Olldcastlebe Signature Series Unit Wall User Manual

BuildingEnvelope
SIGNATURE SERIES UNIT WALL
INSTALLATION MANUAL
JULY 2013
Note: Installation Manual is product specific:
FOR REFERENCE ONLY
 
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
July 2013 00-Assembly-Detail 1-866-Oldcastle (653-2278) www.oldcastlebe.com
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
TABLE OF CONTENTS
SHEET
GENERAL INFORMATION Product Use Protection and Storage Check Material Field Conditions Cleaning Materials Expansion Joints
LAYOUT MULLION AND ANCHOR CENTERLINES
Check Structural Opening Layout Mullion and Anchor Centerlines
3 3 3 4 4 4
5 5
LOCATE AND INSTALL ANCHORS
INSTALL ANCHOR HOOKS
HOISTING FRAMES
STARTER SILL CONDITION
Install Starter Sill Check and Properly Locate PVC Spacers Proper Seal at Starter Sill Install Horizontal Air Seal Gasket
INSTALL GROUND FLOOR FRAMES
Install the First Frame Install Adjacent Frames at Ground Floor
INSTALL UPPER LEVEL FRAMES
Seal the Joint Install Horizontal Air Seal Gasket Seal Hoisting Holes for Windload Anchor Lug Option Install First Frame at Upper Level Install Adjacent Frames at Upper Level
6
7
8-9
10 10 10-11 12
13-14 15-16
17 17 18 19
20-21
JAMB FRAME CONDITION
July 2013 00-Table-of-Contents 1-866-Oldcastle (653-2278) www.oldcastlebe.com
22
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
GENERAL INFORMATION
PRODUCT USE
The unitized curtain wall system is intended for installation by glazing professionals with appropriate
experience. Subcontractors must be qualified to provide field instruction and project management.
Oldcastle BuildingEnvelope does not control the application of its product configurations, sealant or
®
glazing material and assumes no responsibility for the application. It is the responsibility of the owner, architect and installer to make these selections in strict compliance with applicable laws and building codes.
Consult silicone sealant manufacturer for review and recommendation of sealant application. Follow sealant manufacturer's recommendations and literature for proper cleaning, testing and application of silicone sealant.
The air and water performance of the unitized curtain wall is directly related to the completeness and integrity of the installation process. To ensure top performance for this system, particular attention should be given to the following procedures:
1. Surface to be sealed should be cleaned with isopropyl alcohol or solvent and dried as recommended by sealant manufacturer to remove dirt and cutting oils.
2. Vertical movement of mullion at intermediate floors requires special expansion joints and glazing materials. The system permit maximum +/-3/4" movement. For designs and applications that may require greater movement or special considerations, please contact your local Oldcastle BuildingEnvelope facility.
®
Variations on the details shown may occur, but are not the responsibility of Oldcastle BuildingEnvelope.
®
PROTECTION AND STORAGE
Handle all material carefully. Do not drop from the truck, stack with adequate separation so the material will not rub together. Store material off the ground, protecting against the elements and other construction hazards by using a well ventilated covering. Remove material from package if wet or located in a damp area. For further guidelines consult AAMA publication "Care And Handling of
Architectural Aluminum From Shop To Site".
CHECK MATERIAL
Check all material upon arrival at job site for quality and to determine any shipping damage. Using the contract documents, completely check the surrounding conditions that will receive your materials. Notify the general contractor by letter of any discrepancies before proceeding with the work. Failure to do so constitutes acceptance of work by other trades.

July 2013 03-General-Info 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
Check shop drawings, installation instructions, architectural drawings and shipping lists to become familiar with the project. The shop drawings take precedence and include specific details for the project. The assembly and installation instructions are of a general nature and cover the most common conditions.
Due to varying job conditions all sealant must be approved by the sealant manufacturer to ensure it will perform per conditions shown on the instructions and shop drawings. The sealant must be compatible with all surfaces in which adhesion is required, including other sealant surfaces. Use primers where directed by sealant manufacturer. Properly store sealant at the recommended temperatures and check sealant for expiry and shelf life before using.
FIELD CONDITIONS
All material to be installed must be plumb, level and true. Aluminum to be placed in direct contact with masonry or incompatible material should be isolated with a heavy coat of zinc chromate, bituminous paint or non-metallic material unless otherwise specified. After sealant is set and a representative amount of the wall has been glazed (250 sq. ft. or more), perform a water hose test in accordance with AAMA 501.2 "Field Check of Metal Storefront, Curtain Walls and Slope Glazing Systems for Water Leakage". On large projects the hose test must be repeated during the glazing operation. Review anchors or embeds in structure as early as possible to confirm that 'as built' building structure can accommodate anticipated anchor tolerances.
CLEANING MATERIALS
Cement, plaster terrazzo, alkaline and acid based materials used to clean masonry are very harmful to finishes. Any residue should be removed with water and mild soap immediately or permanent staining will occur. A spot test is recommended before any cleaning agent is used. Refer to the architectural finish guide in the detail catalogue.
EXPANSION JOINTS
Expansion joints and perimeter joints shown in these instructions and in the shop drawings are shown at nominal size. Actual dimensions may vary due to perimeter conditions and/or differences in metal temperature between the time of fabrication and the time of assembly/installation. For example, a 12 foot unrestrained length of aluminum can expand or contract 3/32" over a temperature change of 50 degrees F. Any movement potential should be accounted for at the time of the assembly and installation.

July 2013 04-General-Info 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
LAYOUT MULLION AND ANCHOR CENTERLINES
GENERAL NOTE: FRAMES ARE INTENDED TO BE INSTALLED FROM LEFT TO RIGHT WHEN VIEWED FROM
EXTERIOR. DETAILING IN THIS INSTALLATION MANUAL MAY VARY FOR SPECIFIC PROJECTS.
1. CHECK STRUCTURAL OPENING Slab or beam elevation must be within adjustment of anchoring system. Structural surfaces to receive anchoring system must be level and plumb within the adjustment limits
at head, sill and jamb. See approved shop drawings for allowable adjustment.
2. LAYOUT MULLION AND ANCHOR CENTERLINES
Centerline of mullion ±1/32"
1 1/2" 1 1/2" 1 1/2" 1 1/2"
Face of slab/beam
Typical captured mullion
2.50" ±1" building
Centerline of mullion
tolerances
±1/32"
Typical SSG mullion

July 2013 05-Mull-Anchor-Layout 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
LOCATE AND INSTALL ANCHORS
1. LOCATE AND INSTALL ANCHORS See approved shop drawings for anchor types and locations. Locate centerline of aluminum anchor at the mark for centerline of mullion.
Adjust alum anchor bracket for in and out. Apply aluminum serrated washers. Make final in and out adjustment prior to tightening the anchor bolt in place.
Face of slab/beam
Back of mullion
Location of this point
is CRITICAL! Field survey
may be required
Back of mullion
3 1/2" slot
for in/out adjustments
Mullion/anchor centerline
Reference shop drawings for actual anchor configuration and/or project specific information.
Anchor bolt (ref. shop drawings for specific fastener info/torque requirements)
Alum serrated washer
Alum anchor bracket
2 1/2"
±1" building tolerances

July 2013 06-Locate-Install-Anchors 1-866-Oldcastle (653-2278) www.oldcastlebe.com

Face of slab/beam
Reference field conditions. Isolator required to prevent galvanic reaction.
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL ANCHOR HOOKS
1. INSTALL ANCHOR HOOKS Back off FS-341 stopping screw at the bottom of the anchor bracket, slide in the anchor hook.
Tighten up FS-341, the screw is to prevent anchor hook from sliding out of the anchor bracket during frame installation.
Slide the anchor hook into anchor bracket
Tighten up FS-341 stopping screw after anchor hook installation

July 2013 07-Install-Anchor-Hooks 1-866-Oldcastle (653-2278) www.oldcastlebe.com

r
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
HOISTING FRAMES
SAFETY PROCEDURES ARE THE SOLE RESPONSIBILITY OF THE INSTALLER. OLDCASTLE
BUILDINGENVELOPE ASSUMES NO RESPONSIBILITY FOR PROJECT SAFETY
®
PROCEDURES.
1. HOISTING FRAMES Frames can be hoisted either through anchor lugs (shear angle) installed in frame head horizontals o
through sleeves attached to the mullion halves.
Inspect frames prior to hoisting. For illustration purposes only, a spreader bar is shown as a hoisting
device. Other lifting devices can be used. Means & methods are the sole responsibility of the installler. The spreader bar chains should be spaced the same distance as the distance between hoisting holes in head horizontal or hoisting holes on sleeves. Maximum frame weight to be less than 1500 pounds.
Handle frame to hoist smoothly and in a controlled manner, no swinging or spinning allowed during hoisting. Avoid shock loads.
Spreader bar should indicate hoisting configuration depending on frame weight. Ensure hoisting bar is rated for frame weight configuration as required.
Adjust the spreader bar to have chains spaced the same distance as the hoisting holes
Sleeve
HOIST THROUGH SLEEVES

July 2013 08-Hoisting-Frames 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
HOISTING FRAMES
See notes on previous page
Windload anchor lug
HOIST THROUGH
WINDLOAD ANCHOR LUGS

July 2013 09-Hoisting-Frames 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
STARTER SILL CONDITION
1. INSTALL STARTER SILL Locate starter sill per approved shop drawings. The starter sill must be level and straight. The starter
sill should run continuously across elevation, whenever the splicing is necessary, a min. 3/16" gap should be left for proper seal in-between starter sills.
Install windload anchor lug at each mullion location, crimp the windload anchor lug in place on starter
sill. Install starter sill fasteners. Ensure fastener heads will not interfere with frame sill horizontals.
Seal over all fastener heads and tool sealant.
Requires a min. 3/16" gap at splice joint for proper seal
Ensure starter sill fixing bolt will not interfere with frame sill horizontals
The windload anchor lug should be crimped in place at every mullion location
2. CHECK AND PROPERLY LOCATE PVC SPACERS
The 4" long V927 rigid PVC spacers should be pre-assembled on each starter sill. Three pieces of PVC spacers are required per module. One should be located at center of the module, two other pieces should be located at each mullion location.
3. PROPER SEAL AT STARTER SILL
Clean and prepare substrates for sealing per sealant manufacturer's recommendations. Apply backer rod and perimeter seals under starter sill. Tool sealant. Apply sealant at splice joints. All splice joints
should be sealed from the drainage hole on the starter sill to the top of the upturned leg. Connect
sealant at underside of starter sill with sealant at splice joint. See illustration on p.11.
Apply sealant at outer surface for approximately 1" on each side of the joint as shown; set 1-1/2" wide by 3" long silicone sheet on top of the silicone sealant.

July 2013 10-Install-Starter-Sill 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
STARTER SILL CONDITION
Seal from the drain hole to the top of the upturned leg
Marry the sealant at underside of starter sill with sealant at splice joint
Set the 1-1/2" wide silicone sheet in silicone sealant at starter sill joint location
Apply sealant at each end of starter sills for receiving 1-1/2" wide silicone sheet tool sealant

July 2013 11-Seal-Starter-Sill 1-866-Oldcastle (653-2278) www.oldcastlebe.com

4. INSTALL HORIZONTAL AIR SEAL GASKET Clean areas to receive sealant as per sealant manufacturer's recommendations. Install horizontal air
seal gasket GP-50041 into starter sills continuously across elevation. Where splicing is necessary, locate the joint at mid-point of the module, apply bead of sealant to set the ends of gasket in place. Tool squeeze out sealant.
Note silicone must adhere to EPDM gasket e.g. Dow 756 silicone sealant. Ensure fingers of horizontal air seal gaskets are not filled with silicone as this will hamper frame installation.
Tool excess sealant out of fingers
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
STARTER SILL CONDITION
Locate the joint of horizontal air seal gasket at mid-point of the module
V-927 PVC spacers (3) pieces per module
Set the ends of gasket in silicone
Set the ends of EPDM gasket in silicone; tool squeeze out or add additional sealant on outer surface

July 2013 12-Horiz-Air-Seal-Gasket 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL GROUND FLOOR FRAMES
1. INSTALL THE FIRST FRAME Frames are installed from left to right and from bottom to top. Before proceeding to installing first frame, check all starter sill joints to make sure they are properly
sealed and horizontal air seal gaskets have been applied. Apply 3" to 6" long silicone sealant towards exterior portion of the horizontal air seal gasket on top of
starter sill at each end, flatten the sealant at top. Do not allow sealant to skin before installing frame.
Tool sealant flat on top
Apply 3" to 6" long of sealant on top of starter sill towards the exterior portion of horizontal air seal gasket
Seal over all fastener heads and tool sealant

July 2013 13-Install-First-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
r
INSTALL GROUND FLOOR FRAMES
Install the first frame by lifting the frame over starter sill and lower the frame down and rest the ancho hook on pre-set alum anchor at slab/beam.
Use the adjustment bolt on anchor bracket to adjust the elevation of the frame. Adjust the elevation of the frame to make sure the frame is level, plumb and at the correct height. After adjustment, freeze the anchor hook for lateral movement by installing FS-339 #10 by 1/2" hex head screw. Use metal shims if necessary to maintain the nominal distance between bottom of the mullion and top of the starter sill. Remove shims after adjustment for slip anchor condition at ground floor.
Use the adjustment bolt to adjust the elevation of the frame
Install FS-339 to laterally freeze anchor hook in place

July 2013 14-Install-First-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL GROUND FLOOR FRAMES
2. INSTALL ADJACENT FRAMES AT GROUND FLOOR Just prior to installing the next frame, apply sealant at the bottom of the first frame up vertical air seal
gasket GP-50001 for approximately 4" long above horizontal air seal gasket. Connect the vertical seal with the horizontal seal which was previously applied on top of the starter sill. Do not allow sealant to skin before installing next frame.
Apply 4" long sealant at the bottom of the mullion along vertical air seal gasket
Connect vertical seal with horizontal seal
-
"
3
4"
"
6
Install the next frame by lifting the frame up to clear the starter sill. Move the next frame to the left to engage the outer mullion hooks; then rotate the next frame towards building to snap inner hooks; once snapped, slide the next frame down to engage horizontal air seal at stack joint.
Again use the adjustment bolt to level the frame. Check and ensure vertical air seal gasket GP-50001 has not slid down in the gasket raceway in mullion.
Repeat in the same method for installing the rest of the frames at ground floor.

July 2013 15-Install-Adjacent-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL GROUND FLOOR FRAMES
1. Lift the next frame up to clear the starter sill
2. Move to the left to engage the outer hook
3. Rotate the frame towards the building
4. Engage the inner hook
5. Slide the next frame down to engage horizontal air seal

July 2013 16-Install-Adjacent-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL UPPER LEVEL FRAMES
1. SEAL THE JOINTS Clean and prepare the surfaces of the head horizontal at mullion joints per sealant manufacturer's
commendations. Apply sealant completely along the entire joint between head horizontals; also apply sealant at front face for approximately 1" on each side of the joint as shown; set 1-1/2" wide by 2-5/8" long silicone sheet on top of the silicone sealant.
Completely seal the joint between head horizontals
Neatly seal the joints between trims
2. INSTALL HORIZONTAL AIR SEAL GASKET Install horizontal air seal gasket GP-50041 into head horizontals continuously across elevation. Apply
sealant for approximately 3" long on each side of the splice joint, push gasket into raceway, tool squeeze out sealant. Where splicing is necessary, locate the joint at mid-point of the module and apply bead of sealant to set the ends of gasket in place. Push in the next piece of gasket, tool squeeze out sealant and remove excess sealant from outer face.
Apply sealant at outer face for approximately 1" on each side of the joint
Set the 1-1/2" wide silicone sheet in silicone sealant at mullion joint location; tool squeeze out
Apply sealant on each side of splice joint at gasket raceway
Locate the joint of horizontal air seal gasket at mid-point of the module

July 2013 17-Install-Upper-Level-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

Set the ends of the gasket in silicone in place; push in the next piece; tool squeeze out sealant
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL UPPER LEVEL FRAMES
3. SEAL THE HOISTING HOLES FOR WINDLOAD ANCHOR LUG OPTION For frames with windload anchor lug (shear angle) option, clean and prepare the surfaces of the head
horizontal at mullion joints; apply sealant completely along the entire joint between head horizontals; also apply sealant at and around hoisting hole, set 2" by 2" alum plate at hoisting hole location.
Similar to frames with sleeve option, apply sealant to outer face for approximately 1" on each side of the joint as shown; set 1-1/2" wide by 2-5/8" long silicone sheet on top of the silicone sealant.
Then install horizontal air seal gasket GP-50041 into head horizontals continuously across elevation. Where splicing is necessary, to locate the joint at mid-point of the module and apply bead of sealant and set the ends of gasket in place. Tool squeeze out sealant.
Apply sealant at and around hoisting holes for receiving the alum plates
Set alum plates at hoisting hole locations
Set the 1-1/2" wide silicone sheet in silicone sealant at mullion joint location
Completely seal the joint between head horizontals
Apply sealant at front face for approximately 1" on each side of the joint
For smoke seal condition, seal the inboards of splice joint and down along back of mullion until anchor locaiton

July 2013 18-Install-Upper-Level-Frame 1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL UPPER LEVEL FRAMES
4. INSTALL FIRST FRAME AT UPPER LEVEL Before proceeding to upper level, check all horizontal joints at lower level to make sure they are
properly sealed and horizontal air seal gaskets have been applied. Apply a 3" to 6" long bead of silicone sealant towards exterior portion of the horizontal air seal gasket
on top of head horizontal at each end at the frame below, flatten the sealant at top; Install the first frame at upper level by lifting the frame over head horizontal and lower the frame down.
Use the adjustment bolt on anchor bracket to adjust the elevation of the frame. Use shims if necessary to maintain the nominal distance between bottom of the mullion and top of the head horizontal. Remove shims after adjustment.
3" to 6" long
Flatten sealant at top before lowering the frame
Apply 3" to 6" long of sealant on top of head horizontal towards the exterior portion of horizontal air seal gasket
July 2013 19-Install-First-Frm-Upper-Level 1-866-Oldcastle (653-2278) www.oldcastlebe.com
3" to 6" long
For smoke seal condition, seal along the back of the mullion at splice joint down to anchor
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL UPPER LEVEL FRAMES
5. INSTALL ADJACENT FRAMES AT UPPER LEVEL Just prior to installing the next frame, apply sealant at the bottom of the first frame up vertical air seal
gasket GP-50001 for approximately 4" long above horizontal air seal gasket. Connect the vertical seal
with the horizontal seal which was previously applied on top of the head horizontal.
Smoke seal
Connect vertical seal with horizontal seal
Apply 4" long sealant at the bottom of the mullion along vertical air seal gasket
4"
"
6
-
"
3
Smoke seal
Install the next frame by lifting the frame 4" to 6" above previous frame to clear the sleeves and head horizontals. Move the next frame to the left to engage the outer mullion hooks; then rotate the next frame towards building to snap inner hooks; once snapped, slide the next frame down to engage horizontal air seal at stack joint.
Again use adjustment bolt on anchor bracket to adjust the elevation of the frame, then freeze the
lateral movement by installing FS-339 screw on anchor hook. Repeat in the same method for installing the rest of the frames.
July 2013 20-Install-Adjacent-Frm-Upper-Level 1-866-Oldcastle (653-2278) www.oldcastlebe.com
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
INSTALL UPPER FLOOR FRAMES
1. Lift the next frame up to clear the sleeve
2. Move to the left to engage the outer hook
3. Rotate the frame towards the building
4. Engage the inner hook
5. Slide the next frame down to engage horizontal air seal
July 2013 21-Install-Adjacent-Frm-Upper-Level 1-866-Oldcastle (653-2278) www.oldcastlebe.com
SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL
JAMB FRAME CONDITION
1. SEAL AT THE NOTCH ON JAMB MULLION For jamb frames at expansion joints or starter sills, apply sealant at the notch on mullion above and
below the expansion joint. Set 4" wide by 6" long silicone sheet in place.
Set the 4" wide silicone
sheet in silicone sealant at the notch on jamb mullion tool sealant
Interior
Make sure to set the end of the air seal gasket in silicone
Interior
Make sure to set the end of the air seal gasket in silicone

July 2013 22-Jamb-Frame-Condition 1-866-Oldcastle (653-2278) www.oldcastlebe.com

Set the 4" wide silicone sheet in sealant at the notch on jamb; marry the sealant to sealant at underside of starter sill
Loading...