OPTIONAL RECIRCULATING ACCESSORY
MODEL RECIRC30FS AND RECIRC36FS INSTALLATION MANUAL
HOOD WIDTH DIM. "A"
30" 12 - 3/16"
36" 13 - 3/8"
Figure 1
The recirculation kit consists of:
Charcoal Filters to be mounted on each side of the blower. They absorb unpleasant odors caused by cooking.
Air deflector to be mounted on top of the hood.
This serves to redirect filtered air towards the kitchen.
Fittings material
Before installing the recirculation kit
The Installation of the Recirculation kit affects the installation of the hood, so take into consideration the following steps.
Cabinet or soffit preparation when installing the recirculation kit.
For cabinet or soffit preparation take into consideration that there’s no need to provide cutouts on walls for vertical or rear air discharge, since there is no need to install any Duct. See Figure 1 for Conduit passage cut-out. Figure 2 for Air passage cut-out on hood.
Note
The height of the hood with the recirculation kit installed increases from 11" to 15“.
Check that there is enough clearance and that minimum height from the countertop to the bottom of the hood is 24” to 30”.
Hood Preparation
The transition must not be installed, since no ducting is necessary.
LI3QSA
Wall Mount Installation
First install deflector on top of the hood then install to the wall:
1. Fit four screws C on bottom of the deflector, do not tighten completely. See Figure 2.
2. Install the deflector on top of the hood so that screws C go
respectively into Side Slots on top of the hood and Side
Slots on bottom of Deflector (See Figure 2), slide Deflector frontward until stops.
3. Tighten the four screws C from inside of the hood.
4. Fit screws (dim:3.5x9.5), from inside the hood through point B
to final assembly Deflector to the hood (see Figure 2, number depends on hood size).
5. Proceed to install hood as described on Wall Mount
Installation described at the Hood Installation Manual.
Note: The version of 30" only
requires of 7 type “D” screws.
4 7/8”
c
c
c
B
Side Slot (on bottom of Deflector)
Vertical Air cut - out
Side Slot (on top of Hood)
c
Pp.1
SCREWS
C
B
3
4
4
4
Figure 2
CB