7. Connecting the flue gas discharge and air supply 16
7.1 General 16
7.2 Conventional open flue installation 16
7.2.1 Possible lengths for the flue gas discharge pipe 17
7.3 Room sealed installation 18
7.3.1 Possible lengths for the air supply and flue gas discharge 18
7.3.2 Discharge in different pressure areas 20
7.3.3 Connection of flue gas discharge and choice of material 21
7.3.4 Air supply connection and choice of material 21
7.3.5 Additional Directives 21
8. Control and electrical connections 22
8.1 General 22
8.1.1 Boiler control 22
8.1.2 Modulating controls general 22
8.1.3 Modulating room control 22
8.1.4 Modulating weather-compensated control rematic® 22
8.1.5 Modulating cascade controller MC4 23
8.2 Electrical specifications 23
8.2.1 Mains voltage 23
8.2.2 Control box 23
8.2.3 Fuse ratings 24
8.3 Electrical connection options 24
8.3.1 Connection options of standard control unit (PCU-01) 24
8.3.2 On/off control (OT) 24
8.3.3 Modulating controls (OT) 24
8.3.4 External interlock (BL) 24
8.3.5 Input release (RL) 25
8.3.6 Circulation pump (Pump) 25
8.3.7Connecting a PC 25
2
114494-03
GAS 210 ECO PRO
Table of contents
8.3.8 Connection options for the PCB - SCU - X01 25
8.4 Connection options for the optional 0 - 10 V control PCB (IF-01) 26
8.4.1 Connection status (Nc) 26
8.4.2 OTm connection 26
8.4.3 Analogue input (0 - 10 V) 27
8.4.4 Analogue output (0 - 10 V) 27
8.5 Connection options of the optional expanded control/protection PCB (SCU-S01) 28
8.5.1 Flue gas damper control (FgV) 28
8.5.2 Hydraulic valve control (HdV) 28
8.5.3 External gas valve control (EgV) 28
8.5.4 Operation signal and failure signal (Nc / No) 28
8.5.5 Water pressure sensor (Wps) 28
8.5.6 Outside temperature sensor (Tout) 29
8.5.7 Minimum gas pressure switch (Gps) 29
8.5.8 Gas leakage control (VPS; only for 210- 160 and 210- 200 boilers) 29
8.5.9 Wiring diagram 30
9 Commissioning 31
9.1 Control panel 31
9.1.1 Normal start-up procedure 31
9.1.2 Fault during start-up procedure 32
9.1.3 Reading current values 33
9.1.3.1 Status and sub status 34
9.1.4 Adjusting the boiler to the system 34
9.1.5 Changing parameters at user level (without access code) 35
9.1.6 Changing parameters at service level (with access code) 35
9.1.7 Resetting factory settings 38
9.1.8 Setting manual operation ( symbol) 39
9.2 Commissioning 39
9.3 Taking the boiler out of operation 42
9.3.1 Boiler with frost protection, out of operation for a long time 42
9.3.2 Boiler without frost protection, out of operation for a long time 42
10. Inspection and maintenance 43
10.1 General 43
10.2 Combustion check of the boiler 43
10.2.1 Corrective maintenance 43
10.2.2 Cleaning the fan 44
10.2.3 Cleaning the heat exchanger (flue gas side) 46
10.2.4 Cleaning the burner 47
10.3 Cleaning the trap 48
10.4 Checking the ignition electrode 48
10.5 Checking for leaks 48
10.6 Checking water pressure 48
10.7 Putting boiler back into operation 48
11. Control stops and faults 49
11.1 General 49
11.2 Control stops and faults 49
11.3 Control stop codes 49
11.4 Fault codes 51
11.5 Control stop - and fault memory 54
11.5.1 Reading faults 55
11.5.2 Deleting control stops or faults 55
114494-03
3
Table of contents
GAS 210 ECO PRO
12. Service parts 56
12.1 General 56
12.2 Exploded view 57
13. Regulations 58
13.1 General 58
13.2 Standards 58
13.3 Remeha factory test 58
13.4 Supplementary guidelines 59
14. Technical specifications 60
14.1 Technical data 60
15. Efficiency data and gas inspection labels 61
15.1 Unit usable efficiency (HR efficiency) 61
15.2 Water-side efficiency 61
15.3 Zero-load losses 61
15.4 Description of specifications 61
15.5 Accessories 62
15.6 Services 62
15.7 Type of unit 63
15.8 Operating principle 64
15.9 Boiler Control 64
15.9.1 Temperature control 64
15.9.2 Low water level protection 64
15.9.3 Maximum protection 65
15.9.4 Frost protection 65
16. Application data 66
16.1 General 66
16.2 Air and flue gas application options 66
16.3 Hydraulic application options 66
16.4 Cascade application 66
16.5 Control options 69
16.6 Gas application options 69
17. Checklists (records) 70
17.1 Checklist for commissioning (Commissioning record) 70
17.2 Checklist for annual inspection (inspection record) 70
17.3 Checklist for maintenance (maintenance record) 71
4
114494-03
GAS 210 ECO PRO
Table of contents
114494-03
5
Preface
Preface
GAS 210 ECO PRO
PREFACE
This technical information , which contains a lot of practical information about the Remeha Gas 210 ECO PRO, a High efficiency
central heating unit, is mainly intended for installers. It contains
important instructions for safe and trouble-free operation of the
boiler before commissioning and during operation.
Read these instructions carefully before putting the boiler into
operation, familiarise yourself with its control functions, operation
and strictly observe the instructions given. Failure to do so may
invalidate warranty or prevent the boiler from operating. The boiler
is available in the following types:
- Gas 210 ECO PRO 80 (3 sections; 87 kW)
- Gas 210 ECO PRO 120 (4 sections; 120 kW)
- Gas 210 ECO PRO 160 (5 sections; 166 kW)
- Gas 210 ECO PRO 200 (6 sections; 200 kW)
The installation, commissioning, inspection and servicing of the
boiler must be carried out by a competent Corgi registered engineer who holds valid A.C.S. certification and in accordance with
current gas safety (installation and use) regulations, the building
regulations and all other relevant codes of practice.
All electrical work must be carried out by a competent engineer
and to be installed in accordance with the current IEE regulations.
If you have any questions, require an engineer to call on site, or if
you need more information about specific subjects relating to this
boiler, or it's installation please do not hesitate to contact our technical help line 0118 978 3434.
When contacting Broag with a problem on the boiler, please have
available the boiler type, Serial No (located on the bottom of the
casing), and the symptoms or fault code (the fault code is a series
of flashing digits in the display panel).
The data published in these technical instructions is based on the
latest information (at date of publication) and may be subject to
revisions.
We reserve the right to continuous development in both design
and manufacture, therefore any changes to the materials or technology employed may not be retrospective nor may we be obliged
to adjust earlier supplies accordingly.
6
114494-03
GAS 210 ECO PRO
1. EC declaration
EC - DECLARATION OF CONFORMITY
Manufacturer : Remeha B.V.
Address : Kanaal Zuid 110
City, Country : Postbus 32, NL-7300 AA Apeldoorn, Holland
- this is to declare that the following product(s) : Remeha Gas 210 ECO PRO
is/are in conformity with the following EEC-directives:
EEC- Directive: 90/396/EEC tested and examined to the following norms:
EN 656 A1
15240
92/42/EEC
73/23/EEC DIN EN 50165
DIN EN 60335-1
, EN 15417
(2006)
(2006)
(2006)
, EN 50165
(2001)
, EN 60335-1
(2003)
(1997 + A1: 2001)
07
(2002)
1. EC declaration
89/336/EEC EN 55014-1
EN 61000-3-2
(2000+A1:2001)
(2000+A2:2005)
97/23/EEC (article 3, sub 3)
Apeldoorn, aug. 2007
W.F. Tijhuis
Approval manager
, 55014-2
, 61000-3-3
(1997+A1:2001)
(1995+A1:2001)
114494-03
7
2. Introduction
2. Introduction
2.1 Pictograms used
2.2 Important instructions
GAS 210 ECO PRO
The following pictograms are used in this document to emphasise
certain instructions. This is in order to increase your personal
safety and to safeguard the technical reliability of the boiler. The
pictograms used are:
Useful advice.
Important instruction forcarryingout an action.
Possible risk of bodily injury or material damage to boiler,
building or environment.
Possible risk of electrical shocks. Serious bodily injury may
occur.
The boiler must be installed in a frost-free area.
Work on the boiler
Installation, commissioning, maintenance and repair work may
only be carried out by suitably qualified specialist installers in
accordance with the applicable national and local standards and
guidelines.Always disconnect the mains supply and close the main
gas cock when working on the boiler. Check the entire system for
leaks after maintenance and servicing work.
Casing panels may only be removed for maintenance and servicing purposes. Refit all panels on completion of maintenance and
servicing work.
Instruction and warning labels on the boiler must never be
removed or covered and must be clearly legible throughout the
entire service life of the boiler. Replace damaged or illegible
instruction and warning labels immediately. Generally applicable
safety instructions related to accident prevention must be consulted in addition to the information supplied in this technical documentation.
Boiler modifications
Modifications to the boilerrequire the written approval of Broag.
Keep this document near to the installation.
8
114494-03
GAS 210 ECO PRO
3. Safety
3. Safety
Adhere strictly to the specific safety instructions.
Can you smell gas? Proceed as follows:
• do not smoke and avoid fire and sparks
• do not operate electrical switches.
• close the gas cock.
• open doors and windows.
• trace possible leaks and seal them off.
• if the leak is upstream of the gas meter, notify National Gas
Emergency Service tel: 0800 1110999.
Can you smell flue or combustion gases? Proceed as follows:
• isolate the mains power supply from the boiler.
• open doors and windows.
• trace possible leaks and seal them off.
114494-03
9
4. Installation
4. Installation
4.1 Scope of delivery and installation
The boiler is supplied fully assembled and protected. The boiler
is placed on a pallet (70 x 130 cm, 145 cm high), which can be
transported with a pallet truck, hand truck, forklift truck or 4-wheel
transport boards. The packaging passes through all standard
doors (minimum width of 74.5 cm).
The boiler is installed as follows:
- Position the pallet with the boiler in the boiler room;
- Remove the fixing bands and all other packaging (some
components are packaged in the polystyrene cap);
- Lift the boiler from the pallet;
- Slide the boiler into the required position, using the recessed
handles in the boiler base;
- Cover the boiler and do not operate it whilst dust creating
construction processes or insulation to the pipe work etc. are
carried out in the plant room.
GAS 210 ECO PRO
10
114494-03
GAS 210 ECO PRO
4.2 Dimensions
4. Installation
1200
1070125
305160140140121
61
A
1272
61
316
152
1190
fig. 01 Elevation drawings
ConnectionGas 210 ECO PRO 80/120/160Gas 210 ECO PRO 200
É Flow
Ê Return
Gas connection
Ò Condensate drain
Ð Combustion air supply
Ñ Flue gas outlet
1¼” male thread1½” male thread (fit supplied adapter 1¼” > 1½”)
1¼” male thread1½” male thread (fit supplied adapter 1¼” > 1½”)
1¼” male thread1¼” male thread
Ø 32 mm externalØ 32 mm external
Ø 150 mmØ 150 mm
Ø 150 mmØ 150 mm
Dimension “A” 1309 mm1324 mm
Ì Second return (option)
1¼” male thread1¼” male thread
114494-03
450
114492LTAL21H001b
11
4. Installation
4.3 Installation and service clearances
Clearance of at least 60 cm is required at the front of the boiler.
However, we recommend a clearance of 1 m. We recommend a
clearance of at least 40 cm above the boiler control panel, at least
5 cm on the left side and at least 25 cm on the right side in connection with condensed water discharge. Install a gas cock in the
immediate vicinity of/above the boiler.
GAS 210 ECO PRO
1050
1
1490
250119050
450600
1050
2
450600
34
2100
600450450600
2930
2501190502501190
1890
2501190450
1690
1190
250250
fig. 02 Boiler room installation options
12
4501190
1690
50
114492LTAL21H002a
114494-03
GAS 210 ECO PRO
5. Water-side connections
5.1.1 Condensed water discharge
Discharge the condensed water directly into a foul water drain. In
view of the acidity level of condensate (pH between 3 and 5), only
use plastic material for the discharge pipe. After assembly, fill the
trap with clean water. Make an open connection with the drain. The
discharge pipe must slope down by at least 30 mm/m. Condensed
water must not be discharged into gutters or rain water down pipes.
5.1.2 Water treatment
• Use untreated tap water only to fill the CH system.
• The pH value of the system water must be between 7 and 9.
• Where inhibitors are being used, please refer to Broag recom-
mendations in this section and follow the manufactures instructions given.
If used correctly water treatment can improve the boilers efficiency
and increase the anticipated life expectancy of the boiler.
5. Water-side connections
For further information a special document “Remeha water quality
regulations” is available from Broag. The regulations mentioned in
this document must be followed.
As most systems contain a variety of metals, it is considered good
practice to provide some form of water treatment in order to prevent or reduce the following:
• Metallic corrosion
• Formation of scale and sludge
• Microbiological contamination
• Chemical changes in the untreated system water
All scale deposits, however small, will reduce the efficiency of the
boiler and should be prevented.
Suitable chemicals and their use should be discussed with a specialist water treatment company prior to carrying out any work
(environmental aspects, health aspects). The specification of the
system and manufacturers recommendations must be taken into
account, along with the age and condition of the system. New systems should be flushed thoroughly to BS 7593(1992) to remove
all traces of flux, debris, grease and metal swarf generated during installation. Care to be taken with old systems to ensure any
black metallic iron oxide sludge and other corrosive residues are
removed, again by power flushing, ensuring that the system is
drained completely from all low points.
114494-03
Please ensure that the new boiler plant is not in circuit when the
flushing takes place, especially if cleansing chemicals are used to
assist the process.
13
5. Water-side connections
GAS 210 ECO PRO
It is important to check the inhibitor concentration after installation, system modifications, filling the system and every service in
accordance with these instructions.
For the correct dosage and the suitability of inhibitors for use with
our boilers and for further information on water treatment or system cleaning we advise direct contact with either of the following
companies:
Sentinal ‘X100®’ manufactured by:
Sentinel Performance Solutions
The Heath Business & Technical
Park
Runcorn
Cheshire,
WA7 4QX
Tel No: 0800 389 4670
Fax No: 0800 389 4677
Email: info.uk@sentinel-solutions.net
Website: www.sentinel-solutions.net
5.1.3 Pressure relief valve
Install an pressure relief valve in the system, in accordance with
NEN 3028, between any valves and the boiler and in the flow pipe
within 0.5 m of the boiler.
5.1.4 Circulation pump
The boiler is equipped with a pump switch to connect an external
circulation pump. This pump is run once every 24 hours to prevent
sticking (24 hour pump operation). Only on/off pumps can be controlled. For connections, see Section 8.3.6.
P (%)
V
D
010203040
35
∆T (°C)
114492LTAL21H031
fig. 03 Output control characteristic
V = full loadP = heat output
D = part load∆T = temperature difference
14
The hydraulic resistance for the various output options of the
boiler is as follows:
The maximum temperature difference between flow and return,
and the maximum rate of rise of the flow temperature and boiler
block temperature are limited by the boiler's modulating controls.
As a result, the boiler is virtually unaffected by low water flow.
However for a continuous supply of heat, the boiler requires a
minimum flow of 30 % of the nominal flow at the relevant design
temperatures.
114494-03
GAS 210 ECO PRO
114492LTAL21H003a
6. Gas-side connections
6.1 Gas connection
The boiler is suitable for use with natural gas and propane* category II
department. All gas appliances must, by law, be installed by competent persons (e.g. Corgi). Failure to install appliances correctly
could lead to prosecution. It is in your own interest and that of
safety to ensure that the law is complied with.
The gas connection is at the top of the boiler. We recommend
installing a gas filter in the gas supply pipe to avoid pollution of the
gas multiblock. The gas filter's resistance must not be so high that
the minimum inlet gas pressure can no longer be achieved.
* Refer to Broag for using propane.
6.2 Gas pressure
6. Gas-side connections
. For other types of natural gas, consult our Technical
2H3P
5+6 L3+4 L
fig. 04 Gas multiblocks
6.3 Gas/air ratio control
The boiler has been factory set and tested by Remeha to natural
gas (G20) - with an inlet pressure of 17 mbar.
The boiler is suitable for 17 - 30 mbar inlet gas pressure.
For propane (LPG), an inlet pressure of 37 - 50 mbar is required.
The boiler has a zero governor gas valve. This gas valve maintains the ratio between the gas and air quantities in the burner at
a constant level under variable loads. This ensures clean and reliable combustion and high efficiency across the entire load range.
114494-03
15
7. Connecting the flue gas discharge and air supply
GAS 210 ECO PRO
7. Connecting the flue gas discharge and air supply
7.1 General
The Remeha Gas 210 PRO is suitable for conventional room ventilated or room sealed operation. Specify at the time of ordering if
the boiler is to be supplied for room sealed operation. In that case,
the boiler will be supplied with a purpose-designed room sealed
terminal, air supply connection and some accessories. The air
supply connection should rest on the heat exchanger underneath
the boiler casing after removing the standard perforated air inlet
cover. Horizontal components in the flue gas discharge system
should slope towards the boiler. Horizontal components in the air
supply system should slope towards the supply opening.
Room sealed terminals should comply with the national requirements for both horizontal and vertical outlet constructions.
Care should be taken when siting flue exit positions as a vapour
plume will be visible when the boiler is operational (flue gas temperature will be less than 80°C resulting in the water vapour condensing out on contact with the air).
Classification due to discharging flue gases
The boiler is approved according to CE with classification:
Type B23: Conventional room ventilated appliance without draft
diverter. Air supply from boiler room; flue gas discharge on roof.
Type B23P: Conventional room ventilated boiler without draft
diverter. Air supply from boiler room: flue gas discharge on roof,
metal flue gas discharge with CE symbol, meets pressure class P1.
Type C13: Room sealed boiler, connected to combined wall outlet.
Type C33: Room sealed appliance, connected to combined roof
outlet.
Type C43: Room sealed appliance in cascade configuration, connected via two ducts to a common duct system serving more than
one appliance.
Type C53: Room sealed appliance, connected to separate ducts
for the air supply and flue gas discharge, terminated in zones of
different pressure.
Type C63: Room sealed appliance, supplied without the terminal
or the air supply and flue gas discharge ducts.
Type C83: Room sealed appliance, connected to separate air
supply and flue gas discharge duct, with flue gas discharge duct
always in underpressure.
7.2 Conventional open flue installation
The open flue version extracts the necessary combustion air from
the plant room or compartment. A table showing the maximum discharge lengths can be found in Section 7.2.1.
16
114494-03
GAS 210 ECO PRO
7. Connecting the flue gas discharge and air supply
• The air supply opening must stay open.
• The installation area or boiler room must be equipped with the
necessary combustion air supply openings. These openings
must not be obstructed or shut off.
• The combustion air supply must be free of dust and chemically-
aggressive agents (such as trichloroethylene or halogenated
hydrocarbons), as used in aerosol cans, certain types of
adhesive, certain solvents and cleaning agents, and paint, etc.
7.2.1 Possible lengths for the flue gas discharge pipe
Conventional room ventilated, type B23 according to CE.
Maximum permitted flue gas discharge lengths (L) in m
Boiler typeD (mm)Free discharge
10018
210-80
11035
130+
fig. 05 Piping for the conventional room ventilated
11020
210-120
210-160
210-200
13048
150+
13022
15045
180+
13014
15031
180+
table 01 Flue gas discharge table for the open version
+ = Lengths up to 50m possible. For longer lengths, consult our
Technical department
When flue gas discharge pipes with diameters other than 150 mm
are used, an adapter is required: Ø150/100mm, Ø150/110mm,
Ø150/130mm or Ø150/180mm.
For each additional 90° or 45° bend, the pipe length must be
reduced by the amount shown in table 02.
7. Connecting the flue gas discharge and air supply
7.3 Room sealed installation
GAS 210 ECO PRO
The room sealed installation is based on the use of an air supply
pipe connected directly to the boiler. This increases the number of
installation options within a building, while the discharge location is
subject to less stringent requirements because the air supply and
flue gas discharge can be incorporated in the same pressure field.
Additional ventilation will be required to the room/compartment in
accordance with BS 6644-2005 (compartment ventilation).
In addition, air from outside is usually cleaner, which has a beneficial effect on the boiler service life. An air supply and flue gas
discharge table for the enclosed version of the boiler can be found
in table 03. For discharge in two different pressure fields, see Section 7.3.2.
The boilers can be installed on a flue dilution system, but must
have a total flue break to avoid boiler controls being affected
by the flue dilution fan pressures. For full details please contact
Broag.
7.3.1 Possible lengths for the air supply and flue
gas discharge
Room sealed appliance, type C33 according to CE.
Maximum acceptable flue gas discharge/air supply pipe
lengths (L) in m
Boiler
Model
210-80
210-120
210-160
210-200
Pipe Ø D
(mm)
1001008
130130+
130150+
150150+
1001003
13013022
13015025
150150+
13015011
15015022
180150
1301304
15015013
180150+
table 03 Air supply and flue gas discharge table for the
enclosed version
Calculated with
concentric roof feed-
through D
nominal
(mm)
[m]
+
0021H7900017
fig. 06 Piping for the room sealed appliance
18
+ = Lengths up to 30m possible. For longer lengths, consult
our Technical department
114494-03
GAS 210 ECO PRO
7. Connecting the flue gas discharge and air supply
When air supply and flue gas discharge pipes with diameters other
than 150 mm are used, adapters are required: Ø150/100mm,
Ø150/110mm, Ø150/130mm or Ø150/180mm and, for connection to our standard combined vertical roof feed-through sets, also
Ø180/150mm, Ø130/150mm or Ø110/150mm.
For each additional 90° or 45° bend, the pipe length must be
reduced by the amount shown in table 04.
For enclosed versions, combined vertical roof feed-through sets
are available, as well as sealing plates for flat roofs, in accordance
with the following drawings. Please consult our Technical department for this option.
Int
Int
Ext
Ext
Ext
Epo y l y rx a e
Ext
fig. 07 Vertical roof feed-through for room sealed operation
Pdf dakdoorvoer
114494-03
19
7. Connecting the flue gas discharge and air supply
GAS 210 ECO PRO
7.3.2 Discharge in different pressure areas
For installations where supply and discharge points are in two different pressure zones CLV system please contact Broag Technical Dept. for further details and advice. The maximum acceptable
height difference between combustion air supply and flue gas
discharge is 36 m and the maximum acceptable length of the air
supply and flue gas discharge combined is shown in table 05.
table 05 Air supply and flue gas discharge table for 'simplified
CLV system'
114494-03
GAS 210 ECO PRO
7. Connecting the flue gas discharge and air supply
7.3.3 Connection of flue gas discharge and choice
of material
Connecting the flue gas discharge:
Remove the cap from the flue gas discharge opening Ñ;
• Fit the flue gas discharge pipes seamlessly together.
• Seams and joints must be airtight and watertight or fit seamlessly.
• Horizontal parts must be oriented towards the boiler at a gradient (min.
5 cm per metre).
• Connect the pipes stress-free.
• Flue gas discharge pipes longer than 2 m must be fixed separately and
must not rest on the boiler.
Flue gas discharge:
Material:
Rigid single walled: stainless steel (316), aluminium or plastic (to comply
with building regulations).
Flexible: stainless steel (316).
Construction: all joints and seams should be gastight and watertight with
the horizontal runs graded towards the boiler (min. discharge 5 cm per
meter) to allow condensate free drainage to the boiler. Flue gas discharges longer than 2 meters must be supported independently and may not
rest on the boiler.
The flue outlet should terminate with reduction cone and bird guard only
(chinamans hat or GLC type terminals etc. should not be used).
7.3.4 Air supply connection and choice of material
Connecting air supply:
Remove air supply grille from the air supply opening Ð;
• Fit the air supply pipes seamlessly together.
• Seams and joints must be airtight and watertight or fit seamlessly.
• Horizontal parts must be oriented towards the discharge at a
gradient (min. 5 cm per metre).
• Connect the pipes stress-free.
Air supply:
Material:
Single walled, rigid or flexible: aluminium, stainless steel and plastic (to
comply with building regulations).
Air supply ducts longer than 2 meters must be supported independently
and may not rest on the boiler air inlet. Care must be taken to ensure that
if water is able to enter the duct it will run away from the boiler air inlet
connection or supply a suitable train c/w water seal trap.
7.3.5 Additional Directives
Please refer to the manufacturer’s instructions for the material in question when installing the flue gas discharge and air supply materials. If the
flue gas discharge and air supply materials are not installed according to
the instructions (e.g. they are not leakproof, not clamped in place etc.),
this may cause hazardous situations and/or result in bodily injury. After
assembly, check at least all flue gas and air–carrying parts for tightness.
114494-03
21
8. Control and electrical connections
8. Control and electrical connections
8.1 General
The boiler is equipped with electronic control and safety equipment with ionisation flame protection. The advanced boiler control
(abc®), is a microprocessor that protects and controls the boiler.
The boiler is fully prewired; all external connections are made
on the terminal strips. Connect the boiler to the mains supply in
accordance with the local electricity supplier's instructions and IEE
regulations.
8.1.1 Boiler control
The heat output of the Remeha Gas 210 ECO PRO can be controlled as follows:
- Modulating, where the output modulates between the minimum
and maximum values on the basis of the flow temperature
defined by the modulating controller.
- On/off control, where the heat output modulates between
the minimum and maximum values on the basis of the flow
temperature set in the unit. This can be combined with an
outside sensor so that the internal heating curve is used.
- Analogue control (0-10 V), where the heat output or
temperature is controlled by a 0-10 V signal, see Section 8.4.4.
Only possible with optional 0 - 10 V control PCB (IF-01).
GAS 210 ECO PRO
8.1.2 Modulating controls general
The modulating nature of the boiler is used to maximum effect with
a modulating controller based on room and/or outside temperatures. If the controller demands heat, the boiler supplies the heat
output. If the controller demands a flow temperature, the boiler
modulates to this value. This increases the number of operating
hours and drastically reduces the number of starts. Combined with
the fixed gas/air mixture, this results in greater efficiency.
Various types of modulating controls can be connected, including
the following:
- Modulating room control, see Section 8.1.3;
- Modulating weather-compensated control see Section 8.1.4;
- Modulating cascade control, see Section 8.1.5.
8.1.3 Modulating room control
The boiler is set up for communication via the OpenTherm protocol. Modulating controllers can be connected according to the
OpenTherm protocol, e.g. the Remeha iSense. The controller is
mounted in a reference area. Connection is made with a two-core
cable to the On/off - OT terminals of terminal strip X6 (not polarity
sensitive).
8.1.4 Modulating weather-compensated control
rematic
®
22
The following optional controller can be supplied by Broag-Remeha. The controller is supplied with a connection adapter and interface that are built into the boiler. The connections for this feature
are fully pre-wired.
114494-03
Loading...
+ 50 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.