Metro SAQHD25BP-1 Installation Manual

®
SEISMIC FLOOR PLATES
SASES25BP-1 SASES50BP-1
INSTALLATION
INSTRUCTIONS
SASES25BP-2 SASES50BP-2
SASES25BP-4 SASES50BP-4
SAQHD25BP-1 SAQHD50BP-1
SAQHD25BP-2 SAQHD50BP-2
Wire Shelving Systems
Super Adjustable 2™ Super Erecta Shelving
Original Super
®
Erecta® Shelving
Super Erecta qwikSLOT Shelving
®
SAQHD25BP-4 SAQHD50BP-4
®
MetroMaxQ® Shelving HD Super™ Shelving
InterMetro Industries Corporation
North Washington Street, Wilkes-Barre, PA 18705
For Product Information Call: 1-800-433-2232 Visit Our Web Site: www.metro.com
L01-418
without notice. Please confirm at time of order.
9/05
®
SEISMIC FLOOR PLATES
LIST OF COMPONENTS:
(Floor Anchors not included)
INSTALLATION INSTRUCTIONS
For Seismic Floor Plates
Part Number: Consists of:
SASES25BP-1 (4) floor plates (1) hardware bag (1) label bag SASES50BP-1 (4) floor plates (1) hardware bag (1) label bag SASES25BP-2 (2) floor plates (1) hardware bag (1) label bag SASES50BP-2 (2) floor plates (1) hardware bag (1) label bag SASES25BP-4 (1) floor plate (1) hardware bag (1) label bag SASES50BP-4 (1) floor plate (1) hardware bag (1) label bag SAQHD25BP-1 (4) floor plates (1) hardware bag (1) label bag SAQHD50BP-1 (4) floor plates (1) hardware bag (1) label bag SAQHD25BP-2 (2) floor plates (1) hardware bag (1) label bag SAQHD50BP-2 (2) floor plates (1) hardware bag (1) label bag SAQHD25BP-4 (1) floor plate (1) hardware bag (1) label bag SAQHD50BP-4 (1) floor plate (1) hardware bag (1) label bag
FLOOR PLATE ASSEMBLY TO SHELVING POST CONNECTION
The floor plate anchor assembly is designed to allow in-field leveling of the shelving and secure anchorage of the shelving to the floor plates. This is accomplished with standard shelves
and posts with leveling bolts.
1. Place the assembled shelving unit in its intended location.
2. Mark on the floor the location of the shelving posts, or place the floor plates under the posts. Move the shelving unit out of the way.
3. Utilizing a template, or the actual floor plate, mark the location of the floor anchors, drill appropriate holes, and install the floor plates.
4. Move the shelving unit adjacent to the floor plates and level the unit. Lift the shelving unit and place the posts into the pipe sleeves in the floor plate assembly.
5. Once the shelving unit is in place and level, horizontal holes in each pipe sleeve are used to align a 13/32" drill bit and a horizontal hole (or two, as determined from the Seismic Specifying Guide (L04-160)) is drilled through the post. Alternatively, the pipe sleeve holes can be used to mark the post hole locations, the shelving unit removed and the holes in the post drilled.
6. Install a 3/8" diameter clevis pin (or two) from the supplied hardware bag through the floor plate pipe sleeve and post, install a hitch pin clip.
7. Finally, affix the proper label designating the unit as either 30 psf or 50 psf per shelf. The load rating is determined by the tables in the Seismic Specifying Guide and may be shown on the installation drawing provided with the quote package in the planning stage of this project.
Notes: The lowest shelf should be as close as possible to the floor plate, no higher than 12" from floor.
If cleaning is an issue, it is recommended a donut bumper be specified to cover any spaces between the post and the floor plate anchor pipe. These may have been specified in the quoting process and provided — if not, order the donut bumper to match the post type.
Metro does not provide the concrete floor anchors. The correct floor anchors must be used for the specific installation conditions and meet all applicable codes.