COPYRIGHTS & TRADEMARKS: For complete copyright and trademark information,
go to www.zebra.com/copyright.
WARRANTY: For complete warranty information, go to www.zebra.com/warranty.
END USER LICENSE AGREEMENT: For complete EULA information, go to www.zebra.com/eula.
For Australia Only
For Australia Only. This warranty is given by Zebra Technologies Asia Pacific Pte. Ltd., 71 Robinson Road, #0502/03, Singapore 068895, Singapore. Our goods come with guarantees that cannot be excluded under the
Australia Consumer Law. You are entitled to a replacement or refund for a major failure and compensation for any
other reasonably foreseeable loss or damage. You are also entitled to have the goods repaired or replaced if the
goods fail to be of acceptable quality and the failure does not amount to a major failure.
Zebra Technologies Corporation Australia’s limited warranty above is in addition to any rights and remedies you
may have under the Australian Consumer Law. If you have any queries, please call Zebra Technologies
Corporation at +65 6858 0722. You may also visit our website: www.zebra.com for the most updated warranty
terms.
Terms of Use
•Proprietary Statement
This manual contains proprietary information of Zebra Technologies Corporation and its subsidiaries
(“Zebra Technologies”). It is intended solely for the information and use of parties operating and
maintaining the equipment described herein. Such proprietary information may not be used, reproduced,
or disclosed to any other parties for any other purpose without the express, written permission of Zebra
Technologies.
•Product Improvements
Continuous improvement of products is a policy of Zebra Technologies. All specifications and designs are
subject to change without notice.
•Liability Disclaimer
Zebra Technologies takes steps to ensure that its published Engineering specifications and manuals are
correct; however, errors do occur. Zebra Technologies reserves the right to correct any such errors and
disclaims liability resulting therefrom.
•Limitation of Liability
In no event shall Zebra Technologies or anyone else involved in the creation, production, or delivery of the
accompanying product (including hardware and software) be liable for any damages whatsoever
(including, without limitation, consequential damages including loss of business profits, business
interruption, or loss of business information) arising out of the use of, the results of use of, or inability to
use such product, even if Zebra Technologies has been advised of the possibility of such damages. Some
jurisdictions do not allow the exclusion or limitation of incidental or consequential damages, so the above
limitation or exclusion may not apply to you.
2
Revision History
Changes to the original guide are listed below:
ChangeDateDescription
-01 Rev A4/2019Initial Release
-02EN Rev A3/2020- Updated minimum server requirements.
- Updated ATR installation procedures and post installation integration of
ATR7000 with CLAS software.
Tag Board Construction Guidelines ................................................................................................ 56
6
About This Guide
Introduction
This guide provides a comprehensive overview of how to ensure a successful deployment of Zebra’s Advanced
Asset Tracking System (ZAATS) comprised of ATR7000 RTLS overhead readers and Configuration and Analytics
Software (CLAS.)
The objective of this document is to describe the requirements and use case definition, detailed system design
process (including site survey), installation of reader and networking hardware, and post-installation validation of
the ZAATS system. Details of server and software installation are covered in the CLAS Server and Software
Installation Guide, and programming information to support application development are covered in the CLAS API
Developer Guide.
Chapter Descriptions
Topics covered in this guide are as follows:
•ZAATS Introduction provides an overview of Zebra’s Advanced Asset Tracking System, including
ATR7000 overhead RFID readers and CLAS (RTLS Services) software.
•Deployment Overview provides an overview of the ZAATS deployment process.
•Requirement Definition defines the first steps in the deployment process, including team roles and
responsibilities, and defining the identification and location use cases and overall system requirements.
•Preliminary System Design provides a comprehensive overview of the steps that lead to a complete
pro-forma definition of the system, including reader coverage, network design, tag selection, developing
the site map, Equipment Manifest, and bill of materials.
•Site Survey describes the steps and guidelines on how to perform an effective site survey.
•Completing the Final System Design describes the steps involved to finalize the pre-installation site map
and bill of materials based on the results of the site survey.
•Installation of CLAS Server Software references the Zebra documentation used to install CLAS (RTLS
Services) software.
•Installation of ZAATS Reader and Network Hardware provides the detailed steps involved in hardware
installation and how to ensure the reader and network hardware is fully functional.
•Post-Installation ZAATS Validation provides the detailed steps involved to ensure ZAATS can locate and
track items and is ready for handover to an end user.
•Appendix: Tools and Resources lists some helpful resources that can aid in the deployment of ZAATS.
•Appendix: Leica 3D Instructions for ATR7000 describes the steps on how to use Leica 3D DISTO for the
ATR7000 installation.
7
•Appendix: RFID Tag Board for ATR7000 Installation and Validation provides guidelines on tag placement
to test an ATR performance after installation.
Related Documents
The following documents provide more information about ZAATS.
•ATR7000 Advanced Array RFID Reader Integration Guide, p/n MN-003191-xx
•RFID Demo Applications User Guide, p/n 72E-160038-xx
•RTLS Demo Application User Guide, p/n MN-003509-xx
•CLAS API Developer Guide, p/n MN-003198-xx
•CLAS Server & Software Installation Guide, p/n MN-003197-xx
•ZAATS Tag Data & Numbering Guide, p/n MN-003199-xx
About This Guide
For the latest version of this guide and all guides, go to: zebra.com/support
.
8
ZAATS Introduction
Introduction
Zebra’s Advanced Asset Tracking System (ZAATS) provides continuous identification, location, and tracking of
items tagged with passive UHF RFID tags conforming to the GS1 EPC
Generation-2 UHF RFID Specification for RFID Air Interface standard. ZAATS is designed to enhance the
efficiency and work-flows of Zebra’s customers’ operations, which are increasingly focused on cohesive, real-time
data.
ZAATS consists of two primary components: the Real-Time Location System (RTLS) Services software, which
contains the configuration, management, and location analytics components; and the ATR7000 overhead array
readers.
Product Overview
Description and Features
ZAATS is a passive UHF RFID based asset tracking solution developed primarily for indoor warehousing,
manufacturing, and logistics applications. It is based on the ATR7000 overhead RFID reader containing Zebra’s
proprietary advanced array architecture with integral antenna capable of steering beams and estimating the
bearing to RFID tagged items with unprecedented accuracy and speed.
A summary of the key system and product features of ZAATS includes:
•A passive UHF RFID RTLS system that provides real-time identification and location data of tagged items
for continuous asset monitoring.
•Configuration and Location Analytics Software (CLAS) that configures, controls, and manages the system,
as well as a high-performance location analytics engine capable of providing up to 100,000 (1000 readers
at 100 tps) tag location estimates per second with 2 ft typical accuracy.
•APIs to configure, manage, and control the ZAATS system using an HTTP-based RESTful interface.
TM
Radio Frequency Identity Protocols
•Docker container virtualization to simplify integration and deployment into end-user and partner
applications.
•Software tools and documentation to facilitate system installation, including site planning, calibration, initial
start-up, and deployment validation testing.
NOTE: Configuration and Location Analytics Software (CLAS) is needed to run RTLS Software. Configuration
and Location Analytics Software (CLAS) is synonymous with RTLS Services software. The two terms are used
interchangeably throughout this document.
9
ZAATS Introduction
Figure 1 illustrates the high level architecture of the ZAATS system showing the two main components of the
ZAATS system:
•AARs (ATR7000 Advanced Readers)
•RTLS Services software.
Figure 1 Zebra Advanced Asset Tracking System (ZAATS)
In Figure 1, the solid lines correspond to configuration, control, and management interfaces. The dashed lines
correspond to data interfaces. The dashed red lines carry tag ID bearing information and require high bandwidth
and low-latency connections. Therefore, they typically reside on the same segment of a local area network.
ATR7000 Advanced Array Reader (AAR)
The ATR7000 Advanced Array Readers are EPC Gen2 readers with an integral phased array antenna capable of
steering beams and estimating the bearing (angle of arrival) of EPC Gen2 tags. This product in the RFID portfolio
is based on a Zebra proprietary advanced array architecture that provides unprecedented location accuracy and
real time tracking of RFID tags.
10
ZAATS Introduction
A summary of the ATR7000 key product features are:
•Integral 14 element antenna array.
•Advanced multi-channel radio architecture provides accurate bearing estimations in a single read.
•Host software compatible with Zebra’s family of fixed RFID readers with support for embedded and
external applications.
•Integration of Zebra’s proprietary ASIC-based RFID radio.
•GPIO with external power for driving actuators and sensors.
•Support for several standard mounting options to simplify installation.
•Two power options; 802.3at Power over Ethernet (PoE+) or external +24 VDC power supply.
•Environmental specifications suitable for industrial and warehouse applications (-20 C to +55 C operation
and IP51 sealing).
RTLS Services
RTLS Services (CLAS) serves as a data aggregator that executes location analytics to estimate the tag location
and reports out unique tag ID, location, and time-stamp in real-time.
RTLS Services performs the following primary functions:
•Discovers readers on a local network.
•Configures each reader to read tags and report the estimated bearings.
•Estimates the tag location based on the bearings reported by the reader.
•Reports the location estimates to a location endpoint.
•Provides software interfaces to middleware applications that enable end-user solutions to associate items
with identity, location and movement information, and delivers business logic to streamline operations or
workflows.
•Provides an interface to end-users to configure and manage the RTLS system.
•Provides interface to manage and configure the ATR7000 readers in the facility.
•Provides license management functions for RTLS and CLAS software.
The RTLS Services software consists of three major components:
•RTLS Configuration and Management Server (CNM)
•Location Analytics (LA)
•Radio Control & Data (CND)
RTLS Services is deployed as a group of Docker containers. A container is the mechanism that minimizes
operating system and hardware dependencies, as well as isolates RTLS from the other software components that
comprise a solution, allowing them to coexist on the same infrastructure. It is expected that RTLS Services typically
resides on the same physical server as the solution.
A description of these and other components important to system operation follow below.
RTLS Configuration and Management (CNM)
As shown in Figure 1, the RTLS configuration and management server is the primary component within RTLS
Services responsible for managing and configuring the system, including system start and reset, reader discovery,
initial and ongoing configuration of LA and CND, firmware and software upgrades, etc. CNM is a component of
RTLS Services that is resident on the server.
11
ZAATS Introduction
RTLS also provides the configuration and management interfaces (API) to the solution software through a RESTful
interface, a common framework found in enterprise environments.
Location Analytics (LA)
Figure 1 also illustrates that Location Analytics (LA) is the primary component within RTLS Services responsible for
aggregating bearing information received from the ATR7000 overhead readers, estimating x-y-z tag location,
determining if a tag is moving (dynamic) or not moving (static), applying additional advanced algorithms that
enhance static and dynamic location (tracking) accuracy, and reporting a final tag location estimate with metadata
(EPC, timestamp, etc.) to a location data endpoint. LA also has the capability of combining raw bearing and
location estimates from multiple RFID tags affixed to the same asset (for example. forklifts) to improve overall
location accuracy and/or provide orientation and directionality information. The figure illustrates three AARs for
simplicity, although, operation is designed to scale up to the maximum of 1000 readers per site. While LA is
considered a components of RTLS Services, it is deployed by CNM to the readers at system start.
The interface between LA and the CND is optimized to be a high bandwidth, low latency one-way interface that
carries only tag ID and bearing information, as indicated by the red arrows in the Figure 1.
Radio Control & Data (CND)
The Radio Control & Data (CND) component is a reader-based application (process) that configures, controls, and
maintains a connection to the RFID radio (engine), receives tag bearing reports from the radio and passes them to
LA, and ensures the timestamps on the bearing reports are synchronized to the system time source.
While CND is considered a component of RTLS Services, it is deployed by CNM to the readers at system start.
ZAATS Interfaces
ZAATS presents three main interfaces:
1.A REST based management interface.
2.A messaging stream interface for location data.
3.A messaging stream interface for health and monitoring events.
The ZAATS REST API allows applications to view, configure, manage, and monitor various system components in
the RTLS system. The ZAATS location data interface allows the client application to consume the location data
output by the ZAATS system. The ZAATS event interface allows the client application to consume the health and
monitoring events data output by the ZAATS system.
12
Figure 2 Interface Overview
REST Interface
ZAATS Introduction
The REST Interface is the primary mechanism to configure and manage the ZAATS system. It supports the ability
to query the version, status, configuration of the RTLS system; start and stop the system; and reboot the ATR7000
readers. It also supports setting user-defined filters specifying the frequency and format of reported tag data.
Location Data Interface
Location update messages are sent from the LA components within RTLS through the Location Data Interface to a
Location Data Endpoint (MQTT server or a Kafka broker). The RTLS customer’s middleware application can
consume these location update messages from the Location Data Endpoint to transform information about asset
location into solutions that enhance efficiency and workflows of end user operations.
Events Interface
Health and Configuration events notification messages are sent from CNM within RTLS through the Events
Interface to a Event Endpoint (MQTT server or a Kafka broker). The RTLS customer’s middleware application can
consume these event notification messages from the Event Endpoint to implement solutions for monitoring of the
RTLS system and raise alerts to end users about system events.
13
Deployment Overview
Introduction
This chapter provides an overview of the ZAATS deployment process.
Project Phases
A ZAATS deployment generally consists of seven phases, as shown in the Table 1 on page 15 below. The
remaining chapters of this guide describe each of the seven phases and also provide additional guidelines on how
to ensure a successful deployment.
Deployment Team Roles and Responsibilities
The following are critical roles that should be defined as early as possible in the deployment process, along with
major responsibilities:
•Program Manager: oversees and coordinates team activities, works with the business lead, technical lead
(or system designer) and end user to define high-level requirements, and set the overall project objectives.
•System Designer / Solution Architect: responsible for detailed requirement definition, creating the
preliminary and final site map, Equipment Manifest, and bill of materials; working with the end-user to
ensure appropriate selection of RFID tags for all assets to be tracked; as well as ensuring that all system
performance objectives are achieved.
•Network Designer: responsible for designing the local area network (site-based) and backhaul, including
cabling requirements, ensuring adequate switch capacity and port availability, and for assigning IP
addresses to all devices.
•Site Inspector: responsible for observing and ensuring that the use case and workflows are accurately
documented, that the facility site map is accurate, and that all facility-related factors that could impact a
deployment are documented and communicated to the system designer and site survey team.
•Site Survey Team: responsible for ensuring that the final, pre-installation site map, including mounting
locations and methods are viable; identifying all permanent landmarks to be used in the post-installation
survey, and for ensuring that the logistics of a site deployment can be successfully executed according to
the final site map.
•Network and Hardware Installation Team: responsible for the installation of all reader and network
hardware and basic operational verification, post installation survey (exact reader x-y-z locations) and
updating the final Equipment Manifest.
•Software Deployment Lead: responsible for defining the server specification and requirements, deploying
the CLAS software, as well as pre-installation and post-installation validation.
14
Deployment Overview
•Validation Team: responsible for configuring the system and ensuring it is fully operational and performing
as outlined in the requirements.
Table 1 Phases and Detailed Steps in a ZAATS Deployment
Project PhaseDetailed Steps
Requirement Definition
Preliminary System Design
Site Survey
Finalize System Design
Server and Software Installation
Hardware Installation
•End User Interview (or workshop)
•Use Case and Requirement Definition
•Site Inspection
•Select Asset Tag Type(s)
•Preliminary Site (RF Coverage) Map
•Preliminary Network Design
•Preliminary Equipment Manifest
•Preliminary Bill of Materials (BOM)
•Preform Site Survey
•Update Network Design and Site Map
•Update Equipment Manifest and Finalize BOM
•Install CLAS Software
•Network Installation and Cabling
•ATR7000 Reader Installation
•Basic Operational Verification of Reader/Network Hardware
•Survey Reader Locations
Post-Installation Validation
•Finalize Site Map and Equipment Manifest
•RTLS Software Integration
•System-level Operational Validation
•End-User Handoff
15
Requirement Definition
Introduction
This chapter describes the requirement definition phase of a ZAATS deployment, covering the first steps in the
deployment process.
The requirement definition phase consists of the following steps:
1.Determine the use cases, coverage areas, location accuracy, latency, and any other relevant requirements or
constraints.
2.Document the existing network infrastructure (switches, cabling, availability of PoE+, WAN capacity, etc.) and
determine if this will be a local (on-premise) or remote server installation.
3.Define the assets to be tracked, cost, performance, and other process-related considerations.
4.Obtain the site map for each facility.
5.Define an origin location (0,0,0) and coordinate system for the site (or multiple sites).
The above steps can generally be accomplished through an interview or workshop with the end-user or customer
operations team.
Use Case Definition
The first step of any ZAATS deployment is to define the use case(s) and identify specific solution requirements.
Some common applications for ZAATS are:
•Warehouses and Distribution Centers
•Cross-docks
•Manufacturing operations
•Dock doors and portals
The use case(s) will drive the coverage area and accuracy requirements, which in turn drive the RF infrastructure
requirements of the ATR7000s. Equally as important as defining the coverage area and accuracy requirements is
understanding the number of items in a facility to be located and tracked, the density of items, and if the RTLS
system latency (approximately 2-3 seconds) supports the business process and workflow needs.
In documenting the use case(s), it is important to capture the life cycle of an RFID tagged asset, the list of actions
and event steps that comprise the life cycle of the asset, and any implied location accuracy or latency requirement
associated with the steps.
As an example of a use case in a distribution center (DC) or warehouse application, an RFID tagged forklift or hand
truck removes an RFID tagged pallet or item from a trailer and brings it to its destination or to a staging area for
16
processing and later retrieval. The pallet or item must be identified, along with the timestamp and dock door it left
the trailer, the forklift or hand truck that carried the item, and final location of the asset and the time it arrived. A
similar use case in a cross-dock application, an RFID tagged forklift removes an RFID tagged pallet from a trailer,
carries the pallet to another trailer/dock door and places the pallet into the trailer. The pallet must be identified, the
time it left the trailer noted, the dock door it entered, forklift, and the trailer and dock door it was delivered to (with
timestamp) are recorded.
End User Interview
Typically, the first engagement between the technical team (system designer, network designer, software lead)
and end user is structured as an interview or workshop. Below is a sample checklist that can be used to guide the
end-user interview.
•Description of use case(s), business process, and work flow.
•Building type and coverage environment (open space or compartmented, floor material, ceiling height and
type, presence of metallic structural components or obstructions).
•Square foot coverage requirements.
•Request/obtain site map.
•Local coordinate system defined.
•Detailed description of items to be tracked; e.g. size, material composition, total items within facility, item
density, stacking and/or shelving requirements, and maximum expected tag height.
•Location accuracy and tracking (latency) requirements.
Requirement Definition
•Existing network infrastructure, including PoE+ and/or electrical power.
•Identify location of server closet, rack space, and switch location.
•Local premise or remote server.
•Backhaul (WAN) requirements.
In a multi-facility deployment, any similarities and/or differences in any of the above criteria should be noted.
After the interview is complete, the technical team, including the system designer/solution architect and network
designer should document the findings of the interview as well as any additional relevant technical requirements
that may impact the system design and deployment.
17
Preliminary System Design
Introduction
This chapter describes the preliminary system design phase of a ZAATS deployment. The development of the
preliminary system design based on end user requirements and use cases is one of the most important factors in
achieving a successful ZAATS deployment.
The preliminary system design phase consists of the following steps:
1.Perform an (optional) initial site inspection.
2.Define server specification if a local (on-premise) server is used.
3.Determine the type(s) of RFID tags that will be required.
4.Determine the number of ATR readers required to support the coverage area and accuracy requirement and
6.Create a preliminary Equipment Manifest and preliminary bill of materials (BOM) for each facility.
The above steps are performed by the system designer/solution architect and other qualified technical specialists
with experience in network and RF system deployments and site planning.
Initial Site Inspection
Prior to installation of a ZAATS RTLS deployment, a site inspection of the facility is strongly recommended. The
objectives of the site inspection are to:
•Deepen the understanding of the use cases, items to be tracked, the facility environment, and the
processes and work flows that may impact the initial design.
•Document the ceiling type and relevant mounting considerations, especially the maximum and minimum
allowable heights that the ATR7000 readers will be installed. See note below.
•Ensure that the facility map is accurate and note any deviations or RF coverage obstructions.
•Identify the location of server closet and existing network infrastructure.
•Allow the site inspector to document their findings and make suggestions to the system designer or site
survey team through a site inspection report.
NOTE: The mounting height of the ATR7000 readers is one of the most important physical considerations
in a ZAATS deployment. In most cases, the ideal mounting height is between 15’-17’, although,
may range anywhere between 12’-20’.
18
Preliminary System Design
The following are guidelines that should assist the site inspector in creating the site inspection report:
•Walk the facility and verify that the floor plan or layout is consistent with the site map.
•Determine if the use cases, processes, and work flows are consistent with what was documented in the
requirement phase, and note any deviations or other relevant observations in the site inspection report.
•Inspect all areas to be covered with ATR readers, measure the mounting height, and confirm the mounting
method is appropriate for each area (it is possible or likely that one universal mounting approach may not
be applicable to an entire facility).
•Note if the facility has trusses that facilitate mounting with the mounting pole accessory, or determine if a
more customized mounting solution will be required.
•Document and photograph often, especially any challenges that exist and recommend a solution, if
possible.
•After the site inspection, complete a site inspection report and make it available for internal review.
•If necessary, ensure the site map is updated based on your findings to better prepare the site survey team
to conduct an efficient and thorough site survey.
NOTE: In a multi-site installation, it may not be required that every site be visited if the use case is
identical and the facilities are similar.
Minimum Server (System) Requirements
For installations that require an on-premise server, Zebra has validated the CLAS RTLS software on several
hardware platforms. Since most of the intensive location analytics processing is distributed among the ATR7000
readers, the computing requirements are relatively modest. The most important considerations, therefore, are
related to fault tolerance, including hardware reliability and system availability. A server with the following
components related to processing requirements are sufficient to operate the CLAS software:
•Quad Core CPU @ 2.4 GHz (or equivalent)
•16 GB RAM
•64 GB of free hard disk space
•Linux OS (Ubuntu 18.04 LTS and above)
For more information, please refer to the CLAS Server and Software Installation Guide (p/n MN-003197-xx).
Network and Other Hardware Requirements
All ZAATS installations require a LAN to support the ATR7000 reader population. A typical LAN consists of the
following:
•Switch(es) with multi-Gbps switching bandwidth and support for 1000 MB Ethernet
•Cat5e or Cat6 cables, one for each ATR7000
•Rack for mounting
•Fan(s) for cooling
•Power source
The key component of the LAN is the switch (or switches) that comprise the switching fabric. Likely there will be
several switches since most managed enterprise switches for small-to medium-scale edge deployments are
available in 24-port and 48-port models. Ensure that the switch has non-blocking capacity on the order of 1Gbps
19
Preliminary System Design
times the number of ports. Also ensure that the switch supports PoE+ (IEEE 802.3at), or alternatively, one or more
midspans will be required in addition to the switch(es). It may be preferable to use a midspan, as most PoE+
switches do not have the power handling capability to provide full power to every port. Alternatively, the readers
may be powered using the optional 24V external supply available from Zebra (p/n PWR-BGA24V78W1WW).
NOTE: If not powered using the 24 V external power supply, the ATR7000 readers require PoE+ and will
not operate using standard PoE (IEEE 802.3af). LLDP power negotiation is also supported. The
maximum power consumption per reader is 22.9 W (typical 22 W).
See Appendix: Tools and Resources for a list of recommended network hardware for use in a ZAATS deployment.
Tag Selection and Readability
Tag readability and tag read rates are two of the most important factors in achieving good location accuracy and
real-time performance of the ZAATS system. Zebra has identified several tags that provide suitable performance
for a variety of use cases. The Zebra ZBR4000 Tag with the NXP UCODE8 RFID IC, shown in Figure 3, has been
developed specifically for the ZAATS system. It represents the latest in RFID tag performance with high RF
sensitivity, good performance in all tag orientations, and exhibits excellent readability at long distances.
Dual-dipole tags available from Avery, Confidex, Smartrack, and other medium to large size standard dipole RFID
tags with the NXP UCODE8 chip can also be used successfully with the ZAATS system. Table 2 on page 21
provides several examples of tags that may be considered. The exact choice will depend on several factors,
including material composition of the items to be tracked, item density, reader height and density, stacking and/or
shelving requirements, and cost.
Other RFID tags with single dipole designs and older, less sensitive RFID ICs can generally be read at the
distances required of ZAATS, although, they may not have the multi-orientation readability desired which can result
in reduced system performance.
Figure 3 Zebra ZBR4000 Tag
20
Table 2 Tag Types Use Cases
Use CaseTag TypeDescription/Comments
Preliminary System Design
Packages, containers
(non-metallic)
Metal objects, packages, or
containers with no intent for
long-term use or durability.
Metal objects with permanently
affixed tags (e.g. for forklifts,
machinery, trolleys, metal
shelving, etc).
Long Range People IDZebra UHF Badge Cards
Figure 4 Examples of RFID Tags Applied in a Flagged Technique
Zebra ZBR4000 Tag
Most dual-dipole tags
Most mid-sized or large tags
using NXP UCODE8
Same as above applied in a
“flagged” manner - see Figure 4
Printable “on-metal” label such
as Zebra Silverline.
Omni ID Dura 1500
Omni ID Exo 750
Confidex Ironside Slim
Printable “on-metal’ label such
as Zebra Silverline.
The Zebra ZBR4000 Tag with
the NXP UCODE8 chip has
been thoroughly tested to work
well at needed ranges and in
multiple orientations.
A well designed on-metal tag
will use the metal surface of the
object as part of the antenna
structure to increase the
performance of the tag.
Metal mount tags with a
specified range of greater than
25 ft are recommended.
NOTE: To ensure reliable system performance, RFID tags must exhibit “good readability”. Perform a
simple yet reliable tag readability test as follows: using a hand-held reader with transmit power set
to produce 30 dBm EIRP stand 25’ to 30’ away from a tagged item exactly as it will be tagged on
the asset in normal operation; direct the hand-held reader toward the item and wave it slightly up
and down, left and right; ensure that the tag can be reliably read. This test should be performed on
a variety of items representative of all use cases. When readers are mounted higher than 17’ off
the floor and assets are stationary for long periods of time, or when the highest levels of location
accuracy are desired, then a 35’ read distance is recommended.
21
ATR7000 Coverage
The coverage area and number of readers required to reliably support an ATR7000-based ZAATS system
depends on many factors. Most important is the relationship between the reader-to-reader spacing, the height at
which the readers are mounted, the location accuracy requirements, and the tradeoff between cost and
performance. To achieve maximum packing density and, therefore, the most cost-effective coverage, a triangular
grid is employed. Using a triangular grid, the coverage zones are hexagonal and shaped like a honeycomb as
illustrated in Figure 5.
Note in the figure below that the ATR7000 readers are installed at the vertices of equilateral triangles with equally
spaced sides, separated by distance, s. The area per hexagonal cell is given by the equation:
Preliminary System Design
Area
CELL
= √3/2 x s
2
Figure 5 Illustration of Hexagonal Coverage Areas Obtained Using Triangular Grid
The ATR7000 provides coverage over an antenna scanning angle ranging from 0⁰ to 360⁰ in azimuth and from 0⁰
to ±60⁰ in elevation, therefore, the maximum coverage area of a single ATR7000 reader occurs when the spacing,
s = 2* r
= 2 * Tan (60⁰) * h.
max
This maximum coverage is illustrated in Figure 6 and given by the equation:
Area
= √3/2 * 4*Tan2(60⁰) x h2 = 10.4 x h
MAX
2
Where h is the mounting height of the readers.
While the above equation may predict coverage, in practice where high levels of real-time performance and
location accuracy are essential, two modifications to the above are required.
First, the maximum tag height must be taken into consideration:
h = h
reader
- h
tag
Second, a sufficient amount of overlap between ATR coverage areas is required. Although, the ATR7000 elevation
scan range extends to ±60⁰, location accuracy is highest when the elevation scan range extends only to ±54.7⁰.
Therefore, a more typical reader-to-reader spacing becomes:
s
= 2 x r
typ
= 2 x Tan (54.7⁰) x (h
typ
reader
- h
tag
) = 2.83 x (h
reader
- h
tag
)
22
and:
Preliminary System Design
Area
= √3/2 x S
ATR
2
= 6.93 x (h
typ
reader
- h
tag
2
)
Figure 6 Maximum Coverage Area and Typical Coverage Area of ATR7000
NOTE: ZAATS supports “multi-tagged” items, where two or more tags are placed on the same item with a
fixed, known geometry. In this case, the tag height used can be the average (not maximum) tag
height of all tags affixed to the same item. For more information on “multi-tagged” items, see
ZAATS Tag Data and Numbering Guide, (p/n MN-003199-01).
Using the above formula guarantees coverage overlap between ATR readers in adjacent cells and provides
maximum coverage area per reader. However, for applications that require the highest levels of location accuracy,
the reader-to-reader spacing should be reduced by up to 15% (which increases the number of ATR readers by
~30%):
Therefore:
s
max_accuracy
Area
ATR_max_accuracy
= 0.85 x 2.83 x (h
= √3/2 x s
- h
reader
max_accuracy
tag
) = 2.40 x (h
2
= 5.00 x (h
reader
reader
- h
- h
tag
tag
)
2
)
As an example, in an installation with readers mounted at a height of 15’ off the floor and tags mounted 3’ off the
floor, the nominal reader-to-reader spacing is 34’ and the coverage area per reader is 1000 square-feet. For the
highest levels of location accuracy, the reader-to-reader spacing is reduced 15% to 28.8’ and the coverage area
per reader is 720 square-feet. To achieve 1000 square-feet coverage, the reader-to-reader spacing must be 34’,
however, to obtain the additional cell overlap required for the highest levels of performance, the mounting height of
the reader would be increased to 17.1’. In all cases, it is important to ensure that the RFID tags exhibit “good
readability” to achieve reliable accuracy and real time performance (see the previous section Tag Selection and
Readability). It is worth noting that Area
17.1’. This 3-to-1 ratio between Area
MAX
is approximately 3000 square-feet when ATR readers are mounted at
MAX
and Area
is an important factor of how the ZAATS system achieves its
ATR
high levels of performance.
One final point concerning the selection of reader-to-reader spacing (grid size) is that the structural aspects of the
site must also be considered. The basic structural components of most facilities are the support columns and roof
trusses. It is often possible to choose the grid spacing such that a grid can be maintained without interfering with
23
Preliminary System Design
the building structure. It is especially important to ensure readers are not installed within 6’ of a support column
(see additional guidelines below).
NOTE: The preceding material on coverage and best practices has focused on wide area coverage where
readers provide overlapping coverage. Another common coverage scenario is warehouses with
pallet racks where ATR readers are mounted in a linear fashion down the center of each drive
lane. To ensure adequate coverage line of site is required within the cone formed by a 45
emanating from each ATR reader for all but the top shelf (seeFigure 7); i.e., the reader-to-reader
spacing down the center of the aisle should be twice the difference between the mounting height
of the reader and the height of the bottom of the top shelf. The RTLS system will track the item up
and down the racks and send tag reports with x-y-z locations until the item is raised to a maximum
height where the tag report then indicates that the item elevation is out of range. The solution
software must then infer the item is on the shelf above the location it was last observed.
Figure 7 Warehouse Deployment Scenario with Pallet Racks
⁰ angle
Creating the Preliminary Site Map and Equipment Manifest
The next step in the preliminary system design is to specify the installation locations (i.e., x-y-z coordinates) of the
ATR readers and create the preliminary site map. In a multi-facility installation, this should be done for each facility.
The steps to complete this process are outlined below.
1.Highlight the coverage zones on the site map (for each facility) and note local coordinate system origin and any
known reference locations.
24
Preliminary System Design
2.Based on the use case(s), determine the tag height (h
3.Based on the facility mounting or structural constraints and tradeoff between coverage per reader (cost) and
accuracy, determine the ATR mounting height (h
ATR reader.
4.Using the guidelines below, locate the readers on the site map adhering as closely as possible to the
pre-determined reader-to-reader spacing (s), such that all zones have the desired coverage.
5.Create the preliminary Equipment Manifest with the preliminary (target) x-y-z locations of the ATR7000
readers.
The following are guidelines that should assist the system designer in creating the system design and reader
locations (site map):
reader
).
tag
), reader-to-reader spacing (s), and coverage area per
•The mounting height should be as close to 15’-17’ as possible, although, may range anywhere between
12’-20’ as explained in the previous section.
•The triangular grid layout should be adhered to as closely as possible. When deviations from a strict
triangular grid are required, which will typically be the case, the system designer should minimize such
deviations and do so in a way not to create coverage holes. To prevent coverage holes, ensure that
reader-to-reader spacings do not exceed the target by more than 10%.
•Readers should be spaced at least 6' away from structural columns, walls, or zone boundaries, and up to a
maximum of s/3 (ideally somewhere between these two limits, depending on other environmental
constraints).
•Readers should be placed at least 3’ away (and preferably more) from any metal obstruction; e.g. roof
trusses, fans, ventilation ductwork, etc. The exception to this constraint is if the reader is mounted below
the obstruction by at least 6”. In this case, the constraint can be relaxed to 1’.
•Readers should not be placed near objects that would interfere with line-of-sight coverage to the items to
be tracked within a coverage zone. Although, this requirement may be challenging to strictly meet in
practice due to the presence of structural support columns, machinery, and other environmental factors.
•Generally, the actual x-y mounting location of any reader can deviate up to 1.5’, and the z mounting
location (height) of any reader can deviate up to ±0.75’ (higher is better) with minimal impact to
performance.
Mounting Considerations
As described in previous sections, the mounting height of the ATR7000 readers is one of the most important
physical considerations in a ZAATS deployment, as it directly impacts the reader-to-reader spacing, number of
readers, and cost required to cover a given area.
There are three options for mounting the ATR7000 readers to the roof trusses using the accessory mounting poles:
•Installing directly to a truss - see Figure 8below
•Installing using a strut channel clamped to the bottom of the truss.
•Installing using a strut channel and threaded rods clamped to the top of the truss.
When mounting to a truss is not feasible, the system designer will need to define a mounting method using the
optional ATR7000 VESA bracket accessory (Zebra p/n BRKT-VMATR7-00).
25
Figure 8 Installing Directly to a Truss
ATR7000
Collar
UL Certified Telescoping Pole
Safety Cable
Truss
NOTE: The z-axis reference that establishes the mounting height of the ATR7000 is the ground plane of
the antenna array. This reference is located 4.2” (0.35’) above the bottom of the antenna radome
at the seam that joins the radome and top cover. This same z-axis reference point is 2.9” (0.24’)
below the connection point where the mounting bracket attaches to the ATR7000.
Preliminary System Design
In selecting the mounting accessories and hardware, the system designer must take into consideration the height
of the structure the readers are attached to. The site survey team will ensure during the site survey that the method
chosen is suitable for the type of structure and applicable building constraints.
Zebra offers UL certified telescoping poles available in three sizes to accommodate a variety of environments, as
shown in Table 3 below.
As an example, if a reader is intended to be installed at a height of 15’, the bottom of the radome is 14.65’ above
the floor and the connection point to the mounting pole or VESA bracket accessory is 15.24’ above the floor. Using
the BR-000237-01 at its minimum extension the truss will be 16.74’ above the floor; using the BR-000237-03 at its
maximum extension the truss will be 26.74’ above the floor.
In summary, a variety of mounting heights and approaches can be accommodated using the various mounting
options, choice of mounting poles, and VESA bracket accessory (Zebra p/n = BRKT-VMATR7-00). More
information on mounting the ATR7000 readers can be found in the ATR7000 Advanced Array Reader Integration
Guide, (p/n MN-003191-xx)
Equipment Manifest
The Equipment Manifest is a repository of information that captures all attributes required for system installation,
configuration, and operation in a single location. The Equipment Manifest is used by the system designer, survey
team, network installers, installation team, and validation team to identify all materials needed for a ZAATS
installation, and is also used to create the configuration files required during the server and software installation
process.
At the preliminary design phase, the Equipment Manifest will include the ATR friendly names and preliminary x-y-z
reader locations. The serial number, MAC address, x-y-z locations, and reader orientations (
installation. Network related information, for example IP address, should be provided to the system designer by the
network designer by the network designer and/or end user IT department when available, but prior to system
installation.
A sample Equipment manifest is shown in Table 4 below.
Below is a sample checklist of exit criteria that can be used for the preliminary system design phase:
•Preliminary network design, including reader power sources, detailed server specification (if required),
number and type of switches, midspans, and cabling requirements.
•Preliminary RFID tag specification(s).
•Preliminary site map showing the local coordinate system origin, reader locations (x-y) and mounting
height (z), structural features, and other known obstructions or objects that can impair RF coverage.
•Preliminary Equipment Manifest.
Midspan/Switch
Port
•Preliminary comprehensive bill of materials (BOM).
•Preliminary system design document (report) summarizing the above, to be used as a guide for the site
survey and installation teams.
27
Site Survey
Introduction
This chapter provides information for the survey team in performing an in-depth comparison of the preliminary site
map to the respective on-site ZAATS component locations to ensure the map has been developed according to
best practices for ZAATS hardware installations. The survey team also updates the map, where required, for
component locations that are inconsistent with best practices.
The objectives of the site survey are to:
•Ensure that the system will deliver the required wireless coverage and location accuracy.
•Determine the presence or absence of existing network infrastructure, the data capacity of the existing
network, and identify the location of the server closet or mounting location of the switches.
•Validate the local coordinate system and identify permanent reference location points (landmarks).
•Validate that the preliminary site map is accurate, note any deviations or obstructions, and modify the site
map (i.e. reader locations) accordingly.
•Validate that the reader mounting height is practical for each location and modify the site map (i.e. reader
locations) accordingly.
•Ensure that the planned mounting scheme for each reader location is suitable for the type of structure and
applicable building constraints, and to document alternative solutions, if needed.
•Ensure that electrical power is available, either through PoE+ enabled switches or midspans, or by
electrical outlets in near proximity to where the readers will be located.
•Define all materials and tools that will be required by the installation team.
•Develop the site survey report, documenting any challenges that exist or special instructions that need to
be considered by the installation team, and to make the report available for internal review.
Guidelines for Performing the Site Survey
The following are guidelines that should assist the site survey team in performing the site survey and creating the
site survey report:
•Become familiar with the facility map and site map and review all ATR locations.
•Identify the facility landmark that will serve as the (0,0,0) origin for the local coordinate system and identify
the permanent reference location points (landmarks). Identify enough landmarks such that every landmark
has at least two other visible landmarks within 200’.
•Locate each ATR on the site map and ensure that each ATR location is visible to at least two landmarks.
28
Site Survey
•Place yourself in an appropriate viewing location to determine if any obstructions or other factors will
impede the proper installation of the ATR in its planned location.
•Measure from the floor to the lower surface of the structure to determine if the mounting height specified on
the site map is feasible. If the lower surface of the mounting structure is not high enough, then the site
survey lead will need to discuss an alternate approach with the system designer and modify the site map
accordingly.
•If a planned ATR location or mounting height is unsuitable due to an obstruction or mounting at the
specified height is not practical, it is acceptable to move the location in any direction up to 18” or change
the mounting height up to 9”. Take photos of the original location and new location, and indicate the reason
necessitating a move. For consistency, take all photos facing the rear of the facility (if possible) and angled
back to view the ceiling.
•If a minor location or height change is not practical, then the survey team needs to be prepared to modify
the preliminary site map in a manner that maintains the coverage objectives. Typically, this is either by
tolerating a minor sacrifice in coverage, or by replacing a single ATR reader with two ATR readers (at
different locations). It is advised to contact the system designer or technical lead in these situations.
•If a planned location requires any deviation, the site map must be modified to reflect the revised location.
Ensure a person familiar with the best practices for ATR locations updates the map.
•Ensure that the planned mounting scheme for each reader at each location is suitable for the type of
structure and applicable building constraints, and to document alternative solutions (for later review by the
system designer) if necessary.
•Validate the presence or absence of existing network infrastructure and network capacity, including the
location of the server closet or mounting location of the switches.
•Ensure that the electrical power is available, either through PoE+ enabled switches or midspans, or by
electrical outlets in near proximity to where the readers will be located.
•Define all materials and tools that will be required by the installation team.
•Document and photograph any challenges that exist and provide instructions to the installation team in the
site survey report.
•After the site inspection is complete, prepare a site survey report and make it available for internal review.
29
Completing the Final
System Design
Introduction
This chapter describes the final system design phase of a ZAATS deployment, the last step prior to the arrival of
the installation team.
The final system design phase consists of the following steps:
1.Review the site survey report.
2.Finalize the Site Map with exact installation locations of the ATR7000 readers and network hardware.
3.Finalize the network hardware and network design, including assignment of IP addresses if not using DHCP.
4.Update the Equipment Manifest and the final bill of materials (BOM).
5.Prepare the final system design and site report.
After the site survey, working with the site survey lead and network designer, the system designer will finalize the
site map and create detailed installation notes and instructions to guide the network and hardware installation
team.
Finalizing the Pre-Installation Site Map, Equipment Manifest, and Bill of
Materials (BOM)
It is quite often the case that the site survey team needed to make modifications to the preliminary site map based
on mounting considerations, ceiling height, building, or other structural constraints. General guidelines were
provided in the previous section where it is acceptable for the site survey team to move the preliminary x-y location
of a reader in any direction up to 18” or change the mounting height up to 9”. It is very important that these
locations are now considered final, and that no significant deviations to mounting height or x-y location be made by
the hardware installation team after finalization of the site map. However, from a practical perspective, it is
important that the system designer consider that the hardware installation team may still need to make minor
adjustments, up to 6” in height or location, based on each unique mounting situation.
After updating the pre-installation site map, the Equipment Manifest should also be updated with any adjustments
to reader quantities, installation locations, and assigned IP addresses (See Table 5) and the bill of materials (BOM)
updated with the final reader count, mounting hardware, network hardware, or other hardware required for
installation. Comparing the pre-installation manifest in Table 4 to the preliminary manifest in Table 5, note that the
y-locations of the ATR readers were adjusted by 15.0’.
Below is a sample checklist of exit criteria that can be used for the final system design phase:
Hostname
ATR
S/N
MAC
Address
IP AddressX-locY-locZ-locφ
Midspan/Switch
Port
•Final network design, including reader power sources, detailed server specification (if required), number
and type of switches, and cabling requirements.
•Final RFID tag specification(s).
•Updated, pre-installation site map showing the local coordinate system origin, reader locations (x-y) and
mounting height (z), structural features, permanent landmarks, and known obstructions or objects than can
impair RF coverage.
•Updated, pre-installation Equipment Manifest.
•Final comprehensive bill of materials (BOM).
•Final system design and site report with mounting and installation instructions to be used as a guide for the
network and hardware installation team.
31
Installation of CLAS Server
Software
Introduction
In cases where a local on-premise server is used, the CLAS software should be installed and pre-validated on the
on-premise server and should be shipped to the end-user facility prior to the arrival of the installation team.
For more information, see CLAS Server and Software Installation Guide (p/n MN-003197-xx).
32
Installation of ZAATS Reader
and Network Hardware
Introduction
This chapter describes the hardware installation phase of a ZAATS deployment, including the detailed steps
involved in reader and network installation, and how to ensure the hardware is fully functional.
The hardware installation phase consists of the following steps:
1.Install all network hardware and Cat5e/Cat6 cabling.
2.Install electrical power to each reader location (if PoE+ is not available).
3.Configure switch(es), midspan(s), and router(s).
4.Install all ATR7000 readers.
5.Assign an IP address to each ATR7000 (if DHCP is not used).
6.Perform basic reader “health test”, including network connectivity and antenna operation.
7.Measure installed ATR7000 locations with Leica 3D DISTO
8.Finalize site map and Equipment Manifest.
TM
, or equivalent.
Prior to Arrival of Installation Team
After completing the final system design, all materials defined in the bill of materials (BOM) need to be on-site and
accessible prior to the arrival of the network and hardware installation team. In addition, all specialized equipment
and tools required for mounting readers, cabling, and installing network hardware will need to be delivered or
carried on-site by the team. SeeAppendix: Tools and Resources for a listing of some helpful resources that can
facilitate installation and aid in the deployment of a ZAATS system.
Network Installation and Cabling
The first step in deploying hardware is to install all network components in their permanent locations and all
Cat5e/Cat6 cabling should be pre-wired and labeled with termination points at each reader location. It is
recommended to allow a 4’-6’ service loop to facilitate minor adjustments to reader x-y-z location, if needed. If
PoE+ is not available and electrical power is required, power outlets should be installed by a qualified electrician,
preferably within 6’ of the final reader location.
After the Cat5e/Cat6 cables are installed they should be terminated at the switch (or midspan) and the port number
should be recorded in the Equipment Manifest corresponding to each ATR reader location.
A block diagram of a typical system installation is shown in Figure 9, which also illustrates the use of an optional
WAN router and optional test PC.
33
Figure 9 System Design
Installation of ZAATS Reader and Network Hardware
The following are guidelines that should assist the network engineer/specialist to ensure proper operation of the
system after its installation:
•Preferably use a dedicated switch with Gpbs switching capacity for connecting all ATR7000 readers and
server. This will ensure that the high network bandwidth required by the ATR7000 readers and RTLS
software does not impact other devices on the network.
•Ensure IP multi-casting and IP multi-cast routing is enabled in the switch configuration. This will allow
ATR7000 readers to be discoverable over the network during installation.
•Ensure that a DHCP server is available. Even if static IP addresses are used, the installation process
requires DHCP.
•If using the optional WAN router, enable the bridging function to connect the two LANs, This will allow a
roaming laptop (test PC) to access an ATR on the LAN through a local WLAN established by the router.
NOTE: It may be preferable to go through the installation process with the ATR/switch local network not
connected to the end-user (corporate) network. This ensures no conflicts with the corporate
network prior to provisioning by the end user IT department.
WAN Router Setup (Optional)
The use of a cellular WAN router on either a temporary or permanent basis is useful to provide remote access to
authorized personnel to the ZAATS system. Also, during installation, a router with WLAN capability can be used to
establish a temporary WLAN to facilitate ATR “health testing” (See Preliminary Validation of the ATR7000
Readers).
When using the optional WAN router, the following is recommended.
34
Installation of ZAATS Reader and Network Hardware
•Ensure that the router is assigned a static IP address. This will allow direct remote access to specific ports
and services of systems running on the local network.
•Port forwarding needs to be enabled. The following ports will need to be forwarded to the local network
address of the RTLS server.
•SSH: Port 22 (TCP)
•HTTP: Port 80 (TCP)
•HTTPS: Port 443 (TCP)
•If using an optional Windows test PC (see below):
•RDP: Port 3389 (TCP & UDP)
NOTE: To maintain http, https, and SSH access to both the WAN router and the RTLS server, the ports
for these services must be modified for the router.
Figure 10 shows the typical port forwarding requirements for both a local RTLS server and an optional Windows
test PC. IP address 192.168.7.199 represents the RTLS server system and 192.168.7.200 represents the
Windows test PC.
Figure 10 Port Forwarding Requirements for Optional WAN Router
Windows Test PC (Optional)
The use of a small Windows PC on either a temporary or permanent basis is useful for preliminary testing of the
ATR7000 readers (e.g. testing with PowerSession software), post installation validation and/or remote network
monitoring. The optional test PC can be accessed remotely via the remote desktop service on Port 3389, which will
need to be enabled through the firewall of the local network.
NOTE: Port 3389 is a commonly restricted port on many corporate networks, therefore, an alternate
approach may be required. One example of an alternate approach is to use TeamViewer software
(license required) as it does not require inbound port forwarding.
Installing the ATR7000 Readers
After all network components are in their permanent locations, cable drops have been installed, and electrical
power is available at each location, the process of installing reader hardware can begin. All information on
35
Installation of ZAATS Reader and Network Hardware
unpacking and installing the ATR7000 readers can be found in the ATR7000 Advanced Array Reader Integration
Guide (p/n MN-003191-xx) and is not repeated in this document.
The following are guidelines that should assist the installation team in performing the installation:
•Ensure that all Cat5e/Cat6 cables are terminated at the switch (or midspan) prior to installing readers.
•If a PoE+ enabled switch with LLDP power negotiation is used, ensure that the ATR7000 Power
Negotiation configuration setting is enabled. Setting this parameter is explained in the ATR7000 Advanced
Array Reader Integration Guide, MN-003191-xx.
•Locate each ATR on the site map and ensure that each ATR location is visible to at least two landmarks.
•Install the mounting hardware, including mounting poles or brackets, at each ATR location. It is important
to follow the site map as closely as possible, however, deviations in location (x-y) up to 12” or height (z) up
to 6” are allowable if necessary.
•Attach and secure the ATR reader to the mounting bracket and ensure the unit is level to within 5⁰.
•After the ATR reader is mounted, note the orientation of the reader relative to the reference coordinate
system. This is explained in Measure Location and Orientation of the ATR7000 Readers on page 38.
•Connect the reader to the Cat5e/Cat6 cable. If not using PoE+, connect the power supply connector.
Validate the proper boot up sequence. When complete, the LED indicator should be solid green.
•Follow the steps outlined in the section below, Preliminary Validation of the ATR7000 Readers.
•Optionally follow the steps outlined in Basic Operational Verification (Optional) on page 37.
•Repeat for each ATR reader throughout the facility.
•Update the Equipment Manifest with the MAC address, serial number, hostname, and orientation of each
ATR reader (associated with the friendly name and location coordinates).
Preliminary Validation of the ATR7000 Readers
Once the reader is installed, connected to the network and power, and the boot-up sequence has been validated,
the indicator LED should be lit solid green. At this point the IP address (if required by the end-user IT department)
and a basic functional health check should be performed on the reader using the installation software tools as
follows:
•The installer should have a laptop (test PC) with PowerSession installed to facilitate testing immediately
after mounting the reader.
•Ensure DHCP is enabled on the local network.
•If a static IP address is required by the end-user IT department:
•Connect to the reader using the hostname and assign a static IP address assigned to the ATR (per the
Equipment Manifest). This procedure is described in the ATR7000 Advanced Array Reader Integration
Guide (p/n MN-003191-xx).
•Follow the prompts to first apply changes and then re-boot the reader from within the web console
interface for the network configuration changes to take effect.
•Place a tag board directly underneath the reader within 6-10’ of the bottom of the antenna radome. See
Appendix: RFID Tag Board for ATR7000 Installation and Validationfor details on constructing a tag board.
36
Installation of ZAATS Reader and Network Hardware
•Using the PowerSession RFID Demo Application with beams 400-413 enabled (these beams correspond
to individual antenna elements), verify that all elements (beams) are reporting tag reads:
•Connect to the reader being tested using the hostname (or IP address).
•On the Settings tab, enter a custom antenna sequence of “400-413” at 36 dBm EIRP and click apply.
•On the Main tab, click Start to begin reading.
•Confirm that each individual antenna element from 400-413 (14 elements total) are all able to read
tags with the tag board positioned directly underneath the reader within 6-10’ of the bottom of the
antenna radome. This will ensure that all 14 antenna elements are functional.
•Using the PowerSession RFID Demo Application with beam 397 enabled (this beam corresponds to a 0 ⁰
elevation, or boresight beam with left hand circular polarization), verify nominal read performance is
achieved by ensuring that 100% of the tags are read at an output power 6 dB less than maximum (EIRP),
and that greater than 50% of the tags at an output power 12 dB less than maximum (EIRP):
•Connect to the reader being tested using the hostname (or IP address).
•On the Settings tab, enter a custom antenna sequence of “397” at 30 dBm EIRP and clickapply.
•On the Main tab, click Start to begin reading.
•Confirm that 100% of the tags are read with the tag board positioned directly underneath the reader
within 8-12’ of the bottom of the antenna radome.
•On the Settings tab, enter a custom antenna sequence of “397” at 24 dBm EIRP and click apply.
•On the Main tab, clickStart to begin reading.
•Confirm that greater than 50% of the tags are read with the tag board positioned directly underneath
the reader within 8-12’ of the bottom of the antenna radome.
Basic Operational Verification (Optional)
While not strictly necessary, basic operational verification of the ATR7000 systems can be performed two systems
at a time for a given row of ATR7000 readers along the North-South axis, or for a row of readers along the
West-East axis, whichever is most suitable for the given installation. This verification accomplishes the following:
•Confirms that each ATR7000 reader can read RFID tags at the distances it will be required to read during
normal operation.
•Confirms that each ATR7000 reader can read tags in the direction corresponding to a given beam.
•Confirms that each ATR7000 reader’s physical orientation has not been mistakenly reversed or badly
misaligned.
•Confirms that there are no internal antenna faults within the reader being tested.
The basic operational test procedure is as follows:
•Place the tag board approximately three feet off the ground at a point midway between two readers on a
North-South axis.
•Connect to the “South” reader using PowerSession and apply custom antenna sequence “325” at 36
dBm EIRP. This is a left hand circular polarized beam points North (0
°.
of 45
° azimuth) at an elevation angle
Confirm that greater than 50% of tags are read.
•
•Connect to the “North” reader using PowerSession and apply custom antenna sequence “337” at 36
dBm EIRP. This beam points South (180
Confirm that greater than 50% of the tags are read.
•
° azimuth) at an elevation angle of 45°.
37
Installation of ZAATS Reader and Network Hardware
•Repeat the above for all readers to ensure proper North-South beam steering,
•Place the tag board approximately three feet off the ground at a point midway between two readers on an
East-West axis,
•Connect to the “West” reader using PowerSession and apply custom antenna sequence “331” at 36
dBm EIRP. This beam points East (90
Confirm that greater than 50% of the tags are read.
•
° azimuth) at an elevation angle of 45°.
•Connect to the “East” reader using PowerSession and apply custom antenna sequence “343” at 36
dBm EIRP. This beam points West (270
Confirm that greater than 50% of the tags are read.
•
° azimuth) at an elevation angle of 45°.
•Repeat the above for all readers to ensure proper East-West beam steering.
Note that due to multi-path propagation effects, a given system might not be able to read the tag board if the tag
board’s location happens to fall into a null on the specific static test beam and polarization being used. It is
permissible to move the tag board around slightly during testing within a 2-foot radius to confirm tag read
performance. As a best practice, try first moving the tag board further away from the reader under test for a higher
confidence result.
Measure Location and Orientation of the ATR7000 Readers
To achieve the full location accuracy performance potential of ZAATS, it is necessary to accurately survey the
precise positions of the installed ATR7000 readers in the x, y, and z-axis with a surveying tool such as the Leica 3D
Disto system. Manual measurements with hand-held laser rangefinder tools are not recommended as they will
result in too much variability and have a direct negative impact on overall system accuracy.
There are two ways to survey the ATR7000 systems, directly underneath or from the side of the systems. A
procedure for both methods is described in detail in Appendix: Leica 3D Instructions for ATR7000.
The ZAATS system requires that the reference reader orientation φ=0 be in the direction of the positive y-axis. The
positive y-axis is commonly referred to as facility north, which is usually not the same north as defined by a
compass reading. It is recommended, but not required, that the orientation of each reader be the same. The reader
should be laser aligned as closely as possible to adjacent systems within a given row, or to a facility reference
point. Any dependencies should be noted in the Equipment Manifest, as described below. When installing
ATR7000 readers into a facility, it is often not possible to ensure that the orientation of every reader is aligned to
the facility north. An example of a slightly misaligned reader is shown below in Figure 11 on page 39. Note in the
figure, the view is from the perspective of someone standing directly beneath the reader, facing the facility north,
looking straight up. Note the indentions and bulges that define the reader orientation points of 0, 60, 120, 180, and
240 degrees. Also note the green light at approximately 230 degrees azimuth. In this example the reader is
oriented slightly west by 5 degrees. The orientation of this reader should be entered as 355 into the Equipment
Manifest.
38
Installation of ZAATS Reader and Network Hardware
Figure 11 Example of a Slightly Misaligned ATR7000 Reader
Finalizing the Site Map and Equipment Manifest
The last step of the hardware installation process is to update the Equipment Manifest with the final (surveyed)
x-y-z locations of the ATR readers, and to ensure that all the other fields in the Equipment Manifest have been
properly recorded.
The finalized Equipment Manifest becomes the basis for configuring the RTLS Services software, as described in
the following chapter. An example of a completed Equipment Manifest is shown in the table below.
Table 6 Sample Finalized ZAATS Equipment Manifest
Friendly
Name
ATR01ATR7000F422C884248DF42
ATR02ATR7000F476E184248DF47
ATR03ATR7000F3F48984248DF3F
ATR04ATR7000F3F31684248DF3F
Hostname
ATR
S/N
MAC
Address
2C8
6E1
489
316
IP AddressX-locY-locZ-locφ
192.168.7.20140.010017.107
192.168.7.20215.087.517.1
192.168.7.20340.075.017.1011
192.168.7.20415.062.517.103
355
Midspan/
Switch
Port
1
ATR05ATR7000F3F4A184248DF3F
4A1
192.168.7.20540.050.017.11013
39
Installation of ZAATS Reader and Network Hardware
Friendly
Name
ATR06ATR7000F36F4B84248DF36
ATR07ATR7000F3F4B184248DF3F
Hostname
ATR
S/N
MAC
Address
F4B
4B1
Midspan/
IP AddressX-locY-locZ-locφ
192.168.7.20615.037.517.105
192.168.7.20740.025.017.1015
Switch
Port
40
Post-Installation ZAATS
Validation
Introduction
This chapter describes the post installation ZAATS validation phase of a ZAATS deployment and how to ensure
the system is fully functional and ready for handover to an end user.
The objectives of the post-installation validation are to:
•Ensure that the CLAS RTLS software is operational and properly configured.
•Ensure that ZAATS can locate non-moving (static) tags throughout the coverage area with the accuracy
objective specified during the requirement definition phase.
•Ensure that the ZAATS system can locate moving (dynamic) tags throughout the coverage area with the
accuracy and latency objectives specified during the requirement definition phase.
•Place an adequate number of “reference tags” within the coverage area to facilitate ongoing system health
monitoring or troubleshooting.
•Prepare and deliver the system validation and test report to the customer or end user.
Entry Criteria
Prior to validation of the ZAATS system, the following entry criteria are presumed to be satisfied:
•All ATR7000 readers and network hardware have been installed and validated as described in the Basic
Operational Verification (Optional) section of the previous chapter.
•The Equipment Manifest has been finalized with all reader locations recorded as described in the
Finalizing the Site Map and Equipment Manifest section of the previous chapter.
•The CLAS/RTLS Services software has been installed, deployed, and validated as described in the
Validating an CLAS/RTLS Services Installation chapter of the CLAS Server and Software Installation
Guide (p/n MN-003197-xx). This includes starting CLAS with the bundled Kafka broker and verifying that
the bundled Kafka consumer can consume tag ID and location data using the RTLS simulator.
RTLS Integration
After the ATR7000 has been installed and basic hardware and network operation has been validated, and after the
CLAS (RTLS Services) software has been installed on the server, the next step is to integrate these two major
components of the ZAATS system. This ensures that the RFID readers are reading and estimating tag bearings
and that the tag reports from the readers are being ingested by the RTLS location analytics, and the resulting tag
ID and location information is being directed to a live bundled Kafka location endpoint.
41
Post-Installation ZAATS Validation
The following are basic steps to integrate the ATR readers and CLAS (RTLS Services) software:
1.Using the information contained in the Equipment Manifest, update the aar_info.csv file with the ATR host
names, IP addresses, x-y-z locations, and orientations.
2.Ensure that radio_c_and_d_config parameter in the rtls/config/rtls.conf file is set to bearing. This will inform
RTLS Services (software) that it will be operating in live mode.
3.Ensure that there are at least 10-20 RFID tags within the coverage zone, preferably located such that they are
within range of several ATR readers.
4.Start RTLS Services with the bundled Kafka broker and the bundled NTP server. To do this, cd to the rtls folder
and run:
./rtls.sh -nk start
NOTE: If the host is already running an NTP service then remove the “n” option from the command above.
To verify that the RTLS is indeed reporting tag IDs and location estimates on the live bundled Kafka location
endpoint, follow the steps below:
5.List the Kafka topics that are created on the broker using the following command:
8.To confirm that the system is operational, a steady stream of messages like those shown in Figure 12 should
be seen on the Kafka consumer console.
9.Review the messages and verify that all tags are being reported and the location estimates look reasonable. It
is recommended to move the tags throughout the coverage zone and verify that all tags are being read and
their locations are being updated and reported.
10. Stop RTLS Services. To do this, cd to the rtls folder and run:
./rtls.sh -nk stop
42
Post-Installation ZAATS Validation
Figure 12 Tag with Locations Being Reported on the Kafka Consumer Console
Operational Validation: Static Testing
There are two methods for validating static location accuracy. The first method involves the use of reference tags
placed in permanent, known locations. The second method involves the use of a denser, however, temporary grid
of tags. Both reference tags and temporary grid tags have known tag IDs and their exact locations are precisely
measured.
The following are guidelines for static testing of reference tags:
•Use a mid-large sized tag with read ranges of at least 25’ that are designed for industrial environments and
can be permanently mounted. The Dura 1500 tag manufactured by Omni-ID has excellent read range and
is optimized for mounting on metal.
•Reference tags should be encoded using the guidelines outlined in the ZAATS Tag Data and Numbering
Guide, (p/n MN-003199-xx).
•Locate the tags at various heights and in areas where they will be minimally disturbed.
•Do not mount tags closer than 5’ to an ATR reader; mount the tags a minimum of 18” off the ground; and
do not mount the tags such that the reported bearing to the closest ATR reader is higher than 55 ⁰
elevation; i.e., the 0⁰ elevation beam is pointed at the floor (boresight beam) and the 90⁰ elevation beam is
43
Post-Installation ZAATS Validation
pointed at the horizon. For example, if a reference tag is mounted 6’ off the floor, and the ATR readers are
mounted at 16’ off the floor, then the x-y distance from the reference tag to the closest ATR reader should
be less than 15’. As another example, if the reference tag is mounted 18” off the floor, then the closest ATR
reader mounted 16’ off the floor should be no more than 21” away. This angle can be easily measured
using handheld laser range finder devices.
•Use enough tags so that each ATR reader can reliably read at least one tag, preferably two. Also, ideally
place the reference tags so that they are read by more than a single ATR reader.
•Record the exact x-y-z location of each reference tag (measured using the Disto 3D system) and store the
information into the file ref_tag_info.csv.
•Use the built-in feature of the RTLS Demo Application to analyze and report the location accuracy statistics
of the reference tags. See the RTLS Demo Application User Guide (p/n MN-003509-01) for more
information on capturing accuracy statistics.
Using reference tags is a way to ensure proper operation and ongoing health of the RTLS system, even after
handover to an end user. The RTLS system can be configured such that reference tag locations are monitored and
a notification event is sent if the recorded locations deviate by greater than a configurable distance, typically 4’.
The use of reference tags is one method to validate the static location accuracy of the RTLS system. However,
more tag location estimates are needed across the entire coverage area to ensure that the system fully meets the
accuracy objectives specified during the requirement definition phase. Whereas the reference tags are permanent,
the method described below is temporary, although, highly effective at ensuring proper system operation.
An example of a reference tag attached to a permanent metal object is illustrated in Figure 13.
Figure 13 Reference Tag Attached to Permanent Metal Object
A second method for validating static location accuracy involves the use of RFID tags placed in a grid or array. The
tags are surveyed with the DISTO system (See Appendix: Leica 3D Instructions for ATR7000) and their exact x-y-z
locations recorded. The surveyed locations, also referred to as “ground truth”, are then compared to the tag
44
Post-Installation ZAATS Validation
locations estimated by the RTLS system. In this method, RFID tags are temporarily located within the coverage
zone as shown in Figure 14.
The following are tips and guidelines for testing RTLS system operation with temporary grid tags:
•Use omni-directional tags with read ranges of at least 30’. The Zebra Sunrise RTLS tag is an excellent tag
for this purpose.
•Grid tags should be encoded using the guidelines outline in the ZAATS Tag Data and Numbering Guide,
(p/n MN-003199-xx)
•Locate the tags at heights between 2’ to 4’ off the floor.
•Place tags throughout the entire coverage zone, approximately 10-15’ apart.
•If it is not practical to cover the entire area in one step, the process can easily be broken up into multiple
steps. Also, not every facility lends itself to such a uniform coverage of tags and certain trade offs will have
to be made.
•The use of a measuring wheel is highly recommended to setup a grid of tags very quickly with reasonable
precision.
Figure 14 Example of Grid Tags Used to Verify Static Location Accuracy with ATR Locations Superimposed
•To streamline the process, the origin of the grid can start directly underneath the known location of one
ATR7000. Next, setup the tag grid relative to this known location using the measuring wheel to spot and
45
Post-Installation ZAATS Validation
record the grid tag locations. Optionally, the Leica 3D Disto may be used for more precise grid tag
locations for installations that require the highest levels of location accuracy.
•If it is not practical to cover the entire area in one step, the process can easily be broken up into multiple
steps. Also, not every facility lends itself to such a uniform coverage of tags and certain trade offs will have
to be made.
•Record the exact x-y-z location of each grid tag (measured using the Disto system) and store the
information into the file grid_tag_info.csv.
•Use the built-in feature of the RTLS Demo Application to analyze and report the location accuracy statistics
of the grid tags. See the RTLS Demo Application User Guide (p/n MN-003509-01) for more information on
capturing accuracy statistics.
An example of tag location estimates for a typical ZAATS system, with coverage optimized for location accuracy is
shown in Figure 15. A statistical analysis of this data reveals that 95% of the reported tag location estimates were
within 4’ of the actual location.
NOTE: It is important to ensure that 100% of the grid tags are reported by the RTLS system with no
coverage holes.
Figure 15 Example of Grid Tags Used to Verify Static Location Accuracy
46
Post-Installation ZAATS Validation
Operational Validation: Dynamic Testing
Once static location accuracy has been measured and validated, the final step in post-installation validation is to
measure and validate the dynamic location accuracy of the system. Many of the same principles used to determine
static location accuracy are employed for dynamic location accuracy. The procedure consists of establishing
known fixed locations and moving one or several tags between the known locations, and then comparing “ground
truth” to the locations estimated recorded.
Figure 16 illustrates a dynamic test procedure where the starting location is in front of the dock door labeled Door 1
and the ending location is in front of Door 18. The test is conducted where a tag is moved at close to constant
speed between the known locations while the RTLS system is recording location estimates in real time. The test
should be performed at two speeds, approximately 30-50% of the maximum anticipated speed and at 100% of the
maximum anticipated speed. The former can be performed in the form of a walking test where a tag is walked at a
constant pace between the known locations. In cases where multi-tagged items (forklifts, dollys, etc) are being
tracked, the latter is ideally performed with the forklift, hand truck or dolly carrying the tagged items.
Figure 17 illustrates a second dynamic test procedure using a zig-zag pattern. As with the rectangular path, the test
is conducted where a tag is moved at close to constant speed between known locations while the RTLS system is
recording location estimates in real time. As before, the test should be performed at two speeds. In cases where
multi-tagged items (forklifts, dollys, etc) are being tracked, the higher speed test is ideally performed with the
forklift, hand truck, or dolly carrying the tagged items.
The following figures visualize these two testing procedures:
Figure 16 Example of Movement Pattern Used to Verify Dynamic Location Accuracy
47
Post-Installation ZAATS Validation
Figure 17 Example of Zig Zag Pattern Used to Verify Dynamic Location Accuracy
The following are tips and guidelines for dynamic testing:
•Use omni-directional tags with read ranges of at least 30‘ and encode tags using the guidelines outlined in
the ZAATS Tag Data and Numbering Guide, (p/n MN-003199-xx).
•Locate the tags at heights between 2’ to 4’ off the floor.
•Endpoints should be situated such that tags are moved throughout the entire coverage zone.
•Record the exact x-y-z location of each endpoint (measured using the Disto system) and record the
information into the file dyanmic_testi_info.csv.
•Use the built-in feature of the RTLS Demo Application to analyze and report the location accuracy statistics
of the dynamic tags. See the RTLS Demo Application User Guide (p/n MN-003509-01) for more
information on capturing accuracy statistics.
End User Handover
Prior to handover to an end user, the system designer/solution architect will review the validation test results and
prepare a final report. Table 7illustrates a template that can be used to summarize validation test coverage and
location accuracy results that typically should be included in the report.
Depending on end-user specific requirements, there may be additional features and testing required; e.g.
“multi-tag” testing, directionality testing, etc.
48
Post-Installation ZAATS Validation
Table 7 Validation Test Results Template
General Test Conditions
Date Tested:
Location:
Tested By:
Static Testing:
Reference Tags - Coverage
Static Testing:
Reference Tags - Location Accuracy
Static Testing: Grid Tags - CoverageNumber of TagsPercentage of Tags Read
Static Testing: Grid Tags - Location
Accuracy
Dynamic Testing: Slow Speed - Location
Accuracy
Number of TagsPercentage of Tags Read
ExpectedActual
100
R50R95
Expected ActualExpected Actual
< 2.0’< 4.0’
Expected Actual
100
Number of TagsR50R95
Expected ActualExpected Actual
< 2.0’< 4.0’
Number of TagsR50R95
Expected ActualExpected Actual
< 3.0’ < 5.0’
Dynamic Testing: Fast Speed - Location
Accuracy
Depending on end-user specific requirements, there may be additional features and testing required; e.g.
“multi-tag” testing, directionality testing, etc.
Number of TagsR50R95
Expected ActualExpected Actual
< 4.0’< 6.0’
49
Appendix: Tools and
Resources
Introduction
The following table summarizes tools and resources that are recommended for deploying a ZAATS system.
Tools and Resources
Table 8 Tools and Other Resources Used in a ZAATS Deployment
ToolsSupplier
General Tools
Gloves
Zip-Ties
Plier Set
Screwdriver Set
Laser Level
Wrench Set (Basic)
Ratcheting Wrench Set (Recommended)
Bosch GLM80 Laser Rangefinder (Basic)
Leica E7400x Laser Rangefinder (Recommended)
RFID Reader for Read Range TestingZebra RFD8500
USB RFID Reader for RFID Tag Programming
Mounting Hardware
Strut Channel 1 Foot Long Available from McMaster
Clamps I-BeamAvailable from McMaster
Channel Nuts 1/2-13Available from McMaster
50
Tools and Resources
ToolsSupplier
Hex Nuts 1/2-13Available from McMaster
Wave Disc SpringAvailable from McMaster
Measuring and Layout, Advanced
Laser Scanning Distance MeterLeica 3D Disto
Aluminum Tripod Leica CTP104D 790226
Self-Adhesive TargetLeica 780967
Measuring WheelLufkin 12-1/2 in. Contractors Measuring Wheel
LED FlashlightMedium to Large-sized with Adjustable Zoom Head
Binoculars
Computer and Networking
Managed PoE+ Gigabit Switch with SFPUbiquiti Networks EdgeSwitch or equivalent
WAN Router, with WiFICradlePoint IBR600C with LTE/HSPA+/EVDP
Verizon
Cabling
1000 Feet Bulk Cat6 STP Ethernet Cable - Solid
Twisted Pair - Cat6 Shielded 550Mhz 24AWG Full
Copper Wire Pull Box - In -Wall (CM), Blue
Network Tool Repair Kit SGILE Pro 9/1 (or equivalent)
Tone Generator and Probe KitFluke Networks 26000900 Pro3000 (or equivalent)
8-Wire In-Line Modular Adapter with K-PlugFluke Networks 10230101 (or equivalent)
51
Appendix: Leica 3D
Instructions for ATR7000
Introduction
This appendix describes step-by-step instructions to utilize a range finding device to obtain actual, ground-truth
coordinates of the ATR readers, facility landmarks, reference tags, etc.
Detailed Steps
Location accuracy of the ZAATS system depends on having accurate coordinates (“ground truth”) of the fixed
facility landmarks, ATR readers, reference tags, and locations of static tags and walking path endpoints used
during post-installation validation. The Leica 3D DISTO ™ , a cross between a surveyor’s robotic total station and a
hand-held laser distance measurer, can significantly enhance the accuracy and reduce the time required to
perform these critical measurement tasks.
There are two ways to survey the ATR7000 readers, the bottom method (locating the center point of the antenna
radome) or the side method (locating the z-reference point of the south face or north face of the reader). The side
method is quicker, although, the bottom method is somewhat more accurate, depending on the skill level of the
surveyor. Both methods are described below. Therefore, the angle from the Disto to the ATRs being measured
should be 15 degrees or greater (referenced to the horizon). With this limitation in mind, depending on the installed
height of the ATR7000 readers, one will be able to survey anywhere between 2-5 systems per Leica 3D Disto
location using the bottom method or up to 10 systems using the side method before needing to relocate the Disto.
The steps involved with using a Leica 3D Disto for ATR7000 installation are outlined below:
1. Leica 3D Disto Familiarization. Please refer to the extensive documentation and manuals available in the
included CD with the Leica 3D Disto system or online
(https://lasers.leica-geosystems.com/blog/3d-disto-manuals-documents
Disto tool and procedures, and the operation of its software. Once the system documentation has been
reviewed, it is highly recommended to practice with the system and software to gain further familiarity before
heading to a live site where the system will be used.
2. X,Y,Z (0,0,0) Origin Point. The first step in surveying a newly installed deployment is establishing the site
origin. The first point that the Leica 3D Disto system will measure is the z,y,z origin (0,0,0) point defined during
the requirements phase. It is also important to have define the +x and +y directions used in the facility (which
defines the reference “north” direction, etc. The 0,0,0 origin point should preferably be a “hard” building
reference point (landmark) that cannot be moved, such as the corner of a building.
) to gain familiarity with the Leica 3D
52
Appendix: Leica 3D Instructions for ATR7000
3. Defining the X-axis. The next point that the Leica 3D Disto system will measure defines the +x axis and
direction. Measuring clockwise along a wall or floor from the origin point will be defined as the +x direction within
the Leica software, and measuring counter-clockwise from the point of origin will be define as the -x direction in
the Leica software. Note that it will be quite common to end up with a reversed coordinate system within the
Leica software if it’s not possible to survey in the preferred direction. This is not an issue and can simply be
post-processed later.
4. Relocating the Leica 3D Disto System
a. While 3 secure points are the bare minimum for a system relocation, it is highly recommended to use 4-5
secure points every time, both for the best possible relocation accuracy and as a safeguard against having
an issue with a secure point that results in a failed re-location and then having to recover.
b. The secure points, by definition, need to be visible to the system in both the previous and the relocated
position.
c. It is advantages in locations with higher ceilings to define several secure points on ceiling beams and
structures, as these can easily be seen up high, and away from ground level structures and obstacles that
can complicate the relocation procedure.
d. The Leica #780967 self-adhesive target note will stick to most building surfaces, although some surfaces
might need to be wiped down first.
e. Although the Leica 3D Disto system can be used by a single person, a two-person surveying team, each
familiar with the 3D Disto, will allow one to drive the 3D Disto system while the other counts ahead to set
additional secure points for relocating the system as the surveying progresses through the facility. The extra
team member can also help to spot alignment to secure points as the system measures them for relocation.
5. ATR System Measurement
a. In the bottom method, aim the Leica 3D DIsto system at the bottom center of the antenna radome and note
the x-y-z location. The x-y-z location is given by the actual measurement, however, the z location needs to
be compensated. The reference z-axis height of the reader is defined as the position of the antenna ground
plane relative to ground level. This position is located at the seam where the top cover meets the antenna
radome, approximately 4.2” from the bottom of the radome. Thus, one will need to use the vertical offset tool
in the Leica 3D Disto software. Measuring the bottom center of the radome and setting a -4.2” (-0.35’) z-axis
vertical offset will properly define and measure the z location of the ATR reader.
b. The ATR7000 readers can also be surveyed from their sides. Locate the Leica 3D Disto system such that
the South facing side of multiple ATR7000 readers can be observed from the survey point. Aim the Leica
surveying system at a point exactly in the middle of the South side of the ATR7000 reader at the seam
where the top cover meets the antenna radome. As before, this represents the position of the antenna
ground plane and the true z-axis reference point of the reader. Next, use the offset tool of the Leica system
software to compensate for the 9.5” difference between the south face of the reader and its center point (i.e.
add +9.5” to the measured y-position of the south face). This will require greater care to spot accurately,
however, it should allow a greater number of ATR7000 readers to be surveyed per location and allow more
complete use of the Leica 3D Disto’s long range capability. The same process can be applied, if needed, to
then work from North to South along the next rows of ATR7000 readers, but this time targeting the direct
North face of each system, and then applying a -9.5” y-axis offset to record the true center location. This
method can also be used along the East-West axis of the system if the site layout favors this approach.
Accordingly using a 9.5” offset in the +x or -x-axis direction to measure the system center as appropriate, as
opposed to +/- y-axis offsets if surveying along the North-South axis.
53
Appendix: Leica 3D Instructions for ATR7000
Figure 18 Reference Orientation of the ATR7000 Reader
6. Repeat steps 4-5 until all secure points, ATR7000 overhead readers, and permanent reference tags have been measured. Also, capture x-y-z locations of temporary static tags and walking test endpoints used for
post-installation validation. Figure X illustrates the output of the Leica 3D Disto Software in Snapshot View after
the entire facility has been surveyed.
7. Update the Equipment Manifest and Tag Reference File. After surveying is complete, all measurements
must be captured.
a. View the recorded point for each ATR7000 reader and enter its x, y, and z-axis position into the Equipment
Manifest file. This can be done through the graphical interface.
b. If the Leica system had been recorded negative x and y-axis positions for the ATR7000 readers due to its
software limitations, simply reverse their polarity back to positive by hand, if appropriate, while entering them
into the manifest.
c. Manifest example file:
Figure 19 Manifest File
d. View the recorded point for each reference tag and enter its x,y, and z-axis position into the tag reference
file.
54
Appendix: Leica 3D Instructions for ATR7000
The steps described in this Appendix also apply to reference tags, temporary tags, dynamic test endpoints, etc.
Figure 20 Leica 3D Disto Software Snapshot View with Additional Text Annotations
55
Appendix: RFID Tag Board
for ATR7000 Installation
and Validation
Introduction
This appendix describes tag placement for testing the performance of an ATR upon installation.
Tag Board Construction Guidelines
In Preliminary Validation of the ATR7000 Readers and Basic Operational Verification (Optional) a test method was
described that utilizes a tag board to ensure that readers are performing as expected after being installed when
first powered up. The figure below illustrates one example of a tag board that will enable such testing.
Figure 21 Tag Board
In the figure above, the tag board is comprised of ZBR4000 tags (see Table 2) built on a ULINE S-11249
telescoping 16 x 16 x 40-74” box. The tags are placed in a pattern on the side of the box and placed approximately
56
Appendix: RFID Tag Board for ATR7000 Installation and Validation
three feet off the floor to ensure that a 45 degree beam from an ATR system will read the tags at the boundary of
the reader’s coverage area. Tags should be placed in alternating orientations (polarizations) and separated
approximately 4-6 inches away from each other to avoid de-tuning the tags.
Tags used for individual element (400-413) testing must be placed 6-10 feet directly below the ATR reader being
tested (see Preliminary Validation of the ATR7000 Readers); the top mounted tags serve this purpose. Both the
top and side mounted tags are used for North/South/East/West testing of the ATR readers (see Basic Operational
Verification (Optional)).
57
www.zebra.com
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.