Screw not installed or loose.
2. Worn flame detector
3. No spark from Spark Plug
4. Defective Ignition Transformer
5. Defective Ignition/Stepper (IGST) Board
6. Defective SSOV
1. Check for a jumper properly installed across the delayed interlock terminals in the I/O box.
2. If there are 2 external wires on these terminals, check to see if an end switch for a device such as a pump, louver, etc. is tied these interlocks. Ensure that the device and or its end switch are functional. (jumper may be temporarily installed to test interlock)
1. Check I/O Box to ensure signal is hooked up. Hook up if not installed. If installed, check polarity. Measure signal level. Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for the type of signal being sent. Check control signal type set in Configuration Menu.
1. Inspect and install/retighten Burner Ground Screw.
2. Remove and inspect the flame detector for signs of wear. Replace if necessary.
3. Close the internal gas valve in the boiler. Install and arc a spark ignitor outside the unit.
4. If there is no spark, check for 120VAC at the primary side to the ignition transformer during the ignition cycle.
5. If 120VAC is not present, the IGST Board in the Control Box may be defective. Refer fault to qualified service personnel.
6. While externally arcing the spark ignitor, observe the open/close indicator in the Safety Shut-Off Valve to ensure it is opening. If the valve does not open, check for 120VAC at the valves input terminals. If 120VAC is not present, the IGST board in the Control Box may be defective. Refer fault to qualified service personnel.
8-4
Page 61
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
(continued) 7. Carbon or other debris on Burner.
8. Staged ignition ball valve closed.
9. Staged ignition solenoid valve doesn’t open.
10. Clogged staged ignition piece.
FLAME LOSS DURING RUN
HEAT DEMAND
FAILURE
HIGH EXHAUST TEMPERATURE
1. Worn Flame Detector or cracked ceramic.
2. Defective Regulator.
3. Poor combustion calibration.
4. Debris on burner.
5. Blocked condensate drain.
1. The Heat Demand Relays on the Ignition/Stepper board failed to activate when commanded.
2. Relay is activated when not in Demand
1. Defective exhaust sensor.
2. Carboned heat exchanger due to incorrect combustion calibration
7. Remove the burner and inspect for any carbon or debris. Clean and reinstall.
8. Open ball valve downstream of SSOV (see Figure 8-1).
9. W hen boiler goes to ignition, listen to the solenoid valve for a clicking sound to ensure it is opening.
10. Remove and inspect staged ignition piece for blockage.
1. Remove and inspect the Flame Detector for signs of wear or cracked ceramic. Replace if necessary.
2. Check gas pressure readings using a gauge or manometer into and out of the Air/Fuel Valve to ensure that the gas pressure into and out of the valve is correct.
3. Check combustion calibration. Adjust as necessary.
4. Remove the burner and inspect for any carbon or debris. Clean and reinstall.
5. Remove blockage in condensate drain.
1. Press CLEAR button and restar t the unit. If the fault persists, replace Ignition/Stepper (IGST) Board.
2. Defective relay. Replace IGST Board.
1. Measure the actual exhaust temperature and continuity of the exhaust sensor. If the exhaust temperature is less than 475 and the exhaust sensor shows continuity replace the sensor.
2. If exhaust temperature is greater than 500 combustion calibration. Calibrate or repair as necessary.
o
F, check
o
F
8-5
Page 62
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
HIGH GAS
PRESSURE
HIGH WATER TEMP
SWITCH OPEN
HIGH WATER
TEMPERATURE
1. Incorrect supply gas pressure.
2. Defective SSOV Actuator.
3. Defective High Gas P ressure Switch
4. Gas pressure snubber not installed.
1. Faulty Water temperature switch.
2. Incorrect PID settings.
3. Faulty shell temperature sensor.
4. Unit in Manual mode
5. Unit setpoint is greater than Over Temperature Switch setpoint.
6. Boiler Management System PID or other settings not correctly setup.
7. No interlock to boiler or BMS to disable boiler(s) in event that system pumps have failed.
8. System flow rate changes are occurring faster than boilers can respond.
1. See HIGH WATER TEMPERATURE SWITCH OPEN.
2. Temp HI Limit setting is too low.
1. Check to ensure gas pressure at inlet of SSOV is 2 psig maximum.
2. If gas supply pressure downstream of SSOV Actuator cannot be lowered, to 1.5” W.C. using the gas pressure adjustment screw (see para. 4.3, step 10), the SSOV Actuator may be defective.
3. Remove the leads from the high gas pressure switch and measure continuity across the common and normally closed terminals with the unit not firing. Replace the switch if it does not show continuity.
4. See Figure 8-1. Ensure that the gas pressure snubber is installed at the high gas pressure switch.
1. Test the temperature switch to insure it trips at its actual water temperature setting.
2. Check PID settings against Menu Default settings in the Appendix. If the settings have been changed, record the current readings then reset them to the default values.
3. Using the resistance charts in the Appendix C, Measure the resistance of Shell sensor and BTU sensor at a known water temperature.
4. If unit is in Manual Mode switch to Auto Mode.
5. Check setpoint of unit and setpoint of Temperature Switch; Ensure that the temperature switch is set higher than the unit’s setpoint.
6. Check the BMS for changes to PID default values, correct as necessary.
7. If system pump is controlled by Energy Management System other than BMS or pumps are individually controlled by boiler, check to see if there are flow switches interlocked to the BMS or boiler.
8. If the system is a variable flow system, monitor system flow changes to ensure that the rate of flow change is not faster than what the boilers can respond to.
1. See HIGH WATER TEMPERATURE SWITCH OPEN.
2. Check Temp HI Limit setting.
8-6
Page 63
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
IGN BOARD
COMM FAULT
IGN SWTCH CLOSED
DURING PURGE
IGN SWTCH OPEN
DURING IGNITION
1. Communication fault has occurred between the PMC board and Ignition/Stepper (IGST) board
1. Air/Fuel Valve not rotating
2. Defective or shorted switch
3. Switch wired incorrectly
4. Defective Power Supply Board or fuse
5. Defective IGST Board
1. Air/Fuel Valve not rotating to ignition position.
2. Defective ignition switch
3. Defective Power Supply Board or fuse
4. Defective IGST Board
1. Press CLEAR button and restart unit. If fault persists, contact qualified Service Personnel.
1. Start the unit. The Air/Fuel Valve should rotate to the purge (open) position. If the valve does not rotate at all or does not rotate fully open, check the Air/Fuel Valve calibration. If calibration is okay, the problem may be in the Air-Fuel Valve or the Control Box. Refer to qualified service personnel
2. . If the Air/Fuel Valve does rotate to purge, check the ignition switch for continuity between the N.O. and COM terminals. If the switch shows continuity when not in contact with the cam replace the switch.
3. Check to ensure that the switch is wired correctly (correct wire numbers on the normally open terminals). If the switch is wired correctly, replace the switch
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not steady ON, replace Power Supply Board.
5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF every second. If not, replace IGST Board
1. Start the unit. The Air/Fuel Valve should rotate to the purge (open) position, then back to ignition position (towards closed) during the ignition cycle. If the valve does not rotate back to the ignition position, check the Air/Fuel Valve calibration. If calibration is okay, the problem m ay be in the Air/Fuel Valve or the Control Box. Refer fault to qualified service personnel.
2. If the Air/Fuel Valve does rotate to the ignition position, check the ignition position switch for continuity between the N.O. and COM terminals when in contact with the cam.
3. Check DS1 & DS2 LEDs on Power Supply Board. If they are not steady ON, replace Power Supply Board.
4. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF every second. If not, replace IGST Board.
8-7
Page 64
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
INTERLOCK
OPEN
LINE VOLTAGE
OUT OF PHASE
LOW GAS
PRESSURE
LOW WATER
LEVEL
MODBUS COMM
FAULT
PRG SWTCH CLOSED
DURING IGNITION
1. Interlock jumper not installed or removed
2. Energy Management System does not have boiler enabled.
3. Device proving switch hooked to interlocks is not closed.
1. Line and Neutral switched in AC Power Box.
2. Incorrect power supply transformer wiring.
1. Incorrect supply gas pressure.
2. Defective Low Pressure Gas Switch
1. Insufficient water level in system
2. Defective water level circuitry.
3. Defective water level probe.
1. Boiler not seeing information from Modbus network
1. A/F Valve rotated open to purge and did not rotate to ignition position.
1. Check for a jumper properly installed across the interlock terminals in the I/O box
2. If there are two external wires on these terminals check any Energy Management system to see if they have the units disabled (a jumper may be temporarily installed to see if the interlock circuit is functioning).
3. Check that proving switch for any device hooked to the interlock circuit is closing and that the device is operational.
1. Check hot and neutral in AC Power Box to ensure they are not reversed
2. Check transformer wiring, in AC Power Box, against the power box transformer wiring diagram to ensure it is wired correctly
1. Measure gas pressure upstream of the SSOV Actuator(s) with the unit firing. For FM gas trains, ensure it is between 4.0” W.C. and 2 psig. For IRI gas trains, ensure it is between 4.2" W.C. and 2 psig (see para. 2.7.1).
2. Measure gas pressure at the low gas pressure switch. If it is greater than 2.6” W.C., measure continuity across the switch and replace if necessary.
1. Check system for sufficient water level.
2. Test water level circuitry using the Control Box front panel LOW WATER TEST and RESET buttons. Replace water level circuitry if it does not respond.
3. Check continuity of probe end to the shell, change probe if there is no continuity.
1. Check network connections. If fault persists, contact qualified Service Personnel.
1. Start the unit. The Air/Fuel Valve should rotate to the purge (open) position, then back to ignition position (towards closed) during the ignition cycle. If the valve does not rotate back to the ignition position, check the Air/Fuel Valve calibration. If calibration is okay, the problem m ay be in the Air/Fuel Valve or the Control Box. Refer fault to qualified service personnel.
8-8
Page 65
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
(continued) 2. Defective or shorted switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or fuse
5. Defective IGST Board
PRG SWTCH OPEN
DURING PURGE
OUTDOOR TEMP
SENSOR FAULT
REMOTE SETPT
SIGNAL FAULT
1. Defective purge switch.
2. No voltage present at switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or fuse
5. Defective IGST Board
1. Loose or broken wiring.
2. Defective Sensor.
3. Incorrect Sensor.
1. Remote setpoint signal not present: Not yet installed. Wrong polarity. Signal defective at source. Broken or loose wiring.
2. Signal is not isolated (floating) if 4 to 20 mA.
3. Control Box signal type selection switches not set for correct signal type (voltage or current).
2. If the Air/Fuel Valve does rotate to the ignition position, check the purge switch for continuity between the N.O. and COM terminals. If the switch shows c ontinuity when not in contact with the cam, check to ensure that the switch is wired correctly (correct wire numbers on the normally open terminals).
3. If the switch is wired correctly, replace the switch.
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not steady ON, replace Power Supply Board.
5. Check “ Heartbeat” LED DS1 and verify it is blinking ON & OFF every second. If not, replace IGST Board.
1. If the air-fuel valve does rotate, check the purge switch for continuity when closing. Replace switch if continuity does not exist.
2. Measure for 24 VAC from each side of the switch to ground. If 24VAC is not present, refer fault to qualified service personnel.
3. Check to ensure that the switch is wired correctly (correct wire numbers on the normally open terminals).
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not steady ON, replace Power Supply Board.
5. Check “ Heartbeat” LED DS1 and verify it is blinking ON & OFF every second. If not, replace IGST Board.
1. Inspect Outdoor Temperature sensor for loose or broken wiring.
2. Check resistance of sensor to determine if it is within specification.
3. Ensure that the correct sensor is installed.
1. Check I/O Box to ensure signal is hooked up. Hook up if not installed. If installed, check polarity. Measure signal level. Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for the type of signal being sent. Check control signal type set in Configuration Menu.
8-9
Page 66
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
RESIDUAL
FLAME
SSOV FAULT
DURING PURGE
SSOV FAULT DURING RUN SSOV RELAY
FAILURE
SSOV
SWITCH OPEN
STEPPER MOTOR
FAILURE
1. SSOV not fully closed.
2. Defective Flame Detector
See SSOV SWITCH OPEN
1. SSOV switch closed for 15 seconds during run.
1. SSOV relay failed on board.
2. Floating Neutral.
3. Hot and Neutral reversed at SSOV.
1. Actuator not allowing for full closure of gas valve
2. SSOV powered when it should not be
3. Defective Switch or Actuator
4. Incorrectly wired switch.
1. Air/Fuel Valve out of calibration.
1. Check open/close indicator window of Safety Shut-Off Valve (SSOV) and ensure that the SSOV is fully closed. If not fully closed, replace the valve and or actuator.
Close gas shut-off valve downstream of SSOV. Install a manometer or gauge in a gas test port between the SSOV and the gas shut off valve. If a gas pressure reading is observed replace the SSOV valve and or actuator.2.
2. Replace Flame Detector.
1. Replace or adjust microswitch in SSOV actuator. If fault persists, replace actuator.
1. Press CLEAR button and restart unit. If fault persists, replace Ignition/Stepper (IGST) Board.
2. The Neutral and Earth Ground are not connected at the source and therefore there is a voltage measured between the two. Normally this measurement should be near zero or no more than a few millivolts.
3. Check SSOV power wiring.
1. Observe operation of the Safety Shut-Off Valve (SSOV) through indicator on the Valve actuator and ensure that the valve is fully and not partially closing.
2. If the SSOV never closes, it may be powered continuously. Close the gas supply and remove power from the unit. Refer fault to qualified service personnel.
3. Remove the electrical cover from the SSOV and check switch continuity. If the switch does not show continuity with the gas valve closed, either adjust or replace the switch or actuator.
4. Ensure that the SSOV Proof of Closure switch is correctly wired.
1. Refer to GF-112 and perform Stepper Test (para. 6.3.5) to ensure stepper motor rotates properly between the 0% (fully closed) and 100% (fully open) positions. Verify that the VALVE POSITION bargraph and the dial on the Air/Fuel Valve track each other to indicate proper operation. If operation is not correct, perform the Stepper Feedback Calibration (GF-112, para. 6.2.1).
8-10
Page 67
TROUBLESHOOTING
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FAULT INDICATION PROBABLE CAUSES CORRECTIVE ACTION
(continued) 2. Air/Fuel Valve unplugged.
3. Loose wiring connection to the stepper motor.
4. Defective Air/Fuel Valve stepper motor.
5. Defective Power Supply Board or fuse
6. Defective IGST Board
8.2 ADDITIONAL FAULTS WITHOUT SPECIFIC FAULT MESSAGES
Refer to Table 8-2 to troubleshoot faults which may occur without a specific fault message being displayed.
TABLE 8-2. BOILER TROUBLESHOOTING WITH NO FAULT MESSAGE DISPLAYED
2. Check that the Air/Fuel Valve is connected to the Control Box.
3. .Inspect for loose connections between the Air/Fuel Valve motor and the wiring harness.
4. Replace stepper motor.
5. Check DS1 & DS2 LEDs on Power Supply Board. If they are not steady ON, replace Power Supply Board.
6. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF every second. If not, replace IGST Board.
OBSERVED INCIDENT PROBABLE CAUSES CORRECTIVE ACTION
Hard Light-Off 1. Staged Ignition Ball Valve closed.
2. Clogged/damaged Gas Injector (Figure 8-2).
3. Defective Staged Ignition Solenoid (Figure 8-2)
Fluctuating Gas Pressure 1. Gas pressure going into unit is
fluctuating.
2. Damping Orifice not installed.
Air/Fuel Valve “hunting” at the
80% Valve Position
8-11
1. IGST and Power Supply Boards in Control Box are outdated.
1. Open the 1/4” Ball Valve downstream of the SSOV (Fig. 8-1).
2. Remove and inspect Gas Injector to ensure it is not clogged or damaged.
3. Close the 2” and the 1/4” Ball Valve downstream of the SSOV (Fig. 8-1). Start the unit and listen for a “clicking” sound that the Staged Ignition Solenoid makes during Ignition Trial. If “clicking” sound is not heard after 2 or 3 attempts, replace the Staged Ignition Solenoid.
1. Stabilize gas pressure going into unit. If necessary, troubleshoot Building Supply Regulator.
2. Check to ensure that the Damping Orifice is installed in the SSOV Actuator shown in Figure 8-3. (For IRI Gas Trains, the Damping Orifice is installed in the downstream SSOV Actuator).
1. Check to ensure that the IGST and Power Supply Boards are Rev. E or higher.
Page 68
TROUBLESHOOTING
HIGH GAS
PRESSURE
SWITCH
LEAK
DETECTION
BALL VALVE
SSOV
MANUAL
SHUT-OFF
VALVE
GAS
INLET
TO
AIR/FUEL
VALVE
Figure 8-2
Staged Ignition Solenoid Location
1/8" NPT PLUG
(INSTALL
MANOMETER
HERE)
LOW GAS
PRESSURE
SWITCH
STAGED
IGNITION
BALL VALVE
Figure 8-1
High Pressure Gas Switch & Snubber Locat i ons
8-12
Figure 8-3
Damping Orifice Location
Page 69
CHAPTER 9 RS232 COMMUNICATION
9.1 INTRODUCTION
The RS232 port on the fron t panel of the C-More Control Box (Figure 3-1) c an be interfaced to a laptop computer or other suitable terminal using a RS232 adapter cable. RS232 communication can be accomplished using any “Dumb Terminal” emulation, such as “Hyper Terminal” which is included with Microsoft Windows. The RS232 communication feature permits viewing or changing of Control Panel menu optio ns and also provides ac ces s to dat a lo gs s ho w ing E ven t Time Line, Fault and Sensor log displays.
9.2 RS232 COMMUNICATION SETUP
Regardless of the terminal emulation utilized, the following guidelines must be adhered to when setting up the RS232 communication link:
1. Baud Rate – The baud rates which can be used with the C-More Control Panel are:
2400 4800 9600 (Default)
19.2K
1. Data Form at – The program must be set for :
8 data bits, 1 stop bit, no parity and either Xon/Xoff or No flow control.
9.3 MENU PROCESSING UTILIZING
RS232 COMMUNICATION
Viewing data logs and viewing or changing Control Panel menu options using RS232 communication is accomplished as follows:
RS232 COMMUNICATION
M = Display next Menu D = Display menu items N = Display next menu items Cxx = Change item xx F = Fault log display S = Sensor log display T = Time line display L = Log off
NOTE:
The Level 1 password (159) must be entered to change options in the Setup, Configuration and Tuning Menus. The Level 2 password (6817) must be entered to view or change options in the Calibration and Diagnostics Menus.
With the exception of the password entry, all other keyboard entries can be made using either upper or lower case.
5. To view the availabl e menus in the top-do wn sequence shown in Figure 3-2, enter M <Rtn>. The Menu title and first 10 options will be displayed.
6. W hen viewing menus containing more than 10 options, enter N <Rtn> to display the remaining options.
7. Shortcut ke ys are a lso av ai lab le t o g o d irec tly to a specific menu. These shortcut keys are:
m0 Default (Operating) Menu m1 Setup Menu m2 Configuration Menu m3 Tuning Menu m4 Calibration Me nu m5 Diagnostic Men u
1. Start the emulator software program and ensure that the specif ied baud rat e and data formats have been entered.
2. Press the Enter key on the laptop. An asterisk (*) prompt should appear.
3. At the prompt, enter the valid RS232 password (jaguar) in lower case letters and press Enter.
4. “Welcome to Aerc o” will appear in the laptop or “dumb terminal” display with a listing of the following available entry cho ices :
8. To change a value or sett ing for a displa yed menu option, proceed as follows:
(a) Enter C, followed by the number to the
right of the displayed option to be changed, and then press <Rtn>.
(b) Enter the desired value or s etting f or the
option and press <Rtn>. Refer to Chapter 3, Tables 3-2 through 3-5 for allowable entry ranges and settings for the Operating, Setup, Conf iguration and Tuning Menus. (The Calibration and Diagnostic Menus should only be used by Factory-Trained service personnel).
9-1
Page 70
RS232 COMMUNICATION
(c) Menu changes will be stored in non-
volatile memory.
9. To redisplay the menu and view the option which was just changed in step 5, enter D and press <Rtn>.
10. To display the Faul t (F) Log, Sensor (S) Log or Time (T) Line Log, press F, S or T followed by <Rtn>. Refer to paragr a ph 9.4 f or descriptions and samples of these data logs.
11. To log off and terminate the RS232 com­munication link, press L followed by <Rtn>.
9.4 DATA LOGGING
During operation, the C-More Control Panel continuously monitors and logs data associated with operational events, faults and sensor readings associated with the boiler or water heater system. Descriptions of these data logs are provided in the following paragraphs. The basic procedure f or accessing each data log is described in paragraph 9.3, step 7.
9.4.1 Fault Log
9.4.2 Operation Time Log
The Operation Time Log consists of a string of ASCII records stored in non-volatile memory within the C-More Control Panel. Events such as power-up, ignition and turn-off are time stamped. Data logged while the unit is running are run-length encoded. Data is logged or the run-length incremented every 30 seconds. For a new run record to be logged, the fire rate or flame strength must change by more than 5%, or the run mode mus t change. At steady-state, the run-length is allowed to reach a max imum of 30 minutes before the record is logged. This means that no more than 3 0 minutes of data can be lost if the unit loses po wer. Table 9-2 shows a sample Operation Time Log for a boiler:
The Operation T ime Log can onl y be accessed through the RS232 interface using a laptop or other terminal device. Ten operation time records are displayed for each T command entry. The operation time log can be cleared ONLY by factory authorize d personnel usin g the Clear Log option in the Factory menu.
The C-More Control Pane l logs th e last 20 f aults (0 – 19) starting with th e most recent (#0). T hey can be viewed in the front panel display or via the RS232 port. The Fault Log cannot be cleared. If the Fault Log already contains 10 faults, the earliest fault is overwritten when a new fault occurs. A sam ple Fault Log display is shown in Table 9-1.
NOTE:
The Operation Time (T) Log can store thousands of records. Therefore, to view the most recently logged re cord, enter “T” followed by 0 (zero) and press Enter (i.e. T0 <Enter>). T o view earlier records in reverse chronological order, enter T and press Enter. To go ba ck 200 or 1000 records, enter T200 or T1000, etc. and press Enter.
NOTE:
The Sensor (S) Log c an store up to 1 200 records. Therefore, to view the most recently logged re cord, enter “S” foll owed by 0 (zero) and then press Enter (i.e. S0 <Enter>). To view earlier records in reverse chronological order, enter S and press Enter. To go back 200 or 700 records, enter S200 or S700, etc. and press Enter.
9.4.3 Sensor Log
The sensor values c an be logged at a different rate if needed b y setting th e Sensor L og Inter val in the Diagnostics Menu. The log interval can vary from once ever y minute to once every day. Table 9-3 shows a sample Sensor Log ever y 5 minutes for a boiler running in Constant Setp oint mode.
9-2
Page 71
RS232 COMMUNICATION
Table 9-1. Sample Fault Log Display
No. Fault Message Cycle Date Time 0 Direct Drive Signal Fault 609 1/10/02 8:42am 1 Low Gas Pressure 366 7/04/01 5:29pm 2 Loss of Power 0 1/01/01 11:50am
Table 9-2. Sample Operation Time Log Display
Status Fire Rate Flame Run Length Date Time Off, Direct Drive 0 0 8 1/15/02 2:35pm Run, Direct Drive 38 100 34 1/15/02 2:27pm Run, Direct Drive 31 100 30 1/15/02 1:53am Run, Direct Drive 35 100 2 1/15/02 1:23pm Run, Direct Drive 29 100 0 1/15/02 1:21pm Ignition 0 0 0 1/15/02 1:20pm Off, Switch 0 0 35 1/15/02 12:30pm Run, Manual 40 100 0 1/15/02 11:55am Ignition 0 0 0 1/15/02 11:55am Power-up 0 0 0 1/15/02 11:50am
Table 9-3. Sample Sensor Log Display
Setpt Outlet Outdr FFWD Aux Inlet Exhst CO O2 Flow Date Time 130 181 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:51pm 130 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:41pm 130 179 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:36pm 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:31pm 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:26pm 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:21pm 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:16pm 130 179 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:11pm 130 180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:06pm
180 OPEN OPEN OPEN OPEN OPEN 0 .0 0 1/15/02 5:46pm
9-3
Page 72
Page 73
APPENDIX A

APPENDIX A - BOILER MENU ITEM DESCRIPTIONS

MENU LEVEL & OPTION DESCRIPTION
OPERATING MENU Active Setpoint This is the setpoint temperature to which the
control is set when operating in the Constant Setpoint, Remote Setpoint or Outdoor Reset Mode. When in the Constant Setpoint Mode, this value is equal to the Internal Setpoint setting in the Configuration Menu. When in the Remote Setpoint Mode, this value is the setpoint equivalent to the remote analog signal supplied to the unit. When in the Outdoor Reset Mode, this is the derived value from the charts in Appendix D.
Air Temp Air Temp is the air temperature at the input to the
Air/Fuel Valve. This reading is one of the parameters used to control the Blower Motor speed.
Outdoor Temp Displayed only if outdoor sensor is installed and
enabled.
Valve Position In Desired input valve position. This would normally
be the same as the fire valve position shown on the bargraph (valve position out) when the boiler is
operating. Flame Strength Displays flame strength from 0% to 100%. Run Cycles Displays the total number of run cycles from 0 to
999,999. Run Hours Displays total run time of unit in hours from 0 to
9,999,999. Fault Log Displays information on the last 20 faults.
A-1
Page 74
APPENDIX A
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - CONTINUED
MENU LEVEL & OPTION DESCRIPTION
SETUP MENU
Password Allows password to be entered.
Language Permits selection of English, Spanish or French for
Time Displays time from 12:00 am to 11:59 pm. Date Displays dates from 01/01/00 to 12/31/99 Unit of Temp Permits selection of temperature displays in degrees
Comm Address For RS-485 communications (0 to 127). Default
Baud Rate Allows communications Baud Rate to be set (2400
Software Version Identifies the current software version of the control
Once the valid password (159) is entered, options in the Setup, Configuration and Tuning Menus can be modified.
displayed messages. Default is English.
Fahrenheit (°F) or degrees Celsius (°C). Default is °F.
address is 0. RS-232 should have its own (programmable) password.
to 19.2K). Default is 9600.
box (Ver 0.0 to Ver 9.9). CONFIGURATION MENU Internal Setpoint Allows internal setpoint to be set . Default is 130°F. Unit Type Allows selection of KC Boiler, KC Boiler LN, BMK
Unit Size Sets unit size from 0.5 to 6.0 MBTUs. Default is 1.0
Fuel Type Allows selection of Natural Gas or Propane Boiler Mode It allows selection of: Constant Setpoint, Remote
Remote Signal Used to set the type of external signal which will be
Bldg Ref Temp
Boiler, BMK Boiler LN, BMK Boiler Dual, KC Water
Heater, KC Water Heater LN, Water Heater 2010
MBTU.
Setpoint, Direct Drive, Combination, or Outdoor
Reset Mode. Default is Constant Setpoint Mode.
used when operating in the Remote Setpoint, Direct
Drive or Combination Mode. The factory default is
4-20 mA/1-5V.
Allows the building reference temperature to be set
when operating a boiler in the Outdoor Reset Mode.
Default is 70°F.
A-2
Page 75
APPENDIX A
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - Continued
MENU LEVEL & OPTION DESCRIPTION
CONFIGURATION MENU (Cont.)
Reset Ratio Permits setting of Reset Ratio when operating boiler
Outdoor Sensor Allows outdoor sensor function to be enabled or
System Start Tmp If outdoor sensor is enabled, this menu item allows
Setpoint Lo Limit Used to set the minimum allowable setpoint (40°F to
Setpoint Hi Limit Used to set the maximum allowable setpoint
Temp Hi Limit This is the maximum allowable outlet temperature
Max Valve Positon Sets the maximum allowable valve position for the
in the Outdoor Reset Mode. Reset Ratio is
adjustable from 0.1 to 9.9. Default is 1.2.
disabled. Default is disabled.
the system start temperature to be set from 30 to
100°F. Default is 60°F.
Setpoint Hi Limit). Default is 60°F
(Setpoint Lo Limit to 240°F). Default is 200°F.
(40 to 240°F). Any temperature above this setting
will turn off the unit. The temperature must then drop
5° below this setting to allow the unit to run. Default
Hi Limit is 210°F.
unit (40% to 100%). Default is 100%. Pump Delay Timer Specifies the amount of time (0 to 30 min.) to keep
the pump running after the unit turns off. Default is
zero. Aux Start On Dly Specif ies th e amount of time to wait (0 to 120 sec.)
between activating the Aux Relay (due to a demand)
and checking the pre-purge string to start the boiler.
Default is 0 sec. Failsafe Mode Allows the Failsafe mode to be set to either
Constant Setpoint or Shutdown. Default is
Shutdown. Analog Output Must be set to Valve Pos 0-10V for Benchmark
1.5LN.
Lo Fire Timer Specifies how long (2 to 600 sec.) to remain in the
low fire position after ignition, before going to the
desired output. Default is 2 sec. Network Timeout Specifies the timeout value (seconds) before a
Modbus fault is declared. Available settings range
from 5 to 999 seconds. Default is 30 seconds.
A-3
Page 76
APPENDIX A
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - Continued
MENU LEVEL & OPTION DESCRIPTION
CONFIGURATION MENU (Cont.)
HI DB Setpt EN Operating at a Valve Position below this value will
Demand Offset This entry will reduce excessive ON/OFF cycling in
inhibit the DEADBAND feature. When operating at a
Valve Position below this value, the effective
Setpoint is equal to Active Setpoint + DEADBAND
HIGH.
Setting range is from 0 to 100. (Default is 30)
AUTO mode. When this entry is a non-zero value,
the unit will not turn on again until Valve Position In
reaches the Start Level value AND the Outlet
Temperature goes below the Active Setpoint –
Demand Offset. In addition, the boiler will fir e at the
29% Valve Position level or below for a period of
one minute.
When this entry is set to zero, the unit will turn on
again as soon as the Valve Position in reaches the
Start Level value. There will not be a one minute
delay when firing at the 29% Valve Position level.
Setting range is 0 to 25. (Default is 10) Deadband High Deadband Low
Deadband High and Deadband Low settings create
an “Outlet Temperature” Zone. In which no Valve
Position corrections will be attempted.
The Deadband ZONE is defined as operating with
an Outlet Temperature between Active Setpoint +
Deadband High and Active Setpoint – Deadband
Low.
When the Outlet Temperature reaches Active
Setpoint and remains there for a period of 15
seconds, the unit will go into a DEADBAND MODE
at which point no Valve Position corrections will be
attempted while the Outlet Temperature remains
anywhere within the Deadband ZONE. When the
unit is in the DEADBAND MODE, the °F or °C LED
will flash on and off. When the Outlet Temperature
drifts out of the Deadband ZONE, the DEADBAND
MODE will be terminated and the PID LOOP will
again attempt Valve Position corrections.
Setting range is 0 to 25. (Default is 2 for both
Deadband High and Deadband Low)
A-4
Page 77
APPENDIX A
MENU LEVEL & OPTION DESCRIPTION
TUNING MENU
Prop Band G ener ates a fire rate based on the error that exists
between the setpoint temperature and the actual
outlet temperature. If the actual error is less than
the proportional band setting (1 to 120°F), the fire
rate will be less than 100%. If the error is equal to
or greater than the proportional band setting, the fire
rate will be 100%. Integral Gain This sets the fraction of the output, due to setpoint
error, to add or subtract from the output each minute
to move towards the setpoint. Gain is adjustable
from 0.00 to 1.00 (Default is 0.10). Derivative Time T his value (0.0 to 20.0 min.) responds to the rate of
change of the setpoint error. This is the time that
this action advances the output. Reset Defaults? Allows Tuning Menu options to be reset to their
Factory Default values.
A-5
Page 78
Page 79

APPENDIX B - STARTUP, STATUS AND FAULT MESSAGES

MESSAGE DESCRIPTION
DISABLED
HH:MM pm MM/DD/YY
STANDBY Displayed when ON/OFF switch is in the ON position, but
DEMAND DELAY
XX sec
PURGING
XX sec
IGNITION TRIAL
XX sec
FLAME PROVEN
WARMUP
XX sec
WAIT Prompts the operator to wait.
APPENDIX B
TABLE B-1. STARTUP AND STATUS MESSAGES
Displayed if ON/OFF switch is set to OFF. The display also shows the time and date that the unit was disabled.
there is no demand for heat. The time and date are also displayed. Displayed if Demand Delay is active.
Displayed during the purge cycle during startup. The duration of the purge cycle counts up in seconds. Displayed during ignition trial of startup sequence. The duration of cycle counts up in seconds. Displayed after flame has been detected for a period of 2 seconds. Initially, the flame strength is shown in %. After 5 seconds has elapsed, the time and date are shown in place of flame strength. Displayed for 2 minutes during the initial warmup only.
B-1
Page 80
APPENDIX B
FAULT MESSAGE FAULT DESCRIPTION
HIGH WATER TEMP
SWITCH OPEN
LOW WATER
LEVEL
LOW GAS
PRESSURE
HIGH GAS
PRESSURE
INTERLOCK
OPEN
DELAYED
INTERLOCK OPEN
AIRFLOW FAULT
DURING PURGE
PRG SWTCH OPEN
DURING PURGE
IGN SWTCH OPEN
DURING IGNITION
IGN SWTCH CLOSED
DURING PURGE
PRG SWTCH CLOSED
DURING IGNITION
AIRFLOW FAULT
DURING IGN
AIRFLOW FAULT
DURING RUN
SSOV
SWITCH OPEN
SSOV FAULT
DURING PURGE
SSOV FAULT
DURING IGN
SSOV FAULT
DURING RUN
SSOV RELAY
FAILURE
FLAME LOSS
DURING IGN
FLAME LOSS
DURING RUN
HIGH EXHAUST
TEMPERATURE
LOSS OF POWER
TABLE B-2. FAULT MESSAGES
The High Water Temperature Limit Switch is open.
The Water Level Control board is indicating low water level.
The Low Gas Pressure Limit Switch is open.
The High Gas Pressure Limit Switch is open.
The Remote Interlock is open.
The Delayed Interlock is open.
The Blower Proof Switch opened during purge, or air inlet is blocked. The Purge Position Limit switch on the air/fuel valve opened during purge. The Ignition Position Limit switch on the air/fuel valve opened during ignition. The Ignition Position Limit switch on the air/fuel valve closed during purge. The Purge Position Limit switch on the air/fuel valve closed during ignition. The Blower Proof Switch opened during ignition.
The Blower Proof Switch opened during run.
The SSOV switch opened during standby.
The SSOV switch opened during purge.
The SSOV switch closed or failed to open during ignition.
The SSOV switch closed for more than 15 seconds during run. A failure has been detected in one of the relays that control the SSOV. The Flame signal was not seen during ignition or lost within 5 seconds after ignition. The Flame signal was lost during run.
The High Exhaust Temperature Limit Switch is closed.
A power loss had occurred. The time and date when power was restored is displayed.
B-2
Page 81
APPENDIX B
TABLE B-2. FAULT MESSAGES - Continued
FAULT MESSAGE FAULT DESCRIPTION
RESIDUAL
FLAME
HEAT DEMAND
FAILURE
IGN BOARD
COMM FAULT DIRECT DRIVE SIGNAL FAULT
REMOTE SETPT
SIGNAL FAULT
OUTDOOR TEMP
SENSOR FAULT
OUTLET TEMP
SENSOR FAULT
FFWD TEMP
SENSOR FAULT
HIGH WATER
TEMPERATURE
LINE VOLTAGE
OUT OF PHASE
STEPPER MOTOR
FAILURE
NETWORK COMM
FAULT
The Flame signal was seen for more than 60 seconds during standby. The Heat Demand Relays on the Ignition board failed to activate when commanded.
A communication fault has occurred between the PMC board
and Ignition board. The direct drive signal is not present or is out of range.
The remote setpoint signal is not present or is out of range.
The temperature measured by the Outdoor Air Sensor is out of range. The temperature measured by the Outlet Sensor is out of range. The temperature measured by the FFWD Sensor is out of range. The temperature measured by the Outlet Sensor exceeded the Temp Hi Limit setting. The High AC voltage is out of phase from the low AC voltage.
The stepper motor failed to move the valve to the desired position. The RS-485 network information is not present or is corrupted.
B-3
Page 82
Page 83
APPENDIX C
TEMPERATURE SENSOR RESISTANCE VOLTAGE CHART
(BALCO)
TEMP (°F) RES (OHMS) VOLTS*
-40
-30
-20
-10 0
10 20 30 40 50 60 70 80
90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
*Voltage at AUX & Common terminals in the I/O Box
779.0
797.5
816.3
835.4
854.8
874.6
894.7
915.1
935.9
956.9
978.3
1000.0
1022.0
1044.4
1067.0
1090.0
1113.3
1137.0
1160.9
1185.2
1209.5
1234.7
1260.0
1285.6
1311.4
1337.7
1364.2
1391.0
1418.2
1445.7
1.93
1.96
1.99
2.02
2.05
2.07
2.10
2.12
2.15
2.17
2.20
2.23
2.25
2.27
2.30
2.32
2.34
2.36
2.39
2.41
2.43
2.45
2.47
2.50
2.52
2.54
2.56
2.58
C-1
Page 84
Page 85
Air
Temp
50F 45F 40F 35F 30F 25F 20F 15F 10F
5F 0F
-5F
-10F
-15F
-20F
Air
Temp
60F 55F 50F 45F 40F 35F 30F 25F 20F 15F 10F
5F 0F
-5F
-10F
-15F
-20F
APPENDIX D
APPENDIX D. - INDOOR/OUTDOOR RESET RATIO CHARTS
Table D-1. Header Temperature for a Building Reference Temperature of 50F
RESET RATIO
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
50 50 50 50 50 50 50 50 50 50 53 54 55 56 57 58 59 60 60 62 56 58 60 62 64 66 68 70 72 74 59 62 65 68 71 74 77 80 83 86 62 66 70 74 78 82 86 90 94 98 65 70 75 80 85 90 95 100 105 110 68 74 80 86 92 98 104 110 116 122 71 78 85 92 99 106 113 120 127 134 74 82 90 98 106 114 122 130 138 146 77 86 95 104 113 122 131 140 149 158 80 90 100 110 120 130 140 150 160 170 83 94 105 116 127 138 149 160 171 182 86 98 110 122 134 146 158 170 182 194 89 102 115 128 141 154 167 180 193 206 92 106 120 134 148 162 176 190 204 218
Table D-2. Header Temperature for a Building Reference Temperatrure of 60F
RESET RATIO
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
60 60 60 60 60 60 60 60 60 60 63 64 65 66 67 68 69 70 71 72 66 68 70 72 74 76 78 80 82 84 69 72 75 78 81 84 87 90 93 96 72 76 80 84 88 92 96 100 104 108 75 80 85 90 95 100 105 110 115 120 78 84 90 96 102 108 114 120 126 132 81 88 95 102 109 116 123 130 137 144 84 92 100 108 116 124 132 140 148 156 87 96 105 114 123 132 141 150 159 168 90 100 110 120 130 140 150 160 170 180 93 104 115 126 137 148 159 170 181 192 96 108 120 132 144 156 168 180 192 204
99 112 125 138 151 164 177 190 203 216 102 116 130 144 158 172 186 200 214 105 120 135 150 165 180 195 210 108 124 140 156 172 188 204
D-1
Page 86
APPENDIX D
Table D-3. Header Temperature for a Building Reference Temperature of 65F
Air
Temp
65 60 55 50 45 40 35 30 25 20 15 10
5 0
-5
-10
-15
-20
Air
Temp
70F 65F 60F 55F 50F 45F 40F 35F 30F 25F 20F 15F 10F
5F 0F
-5F
-10F
-15F
-20F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
65 65 65 65 65 65 65 65 65 65 68 69 70 71 72 73 74 75 76 77 71 73 75 77 79 81 83 85 87 89 74 77 80 83 86 89 92 95 98 101 77 81 85 89 93 97 101 105 109 113 80 85 90 95 100 105 110 115 120 125 83 89 95 101 107 113 119 125 131 137 86 93 100 107 114 121 128 135 142 149 89 97 105 113 121 129 137 145 153 161 92 101 110 119 128 137 146 155 164 173 95 105 115 125 135 145 155 165 175 185
98 109 120 131 142 153 164 175 186 197 101 113 125 137 149 161 173 185 197 209 104 117 130 143 156 169 182 195 208 107 121 135 149 163 177 191 205 219 110 125 140 155 170 185 200 215 113 129 145 161 177 193 209 116 133 150 167 201 218
Table D-4. Header Temperature for a Building Reference Temperature of 70F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
70 70 70 70 70 70 70 70 70 70
73 74 75 76 77 78 79 80 81 82
76 78 80 82 84 86 88 90 92 94
79 82 85 88 91 94 97 100 103 106
82 86 90 94 98 102 106 110 114 118
85 90 95 100 105 110 115 120 125 130
88 94 100 106 112 118 124 130 136 142
91 98 105 112 119 126 133 140 147 154
94 102 110 118 126 134 142 150 158 166
97 106 115 124 133 142 151 160 169 178 100 110 120 130 140 150 160 170 180 190 103 114 125 136 147 158 169 180 191 202 106 118 130 142 154 166 178 190 202 214 109 122 135 148 161 174 187 200 213 112 126 140 154 168 182 196 210 115 130 145 160 175 190 205 118 134 150 166 182 198 214 121 138 155 172 189 206 124 142 160 178 196 214
RESET RATIO
RESET RATIO
D-2
Page 87
APPENDIX D
Table D-5. Header Temperature for a Building Reference Temperature of 75F
RESET RATIO
Air
Temp
75F 70F 65F 60F 55F 50F 45F 40F 35F 30F 25F 20F 15F 10F
5F 0F
-5F
-10F
-15F
Air
Temp
80F 80 80 80 80 80 80 80 80 80 80 75F 83 84 85 86 87 88 89 90 91 92 70F 86 88 90 92 94 96 98 100 102 104 65F 89 92 95 98 101 104 107 110 113 116 60F 92 96 100 104 108 112 116 120 124 128 55F 95 100 105 110 115 120 125 130 135 140 50F 98 104 110 116 122 128 134 140 146 152 45F 101 108 115 122 129 136 143 150 157 164 40F 104 112 120 128 136 144 152 160 168 176 35F 107 116 125 134 143 152 161 170 179 188 30F 110 120 130 140 150 160 170 180 190 200 25F 113 124 135 146 157 168 174 190 201 212 20F 116 128 140 152 164 176 188 200 212 15F 119 132 145 158 171 184 197 210 10F 122 136 150 164 178 192 206
5F 125 140 155 170 185 200 215 0F 128 144 160 176 192 208
-5F 131 148 165 182 199 216
-10F 134 152 170 188 206
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
75 75 75 75 75 75 75 75 75 75
78 79 80 81 82 83 84 85 86 87
81 83 85 87 89 91 93 95 97 99
84 87 90 93 96 99 102 105 108 111
87 91 95 99 103 107 111 115 119 123
90 95 100 105 110 115 120 125 130 135
93 99 105 111 117 123 129 135 141 17
96 103 110 117 124 131 138 145 152 159
99 107 115 123 131 139 147 155 163 171 102 111 120 129 138 147 156 165 174 183 105 115 125 135 145 155 165 175 185 195 108 119 130 141 152 163 174 185 196 207 111 123 135 147 159 171 183 195 207 219 114 127 140 153 166 179 192 205 218 117 131 145 159 173 187 201 215 120 135 150 165 180 195 210 123 139 155 171 187 203 219 126 143 160 177 194 211 129 147 165 183 201 219
Table D-6. Header Temperature for a Building Reference Temperature of 80F
RESET RATIO
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
D-3
Page 88
APPENDIX D
Table D-7. Header Temperature for a Building Reference Temperature of 90F
RESET RATIO
Air
Temp
90F 85F 80F 75F 70F 65F 60F 55F 50F 45F 40F 35F 30F 25F 20F 15F 10F
5F 0F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
90 90 90 90 90 90 90 90 90 90
93 94 95 96 97 98 99 100 101 102
96 98 100 102 104 106 108 110 112 114
99 102 105 108 111 114 117 120 123 126 102 106 110 114 118 122 126 130 134 138 105 110 115 120 125 130 135 140 145 150 108 114 120 126 132 138 144 150 156 162 111 118 125 132 139 146 153 160 167 174 114 122 130 138 146 154 162 170 178 186 117 126 135 144 153 162 171 180 189 198 120 130 140 150 160 170 180 190 200 210 123 134 145 156 167 178 189 200 126 138 150 162 174 186 198 210 129 142 155 168 181 194 207 132 146 160 174 188 202 216 135 150 165 180 195 210 138 154 170 186 202 218 141 158 175 192 209 144 162 180 198 216
D-4
Page 89
APPENDIX E
MENU & OPTION FACTORY DEFAULT
BOILER DEFAULT SETTINGS
Setup Menu
Password 0 Language English Unit of Temp Fahrenheit Comm Address 0 Baud Rate 9600
Configuration Menu
Internal Setpt 130°F Unit Type BMK Boiler LN Unit Size 1.5 MBTU Boiler Mode Constant Setpoint Remote Signal
(If Mode = Remote Setpoint, Direct Drive or Combination)
Bldg Ref Temp (If Boiler Mode = Outdoor Reset)
4 – 20 mA / 1-5V
70°F
Reset Ratio (If Boiler Mode = Outdoor Reset)
Outdoor Sensor Disabled System Start Tmp
(If Outdoor Sensor = Enabled) Setpt Lo Limit 60°F Setpt Hi Limit 200°F
Temp Hi Limit Max Valve Position 100% Pump Delay Time r 0 min Aux Start On Dly 0 sec Failsafe Mode Shutdown Analog Output Valve Position 0-10V
CAUTION: DO NOT Change Lo Fire Timer 2 sec Setpt Limit Band (If Setpt Limiting = Enabled) 5°F
1.2
60°F
215°F
E-1
Page 90
APPENDIX E
MENU & OPTION FACTORY DEFAULT
BOILER DEFAULT SETTINGS - Continued
Configuration Menu --Continued
Network Timeout 30 seconds Hi DB Setpt En 30 Demand Offset 10 Deadband High 2 Deadband Low 2
Tuning Menu
Prop Band 70°F Integral Gain 1.00 Derivative Time 0.0 min
E-2
Page 91
APPENDIX F
B
REV.
3/4" ELECTRICAL
CONDUIT CONNECTION
LIFTING LUGS
(12.2)
4-1/16
4-13/16 (12.2)
1500
CAPACITY MBH
MIN. RELIEF VA.
28 (71.1)
14-9/16
6" EXHAUST
(37.1)
12-1/4 (31.2)
OUTLET
5-11/16
6" AIR INLET
(14.4)
36-1/4 (92.1)
45-3/4 (116.2)
18 (45.7)
THIS AREA TO BE
ACCESSIBLE FOR
MAINTENANCE.
8-1/8
(20.6)
PRESS./TEMP. GAUGE
PRESS. RELIEF VALVE
INLET CONN.
3/4" NPT GAS
1-1/2" NPT NATURAL GAS
VENT CONN.
FOR "IRI" GAS
TRAIN OPTION" ONLY
PANEL
DISPLAY
CONTROL
79-5/16
51-7/8
(201.4)
(131.8)
55-1/2
(141.0)
(99.4)
39-1/8
3 (7.6)
3"-150# FLG'D
COLD WATER
INLET CONN.
5-15/16
22-15/16
(15.1)
1-1/2" NPT
DRAIN CONN.
(58.2)
NORTHVALE, NJ 07647
BENCHMARK 1.5 MIL. LOW NOx BTU
AERCO
UNIT FLUSH AT REAR
4" CONCRETE PAD - SET
GAS FIRED BOILER
AP-A-832
A
101807
SIZE
DATE
DIMENSIONAL DRAWINGS
JK
REV.DATE
CHKD. APPD.
DWN.BY
SCALE
HT'G SURFACE
TEST PRESS.
MAXIMUM
HEAT EXCHANGERS & COMBUSTION CHAMBER DESIGN STANDARDS
MAX. WORKING
110
SQ.FT.
240
(PSIG)
TEMP. (°F)
160 210
PRESS. (PSIG)
ASME B & PV CODE: SECTION IV STAMP H (PRIMARY H.X.)
SECTION VIII STAMP U (SECONDARY H.X.)
3"-150# FLG'D
HOT WATER OUTLET CONN.
64-3/4
164.5)
(62.4)
24-9/16
(23.6)
9-15-/16
(25.9)
10-3/8
12-7/8 (32.8)
24-1/8 (61.3)
21-11/16 (55.0)
12-15/16 (32.9)
2) RELIEF VALVE, TRIDICATOR & CONDENSATE TRAP ARE INCLUDED SEPARATELY IN SHIPMENT.
1) ALL DIMENSIONS SHOWN ARE IN INCHES (CENTIMETERS).
NOTES:
F-1
Page 92
APPENDIX F
A
REV
REAR
INTERNATIONAL, INC.
NORTHVALE, NJ 07647
GAS FIRED BOILER
AERCO
BENCHMARK 1.5 LOW NOx
SD -A -730
*NOT TO SCALE*
ANCHOR BOLT LOCATION
DRWN BY:SJD
DATE:10/12/07
F-2
FRONT
1) ALL HOLES ARE FLUSH WITH THE BOTTOM SURFACE OF THE FRAME
2) ALL DIMENSIONS SHOWN ARE IN INCHES (CENTIMETERS)
NOTES:
Page 93
APPENDIX F
F-3
Page 94
APPENDIX F
A
REV
24"
24"
28"
42"*
24"
FRONT
REAR
1) REAR CLEARANCE MAY BE REDUCED TO 30" DEPENDENT UPON
NOTES:
AND LOCAL CODE REQUIREMENTS
PIPING AND VENTING COMPONENT SELECTION, ARRANGEMENT,
INTERNATIONAL, INC.
NORTHVALE, NJ 07647
BENCHMARK 1.5 LOW NOx
AERCO
GAS FIRED BOILER
INSTALLATION CLEARANCES
DRWN BY: SJD
SD - A - 731
*NOT TO SCALE*
DATE: 10/12/07
SIDE VIEW TOP VIEW
18"
44.5"
101"
79"
LEFT & RIGHT SIDES: 24"
FRONT: 24"
REAR: 42" *
CEILING HIEGHT: 101"
F-4
INSTALLATION CLEARANCES:
1) THIS APPLIANCE MAY BE INSTALLED ON COMBUSTIBLE FLOORING
2) MINIMUM CLEARANCES TO ADJACENT CONSTRUCTION ARE AS
FOLLOWS:
Page 95
APPENDIX F
F-5
Page 96
APPENDIX F
1.5" FULL
PORT BALL
VALVE
P/N: 92006-7
B
REV
TEST
COCK
HIGH GAS PRESSURE
SWITCH P/N: 61002-3
SAFETY SHUT-OFF VALVE
ACTUATOR P/N: 64048
LOW GAS PRESSURE
1/8" NPT PLUG
(INSTALL MANOMETER
HERE)
SWITCH P/N: 61002-1
INTERNATIONAL, INC.
NORTHVALE, NJ 07647
AP - A - 830
IRI GAS TRAIN
*NOT TO SCALE*
AERCO
P/N: 124178
CONNECTING FLANGE
1.5" DOUBLE BODY SSOV
1.5" SCH.40 PIPE
3/4" SCH.40 PIPE
VENT TO ATMOSPHERE
PER ANSI Z223.1 (NFPA54)
BENCHMARK 1.5 LOW NOx
DRWN BY:SJD
DATE:10/11/07
F-6
1.5" DOUBLE BODY
SSOV P/N: 124137
ENTIRE BMK 1.5 LN IRI GAS
TRAIN P/N: 22039-2
NORMALLY OPEN
VENT VALVE
P/N: 122774
SAFETY SHUT OFF VALVE ACTUATOR WITHOUT
PROOF OF CLOSURE SWITCH P/N: 69038
Page 97
APPENDIX F
F-7
Page 98
APPENDIX F
F-8
EXHAUST MANIFOLD
ITEM PART NO. QTY DESCRIPTION
43045 1 EXHAUST MANIFOLD
1
84020 1 EXHAUST MANIFOLD SEAL
2 3
GAS TRAIN ASSEMBLY
ITEM PART NO. QTY DESCRIPTION
22039-1 22039-2
4
(3)
22039-3 22039-4
BLOWER, BURNER & AIR/FUEL VALVE
ITEM PART NO. QTY DESCRIPTION
5 24111 1
6 24010-2 1 A/F VALVE ASSEMBLY
7 24226 1
8 81063 2 BURNER GASKET
STD FM GAS TRAIN ASSBLY
IRI GAS TRAIN ASSEMBLY
1
DUAL FUEL FM GAS TRAIN
DUAL FUEL IRI GAS TRAIN
BLOWER ASSEMBLY
BMK1.5LN STAGED
IGNITION ASSY.
HOSES,GASKETS, & INSULATION
ITEM PART NO. QTY DESCRIPTION
22 88003 1 O-RING #2-339 (A/F VALVE)
24 88004 1
25 62005 1 CORD GRIP
O-RING #2-244 BUNA - N (BLOWER)
9 46015 1 BURNER
HEAT EXCHANGER
ITEM PART NO. QTY DESCRIPTION
10 80036 1
11 80035 1
12 28017 1
13
ITEM PART NO. QTY DESCRIPTION
15 123815 1 IRIS AIR DAMPER
16 81064 1 BLOWER GASKET
17 39054 1 ADAPTOR, AIR INLET
18 39059 1
19 97004-18 1 HOSE, FLEXIBLE 6" I.D. - A/F
20 123583 3 CLAMP HOSE SAE #96
21 81057 1 BLOWER GASKET (A/F)
HEAT EXCHANGER
UPPER INSULATION
HEAT EXCHANGER
LOWER INSULATION
HEAT EXCHANGER
BLOWER
CAP, SCREENED, AIR INLET 6"
AERCO
NORTHVALE, NJ 07647
BENCHMARK 1.5 LOW NOx
BOILER PARTS LIST
INTERNATIONAL, INC.
F-8
DRWN BY:SJD DATE:12/08/08
*NOT TO SCALE*
PL - A - 157
(SHEET 1 OF 7)
REV
D
Page 99
APPENDIX F
F-9
CONTROLS
ITEM PART NO. QTY
26 65090 1
27 123966 1 OVER TEMP SWITCH AUTO
28 123552 1 OVER TEMP SWITCH MANUAL
29 61002-5 1
30 60011-1 1
31 161560 1 I /O WIRING BOX
32 181197 1 C-MORE CONTROL BOX
33
GP-122464
34 33048 1 VFD MOUNTING BRACKET
36 61024 1 AIR TEMP SENSOR
38
(1)
(1)
(5)(1)
(6)
(7)(5)
GP- 122569
39 63016 1 BMK1.5LN SHELL HARNESS
40 63038 1 BLOWER HARNESS
42 64059 1 120V POWER WIRING BOX
43 161450 1
44 122843 1 LOW WATER CUT-OFF
45 123449 1 SHELL TEMP. SENSOR
46 161521 1
47 61002-1 1
61002-12
48
61002-12
61002-3
49
1 IGNITION TRANSFORMER
1 IGNITION CABLE ASSY.
BMK1.5LN GAS TRAIN WIRING
1
DESCRIPTION
DRIVE REACTOR
BLOCKED INLET SWITCH
BLOWER PROOF SWITCH
HARNESS
THERMOWELL, DUAL AQUASTAT BULB
LOW GAS PRESSURE SWITCH
HIGH GAS PRESSURE SWITCH
(NON DUAL FUEL)
DUAL FUEL HGPS - NAT. GAS
DUAL FUEL HGPS - PROPANE
OTHER DUAL FUEL COMPONENTS
ITEM PART NO. QTY DESCRIPTION
56 72031 1 "PROPANE" LABEL
(4)(1)
57 72032 1 "NAT. GAS" LABEL
(4)(1)
58 63032 1
(5)(4)(1)
59 65024 1 FUEL SELECTOR SWITCH
(4)
60 33036 1
(4)(1)
61 72030 1
(4)
62 63034 1 DUAL FUEL WIRING HARNESS
(4)(1)
63
SHEET METAL / PANEL ASSEMBLY
ITEM PART NO QTY DESCRIPTION
64 37017 1 LEFT REAR PANEL
65 37018 1 RIGHT REAR PANEL
66 49064 2 TOP RAIL
67 201233 1 MOUNTING PANEL
68 201113 1
69 201120 1 FRONT DOOR ASSY.
70
GP-122620
71 37019 2 TOP PANEL
72 37002 4 SIDE PANEL
73 74003 1 BMK1.5LN LOGO
OTHER PARTS
ITEM PART NO QTY DESCRIPTION
74 99017 1
DOUBLE GAS TRAIN WIRING
FUEL SELECTOR SWITCH LABEL
4HANDLE
HARNESS
FUEL SELECTOR SWITCH
MOUNTINGBRACKET
FRONT PANEL
ENCLOSURE
GAS PRESSURE SNUBBER -
PART OF GAS TRAIN
OTHER ACCESORIES / PARTS
ITEM PART NO. QTY DESCRIPTION
50 69087- 1 PRESS./TEMP. GAUGE
(2)
(1)
51
SEE SD-A-751
52 92006-7 1
(1)(6)
54 92006-7 1 1-1/2" NPT BALL VALVE
(5)
55 24060 1 COND. TRAP ASSEMBLY
(1)
1 PRESSURE RELIEF VALVE
EXT. MANUAL SHUT-OFF VALVE
NOTES:
NOT SHOWN IN DRAWING
(1) (2)
-5 (30 AND 50 PSI RELIEF VALVE SETTING)
-6 (60,75,100 & 125 PSI RELIEF VALVE SETTING)
-7 (150 PSI RELIEF VALVE SETTING)
(3)
FOR PICTORAL PURPOSES ONLY, FM GAS TRAIN (NON DUAL FUEL) IS SHOWN
ONLY NEEDED ON DUAL FUEL
(4) (5)
PART OF GAS TRAIN ASSY. TWO (2) REQUIRED FOR DUAL FUEL BMK1.5 LN(6)
(7)
SEE DRAWING AP-A-833 FOR DUAL FUEL DETAILS
AERCO
INTERNATIONAL, INC. NORTHVALE, NJ 07647
BENCHMARK 1.5 LOW NOx
BOILER PARTS LIST
DRAWN BY: SJD DATE: 12/08/08
*NOT TO SCALE*
PL - A - 157
(SHEET 2 OF 7)
D
F-9
Page 100
APPENDIX F
F-10
F-10
Loading...