McQuay RAH 407C Installation Manual

Installation and Maintenance Manual IM 487-5
RoofPak™ Applied Rooftop Systems Air Handler
RAH 407C - 077C, 12000 to 50000 cfm
RDS 800C - 802C, 4000 to 20000 cfm
Part Number: IM 487
Date: June 2006
US
© 2006 McQuay International
Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Gas Burner Nameplate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Hazard Identification Information . . . . . . . . . . . . . . . . . . . . . . . 3
Typical Component Locations . . . . . . . . . . . . . . . . . . . . . . . . . 4
Control Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Control Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Controls, Settings, and Functions . . . . . . . . . . . . . . . . . . . . . 12
Mechanical Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Unit Clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Ventilation Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Overhead Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
IBC Seismic Compliant Units . . . . . . . . . . . . . . . . . . . . . . . . 20
Roof Curb Arrangement . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Post and Rail Arrangement . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Post and Rail Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Rigging and Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Split Units . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Unit Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Steam Coil Piping (All Units) . . . . . . . . . . . . . . . . . . . . . . . . . 33
Steam Piping Recommendations . . . . . . . . . . . . . . . . . . . . . 33
Steam Trap Recommendations . . . . . . . . . . . . . . . . . . . . . . . 34
Vestibule Assembly Instructions . . . . . . . . . . . . . . . . . . . . . . 38
Damper Assemblies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
Cabinet Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . 45
Installing Ductwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Installing Duct Static Pressure Sensor Taps . . . . . . . . . . . . . 46
Installing Building Static Pressure Sensor Taps . . . . . . . . . . 47
Electrical Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Field Power Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Field Control Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Preparing Unit for Operation . . . . . . . . . . . . . . . . . . . . . 52
Spring Isolated Fans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
Relief Damper Tie-Down . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
Adjusting Scroll Dampers . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
Adjusting Supply Fan Thrust Restraints . . . . . . . . . . . . . . . . 53
Adjusting Seismic Restraints . . . . . . . . . . . . . . . . . . . . . . . . . 54
Sequences of Operation . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Power-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Fan Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Economizer Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Heating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Wiring Diagrams . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
Unit Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
Enthalpy Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
External Time Clock . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Smoke and Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Smoke Detectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Freeze Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Entering Fan Temperature Sensor . . . . . . . . . . . . . . . . . . . . 87
Duct High Pressure Limit . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
MicroTech II™ Remote User Interface (UI) . . . . . . . . . . . . . . 87
Variable Frequency Drive Operation . . . . . . . . . . . . . . . . . . . 89
Convenience Receptacle/Section Lights . . . . . . . . . . . . . . . . 89
DesignFlow™ Outdoor Air Damper Option . . . . . . . . . . . . . . 89
Propeller Exhaust Fan Option . . . . . . . . . . . . . . . . . . . . . . . . 92
Exhaust Fan On/Off Control . . . . . . . . . . . . . . . . . . . . . . . . . . 94
Ultraviolet Lights Option . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
Ultraviolet Light Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
Check, Test, and Start Procedures . . . . . . . . . . . . . . . 97
Servicing Control Panel Components . . . . . . . . . . . . . . . . . . 97
Before Start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
Power Up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
Fan Start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
Economizer Start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
Heating System Start-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
Air Balancing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
Sheave Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
Drive Belt Adjustment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
Mounting and Adjusting Motor Sheaves . . . . . . . . . . . . . . . 101
Final Control Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . 104
Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
Servicing Control Panel Components . . . . . . . . . . . . . . . . . 108
Planned Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
Unit Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
Gas Furnace . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
Bearing Lubrication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
Setscrews . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Supply Fan Wheel-to-Funnel Alignment . . . . . . . . . . . . . . . 112
Winterizing Water Coils . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
Control Panel Components . . . . . . . . . . . . . . . . . . . . . . . . . 113
Replacement Parts List . . . . . . . . . . . . . . . . . . . . . . . . . . 117
Service and Warranty Procedure . . . . . . . . . . . . . . . . 119
Limited Product Warranty (North America) . . . . . . 120
Exceptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
Assistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
Sole Remedy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
Rooftop Equipment Warranty Regist. Form . . . . . 121

Introduction

Introduction
This manual provides general information about the “C” vintage McQuay RoofPak applied rooftop unit, models RDS and RAH. In addition to an overall description of the unit, it includes mechanical and electrical installation procedures, commissioning procedures, sequence of operation information, and maintenance instructions. For further information on the optional forced draft gas-fired furnace, refer to Bulletin No. IM 684 or IM 685.
The MicroTech II applied rooftop unit controller is available on “C” vintage applied rooftop units. For a detailed description of the MicroTech II components, input/output configurations, field wiring options, requirements, and service procedures, see IM 696-3. For operation and information on using and programming the MicroTech II unit controller, refer to the appropriate operation manual (see Table 1).
For a description of operation and information on using the keypad to view data and set parameters, refer to the appropriate program-specific operation manual (see Table 1).
Table 1: Program specific rooftop unit operation literature
Rooftop unit control configuration
VFDs Vendor IM manuals
Discharge Air Control (VAV or CAV) OM 137-2
Space Comfort Control
(CAV-Zone temperature control)
Operation manual bulletin
number
OM 138-2

Gas Burner Nameplate

On units that include gas heat, the nameplate is located on the lower right corner of the main control box door. It includes the burner model number, minimum/maximum input, maximum temperature rise, and minimum cfm.

Hazard Identification Information

WARNING
Warnings indicate potentially hazardous situations, which can result in property damage, severe personal injury, or death if not avoided.
CAUTION
Cautions indicate potentially hazardous situations, which can result in personal injury or equipment damage if not avoided.
Figure 1: Nomenclature
RoofPak
Unit Size RDS 800 = 4000 – 16000 CFM RDS 802 = 8000 – 20000 CFM RAH 47 = 12000 – 30000 CFM RAH 77 = 23000 – 50000 CFM
R AH — 047 C S E
Heat medium A = Natural gas E = Electric F = Fuel oil S = Steam W = Hot water Y = None
Cooling coil size S = Standard (low airflow) L = Large (high airflow) Y = None or contractor coil
Design vintage
McQuay IM 487-5 3
Introduction

Typical Component Locations

Figure 2 shows a typical blow-through unit with the locations of the major components. Figure 2 shows a typical draw-through unit with the locations of the major components.
These figures are for general information only. See the project’s certified submittals for actual specific dimensions and locations.
Figure 2: Control locations
Supply fan
discharge
plenum
section
C9
Economizer
return air
Heat
section
DX
section
Filter
section

Control Locations

All controls are optional. If controls are ordered, Figure 2 shows the locations of the various control components mounted throughout the units. See “Control Panel” on page 5 for the locations of control components mounted in control panels. Additional information is included in Table 2 on page 12 and the wiring diagram legend, which is included in “Wiring Diagrams” on page 58. Figure 2 shows the blow-through heat and the blow-through coil sections.
C19, 20
(optional)
RAT
LT11 (optional)
S11, REC11
SD2
(optional)
(optional)
RAE
(optional)
ACT3
ACT6
PC5
OAE
OAT
VM1
(optional)
FS1
(optional)
DAT
LT10 (optional)
S10, REC10 (optional)
SD1 (optional)
SV1, 2
SV5, 6 (optional)
4 McQuay IM 487-5

Control Panel

Introduction
The unit control panels and their locations are shown in the following figures. These figures show a typical unit
Figure 3: Control panel locations
configuration. Specific unit configurations may differ slightly from these figures depending on the particular unit options.
McQuay IM 487-5 5
Introduction
Figure 4: Typical main control panel, 800C to 802C, 460 volt
Keypad display
Remote
keypad
HS1 S1
Serial conn
See separate
detail, page 14.
GCB1
ERB1
S7S4
Resistor
R58
R20 R26 R27 R28
R48
R46
MMP60 MMP10 MMP20
M60
R30
M10
R24 R25 R28
R60
R45
R69
M20
F3
F1A
F1B
MCB
F1C
TB1
Power supply
T1
DHL
SPS2
EHB1
SPS1
VFD remote
display
DS1
REC1
TB3,
first seven
blocks
TB2,
remaining
blocks
TB7
GND LUG DS1
SPS1,2 fittings
for static
pressure tubing
6 McQuay IM 487-5
Figure 5: Typical main control panel, 047C, 460 volt
Introduction
VFD remote
display
TB2
F1A
F1B
F1C
14.
GFR1
TB7
SPS1,2
fittings for
static pressure
tubing
McQuay IM 487-5 7
Introduction
Figure 6: Typical main control panel, 077C, 460 volt
14.
8 McQuay IM 487-5
Introduction
e
A
Figure 7: Typical gas heat panel, 1000 MBH
IT
R22
TD10
R20
S
R23 R21
LS2
Figure 9: VFD bypass panel, 40 HP, 460 volt)
LS1
S3
Figure 10: Electric heat panel, sizes 800, 802C
FSG
FSG Tim
FB33 FB32 FB31
Figure 8: Typical propeller exhaust panel, 3 fans, 460 volt
M33 M32 M31
FB43 FB42 FB41
M41 M42 M41
SR2
SR3
SR1
TB11
PB3
McQuay IM 487-5 9
Introduction
Figure 11: Electric heat panel, size 047C Figure 12: Electric heat panel, size 077C
FB31FB32FB33
DS3
M42
GLG3
FB31FB32FB33 M31M32M33
FB41FB42FB43
M41M43
H53
TB11
M31M32M33
FB34FB44
M34M44
FB41FB42FB43
M41M42M43
GLG3
H53
TB11
DS3
10 McQuay IM 487-5
Figure 13: Harness plug connector detail
RATS OATSDATS
FP1 OPEN1EPTS
AFD10 AFD20
SV12 SV56
ACT3 OPEN2
OAE PC7PC5
Introduction
HL22 OPEN3
GSHT1 GSHT2
SD1 SD2
DFRH DFLH OPEN4
LT11LT1 0
LT OP1 LT OP2
McQuay IM 487-5 11
Introduction

Controls, Settings, and Functions

Table 2 below lists all of the unit control devices and associated information.
Table 2: Controls, settings, and functions
Symb
ol
DAT
DHL
EFT
FP1, 2
FS1
MCB
OAE
OAT
PC5
PC6
PC7
RAE
RAT
SD1
SD2
SPS1
Description Function
Discharge air temperature sensor
Duct high limit switch
Entering fan air temperature sensor
Evaporator frost protection
Freezestat
Main control board Processes input information
Enthalpy control (electro­mechanical)
Enthalpy control (electronic)
Outside air temperature sensor
Dirty filter switch Senses filter pressure drop
Dirty filter switch Senses filter pressure drop
Airflow proving switch
Return air enthalpy sensor
Return air temperature sensor
Smoke detector, supply air
Smoke detector, return air
Static pressure sensor duct #1
Senses discharge air temperature
Prevents excessive VAV duct pressures; shuts off fan
Senses entering fan air temperature
Senses low refrigerant temperature
Shuts off fans, opens heating valve, and closes outdoor damper if low air temperature at coil is detected
Returns outside air dampers to minimum position when enthalpy is too high
Returns outside air dampers to minimum position when outside air enthalpy is higher than return air empalthy (use RAE)
Senses outside air temperature
Senses supply fan pressure to prove airflow
Used to compare return air enthalpy to outside air enthalpy (used with OAE)
Senses return air temperature
Initiates unit shutdown if smoke is detected
Initiates unit shutdown if smoke is detected
Converts static pressure signals to voltage signals
Rese
N/A
Auto
N/A
N/A
Auto
N/A
Auto
Auto
N/A N/A N/A
Auto
Auto
Auto
N/A
N/A
ManualDischarge air
ManualReturn air
N/A
Location Setting Range Differential Part no.
t
Discharge air
section
Main control
panel
Inlet of supply
fan
Return bends of evaporative
coil
Heating section
Main control
box
Economizer
section
Economizer
section
First filter
section
Final filter
section
Supply fan
section
Economizer
section
Return air
section
section
section
Main control
box
N/A N/A
3.5" w.c
(871.8 Pa)
N/A N/A
Opens at
30°F
Closes at
45°F
38°F (3°C)
or as
required
N/A N/A N/A
“B” or as required
Fully CW
past “D”
(when used
with RAE)
As required
As required
.10" wc (25
Pa)
N/A N/A N/A
N/A N/A
N/A N/A N/A 04925001
N/A N/A N/A 04925001
N/A
0.05–5.0" wc (12.5–1245.4
Pa)
N/A N/A
35°F–45°F
(2°C–7°C)
A–D
A–D N/A
.05-5" wc
(12.5–1245.4
Pa)
.05-5" wc
(12.5–1245.4
Pa)
.03-1.40" wc
(7.5–348 Pa)
0–5" wc (0–1245.4 Pa) 1–6 V (dc) out
.05" wc
(12.5 Pa),
fixed
12°F (7°C),
fixed
Temperature:
3.5°F (2°C) Humidity:
5% fixed
.05" wc
(12.5 Pa)
.05" wc
(12.5 Pa)
.03" wc
(7.5 Pa),
fixed
N/A
06000470
5
06549380
1
06000470
5
07250190
1
06583000
1
06000610
1
03070670
2
04926220
1
06000470
5
06549380
1
06549380
1
06001580
1
04926220
2
06000470
5
04954500
7
12 McQuay IM 487-5
Table 2: Controls, settings, and functions (continued)
Symb
ol
SPS2
S1
S7
Description Function
Converts static pressure Static pressure sensor duct #2
Static pressure sensor: building (space) pressure
System switch
ON-OFF-AUTO switch
signals to voltage signals and
sends them to MicroTech II
controller
Converts static pressure
signals to voltage signals.
Shuts off entire control circuit
(except crankcase heaters)
Used to manually switch unit
Rese
t
N/A
N/A
N/A
N/A
Introduction
Location Setting Range Differential Part no.
Main control
box
Main control
box
Main control
box
Main control
box
N/A
N/A
N/A N/A N/A
N/A N/A N/A
0–5" wc (0–1245.4 Pa) 1–6 V (dc) out
-025–0.25" wc
(-62.3–62.3 Pa)
1–5 V (dc) out
N/A
N/A
04954500
04954500
00135500
7
6
0
McQuay IM 487-5 13

Mechanical Installation

Mechanical Installation
Note – The installation of this equipment shall be in accordance
with the regulations of authorities having jurisdiction and all applicable codes. It is the responsibility of the installer to determine and follow the applicable codes.
CAUTION
Sharp edges on sheet metal and fasteners can cause personal injury. This equipment must be installed, operated, and serviced only by an experienced installation company and fully trained personnel.
Receiving Inspection
When the equipment is received, all items should be carefully checked against the bill of lading to be sure all crates and cartons have been received. If the unit has become dirty
during shipment (winter road chemicals are of particular concern), clean it when received.
Figure 14: Service clearances, unit with housed DWDI supply fan
72"
(1829 mm)
All units should be inspected carefully for damage when received. Report all shipping damage to the carrier and file a claim. In most cases, equipment ships F.O.B. factory and claims for freight damage should be filed by the consignee.
Before unloading the unit, check the unit nameplate to make sure the voltage complies with the power supply available.

Unit Clearances

Service Clearance
Allow an approximate service clearance as indicated in Figure 14. Also, McQuay recommends providing a roof walkway to the rooftop unit as well as along two sides of the unit that provide access to most controls and serviceable components.
72"
(1829 mm)
Roof
Walkway
Note: Sections with heating and/or cooling coils or DWDI supply fan must have noted service clearance on the control box side.
To Roof
Access
Location
A
(1524 mm)
B C
60"
D
Varies With Unit Arrangement
Refer to Certified Drawing & Note
E
X
Dimension "X" RDS 800-802 = 90" (2286mm) RAH 47-77 = 96" (2438mm)
D
C
F
24"
(635 mm)
Legend: A = Return Air Section B = Filter Section C = Cooling Section D = Cooling/Supply Fan Section E = Heat Section F = Discharge Plenum Section
14 McQuay IM 487-5
Figure 15: Service clearances, unit with SWSI plenum supply fan
72"
(1829 mm)
Mechanical Installation
72"
(1829 mm)
Roof
walkway
Note: Sections with heating and/or cooling coils or DWDI supply fan must have noted service clearance on the control box side.
To roof
access
location
A
(1524 mm)
B C
60"
Varies with unit arrangement. Refer to Certified Drawing and note below.
D
96"
(2438 mm)

Ventilation Clearance

Below are minimum ventilation clearance recommendations. The system designer must consider each application and provide adequate ventilation. If this is not done, the unit will not perform properly.
Unit(s) surrounded by a screen or a fence:
1 The bottom of the screen or fence should be at least 1 ft.
(305 mm) above the roof surface.
2 The distance between the unit and a screen or fence should
be as described in Figure 15.
3 The distance between any two units within a screen or
fence should be at least 120" (3048 mm).
Unit(s) surrounded by solid walls:
1 If there are walls on one or two adjacent sides of the unit,
the walls may be any height. If there are walls on more than two adjacent sides of the unit, the walls should not be higher than the unit.
2 The distance between the unit and the wall should be at
least 96" (2438 mm) on all sides of the unit.
3 The distance between any two units within the walls should
be at least 120" (3048 mm).
E F
X
Legend: A = Return air section B = Filter section C = Cooling section D = Cooling/supply fan section E = Heat section F = Discharge plenum section
Dimension "X" RDS 800–802 = 90" (2286mm) RAH 47–77 = 96" (2438mm)
Do not locate outside air intakes near exhaust vents or other sources of contaminated air.
If the unit is installed where windy conditions are common, install wind screens around the unit, maintaining the clearances specified (see Figure 16). This is particularly important to prevent blowing snow from entering the outside air intake and to maintain adequate head pressure control when mechanical cooling is required at low outdoor air temperatures.

Overhead Clearance

1 Unit(s) surrounded by screens or solid walls must have no
overhead obstructions over any part of the unit.
2 The following restrictions must be observed for overhead
obstructions above the air handler section (see Figure 16):
a There must be no overhead obstructions above the
furnace flue, or within 9" (229 mm) of the flue box.
b Overhead obstructions must be no less than 96"
(2438 mm) above the top of the unit.
c There must be no overhead obstructions in the areas
above the outside air and exhaust dampers that are farther than 24" (610 mm) from the side of the unit.
McQuay IM 487-5 15
Mechanical Installation
Figure 16: Overhead clearance
24" (610 mm) Maximum
Overhead Canopy
9" (229 mm) Minumum to Flue Box Typical All Sides
2" (51 mm)
Minumum
Top of Unit
to Overhead
Obstruction
Figure 17: Side discharge
Flue Box
24" (610 mm) Maximum
Notice
On units with side discharge, access to plenum-mounted components becomes difficult once ductwork is installed. Installer must provide access in the ductwork for plenum mounted controls
Side Discharge Opening (Access in Ductwork Must be Removed)
16 McQuay IM 487-5
Mechanical Installation
Roof Curb Assembly and Installation
Locate the roof curb and unit on a portion of the roof that can support the weight of the unit. The unit must be supported to prevent bending or twisting of the machine.
If building construction allows sound and vibration into the occupied space, locate the unit over a non-critical area. It is
the responsibility of the system designer to make adequate provisions for noise and vibration in the occupied space.
WARNING
Mold can cause personal injury. Some materials such as gypsum wall board can promote mold growth when damp. Such materials must be protected from moisture that can enter units during maintenance or normal operation.
Install the curb and unit level to allow the condensate drain to flow properly and allow service access doors to open and close without binding.
Integral supply and return air duct flanges are provided with the RAH roof curb, allowing connection of duct work to the curb before the unit is set. The gasketed top surface of the duct flanges seals against the unit when it is set on the curb. These flanges must not support the total weight of the duct work. Assembly of a typical RAH roof curb is shown in Figure 18 on page 18. Parts A through H are common to all units having bottom return openings. Depending on the unit length, Parts L and M may be included with the roof curb kit to create the correct overall curb length.
Assembly instructions
1 Set curbing parts A through H per dimensions shown over
roof opening or on a level surface (see Figure 18 on page 18). Note location of return and supply air openings.
2 If applicable, set other curbing parts (D, L, M, etc.) in place
making sure that the orientation complies with the assembly instructions (see Detail A). Check alignment of all mating bolt holes.
3 Bolt curbing parts together using fasteners provided.
Tighten all bolts finger tight.
4 Square entire curbing assembly and securely tighten all
bolts.
5 Position curb assembly over roof openings. Curb must be
level from side to side and over its length. Check that top surface of the curb is flat with no bowing or sagging.
6 Weld curbing in place. Caulk all seams watertight. Remove
backing from 0.25" (6 mm) thick × 1.50" (38 mm) wide gasketing and apply to surfaces shown by cross-hatching.
7 Flash curbing into roof as shown in Detail B.
8 Parts E and F are not required on units with no return shaft
within the curb perimeter.
9 Parts G and H are not required on units with no supply shaft
within the curb perimeter.
10 Be sure that electrical connections are coordinated (see
Figure 26).
McQuay IM 487-5 17
Mechanical Installation
Figure 18: RAH roof curb assembly instructions
Detail A
Equal Length Side Supports
M
L
D
Using remaining side supports in this area, align lengths on opposite sides of assembly and install a cross support "D" at each side.
M
L
3.50"
(90 mm)
8.75"
(222 mm)
H
81.00"
(2057 mm)
Inside
A
G
7.50"
(191 mm)
2.00"
(51 mm)
"Y"
Inside
C
G
Supply
H
Air
D
"X"
Inside
E
A
(222mm)
3.50"
(90mm)
8.75"
87.00"
(2210 mm)
Inside
90.00"
(2286 mm)
Figure 19: Roofing detail “B”
Curb gasketing
B
F
Return
Unit base
2 × 4 nailer strip
C
70.75"
D
F
Air
E
B
See Detail "A"
(1797 mm)
Dimensions
94.75"
(2407 mm)
RAH unit
047C 077C with flat cooling coil and /or 44" SWSI plenum supply fan 077C with staggered or no cooling coil, and/or 49" SWSI plenum supply fan
X Y
in mm in mm
38 965 28 711
157
5
157
5
38 965
46 1168
62
62
(not furnished)Counterflashing
Flashing (not furnished)
Rigid insulation
(not furnished)
Cant strip (not furnished)
Roffing material
(not furnished)
Galvanized
curb
Main unit
curb
18 McQuay IM 487-5
Figure 20: RDS roof curb assembly instructions
C
20.00"
(508 mm)
Inside
G
D
6.80"
(173 mm)
H
H
Supply
Air
Mechanical Installation
1.50"
(38 mm)
76.00" (1930 mm) Inside
A
G
7.50"
(191 mm)
2.00"
(5.1 mm)
B
"X"
Inside
"YY"
"XX"
E
F
A
"Y"
Inside
85.00"
(2159 mm)
F
Return
Air
Table 3: RDS roof curb assembly instructions
Unit size Fan
None 24.0 610 82.0 2083 6.8 173 1.5 38
800–802C
(2) 15” FC 24.0 610 82.0 2083 6.8 173 1.5 38 (2) 15" FC 24.0 610 82.0 2083 6.8 173 1.5 38
30" AF 30.0 762 76.0 1930 6.8 173 4.5 114 30" AF 30.0 762 76.0 1930 6.8 173 4.5 114 40" AF 36.0 914 78.0 1981 14.8 376 3.5 89 40" AF 36.0 914 78.0 1981 14.8 376 3.5 89
X Y XX YY
in mm in mm in mm in mm in mm in mm in mm in mm
C
38.80"
D
See Detail "A"
E
B
62.80"
(1594 mm)
Unit size
Return
fan
X Y XX YY
(984 mm)
None 24.0 610 82.0 2083 6.8 173 1.5 38
800–802C
McQuay IM 487-5 19
Mechanical Installation

IBC Seismic Compliant Units

It is important to follow these installation instructions for all IBC Seismic compliant McQuay Rooftop units.
IBC Seismic compliant McQuay Rooftop units can be mounted to either a roof curb or a post and rail setup. If using a roof curb, it must be specifically designed for seismic restraint and be IBC seismic compliant (spring isolated or non-isolated type seismic roof curbs are available). Typical construction of a seismic rated roof curb is from structural steel framing and contains seismic hold down brackets for attachment of the rooftop unit (see Figure 21). Post and rail arrangements rated for seismic applications are also available (spring isolated or non-isolated).
IMPORTANT: An acceptable IBC seismic installation provides a direct positive attachment to both the building structure and the roof mounted equipment.
Refer to the roof curb manufacturer’s submittal drawings for actual roof curb assembly, attachment details and rigging instructions for both roof curb and post and rail arrangements.
Figure 21: Typical seismic roof curb (spring isolated)

Roof Curb Arrangement

1 Set the rooftop unit on the roof curb (McQuay Rooftop
units are designed to overhang from the roof curb).
2 Adjust the seismic hold down brackets so they come into
contact with the unit base per Figures 22 and 23 on page
21.
a The seismic hold down brackets should be adjustable
and accommodate the overhang of the rooftop unit.
b If the hold down bracket cannot reach the unit base, use
a shim spacer. See Figure 23 on page 21.
3 Weld each seismic hold down bracket (and shim spacer, if
required) to the unit base as shown in the acceptable weld zone detail in Figure 22 on page 21.
CAUTION
When welding unit to the curb, do not damage wiring (control panel side). Weld ONLY in the specified zone in the acceptable weld zone (see Figure 22 on page 21). Welding must comply with weld fillet size, etc. as indicated in Figure 22 on page 21.
Note – High temperature insulation is installed at the factory to
allow for field welding along the lower front edge region of the unit base.
Duct opening
Seismic hold down brackets
Structural steel frame
Seismic hold down brackets
Spring isolator
20 McQuay IM 487-5
Figure 22: Welding of hold down brackets—unit base, cross-sectional view
Unit power wiring (by factory)
Unit base
.25
Field attachment
Mechanical Installation
Unit control wiring (by factory)
weld
Weld zone
.50"
Acceptable weld zone
Figure 23: Shim spacers on hold down brackets
Shim
spacer
It may be necessary for the contractor to field fabricate spacers or new seismic hold-downs for rooftop units having larger overhang dimensions.
Unit power wiring
(by factory)
Unit base
High temp Insulation
Seismic hold down bracket
Unit control wiring (by factory)
Roof curb
Seismic hold down bracket
Roof curb
McQuay IM 487-5 21
Mechanical Installation

Post and Rail Arrangement

1 Set the rooftop unit on the rails. The rails should run
lengthwise and support the entire unit base.
2 Weld both sides of the unit directly to each rail as shown in
Figures 24 and 25 on page 22. required is dependent on the length of the unit.
a Make the fillet welds 2 inches long, spaced 48 inches
apart on centers.
b Place the end welds 6 to 12 inches from the unit edge.
Figure 24: Welding of unit to rail—unit base, cross-sectional view
The total number of welds
Note – High temperature insulation is installed at the factory to
CAUTION
When welding unit to the curb, do not damage wiring (control panel side). Weld ONLY in the specified zone in the acceptable weld zone (see Figure 24 on page 22). Welding must comply with weld fillet size, etc. as indicated in Figure 24 on page 22.
allow for field welding along the lower front edge region of the unit base.
Unit base
.25
Weld zone
2–48
.50"
Acceptable weld zone
Figure 25: Weld locations for rail arrangement
6–12"
Unit power wiring
(by factory)
Unit base
Rail
Field attachment
weld
High temp insulation
Unit control wiring
(by factory)
Rail
Rooftop unit
.25
2–48
Weld every 48"
Rails
6–12"
22 McQuay IM 487-5
Mechanical Installation
Figure 26: Typical power wire entrance, curb view (RDS 800–802 shown; for exact values, refer to submittal)
D
B
D
Detail A
20.0
SA
OPNG
6.0
6.8
1.5
76.0
B
7.5
6.0
E
3.0 Dia. K.O.
RPS only
97.0
B
8.0
2Typ 4Typ
K.O.
A
RA
OPNG
A
A
See Detail A
Unit length minus 6.4
12.1
5.1
3.4
C
0.9 Dia.
2.0
4.6
4.8
9.7
2.1
3.1
4.3
McQuay IM 487-5 23
Mechanical Installation

Post and Rail Mounting

When mounting by post and rail, run the structural support the full length of the unit. Locate the structural member at the base of the unit as shown in Figure 27, assuring the I-beam is well
supported by the structural member.
CAUTION
The unit must be level side to side and over the entire length. Equipment damage can result if the unit is not level.
If resilient material is placed between the unit and the rail, insert a heavy steel plate between the unit and the resilient material to distribute the load. Seal cabinet penetrations (electrical, piping, etc.) properly to protect against moisture and weather.
Figure 27: Post and rail mounting
99" RAH
(2515 mm)
94" RDS
5" *
(127mm)
(2388 mm)
1 Support the unit well along the length of the base rail.
2 Level the unit (no twists or uneven ground surface).
3 Provide proper drainage around the unit to prevent flooding
of the equipment.
4 Provide adequate protection from vandalism, mechanical
contact, etc.
5 Securely close the doors.
6 If there are isolation dampers, make sure they are properly
installed and fully closed to prevent the entry of animals and debris through the supply and return air openings.
7 Cover the supply and return air openings on units without
isolation dampers.
Figure 28 shows an example of the rigging instruction label shipped with each unit.
WARNING
Use all lifting points. Improper lifting can cause severe personal injury and property damage.
Figure 28: Rigging and handling instruction label

Rigging and Handling

Lifting brackets with 2" (51 mm) diameter holes are provided on the sides of the unit.
Use spreader bars, 96" to 100" (2438 to 2540 mm) wide, to prevent damage to the unit cabinet. Avoid twisting or uneven lifting of the unit. The cable length from the bracket to the hook should always be longer than the distance between the outer lifting points.
If the unit is stored at the construction site for an intermediate period, follow these additional precautions:
Unit has either four or six lifting points (four-point shown below).
Rigging cables must be at least as long as distance “A.”
Spreader bars
required
A
Caution: Lifting points may not be symmetrical to center of gravity of unit. Balast or unequal
Lift only as indicated
cable lengths may be required.
CAUTION
Lifting points may not be symmetrical to the center of gravity of the unit. Ballast or unequal cable lengths may be required.
24 McQuay IM 487-5
Mechanical Installation
Lifting Points
To determine the required lifting cable lengths and whether four-point or six-point lifting is required, use Tables 4 and 5 and Figure 29.
Referring to Figure 29, note that dimension A is the distance between the outer lifting points. The four outer rigging cables must be equal to or longer than dimension A. Dimension B shows the minimum distance between the outer and the inner lifting points for six-point lifting. Use this to roughly determine the required length of the middle cables for six­point lifting. Determine dimension A by subtracting dimensions X and Y from dimension Z (e.g., A = Z – X – Y).
Where:
Z = Total unit length in inches
(refer to certified drawings for this dimension).
X = Outdoor/return air section length (refer to Figure 29 and Table 5 for this dimension).
If A 288" (7315 mm), 4-point lifting is sufficient.
If A > 288" (7315 mm), 6-point lifting is required.
Table 4: RAH X dimension (see Figure 29) Economizer section
Type of economizer
section
100% OA 0 0
Plenum 48” (1219 mm) 72” (1829 mm)
0–30% OA 48” (1219 mm) 72” (1829 mm)
0–100% economizer 72” (1829 mm) 96” (2438 mm)
0–100% economizer with return fan 72” (1829 mm) 96” (2438 mm)
047C 077C
Figure 29: Unit type RAH lifting points
4 Lifting Points
A
Z
X
6 Lifting Points
B
Z
A
Table 5: RDS X dimension (see Figure 29) Outdoor/return air section
Outdoor/return air section 800C 802C
100% OA 0 0
Plenum 40” (1016 mm) 52" (1321 mm)
0–30% OA 40” (1016 mm) 52" (1321 mm)
0–100% economizer 40” (1016 mm) 52" (1321 mm) 0–100% economizer with 15" return fan 62" (1575 mm) — 0–100% economizer with 30" return fan 52" (1321 mm) 52" (1321 mm) 0–100% economizer with 40" return fan 80" (2032 mm)
X
RDS 800: B Min. = 62" (1515 mm) RDS 802: B Min. = 84" (2134 mm) RAH 47: B Min. = 96" (2438 mm) RAH 77: B Min. = 120" (3048 mm)
McQuay IM 487-5 25
Mechanical Installation

Split Units

Although units typically ship from the factory as complete units, they can be factory split at the supply fan bulkhead and connected later on the roof. This configuration is ordered if the shipping length or a weight limitation prevents ordering a packaged unit.
A single nameplate is attached to the air handler section and power is supplied to both sections through the optional main control box as in a packaged unit.
RAH Factory Split at Fan
Field reassembly of an RAH unit that shipped split at the fan takes place in three phases: (1) setting the sections,
Figure 30: Set sections
Remove plywood and retaining
Remove top cap and save for reassembly.
angles from unit and discard.
Discharge end of unit
(2) mechanically recoupling the cabinet, and (3) reconnecting power and control wiring.
Phase I. Set sections
Remove top cap and save for Phase II, Step 1.
1
2 Remove screws on fan panel, leaving retainer clips in place
to secure bulkhead. Save screws for Phase II, Step 5.
3 Remove plywood and retaining angles from unit and
discard.
4 Carefully lower both sections of unit (fan end and
discharge end) into place, making sure the roof curb engages the recesses in the unit base.
Fan end of unit
26 McQuay IM 487-5
Remove screws on fan panel, leaving retainer clips in place. Save screws for reassembly.
Phase II. Reassemble cabinet (Figure 31)
1 Reinstall top cap removed in Phase I, Step 1.
2 Caulk (watertight) ends of splice cap.
3 Caulk (watertight) vertical seam.
4 Install #10 screws (provided).
5 Install screws (.25–20 ×.75) removed in Phase I, Step 2.
6 Install splice cover (provided).
Figure 31: Reassemble cabinet
Mechanical Installation
Reinstall top cap saved in step 1
Caulk ends of splice cap
Splice cover, provided
See detail
Caulk vertical seam
Install screws (.25 to 20 × .75) saved from step 1
#10 screws, provided
Nut clip-on, provided
McQuay IM 487-5 27
Mechanical Installation
Phase III. Reconnect power and control wiring
Once the sections are physically reconnected, the ends of the power harness are fed back through the unit base into the junction box, per the unit’s electrical schematics.
CAUTION
Connect the power block correctly and maintain proper phasing. Improper installation can cause severe equipment damage.
1 Make electrical connections and reinstall inner raceway
cover as shown in Figure 32.
Figure 32: Electrical connections and raceway cover installation
If applicable, install as shown with provided fasteners.
After routing wires, install inner raceway cover (see step 6).
3.72 ref. (94 mm)
Field Refrigerant Piping and Charging of DX Coils
Units that ship from the factory with DX coils installed do not include refrigerant piping or refrigerant controls. The coil assembly is ready for field connections at the distributors and at the suction headers. Piping kits that provide the necessary liquid and hot gas piping and control components are available for field installation. Field-installed refrigerant piping may exit the unit cabinet at one of the following locations:
Through the floor of the unit.
Through the discharge and bulkhead of the unit.
Through a cabinet door near the DX coil that is not required
for service areas.
CAUTION
For any of the above cabinet penetrations, tightly seal the hole to prevent water or air leakage.
In preparing for field piping, remove the plastic plugs on the distributors and unsweat the copper caps at the suction header connections.
Follow piping design, sizing, and installation information presented in ASHRAE handbooks in the design and installation of interconnecting piping. The DX coil and condensing unit are intended to be set at the same elevation, as close as possible to each other to minimize refrigerant pressure drop. Design piping to prevent liquid refrigerant carryover to the compressor and to provide a continuous return of
compressor oil from the system.
2 When power wire reconnection is complete, reinstall the
inner raceway cover in the blank or heat section. Figure 32 shows a typical installation of the raceway cover.
3 Run the control harnesses by removing the external
raceway covers on either side of the unit split.
4 Remove the excess harness length from the external
raceway on the downstream side of the split; then route along the raceway, through the bushed hole in the fan section and into the junction box where control wiring terminal blocks are provided for reconnection.
5 Make all electrical connections per the unit’s electrical
schematics.
6 Reinstall the external raceway covers after routing of the
control wires is complete.
CAUTION
The pounds of refrigerant in the system may exceed the capacity of the condenser, depending on the amount of refrigerant in the liquid lines between the DX coil and the condensing unit. Refer to condenser manufacturer for information about refrigerant capacity. Suitable means of containing the refrigerant is required.
CAUTION
To prevent liquid return and damage to the compressor on systems with optional hot gas bypass, it is important to locate the bypass solenoid valve at the condensing unit and not at the DX coil.
28 McQuay IM 487-5
Mechanical Installation
Piping Recommendations
7 Use type K or L clean copper tubing. Thoroughly clean or
braze all joints with high temperature solder.Base piping sizes on temperature/pressure limitations as recommended in the following paragraphs. Under no circumstances should pipe size be based strictly upon coil or condensing unit piping connection size.
8 Do not exceed suction line piping pressure drop equivalent
to 2°F (1°C), 3 psi (20.7 kPa) per 100 feet (30.5 m) of equivalent pipe length. After the suction line size is determined, check the vertical suction risers to verify that oil will be carried up the riser and back to the compressor. Pitch the suction line(s) in the direction of refrigerant flow and make sure they are adequately supported. Lines should be free draining and fully insulated between the evaporator and the compressor. Install a trap on the vertical riser to the compressor.
9 To determine the minimum tonnage required to carry oil up
suction risers of various sizes, check the vertical suction risers using Table 6. Insulate suction lines inside the unit
cabinet to prevent condensation.
Table 6: Minimum tonnage (R-22) to carry oil up suction riser at 40°F saturated suction
Line size O.D. Minimum tonnage
1 1/8" 1.5 1 3/8" 2.5 1 5/8" 3.8 2 1/8" 7.6 2 5/8" 13.10 3 1/8" 20.4 3 5/8" 29.7 4 1/8" 41.3
10 Size the liquid line for a pressure drop not to exceed the
pressure equivalent of 2°F (1°C), 6 psi (41.4 kPa) saturated temperature.
Leak Testing
bring the pressure to a maximum of 125 psig. The unit should then be leak tested with halide or electronic leak detector. After making any necessary repair, the system should be
evacuated as described in the following paragraphs.
WARNING
Do not use oxygen or air to build up pressure. Explosion hazard can cause severe personal injury or death.
Evacuation
After determining the unit is tight and there are no refrigerant leaks, evacuate the system. Use a vacuum pump with a pumping capacity of approximately 3 cu.ft./min. and the ability to reduce the vacuum in the unit to at least 1 mm (1000 microns).
1 Connect a mercury manometer or an electronic or other
type of micron gauge to the unit at a point remote from the vacuum pump. For readings below 1 millimeter, use an electronic or other micron gauge.
2 Use the triple evacuation method, which is particularly
helpful if the vacuum pump is unable to obtain the desired 1 mm of vacuum. The system is first evacuated to approximately 29" (740 mm) of mercury. Then add enough refrigerant vapor to the system to bring the pressure up to 0 pounds (0 microns).
3 Evacuate the system again to 29" (740 mm) of vacuum.
Repeat his procedure three times. This method is most effective by holding system pressure at 0 pounds (0 microns) for a minimum of 1 hour between evacuations. The first pulldown removes about 90% of the noncondensables; the second removes about 90% of that remaining from the first pulldown. After the third pulldown, only 1/10 of 1% of noncondensables remains.
Table 7 on page 30 shows the relationship between pressure, microns, atmospheres, and the boiling point of water.
In the case of loss of the nitrogen holding charge, the unit should be checked for leaks prior to charging the complete system. If the full charge was lost, leak testing can be done by charging the refrigerant into the unit to build the pressure to approximately 10 psig and adding sufficient dry nitrogen to
McQuay IM 487-5 29
Before replacing refrigerant sensors or protective devices, see “Refrigerant Charge” on page 31 for an important warning to prevent an abrupt loss of the entire charge.
CAUTION
Mechanical Installation
Table 7: Pressure-vacuum equivalents
Absolute pressure above zero Vacuum below 1 atmosphere
Microns PSIA Mercury (mm) Mercury (in)
0 0 760.00 29.921
50 0.001 759.95 29,920 1/15,200 –50
100 0.002 759.90 29.920 1/7,600 –40
150 0.003 759.85 29.920 1/5,100 –33
200 0.004 759.80 29.910 1/3,800 –28
300 0.006 759.70 29.910 1/2,500 –21
500 0.009 759.50 29.900 1/1,520 –12
1,000 0.019 759.00 29.880 1/760 1
2000 0.039 758.00 29.840 1/380 15
4,000 0.078 756.00 29.760 1/189 29
6000 0.117 754.00 29.690 1/127 39
8,000 0.156 752.00 29.600 1/95 46
10,000 0.193 750.00 29.530 1/76 52
15,000 0.290 745.00 29.330 1/50 63
20,000 0.387 740.00 29.130 1/38 72
30,000 0.580 730.00 28.740 1/25 84
50,000 0.967 710.00 27.950 1/15 101
100,000 1.930 660.00 25.980 2/15 125
200,000 3.870 560.00 22.050 1/4 152
500,000 9.670 260.00 10.240 2/3 192
760,000 14.697 0 0 1 atmosphere 212
Approximate fraction
of 1 atmosphere
H2O boiling point at each
pressure (
o
F)
Charging the System
Units are leak tested at the factory and shipped with a nitrogen holding charge. If the holding charge has been lost due to shipping damage, charge the system with enough refrigerant to raise the unit pressure to 30 psig after first repairing the leaks and evacuating the system.
1 After all refrigerant piping is complete and the system is
evacuated, it can be charged as described in the paragraphs following. Connect the refrigerant drum to the gauge port on the liquid shutoff valve and purge the charging line between the refrigerant cylinder and the valve. Then open the valve to the mid position.
2 If the system is under a vacuum, stand the refrigerant drum
with the connection up, open the drum, and break the vacuum with refrigerant gas.
3 With a system gas pressure higher than the equivalent of a
freezing temperature, invert the charging cylinder and elevate the drum above the condenser. With the drum in
this position and the valves open, liquid refrigerant flows into the condenser. Approximately 75% of the total requirement estimated for the unit can be charged in this manner.
4 After 75% of the required charge enters the condenser,
reconnect the refrigerant drum and charging line to the suction side of the system. Again, purge the connecting line, stand the drum with the connection side up, and place the service valve in the open position.
Important: At this point, interrupt the charging procedure and do prestart checks before attempting to complete the refrigerant charge.
Note – Stamp the total operating charge per circuit on the unit
nameplate for future reference.
CAUTION
Adding refrigerant to the suction always risks liquid-related damage to the compressor.
30 McQuay IM 487-5
Mechanical Installation
Take special care to add refrigerant slowly enough to the suction to prevent damage. Adjust the charging tank hand valve so liquid leaves the tank but vapor enters the compressor.
Refrigerant Charge
Factory-installed DX coils are designed to use R-22. The total charge per circuit is the sum of the following three values:
Condenser section charge. Refer to manufacturer’s data.
Evaporator coil charge.
Charge for length of interconnecting piping, installed by
field.
Note – Factory-installed DX coils are intended for one refrigerant
Note – The total operating charge per circuit should not exceed
Table 8: Approximate DX coil refrigerant charge per circuit
Table 9: Approximate refrigerant charge per circuit
* The RDS 802C unit has two refrigerant circuits.
circuit on unit size 800 and two refrigerant circuits containing identical weights of refrigerant on all other sizes. The values shown in Table 8 and Table 9 are for each circuit.
the pumpdown capacity per circuit.
Unit size
047C 3 x no. of DX rows 3.5 x no. of DX rows 077C 5 x no. of DX rows 6.5 x no. of DX rows
Unit size Evaporator coil (lbs/ckt/coil row)
802 3.30
802C* 2.45
DX Coil R-22 charge (lbs./circuit)
Flat coil Staggered coil
Where the cooling coils have intermediate condensate pans on the face of the evaporator coil, copper tubes near both ends of the coil provide drainage to the main drain pan. Check that the copper tubes are in place and open before the unit is put into operation.
On units with staggered cooling coils, the upper drain pan drains into the lower coil drain pan through a copper tube near the center of the drain pan. Check that this tube is open before putting the unit into operation and as a part of routine maintenance.
Because drain pans in any air conditioning unit have some moisture in them, algae, etc. will grow. Periodically clean to prevent this buildup from plugging the drain and causing the drain pan to overflow. Clean drain pans to prevent the spread of disease. Cleaning should be performed by qualified
personnel
.
WARNING
Drain pans must be cleaned periodically.
Material in uncleaned drain pans can cause disease.
Cleaning should be performed by qualified personnel.
Figure 33: Condensate drain connection

Unit Piping

Condensate Drain Connection
The unit is provided with a 1.5" male NPT condensate drain connection. Refer to certified drawings for the exact location. For proper drainage, level the unit and drain pan side to side and install a P-trap
Units may have positive or negative pressure sections. Use traps in both cases with extra care given to negative pressure sections. In Figure 33, dimension “A” should be a minimum of 8" (203 mm). As a conservative measure to prevent the cabinet static pressure from blowing or drawing the water out of the trap and causing air leakage, dimension A should be two times the maximum static pressure encountered in the coil section in inches wc.
Draining condensate directly onto the roof may be acceptable; refer to local codes. Provide a small drip pad of stone, mortar, wood, or metal to protect the roof against possible damage.
If condensate is piped into the building drainage system, pitch the drain line away from the unit a minimum of 1/8" per foot. The drain line must penetrate the roof external to the unit. Refer to local codes for additional requirements. Sealed drain lines require venting to provide proper condensate flow.
S e e V i e w " A "
C o p p e r T u b e
( o n e e a c h e n d o f c o i l )
S t a t i c P r e s s u r e " P "
4 " ( 1 0 2 m m )
M i n i m u m
" A "
8 " ( 2 0 3 m m )
M i n . o r 2 x " P "
( i n . w . o . )
D r a i n P a n
V i e w A
N o t e : D r a i n l i n e m u s t
n o t b e r u n h i g h e r
t h a n t h i s l e v e l
M i n i m i z e T h i s
e n s i o n
D i m
Gas Piping
See the “Installation” section of the gas-fired furnace installation manual, Bulletin No. IM 684 or 685.
McQuay IM 487-5 31
Mechanical Installation
s
Piping for Steam, Hot Water/ChIlled Water Coils
Factory-installed chilled water coils are installed in a coil section that can be designed to accept a factory-installed heating coil immediately upstream. The coil section can be ordered in either the draw-through or blow-through position. All chilled water piping can be done internal to the unit without requiring a piping vestibule (except on sizes 800–802 when heating coils are included in the cooling coil section).
Steam and hot water coils can be factory installed in either a heat section, or in the combination coil section. These sections can be located either in the draw-through or blow-through position. When a steam or hot water coil is installed in the heat section, all piping can be done internal to the unit without requiring a piping vestibule. Refer to Figure 35 and Figure 37 on page 34.
When a steam or hot water coil is installed in the combination coil section, the coil connections project to the inside surface of the door panel. Holes can be cut in the door panels to connect the piping to the coils, or an accessory piping vestibule can be added to the unit to provide piping space. Refer to the section on vestibule assembly instructions. The piping can then be routed back within the unit as shown in Figure 35 on page 33.
To avoid piping penetrations through the roof external to the curb, holes can be cut through the floor of the unit at the
locations specified on the certified drawings.
With the factory piping and valve package, the two coils are piped in parallel and controlled through a single three-way valve. Field piping connections are of the same NPT size as the valve-male threads at the supply connection, female threads at the return connection.
Figure 34: Hot water heat section (shown with factory valve and piping)
2.12 " ODM Copper Coil Connection
Lower Coil
Bypass
Air Flow
Upper Coil
Supply
CAUTION
Seal all holes in the unit floor to prevent water leakage into the building.
Hot Water Piping
Hot water coils are provided without valves for field piping or piped with three-way valves and actuator motors.With the factory piping and valve package, the two coils are piped in parallel and controlled through a single three-way valve. Field piping connections are of the same NPT size as the valve-male threads at the supply connection, female threads at the return connection.
Hot water coils are not normally recommended for use with entering air temperatures below 40°F (4°C). No control system can guarantee a 100% safeguard against coil freeze-up. Glycol solutions or brines are the only freeze-safe media for operation of water coils at low entering air temperature conditions. Refer to the “Maintenance” section of this manual for more on winterizing coils. The hot water section consists of two stacked soils, as shown in Figure 34.
When no factory piping or valve is included, the coil connections are 1.625” ODM copper on 800 and 802C, and
2.125" ODM copper on 047 and 077C.
The valve actuator spring returns to a stem up position upon power failure. This allows full flow through the coil.
Refer to the certified drawings for the recommended piping entrance locations. Seal all piping penetrations to prevent air and water leakage.
Note – Factory-installed water valves and piping are bronze,
brass, and copper. Dissimilar metals within the plumbing system can cause galvanic corrosion. To avoid corrosion, provide proper di-electric fittings as well as appropriate water treatment.
CAUTION
Coil freeze possible. Can damage equipment. Follow instructions for mixing antifreeze solution used. Some products have higher freezing points in their natural state than when mixed with water. The freezing of coils is not the responsibility of McQuay International. Refer to “Experience in the field has shown that R-407C systems can be “topped off” after a leak has been repaired and operate normally. There is no need, except in the case of a critically charged systems, to replace the entire charge after a leak has been repaired.” on page 113.
32 McQuay IM 487-5
Mechanical Installation

Steam Coil Piping (All Units)

The steam heat section consists of two stacked coils pitched at 1/8" (3 mm) per foot (305 mm) as shown in Figure 35 to provide positive condensate removal. When no factory piping or valve is included, the coil connections are 2.5" male NPT iron pipe.
Note – The valve actuator spring returns to a stem up position
Figure 35: Steam heat section (shown with factory valve and piping)
With the factory piping and valve package, the two coil supplies are piped in parallel and controlled through a single two-way valve. The field supply connection is of the same female NPT size as the valve. Field return connections are made at the 2.50" male NPT fittings on each of the two stacked coils.
Note – Refer to the sections on steam coil piping and trap
upon power failure. This allows full flow through the coil.
Upper Coil
Lower Coil
Supply
recommendations for additional information.The valve actuator spring returns to a stem up position upon power failure. This allows full flow through the coil.
2.12 " ODM Copper Coil Connections
Return
Return
Figure 36: Two-way valve package

Steam Piping Recommendations

1 Be certain that adequate piping flexibility is provided.
Stresses resulting from expansion of closely coupled piping and coil arrangement can cause serious damage.
2 Do not reduce pipe size at the coil return connection. Carry
return connection size through the dirt pocket, making the reduction at the branch leading to the trap.
3 Install vacuum breakers on all applications to prevent
retaining condensate in the coil. Generally, the vacuum breaker is to be connected between the coil inlet and the return main. However, if the system has a flooded return main, the vacuum breaker to the atmosphere; the trap design should allow venting of the large quantities of air.
4 Do not drain steam mains or takeoffs through coils. Drain
mains ahead of coils through a steam trap to the return line.
5 Do not attempt to lift condensate when using modulating or
on-off control.
6 Pitch all supply and return steam piping down a minimum
of 1" (25 mm) per 10 feet (3 m) of direction of flow.
McQuay IM 487-5 33
Mechanical Installation

Steam Trap Recommendations

1 Size traps in accordance with manufacturers’
recommendations. Be certain that the required pressure differential will always be available. Do not undersize.
2 Float and thermostatic or bucket traps are recommended for
low pressure steam. Use bucket traps on systems with on­off control only.
3 Locate traps at least 12" (305 mm) below the coil return
connection.
4 Always install strainers as close as possible to the inlet side
of the trap.
5 A single tap may generally be used for coils piped in
parallel, but an individual trap for each coil is preferred.
Figure 37: Heating coil piping with vestibule
Steam Coil Freeze Conditions
If the air entering the steam coil is below 35°F (2°C), note the following recommendations:
1 Supply 5 psi (34.5 kPa) steam to coils at all times.
2 Modulating valves are not recommended. Control should
be by means of face and bypass dampers.
3 As additional protection against freeze-up, install the tap
sufficiently far below the coil to provide an adequate hydrostatic head to ensure removal of condensate during an interruption on the steam pressure. Estimate 3 ft. (914 mm) for each 1 psi (7 kPa) of trap differential required.
4 If the unit is to be operated in environments with possible
freezing temperatures, an optional freezestat is recommended. See “Freeze Protection” on page 86 for additional information.
Figure 38: Valve assembly
S t e m C l i p
S t e m
Figure 39: Steam valve package
S e t s c r e w s
34 McQuay IM 487-5
Mechanical Installation
Chilled Water Piping
Chilled water coils are provided without valves for field piping, or piped with three-way valves with motor actuators. Table 10 provides information on units with factory installed piping and valve packages. The table also provides field sweat connection information for units not furnished with factory installed piping and valve packages.
With the factory piping and valve package, the coil assembly is controlled through a single three-way valve. When two coils are included in the assembly, they are piped in parallel. Field connections are male NPT, sized as shown in Table 10. Refer to Figure 40 for a typical cooling coil with factory valve and piping.
Figure 40: Chilled water coil (with factory valve and piping)
Air Flow
Return
Bypass
Supply
McQuay IM 487-5 35
Mechanical Installation
Table 10: Piping connection sizes/valve size options for chilled water piping
Cabinet
size
047C
077C
Application
code
Blow-thru or
draw-thru small
coil section
Blow-thru or
draw-thru large
coil section
Face and bypass
section with
small coil
Face and bypass section with large
coil
Blow-thru or
draw-thru small
coil section
Blow-thru or
draw-thru large
coil section
Face and bypass
section with
small coil
Face and bypass section with large
coil
Coil size
Hx 83"
(2108 mm)
long
33 + 33
(2 coils) (838
+
838 mm)
39 + 39
(2 coils) (991
+
991 mm)
48
(1219 mm)
39 + 39
(2 coils) (991
+
991 mm)
45 + 45
(2 coils)
(1143 +
1143 mm)
63 + 63
(2 coils)
(1600 +
1600 mm)
63
(1600 mm)
54 + 54
(2 coils)
(1372 +
1372 mm)
Face area sq.
ft. (sq. m)
38.0
(3.53 m²)
45.0
(4.18 m²)
27.7
(2.57 m²)
45.0
(4.18 m²)
51.9
(4.82 m²)
72.6
(6.74 m²)
36.3
(3.37 m²)
62.3
(5.74 m²)
Available rows
(available with 8,
10, 12 fins/in)
3DRDQAQAP 4 DRDQBQBQBP 5DRDQBQAP 6 DRDQBQBQAP 8 DRDQBQBQBP 3DRCQAQAP 4DRCQCQCQBP 5DRCQCQAP 6DRCQCQCQAP 8DRCQCQCQBP 3 FUET——ASAS 4 FUETCSCSCS 5FUETCSAS 6FUETCSCSAS 8 FUETCSCSCS 3DRCQAQAP 4DRCQCQCQBP 5DRCQCQAP 6DRCQCQCQAP 8DRCQCQCQBP 3 CRCQ——APAP 4 CRCQCPBPBP 5 CRCQ——BPAP 6 CRCQCPBPAP 8 CRCQCPBPBP 3 BQBP——APAP 4 BQBPBPBPBP 5 BQBP——BPAP 6 BQBPBPBPAP 8 BQBPBPBPBP 3 ETCS——ASAS 4 ETCSCSCSCS 5ETCSCSAS 6 ETCSCSCSAS 8 ETCSCSCSCS 3 CRCQ——APAP 4 CRCQBPBPBP 5 CRCQ——BPAP 6 CRCQBPBPAP 8 CRCQBPBPBP
5WH 5WL 5WS 5WM 5WD
1 2 1 2 1 2 1 2 1 2
Available circuiting
Columns (see next page for explanation)
36 McQuay IM 487-5
Mechanical Installation
Table 10: Piping connection sizes/valve size options for chilled water piping
3 G T G T —————— 4 GTGTGT———— 5 G T G T —————— 6 GTGTGT———— 3 G T G T —————— 4 GTGTGT———— 5 G T G T —————— 6 GTGTGT———— 3 — L —M——— N — N 4 — L —M—M—N— N 5 — L —M——— N — N 6 — L —M—M—N— N 8 — L —M—M—N— N
10 — L —M——— N — N
3—LMKNN 4 — L —M——— N — N 5—LMKNN 6—LMKNN 8—LMKNN
10 L M K N N
draw-thru cooling
800
or
Face and bypass
802
Blow-thru or
only coil section
Blow-thru or
draw-thru unit
coil section
section with
small coil
Blow-thru or
draw-thru
contractor coil
section
48 + 78 (1220 +
1981 mm)
48 + 78 (1220 +
1981 mm)
30 + 79
(763 +
2006 mm)
36 + 79
(915 +
2006 mm)
26.0
(2.42 m²)
26.0
(2.42 m²)
16.5
(2.57 m²)
19.8
(4.18 m²)
Table Available Circuiting Legend
Column 1:
These units are available with a factory installed package consisting of a three-way water valve and connecting piping.
A = This combination is not available with a factory-installed piping and valve package. B = 300, 2.50, or 200 inch three-way valves can be specified C = 300, 2.50, 2.00, or 150 inch three-way valves can be specified D = 250, 200, or 150 inch three-way valves can be specified E = 250, 200, 150, or 1.25 inch three-way valves can be specified F = 200, 1.50, or 125 inch three-way vales can be specified G = 1.25, 1.50, 2.00 or 2.50 inch three-way valves can be specified Field supply and return female NPT connection sizes are the same as the valve size.
Column 2:
The following letters designate units that are not furnished with the factory installed piping/valve package. Required are field sweat connections, at one or two coils, to male copper tubing for the supply and return water piping.
K = A single 2.00 inch NPT supply and return if fin height is 21–30 inches and 2.50 inches of fin height is 30–36 inches. L = A single 1.50 inch NPT supply and return M = A single 2.00 inch NPT supply and return if fin height is 21–30 inches N = A single 2.50 inch NPT supply and return P = Two 3.12 inch O.D. supply and two 3.12 O.D. return connections Q = Two 2.62 inch O.D supply and two 2.62 O.D. return connections R = Two 2.12 inch O.D. supply and two 2.12 O.D. return connections S = One 3.12 inch O.D supply and one 3.12 O.D. return connections T = One 2.62 inch O.D supply and one 2.62 O.D. return connections U = One 2.12 inch O.D supply and one 2.12 O.D. return connections
McQuay IM 487-5 37
Mechanical Installation

Vestibule Assembly Instructions

An accessory vestibule is available to provide additional piping space for coils installed in a four-foot section. A vestibule is required to maintain door access on a combination heating and cooling section. Assemble the vestibule to the unit part by part as shown in Figure 41.
Note – The door, hinge, and latch assemblies from the unit are
used on the vestibule.
Step 1
Remove door from section where vestibule is to be located by removing screws holding hinges to upright support (leave hinges on door). Set door aside and save for Step 4.
Remove door latch assembly from other side upright support. Use offset Phillips screwdriver or a wrench to remove screws holding latch assembly in place. Save door latch assembly, screws and bushings for Step 4.
Figure 41: Step 1 illustration
Door
Door Latch Assembly
Step 2
Remove gasketing around door flange and save for use on vestibule. See Step 4. Remove door and save for Step 4.
Figure 42: Step 2 illustration
Gasketing
Door Prop
38 McQuay IM 487-5
Mechanical Installation
Step 3
1 Assemble side panels A and B to uprights using #10 drill
screws supplied. Make certain side panels are flush against uprights before securing into place.
2 Fasten bottom panel D to base channel using #10 drill
screws and to side panels A and B using #10 screws supplied.
3 Set top panel C in place and fasten to side panels A and B
using #10 screws and to top panel using #10 screws supplied.
Figure 43: Step 3 illustration
#10 Screw
#10 Drill Screw
Step 4
Reassemble access door to vestibule by screwing hinges
1
into side panel using screws saved from Step 1. (Access door must be attached to the vestibule in the same opening direction as it was on the unit.)
2 Remove and discard latch handle locking screws and
retaining washer. Fasten door latch assembly to side panel using screws and bushings saved from Step 1. (Latch must be fastened on the same side as when located on the unit.)
3 Fasten upright angles to vestibule using #10 screws
supplied.
4 Seal between unit and vestibule with silicone sealant along
top and sides as shown.
Note – Any holes cut in the floor of the unit must be sealed to
Figure 44: Step 4 illustration
prevent water leakage.
Gasketing
Upright Angle
#10 Screw
Silicone Sealant
Silicone Sealant
#10 Screw
Door
Gasketing
Door Prop
Upright Angle
Door Latch Assembly (See Note)
McQuay IM 487-5 39
Mechanical Installation

Damper Assemblies

The optional damper assemblies described in this section normally are ordered with factory-installed actuators and linkages. The following sections describe operation and linkage adjustment of the factory option.
Economizer Dampers
Outside air intake is provided on both sides of the unit, and the return air path is at the center of the damper set. As the single actuator modulates the outside air dampers open, the return air dampers close. Exhaust air exits the unit through the gravity relief dampers provided at the end of the economizer section.
The outside air return air damper assembly (economizer) comes with manually adjustable linkage. This adjustable
Figure 45: Economizer dampers
Outside
Air
Optional Return Air Fan
Economizer
linkage also can be used for connecting a damper operator. The damper is set so that the crankarm moves through a 90-degree angle to bring the economizer dampers from full open to full close (see Figure 45). Access to the actuator and linkage is from the filler section. Mechanical stops are placed in the crankarm mounting bracket. Do not remove stops. Driving the crankarm past the stops results in damage to the linkage or damper. The unit ships with a shipping bolt securing the linkage crankarm. Remove shipping bolt before use.
Note – For good airflow control, adjust linkages so damper
blades do not open beyond 70 degrees. Opening a damper blade beyond 70 degrees has little effect on its airflow. Do not “over close” low leak damper blades. The edge seal should just lightly contact the adjoining blade. The blades will lock up if they are closed so far the seal goes over center.
Outside
Air
Shaft .500 Dia.
x 1.50 Long
OA
Open
90°
Stroke
.75
RDS 800C & 802C
.25
3.00
OA
Closed
OA
Closed
.500 (13mm) Dia. Shaft
x 1.30" (33mm) Long
RAH 047C - 077C
90°
Stroke
OA
Open
.25" (6mm)
40 McQuay IM 487-5
Mechanical Installation
Intake Hood Damper (0% to 100% outside air, RAH 47–77 only)
Units requiring 100% outside air are provided with a rain hood and dampers that can be controlled by a single actuator. The actuator provides two-position control for opening the dampers fully during unit operation and closing the dampers during the off cycle. No unit mounted exhaust dampers are provided.
Intake Hood Damper (0% to 30% outside air)
These dampers are intended to remain at a fixed position during unit operation, providing fresh air quantities from 0 to 30% of the total system airflow, depending on the damper setting. This setting is made at the linkage rod on units with manually adjustable linkages.
On units provided with MicroTech II controls, the damper position may be set at the controller keypad. During unit operation, the two-position actuator drives the damper to the position set on the keypad. During the off cycle, the damper is automatically closed.
No unit-mounted exhaust dampers are provided with this option.
Figure 47: Intake hood damper adj., 0% to 100% outside air
Airflow
Figure 46: Intake hood damper, 0% to 30% outside air
A i r f l o w
3 . 1 5 " ( 8 0 m m ) M a x . S t r o k e o f D a m p e r L i n k a g e B a r
OA
closed
Note – Figure 46 shows the RAH 47–77 (The linkage is on the
RH side). The RDS 800–802 are the same except the linkage is on the LH side.
90
stroke
OA
open
.25" (6mm)
McQuay IM 487-5 41
Mechanical Installation
)
Mixing Box (RAH 47–77 only)
This section uses an outside air damper and a return air damper. Using these dampers allows outside air to blend with return air. Synchronized operation of the dampers is accomplished by interconnecting rods. As one damper section opens, the other section is closed. A total of 100% cfm is always drawn from this section. Damper positioning can be manually or automatically adjusted. With a field-installed controller, automatic operation can be obtained.
Figure 48: Mixing box
OA
CLOSED
These dampers provide a similar function to economizer dampers. This option differs from an economizer in that no unit mounted exhaust dampers are provided.
Note – For good airflow control, adjust linkages so damper
blades do not open beyond 70 degrees. Opening a damper blade beyond 70 degrees has little effect on its airflow. Do not “over close” low leak damper blades. The edge seal should just lightly contact the adjoining blade. The blades lock up if they are closed so far that the seal goes over center.
90°
STROKE
OA
OA
CLOSED
OPEN
.25" (6 mm
OA
OPEN
.75"
(19 mm)
3.00"
(76 mm)
42 McQuay IM 487-5
Face and Bypass Dampers
Face and bypass dampers are available in a flat arrangement for use with heating coils and standard face area cooling coils, as well as a staggered arrangement for large face area cooling coils. The damper sets are linked through a jack shaft for connection to a single actuator (factory or field installed).
Figure 49: Face and bypass dampers, RDS 800–802 only
Mechanical Installation
Airflow
Face Dampers Open
Face and Bypass Damper
.75"
(19mm)
90°
Stroke
3.00"
(76mm)
Face Dampers Closed
McQuay IM 487-5 43
Mechanical Installation
Figure 50: Face and bypass dampers, staggered arrangement–RAH 47–77 only
Face Damper
Open
(19mm)
.75"
90°
Stroke
.25"
(6mm)
3.00"
(76mm)
Closed
Airflow
Figure 51: Face and bypass dampers, flat arrangement—RAH 47–77 only
Optional
Contractor
Coil
Bypass Damper
Face and Bypass Damper
Extended Shaft
Face and Bypass Dampers
44 McQuay IM 487-5
Mechanical Installation

Cabinet Weather Protection

This unit ships from the factory with fully gasketed access doors and cabinet caulking to provide weather resistant operation. After the unit is set in place, inspect all door gaskets for shipping damage and replace if necessary.
Protect the unit from overhead runoff from overhangs or other such structures.
Recaulk field-assembled options such as external piping or vestibules per the installation instructions provided with the option.
CAUTION
Transportation, rigging, or maintenance can damage the unit’s weather seal. Periodically inspect the unit for leakage. Standing moisture can promote microbial growth, disease, or damage to the equipment and building.

Installing Ductwork

On bottom-supply/bottom-return units, if a McQuay roof curb is not used, the installing contractor should make an airtight connection by attaching field-fabricated duct collars to the bottom surface of either the roof curb’s duct flange or the unit’s duct opening. Do not support the total weight of the duct work from the unit or these duct flanges. See Figure 52.
discharge duct collars on a side discharge unit, remove the plenum section access door and the door gasketing.
Use flexible connections between the unit and ductwork to avoid transmission of vibration from the unit to the structure.
To minimize losses and sound transmission, design duct work per ASHRAE and SMACNA recommendations.
Where return air ducts are not required, connect a sound-absorbing T or L section to the unit return to reduce noise transmission to the occupied space.
WARNING
Mold can cause personal injury. Materials such as gypsum wall board can promote mold growth when damp. Such materials must be protected from moisture that can enter units during maintenance or normal operation.
Ductwork exposed to outdoor conditions must be built in accordance with ASHRAE and SMACNA recommendations
and local building codes
.
NOTICE
Installer must provide access in the ductwork for plenum-mounted controls. Once duct work is installed in units with side discharge, access to plenum-mounted components is difficult.
Units with optional back return, side discharge, or end discharge all have duct collars provided. To expose the
Figure 52: Installing duct work
U n i t D u c t O p e n i n g
9 . 7 6 "
F l e x i b l e
C o n n e c t o r
D u c t w o r k
D u c t F l a n g e r i n R o o f C u r b
U n i t B a s e
4 . 5 8 "
R o o f C u r b
McQuay IM 487-5 45
Mechanical Installation

Installing Duct Static Pressure Sensor Taps

For all VAV units, field install and connect duct static pressure taps to the pressure sensors in the unit. Sensor SPS1 is standard; additional sensor SPS2 is optional. These sensors are located in the main control panel (see “Control Panel” on page
5).
Carefully locate and install the duct static pressure sensing tap. Improperly locating or installing the sensing tap causes unsatisfactory operation of the entire variable air volume system. Below are pressure tap location and installation recommendations. The installation must comply with local code requirements
1 Install a tee fitting with a leak-tight removable cap in each
tube near the sensor fitting. This facilitates connecting a manometer or pressure gauge if testing is required.
2 Use different colored tubing for the duct pressure (HI) and
reference pressure (LO) taps, or tag the tubes. McQuay recommends 1/4" plastic tubing.
3 Locate the duct pressure (HI) tap near the end of a long
duct to ensure that all terminal box take-offs along the run have adequate static pressure.
4 Locate the duct tap in a nonturbulent flow area of the duct.
Keep it several duct diameters away from take-off points, bends, neckdowns, attenuators, vanes, or other irregularities.
5 Use a static pressure tip (Dwyer A302 or equivalent) or the
bare end of the plastic tubing for the duct tap. (If the duct is lined inside, use a static pressure tip device.)
6 Install the duct tap so that it senses only static pressure (not
velocity pressure). If a bare tube end is used, it must be smooth, square (not cut at an angle) and perpendicular to the airstream (see Figure 54).
7 Locate the reference pressure (LO) tap somewhere near the
duct pressure tap within the building (see Figure 53). If the reference tap is not connected to the sensor, unsatisfactory operation will result.
8 Route the tubes between the curb and the supply duct, and
feed them into the unit through the knockout in the bottom of the control panel (see Figure 53). Connect the tubes to appropriate barbed fittings in the control panel. (Fittings are sized to accept 1/4" plastic tubing.)
Figure 53: Static pressure tubing entrance location
St atic pressure
tubing
Figure 54: Pressure sensing tubing installation
Main Contr ol Panel
"HI line"
"LO" line
To Sensor "HI" input
Remote Sense Point
Ductwork
(Remote Location)
SPS1
Rubber Grommet
Tubing Extends thru Approx. 1/8"
Roof
To Sensor "LO" Input
Pressure Sensing Tubing
46 McQuay IM 487-5
Mechanical Installation

Installing Building Static Pressure Sensor Taps

If a unit has direct building static pressure control capability, you must field install and connect static pressure taps to pressure sensor SPS2 in the unit. This sensor is located at the bottom of the main control panel next to terminal block TB2.
Carefully locate and install the two static pressure sensing taps. Improper location or installation of the sensor taps causes unsatisfactory operation. Below are pressure tap location and installation recommendations for both building envelope and lab, or “space within a space” pressure control applications.
The installation must comply with local code requirements.
CAUTION
Fragile sensor fittings. If you must remove tubing from a pressure sensor fitting, use care. Do not use excessive force or wrench the tubing back and forth to remove; the fitting can break off and damage sensor.
Building Pressurization Applications
1 Install a tee fitting with a leak-tight removable cap in each
tube near the sensor fitting. This facilitates connecting a manometer or pressure gauge if testing is required.
2 Locate the building pressure (HI) tap in the area that
requires the closest control. Typically, this is a ground level floor that has doors to the outside.
3 Locate the building tap so it is not influenced by any source
of moving air (velocity pressure). These sources may include air diffusers or outside doors.
4 Route the building tap tube between the curb and the
supply duct and feed it into the unit through the knockout in the bottom of the control panel (see Figure 53). Connect the tube to the 1/4-inch HI fitting for sensor SPS2.
5 Locate the reference pressure (LO) tap on the roof. Keep it
away from the condenser fans, walls, or anything else that may cause air turbulence. Mount it high enough above the roof so it is not affected by snow. Not connecting the reference tap to the sensor results in unsatisfactory operation.
6 Use an outdoor static pressure tip (Dwyer A306 or
equivalent) to minimize the adverse effects of wind. Place some type of screen over the sensor to keep out insects. Loosely packed cotton works well.
7 Route the outdoor tap tube out of the main control panel
through a small field-cut opening in the edge of the control wiring raceway cover (see Figure 53 on page 46). Cut this “mouse hole” in the vertical portion of the edge. Seal the penetration to prevent water from entering. Connect tube to the 1/4-inch LO fitting for sensor SPS2.
Lab Pressurization Applications
1 Install a “T” fitting with a leak-tight removable cap in each
tube near the sensor fitting. This facilitates connecting a manometer or pressure gauge if testing is required.
2 Use different colored tubing for the controlled space
pressure (HI) and reference pressure (LO) taps, or tag the tubes.
3 Regardless whether the controlled space is positive or
negative with respect to its reference, locate the HI pressure tap in the controlled space (the setpoint can be set between –0.2 and 0.2" wc).
4 Locate the reference pressure (LO) tap in the area
surrounding the controlled space. Not locating the reference tap to the sensor results in unsatisfactory operation.
5 Locate both taps so they are not influenced by any source
of moving air (velocity pressure). These sources may include air diffusers or doors between the high and low pressure areas.
6 Route the building tap tube between the curb and the
supply duct and feed it into the unit through the knockout in the bottom of the control panel (see Figure 53).
7 Connect the tube to the 1/4-inch HI fitting for sensor SPS2.
McQuay IM 487-5 47

Electrical Installation

Electrical Installation

Field Power Wiring

All of the unit side panels are hinged. Do not mount disconnect switches and/or motor starters on panels that provide access to internal components. Wiring conduits can penetrate the cabinet bottom, base frame, or through the hinge and latch cap without interfering with the access panels.
Note – Seal all holes cut into the unit to prevent water leakage.
Seal conduits connecting the unit to external panels, which will be exposed to relative humidity and air pressure differentials. Ground the motor using copper or other corrosion resistant conductor.
Figure 55: Field power wiring
Access Panels
Hinge and Latch Cap
To p
overload. Before replacing a fuse, circuit breaker, MMP, or restarting a fan motor, identify the trouble and correct.
According to the National Electrical Code, a disconnecting means shall be located within sight of and readily accessible from the air conditioning equipment. The unit can be ordered with an optional factory mounted disconnect switch. This switch is not fused. Power leads must be over-current protected at the point of distribution. The maximum allowable overcurrent protection (MROPD) appears on the unit nameplate.
All RDS and RAH Units
All units are provided with internal power wiring for single or dual point power connection. The power block or an optional disconnect switch is located within the main control panel. Field power leads are brought into the unit through 3" knockouts in the bottom of the main control panel. Refer to the unit nameplate to determine the number of power connections. See Figure 56 and Table 12 on page 50.
WARNING
Hazardous voltage. Can cause severe injury or death. Disconnect electric power before servicing equipment. More than one disconnect may be required to de-energize the unit.
Bottom
Must Seal
Access Panel
Base Frame
Bottom
Wiring must comply with all applicable codes and ordinances. The warranty is voided if wiring is not in accordance with these specifications. An open fuse, tripped circuit breaker, or Manual Motor Protector (MMP) indicates a short, ground, or
If the unit has a factory mounted disconnect switch, generally the switch must be turned off to open the main control panel door. However, the door can be opened without disconnecting power by following the procedure covered on page 114. If this is done, use caution since power is not removed from the unit or the controller.
Note – To wire entry points, refer to certified drawings for
dimensions.
Figure 56: RDS and RAH power wiring connections
Electric heat control panel
Optional
disconnect
(DS3)
3" power
knockouts
Optional
disconnect (DS2)
Main disconnect (DS1)
or power block (PB1)
3" power
knockouts
48 McQuay IM 487-5
Electrical Installation
g
Figure 57: Optional side power wiring entrance
The preferred entrance for power cables is through the bottom knockouts provided on the unit. If side entrance is
M a i n C o n t r o l P a n e l
2 . 7 5 " ( 7 0 m m )
3 " ( 7 6 m m )
M a x D i a .
the only option, a drilling location is provided.
CAUTION
Wires are located in base rail. Move wires before drilling hole through base rail.
Follow the drilling dimensions exactly to prevent damage to the control panel. The dimensions provided are the only possible point of side entrance for the power cables.
1 6 "
10.0
C
B
( 4 0 6 m m )
Supply air opening
A
1.50 MPT drain
20.0
10.0
6.0
76.0
3.8
86.5
R e m o v e L i f t i n g B r a c k e t ( I f L o c a t e d H e r e ) B e f o r e D r i l l i n
H o l e
Figure 58: Typical power wire entrance, unit view—RDS 800C shown (actual opening shown on submittal documents)
3.8
94.0
E
Detail B
C
3.8
0.9 Dia. K.O. (Qty 4)
Bottom ret urn opening
24.3
Va r ie s
based on
options
17.7
22.3
12.9
15.3
3.0 Dia. K.O. (Qty 3)
6.8
11. 9
12.0
Reference from leaving air end of section
8.8
7.6
6.6
3.8
McQuay IM 487-5 49
Electrical Installation
All Units
The minimum circuit ampacity (wire sizing amps) is shown on the unit nameplate. Refer to Table 12 on page 50 for the recommended number of power wires.
Copper wire is required for all conductors. Size wires in accordance with the ampacity tables in Article 310 of the National Electrical Code. If long wires are required, it may be necessary to increase the wire size to prevent excessive voltage drop. Size wires for a maximum of 3% voltage drop. Supply voltage must not vary by more than 10% of nameplate. Phase voltage imbalance must not exceed 2%. (Calculate the average voltage of the three legs. The leg with voltage deviating the farthest from the average value must not be more than 2% away.) Contact the local power company for correction of improper voltage or phase imbalance.
CAUTION
Provide proper line voltage and phase balance. Improper line voltage or excessive phase imbalance constitutes product abuse. It can cause severe damage to the unit's electrical components.
A ground lug is provided in the control panel for each disconnect or power block. Size grounding conductor in accordance with Table 250-95 of the National Electrical Code.
In compliance with the National Electrical Code, an electrically isolated 115V circuit is provided in the unit to supply the factory mounted service receptacle outlet and optional unit lights. This circuit is powered by a field connected 15A, 115V power supply. Leads are brought in through a 7/8" knockout in the bottom of the main control panel, near the power wire entry point.
Table 11: Multiple point power connection options
Number of
electrical
circuits
2
2
Disconnect
designation
DS2
DS1 Balance of unit Main control panel
DS3 Electric heat
DS1 Balance of unit Main control panel
Load
Supply and return fan
motors plus controls
Location
(see Figure 2 on
page 4)
Main control panel
Electric heat
control panel
Table 12: Recommended 3-phase power wiring to ensure disconnects and power blocks mate with power wiring
Wire
gauge
10 1 75 1 1/2 35
8 1 75 1 3/4 50 6 1 75 1 1 65 41 75 1 1 1/4 85 3 1 75 1 1 1/4 100 2 1 75 1 1 1/4 115
1 1 75 1 1 1/4 130 1/0 1 75 1 1 1/2 150 2/0 1 75 1 2 175 3/0 1 75 1 2 200 4/0 1 75 1 2 230
250 1 75 1 2 1/2 255 300 1 75 1 2 1/2 285 350 1 75 1 3 310 400 1 75 1 3 335 500 1 75 1 3 380
3/0 2 75 2 2 400 4/0 2 75 2 2 460
250 2 75 2 2 1/2 510 300 2 75 2 2 1/2 570 350 2 75 2 3 620 400 2 75 2 3 670 500 2 75 2 3 760 250 3 75 3 2 1/2 765 300 3 75 3 2 1/2 855 350 3 75 3 3 930
1.All wire sizes assume separate conduit for each set of parallel conductors.
2.All wire sizes based on NEC Table 310-16 for 75°C THW wire (copper). Canadian electrical code wire ampacities may vary.
3.All wire sizes assume no voltage drop for short power leads.
Qty./
pole
Insulation
rating
(°C)
No. of
conduits
Conduit
(trade size, in.)
For MCA
up to
(amps)
50 McQuay IM 487-5

Field Control Wiring

2
ol
c
ng
Electrical Installation
Units are available with several control arrangements which may require low voltage field wiring. Detailed descriptions of various field control wiring options and requirements are included in the “Field Wiring” section of Bulletin No. IM 696, “MicroTech II Applied Rooftop Unit Controller.” Refer to the unit wiring diagrams for additional installation information.
Wiring must comply with applicable codes and ordinances. The warranty is voided if wiring is not in accordance with these specifications.
All field control wiring connections are made at the class II terminal block TB2, which is located in the main control panel. Field wiring connections to the 115-volt receptacle and lights are made at terminal block TB7, which is also located in the main control panel. Refer to Figure 59 and “Control Panel” on page 5. Two 7/8" knockouts are provided for wire entry.
Figure 59: Field control wiring connections
Main control panel
4V field terminal
block (TB2)
Interconnecting wiring enters the air handler unit through 7/8" knockouts in the bottom of the main control panel. The interconnecting wiring is connected to TB4 in the air handler unit. Refer to Figure 60. A 7/8" knockout is also available in the end of the unit base as shown in Figure 59.
Note – If a single conduit containing 24V and 115V wiring is run
Figure 60: Interconnecting control wiring
above the roof line between the air handler and condensing units, install the 24V wiring as a NEC Class I wiring system.
Main ontrol
panel
TB4
DS2
PB1/DS1
To condensi unit
WARNING
Electrical shock hazard. Can cause severe injury or death.
Control wiring raceway cover (remove for access to harness from main contr box to unit-mounted control devices)
Connect only low voltage NEC Class II circuits to terminal block TB2. Reinstall and secure all protective deadfront panels when the wiring installation is complete.
McQuay IM 487-5 51

Preparing Unit for Operation

This bracket is added,
ns
a
Preparing Unit for Operation
WARNING
Moving machinery hazard. Can cause severe injury or death. Before servicing equipment, disconnect power and lock off. More than one disconnect may be required to de-energize unit.
Figure 61: RAH spring mount hold down fasteners
Hold-down fasteners
Hold-down fasteners

Spring Isolated Fans

Releasing Spring Mounts
The optional spring-mounted supply and return fans are locked down for shipment. Hold-down fasteners are located at each spring mount. Remove these fasteners before operating the fans. Figure 64 shows a typical spring mount. Note that the 3/8" hold-down bolt securing the fan base to the unit cross channel must be removed.
After removing the hold-down fasteners, rock the fan assembly by hand to check for freedom of movement.
Figure 62: Spring mounted hold-down fasteners, all units
Figure 63: Fan spring mount adjustment
Leveling screw
Spring mount
assembly
Cross
channel
* Grossly out-of-adjustment thrust restraints can affect this
dimension. Recheck after thrust restraints are adjusted.
Jam nut
Fan base
3/8" ± 1 /4" with fan running
Adjusting Spring Mounts
To change spring compression:
Loosen the .625-18 UNF hex nut.
Place some additional weight on the fan sled frame (use a lever to slightly compress the spring/or raise the sled) to allow the bolt to turn freely.
Place one or two drops of oil on the threads if needed. Use a wide, flat, blade socket drive bit with a recommended 1/2” drive handle. Ensure that as the slotted bolt is turned, the upper-rebound plate also turns. This action allows the bolt to compress/decompress the compression plate, while having the same affect on the spring. If the spring is compressed too much, lift the sled before turning. If the spring is not compressed enough, place weight on the sled corner to force it down before turning.
Re-adjust the position of the lower-rebound plate so that the sled has at lest 3/4” travel and no more than 1.25” travel.
Figure 64: Spring mount
and these 3/8" tie dow
are used for RDS 800C.
This bracket is added,
and these 3/8" tie downs
re used for RDS 800C.
52 McQuay IM 487-5
WARNING
Moving machinery hazard. Can cause severe injury or death. Start the fans for the first time according to the “Check, Test, and Start Procedures” on page 97. If this is not done, equipment damage, severe personal injury, or death can occur.

Relief Damper Tie-Down

Preparing Unit for Operation
Figure 66: Thrust restraint adjustment
Jam nut A
Nut B
Spring clip
Washer
Nut C
Fan bulkhead
Economizer sections with a 30" or 40" return fan have a relief damper that is tied down for shipping. Remove the two brackets and two screws before operation to allow free movement of dampers. Access is from inside the economizer section.

Adjusting Scroll Dampers

Two sets of scroll dampers are provided in the housing of the twin 15" x 6" supply fan to allow control of air volume to each fan wheel. At the factory, these dampers are fully closed, unrestricting airflow. If fan paralleling occurs, correct it by loosening the adjustment screw on top of the fan housing (see Figure 65) and slightly lowering the rod until air distribution between the fans is even.
Figure 65: Scroll damper adjustment
Adjustment assembly
Scroll damper
Jam nut A
Thrust restraint angle
Fan housing frame
Detail A
See Detail A
Thrust restraint adjustment (with fan off)
1. Loosen jam nuts A.
2. Turn nut C until spring cup and washer contact thrust restraint angle.
3. Turn nut B until spring is compressed by two turns of nut B.

Adjusting Supply Fan Thrust Restraints

4. Tighten jam nuts A.
Thrust restraints are provided when housed double-width fans are mounted on springs. After the spring mounts are adjusted for level operation when the fan is running, check the thrust restraints. With the fan off, set the adjustment nuts so the spring is slightly compressed against the angle bolted to the fan housing frame. Refer to Figure 66. When the fan is turned on, the fan moves back to a level position and the thrust restraint spring compresses.
McQuay IM 487-5 53
Preparing Unit for Operation

Adjusting Seismic Restraints

Spring-mounted supply air and return air fans can be ordered with factory-installed seismic restraints. The system consists of four snubbers, one located next to each spring isolator. These snubbers allow free movement of the fan assemblies during normal operation because normal operation does not cause fan movements that exceed .25" (6 mm). However, if an abnormal condition occurs, they restrain the fan assembly and limit movement to .25" (6 mm) in any direction.
The position the fan assumes during normal operation is determined by actual job site airflow and static pressure. Therefore, for proper operation, field adjust the seismic restraints as part of the normal “Check, Test and Start” procedure. When the fan is operating in a normal manner, there should be no contact between the snubber restrainer angle and the snubber neoprene bumper. However, in a “seismic event,” the snubber limits movement of the spring mounted fan assembly to .25" (6 mm) in any direction, thereby helping to prevent the fan from being tossed about and damaged, or causing damage.
When a seismic restraint is properly adjusted and the fan is operating normally, the neoprene center bumper is centered within the 2" (51 mm) diameter hole in the restrainer angle, and the restrainer angle is centered vertically between the flanges of the neoprene center bumper. This results in .25" (6 mm) clearance in all directions. When the fan is turned off, the restrainer angle may come to rest on the neoprene center bumper.
Figure 67: Cross section of seismic restraint
Fan base channel
Snubber restrainer angle
Adjust up or down or back and forth
Snubber neoprene
bumper
.25 (6 mm) gap
(fan running)
Snubber neoprene
bumper
Adjust in and out
The seismic restraint is adjustable in all directions. Vertical slots in the restrainer angle and horizontal slots in the blower base allow the restrainer angle to be adjusted up and down and back and forth. The neoprene center bumper is mounted on a slotted hole allowing in and out adjustment.
Removing the neoprene center bumper bolt allows removal, disassembly, and replacement of the neoprene components.
54 McQuay IM 487-5

Sequences of Operation

Sequences of Operation
The following sequences of operation are for a typical “C” vintage applied rooftop unit equipped with MicroTech II, an economizer, 3 to 1 turn down burner, variable frequency drives (VFD), a return air fan and an external time clock. These sequences describe the ladder wiring diagram logic in detail; refer to “Wiring Diagrams” on page 58 as you read them. Note that your unit’s sequences of operation may vary from those described here. Refer to the wiring diagrams supplied with the unit for exact information.
For detailed description of operation information relating to the MicroTech II controller's software, refer to the appropriate operation manual (see Table 1 on page 3). These manuals describe the various setpoints, parameters, operating states, and control algorithms that affect rooftop unit operation.

Power-up

When primary power is connected to the unit, 115VAC power is fed through control circuit transformer T1 and control circuit fuse F1C (line 168) to compressor crankcase heaters HTR-1, HTR-2, HTR-3 and HTR-4 (lines 815, 848, 820, and 853).
When system switch S1 (line 203) is closed, low voltage transformers T2 (line 203), T3 (line 301)and T9 (line 802) energize, and 115VAC power is supplied to the following:
Smoke detectors (lines 265 and 267)
Economizer actuator ACT3 (line 313)
M30A to energize the supply fan VFD (line 426)
M40A to energize the return fan VFD (line 430)
Heating control panel (line 603)
Compressor circuit switches CS1 and CS2 (lines 805 and
838)
Transformer T2 supplies 24VAC power to terminals 24V and COM on the main control board MCB (lines 207 and 208). Transformer T2 supplies 24VAC power to the following:
Switch S7 On-Auto-Off (line 217)
Enthalpy sensor OAE (line 250)
External time clock contacts (line 215)
External exhaust fan status contacts (line 257, VAV only)
Airflow interlock switch PC7 (line 228)
Dirty filter switches PC5 and PC6 (lines 242 and 247)
Duct high limit switch DHL (line 260, VAV only)
Gas furnace alarm relay R24 (line 225)
Freezestat switch FS1 (line 231, hot water or steam heat
only)
Smoke detectors SD1 and SD2 (line 237)
When the field supplied Cool Enable switch is in the OFF position, field wiring terminal TB2 105 de-energizes (line
220). Binary input MCB-BI3 de-energizes and the cooling is disabled. When the field supplied Heat Enable switch is in the OFF position, field wiring terminal TB2 106 de-energizes (line
223). Binary input MCB-BI4 de-energizes and the heating is disabled.
Note – Unit ships with factory installed jumpers between TB2 101
and 105 and between 101 and 106.

Fan Operation

When the main control board (MCB) commands the supply and return fans to start, the unit enters the Startup operating state. As a result, a 3-minute timer is set, output MCB-BO3 (line 307) energizes, and relay R26 energizes (line 306).
After the 3-minute timer expires, the unit enters the Recirc operating state. As a result, output MCB-BO1 energizes relay R67 (line 401). This gives a start signal to supply fan drive AFD10 (line 445). Four seconds after MCB-BO1 is energized, output MCB-BO2 energizes relay R68 (line 404). This gives a start signal to return fan drive AFD20 (line 445).
Within 120 seconds after the fans start, the controller expects airflow switch PC7 (line 228) to close and thus energize binary input MCB-BI6. (If MCB-BI6 does not energize, the controller assumes the fans did not start. It then shuts down the unit and generates an alarm.)
During the Recirc operating state, the outside air damper is held closed. The controller does this by energizing output MCB-BO5 (line 318). On VAV units, output MCB-BO12, the VAV box output, is also de-energized (line 309) during the Recirc state.
McQuay IM 487-5 55
Sequences of Operation
The supply fan adjustable frequency drive (AFD10) is modulated to maintain the duct static pressure setpoint. When energized, output MCB-BO14 (line 407) drives AFD10 toward increased capacity; MCB-BO13 (line 405) drives it toward decreased capacity. On VAV units or CAV units equipped with return fan capacity control, the adjustable frequency drive (AFD20) is modulated to maintain an acceptable building static pressure (using either VaneTrol logic or direct measurement of building pressure; see the appropriate OM for more information). When energized, output MCB-BO16 (line
409) drives AFD20 toward increased capacity; MCB-BO15 (line 411) drives them toward decreased capacity.
Note – If the inverter bypass switch S4 (lines426 and 430) is in
the bypass position, MMP30 and MMP40 (line 132 and
144) protect the fans from excessive current draw. If either the supply or return fan is drawing excessive current, one of the MMPs triggers an auxiliary contacts (line 426) and open the circuit, causing both fans to stop.

Economizer Operation

When the outdoor air is suitable for free cooling, the switch in enthalpy sensor OAE is in position “3” (line 252) energizing binary input MCB-BI11. When MCB-BI11 energizes, the economizer is enabled. (Note: If selected from the keypad, the enthalpy decision can be made based on outdoor temperature. In that condition, if the outdoor air temperature is less than or equal to the changeover set point, the economizer is enabled.) If cooling is required, the economizer dampers (ACT3) are modulated to maintain the discharge air temperature setpoint. When energized, output MCB-BO6 drives the outdoor air dampers toward the open position; MCB-BO5 drives them toward the closed (line 318). If the outdoor air dampers are wide open and more cooling is required, the dampers hold their positions and mechanical cooling is activated (see below).
When the outdoor air is not suitable for free cooling, the switch in enthalpy sensor OAE is in position “1,” de-energizing binary input MCB-BI11. (Alternatively, the outdoor air temperature is above the changeover setpoint plus the economizer changeover differential). When the economizer is disabled, the dampers are held at their minimum position.
56 McQuay IM 487-5

Heating

Sequences of Operation
Gas Furnace, Modulating Burner (3 to 1 turn down)
Refer to “Standard Mod, furnace control (1000 MBh)” on page 79 as you read this sequence of operation. Note that the gas furnace wiring diagrams supplied with the units include a detailed sequence of operation. Refer to the wiring diagram supplied with the unit for exact wiring and sequence of operation information.
When system switch S1 is closed, 115 V (ac) power is supplied to the furnace control circuit. If burner switch S3 and safeties HL22, HL23 are closed (line 603), terminal 5 (line 609) on the flame safeguard control (FSG) energizes as does the modulating gas valve VM1. If heating is enabled (MCB-BI4 is energized—line 223) and heating is required, the MCB-BO11 energizes relay R20 (line 413). The normally open R20 contacts (line 603) close, and if manual burner switch S3 and safeties HL22, HL23, FLC (high limit switch) (line 603), LP5, and HP5 are closed (optional, not shown on page 79), terminal 6 (line 618) on the flame safeguard control (FSG) energizes. FSG energizes terminal 4 to start the blower motor (BM) (line
609) through contactor M29 on large burners. If the blower is operational, air switch AS (line 621) closes and makes electrical continuity from FSG terminal 6 to 7. After a 90­second prepurge period, FSG terminals 8 (line 613) and 10 (line 621) energize. As a result, ignition transformer IT and pilot gas valve GV1 energize. The pilot flame ignites and is detected by FSG through flame rod FD (line 612). Upon detection of pilot flame after the 10-second trial for ignition period, the FSG de-energizes terminal 10 and energizes terminal 9 to energize main gas valves GV2 and GV3 (lines 617, 619) and low fire start relay R23 (line 624). The R23 contacts (lines 632 and 633) allow the MCB to modulate gas valve actuator VM1 as required to satisfy the heating demand.
Whenever the burner is operating, its firing rate is determined by the position of gas valve actuator VM1. This actuator modulates the butterfly gas valve and combustion air damper,
thus varying the furnace firing rate between 33% and 100% of full capacity. When the MCB-BO10 energizes (line 634), VM1 modulates toward open and the firing rate increases. When MCB-BO9 energizes (line 633), VM1 modulates toward closed and the firing rate decreases. When both MCB-BO10 and MCB-BO9 are open, VM1 holds its position and the firing rate remains constant.
When heating is no longer necessary, MCB-BO11 opens, de-energizing relay R20 and opening its contacts (line 603). As a result, the flame safeguard control de-energizes, all gas valves close, the combustion air blower motor stops, and gas valve actuator VM1 closes. If the furnace is warm enough to close it, the FLC fan controls switch (line 602) overrides supply fan start/stop output MCB-BO1 through R25 (line 402) and keeps the supply fan running until the furnace cools down (this might happen during night setback operation).
If the furnace overheats, the FLC high limit control (line 603) cycles the burner, preventing the furnace temperature from exceeding the limit control’s setpoint. When the furnace cycles off, low fire start relay R23 de-energizes. The normally closed R23 contacts (line 633) cause VM1 to drive to its minimum position, overriding MicroTech II control of VM1 via MCB-BO10 and MCB-BO9. Because relay R23 de-energizes whenever GV2 de-energizes, the burner always starts at low fire.
Safety Lockout
If the pilot flame does not ignite or the flame safeguard fails to detect its flame within 10 seconds, the flame safeguard control enters the “safety lockout” state. FSG terminals 4, 8, 9, and 10 de-energize and the burner shuts down. FSG terminal 3 energizes relay R24 (line 610). The R24 contacts (line 225) signal the controller that the problem exists by energizing the input to MCB-BI5. If a safety lockout occurs, manually reset the flame safeguard control.
McQuay IM 487-5 57

Wiring Diagrams

Wiring Diagrams
Legend
General Notes
1. Field wiring
2. Factory wiring
3. Shielded wire/cable
4. Main control box terminals
5. Auxilliary box
6. Field terminals
7. Plug connector
8. Wire/harness number
200/ H200
terminals
ID Description Standard location
CB11 Circuit breaker, evaporative
condenser fan(s)
CB20 Circuit breaker, return/
exhaust fan
CB60 Circuit breaker, energy
recovery wheel
CCB1, 2 Compressor control boards,
refrig. circuits
CPC Circuit board, main, micro
controller
CPR Circuit board, expansion,
micro controller
DAT Discharge air temperature
sensor DFLH Design flow lefthand sensor Return section DFRH Design flow righthand sensor Return section DHL Duct hi-limit Main control box DS1 Disconnect, total unit or cond/
heat DS2 Disconnect, SAF/RAF/
controls DS3 Disconnect, electric heat Electric heat box EAT Exhaust air temperature
sensor EFT Entering fan air temperature
sensor EHB1 Staged electric heat board Main control box ERB1 Energy recovery board Main control box ERM1 Energy recovery wheel motor #1Energy recovery section
ERM2 Energy recovery wheel motor #2Energy recovery section
Main/cond. control box
Main control box
Main control box
Main control box
Main control box
Main control box
Discharge section
Main control box
Main control box
Energy recovery section
Supply fan section
WN7
9. Wire nut/ID
ID Description Standard location
ACT3, 4 Actuator motor, economizer Economizer section ACT5 Actuator motor, discharge
isolation damper
ACT6 Actuator motor, return air
isolation damper
ACT7 Actuator motor, heat face/
bypass
ACT8 Actuator motor, cool face/
Bypass
ACT10, 11Actuator motor, exhaust
dampers
ACT12 Actuator motor, enthalpy
wheel bypass damper
AFD10 Adjustable frequency drive,
supply fan
AFD11 Adjustable frequency drive,
evap cond. fans
AFD20 Adjustable frequency drive,
return/exhaust fan
AFD60 Adjust. freq. drive, energy
recovery wheel(s) AS Airflow switch, burner blower Gas heat box BM Burner blower motor Heat section, gas C10 Power factor capacitors,
supply fan C20 Power factor capacitors,
return fan CB10 Circuit breaker, supply fan Main control box
Discharge section
Return section
Coil section, heat
Coil section, cool
Return section
Energy recovery section
AFD/supply fan section
Main/RCE control box
AFD/ret. ex. fan section
Energy recovery section
Supply Fan section
Return section
F1A, B Fuse, control circuit
transformer (T1), primary
F1C Fuse, control circuit
transformer (T1), secondary
F2 Fuse, control circuit
transformer (T2), primary F3 Fuse, burner blower motor Main control box FB31–40 Fuseblock, electric heat (top
bank) FB41–50 Fuseblock, electric heat (bot.
bank) FD Flame detector Heat section, gas FLC Fan limit control Heat section, gas FP1, 2 Frost protection, refrig. circuits Coil section, cool FS1, 2 Freezestat control Coil section, heat/cool FSG Flame safeguard Gas heat box GCB1 Generic condenser board,
refrig. circ. GFR1, 2 Ground fault relay Main control box GFS1, 2 Ground fault sensor Main control box GRD Ground All control boxes GV1 Gas valve, pilot Heat section, gas GV2 Gas valve, main/safety Heat section, gas GV3 Gas valve, redundant/safety Heat section, gas GV4–8 Gas valve, main, hi turn down Heat section, gas HL1–10 Hi-limits, pwr, elec heaters
(top bank) HL11–20 Hi-limits, pwr, elec heaters
(bot. bank) HL22 Hi-limits, gas heat (pre-filters) Supply fan section HL23 Hi-limits, gas heat (final filters) Final filter section HL31–40 Hi-limits, ctl. elec heaters (top
bank) HL41–50 Hi-limits, ctl. elec heaters (bot.
bank) HP5 Hi-pressure controls, gas Heat section, gas
Main control box
Main control box
Main control box
Electric heat box
Electric heat box
Main control box
Heat section, electric
Heat section, electric
Heat section, electric
Heat section, electric
58 McQuay IM 487-5
Wiring Diagrams
ID Description Standard location
HS1 Heat switch, electric heat
HS3 Heat switch, electric heat
HTR65 Heater, sump Evap. condenser section HTR66 Heater, vestibule Evap. condenser vestibule HUM1 Humidstat sensor Energy recovery section IT Ignition transformer Gas heat box LAT Leaving air temperature
LP5 Low-pressure control, gas Heat section, gas LR10 Line Reactor, supply fan Inverter bypass box LR20 Line reactor, return/exhaust
LS1, 2 Limit switch, low fire, high fire Gas heat box LT10–23 Light, cabinet sections Supply fan section M10 Contactor, supply fan Main control box M20 Contactor, return fan Main control box M29 Contactor, burner motor Gas heat box M30 Contactor, reversing, invertor
M31–39 Contactor, electric heat (top
M40 Contactor, reversing, Invertor
M41–50 Contactor, electric heat (bot.
M60 Contactor, energy recovery
MCB Microprocessor circuit board Main control box MJ Mechanical Jumper All control boxes MMP1–8 Manual motor protector,
MMP10 Manual motor protector,
MMP11–18Manual motor protector, cond.
MMP20 Manual motor protector, return
MMP21–28Manual motor protector, cond.
MMP30 Manual motor protector, invrtr.
MMP40 Manual motor protector, invrtr.
MMP51, 52, 53
MMP60 Manual motor protector,
MP1–6 Motor protector, compr.#1-6 On compressors OAE Outside air enthalpy sensor Economizer section OAT Outside air temperature
PB1, 2 Power block, power
PB3 Power block, power
PB9, 10 Power block, supply fan Junction box, split unit PB11, 12 Power block, power
PB19, 20 Power block, return/exhaust
PC5 Pressure control, clogged filter Pre filter section PC6 Pressure control, clogged final
PC7 Pressure control, proof airflow Supply fan section PC8 Pressure control, minimum
PM1 Phone modem Main control box PVM1, 2 Phase voltage monitor Main control box R20 Relay, Heat, gas/ steam/ hot
shutdown
deadfront interlock
sensor
fan
bypass, supply fan
bank)
Bypass, Return Fan
bank)
wheel
compressors
supply fan
fans, ckt#1
fan
fans, ckt#2
bypass, sup. fan
bypass, ret. fan Manual motor protector,
exhaust fan(s)
energy recovery wheel
sensor
distribution
distribution, electric heat
distribution
fan
filter
airflow
water
Main control box
Electric heat box
Energy recovery section
Inv. bypass/main cont. box
Inverter bypass box
Electric heat box
Inverter bypass box
Electric heat box
Main control box
Main/cond. control box
Main control box
Main/cond. control box
Main control box
Main/cond. control box
Inverter bypass box
Inverter bypass box
Prop exhaust box
Main control box
Economizer section
Main control box
Electric heat box
Main control box
Junction box, split unit
Final filter section
Coil section, cool
Gas heat/main cont. box
ID Description Standard location
R21, 22 Relay, heat, gas (hi-turn
down) R23 Relay, heat, gas & electric Gas/electric heat box R24 Relay, heat alarm, gas Main control box R25 Relay, heat, gas, start supply
fan inverter R26 Relay, isol/exh. dampers,
open/close R28 Relay, isolation damper,
safety R29 Relay, remote fire alarm Main control box R30 Relay, cool valve with face
bypass R45 Relay, UV lights Main control box R46, 47 Relay, supply fan inverter,
incr/decr R48, 49 Relay, return fan inverter, incr/
decr R58,59 Relay, heat wheel inverter,
incr/decr R60 Relay, energy recovery wheel,
enable R61 Relay, smoke detector,
discharge air R62, 63, 65Relay, use on specials Main control box
R66 Relay, smoke detector, return
air R67 Relay, supply fan, enable Main control box R68 Relay, return fan, enable Main control box R69 Relay, Inv. bypass VAV box
interlock R70–79 Relay, use on specials Main control box RAE Return air enthalpy sensor Return section RAT Return air temperature sensor Return section REC1 Receptacle, main box Main control box REC3 Receptacle, field power, 115V Discharge bulkhead REC10–23Receptacle, cabinet sections Cabinet sections
S1 Switch, system on/off Main control box S3 Switch, furnace on/off Gas heat box S4 Switch, inverter bypass, on/ off Main control box S7 Switch, local on/auto/off to
controller S10–23 Switches, cabinet section
lights S40–45 Switches, door interlock, UV
lights SD1 Smoke detector, supply Discharge section SD2 Smoke detector, return Return section SPS1, 2 Static pressure sensors, duct/
building SR1-3 Sequencing relays, electric
heat T1 Transformer, main control
(line/115 V (ac) T2 Transformer, control input
(115/24 V (ac) T3 Transformer, control output
(115/24 V (ac) T4 Transformer, exh. damper
actuator (115/12 V (dc) T5 Transformer, electric heat Electric heat box T6 Transformer, dew point
controller (115/24 V (ac) T9 Transformer, refrig. circuit 24V Main control box TB1 Terminal block, internal Main control box TB2 Terminal block, field Main control box TB3 Terminal blocks, factory Main control box TB4 Terminal block, RFS, field Main control box TB7 Terminal block, 115V
convenience outlet, field
Gas heat box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
Cabinet sections
Cabinet sections
Main control box
Electric heat box
Main control box
Main control box
Main control box
Main control box
Main control box
Main control box
McQuay IM 487-5 59
Wiring Diagrams
ID Description Standard location
TB11 Terminal block, heat Heat control box TB25, 26,
27, 28 TD5–8 Time delay, part winding,
TD10 Time delay, hi turn down
TR1, 2 Transducer, pressure Main control box UV Ultra-violet light(s) Coil/discharge section VM1 Valve motor #1, heating Gas heat box/ heat section VM5 Valve motor #5, cooling Coil section, cool VV1 Vent valve, gas heat Heat Section, Gas ZNT1 Zone temp. sensor, setback Field installed
Terminal block, split unit junction box
compr #1 - 4
burner
Junction box, split unit
Main control box
Gas heat box
60 McQuay IM 487-5
Figure 68: Power package only, main power
Wiring Diagrams
100
101
102
103
104
ELECTRICAL
105
106
T2A
T1A
T1B
DS1
L1
SUPPLIED
CUSTOMER
CIRCUIT #1
107
108
T2B
L2
POWER
109
(Schematic continues on next page.)
T3A
T3B
GLG1
G
L3
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
McQuay IM 487-5 61
Wiring Diagrams
Figure 69: Power package only, main power, continued
+NB
SUPPLY-FAN
HSAF-1
T1
HSAF-2
MTR
T2
T3
HSAF-3
+NB
RETURN-FAN
T1
HRAF-1
MTR
HRAF-2
T3
T2
168C
T1_N
/4.00
/2.00/2.00
HRAF-3
567
8
GRD
T1
H4
X1X2
H3
H2
X3
T1L1
T3
M10
T2
426
L3
L2
(Schematic continues on previous page.)
M20
T1L1
T3
T2
431
L3
L2
H1
164A
162A
21
F1A
168B
21
21
F1C
F1B
T3A
T3B
T2A
T1A
T2B
T1B
L3A
L2B
L2A
139
138
T2-3
383940
426
L3B
108
T3-3
414243
44
45
MMP20
46
47
484950
MMP10
L1B
L1A
137
DS1
T1-3
35
36
37
T3A
T3B
T2A
T1A
T2B
T1B
426
162
DS1
T1-1
626364
164
T2-1
L3B
L3A
L2B
L2A
L1B
L1A
151
149
150
DS1
T1-5
108
T3-5
T2-5
51
52
53
54
55
565758
596061
123
4
TB1A TB1A
168A
666768
T1_115VAC
69
108
T3-1
65
62 McQuay IM 487-5
Figure 70: Power package only, control power
CUSTOMER SUPPLIED POWER
168C
204B
Wiring Diagrams
426221 256
114 54
TB2 TB2
227B
P20
+PP
5
2
4
115 VAC
REC1
201B 201C
TB7 TB7
102
H235-5
H237-4
H265-2
R63
17
1415GRD
16
TB1B
T2
1
4
24V
115V
CLASS 2
2
3
101112
203D
G
TB7
GND29
23
24
201D
G
N
TB1D
H
H N
13
TB1B
204A
219A
13
21
219
R63
DHL
SUPPLY AIR
SMOKE DETEKTOR
(24 VOLT SIGNAL FROM THE FIELD)
TB2
RETURN AIR
SMOKE DETEKTOR
(24 VOLT SIGNAL FROM THE FIELD)
21
S1
TB2 TB2 TB2
16
SD1
+NB
55
+PP
PL21
SD2
+NB
56 113 53
227A
H235-6
H 115
6
H265-1
H237-3
P20
1
+PP
3
228C 228D
+PP
+PP
PL11
PL11
6
5
2
H237-5
H267-2
17
16
H 115
6
H267-1
H237-3
1
+PP
PL21
3
228A 228B
+NB
ACT3
+PP
PL11
21
H313-2
WHT
(ECON/OADM)
BLK
H313-1
4/R-COM
+PP
86
H315-8
2-CW
1-CCW
H315-6
PL11
238A
+PP
H316-7
(Schematic continues on next page.)
238B
TB2
PL11
239A
7
TB2
(CLOSE) (OPEN)
(20VA PILOT DUTY MINIMUM CONTACT RATING)
67 68 69
TB2
/1.68 /1.68
168A
T1_115VAC T1_N
T2_115VAC
00010203040506070809101112131415161718192021222324252627282930313233343536373839404142
McQuay IM 487-5 63
Wiring Diagrams
Figure 71: Power package only, control power, continued
(Schematic continues on previous page.)
104108
TB2TB2
1413
426
M10
26OA 260B
(S.A. FAN AUX CONTACT)
TB2TB2
R63
76
256A 256B
105106
219
(DUCT HI-LIMIT)
NOTE: THESE CONTACT ARE FOR USE IN A 24 VOLT A.C. CLASS #2 CIRCUIT.
44454647484950515253545556575859606162636465666768
69
64 McQuay IM 487-5
Figure 72: VAV fan power (with SAF and RAF VFDs and manual bypass)
+NB
SUPPLY-FAN
HSAF-1
Wiring Diagrams
MTR
T1
T3
T2
HSAF-2
HSAF-3
PB11
109A
T1
T3
M30B
MMP30
T2
L1
L3
L2
135B
134B
133B
T3A
T3B
T2A
T1A
T2B
T1B
L3B
L3A
L2B
L2A
L1B
L1A
+BB
L3B
L3A
L2B
L2A
L1B
L1A
+BB
111A
110A
T1
T3
427
+BB
426
T2
134A 138A 138B
425
L3
L2
V2
W2
GND
V1
W1
H140
C2
B2
C1
B1
135A 139A 139B
GND10
G
M30I
L1
U2
440
+NB
AFD10
U1
A2
+BB
LR10
A1
133A 137A 137B
(Schematic continues on the next page.)
H139
H137
H138
T2
T1
T3
CB10
L3L3
L1L1
L2L2
T3A
T2A
T1A
DS2
CIRCUIT #1
ELECTRICAL
107
108
T1B
L1
SUPPLIED
CUSTOMER
109
T2B
L2
POWER
110
T3B
GLG1
G
L3
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
PB11
139
138
137
109
L3-3
L2-3
L1-3
137
138
139
140
141
142
McQuay IM 487-5 65
Wiring Diagrams
Figure 73: VAV fan power (with SAF and RAF VFDs and manual bypass), continued
+NB
MTR
RETURN-FAN
T1
T3
T2
HRAF-1
HRAF-2
HRAF-3
168C
T1_N
/2.66
/8.00
/6.00
/4.00
/3.00
/2.00
T1
T3
M40B
MMP40
T2
L1
L3
L2
T3A
T3B
T2A
T1A
T2B
T1B
L3B
L3A
L2B
L2A
L1B
L1A
+BB
+BB
(Schematic continues on the previous page.)
T1
T3
+NB
M40I
AFD20
+BB
CB20
LR20
440
145A 149A 149B
H149
T2
430
L1
L3
L2
V2
W2
U2
GND
V1
W1
U1
H152
C2
B2
A2
C1
B1
A1
147A 151A 151B
146A 150A 150B
GND20
G
F1A
H151
H150
T2
T1
T3
L3L3
L1L1
L2L2
PVM1
162
203
3
2
1
164
163
H4
H3
H2
H1
164A
162A162
21
F1B
567
8
GRD
T1
X1X2
X3
168B
21
115T1/2.00
21
F1C
123
4
TB1A TB1A
432
+BB
426
151
149
143
144
145
146
147
148
PB11
149
150
109
L3-6
L2-6
L1-6
150
151
152
153
154
155
156
157
158
159
160
161
PB11
162
164
109
L3-1
L2-1
L1-1
163
164
165
166
167
168A
T1_115VAC
168
/8.00
/2.00
169
170
66 McQuay IM 487-5
Figure 74: Constant volume fan power (SAF and RAF)
106
1071081091101111121
1331341351361371381391401
)
L3B
L3A
L2B
L2A
L1B
L1A
PB11
SUPPLY-FAN
HSAF-1
T1
MTR
HSAF-2
T2
Wiring Diagrams
T3
HSAF-3
109A
T1
DS1
L1
CIRCUIT #1
ELECTRICAL
SUPPLIED
CUSTOMER
110A
T2
L2
POWER
T3
L3
111A
T1L1
T3
T2
M10
137A
138A
T2A
T1A
T1B
GLG1
G
MMP10
PB11
L2A
L1B
L1A
137
138
L1-3
13
426
L3
L2
139A
T3A
T3B
T2B
L3B
L3A
L2B
139
109
L3-3
L2-3
(Schematic continues on next page.
426
41
McQuay IM 487-5 67
Wiring Diagrams
Figure 75: Constant volume fan power (SAF and RAF), continued
MTR
RETURN-FAN
T1
T3
T2
HRAF-1
HRAF-2
HRAF-3
168C
T1_N
/2.00
/3.00
/4.00
/8.00
567
8
GRD
T1
H4
X1X2
H3
H2
X3
T1L1
T3
T2
M20
431
L3
L2
F1A
T3A
T3B
T2A
T1A
T2B
MMP20
PB11
T1B
426
L3B
L3A
L2B
L2A
L1B
L1A
151
149
150
109
L3-6
L2-6
L1-6
PB11
(Schematic continues on the previous page.)
162A
162
H1
168B
164A
21
F1B
21
21
F1C
123
4
TB1A TB1A
164
109
L3-1
L2-1
L1-1
168A
/8.00
/2.00
T1_115VAC
144
145
146
147
148
149
150
151
152
161
162
163
164
165
166
167
168
169
170
68 McQuay IM 487-5
Wiring Diagrams
8
N
Figure 76: VAV control inputs
168C
SENSOR)
(RETURN AIR
H224-2
DRN-4
2
225C
224C
BLK
DRN
214B
SENSOR)
(OUTDOOR AIR
OAT
+NB
C
A
H227-2
H226-1
4
1
PL3
+PP
227C
226C
WHT
BLK
DRN-4
2
227D
DRN
TEMPERATURE)
(ENTERING FAN
EFT
+NB
H228-1
H229-2
4
PL5
1
+PP
229C
228C
WHT
BLK
+NB
DRN-4
2
230C
DRN
DFRH_DS
3
H230-3
4
+PP
PL22
SIDE)
(DRIVE
1
2
H232-2
DRN-4
H231-1
1
2
3
4
233C
232C
231C
RED
WHT
BLK
DRN
G
5V+
5VDC
PWR
PWR SUP
H
5V-
204B
1415GRD
1610
TB1B
T2
1
4
24V
115V
CLASS 2
2
3
111213
TB1B
23
24
DISPLAY
KEYPAD
208C
209C
WHT
N2+/8.06
210C
BLK
TO CCB1
N2-/8.06
REF/8.07
210D
DRN
214A
+NB
SPACE
ZNT1
ZONE OR
3
OVERRIDE
120
TB2
WHT
BLK
SENSOR
EXTERNAL RESET
TEMPERATURE
DISCHARGE AIR
4
REQ'D FOR NIGHT SETBACK OR SPACE RESET
121
132
GRD
133
219C
218C
217C
DRN
WHT
BLK
SENSOR)
(DISCHARGE AIR
RAT
+NB
DAT
+NB
C
A
DRN-4
H221-2
H220-1
H223-1
4
PL1
1
PL2
+PP
1
+PP
2
GRD
223C
221C
221D
220C
DRN
WHT
WHT
BLK
DRN
115T1/1.68
TB1D
24VAC
J1
COM
REF
N2-
N2+
204A
MCB
BCNT
COMM. CARD
BACNET-MSTP
REF
N2-
N2+
MICROPROCESSOR CONTROL BOARD
WHT
BLK
DRN
211A
210A
209A
168B
21
F3
43
203
S1
PVM1
S1
203A
54
156
21
200
TB2
BACnet MSTP
128
connection shown.
129
LON and BACnet IP
GRD
wiring not shown.
201A 200A
S1/6.00
INPUT
ANALOG
RS232 PORT
P1
BINARY
OR UNOCCUPIED
SHOWN IN NIGHT
A (DB9-MALE) CONNECTION
IS LOCATED ON DEADFRONT
+NB
CONN.
SERIAL
RS-232
1
AI1
NJ=VDC
3=NTC
2=MA
1=RTD
SW1
1
INPUT
BI1
215A 215C
102
TB2
3
MODE
TIME_CLOCK
NOTES TO FIELD:
1. REFER TO I.M. FOR
2
1C
3
2
1=RTD
NJ=VDC
1
v t
#1
R
BI2
AUTO
OFF
ON
1
2
S7
MANUAL_ENABLE
MUST NOT BE
CONFIGURATION.
TERMINALS 101 & 102
MICROTECH II ALARM
INTERNAL TIME CLOCK,
2. TO ENABLE SOFTWARE
AI2
2C
2
3=NTC
2=MA
13
v t
SW1
#2
2
217A
104
TB2
TB2
JUMPERED
ENABLE SWITCHES
INSTALLING COOL/HEAT
JUMPERS WHEN
THE FIELD TO REMOVE
3.
3
AI3
3C
3
2
NJ=VDC
3=NTC
2=MA
1=RTD
1
SW1
#3
3
BI3
220
105
TB2
COOL_ENABLE
101
v t
R
TB2
4
AI4
3
2
NJ=VDC
3=NTC
2=MA
1=RTD
1
SW1
4
BI4
223
106
TB2
HEAT_ENABLE
101
TB_101
5
4C
NJ=VDC
3=NTC
2=MA
1=RTD
v t
#4
5
BI5
225A
111
TB2
DURING NORMAL OPERATION
CONTACT MUST BE OPEN
35
610
R24
GAS HEAT ALARM
6
AI5
2
SW1
AI6
5C
3
1
2
NJ=VDC
3=NTC
2=MA
1=RTD
v t
SW1
#5
6
R
BI6
228A
108
TB2
+PP
PL15
PC7
+NB
12
AIR FLOW
H228-4 H228-1
41
+PP
PL15
7
AI7
NJ=VDC
1=RTD
231A
7
2=MA
3=NTC
2
SW1
BI7
7C
13
v
t
#7
(Schematic continues on next page.)
6C
3
1
v t
#6
112
TB2
3/Y1/R
FS1
+NB
H231-1 H231-3
101
TB_101
TB2
/1.68 /1.6
168A
T1_115VAC T1_
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
McQuay IM 487-5 69
Wiring Diagrams
Figure 77: VAV control inputs, continued
445
445
204B
SIG_SD/2.41
313
ACT3
+NB
+PP
PL23
DFLH_ODS
DRN-4
H234-2
4
234C
SIDE)
(OPP
DRIVE
1
3
2
H235-1
H236-3
1
2
3
214B
236C
235C
+NB
(OP)CW(CL)
CCW
7
8
4
H239-3
DRN-9
H240-4
+PP
PL11
9
3
240C
214B
238C
H243-4
H241-5
5
4
+PP
PL18
241C
214B
107
TB2
24VCOM/2.51
VM1
+NB
(OP)
CW
(CL)
CCW
T
Y
G
H244-2
H245-3
DRN-1
1
3
2
4
131
TB2
+S
PWRCOM
+NB
SHS1
SPS1
(DUCT STATIC
SPACE
SENSOR
HUMIDITY
OUT
(0-5V)
126
PRES SENSOR)
-
127
GRD
440
+NB
AFD10
7+
500HOM
H262-8
H261-10
PL7
+PP
10813
8-
DRN-13
440
+NB
AFD20
7+
8-
500HOM
DRN-3
H264-6
H265-8
PL8
+PP
683
TB2
266C
265C
264C
263C
262C
244C
245C
246C
252C
253C
254C
257C
261C
WHT
BLK
RED
WHT
BLK
DRN
RED
WHT
BLK
DRN
WHT
RED
BLK
DRN
WHT
BLK
DRN
DRN
INPUT
OPEN ANALOG
8
AI8
8C
2
3=NTC
1=RTD
NJ=VDC
2=MA
1 3
v
t
SW1
#8
R
8
BI8
113
237A
TB2
(Schematic continues on previous page.)
PL20
+PP
+PP
PL20
5
H237-4
H235-5
17
16
235A
265267
6
SD1
+NB
H237-3
+PP
PL21
6
35
+PP
PL20
H237JMP
H235-6
+PP
PL21
H237-5
17
16
6
SD2
+NB
H237-3
+PP
PL21
3 4
9
NJ=VDC
AI9
9C
2
3=NTC
1=RTD
2=MA
1 3
v
t
SW4
#9
FILTER
FOR FIELD
INDICATION
243A
10
AI10
10C
2
3=NTC
1=RTD
NJ=VDC
2=MA
1 3
v
t
SW4
#10
9
BI9
11
AI11
11C
3
2
NJ=VDC
3=NTC
2=MA
1=RTD
1
v
t
SW4
#11
10
R
BI10
NJ=VDC
12
3=NTC
1=RTD
2=MA
11
13
AI12
12C
2
1=RTD
NJ=VDC
2=MA
1 3
15V DC
v
t
SW4
#12
12
R
BI11
BI12
252A
109
SIG_SD/2.38
TB2
242A
1
3
+PP
PL14
24VCOM/2.47
204B
+PP
+PP
2
PL13
PL13
204B
H252-2
H242-3
H243-1
2
87
R61
R66
3
87
PC5
1
+NB
PRE FILTER
H242-4
+PP
4
PL14
H250-4
1
3
TR1TR
OAE
+NB
+PP
HUM
2
+
SR
JPR
H25O-+
H252-1
H25O-SR
S
+
14
PL13
RAE
+NB
OPEN ANALOG
14
AI13
13C
2
3=NTC
1=RTD
NJ=VDC
2=MA
1 3
v
t
SW4
#13
13
BI13
257A
103
TB2
EXS
+NB
EXTERNAL EXHAUST SWITCH
(SHOWN WITH FAN IN OFF POSITION)
INPUT
AI14
3=NTC
R
WHT
BLK
DRN
WHT
BLK
DRN
15
14C
2
1 3
SW4
3=NTC
1=RTD
NJ=VDC
2=MA
3=NTC
1=RTD
NJ=VDC
2=MA
v
t
#14
14
BI14
260A
31
DHL
16
AI15
2
2
1 3
1 3
SW4
SW4
AI16
15C
v
v
t
t
#15
#15
15
16C
2
2
3=NTC
1=RTD
NJ=VDC
2=MA
3=NTC
1=RTD
NJ=VDC
2=MA
1 3
1 3
v
v
t
t
SW4
SW4
#16
#16
16
R
BI15
BI16
168C
T1_N
/1.68
+PP
+PP
PL21
21
2
PL20
H265-2
H267-2
115
115
SD1
SD2
+NB
+NB
H
H
DUCT HI-LIMIT
SA SMOKE DETECTOR
RA SMOKE DETECTOR
H265-1
H267-1
1
+PP
+PP
PL21
PL20
203B
/8.01
/4.00
/3.00
T2_115VAC
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
70 McQuay IM 487-5
Wiring Diagrams
/1.68 /1.68
N
Figure 78: CV control inputs
168C
(RETURN AIR
RAT
H224-2
1
224C
AI4
2
3=NTC
SW1
4
223
TB_101
SENSOR)
BLK
4C
3
1
#4
106
DRN-4
2
225C
v t
214B
SIDE)
+PP
4
DFLH_ODS
+NB
DRN-4
PL23
234C
DRN
H234-2
4
BLK
(OPP
DRIVE
1
3
2
H235-1
H236-3
1
2
3
214B
236C
235C
RED
WHT
SENSOR)
(OUTDOOR AIR
OAT
+NB
C
A
H226-2
H226-4
H225-1
4
DRN
4
PL3
1
+PP
2
226C
227D
227C
WHT
BLK
DRN
DFRH_DS
+NB
SIDE)
(DRIVE
1
2
3
H232-2
H230-3
DRN-4
H231-1
1
2
+PP
3
PL22
233C
232C
231C
RED
WHT
BLK
DRN
INPUT
OPEN ANALOG
5
NJ=VDC
1=RTD
5
BI5
6
AI5
3=NTC
2=MA
SW1
AI6
5C
3
2
NJ=VDC
3=NTC
2=MA
1=RTD
1
v t
SW1
#5
6
R
BI6
7
AI7
NJ=VDC
7C
2
3=NTC
1=RTD
2=MA
13
v t
SW1
#7
7
BI7
6C
3
2
1
v t
#6
8
AI8
8C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v t
SW1
#8
R
8
BI8
1133113
TB2
TB2
PL21
235A
H235-6
H235-6
237A
PL20
+PP
+PP
5
H235-5
H235-5
17
265267
SD1
+NB
6
+PP
+PP
+PP
17
SD2
+NB
+PP
PL20
PL21
PL20
H237-4
H237-4
H237-3
H237-3
H237JMP
H237JMP
PL21
H237-5
H237-5
H237-3
H237-3
(Schematic continues on next page.)
16
6
35
16
6
3 4
228A
TB2
+PP
PL15
231A
108
112
TB2
+PP
3/Y1/R
TB_101
+NB
FS1
H231-1 H231-3
101
TB2
PC7
+NB
12
AIR FLOW
H228-4 H228-1
41
+PP
PL15
G
5V+
5VDC
PWR
PWR SUP
H
204B
GRD
14
15
1610
TB1B
T2
1
4
24V
115V
CLASS 2
2
3
111213
TB1B
23
24
TB1D
COM
24VAC
TO CCB1
N2+/8.06
N2-/8.06
REF/8.07
210D
210C
209C
DISPLAY
KEYPAD
WHT
BLK
DRN
208C211C
J1
REF
N2-
N2+
204A
MCB
BCNT
COMM. CARD
BACNET-MSTP
REF
N2-
N2+
MICROPROCESSOR CONTROL BOARD
WHT
BLK
DRN
128
129
GRD
TB2
54
PVM1
203A
21
S1
BACnet MSTP
connection shown.
LON and BACnet IP
wiring not shown.
5V-
A (DB9-MALE) CONNECTION
RS232 PORT
P1
IS LOCATED ON DEADFRONT
CONN.
SERIAL
RS-232
+NB
3
214A
TB2
BLK
INPUT
ANALOG
NJ=VDC
1=RTD
INPUT
BINARY
215A 215C
TB2
MODE
OR UNOCCUPIED
SHOWN IN NIGHT
+NB
TIME_CLOCK
ZNT1
1
2=MA
1
NOTES TO FIELD:
ZONE
SENSOR
OVERRIDE
120
RED
AI1
3
2
3=NTC
1
SW1
BI1
102
ON
3
MICROTECH II ALARM
1. REFER TO I.M. FOR
4
121
1C
v t
#1
R
AUTO
S7
CONFIGURATION.
2. TO ENABLE SOFTWARE
SETPOINT
HEATING
COOLING &
6
132
217C
WHT
DRN
2
AI2
3=NTC
1=RTD
NJ=VDC
2=MA
SW1
2
BI2
217A
TB2
OFF
1
2
MANUAL_ENABLE
JUMPERED
MUST NOT BE
TERMINALS 101 & 102
INTERNAL TIME CLOCK,
THE FIELD TO REMOVE
3.
WALLSTAT
+PP
GRD
2C
2
13
v t
#2
104
COOL_ENABLE
101
TB2
ENABLE SWITCHES
INSTALLING COOL/HEAT
JUMPERS WHEN
C
PL2
220C
NJ=VDC
220
TB2
+NB
H220-1
WHT
3
2=MA
1=RTD
3
SENSOR)
(DISCHARGE AIR
DAT
A
H221-2
1
221C
BLK
AI3
3
2
3=NTC
1
SW1
BI3
105
+NB
H223-1
DRN-4
4
PL1
+PP
2
223C
222C
DRN
WHT
4
3C
NJ=VDC
2=MA
1=RTD
v t
#3
R
BI4
TB2
HEAT_ENABLE
101
TB2
168A
T1_115VAC T1_
000102
McQuay IM 487-5 71
03
04050607080910
11
1213141516
171819
202122
2324252627
282930
31
32
203B
3334353637
Wiring Diagrams
(Schematic
continues
on
previous
page
)
Figure 79: CV control inputs, continued
131
131
TB2
TB2
PWRCOM
PWRCOM
252
+NB
+NB
SHS1
SHS1
SPACE
SPACE
SENSOR
SENSOR
HUMIDITY
HUMIDITY
OUT
OUT
(0-5V)
(0-5V)
127
127
GRD
GRD
126
126
TB2
TB2
254C
253C
252C
WHT
BLK
DRN
WHT
BLK
DRN
DFRH_DS
+NB
+PP
3
H230-3
PL22
RED
(DRIVE
H231-1
3
231C
WHT
107
TB2
24VCOM/2.51
ACT3
+NB
DRN-9
PL11
238C
DRN
CCW
H239-3
9
214B
RED
313
(OP)CW(CL)
8
4
H240-4
3
4
240C
WHT
7
H241-5
5
241C
BLK
SIDE)
4
+NB
+PP
DFLH_ODS
DRN-4
H234-2
4
PL23
234C
DRN
BLK
(OPP
DRIVE
1
3
2
H235-1
H236-3
1
236C
RED
+PP
3
214B
2
235C
WHT
SIDE)
1
2
H232-2
DRN-4
1
2
233C
232C
BLK
DRN
343
VM1
+NB
(OP)
CW
(CL)
CCW
8
7
4
H243-4
H244-2
H245-3
DRN-1
1
3
2
4
+PP
PL18
246C
245C
244C
214B
RED
DRN
WHT
BLK
.
INPUT
+PP
PL6
H247-4
+NB
+PP
PC6
PL6
NJ=VDC
BI10
4
2
H247-1
11
1=RTD
10
248A
H248-2
1
1
OPEN ANALOG
AI11
11C
3
2
3=NTC
2=MA
1
v
t
SW4
#11
NJ=VDC
NJ=VDC
12
AI12
2
2
3=NTC
1=RTD
2=MA
3=NTC
1=RTD
2=MA
13
13
SW4
SW4
11
BI11
252A
24VCOM/2.47
204B
+PP
+PP
2
3
+NB
FINAL FILTER
+PP
2
PL13
PL13
H252-2
H250-4
1
3
TR1TR
OAE
PL13
HUM
2
+
SR
JPR
H25O-+
H252-1
H25O-SR
S
+
14
RAE
+NB
NJ=VDC
9
AI9
9C
2
3=NTC
1=RTD
2=MA
13
v
t
SW4
#9
FILTER
FILTER
TB2
TB2
FOR FIELD
FOR FIELD
INDICATION
INDICATION
10
AI10
10C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v
t
SW4
#10
9
R
BI9
243A
109
109
242A
1
1
3
+PP
PL14
H242-3
H242-3
H243-1
H243-1
2
3
PC5
1
+NB
PRE FILTER
H242-4
H242-4
+PP
4
PL14
7
AI7
7C
2
3=NTC
1=RTD
NJ=VDC
2=MA
231A
13
v
t
SW1
#7
7
BI7
112
TB2
3/Y1/R
FS1
+NB
H231-1 H231-3
101
204A
TB_101
TB2
8
AI8
8C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v
t
SW1
#8
235A
H235-6
H235-6
8
BI8
113
113
237A
PL20
+PP
+PP
PL20
5
H237-4
H237-4
H235-5
H235-5
17
16
265267
6
SD1
+NB
H237-3
H237-3
6
35
3
+PP
+PP
PL20
H237JMP
H237JMP
+PP
PL21
H237-5
H237-5
17
16
6
SD2
+NB
H237-3
H237-3
+PP
PL21
3 4
R
TB2
TB2
+PP
PL21
INPUT
253 253
253 253
OPEN ANALOG
13
12C
#12
#12
AI13
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
15V DC
v
v
t
t
SW4
12
R
BI12
INPUT
OPEN ANALOG
14
AI14
13C
v
t
#13
14C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v
t
SW4
#14
R
13
BI13
INPUT
OPEN BINARY
INPUT
OPEN ANALOG
15
AI15
15C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v
t
SW4
#15
15
14
BI14
INPUT
INPUT
OPEN ANALOG
16
AI16
16C
2
3=NTC
1=RTD
NJ=VDC
2=MA
13
v
t
SW4
#16
16
R
BI15
BI16
168C
T1_N
/1.68
OPEN BINARY
+PP
+PP
PL21
21
2
PL20
H265-2
H265-2
H267-2
H267-2
115
115
SD1
SD2
+NB
+NB
H
H
SA SMOKE DETECTOR
RA SMOKE DETECTOR
H265-1
H265-1
H267-1
H267-1
1
+PP
+PP
PL21
PL20
203B
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
/3.00
T2_115VAC
267
268
269
72 McQuay IM 487-5
/8.01
Figure 80: Control actuator outputs (CV, stream, or hot water, plus economizer)
364 362
168C
T1_NT2_115VAC
/1.68/2.68
2 COILS
EXCEED 15 VA
MUST HAVE 24VAC CLASS
MOUNTED RELAYS CAN NOT
THE TOTAL VA OF THE FIELD
NOTES TO FIELD:
1. ALL FIELD MOUNTED RELAYS
117115
TB2TB2
R26
2.
102
Wiring Diagrams
(EXT_ALARM_SIGNAL)
T3
1
4
24V
115V
CLASS 2
303A 303B
TB1C TB1C
305A
1819 20 21
jprs
24V SRC
4NO4
BO4
2
3
MCB
207
SOURCE 1-8
WIRED INTERNAL
TO MOTHERBOARD
(FAN_OPERATION)
116
TB2
307A
jprs
24V SRC
3NO3
BO3
207
207
MCB
1-8
SRC
/4.00 /4.00
T3_24V T3_COM
+NB
+PP
+PP
239
ACT3
PL11
H313-2
H313-1
PL11
+PP
PL11
86
21
6NO6
BO6
207
PL11
(OPEN)
MCB
jprs
24V SRC
318A
5NO5
BO5
207
(CLOSE)
MCB
jprs
24V SRC
(Schematic continues on next page.)
H315-8
L2
3-CCW
+PP
H316-7
7
X-COM
(ECON/ACT)
L1
2-CW
H315-6
+PP
PL11
315A 315B
203B
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
McQuay IM 487-5 73
Wiring Diagrams
Figure 81: Control actuator outputs (CV, stream, or hot water, plus economizer), continued
jprs
24V SRC
B09
(CLOSE)
+PP
PL18
H343-9
9
jprs
24V SRC
10NO10 9NO9
B10
207 207
(OPEN)
MCB M CB
339A 339C
(Schematic continues on previous page.)
+NB
243
VM1
+PP
PL18
+PP
5
87
PL18
H343-5H343-6
H344-8
L2
3-CCW2-CW
HEAT
X-COM
L1
H344-7
PL18
+PP
+PP
PL18
6
SIDE)
RELIEF
DAMPER
(OPP.DR
+NB
ACT11
BLK
WHT
H969
H968
5555555
6666666
H365-1
H366-3
3
1
+PP
PL17
363B
6
7
11
R26
9
5
R26
306
306
362A 362B
33
TB1F
8
TB1F
+NB
SIDE)
(DRIVE
RELIEF
DAMPER
ACT10
WHT
BLK
H965
H964
T4
X2
L2
12V
115V
X1
L1
368A
367A
35
34
TB1F
TB1F
AC
AC
-+ DC
RECTIFIER
RECT
36
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
74 McQuay IM 487-5
Figure 82: VFD control (SAF and RAF)
/1.68/2.68 /3.11 /3.11
427 445
T1_NT2_115VAC
432 445
168C
Wiring Diagrams
631603
445
137
PL7
+PP
2
309
445
133
149
145
PL8
+PP
11
303B
102
R67
102
H1C
R46_47
H1DN
447
H1UP
R68
R48_49
H1DN
H1C
447
+PP
PL18
H1UP
C3C1
R20
+GB
A2A1
+BB
+BB
M30I
M30B
I
H427-9
H425-12
PL7
+PP
PL7
+PP
12
H425-2
H429-11
A2A1
I
R69
9
A2A1
+BB
M40I
87
H429-10
PL8
+PP
A2A1
+BB
M40B
I
I
H431-7
PL8
+PP
7
10
427B
35
604
R25
409A
407A
405A
1NO1
207
SUPPLY FAN
404A
jprs
jprs
jprs
BO2
MCB
24V SRC
2NO2
207
RETURN FAN
24V SRC
BO13
MCB
24V SRC
14NO14
13NO13
BO14
207
207
SAF DECR
MCB
SAF INCR
jprs
jprs
24V SRC
15NO15
BO16
BO15
207
RAF DECR
MCB
MCB
401A
jprs
24V SRC
BO1
MCB
411A
24V SRC
H413-7 H413-6
+PP
76
PL18
413A
jprs
24V SRC
16NO16
11NO11
BO11
207
207
RAF INCR
HEAT ENABLE
MCB
425A
INVERTER
S4
1NC
AIR
SUPPLY
426B
PL8
+PP
13
401
R67
429A
427A
1NO
BYPASS
INVERTER
1C
S4
SIG_1/6.01
2NC
AIR
RETURN
13
404
R68
431A 431B
2ND
BYPASS
2C
46
(Schematic continues on next page.)
H426-4H426-6H426-3
+BB
MMP40
H426-1
PL8
1
+BB
+PP
426A
PL7
+PP
MMP30
PL7
+PP
12(32)11(31) 12(32)11(31)
3
133 145
T3_24V T3_COM
45 42
TB2 TB2
SOURCE 9-16
WIRED INTERNAL
TO MOTHERBOARD
MCB
9-16
SRC
207
303A
203B
00
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
McQuay IM 487-5 75
Wiring Diagrams
Figure 83: VFD control (SAF and RAF), continued
149
264
14
9
1216
RAF
+NB
AFD20
ABB401
10
8
1113
+PP PL8
H443-2
2
+PP PL8
H443-5
5
443H
H2DNH2VH2UP
DECRINCR
443G
409
35
R48_49
R66
76
404 241430
R68
445C 445D
PL8
+PP
15
H443C
+PP PL8
H443-12
12
+PP PL7
H443-1
137
261
14
9
(Schematic continues on previous page.)
1216
SAF
+NB
AFD10
ABB401
10
8
1113
1
+PP PL7
H443-4
4
H443A
H443-15
1413
+BB
M40I
443E
443D
H2DNH2VH2UP
DECRINCR
443C
405
351413
R46_47
R61M30I
76
401 239425
R67
445A 445B
PL7
+PP
14
H443-14
+BB
+PP
H443-7
7
PL7
443A
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
76 McQuay IM 487-5
Figure 84: Super Mod gas furnace control (1000 MBh)
Wiring Diagrams
402
H604-5
NB
+PP
PL19
T1_N
/1.68
168C
+MB
R25
TB11
5
87
604B
+PP
3
PL19
H604-3
10
TB11
RED_G602-L1
604A
L2
L4
FLC
L1
L3
RED_G603-L3
42
413
RED_G602-L1
R20
5
7
1
S3
4
8
2
TB11
RED_G602-L2
10
11
607A
602A
8
9
TB11
H603-4
+PP
PL19
H602-2
603A 603B 603C
+PP
2
PL19
PL16
+PP
H603-2
426B
SIG_1/4.28
21 42
HL22
225
627
NB
TB11
31
R22
20202020202020
R24
+MB
87
WHITE
WHITE
WHTBLK
GV1A
1
+PP
PL19
BLACK
H610-1
1
BLKBLK
BM
6
19191919191919
GV1B
WHITE
WHITE
WHTBLK
WHTBLK
WHTBLK
GV4A
GV4B
BLACK
BLACK
BLACK
SEE THE PIPING SCHEMATIC BELOW
REQUIRED FOR YOUR BURNER SIZE
FOR THE NUMBER OF MAIN GAS VALVES
21212121212121
C2C1
R23
L2
L1
TB11
RED_G609-L WHT_G609-R
RED_G613-L
LS1
RED_G617-L WHT_G617-R
NOCOM
R23
5
31
625
TB11
3
BLACK BLACK
TB11
TB11
610A 610B
3
4
8
L2
613A 613B
611A
4K1
617A
9
2K2
621C
107
5K12K11K1
3K1
I
T
R
E
MICROCOMPUTER
M
FIER
FSG
AMPLI
FLAME
FSG-F
FSG-G
FD
(FLAME ROD)
(FLAME SAFEGUARD)
(PLUG-IN TYPE
CONTROLLER)
6
621B
NO
ASLS2
COM
621A
NO
COM
FSG
6K1
(L1)
5
2
TB11
632615
632628
C2C1
R21
IGNITION TRANSFORMER
X2
115V
6000V
X1
IT
4
2131
TD10
628A
42
612
R22
7
TB11
R21
10NO10
BO10
207
MCB
+MB
jprs
jprs
+MB
+PP
9
PL19
H632-9
24V SRC
24V SRC
9NO9
BO9
207
MCB
+PP
PL18
+PP
9
8
PL18
H633-9
H634-8
11
12
TB11
TB11
633A 633B
625
R23
R21
631A
5
R20
4
YEL_G632-R
VM1
VALVE
ACTUATOR
(FLOATING)
GAS & AIR
MODULATING
BLK WHT
RED_G630-B WHT_G630-W
628
634A 634B
5
4
6
628
5
46
632A 632B
413
6
YEL_G634-2
OPEN
2
CCW
G
(Schematic continues on next page.)
(CL)
YEL_G633-1
COM
CLOSE
1
R
(OP)
CW
T
Y
H603-1
1
+PP
PL16
S1/2.01
201A
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
(FSG) CONTROLLER.
COMBINATION VALVE WITH PRESSURE
LIGHTS ARE PART OF THE FLAMESAFEGUARD
IS THE SECOND VALVE OF A REDUNDANT
1.POWER, PILOT & MAIN VALVE INDICATION
2. GV-A IS THE FIRST VALVE AND GV-B
NOTE:
630
631
REGULATION AND MANUAL SHUTOFF
632
633
634
635
636
McQuay IM 487-5 77
Wiring Diagrams
Figure 85: Super Mod gas furnace control (1000 MBh), continued
(THRU 1/2 P.S.I.)
COCK
SHUTOFF
PIPING DIAGRAM
COCK
SHUTOFF
REG.
HIGH PRESS.
OVER 1/2 P.S.I.
WHEN 120 VOLT
(Schematic continues on previous page.)
SAFEGUARD (FSG). UPON A CALL FOR HEAT, THE CONTROL SYSTEM WILL CLOSE (BO#11) ON THE MAIN CTRL BRD (MCB), THUS ENERGIZING RELAY (R20).
WHEN THE ROOFTOP UNIT IS ENERGIZED 120 VOLT POWER IS SUPPLIED TO THE SYSTEM ON-OFF SWITCH (S1), TO BURNER ON-OFF SWITCH (S3) AND 24 VOLTS TO THE (BO#11)
POWER IS FURNISHED THROUGH THE SYSTEM ON-OFF SWITCH (S1), THROUGH THE BURNER ON-OFF SWITCH (S3), THROUGH RELAY (R20 CONTACTS, THROUGH THE HIGH LIMIT
CONTACTS ON THE MAIN CTRL BRD (MCB). BURNER ON-OFF SWITCH (S3) WILL POWER THE MODULATING GAS VALVE ACTUATOR (VM1) AND TERMINAL #5(L1) ON THE FLAME
SEQUENCE OF OPERATION
PREPURGE PERIOD WILL BEGIN.
BLOWER MOTOR (BM). WHENEVER POWER IS RESTORED TO THE FLAME SAFEGUARD, THE FLAME SAFEGUARD WILL GO THROUGH A 10 SECOND INITIATION PERIOD BEFORE THE
CONTROL (FLC) AND TERMINAL #6 ON THE FLAME SAFEQUARD (FSG) IS POWERED. THE FLAME SAFEGUARD THEN ENERGIZES ITS TERMINAL #4, WHICH POWERS THE BURNER COMBUSTION AIR
THE BURNER AIR CONTROL VALVE WILL BE AT THE MINIMUM POSITION DURING OFF CYCLES. UPON A CALL FOR HEAT OR ANY OTHER TIME THAT A PREPURGE CYCLE OCCURS
AIR SWITCH (AS). THIS INITIATES THE 60 SECOND PREPURGE CYCLE. CONCURRENTLY, (LS2) POWERS TIMER (TD10) WHICH WILL ENERGIZE RELAY (R21) AFTER 20 SECONDS.
POSITION FOR PREPURGE. WHEN THE AIR CONTROL VALVE REACHES THE FULL OPEN POSITION SWITCH (LS2) IS 'MADE', POWERING (FSG) TERMINAL #7 THROUGH THE BURNER
FOR A NEW CALL FOR HEAT, (VM1) THROUGH THE N/O CONTACTS OF (R20) AND THE N/C CONTACTS OF (R21), WILL RE-POSITION THE BURNER AIR VALVE TO ITS MAXIMUM OPEN
WHEN (R21) IS ENERGIZED (VM1) WILL START THE AIR CONTROL VALVE ON ITS WAY TOWARD THE MINIMUM AIR VALVE POSITION THROUGH THE N/O CONTACT OF (R21) AND THE
(VM1), THROUGH THE N/C CONTACTS OF (R20) AND (R23), POSITIONS THE BURNER AIR AND GAS CONTROL VALVES TO MINIMUM AFTER A RUN CYCLE. WHEN (R20) IS ENERGIZED
THE AIR CONTROL VALVE WILL BE RE-POSITIONED TO THE MAXIMUM POSITION FOR THE PREPURGE AND THEN RETURNED TO THE MINIMUM POSITION FOR LOW FIRE START.
IGNITION PERIOD TERMINAL #10 (IGNITION TRANSFORMER--IT) WILL BE DE-ENERGIZED AND TERMINAL #9 (RELAY R23 COIL AND MAIN GAS VALVES--GV4 & GV5) WILL BE ENERGIZED
AND THE CONTROL SYSTEM WILL BE ALLOWED TO CONTROL THE FIRING RATE. THE FLAME SAFEGUARD CONTAINS "LEDS"(LOWER LEFT CORNER) THAT WILL GLOW TO INDICATED OPERATION.
(LS1) WILL BE 'MADE'. IF (LS1) IS NOT 'MADE' THE COMBINATION GAS CONTROL START VALVES (GV1) WILL NOT OPEN AND THE BURNER WILL GO OUT ON SAFETY LOCKOUT.
N/C CONTACT OF (R23). AT THE COMPLETION OF THE 60 SECOND PREPURGE CYCLE THE VALVE WILL BE AT THE MINIMUM OPEN POSITION AND THE MINIMUM POSITION SWITCH
TERMINAL #10 (IGNTION TRANSFORMER--IT) WILL BE ENERGIZED. IF FLAME IS BEING DETECTED THROUGHT THE FLAME ROD (FD) AT THE COMPLETION OF THE 10 SECOND TRIAL FOR
AFTER COMPLETION OF THE 60 SECOND PREPURGE PERIOD THERE WILL BE A 10 SECOND TRIAL FOR IGINITION DURING WHICH TERMINAL #8 (COMBINATION GAS VALVE--GV1) AND
AFTER THE FLAME HAS LIT AND BEEN PROVEN, RELAY (R23) IS ENERGIZED ALLOWING (VM1), AS CONTROLLED BY (BO#9) & (BO#10) ON THE MAIN CTRL BRD (MCB), TO POSITION
AT ITS PRESENT POSITION. THE HEATING CAPACITY IS MONITORED BY THE MAIN CTRL BRD (MCB) THROUGH (AI#10) VIA A POSITION FEEDBACK POTENTIOMETER ON THE ACTUATOR.
THE ACTUATOR WILL RE-POSITION TOWARD A LOWER FIRING RATE. IF NEITHER (BO#9) OR (BO#10) ON THE MAIN CONTROL BOARD (MCB) ARE CLOSED, THE ACTUATOR WILL REMAIN
WILL RE-POSITION TOWARD A HIGHER FIRING RATE UNTIL (BO#10) OPENS OR THE ACTUATOR REACHES ITS MAXIMUM POSITION. WHEN THE MAIN CONTROL SYSTEM CLOSES (BO#9),
THE BURNER AIR AND GAS VALVES FOR THE REQUIRED FIRING RATE. WHEN THE MAIN CONTROL SYSTEM CLOSES (BO#10) ON THE MAIN CTRL BRD (MCB), THE GAS VALVE ACTUATOR
INPUT #5 ON THE MICROTECH II MAIN CONTROL BOARD (MCB).
TERMINAL #3 WILL ENERGIZE THE HEAT ALARM RELAY (R24), WHICH WOULD THEN ENERGIZE THE REMOTE 'HEAT FAIL' INDICATOR LIGHT AND SEND A FAIL SIGNAL TO BINARY
THUS DE-ENERGIZING THE BURNER AND TERMINAL #3 WILL BECOME ENERGIZED. THE FLAME SAFEGUARD WOULD THEN BE ON SAFETY LOCKOUT AND WOULD REQUIRE MANUAL RESETTING.
IN THE EVENT THE FLAME FAILS TO IGNITE OR THE FLAME SAFEGUARD FAILS TO DETECT ITS FLAME WITHIN 10 SECONDS, TERMINALS #4, 8, 9, AND 10 WILL BE DE-ENERGIZED,
--FIRST
VALVE AND
GV1A
MANUAL VALVE.
(TYPICAL)
PRESS. REG.
TEST
COCK
TEST
CONN.
V
GV4B GV4A
V
GV5B GV5A
MODULATING
ACTUATOR
AIR
BURNER
BLOWER
SWITCH
--MAIN
VALVE AND
COMBINATION GAS CONTROLS
GV1B
THE EARLIER DESCRIBED PREPURGE CYCLE WITH THE WIDE OPEN AIR VALVE WILL BE REPEATED.
IF AN ATTEMPT IS MADE TO RESTART THE BURNER BY RESETTING THE FLAME SAFEGUARD, OR IF AN AUTOMATIC RESTART IS INITIATED AFTER FLAME FAILURE,
IF THE UNIT OVERHEATS, THE HIGH LIMIT CONTROL (FLC) WILL CYCLE THE BURNER, LIMITING FURNACE TEMPERATURE TO THE LIMIT CONTROL SET POINT.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
78 McQuay IM 487-5
Figure 86: Standard Mod, furnace control (1000 MBh)
402
H604-5
NB
TB11
+PP
5
PL19
T1_N
/1.68
168C
+MB
87 8
R25
604B
+PP
3
PL19
H604-3
10
TB11
RED_G602-L2
FLC
RED_G602-L1
L2
L1
R20
TB11
RED_G602-L1
L4
L3
RED_G603-L3
31
413
604A
225
NB
TB11
R24
+MB
87
1
+PP
PL19
BLK
H610-1
1
BLKBLK
BM
GV1
BLK
6
BLACK BLACK
TB11
RED_G609-L WHT_G609-R
WHT_G617-R
GV2
BLACK WHITE
RED_G617-L
TB11
Wiring Diagrams
632
C2C1
202020202020
20
WHT
WHT
GV3
BLK
BLK
BLACK WHITE
21212121212121
619
5
R23
624
IGNITION TRANSFORMER
L2
X2
115V
6000V
X1
L1
IT
BLACK BLACK
10NO10
BO10
207
jprs
MCB
+MB
24V SRC
jprs
9NO9
BO9
24V SRC
207
MCB
+MB
633B
634B
632B
+PP
PL19
H632-9
64
PL18
+PP
9
9
8
PL18
H633-9
H634-8
11
12
TB11
TB11
625
633C
5
+PP
R23
S1/2.01
600
S3
SIG_1/4.28
TB11
4
YEL_G634-2
OPEN
(CL)
CCW
G
(Schematic continues on next page.)
YEL_G632-R
YEL_G633-1
COM
CLOSE
1
2
R
WHTBLK
VMI
VALVE
ACTUATOR
(FLOATING)
GAS & AIR
MODULATING
(OP)
CW
T
Y
RED_G630-B WHT_G630-W
1
4
11
8
2
607A
602A
8
9
TB11
611A
610A 610B
609
3
4
L2
H603-4
+PP
PL19
H602-2
603A 603B 603C
+PP
2
PL19
+PP
PL16
H603-2
3K1
FSG
6K1
MICROCOMPUTER
(L1)
5
426B
2
21 42
TB11
3
TB11
(FLAME SAFEGUARD)
(PLUG-IN TYPE
2K2
CONTROLLER)
617A
9
621C
107
5K12K11K1
6
621B
NO
AS
COM
618
613A
8
4K1
I
T
R
E
M
FIER
FSG
AMPLI
FLAME
FSG-F
FSG-G
FD
(FLAME ROD)
10
5
7
HL22
H603-1
1
+PP
PL16
201A
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
(FSG) CONTROLLER.
LIGHTS ARE PART OF THE FLAMESAFEGUARD
1.POWER, PILOT & MAIN VALVE INDICATION
NOTE:
631
632
633
634
635
636
McQuay IM 487-5 79
Wiring Diagrams
Figure 87: Standard Mod, furnace control (1000 MBh), continued
(THRU 1/2 P.S.I.)
COCKCOCK
SHUTOFFSHUTOFF
(THRU 1/2 P.S.I.)
PIPING DIAGRAMPIPING DIAGRAM
COCKAIR COCK
SHUTOFFSHUTOFF
REG.REG.
HIGH PRESS.
HIGH PRESS.
OVER 1/2 P.S.I.
OVER 1/2 P.S.I.
(Schematic continues on the previous page.)
WHEN THE ROOFTOP UNIT IS ENERGIZED 120 VOLT POWER IS SUPPLIED TO THE SYSTEM ON-OFF SWITCH (S1), TO BURNER ON-OFF SWITCH (S3) AND 24 VOLTS TO THE (BO#11)
CONTACTS ON THE MAIN CTRL BRD (MCB). BURNER ON-OFF SWITCH (S3) WILL POWER THE MODULATING GAS VALVE ACTUATOR (VM1) AND TERMINAL #5(L1) ON THE FLAME
SEQUENCE OF OPERATION
WHEN 120 VOLT
THE PILOT FLAME WILL IGNITE AND BE DETECTED BY THE FLAME SAFEGUARD THROUGH
ALSO, THE FLAME SAFEGUARD CONTAINS "LED'S" (LOWER LEFT CORNER) THAT WILL GLOW TO INDICATE OPERATION.
THE RELAY DRIVES THE GAS VALVE ACTUATOR (VM1) TO THE MINIMUM FIRING RATE POSITION WHENEVER THE FLAME IS NOT
UPON DETECTION OF PILOT FLAME, TERMINAL #10 (IGNITION TRANSFORMER--IT) WILL BE DE-ENERGIZED AND TERMINAL #9 (MAIN GAS VALVES--GV2 & GV3)
THE BURNER COMBUSTION AIR BLOWER MOTOR (BM). WHENEVER POWER IS RESTORED TO THE FLAME SAFEGUARD, THE FLAME SAFEGUARD WILL GO THROUGH A 10 SECOND
CONTROL (FLC) AND TERMINAL #6 ON THE FLAME SAFEQUARD (FSG) IS POWERED. THE FLAME SAFEGUARD THEN ENERGIZES ITS TERMINAL #4, WHICH POWERS
SAFEGUARD (FSG). UPON A CALL FOR HEAT, THE CONTROL SYSTEM WILL CLOSE (BO#11) ON THE MAIN CTRL BRD (MCB), THUS ENERGIZING RELAY (R20).
POWER IS FURNISHED THROUGH THE SYSTEM ON-OFF SWITCH (S1), THROUGH THE BURNER ON-OFF SWITCH (S3), THROUGH RELAY (R20) CONTACTS, THROUGH THE HIGH LIMIT
BLOWER OPERATION IS SENSED BY THE AIR SWITCH (AS), WHICH MAKES TERMINAL #6 TO #7. AFTER A 90 SECOND PREPURGE PERIOD, TERMINAL #8 (FIRST GAS VALVE
INITIATION PERIOD BEFORE THE PREPURGE PERIOD WILL BEGIN.
THE FLAME ROD (FD).
(PILOT)--GV1) AND TERMINAL #10 (IGNITION TRANSFORMER--IT) WILL BE ENERGIZED.
GAS VALVE AND COMBUSTION AIR DAMPER AND CAN SET THE FIRING RATE BETWEEN 33% AND 100% OF NORMAL RATE. WHEN THE MAIN CONTROL SYSTEM CLOSES (BO#10) ON THE
WHENEVER THE BURNER IS IN OPERATION ITS FIRING RATE WILL BE DETERMINED BY THE "FLOATING" GAS VALVE ACTUATOR (VM1). THIS ACTUATOR POSITIONS THE BUTTERFLY
WILL BE ENERGIZED AND THE MAIN FLAME WILL COME ON.
ON, AND HOLDS IT THERE UNTIL THE FLAME HAS LIT AND BEEN PROVEN.
LOW FIRE START IS PROVIDED BY RELAY (R23).
REG.
REG.
MAIN
MAIN
PRESS.
PRESS.
COCKCOCK
PILOT
PILOT
PRESS. REG.PRESS. REG.
GV2GV2
GV3
GV3
MAIN GAS VALVES
MAIN GAS VALVES
TEST
TEST
GAS
GAS
MOD.
MOD.
TEST
TEST
(BO#9) OR (BO#10) ON THE MAIN CONTROL BOARD (MCB) ARE CLOSED THE ACTUATOR WILL REMAIN AT ITS PRESENT POSITION. THE HEATING CAPACITY IS MONITORED BY THE
POSITION. WHEN THE MAIN CONTROL SYSTEM CLOSES (BO#9) ON THE MAIN CTRL BRD.(MCB), THE ACTUATOR WILL REPOSITION TOWARD A LOWER FIRING RATE. IF NEITHER
MAIN CTRL BRD.(MCB), THE GAS VALVE ACTUATOR WILL REPOSITION TOWARD A HIGHER FIRING RATE UNTIL EITHER (BO#10) OPENS OR THE ACTUATOR REACHES ITS MAXIMUM
MAIN CONTROL BOARD (MCB) THROUGH (AI#10) VIA A POSITION FEEDBACK POTENTIOMETER ON THE ACTUATOR (VM1).
DE-ENERGIZED, THUS DE-ENERGIZING THE BURNER. THE FLAME SAFEGUARD WOULD THEN BE ON SAFETY LOCKOUT AND WOULD REQUIRE MANUAL RESETTING. THE HEAT ALARM
RELAY (R24) WOULD THEN BE ENERGIZED AND WOULD THEN ENERGIZE THE REMOTE "HEAT FAIL" INDICATOR LIGHT AND SEND A FAIL SIGNAL TO BINARY INPUT #5 ON THE
IN THE EVENT THE PILOT FAILS TO IGNITE OR THE FLAME SAFEGUARD FAILS TO DETECT ITS FLAME WITHIN 10 SECONDS, TERMINALS #4, 8, 9, AND 10 WILL BE
IF THE UNIT OVERHEATS, THE HIGH LIMIT CONTROL (FLC) WILL CYCLE THE BURNER, LIMITING FURNACE TEMPERATURE TO THE LIMIT CONTROL SET POINT.
MICROTECH II MAIN CONTROL BOARD (MCB).
COCK
COCK
VALVE
VALVE
CONN.
CONN.
GV1
GV1
PILOT VALVE
PILOT VALVE
TEST
TEST
CONN.
CONN.
AIR
AIR
BURNER
BURNER
BLOWER
BLOWER
SWITCH
SWITCH
AIR
DAMPER
DAMPER
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
80 McQuay IM 487-5
Figure 88: Electric heat control
PB3
Wiring Diagrams
L1
HL14
(MANUAL)
518G
M44
FB44
518E 518F
PB3
PB3
HTR4B
3
1
T1
L1
T1
L1
L1-8
L1-4
519E 519F
L3
L2
4
2
T3
T2
556
L3
L2
T3
T2
L2
L3
520D 520E 520F
500
L3-8
L2-8
500
L3-4
L2-4
HL12
(MANUAL)
510G
M42
FB42
510E 510F 510H
PB3
PB3
L1
HTR2B
3
1
T1
L1
T1
L1
L1-6
L1-2
511G
511E 511F 511H
L3
L3
L2
4
2
T3
T2
548
L3
L2
T3
T2
L2
L3
512D 512E 512F
500
L3-6
L2-6
500
L3-2
L2-2
L1
HL13
(MANUAL)
514G
M43
FB43
514E 514F
PB3
PB3
L2
4
3
2
1
515G
T1
T3
T2
552
L1
L3
L2
T3
T2
T1
L1
L2
L3
515E 515F
516D 516E 516F
500
L3-7
L2-7
L1-7
500
L3-3
L2-3
L1-3
HTR1B
L3
L1
L2
4
3
HL11
2
1
(MANUAL)
507G
506G
T1
T3
T2
507E 507F 507H
547
L3
L2
T3
T2
L2
L3
508D 508E 508F
500
L3-5
L2-5
500
L3-1
L2-1
M41
L1
T1
FB41
L1
506E 506F 506H
PB3
L1-5
L3B
L3A
L2B
L2A
L1B
L1A
L1-1
PB3
L3
L2
L1
FB31
T1
T3
T2
508B 508C
507C 507D
506C 506D
M31
506B
HL1
(MANUAL)
L1
T1
3
1
507B
546
L3
L2
T3
T2
4
2
FB32
510C 510D
M32
510B
HL2
(MANUAL)
508A
507A
506A
L2
L1
L3
510A
HTR1A
00
01
020304
05
06
07
080910
11
121314
L1
L1
T1
L1
T1
3
1
HTR2A
511C 511D
511B
511A
L3
L2
T3
T2
512B 512C
550
L3
L2
T3
T2
4
2
FB33
514C 514D514A
M33
514B
HL3
(MANUAL)
512A
L2
L3
15
16
17
18
19
202122
L1
L1
T1
L1
T1
3
1
HTR3A HTR3B
515C 515D
515B
515A
L3
L2
T3
T2
516B 516C
553
L3
L2
T3
T2
4
2
FB34
518C 518D518A
M34
518B
HL4
(MANUAL)
516A
L3
L2
L1
T1
T3
T2
520B 520C
519C 519D
554
L1
L3
L2
T1
T3
T2
519B 519G
4
3
2
1
520A
519A
L2
L3
L2
L1
L3
HTR4A
23
24
25
26
27
28
29
30
31
32
33
(Schematic continues on next page.)
McQuay IM 487-5 81
Wiring Diagrams
534535536537538539540541542543544545546547548549550551552553554555556557558559560561562563564565566567568569570
P
534535536537538539540541542543544545546547548549550551552553554555556557558559560561562563564565566567568569570
P
Figure 89: Electric heat control, continued
PL12+P
PL12+P
168C
2
168C
T1_N/1.68
T1_N/1.68
2
TB11
NB2
NB2
TB11
544C
506
506
514
506
506
514
544C
522
514
514
522
522
530
530
530
530
522
(Schematic continues on previous page.)
UNDER HEATER
T1_115VAC/1.68
(Schematic continues on previous page.)
HS3
DEADFRONT
536A 536B
TB11
+PP
PL12
43
HS3
DEADFRONT
43
UNDER HEATER
536A 536B
171
TB11
933
171
TB11
+PP
PL12
168A
T1_115VAC/1.68
+PP
PL12
168A
538B
ON SWITCH BRACKET
IN MAIN CONTROL PANEL
HS1
21
ON SWITCH BRACKET
538A
IN MAIN CONTROL PANEL
+PP
T3_COM/3.11T3_24V/3.11
HS1
933
TB11
N2+B/1
PL12
538B
21
538A
NC-B/1
T3_COM/3.11T3_24V/3.11
303B
303A
REFB/1
24C
24V
N2+B/1
NC-B/1
REFB/1
N2+A/1
303B
24C
24V
N2+
303A
N2-A/1
N2-
N2+A/1
N2-A/1
REFA/1
N2-
N2+
REF
J10
BO11
MCB
T3_24V/3.11
REFA/1
REF
544B
T3_24V/3.11
9-16
9-16
9-16
9-16
MCB
SRC
BI12
303A
BO11
M31
M31
A1 A2
21
(AUTO)
HL31
(AUTO)
546B 546C
94
TB11
+PP
4
+PP
PL12
546A
STAGE 1
1
BI12
J10
STAGE 1
544B
11NO11
207
MCB
3
9-16
9-16
9-16
9-16
11NO11
MCB
SRC
207
303A
M41
M42
M42
A1 A2
A1 A2
M41
A1 A2
M32
A1 A2
M43
M43
A1 A2
M32
A1 A2
A1 A2
549A
549A
21
21
HL42
(AUTO)
21
HL42
(AUTO)
21
HL41
(AUTO)
HL32
(AUTO)
548B 547A
95
TB11
95
TB11
5
+PP
PL12
5
548A
+PP
+PP
PL12
PL12
2
548A
STAGE 2
54
STAGE 3
STAGE 2
6
54
HL43
(AUTO)
21
HL43
(AUTO)
21
HL32
(AUTO)
552B 552C
550B 550C
552B 552C
550B 550C
96
TB11
TB11
96
TB11
TB11
6
+PP
+PP
PL12
PL12
6
550A
552A
+PP
PL12
550A
552A
STAGE 3
STAGE 4
6
87
STAGE 4
87
HL31
PL12
(AUTO)
546B 546C
TB11
546A
21
HL41
548B 547A
94
4
1
2
3
M34
M34
A1 A2
A1 A2
M33
A1 A2
A1 A2
M33
A1 A2
A1 A2
555A
555A
21
21
(AUTO)
(AUTO)
HL33
HL33
21
(AUTO)
21
(AUTO)
HL34
HL34
21
21
(AUTO)
(AUTO)
554B 553A
554B 553A
97
98
TB11
97
98
TB11
7
8
+PP
PL12
7
8
554A
+PP
+PP
PL12
11
554A
STAGE 5
11
910
STAGE 5
910
M44
M44
+PP
STAGE 6
STAGE 6
HL44
HL44
556B 556C
TB11
PL12
PL12
556A
556B 556C
TB11
556A
A1 A2
A1 A2
21
21
99
99
9
9
120 KW
4 B
M44
HEATER
8 B
BANK "B"
13 12
HEATER
BANK "B"
M31
13 12
HEATER
BANK "A"
HEATER
BANK "A"
1 A
5 A
M41
3 B
2 B
1 B
M43
M42
7 B
120 KW
4 B
M44
120 KW
8 B
2 A
M32
6 A
M31
1 A
5 A
M41
3 B
2 B
1 B
M43
M42
7 B
4 A
3 A
M33
M34
120 KW
2 A
3 A
4 A
M32
M33
M34
6 A
82 McQuay IM 487-5
Wiring Diagrams
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
433
Figure 90: Fan control, power package only
/1.68
00
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
R63
811
219
MMP20MMP10
426A 426B 426C426D
76757675
149137
TB4
207
SUPPLY FAN ON/OFF
TB4
208
M10
A1 A2
28
29
30
31
32
RETURN FAN ON/OFF
TB4
431A
209
M20
A1 A2
McQuay IM 487-5 83
T1_N115VAC_GF/1
137 260
149
Wiring Diagrams
Figure 91: CV fan control (SAF and RAF)
/3.11
115VAC_GF/1 T1_N
11(31)
T3_24V
SOURCE 9-16
MCB
WIRED INTERNAL
TO MOTHERBOARD
207
SRC 9-16
MMP10
12(32) 11(31)
jprs
MCB
TB2
45
MMP20
TB2
42
12(32)
1 1NO
207
SUPPLY FAN
MCB
2 2NO
207
RETURN FAN
BO1
24V SRC
401A
jprs
BO2
24V SRC
404A
R67
3
1
401
426C426B426A
/3.11
T3_COM
R67
10
2
R68
2
10
M10
A2A1
/1.68
R68
3
1
404
431A
M20
A2A1
Figure 92: Light and receptacle power
FIELD SUPPLIED 115V/60/1
REC1
H
TB7
CP SL
GRD
1004B
1003B1003A
TB7
1005B1005A
SLCP
PL31
PL32
H1006-1
1
1
84 McQuay IM 487-5
H775
H775
S10
H775
S11
H775
REC10
H
REC11
H
BLK WHT
N
G
BLK WHT
N
G
LT10
LT11
w
H776
G1009
w
H776
G1012
H1006-2
30
H1010-2H1010-1
31
PL31
2
PL32
2
N
G
TB7
G1004

Unit Options

Unit Options

Enthalpy Control

Outside Air Enthalpy Control (OAE)
Units with MicroTech II control and an economizer come standard with an electromechanical enthalpy control device (OAE) that senses both the humidity and temperature of the outside air entering the unit. This device has an enthalpy scale marked A through D. Table 13 shows the control points at 50% RH for settings A through D. Figure 93 shows this scale on a psychrometric chart. When the outside air conditions exceed the setting of the device, the outside air dampers are positioned to the minimum outside air intake position by the MicroTech II
controller.
Table 13: Enthalpy control settings
Control curve Control point temperature at 50% RH
A73°F (23°C) B70°F (21°C) C 67°F (19*C) D63°F (17°C)
Differential Enthalpy Control (OAE/RAE)
An optional electric differential enthalpy control arrangement (OAE/RAE) is available on units with MicroTech II control. In this configuration a solid-state humidity and temperature sensing device is located in both the return (RAE) and outside intake (OAE) airstreams. This OAE device has the same A through D scale as the device described above. However, with the OAE/RAE arrangement the switch on, OAE must be set all the way past the D setting. With this done, the MicroTech II controller adjusts the return and outside air dampers to use the airstream with the lowest enthalpy.
Ground Fault Protection
The ground fault protection is designed to protect motors from destructive arcing ground faults. The system consists of a ground fault relay and a ground fault current sensor. The ground fault relay employs solid state circuits that will instantly trip and open a set of relay contacts in the 115-volt control circuit to shut the unit down whenever a ground fault condition exists. The ground fault relay is self powered. The ground fault sensor is a current transformer type of device
located on the load side of the power block through which the power wires of all phases are run.
Figure 93: Enthalpy control settings
8 5
9 0
9 5
1 0 0
( 2 9 . 5 )
( 2 6 . 5 )
( 3 2 )
0 . 8 0
0 . 9 0
0 . 7 0
0 . 6 0
0 . 5 0
A
B
8 0
8 5
9 0
( 2 9 . 5 )
( 3 2 )
4 6
4 4
4 2
8 0
( 2 6 . 5 )
4 0
3 8
3 6
3 4
3 2
3 0
2 8
2 6
E N T H A L P Y  B T U P E R P O U N D D R Y A I R
2 4
2 2
2 0
1 8
1 6
1 4
1 2
( 1 . 5 )
4 5
( 7 )
4 0
( 4 . 5 )
3 5
3 5
4 0
4 5
( 1 . 5 )
( 4 . 5 )
( 7 )
6 0
( 1 5 . 5 )
5 5
( 1 3 )
B
5 0
C
( 1 0 )
D
5 0
5 5
6 0
( 1 0 )
( 1 3 )
( 1 5 . 5 )
A
( 1 8 . 5 )
6 5
( 1 8 . 5 )
7 5
( 2 4 )
7 0
( 2 1 )
C
D
6 5
7 0
7 5
( 2 1 )
( 2 4 )
1 0 5
( 3 5 )
( 3 8 )
( 4 0 . 5 )
R E L A T I V E
H U M I D I T Y
0 . 4 0
0 . 3 0
0 . 2 0
0 . 1 0
9 5
1 0 0
1 0 5
0 . 5 )
( 3 5 )
( 3 8 )
( 4
Phase Voltage Monitor
The phase voltage monitor (see page 116) protects against high voltage, phase imbalance, and phase loss (single phasing) when any one of three line voltages drops to 74% or less of setting. This device also protects against phase reversal when improper phase sequence is applied to equipment, and low voltage (brownout) when all three line voltages drop to 90% or less of setting. An indicator run light is ON when all phase voltages are within specified limits. The phase voltage monitor is located on the load side of the power block with a set of contacts wired to the 115-volt control circuit to shut the unit down whenever the phase voltages are outside the specified limits.
McQuay IM 487-5 85
Unit Options

External Time Clock

You can use an external time clock as an alternative to (or in addition to) the MicroTech II controller’s internal scheduling function. The external timing mechanism is set up to open and close the circuit between field terminals 101 and 102. When the circuit is open, power is not supplied to binary input MCB-BI1. This is the normal condition where the controller follows the programmable internal schedule. When the circuit is closed, power is fed to BI1. The MicroTech II controller responds by placing the unit in the occupied mode, overriding any set internal schedule.
For more information, see the “Digital Inputs” section of Bulletin No. IM 696, “MicroTech II Applied Rooftop Unit Controller.”

Smoke and Fire Protection

McQuay optionally offers factory installed outdoor air, return air, and exhaust air dampers as well as smoke detectors in the supply and return air openings, complete with wiring and control. These components often are used in the building’s smoke, fume, and fire protection systems. However, due to the wide variation in building design and ambient operating conditions into which our units are applied, we do not represent or warrant that our products will be fit and sufficient for smoke, fume, and fire control purposes. The owner and a fully qualified building designer are responsible for meeting all local and NFPA building code requirements with respect to
smoke, fume, and fire control.
be restarted until the alarm is manually cleared. Refer to the operation manual supplied with the unit for information on clearing alarms (OM138 or OM137).
The smoke detectors themselves must be reset manually once they have tripped. Power must be cycled to the smoke detector to reset.

Freeze Protection

An optional freezestat is available on units with MicroTech II control that have hot water, chilled water, or steam heating coils. The sensing element is located on the downstream side of the heating coil in the heating section of the unit. If the freezestat detects a freezing condition and closes, the MicroTech II controller takes different actions, depending on whether the fans are on or off. The freezestat is an auto reset type of control; however, the controller alarm that it causes is manually reset if the fan is on and auto reset if the fan is off.
Fan On Operation
If the freezestat detects a freezing condition while the fan is on, the MicroTech II controller shuts down the fans, closes the outdoor air dampers, opens the heating valve, and sets a 10­minute timer. The MicroTech II controller’s active alarm is “Freeze Fault.”
When the 10-minute timer expires, the controller begins checking the freezestat again. If the freezestat is open, the heating valve closes. If the freezestat closes again, the heating valve opens, and the 10-minute timer resets.
WARNING
Improper smoke, fire, or fume air handling can result in severe personal injury or death.

Smoke Detectors

Optional smoke detectors can be located at the supply and return openings. The wiring for these smoke detectors is shown on any of the “Typical Main Control Circuit” wiring schematics within the “Wiring Diagrams” section on pages 65–88.
The sequence of operation for these detectors is as follows: When smoke is detected by either sensor, the normally closed sensor contacts open. This removes power from binary input BI8 on the Main Control Board.
The MicroTech II controller responds by shutting down the unit. The controller is placed in the Alarm Off state and cannot
The unit remains shut down until the “Freeze Fail” alarm is manually cleared. Refer to the operation manual supplied with the unit for information on clearing alarms (OM138 or OM137).
Fan Off Operation
If the freezestat detects a freezing condition while the fan is off, the MicroTech II controller opens the heating valve and sets a 10-minute timer. The MicroTech II controller’s active alarm is “Freeze Problem.”
When the 10-minute timer expires, the controller begins checking the freezestat again. If the freezestat is open, the heating valve closes. If the freezestat closes again, the heating valve opens, and the 10-minute timer resets.
When the freezestat opens again, the “Freeze Prob” alarm automatically clears. This feature protects the coil and allows the system to start normally after a cold night.
86 McQuay IM 487-5
Unit Options

Entering Fan Temperature Sensor

The entering fan temperature (EFT) sensor and an associated “Lo Airflow Problem” alarm are provided on VAV units with MicroTech II control and gas or electric heat. The EFT sensor is located in the supply fan section of the unit at the supply air funnel.
Heat is disabled whenever the airflow is detected to be too low for safe heating operation. This condition is indicated when the supply air temperature exceeds the mixed air temperature by more than 60°F (16°C).
Note – This value is not always 60°F. It depends on whether the
unit is gas or electric heat and on the burner/baffling arrangement on gas heat units.
In this case, a “Lo Airflow Problem” alarm is generated and heat is not enabled until the alarm is manually cleared. Refer to the operation manual supplied with the unit for information clearing alarms (OM 138 or OM 137).

Duct High Pressure Limit

The duct high pressure limit control (DHL) is provided on all VAV units. The DHL protects the duct work, the terminal boxes, and the unit from over pressurization, which could be caused by, for example, tripped fire dampers or control failure.
The DHL control is factory set to open when the discharge plenum pressure rises to 3.5" wc (872 Pa). This setting should be correct for most applications; however, it is adjustable. Removing the front cover of the device reveals a scale showing the current setting. Turning the adjustment screw (located on the bottom of the device) adjusts the setting up or down.
If the DHL switch opens, digital input MCB BI 14 on the Main Control Board de-energizes. The MicroTech II controller then shuts down the unit and enters the Off-Alarm state. The alarm must be manually cleared before the unit can start again. Refer to the operation manual supplied with your unit for more information on clearing alarms (OM 138 or OM 137).

MicroTech II™ Remote User Interface (UI)

Both a unit mounted and an identical, remote mounted keypad and display are provided with this option. A remote-mounted user interface (UI) is available as an option with all rooftop units. The following items are provided:
Unit mounted UI
Unit mounted power supply and R485 isolator for the
remote UI
Selector switch to activate either the unit mounted UI or the remote UI. Only one UI is active at a time.
Wall mounted electrical box that contains the remote UI. See Figure 94.
Cable and Wiring Recommendations
Remote wiring to connect the unit to the remote UI is not included. See Figure 95 on page 88 for wiring information and the following recommendations.
No more than 1200 feet of wiring can be used to connect the remote user interface to the unit.
Use overall foil shield, 3 twisted pairs, 22 AWG stranded connectors with drain wire.
UL 910 plenum rated = Belden 6542FE-1000-877
Non-plenum rated = Belden 5542FE-1000-8
McQuay IM 487-5 87
Unit Options
odule
Figure 94: Factory-assembled remote user interface
4.4 "
7.2 "
(4) #6-32 Hex Nuts
(4) #6 Split Lock Washers
6.9 "
Enclosure with Cover
Surface Mount, Modular Jack with 6 contacts, Screw Terminals
Cable Assembly
Keypad/Display M
Ground
Figure 95: Remote user interface wiring diagram
88 McQuay IM 487-5
Unit Options

Variable Frequency Drive Operation

Refer to the vendor instructions supplied with the unit.

Convenience Receptacle/Section Lights

A Ground Fault Circuit Interrupter (GFCI) convenience receptacle is provided in the main control box on all units.
To use this receptacle, connect a separate field-supplied 115 V power wiring circuit to the 115V field terminal block TB7, located in the main control box.
Optional lights are available for certain sections in the unit. Each light includes a switch and convenience receptacle and is powered by the external 115V power supply connected to TB7.

DesignFlow™ Outdoor Air Damper Option

DesignFlow™ airflow measurement stations are located inside the louvered outdoor air intake doors between the intake louver and outside air dampers. Essentially, they consist of a vane that is repositioned by airflow, the amount of rotation indicating the amount of airflow. They are calibrated precisely at the factory and no further calibration is required. However, a leveling adjustment is required in the field so that the DesignFlow unit is in the same orientation as when it was factory calibrated. See “DesignFlow Station Startup” below.
The rotational position of the DesignFlow unit vane is translated into CFM by the microprocessor in the MicroTech II control system. The position of the vane is determined by two things—the force of the airflow impacting the vane and the gravitational effect on the vane. Gravity is the only factor at the lower CFM end of the range. On a correctly leveled unit, this gravitational effect will be the same as when the unit was calibrated in the factory.
Accurately leveling a station involves applying a precise mechanical force against the vane. This force should cause the vane to move to a specific position if the DesignFlow unit is correctly leveled.
DesignFlow Station Startup
Before initial startup of the rooftop unit, carry out the following procedure on both the right-hand (control panel side) and left-hand (side opposite the control panel) DesignFlow station vanes (see Figure 96).
Note – This procedure is much easier to carry out with two
people—one making the mechanical adjustments and the other viewing and recording readings on the MicroTech II control panel.
1 Verify that power is supplied to the unit’s MicroTech II
control system. The DesignFlow startup procedure cannot be completed without use of the MicroTech II controls.
2 Unlock and open the louvered outdoor air intake door on
the side of the unit (see Figure 96).
3 The swinging vane on the measurement station is locked in
place for shipment. Unlock it by removing the two shipping screws. One is located one inch from the top of the vane and the other one inch from the bottom of the vane. Both are about eight inches in from the outer edge of the vane.
4 Examine the station for shipping damage. Manually rotate
the vane and verify that it does not rub against anything.
Figure 96: DesignFlow station
Manually hold the vane closed against the mechanical stop
5
at the top of the assembly. Then, read the current vane leveling position on the MicroTech II keypad/display.
Do this by viewing the LH Lvl Pos= or RH Lvl Pos= parameter in the DesignFlow setup menu. The LH Lvl Pos= parameter indicates the current position of the vane for the left-hand DesignFlow station (side opposite the control panel). The RH Lvl Pos= parameter indicates the current position of the vane for the right-hand DesignFlow station (control panel side).
Important: Wait several seconds until the value on the keypad stabilizes before taking the reading.
For detailed information regarding operation and navigation through the unit keypad, refer to Operation manual OM 137 (discharge air control units) or OM 138 (zone control units).
6 Confirm the value of the reading. Ideally, it should read
close to 20.00 (19.50 to 20.50 is acceptable). If the reading is out of range, loosen the screws fixing the mechanical stop at the top of the assembly, make a small adjustment, and recheck until the reading is in the specified range.
Note: Generally, adjustments should not be necessary.
7 Locate the leveling component kit, which is shipped with
the unit, in the unit mail control panel.
8 Duct tape the fulcrum alignment plate to the bottom corner
of the vane (see Figure 97) aligning it as follows:
a The bottom edge of its notches should be flush with the
bottom edge of the vane.
b The side of one notch should be even with the bend near
the outer edge of the vane.
McQuay IM 487-5 89
Unit Options
e
c
The plate should be flat against the outer surface of the vane.
Figure 97: Tape fulcrum alignment plate to vane
Vane
Duct tape
This edge flush with bottom of vane
These edges flush with bottom of van
9 Locate and install the fulcrum used in the leveling
Alignment plate
Fulcrum
Duct tape
procedure as follows (see Figure 97):
a Wipe the bottom of the louver door where the fulcrum
will be located so that the duct tape will stick to it.
b Pre-apply duct tape to the top surface of the bottom
portion of the fulcrum, extending it about one inch beyond the edges on three sides.
c With the alignment plate taped to the vane and the vane
in the zero airflow position, locate the fulcrum parallel to and against the alignment plate.
Note – The zero airflow position is when the vane is swung away
from the back wall and gently resting against its stop.
d Once the fulcrum is in position, press the duct tape
extensions down to hold the fulcrum in place.
e Remove the alignment plate after installing the fulcrum.
10 Close and latch the louvered intake door.
11 Remove the cover from the access opening in the bottom
blade of the outdoor air intake louver (see Figure 100).
12 Verify that the unit fans are off and that the outdoor air
dampers are closed. If there is a wind, cover the outdoor air louvers with poly film, cardboard, or other suitable material to prevent adverse readings due to wind.
13 Rest the leveling weight assembly on the fulcrum, as shown
in Figure 98, so that:
a Its bottom two thumbscrews rest on the top edge of the
fulcrum.
b Its top thumbscrew rests against the vertical alignment
mark on the vane.
Note: The alignment mark is located 0.50 inch in from the
bend on the outer edge of the vane. It intersects with a hole located one inch up from the bottom outer edge of the vane.
Figure 98: Place leveling weight on fulcrum
14 Set up the leveling test as follows:
a While holding the weight so it stays on the fulcrum,
manually rotate the vane to the wide-open position, manually return it to the zero CFM position, and gently release the vane.
b Locate the leveling weight assembly so its contact point
is against the vertical mark on the vane.
c While the weight assembly teeters on the fulcrum,
gently rap the base frame to slightly vibrate the assembly and encourage the vane to seek its equilibrium point.
15 Read the current LH Lvl Pos= (or RH Lvl Pos=) parameter
in the DesignFlow Setup menu on the keypad/display. These parameters vary from 20% to 80% depending on the position of the DesignFlow vane
16 If the value indicated by the LH Lvl Pos= (or RH Lvl Pos=)
parameter is not within the range of 23.64% to 24.08%, adjust the level of the DesignFlow unit using the procedure described in “Making Level Adjustments” below.
17 When the LH Lvl Pos= (or RH Lvl Pos=) value is in range,
remove the fulcrum and leveling weight assembly and replace the access opening cover in the louvered door.
90 McQuay IM 487-5
Unit Options
Making Level Adjustments
The DesignFlow unit is mounted so that it pivots at the top when three lock nuts are loosened, two at the top and one at the bottom of the assembly (see Figure 99). Leveling the unit involves precisely pivoting the assembly with a known force applied to the vane until the vane opens to a specific position.
If after performing Steps 13 through 15 (previous page), the vane does not come to rest within the specified range, carry out the following steps:
1 Unlock and open the louvered outdoor air intake door on
the side of the unit.
2 Loosen the two .25-20 NC lock nuts at the top of the
DesignFlow frame (see Figure 99).
Figure 99: DesignFlow frame
Top lock nuts
Vane
Pivot point
7 When finished making the adjustments, tighten the .25-20
NC lock nut in the slotted hole at the bottom of the DesignFlow frame (see Figure 101).
8 Gently rap the base frame to slightly vibrate the assembly
to encourage the vane to seek its equilibrium point.
9 Recheck the vane position compared to the range specified
in Step 16 (previous page). Readjust the level as necessary.
10 When the level is correct, unlock and open the louvered
outdoor air intake door on the side of the unit and tighten the two .25-20 NC lock nuts at the top of the DesignFlow frame (see Figure 99).
11 Close and lock the intake door.
12 Recheck the vane position and readjust the level as
necessary.
13 When the vane position is correct, replace the access
opening cover in the louvered door.
Figure 100: Remove covers from access opening
Louvered door
Bottom lock nut
3 Close and lock the intake door.
4 Remove the cover from the access opening in the bottom
blade of the outdoor air intake louver (see Figure 100).
5 Loosen the .25-20 NC lock nut in the slotted hole at the
bottom of the DesignFlow frame (see Figure 101).
6 If the LH Lvl Pos= (or RH Lvl Pos=) value obtained in
step 15 above is HIGHER than the specified range, move the bottom of the DesignFlow frame closer to the outdoor air dampers (away from the back end of the unit). Do this by turning the long adjuster nut to increase the L dimension in Figure 101.
If the LH Lvl Pos= (or RH Lvl Pos=) value obtained in step 15 above is LOWER than the specified range,
move the bottom of the DesignFlow frame away from the outdoor air dampers (toward the back end of the unit). Do this by turning the long adjuster nut to decrease the L dimension in Figure 101.
Note: If the necessary adjustment cannot be made using
the long adjuster nut, reposition the two .25-20 NC jam nuts on the threaded rod to make larger adjustments (see Figure 101).
Access opening
Cover
Figure 101: Leveling adjustment
Threaded adjuster
assembly
Long adjuster nut
Jam nuts
To INCREASE L dimensionLTo INCREASE L dimension
Right hand adjuster Left hand adjuster
Locknut
L
McQuay IM 487-5 91
Unit Options
A

Propeller Exhaust Fan Option

Economizer units may include propeller exhaust or centrifugal return fan options. This section covers maintenance and operating instructions for the propeller exhaust option. Centrifugal return fan construction, maintenance and operation is similar to that for supply fans and covered in other sections of this manual.
Figure 102: Two fans with back return shown
Fans and motors
substantial increase in horsepower required from the motor. Always check motor load amperage and compare to name plate rating when changing fan speed.
Figure 103: Fan rotation
i r f l o w
R o t a t i o n
A i r f l o w
R o t a t i o n
Once the fan is put into operation, set up a periodic maintenance program to preserve the reliability and performance of the fan. Items to include in this program are:
Belts
Bearings
Fasteners
Setscrews
Lubrication
Dust/dirt removal
VFD
Starters
Prestarting Checks
Check all fasteners and set screws for tightness. This is especially important for bearing set screws.
The propeller should rotate freely and not rub on the fan panel venturi. Rotation direction of the propeller should be checked by momentarily turning the unit on. Rotation should be in the same direction as the rotation decal affixed to the unit or as shown in Figure 103. For three-phase installations, fan rotation can be reversed by simply interchanging any two of the three electrical leads. For single phase installations follow the wiring diagram located on the motor.
The adjustable motor pulley is preset at the factory for the specified fan RPM. Fan speed can be increased by closing (or decreased by opening) the adjustable pulley. Two or three groove variable pitch pulleys must be adjusted an equal number of turns open. Any increase in fan speed represents a
Belts
Premature belt failures are frequently caused by improper belt tension (either too tight or too loose) or misaligned pulleys. The proper tension for operating a V-belt is the lowest tension at which the belts will not slip peak load conditions. For initial tensioning, the proper belt deflection half way between pulley centers is 1/64" for each inch of belt span. For example, if the belt span is 64 inches, the belt deflection should be one inch using moderate thumb pressure at midpoint of the drive (see Figure 104).
Check belt tension two times during the first 24 hours of operation and periodically thereafter. To adjust belt tension, simply loosen four fasteners (two on each side of the motor plate) and slide the motor plate away from the fan shaft until proper belt tension is attained. On some fans, fasteners attaching the motor to the motor plate must be loosened to adjust the belt.
It is very important that the drive pulleys remain in proper alignment after adjustments are made (see Figure 105). Misalignment of pulleys results in premature belt wear noise,
vibration, and power loss.
WARNING
Rotating parts can cause severe personal injury or death. Replace all belt/fan guards that are removed temporarily for service.
92 McQuay IM 487-5
Figure 104: Belt adjustment Figure 105: Drive pulley alignment
e
e
M u s t b e p a r a l l e l
D e f l e c t i o n =
B e l t S p a n
B e l t S p a n
6 4
Unit Options
B e a r i n g
M o t o r
M u s t b e p a r a l l e l
Table 14: Propeller exhaust fan troubleshooting
Problem Cause Corrective Action
Reduced
Airflow
Excessive
Noise
System resistance is too high.
Check backdraft dampers for proper operation. Remove obstructions in ductwork. Clean dirty filters.
Check for adequate supply for air exhaust fans or exhaust air for supply fans. Unit running backwards. See “Prestarting Checks” on page 92 Fan speed too low. Increase fan speed Excessive dirt on propeller. Clean propeller Bearings Tighten bearing collars and setscrews. Lubricate bearings. Replace defective bearings. V-Belt drive Tighten pulleys on motor shaft and fan shaft. Adjust belt tension. Align pulleys. Replace worn belts or pulleys. Excessive vibration Clean dirt build-up from propeller. Check all setscrews and fasteners for tightness. Check for worn bearing.
Correct propeller imbalance. Check for loose dampers, guards or ductwork. Defective motor Replace motor.
C e n t e r l i n e s m u s t c o i n c i d
A d j u s t a b l e S h e a v e
Figure 106: Propeller exhaust fan replacement parts list
1
9
11
2
8
7
1 0
4
3
6
5
1 . F a n pa n e l 2 . P r o p e l l e r 3 . D r i v e fr a m e ch a n n e l ( 2 ) 4 . M o to r pl a te 5 . M o to r 6 . M o to r pu l l e y 7 . S h a ft p u l l e y 8 . F a n sh a ft 9 . B e a r i n g s
1 0. B e l t
a r i n g pl a t
1 1. B e
McQuay IM 487-5 93
Unit Options
Bearings
Bearings are the most critical moving part of the fan and should be inspected at periodic intervals. Locking collars and set screws, in addition to fasteners attaching the bearings to the bearing plate, must be checked for tightness. In a clean environment and temperatures above 32°F/below 200°F, fan shaft bearings with grease fittings should be lubricated semiannually using a high quality lithium based grease. If unusual environmental conditions exist temperatures below 32°F/above 200°F, moisture or contaminants, more frequent lubrication is required.
With the unit running, add grease very slowly with a manual grease gun until a slight bead of grease forms at the seal. Be careful not to unseat the seal by over lubricating or using excessive pressure. Bearings without grease fittings are lubricated for life.
Fasteners and Setscrews
Any fan vibration has a tendency to loosen mechanical fasteners. A periodic inspection should include checking all fasteners and set screws for tightness. Particular attention should be paid to setscrews attaching the propeller to the shaft and the shaft to the bearings. Loose bearing set screws will lead to premature failure of the fan shaft.
manufacturer’s instructions printed on the motor. Use a high grade SAE 20 machine oil and use caution not to over lubricate.
Motors supplied with grease fittings should be greased according to directions printed on the motor.
Removal of Dust/Dirt
Thoroughly clean the exterior surface of the motor, fan panel, and entire propeller periodically. Dirt can clog cooling openings on motor housings, contaminate bearing lubricant, and collect on propeller blades causing severe imbalance if left unchecked. Use caution and do not allow water or solvents to enter the motor or bearings. Under no circumstances should motors or bearings be sprayed with steam or water.

Exhaust Fan On/Off Control

The exhaust fans are turned on and off based on building static pressure, outdoor air damper position, and discharge fan capacity. Exhaust fans do not have to always run while the supply fan is on, as does a return fan. They are turned on and off through output MCB-B02 on the Main Control Board. For detailed information on Propeller Exhaust Fan Control, refer to the operation manual supplied with the unit (OM 138 or OM 137).
Lubrication
Refer to “Bearings” for bearing lubrication. Many fractional horsepower motors installed on the smaller fans are lubricated for life and require no further attention. Motors equipped with oil holes should be oiled in accordance with the
Exhaust Fan Troubleshooting
Table 14 provides guidelines for troubleshooting problems with the propeller exhaust fan options. A list of parts is provided in Figure 106.
94 McQuay IM 487-5
Unit Options

Ultraviolet Lights Option

When this option is employed, ultraviolet C light bathes the moist surfaces on the coil and drain pan, killing most micro­organisms that can grow there.
Typically, ultraviolet lights are installed on the leaving side of the cooling coils in the unit. Each light module is mounted on a rail and is removable for convenient bulb replacement.
UV Light Power Disconnect switches (two per door) are factory installed on every door that allows a direct line of sight to the UV lamps when opened. These switches are designed to prevent UV exposure when cabinet doors are opened and must not be disabled.
A viewing window near the UV lights allows viewing to determine if the lights are energized. The viewing windows use specially designed glass that blocks harmful UV light.
WARNING
UVC exposure is harmful to the skin and eyes. Looking at an illuminated bulb can cause permanent blindness. Skin exposure to UVC can cause cancer. Always disconnect power to unit before servicing. Do not operate if disconnect switch has been disabled.
Figure 107: Typical ultraviolet light installation
Cooling Coil
View Window
AIRFLOW
Light Power Disconnect Switch
Ultraviolet Light Units
Light Power Disconnect Switch
McQuay IM 487-5 95
Unit Options

Ultraviolet Light Operation

Refer to the wiring schematic below. 115VAC power for the UV lights is provided by control circuit transformer T1. The lights operate whenever the unit is powered, system switch S1 is closed, and all doors with door power disconnect switches are closed. To turn the lights off, disconnect power to the entire unit, or open system switch S1.
Figure 108: Typical ultraviolet light wiring schematic
The normally open disconnect switches are wired in series in a circuit that supplies 24VAC to the coil of relay R45. When all doors are closed, relay R45 is energized, and its normally open contacts (in series with system switch S1) provide 115VAC to the UV lights.
96 McQuay IM 487-5

Check, Test, and Start Procedures

Check, Test, and Start Procedures
All units are completely run tested at the factory to promote proper operation in the field. Nevertheless, the following check, test, and start procedures must be performed to properly start the unit. To obtain full warranty coverage, complete and sign the check, test, and start form supplied with the unit and return it to McQuay International.
WARNING
Electric shock and moving machinery hazard. Can cause severe equipment damage, personal injury, or death. Disconnect and tag out all electrical power before servicing this equipment. All start-up and service work must be performed only by trained, experienced technicians familiar with the hazards of working on this type of equipment. Read and follow this manual: “MicroTech II Applied Rooftop Unit Controller” manual (Bulletin IM 696), and operation manual (Bulletin OM 137 or OM 138) before operating or servicing. Bond the equipment frame to the building electrical ground through grounding terminal or other approved means.
A representative of the owner or the operator of the equipment should be present during start-up to receive instructions in the operation, care, and maintenance of the unit.
If the unit has a factory mounted disconnect switch, use the switch’s bypass mechanism to open the main control panel door without de-energizing the control panel (see page 114 for instructions).
Whenever accessing the main control panel while it is still energized, keep the inner deadfront protective panels on to avoid exposure to high voltage power.

Servicing Control Panel Components

WARNING
Hazardous voltage. Can cause severe injury or death. Disconnect electric power before servicing equipment. More than one disconnect may be required to de-energize the unit.
Disconnect all electric power to the unit when servicing control panel components located behind the protective deadfront panels. Unless power is disconnected to the unit, the components behind the protective deadfront panels are energized with high voltage. Always inspect units for multiple disconnects to ensure all power is removed from the control panel and its components before servicing.

Before Start-up

1 Verify that the unit is completely and properly installed
with ductwork connected.
2 Verify that all construction debris is removed, and that the
filters are clean.
3 Verify that all electrical work is complete and properly
terminated.
4 Verify that all electrical connections in the unit control
panel and compressor terminal box are tight, and that the proper voltage is connected.
5 Verify all nameplate electrical data is compatible with the
power supply.
6 Verify the phase voltage imbalance is no greater than 10%.
7 Verify that gas piping is complete and leak tight.
8 Verify that the shutoff cock is installed ahead of the
furnace, and that all air has been bled from the gas lines.
9 Manually rotate all fans and verify that they rotate freely.
10 Verify that the belts are tight and the sheaves are aligned.
11 Verify that all setscrews and fasteners on the fan assemblies
are still tight. Do this by reading and following the instructions in “Setscrews,” which is in the “Maintenance” section of this manual.
12 Verify that the coding coil condensate drain is trapped and
that the drain pan is level.
13 If unit is curb mounted, verify that the curb is properly
flashed to prevent water leakage.
14 Before attempting to operate the unit, review the control
layout description to become familiar with the control locations.
15 Review the equipment and service literature, the sequences
of operation, and the wiring diagrams to become familiar with the functions and purposes of the controls and devices.
16 Determine which optional controls are included with the
unit.
17 Before closing (connecting) the power disconnect switch,
open (disconnect) the following unit control circuit switches:
a Main Control Panel
– Turn system switch S1 to OFF.
– Electric heat units: turn switch HS1 to OFF.
b Furnace Control Compartment
– Turn furnace switch S3 to OFF.
– Main Control Panel Switch
S7 to OFF.
McQuay IM 487-5 97
Check, Test, and Start Procedures
18
If the DAC or SCC unit does not have an optional zone temperature sensor (ZNT1) connected to it, you may need to change the keypad entry under Setup/Service \ Unit Configuration \ Space Sensor= from YES to NO.
Note – If desired, you can significantly reduce all MicroTech II
internal control timers by the changing the entry under keypad menu Setup/Service\Unit Configuration\Timer Settings\Service= from “0 min” to “X min” where X is the number of minutes you want the unit to operate with fast timers.

Economizer Start-up

CAUTION
Adjust dampers properly. Improper adjustment can damage the dampers. When an economizer is ordered without an actuator, the linkage requires a 3.14" linear stroke to open it fully. Do not allow dampers to be driven beyond their normal full closed or full open position.

Power Up

1 Close the unit disconnect switch. With the control system
switch S1 in the OFF position, power should be available only to the control circuit transformer (TI) and the compressor crankcase heaters.
2 Turn the Switch S1 to ON. Power should now be supplied
to the control panel and the LEDs on MCB1 should follow the normal startup sequence (refer to the “MCB LED Power-Up Sequence” of IM 696).

Fan Start-up

1 Verify all duct isolation dampers are open. Unit mounted
isolation dampers may be mounted in the supply or return sections.
2 Place the unit into the “Fan Only” mode through the
keypad menu System Summary\System\Ctrl Mode= Fan Only.
3 Turn Switch S7 to ON. The controller should enter the
“Startup Initial” operating state. If the fan does not run:
a Check fuses F1 and F3.
b Check the manual motor protectors or that the circuit
breakers have not tripped.
c Check the optional phase monitor.
4 If the fans are equipped with optional spring isolators,
check the fan spring mount adjustment. When the fans are running they should be level. Refer to “RAH spring mount hold down fasteners” on page 52.
5 Verify the rotation is correct.
6 Verify the DHL safety is opening at a pressure compatible
with duct working pressure limits.
Note – The supply and return fan drives usually are selected for
operation in the drive's midspeed range. The return fan drives are usually shipped with fixed pitch sheaves that will provide the selected fan speed; however, the supply fan drives are usually shipped with variable pitch sheaves that are adjusted to provide the minimum fan speed. Both drives should be adjusted for proper airflow during air balancing. For more information, refer to “Air Balancing” on page 99.
1 Check whether the outdoor air is suitable for free cooling
by displaying the keypad menu Temperature\OA Damper\OA Ambient=. “Low” indicates low outdoor air
enthalpy; “High” indicates high outdoor air enthalpy. See “Enthalpy Control” on page 85 to verify that the enthalpy changeover control is working properly. You may want to take temperature and humidity measurements.
2 Verify that switches PS1 and PS2 are at OFF. This prevents
compressor operation during the procedure.
3 At the keypad, set the cooling setpoint low enough so the
controller calls for cooling. Adjust the value in Temperature\Zone Cooling\Occ Clg Spt= below the temperature shown in Temperature\Zone Cooling\Control
Te mp =. In addition, on DAC units, adjust the value in Temperature\Discharge Cooling\DAT Clg Spt= below the temperature shown in Temperature\Discharge Cooling\Disch Air=.
4 Place the unit into cooling mode through the keypad menu
System Summary\System\Ctrl Mode= Cool Only.
5 Observe the outdoor air dampers:
a If the outdoor enthalpy is low, the control algorithm
should start to modulate the dampers open to maintain the discharge air setpoint.
b If the outdoor enthalpy is high, the dampers should
maintain their minimum position. Look at menu Temperature\OA Damper\MinOA Pos=. Change this entry to another value. Verify that the dampers move to the new minimum position setpoint.
6 If the unit is equipped with the electromechanical enthalpy
changeover control (Honeywell H205) and the outdoor air condition is borderline, attempt to change its input to the MicroTech II controller by turning the switch adjustment to “A” or “D.” Check enthalpy status in keypad menu Temperature \ OA Damper \ OA Ambient=. If this reading is “Low,” go to step 5a. If it is “High,” go to step 5b.
Note – It may not be possible to check the economizer operation
in both low and high enthalpy states on the same day. If this is the case, repeat this procedure on another day when the opposite outdoor air enthalpy conditions exist.
98 McQuay IM 487-5
Check, Test, and Start Procedures

Heating System Start-up

General
1 At the keypad, set the heating setpoints high enough so that
the controller will call for heating. The value in Temperature \ Zone Heating \ Occ Htg Spt= will need to be adjusted above the temperature shown in Temperature \ Zone Heating \ Control Temp=. In addition, on DAC units, the value in Temperature \ Discharge Heating \ DAT Htg Spt= will need to be adjusted above the temperature shown in Temperature \ Discharge Heating \ Disch Air=.
2 Place the unit into heating mode through the keypad menu
System Summary \ System \ Ctrl Mode= Heat Only.
3 Verify that the high ambient heat lockout temperature
setpoint, Temperature \ Zone Heating \ OATHtg Lock= is set above the current outside air temperature (shown in System Summary \ Temperatures \ OA Temp=).
Gas Furnace
Refer to the “Start-up and Operating Procedures” section of the Forced Draft Gas Fired Furnace Installation Manual, Bulletin No. IM 684 or 685. Perform the start-up procedures given in it.
Electric Heat
Turn the electric heat switch HS1 to ON. The electric heaters should energize. If the unit has multistage electric heat, the MicroTech II Auxiliary Control board EHB1 should energize the heaters in successive stages. The rate of staging is set in keypad menu Setup/Service \ Heating Setup \ Stage Time=. The default value of “5 min” can be adjusted from 2 to 60 minutes.
Steam Heat
The steam valve actuator should open the valve. The steam valve is open when the valve stem is up. If the unit loses power, the spring in the actuator should drive the valve wide open. Check this by opening system switch S1.
Hot Water Heat
The hot water valve actuator should open the valve to the coil. The three-way hot water valve is open to the coil when the valve stem is down. If the unit loses power, the spring in the
actuator should drive the valve wide open to the coil. Check this by opening system switch S1.

Air Balancing

Air balancing should be performed by a qualified air balancing technician. Note that the supply fan motors are usually shipped with variable pitch sheaves which are typically set at the low end of the drive’s fan rpm range. See “Mounting and Adjusting Motor Sheaves” on page 101. The return fan motors are
usually shipped with fixed pitch sheaves.
WARNING
Moving machinery hazard. Can cause severe personal injury or death. Do not use a mechanically driven tachometer to measure the speed of return fans on this fan arrangement. Use a strobe tachometer.
The following should be performed as part of the air balancing procedure:
1 Check the operating balance with the economizer dampers
positioned for both full outdoor air and minimum outdoor air.
2 Verify that the total airflow will never be less than that
required for operation of the electric heaters or gas furnace.
3 For VAV units that have fan tracking control, adjust the
supply/return fan balance by using the MicroTech II controller's built-in, automatic capability. For complete information on using this feature, see the “Return Fan Airflow Control: Fan Tracking” section in Bulletin No. OM 137, “MicroTech II Applied Rooftop Unit Controller.”
4 When the final drive adjustments or changes are complete,
check the current draw of the supply and return fan motors. The amperage must not exceed the service factor stamped on the motor nameplate.
5 Upon completion of the air balance, replace variable pitch
motor sheaves (if any) with comparably sized fixed pitch sheaves. A fixed pitch sheave will reduce vibration and
provide longer belt and bearing life.
WARNING
Rotating parts can cause severe personal injury or death. Replace all belt/fan guards that are temporarily removed for service.
McQuay IM 487-5 99
Check, Test, and Start Procedures
e

Sheave Alignment

Mounting:
1 Verify both driving and driven sheaves are in alignment and
the shafts are parallel. The center line of the driving sheave must be in line with the ce1nter line of the driven sheave. See Figure 109.
2 Verify that all setscrews are torqued to the values shown in
Table 20 on page 111 before starting drive. Check setscrew torque and belt tension after 24 hours of service.
Figure 109: Sheave alignment (adjustable shown)
M u s t b e p a r a l l e l
B e a r i n g
M o t o r
C e n t e r l i n e s m u s t c o i n c i d

Drive Belt Adjustment

General Rules of Tensioning
1 The ideal tension is the lowest tension at which the belt will
not slip under peak load conditions.
2 Check tension frequently during the first 24 - 48 hours of
operation.
3 Over tensioning shortens belt and bearing life.
4 Keep belts free from foreign material which may cause
slippage.
5 Make V-drive inspection on a periodic basis. Adjust tension
if the belt is slipping. Do not apply belt dressing. This may damage the belt and cause early failure.
Tension Measurement Procedure
1 Measure the belt span. See Figure 110.
2 Place belt tension checker squarely on one belt at the center
of the belt span. Apply force to the checker, perpendicular to the belt span, until the belt deflection equals belt span distance divided by 64. Determine force applied while in this position.
3 Compare this force to the values on the drive kit label
found on the fan housing.
M u s t b e p a r a l l e l
A d j u s t a b l e S h e a v e
Figure 110: Drive belt adjustment
D e f l e c t i o n =
B e l t S p a n
B e l t S p a n
6 4
100 McQuay IM 487-5
Loading...