Installation Instructions
Cerberus Division
CERBERUS PYROTRONICS
TM
Model ALI-8
The CERBERUS PYROTRONICS
ALI-8 is an enclosure assembly that accommodates up to eight TRI-60Ds to provide the
interface between the MXL and the
AnaLASER control panels (See also
Installation Instructions,
Fasten the enclosure securely to a clean, dry,
shock-free, and vibration-free surface. Consider the following when mounting the box.
—Mounting height for visual and manual
access to the modules in the enclosure
—Weight and size of the enclosure
—Local mounting codes
P/N 315-092329).
TM
Model
TRI-60D
—The maximum cable length of 200 feet
(18 AWG) for the TRI-60Ds to the
AnaLASER equipment
When mounting, position the backbox clear of
obstruction so that the door can open freely
and so that the modules are easily accessible.
TO INSTALL THE ALI-8
1. Slip the door off the hinges of the box and
put it to one side temporarily.
2. Cover the opening in the door by placing
the black metal plate over the studs
located on the door.
Siemens Building Technologies, Inc.
8 Fernwood Road
Florham Park, New Jersey 07932
P/N 315-093305-2
Figure 1
Enclosure for the ALI-8
Siemens Building Technologies, Ltd.
50 East Pearce Street
Richmond Hill, Ontario L4B 1B7 CN

3. Fasten the plate to the door using the six
6-32 nuts provided.
4. (Refer to Figure 1.) Remove knockouts in the
backbox where field wiring is required.
5. Place the interface plate over the four studs
marked A in Figure 1, and secure it to the
enclosure with the four 6-32 nuts provided.
6. Hold the empty enclosure against the wall at
a height that provides easy access.
7. Mark drill points on the wall in the center of
the two slots on the upper rear of the box.
8. Drill the two holes and screw in the top
screws using 1/4" or 3/8" mounting hardware
(user supplied). Leave a small gap between
the wall and each top screw.
9. Mount the enclosure on the two screws and
then install the bottom screws.
10. Tighten all screws securely against the back
wall of the enclosure.
11. Place the TRI-60Ds on the studs (marked B)
of the interface plate in two rows of four
across making sure that all of the screw
terminals on the TRI-60Ds are facing in the
same direction.
12. Fasten each TRI-60D to the interface plate
using two 6-32 nuts provided.
13. Slip the door back on the hinges of the
enclosure.
P/N 315-093305-2