Sunway NT 6000, NT 4000, NT 2600 User Manual

0 (0)

MANUAL

User Manual for Sunways

Solar Inverters NT 2600, NT 4000 and

NT 6000

180 mm

300 mm

mm 510

List of Contents

1.0General information

1.1

Safety information

83

General safety information

 

 

 

84

Opening the unit

 

1.2

Sunways Solar Inverters

85

Scope of supply, inspecting the delivery

 

 

NT 2600, NT 4000 and NT 6000

86

Integration into the PV system

 

 

 

 

Design of the PV generator

EN

 

 

87

Standard components of a PV system

 

 

 

88

Protection concept

 

2.0Information on installation

2.1

Safety information

90

Electrical safety

 

 

 

Mechanical safety

 

 

91

Information on cleaning

2.2

Installation

93

Requirements on the place of installation

 

 

94

Electrical connection and cable entry

 

 

95

Grid connection

 

 

97

PV generator connection

 

 

98

Important Information

 

 

100

Communication connections

79

 

102

Connecting the sensors

2.3 Commissioning

104

Switching the solar inverter on and off

 

106

Configurations

 

108

Structure and menu levels for configuration

3.0Information on operation

3.1

Monitoring and diagnosis

111

Display

 

 

112

Data memory

3.2

Sunways NT Monitor software

113

General information

 

 

114

Initialising the remote modem

 

 

115

Connection and circuitry options

 

 

120

Configuring the interface cables

 

 

122

Sunways NT Monitor data acquisition

 

 

123

Operation of Sunways NT Monitor

3.3

Fault indications

125

Screen displays

3.4

Fault diagnosis

127

Indications, causes and remedies

3.5

Warranty terms and conditions

130

Warranty period

 

 

 

Terms and exclusion of liability for

 

 

 

solar inverters

80

4.0Appendix

4.1

Subject and abbreviation index

133

Designation and description

 

4.2

Function and information index

135

Functional principle and explanations

 

 

 

138

Block diagram

 

 

 

140

Technical data

 

 

 

144

TYCO SOLARLOK connectors

 

 

 

146

Conformity and safety declarations

 

 

 

150

General exclusion of liability, rights,

EN

 

 

 

registered trademarks

81

1.0 General information

82

1.1Safety information

The User Manual contains safety hints. These are identified by a triangle with an exclamation mark.

!

General safety information

All safety hints contained in this section and throughout the User Manual must

be complied with at all times to guarantee the user's safety. The described product must not be operated if any mechanical or electrical components are defective.

Before commissioning the system, we

strongly advise you to carefully read and EN heed the instructions! Non-compliance

can have serious consequences, for example damage to the unit or other property or physical injuries with possible loss of life.

The solar inverter must be installed by a trained, qualified electrician. The electrician must be approved by the competent electricity board (EB).

The relevant tasks to be carried out are identified by an additional adjacent symbol in the respective chapter headings.

83

Opening the unit

! Before opening the cabinet, the unit must always be disconnected from the grid and from the PV generator.

The unit continues to conduct a hazardous voltage internally and at the connection sockets for ca. five minutes after disconnecting from the PV generator. The energy storage capacitors are only fully discharged after this period.

After disconnecting the unit from the grid and from the PV generator, you must wait at least five minutes before opening the unit.

84

1.2 Sunways Solar Inverters NT 2600,

Inspecting the delivery

 

NT 4000 and NT 6000

 

 

 

The condition of our products is checked

 

Scope of supply

prior to delivery. Although our products

 

 

are carefully packed in recyclable packing,

 

· Sunways Solar Inverter in the NT series

transportation damages can still occur.

 

· Installation frame

These are generally the transport compa-

 

· Manual, setup, warranty card, CD-Rom

ny's responsibility.

 

with software

 

 

· 2 pairs of TYCO SOLARLOK connectors

Please inspect the delivered solar inverter

 

 

thoroughly!

EN

 

If you discover any damage to the packing

 

 

or the solar inverter, please inform the

 

 

transport company immediately. Your

 

 

specialist dealer will be glad to assist you

 

 

if required. Any damages must always be

 

 

reported to the transport company in wri-

 

 

ting seven days after receipt of the goods

 

 

at the latest.

 

85

Integration of the solar inverter into the PV system

Design of the PV generator

The technical data of the selected PV generator must be within the specification of the solar inverter (see Technical Data). The Sunways NT Sundim design program for the PV generator may be helpful. Sunways NT Sundim is available on the enclosed CD or from our website, www.sunways.de.

Please take account of the following points before planning your system:

·Pay attention to the skyward alignment of the modules. You will obtain maximum yield in Central Europe with a module inclination of 30° to the horizontal and a direct southerly alignment of the generator field.

·The output of the cells decreases as the module temperature increases. Install your PV generator with adequate rear ventilation.

·Check your PV generator for soiling ca. every three years. This occurs particularly at the lower edge of the modules and forms a film, which even heavy rain cannot wash away. Decreases in yield can be prevented by cleaning with a wet cloth or a brush.

·Avoid shading of individual modules or solar cells in your system. This can result in heavy losses in yield.

86

Standard components of a PV system

Depending on the recommendations of your electrician, your PV system will consist of the following components:

Standard components of the PV system

PV

 

SUNWAYS NT

 

(1)

PV generator switch

EN

 

 

(2)

sensor

 

 

 

Irradiation sensor with

 

 

 

 

 

 

integrated temperature

 

PV

(1)

(3)

(4)

(3)

Mains fuse

 

 

(4)

Energy meter

 

(2)

 

 

PC

Grid

 

 

PV generator switch:

Designed as DC load break cut-out to cut off the PV generator from the solar inverter. Dimensioning: min. 800 V, 16 A

Grid connection:

3-phase (Feed-in: 1-phase; grid monitoring: 3-phase)

87

Protection concept

The following parameters are monitored

 

continuously and in parallel by the micro-

 

controller and displayed on the screen:

 

· AFI error (ground fault)

 

· Overheating of the cooling element

 

·

DC overvoltage

 

·

AC undervoltage/overvoltage

In the event of a fault, the conversion is immediately blocked and the grid relay disconnected.

In addition, the following protective devices are provided on both grid and PV generator side:

· Grid-side varistors

Protect the power semiconductors from high-energy, time-limited voltage spikes on the grid and provide for a reduction of energy in the throttle in the event of grid disconnection.

· Generator-side varistors

Thermally monitored varistors provide protection against atmospheric overvoltages (e.g. due to remote strikes during storms).

88

2.0Information on installation

89

2.1 Safety information

Electrical safety

Before opening the cabinet, the solar

! inverter must be disconnected from the grid and from the PV generator.

The solar inverter continues to conduct

a hazardous voltage internally and at the connection sockets for the PV generator for ca. five minutes after disconnecting from the PV generator. The energy storage capacitors are only fully discharged after this period.

After disconnecting the solar inverter from the grid and PV generator, you must wait at least five minutes before opening the solar inverter.

Mechanical safety

During installation, make sure that the cables or connection lines fitted to the solar inverter are securely laid and that suitable mechanical cable supports (cable ducts etc.) are used.

90

!

91

Information on cleaning

 

Before cleaning, disconnect the system

 

from the power grid by opening the grid

 

breaker (main fuse) and open the DC

 

switch on the PV generator, in order to

 

exclude the danger of electric shocks.

 

Use a soft, dry cloth to clean the system.

 

Never use corrosive, solvent-containing

 

or abrasive cleaners or polishes.

EN

 

2.2Installation

The solar inverter must be installed by a trained, qualified electrician. A special tool is

necessary for installation. Please read this chapter very carefully.

Warm

Air

mm 300

150 mm

150 mm

Cool

Air

mm 300

92

Requirements on the place of installation

· Mechanical bearing capacity

During installation please bear in mind that the solar inverter weighs 26 kg. The installation base must be firm and capable of continuously bearing the weight.

· Thermal interaction

The installation base must consist of flame-retardant material (e.g. no wood or plastic in the base; concrete and brickwork are suitable), as the heat sink emits temperatures up to max. 85°C.

A minimum distance of 300 mm must be maintained above and below the cabinet, and 150 mm on right and left from other units, cabinets, ceilings, cable ducts etc..

The solar inverter must be installed vertically, so as not to hinder adequate free convection.

Several solar inverters must not be installed on top of each other, so as to prevent reciprocal heating.

If installing the solar inverter in a switch box, ensure adequate heat dissipation.

The ambient temperature must not fall below or exceed –25°C or +40°C.

The solar inverter should not be exposed to direct solar irradiation, so as to protect it from unnecessary external heating.

· Protection from damp and foreign bodies

EN

 

The IP54 high protection class permits installation both inside and in roofed outdoor areas, but the solar inverter must not be exposed to direct rain.

Make sure that the solar inverter cannot be exposed to foreign bodies (deposits of dust and dirt).

93

Sunway NT 6000, NT 4000, NT 2600 User Manual

Electrical connection and cable entry

!

For installation, please observe the instructions in the "Setup" leaflet!

– DC – DC +DC +DC

If the solar inverter is fixed to the installation frame, the electrical connection can be led through. The unit may only be opened by a qualified electrician. The cabinet cover must first be released and removed.

The following cable inlets are located on the underside:

RS 232, RS 485,

 

Irradiation sensor with inte-

 

grated temperature sensor

AC wiring loom

cable

L1, L2, L3, N, PE

Fig.: Inlets on the unit underside

94

Grid connection

!

The grid connection of the solar inverter must have 5 wires (L1, L2, L3, PE, N). Cable cross-sections of 5 x 4 mm2 are recommended.

The solar inverter is connected to the supply grid via the circuit board terminals inside the unit.

As line safety element in the grid feed-in direction, we recommend a 3 x 25 A automatic cut-out. No consumption units must be connected to the feed line from the solar inverter to the automatic cut-out. The solar inverter only feeds in via terminal L1.

If several solar inverters are operated in parallel, the feed-in phase L1 of the unit

must be evenly distributed over grid EN phases L1, L2 and L3 (see figure below).

Three-phase grid connection distributed over three units

L1 N L2 L3 PE

L1 N L2 L3 PE

L1 N L2 L3 PE

L1

L2

L3

N

PE

95

You must use adequately dimensioned cable cross-sections in order to avoid a considerable increase in the grid impedance between the domestic distribution and the solar inverter. The terminal range of the AC terminals is 0.5 to 6 mm2 for rigid cables and 0.5 to 10 mm2 for flexible cables. With a high grid impedance, i.e. with a long line or too small a crosssection, the voltage increases at the grid terminal during feed-in.

If the terminal voltage exceeds the permissible value, the solar inverter is disconnected from the grid.

Carefully perform the following steps:

·Check that there is no voltage before introducing the supply main into the unit.

·Lead the 5-core AC cable (outer diameter 9 – 17 mm) through the M25 threaded cable gland.

·Connect cables L1, L2, L3, PE and N to the relevant circuit board terminal with the help of a slot-head screwdriver (see figure below).

· Tighten the M25 screw connection, so that the cable cannot exert any mechanical force on the circuit board terminal.

96

PV generator connection

!

· Preparation

Execute the DC cabling according to your electrician's system dimensioning. Check each PV string for correct functioning

by performing a no-load voltage current and short-circuit current measurement.

To achieve the necessary protection against hazardous contact voltage during the installation of PV systems, the positive and negative conductors must be kept separate from the ground potential (PE).

Contactable, conductive parts of the PV generator (e.g. metal frame, supporting structure etc.) must be earthed (connected to PE).

Check that the generator is free from ground faults.

Make the electrical connection to the 97 solar inverter.

· Connection

The PV generator is connected via the externally accessible, shock-proof TYCO SOLARLOK connectors, which are enclosed with the delivery. The TYCO SOLARLOK connectors are designed for a cable crosssection of 4 mm2 and must be crimped (see data sheet and connector assembly with TYCO crimping tool on page 144).

Connect the two right DC female connectors

EN

with «+», the two left DC female connectors

 

with «-» of the PV generator (see figure

 

below).

 

Important information

!

·The direct PV generator voltage is available internally after connecting the PV generator to the solar inverter via the DC connectors and switching on the PV generator switch!

·Please note that the input capacitors are still charged even after switching off the PV generator switch or removing the PV generator plug connection!

·After disconnecting the AC and DC side, the solar inverter still conducts voltage for up to ca. five minutes!

·Therefore, wait for at least five minutes until the internal voltage has dissipated. Then you can work on the terminals!

Please note the general safety information on pages 83 and 84!

98

·The DC voltage can be up to 750 V. The unit may only be opened by a qualified electrician!

·Always disconnect the PV generator side first by opening the PV generator switch, and then the grid connection by isolating the relevant mains fuse!

·If you do not have a PV generator switch

in your PV system, you must disconnect

EN

the grid connection first of all by isola-

 

ting the relevant mains fuse. However, a

 

«grid error» will be entered in the error

 

memory of the solar inverter!

 

·Disconnection of the PV generator by removing the TYCO SOLARLOK DC connectors must never be performed under load. In the event of non-compliance, the connectors could be damaged by a strong electric arc. In this case, the relevant connectors must be replaced!

99

Loading...
+ 53 hidden pages