Zebra Technologies MM718101 Installation Guide

AP 7181 Access Point
Installation Guide
Version 1.0.0.A
March 12, 2010
68009287001
Contents
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Document Conventions . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2 Hardware Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.2 Deployment Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.3 Installation Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.4 Grounding Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.5 Minimum Installation Requirements . . . . . . . . . . . . . . . . . 5
2.6 Package Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.7 Access Point Placement . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.7.1 Site Surveys . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.7.2 Root Node Placement . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.7.3 Non Root Node Placement . . . . . . . . . . . . . . . . . . . . . . . 6
2.7.4 Mounting Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.7.5 Device Deployment Height . . . . . . . . . . . . . . . . . . . . . . . 7
2.8 Antenna Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.9 AP 7181 Power Options . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.9.1 Power Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.10 Mounting an AP 7181 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.10.1 Pole Mounted Installations. . . . . . . . . . . . . . . . . . . . . . 10
2.11 Installing an AP 7181 . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.11.1 Required Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.11.2 AP 7181 Connections and Ports. . . . . . . . . . . . . . . . . . 11
2.11.3 LED Status Indicator Panel . . . . . . . . . . . . . . . . . . . . . 14
2.11.4 Removing the AP 7181 Kit from the Shipping Carton 15
2.11.4 Staging the Device Prior to Installation . . . . . . . . . . . . 17
2.12 Field Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
2.12.1 Bottom Mount Installation . . . . . . . . . . . . . . . . . . . . . . 25
2.12.2 Top Mount Installation. . . . . . . . . . . . . . . . . . . . . . . . . 33
2.13 Remote Panel Antenna Installation. . . . . . . . . . . . . . . . . 42
2.13.1 Preparing the AP 7181 . . . . . . . . . . . . . . . . . . . . . . . . . 45
2.13.2 Installing the Remote Panel Antenna. . . . . . . . . . . . . . 47
2.13.3 Installing the Blank Antenna Panel . . . . . . . . . . . . . . . 51
3 Getting Started . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
3.1 Initially Connecting to the Access Point. . . . . . . . . . . . . . 55
3.1.1 Connecting to the Access Point Using the WAN Port. . 56
3.1.2 Connecting to the Access Point Using the LAN Port . . 57
3.2 Basic Device Configuration . . . . . . . . . . . . . . . . . . . . . . . 59
3.2.1 Configuring Device Settings . . . . . . . . . . . . . . . . . . . . . 61
3.2.2 Configuring WLAN Security Settings. . . . . . . . . . . . . . 69
3.2.3 Creating a Secure Recovery WLAN . . . . . . . . . . . . . . . 71
3.2.4 Testing Connectivity . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
3.2.5 Creating a Mesh Point . . . . . . . . . . . . . . . . . . . . . . . . . . 78
3.3 Where to Go From Here? . . . . . . . . . . . . . . . . . . . . . . . . . 84
4 Regulatory Compliance. . . . . . . . . . . . . . . . . . . . . . . . . . . 85
4.1 Health and Safety Recommendations . . . . . . . . . . . . . . . 85
4.1.1 Warnings for the Use of Wireless Devices . . . . . . . . . . 85
4.1.2 Potentially Hazardous Atmospheres . . . . . . . . . . . . . . . 85
4.1.3 Reducing RF Exposure - Use Properly . . . . . . . . . . . . . 85
4.2 Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
4.3 FCC Regulatory Information . . . . . . . . . . . . . . . . . . . . . . 86
4.3.1 RF Exposure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
4.3.2 Intentional and Unintentional Radiators . . . . . . . . . . . . 86
4.3 Canada Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
5 Customer Support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
MOTOROLA and the Stylized M Logo are registered in the US Patent & Trademark Office. All other product or service names are the property of their respective owners. © Motorola, Inc. 2010. All rights reserved.
Introduction
!
1Introduction
The purpose of this document is to provide installation and setup procedures for Motorola’s AP 7181 Access Point.
The AP 7181 is a wireless broadband data system that uses mesh networking technology to support wide-area broadband data coverage. The system offers both 2.4 GHz 802.11b/g/n and 5.x GHz 802.11n Wi-Fi client access with 2.4 GHz 802.11 b/g/n and 5.x GHz 802.11a/ n meshing. The dual-band system supports industry standard client devices and features easily deployed fixed infrastructure nodes.
The AP 7181 is also designed to meet the needs of large, distributed outdoor networks. The network can be configured and managed for optimal performance using the Wireless Manager (WM) network Management application.
1
The most current versions of this manual and other AP 7181 documentation can be found at:
http://motorola.wirelessbroadbandsupport.com/support/mesh/library
1.1 Document Conventions
The following graphical alerts are used in this document to indicate notable situations:
NOTE Tips, hints, or special requirements that you should take note of.
CAUTION Care is required. Disregarding a caution can result in data loss
or equipment malfunction.
WARNING! Indicates a condition or procedure that could result in personal
injury or equipment damage.
2
!
AP 7181 Access Point: Installation Guide
2 Hardware Installation
An AP 7181 access point installation includes mounting the access point, connecting the access point to the network, and applying power. Installation procedures vary for different environments.
2.1 Precautions
Before installing an AP 7181 model access point verify the following:
Become familiar with grounding requirements (see Grounding Requirements).
Verify the environment has a continuous temperature range between -40° C to 55° C.
AP 7181 devices must be installed by trained professionals familiar with RF planning and regulatory limits defined by the regulatory bodies of the country where the devices are being deployed. All common precautions for grounding and ESD (Electrostatic Discharge) protection should be observed during deployment and installation. AP 7181 devices are designed to be installed outdoors and must be installed such that no harmful interference results from device operation.
CAUTION All device wiring must comply with the National Electric code
(NEC) or regulations and procedures defined by the regulatory bodies of the country or region where the devices are being deployed. All local building and structure codes must be observed.
WARNING! Strictly observe the following Safety Precautions during the AP
7181 Installation Procedure.
Installations must be performed by professionals who are properly trained and certified.
Avoid contact with overhead power lines.
Hardware Installation
Take precautions to avoid injury from falling tools and equipment. Crews should
wear hardhats in and around the installation work site.
Be aware of vehicular traffic in and around the installation work site.
Do not hold any component containing a radio such that the antenna is very close
to or touching any exposed parts of the body, especially the face or eyes, while transmitting.
Do not operate a portable transmitter near unshielded blasting caps or in an
environment where explosives are present unless the transmitter is especially certified for such use.
2.2 Deployment Guidelines
Observe the following recommended guidelines to help ensure a successful network deployment:
3
Mounting height for network devices should not exceed 30 to 35 feet. Mounting
height should vary to accomodate the topography of the deployment area, foliage, and other obstructions.
Devices can be deployed using either the Bottom Mount Installation or the Top
Mount Installation procedure.
Point-to-Point (PTP (Slave)) or Point-to-Multipoint (PMP (SM)) nodes providing
backhaul should be oriented to point away from AP 7181 antenna panels.
NOTE For more detailed deployment considerations for backhaul, refer
to the Mesh AP 7181 System Planner.
Custom stand-off brackets should be used as required to provide adequate pole
separation in an an effort to minimize reflective received power.
LoS guidelines should be given special consideration whenever devices will not be
installed in a straight line, such as deploying devices on alterating sides of a roadway.
Ensure that all Root nodes are deployed with line of site to the wireless backhaul
cluster points.
4
!
AP 7181 Access Point: Installation Guide
2.3 Installation Methodology
Consideration of the order in which units are installed when deploying an AP 7181 wireless network can work to ensure a more stable and functional network. The PTP backhaul layer should be deployed first. Next deploy all nodes for the PMP Access Point distribution layer. Next deploy Root nodes along with PMP Subscriber Modules (SMs) such that backhaul and network connectivity can be verified or corrected. Finally, deploy all Mesh Point wireless nodes in order of the least to most hops (1 hop nodes first, followed by 2 hop nodes, etc.).
2.4 Grounding Requirements
To avoid damage to the equipment, become familiar with Motorola Policy R56 before installing AP 7181 units. Refer to Standards and Guidelines For Communication Sites, Version B. Both the hardcopy manual (Part Number 68P81089E50-B) and the CD version (Part Number 9880384V83) can be ordered from Motorola.
Section 7.6.4 Broadband - Wireless Access Point Network from the Standards and
Guidelines For Communication Sites applies directly to AP 7181 deployments:
SPD (Surge Protection Device) considerations for broadband shall include the use of SPDs to protect pole-mounted access points and ground-based cabinet architecture. It is important to install proper SPD applications on both ends of Ethernet, Power-Over Ethernet (POE), Giga-Ethernet (GigE) and AC cable runs. SPDs shall be located within the node or cabinet, or as close to the entrance as possible, and properly installed into load centers, control panels and utility power cabinets. While RF protection is a consideration, it shall only be required when antennas are connected to the node with coaxial cables greater than 610 mm (2 ft.) in length.
CAUTION It is required that all root and portal nodes be adequately
grounded. In addition, all root nodes and portals using the Ethernet port or attached devices (e.g. a camera) must not only be grounded, but they should also include surge suppression for network reliability. This is particularly important for network configurations with a public safety component.
When grounding a unit installed on a wooden pole, a ground conductor and rod is required. This requirement should be factored into the project deployment costs, particularly if the equipment must be installed by a utility company.
Hardware Installation
2.5 Minimum Installation Requirements
The minimum requirements for installing an AP 7181:
AP 7181 Access Point
Power Cable (Flying Leads)
Standard Ethernet cable
Yoke (attached)
22 mm Socket and driver to remove port caps
#6 metric Allen Wrench to remove the Yoke (if a top mounted installation is
required)
2.6 Package Contents
5
Check the package contents for the AP 7181. Each unit should contain:
AP 7181 Access Point (assembled with Mounting Yoke attached)
Power Cable
Optional accessories (in a separate box inside the AP 7181 shipping container)
Contact the Motorola Support Center to report missing or improperly functioning items. Refer to Customer Support.
2.7 Access Point Placement
Typically, roadways in the deployment area become main arteries for the wireless mesh network. Roadways can provide LoS coverage over large distances between Root and Non Root APs.
2.7.1 Site Surveys
Motorola recommends conducting a site survey prior to installing an access point. A thorough site survey must include a visit to the customer site to identify the characteristics of the coverage area, including availability of electrical distribution for power sources and the location of existing network infrastructure.The site survey should also include preliminary WLAN measurements to identify candidate AP locations
When scheduling a visit to conduct a site survey, request access to wiring closets, adjacent floors, and other locations that may require special permission.
6
AP 7181 Access Point: Installation Guide
2.7.2 Root Node Placement
When planning for Root Node placement:
Identify Root node wireless backhaul technology (Point-to-Point (PTP), Point-to­Multipoint (PMP)).
Identify Ethernet or fiber optic backhaul.
Identify Root node locations.
Obtain all required permits and/or lease agreements.
Verify that power is available at each potential node deployment location.
Give careful consideration to the fact that Root nodes with a wireless backhaul usually backhaul traffic to a cluster point (i.e. PMP Canopy).
Wireless backhaul clusters can be on towers, rooftops, etc.
Ensure that all Root nodes are deployed with LoS to cluster points.
2.7.3 Non Root Node Placement
The same guidelines as Root nodes apply with the exception of a backhaul requirement
The placement of Non Root nodes will depend heavily on the RF network design. Consider the guidelines for optimizing wireless network performance when identifying potential mounting sites.
In addition, consider the following when planning for Non Root node placement:
Light Poles, Utility Poles, or Traffic Poles
Obtain all required supplemental agreements from local governments and
utilities.
Obtain a generic mounting agreement that is not specify specific poles, since
installation locations may need to be modified during deployment.
Plan for AC power usage of 84 watts average, 126 watts peak.
The AP 7181 is rated for wind loading of up to160 mph.
Ensure that proper grounding can be established.
Rooftops and Towers
May require lease agreements.
Identify AP locations based on optimal communication with the Root nodes.
Non Root node placement will be dependent on asset availability, terrain, etc.
Hardware Installation
Ensure that nodes are placed at the same height.
Build the network outward from each root node, from least to greatest number of
hops.
As with Root nodes, it should be noted that it is incumbent upon the customer to obtain the required Pole Attachment Agreements for devices to be installed on traffic / utility poles. Obtaining the agreements can be a lengthy process, so ample lead time must be allowed.
The potential pole locations should be logged with GPS to obtain accurate coordinates. Also log any identifying numbers on the pole so that this information can be provided to the appropriate utility agency. Alternate mounting locations should also be identified in the event that your initial request is denied.
Specialized brackets may be required for attaching devices to decorative light poles and these brackets may have to be custom fabricated. If this is the case, allow enough lead time for ordering the proper equipment.
7
Also consider any requirements to coordinate requests with multiple utility agencies within the same community. Verify that light pole selections have power available continuously and that the power source is within the operational range of the device being connected.
2.7.4 Mounting Locations
To avoid distortion of the RF pattern, device locations should be chosen such that the AP 7181 ADvanced Element Panel Technology (ADEPT) antenna panels are at least 30 inches from any nearby metal poles and not co-located or operating in conjunction with any other antenna or transmitter.The antenna panels must also have a separation distance of at least 2 meters from anyone who may come into proximity of the AP 7181.
2.7.5 Device Deployment Height
AP 7181 nodes are typically mounted at a height of 30 to 35 feet. Ensure that neighboring nodes are mounted at or near the same device height.
Excessive height should be avoided since this may result in increased congestion and interference in dense RF environments. This is especially true for the 2.4 GHz band.
Nodes deployed with too great a difference in height or too close to each other may not mesh properly.
8
AP 7181 Access Point: Installation Guide
Always consider these general guidelines for device deployment height:
Maintain a typical deployment height of 30 to 35 feet.
For optimum performance, ensure that devices are oriented to have LoS to all neighboring devices.
Locate Root Nodes which support Wireless Backhaul so that they have LoS to Backhaul clusters or PTP locations, such as towers.
2.8 Antenna Options
The AP 7181 features an integrated ADvanced Element Panel Technology (ADEPT) antenna system that is designed to take full advantage of the 802.11n radios. No other antennas are supported.
2.9 AP 7181 Power Options
Details of the power sourcing equipment for the AP 7181 should be handled by a professional installer. The requirements for deploying the system are:
Over current protection device with a maximum rating of 20 Amps.
AP 7181 AC Model - 100-240 VAC input capable of sourcing 180 watts.
AP 7181 DC Model - Nominal 48 Volt Power source (41-58 VDC) capable of sourcing 150 watts. Battery floating voltage should not exceed 60 VDC.
2.9.1 Power Cables
Flying lead power cables are available based on the country of operation.
Four Wire AC Right Angle Power Cable
(North America and International)
Three Wire AC Power Cable
Black (Line)
White (Neutral)
Red (Unused)
Green/Yellow (Ground)
Brown (Line)
(International)
Two Wire DC Power Cable
(North America and International)
Blue (Neutral)
Green/Yellow (Ground)
Black (Negative)
Red (Positive)
Hardware Installation
!
!
CAUTION Never plug a power cable wired to a power source for an AC
unit into a DC unit.
If the units will be plugged directly into an electircal wall outlet, power plug adapters are available for North America, Europe, and Australia.
CAUTION Do not use the connector on the power cables for
interrupting current. Never actively plug or unplug the connector while the cable is energized.
9
2.10 Mounting an AP 7181
The AP 7181 is designed for outdoor installations. All hardware installations should be performed by a professional installer.
Devices can be deployed using either the Bottom Mount Installation or the Top Mo unt
Installation procedure.
Mounting options are available for light pole, building roof tops, and building walls. Choose one of the following mounting options based on the physical environment coverage area requirements.
10
AP 7181 Access Point: Installation Guide
2.10.1 Pole Mounted Installations
The optional Wall Gooseneck can also be used with the Pole Adapter for pole mounting.
The Wall Gooseneck dimensions are 10x12x6 inches and it weighs 4 pounds. The Pole Adapter dimensions are 4x2.62x7 inches and it weighs 3 pounds.
The Gooseneck attaches to the Yoke, which can be attached to the top or the bottom of the AP 7181. Secure the Gooseneck and adaptor to the pole using band clamps with the threaded portion pointing either up or down.
If using a bottom mount, drill a 1/4 inch diameter hole at the lowest point on the bend to allow water to drain from the Gooseneck.
2.11 Installing an AP 7181
The following guidelines and procedures should be observed when installing an AP 7181 device.
2.11.1 Required Tools
The following is a list of the minimal tool set required to install an AP 7181 device:
24 mm Socket and driver - for cable gland
22 mm Socket and driver - for GE1 and GE2 port caps
19 mm Socket and driver - for Console port cap
21 mm Socket and driver - for set screw
8 mm Socket and driver - for ground screw
6 mm Allen Wrench bit - for mounting bracket (Yoke)
T27 Torx bit - for the Sun Shields
Hardware Installation
Torque Screwdriver - for the Sun Shields
Torque Wrench
Adjustable Wrench
Standard Level
Tube of Lithium Grease
2.11.2 AP 7181 Connections and Ports
The power cable and grounding connections, power indicator light, Ethernet and reset ports, and LED Status Panel on the bottom the AP 7181 are shown in the figure below.
11
12
AP 7181 Access Point: Installation Guide
The Horizontal (HP) and Vertical (VP) connectors for the antenna cables are loacted on the top of the AP 7181.
All Radome antenna panel cables are labeled as HP or VP. Attach each cable to the corresponding connector when performing a Remote Panel Antenna Installation or any other procedure which requires attaching antenna cables to the connectors.
Hardware Installation
!
WARNING! When disconnecting the antenna cables from the unit or
removing an antenna panel and replacing it with a Blank panel, terminators MUST be placed on the unused horizontal and vertical connectors on the top of the unit.
13
CAUTION It is also recommended that the antenna cable connectors and
terminators on the horizontal and vertical connectors on the top of the AP 7181 be wrapped with both mastic tape and electrical tape.
14
AP 7181 Access Point: Installation Guide
2.11.3 LED Status Indicator Panel
There are six LEDs on the AP 7181 which are visible on the bottom of the unit through light pipes.The LEDs have the following display characteristics and functionality:
LED 1 LED 2 LED 3
Blinking
Red
indicates
booting.
Solid Red
defines a
failure
condition.
White defines normal
operation
Green
defines
normal GE1
operation.
Yellow
defines a
collision
Green
defines
normal GE2
operation.
Yellow
defines a
collision
LED 4 - 5
GHz
Amber
defines 5
GHz radio as
configured.
LED 5 - 2.4
GHz LED 6
Emerald
defines 2.4
GHz radio as
configured.
Not used
Hardware Installation
!
2.11.4 Removing the AP 7181 Kit from the Shipping Carton
CAUTION Never lift an AP 7181 using the Radome antenna panels or
other plastic parts. Always lift the unit by the Yoke or metal antenna rings.
WARNING! An AP 7181 weighs 39 pounds. Use all appropriate cautions
when lifting and consider a two man lift when necessary.
1. Open the shipping carton and remove top packaging material.
15
16
AP 7181 Access Point: Installation Guide
2. Remove the accessories pack from the shipping carton.
In the accessories box, you will find the following items:
Water Proof Ethernet Adaptor (Cable Gland) (Part number: 09009302001)
Power Cable (Part number: 30009307001, 30009308001, or 30009315001)
Sun Shields with Captive Screws (Part number: HKLN4446A)
Hardware Installation
!
3. Open the plastic bag covering the unit.
4. Roll the plastic bag to the bottom of the shipping carton and using the Yoke or Antenna Ring, carefully remove the unit from the box . Using this method will help prevent damage to the antenna assembly.
2.11.5 Staging the Device Prior to Installation
WARNING! An AP 7181 weighs 39 pounds. Use all appropriate cautions
when lifting and consider a two man lift when necessary.
1. Place on solid surface with the Yoke facing up.
17
CAUTION Never lift an AP 7181 using the Radome antenna panels or
other plastic parts. Always lift the unit by the Yoke or metal Antenna rings.
2. Using the 6mm Allen Wrench, loosen the Allen head bolts to remove the Yoke.
18
AP 7181 Access Point: Installation Guide
3. To gain access to the Ethernet and or console ports you will need to remove the protective caps. A 22 mm socket will be required to remove the Ethernet port caps covering Gigabit Ethernet ports GE1 and GE2. A 19 mm socket is required to remove the console port cap (if required).
4. Using the 22 mm socket remove the port caps for Gigabit Ethernet GE1 and GE2.
5. Remove the cap on the cable gland as shown below.
Hardware Installation
6. Carefully hand tighten the gland into Gigabit port GE1. Once the gland is snug, use
a 24 mm socket and finishing tighten the gland.
19
If the node is going to be configured as a Mesh Point Root node (Mesh Point Root nodes have a direct wired Ethernet connection to the core network or an Ethernet connection to a wireless backhaul) a cable gland will be required for Gigabit Ethernet port GE1.
20
AP 7181 Access Point: Installation Guide
If the Mesh Point Root node is also going to have an external device attached (e.g. surveillance camera) an additional cable gland will be required for Gigabit Ethernet port GE2 (make sure the WAN port GE2 has been configured to permit an attached external device during the configuration process).
NOTE The AP 7181 supports 802.af compliant Power over Ethernet
(PoE) on Ethernet port GE1 and can provide power to an external PoE capable device such as a surveillance camera. PoE is auto sensing and is enabled when the AP-7181 senses a PoE capable device.
Hardware Installation
If the device being staged is a Mesh Point node (no wired connection to the core network) and no external device is going to be attached then no cable glands are required.
21
If the Mesh Point node is going to have an external device attached (e.g. surveillance camera) a cable gland is required for Gigabit Ethernet port GE1.
22
AP 7181 Access Point: Installation Guide
7. Repeat the process if a second cable gland is required.
8. Attach an Ethernet cable to Gigabit Ethernet port GE2 (to be used with an external laptop for configuring the unit). You will also need to terminate the flying lead power cable with the proper plug (for the country of operation) so the unit can be powered for configuration. After preparing the power cable attach the cable to the power port. Notice that the power connector is keyed. Next configure the unit. Refer to Getting Started for initial device configuration.
Hardware Installation
9. After the unit has been configured, if the GE2 port is not going to be used to attach
an external device to the AP7181, reattach the port cap. If the GE2 port is going to be used to attach and external device, attach the cable gland to the GE2 port.
23
10. Reattach the Yoke.
11. Return the unit to the shipping carton for transport to the installation site. Due to
the nature of the electronic components and antenna array, using the shipping carton is the most secure method for transport.
Loading...
+ 67 hidden pages