McQuay PLH048 Installation Manual

Page 1
Installation Instructions For
CENTRIFUGAL WATER CHILLERS
LESS CONDENSERS
Models
13600 Industrial Park Blvd., P 0. Box 1551,
PLH
046, 079,
Minneapolis
048, 087,
MN 55440
050,
100
063
Page 2
Page 3
Page 4
GENERAL
The less condenser chiller unit is partially factory as­sembled, wired and checked. Installation (by others) will re­quire piping, power, and control interlock connections to the machine. Factory mounted and wired compressor motor starters are available as an optional accessory. All units are shipped with a holding charge of refrigerant.
All rigging, installation, power and control wiring and refrig­erant piping are the responsibility of the installer. Recommen­dations for the installation of the less condenser unit are pro­vided in the paragraphs following.
IMPORTANT: The responsibility and/or duties of the installer and McQuay at the time of startup are de­tailed in the startup section on page 11. It is important that the installer be aware of the limits of this respon­sibility since McQuay startup services beyond these limits will only be performed after written authorization has been obtained from the owner and/or installer.
Do not under any circumstance make final power connections to the unit mounted starter (when supplied) or to the compressor terminals when a remote starter is used. The compressor cannot be put in operation un­til the the McQuay service technician has checked the unit installation and electrical phase sequence for pro­per compressor rotation.
McQuay equipment when applied to perform the duty for which it has been designed, and when it is operated within limits of the design specifications, will provide safe and depen­dable service.
CAUTION
DO NOT ABUSE THE EQUIPMENT.
MODEL NOMENCLATURE
PLH -
0635 - AE - 30R I E2212 - GB - 2RA
Nomenclature Change: The 2-letter model code new code for PE chillers less condenser
IO12
(“L”
at the end of
“PL”
is a
the old model number signified less condenser). The letter “H”
has been added behind the first two digits of the model code to signify a hermetic compressor motor. Model PLH is synonymous with model PE-L.
UNIT NAMEPLATE
Whenever requesting information or assistance on the model PLH water chilling unit, the unit model number, shop order number and serial number should be copied from the unit nameplate. A reproduction of this nameplate is shown in Figure 3.
Figure 3. Unit Nameplate
Do not step on any piping or climb over the machine. Do not exceed test pressures. Be sure to verify
allowable test pressure for the McQuay unit and other items in the piping system.
Be sure all pressure relief devices are correctly in­stalled. When vent piping to the outside is utilized, be sure piping has a flexible connection and a drain to prevent buildup of rain water or condensate. See Figure 7.
Do not use oxygen to purge or apply pressure to a unit or system for any reason.

RECEIVING THE EQUIPMENT

1. CHECK EQUIPMENT before removing it from the ship- ping vehicle. The unit nameplate contains the unit model number, serial number, etc. Figure 3 indicates the infor- mation
contained on the nameplate. Check the nameplate data against shipping papers and job information. Pay careful attention to voltage characteristics. (Check voltage on compressor nameplate.)
HOLDING
CHARGE
ONLY
MODEL
STYLE
SERIAL S.O. NO.
\
I
PLH~J
1
PE5210-GO1
5NAl23~500 ~~
PE-5210
FACTORY CHARGED
_
LBS. REFRIGERANT=
LEAK TEST PRESSURE
MOTOR - COMPRESSOR CONTROLLER
AND OVERLOAD PROTECTION FIELD
SUPPLIED. SEE SPEC. PE-D4
19SP1Wi01-A MADE IN U.S.A.
100 PSIG.
2. INSPECT the unit while it is still on the shipping vehicle, record any damage and note whether or not unit has been
torn from the shipping skid. In the event that the unit has lost the refrigerant holding charge, look for damage to
refrigerant lines and connections. See testing and
evacua­tion section on page 9. Have all damage checked by the transportation inspector or their representative before
Page 4
/
IM 310
Page 5
removing the unit from the vehicle. Promptly forward claim forms directly to the carrier. Notify the nearest McQuay sales office or representative of any item missing from the shipment.
NOTE: All equipment furnished by McQuay is shipped F.O.B. factory and all claims for handling
3. RIGGING. Lift unit only from points indicated in Figure 2. Where required, use a spreader bar to prevent damage to the unit. Be sure rigging equipment and procedures

INSTALLATION

followed are adequate to handle the unit weight. When skidding the unit, be sure a minimum of 3 rollers are used. Under no circumstances should the unit be dragged with or without the skid.
PROTECTION. The unit assembly and starter (where separate) must be adequately protected against dirt, moisture and freezing during construction.
Chillers are drained of water before leaving the factory. The chiller is not self-draining and must be blown out to remove water if water has been added at the jobsite. When the unit will be exposed to low temperatures during con­struction, a small amount of antifreeze should be put in the chiller to protect it from freezing.
1.
CLEARANCES. A clearance for chiller tube removal at one
end of the unit must be provided. This clearance is
for shells with
1
2-foot
tubes. For all other unit sides and top, a clearance
8-foot
tubes and 14 feet for shells with
10 feet
of 3 feet is required.
2. UNIT SUPPORT. The floor or structural support must be level and adequate to handle the full operating weight of
the unit. Operating weights for units are shown in Table
3. VIBRATION ISOLATION
a. “lsomode” or “Shearflex” pads are supplied with the
unit for installation under each corner of the
Unit
base
members.
It is not normally necessary to attach the unit to the concrete slab or framework, but should this be desirable,
1%” diameter holes are provided as shown
on the submittal drawings for the unit.
Figure
4. Typical Installation of Standard Isolation
UNIT TUBE
SHEET SUPPORT
r
ISOMODE
FURNISHED WITH
PAD
“NIT
Note: Pads are shipped stored
in the switch section
of the control center. Spring Isolators supplied by others may be placed
b.
under base support plates on both ends of the unit. Job information should contain details on type and arrange­ment. Figure 5 shows a typical installation of spring isolators. Spring isolation is not generally required but
1.
may be necessary if the unit is installed on the upper floor of a building.
Table 1. Rigging 81 Operating Weights (Less Condenser)
(For weights of other
EYmtm
OODE
combinations,
RfQKOIWQ
WT.
(MS.)
cp
see certified drawings)
OPERATtAKS
WT.
OD
(LB%)
luooeLI tI4@, 048, oao
El 606-A’
-0’
E2006-1
l
-2’
E2012-C’
E2212-G’
E1612.1
I I
-D’
-E’
-J’
I
2102 2203
2637 2726
3060 3262 3416
3533 3633
McBaEL
3399
I I
033
I
2616 2697
3401 3470
4210 4372 4566
4665 5145
4088
LEVEL SUPPORT
BASE
Figure 5. Typical Installation of Spring Isolators
llN,T
BASE
ATTACH SECURELY
TO VIBRATION
\
LEVEL FLOOR OR SUPPORT NEOPRENE PAD
SUPPORl
-4 4426
E2016-1
-2
-3 4959
-4 5065
E2212-1
-2 4536
-3 4637
E2216-1
-2
-3
-4 6823
r&m% m
MOlM&tia7..‘.....,.
f#%@kL
%
Rigging Weight: Unit Weight + Holding Charge of Refrigerant
0
Operating Weight: Rigging Weight + Water Weight + Operating Charge
of Refrigerant
. . . . . . . . .
toO .
. . . . . I. .
4619 4671
4457
4894
6539 6665
Add
35s Fb8.
to
Add
11@6 Lb. to osl)
*
Add
1972 Lbs. to 003
063 Evaporator WsiQhts
Evaporator Weights
Evaporator
5450 5915
6167 6255 6381
5675 5756 5655
6334
9103 9229 9387
WelaMs
IM 310 I Page 5
Page 6

PIPING

General - Chiller water and refrigerant piping connections
to the unit are required and good piping practice must be followed during installation. All piping should be installed per specific job piping drawings and details covered by these drawings. In addition, the details and provisions following
below must be considered.
Adequate attention must be paid to the support and isola-
tion of piping particularly when spring type vibration mount-
ings are used. WATER PIPING
NOTE: Chiller inlet and outlet connections are marked. Do not reverse these connections or the unit cooling capacity will be reduced.
Chiller connections will accommodate grooved piping con-
1. nections or weld type flanges, or if ordered, the unit can be factory supplied with flanges installed. See job details for specific arrangement. Chiller water heads can be in­terchanged end for end. If this is done, new gaskets must be used.
Offset piping flanges (see Figure 6) to permit removal of
2. the pipe sections between the evaporator stubs and the pipe flanges for general maintenance or to permit head
removal for tube inspection.
Air vents should be installed at high points to remove air
3. from the system which, if not removed, can cause erosion and other problems.
Chilled water flow switch or pressure differential switch,
4. when used, must have a vapor tight construction. The flow
switch must be installed in a horizontal run a minimum of five pipe diameters from any bend and must be located in a vertical position at the top of the pipe.
Water Pump Noise. Avoid two pole (3600 rpm) water
5. pumps. This design of pump can quite often operate with
objectionable noise and vibration. It is also possible to create a “frequency beat” because of the slight vibration difference between the pump motor and centrifugal com­pressor. We encourage the use of 1740 rpm (four pole) motors on water pumps whenever possible.
6.
Water Flow. Located on the chiller heads are
l/B”
test cocks for venting and draining. Chiller pressure drop in­formation is available through your McQuay sales repre­sentative.
1.
UIL COOLER PIPING
Model PLH
046,048,050
and 063 units include a refrigerant cooled oil cooler piped into the chiller system as standard. This oil cooler does not require field piping connections. Model PLH 079,087 and 100 units are supplied as standard with a water cooled oil cooler. (A refrigerant cooled oil cooler is available as an optional accessory.)
The water cooled oil cooler is factory mounted with all oil piping provided. Water piping to this cooler must be field sup­plied and installed. The installation of water piping should follow accepted good piping practice. Piping should include inlet and outlet shutoff valves, a cleanable strainer (40 mesh maximum), a balancing valve, a solenoid operated shutoff valve (field wired into the unit control circuit as indicated on the unit wiring information), and a drain valve or removable
plug.
Water for the oil cooler can be obtained from any of the following sources.
1. The chilled water circuit. This water source is preferred and is strongly recommended.
2. An independent water source such as city water or other domestic source.
3. Cooling tower makeup water circuit. Note: The use of con­denser water from a cooling tower is not recommended
because of the dirt and contamination contained in such
water.
Oil cooler water piping must be sized using not less than
the gpm shown in the table below. At the time the centrifugal
Figure 6.
NOTES:
1.
Offset piping flanges to allow removal of water head(s) for tube clean­ing or maintenance.
2.
Install air vents at high points in water piping.
3.
Locate flow switch in horizontal pipe run. Switch should be in vertical position a minimum of five (5) pipe diameters from any bend. if ferential pressure switch is used in lieu of a flow switch, it should be installed across the chilled water vessel, not across the water pump.
4.
Be sure water flow is into unit through nozzle marked “inlet.” Some vessels require water inlet on the bottom nozzle; some on the top.
INSTALL
l/8”
Et
DRAIN VALVES
VENT
dif-
GROOVED TYPE COUPLINGS OR
CHILLER
CONNFLTIONS
SUITABLE FOR
COUPLlNtiS
OR
GROOVEU
WELDFO / LDb.<,t’
NOTE
F, ANGEI‘I
PIPE
THEY
cITTINf,S ARE
MAY
BE SCREWED
SHDWN
CONNECTIONS IF SIZING PERMITS
Page 6 / IM 310
Page 7
unit is checked out and started, the McQuay technician will adjust the water flow through the oil cooler to maintain oil temperature leaving the cooler at an acceptable level.
Water Flow Rate for Oil Cooler Pipe Siring’
should the oil cooler be piped in parallel with a single pass
evaporator.
Units are available with oil cooler water solenoid valves fac-
tory supplied and mounted. On units where the solenoid valve
is field supplied, the solenoid valve recommended is an ASCO
type 8210827 (McQuay part
alternate
valve
is considered it should be of comparable quali-
#350A484H45).
If the use of an
ty and McQuay approved.
*CAUTION: Water temperatures entering the oil cooler should not exceed 90 o F unless the application has been approved by McQuay.
Recommended oil cooler piping is illustrated in Figure 7.
On some applications, where chiller water is used for oil cool-
ing and the unit is shut down for extended periods of time over a weekend or for other reasons, the chilled water loop temperature can substantially increase above the normal
chilled water temperature. Should this occur, the use of a
temperature actuated modulating water valve or other con-
trol means may be required to adjust water flow when the
unit is restarted. The purpose of this control is to compen-
sate for the effect of the different water temperatures on oil
temperature leaving the oil cooler when the unit starts and
after it has run and dropped the chilled water temperatures.
Figure 7.
r
Oil Cooler Connected Across Pump
RELIEF VALVE PIPING
The
ANSI/ASHRAE
Standard
15-1978
specifies that pressure relief valves on vessels containing Group 1 refrigerants (R-12 and R-500) “shall discharge to the atmosphere at a location not less than 15 feet above the adjoining ground level and not less than 20 feet from any window, ventilation opening or exit in any building.” The piping must be provided with a rain cap at the outside terminating point and a drain at the low point on the vent piping to prevent water buildup on the atmospheric side of the relief valve. In addition, a flexible pipe section should be installed in the line to eliminate any piping stress on the relief valve(s).
The size of the discharge pipe from the pressure-relief valve shall not be less than the size of the pressure relief outlet. When two or more vessels are piped together, the common header and piping to the atmosphere shall not be less than the sum of the area of the relief valve outlets connected to the header. Fittings should be provided to permit vent pip­ing to be easily disconnected for inspection or replacement of the relief valve. Larger size piping may be required if the piping length is long. If in doubt, contact the local inspector.
Note: Provide adequate fittings in piping to permit repair or replacement of relief valve.
Figure
8. Relief Valve Vent Piping
CAP
Independent Water Source
WATER LEAVING OIL COOLER CAN
\GO
OR ‘VNVE
L
TO OPEN SIGH DRAIN OR INTO COOLING TOWER
T
When the oil cooler is piped into the chilled water circuit, the oil cooler water piping system should be connected across the chilled water pump so that full pump pressure differen-
tial is maintained across the oil cooler at all times the pump is running. For those systems where it may be desirable to pipe the cooler in parallel with the evaporator, it can only be done when the evaporator water pressure drop is equal to or greater than the pressure drop through the oil cooler water piping system.
On installations utilizing an independent water source such as city water makeup to a cooling tower, the water must be piped from the oil cooler to the cooling tower where it must
enter at a point above the highest possible water level. If the
water is not utilized in the cooling tower then it must be dis-
posed of through an open drain. Under no circumstances
FO
CONDENSAilON
PITCH TO OUTSIDE
I
FLEXIBLE CONNECTION INSTALL AS CLOSE AS
POSSIBLE TO
VALVE
RELiEF
7
REFRIGERANT EVAPORATOR
m
kv
OUTSIDE WALL
3.
EVAPORATOR
-RELIEF
VALVE FACTORY SUPPLIED MOUNTED AT EVAPORATOR
VENT
I
15FT
MINIMUM
CLEARANCE TO GROUND LEVEL
ISEE
ADJACENl
INFORMATION1
IM 310 I Page 7
Page 8
Page 9
nished with grooves on one end and will have to be con­nected to the unit before piping connections are made.
The discharge connection at the unit is shipped capped.
Before attaching the discharge line section, relieve the refrigerant pressure, remove the cap and use the same
grooved coupling to secure the discharge line in place.
Discharge and liquid line connections to the unit can be run in either copper or steel.
Remote air or evaporative condensers must have an adequate means for controlling head pressure. Operating head pressure’should not be permitted to drop below 75 psig on units utilizing either R-12 or R-500 refrigerant or erratic expansion valve operation can be expected.
IMPORTANT The expansion valve supplied with the unit requires a 45 psig minimum pressure difference across it for proper operation. Provisions must be made to assure this during periods of low outside tempera­tures.
IMPORTANT Figure 9 is applicable to systems where the con­denser is above or on the same level as the cen­trifugal chiller. When the unit is above the con­denser, the liquid lift from the condenser to the chiller is limited to 20 feet. When liquid lifts greater than 20 feet are necessary, liquid subcooling from an auxiliary source will be required. Contact your McQuay sales representative for recommendations.
The McQuay Applications Department is available to assist on piping questions.
3. Refrigerant Lines. The job data should contain detailed information on refrigerant line sizes and runs. McQuay refrigerant line sizing data
is available
where refrigerant lines must be sized or checked. In addition, McQuay Ap­plications Department personnel are available for consulta­tion on piping details where required.
The liquid line piping must contain a refrigerant drier with removable cores. The cores should be left in the line until there are no traces of abnormal moisture levels. The cores should then be removed. Piping should be ar­ranged to permit bypassing the drier or valving it off for core removal. See Figure 9.
Where an evaporative condenser is used, a subcooing coil and an operating liquid receiver are required to con­tain adequate system refrigerant for both full load and part load operation.
Oil circulation in centrifugal systems is negligible. The
use of double risers is not generally required. A
typical piping arrangement for a remote air cooled or evaporative type condenser is shown in Figure 9.
4. Hot Gas Lines. Pressure drop in the hot gas line should be limited to the equivalent of
1
to 2 degrees. A hot gas
check valve (with low pressure drop) should be installed
in the discharge line just ahead of the condenser inlet gas
connection to limit refrigerant migration during periods when the compressor is not operating.
If refrigerant velocity noise may be a problem, or if the
piping will be run in, or near, an occupied space, the use
of a steel discharge line is recommended.
The McQuay Applications Department is available to
assist on piping questions.
5. Pressure Testing. No pressure testing is necessary
unless damage was incurred during shipment or rigging.
Damage may be determined by a visual inspection of the exterior piping assuming no breakage has occurred or fit-
tings have loosened. Panel gauges should show a positive pressure. If no pressure is evident on the gauges, a leak has probably occurred releasing all or part of the refrigerant charge. In this case, the unit should be leak tested.
6
Leak Testing. If the refrigerant holding charge is lost, the unit should be checked for leaks prior to charging the com­plete system. Leak testing can be accomplished by charg­ing enough refrigerant into the unit to build the pressure to approximately 10 psig and adding sufficient dry nitrogen to bring the pressure to a maximum of 125 psig. The unit should then be leak tested with a Halide or electronic leak detector. Water flow through the chiller should be main­tained any time refrigerant is added or removed from the system. CAUTION: Do not use oxygen to build up
pressure. A serious explosion could result.
A pressure regulating valve should always be utilized on the drum be­ing used to build up the system pressure. The regulating valve must be set not to exceed the 125 psig test pressure.
When the test pressure is reached, disconnect the gas cylinder to prevent an accidental further increase in pressure.
If the leaks are found in welded or brazed joints or it is necessary to replace a gasket, relieve the test pressure in the system before proceeding. For copper joint repair, the use of silver solder is recommended.
After making any necessary repairs, the system should
be evacuated as described in the following paragraphs.
7
Evacuation. After it has been determined that the unit is
tight and there are no refrigerant leaks, the unit should be evacuated. The use of a vacuum pump with a pump­ing capacity of approximately 3 cu. ft./min. and the ability to reduce the vacuum in the unit to at least 1 millimeter (1000 microns) is recommended.
a.
A mercury manometer, electronic or other type of micron gauge should be connected to the unit at a point remote from the vacuum pump. For readings below 1 millimeter, an electronic or other micron gauge should be used.
b.
The triple evacuation method is recommended and is particularly helpful if the vacuum pump is unable to ob­tain the desired 1 millimeter of vacuum. The system is first evacuated to approximately 29 inches of mer­cury. Enough refrigerant vapor is then added to the system to bring the pressure up to zero pounds.
C.
Then the system is once again evacuated to approx­imately 29 inches of mercury. This is repeated three times. The first pulldown will remove about 90% of the non-condensables, the second about 90% of that re­maining from the first pulldown, and after the third on­ly one-tenth of 1% of the non-condensables will remain.
8.
Charging the System. Less condenser units are leak
tested at the factory and shipped with a holding charge of refrigerant.
a. After all refrigerant and water piping is complete and
the system has been leak tested and evacuated,
refrigerant charging can proceed as described in the following paragraphs. (Do not under any circumstance start the compressor.)
b. Turn on the condenser fans (on evaporative type con-
densers also turn on the spray pump), chilled water pump and the main system fans. (It will be necessary to manually close the chilled water pump starter.)
c. Connect the refrigerant drum to the purge valve located
ahead of the filter-drier and purge the charging line be-
tween the refrigerant cylinder and the valve (Check the
position of the valves at the liquid receiver.) If the system is under a vacuum, stand the refrigerant drum
with the connection up and open the valve on the
IM 310
/
Paae
9
Page 10
refrigerant drum to the mid-position and break the vacuum with refrigerant gas. With system gas pressure higher than the equivalent of a freezing temperature, invert the charging cylinder and elevate the drum above the purge valve. With the drum in this position, valves, open, water pumps and system fans operating, liquid refrigerant will flow into the system. Approximately 25% of the total requirement estimated for the unit can be charged in this manner. After 25% of the required charge has entered the system, reconnect the refrigerant drum and charging line to the compressor. Again purge the connecting line; stand the drum with the connection up and place the service valve in the open position. The charge can be raised to approximately 50% in this manner. Once approx­imately 50% of the system charge has been installed, shut off the drum and disconnect the charging line.
5/B”
service valve on the suction line at the

ELECTRICAL

All wiring must, as a minimum, satisfy the requirements of the National Electrical Code and where necessary local code
requirements. Motor starters must meet the McQuay starter specifications contained in Certified Drawing 461451Y (copies will be supplied on request).
IMPORTANT
At this point the charging procedure should be
interrupted and prestart checks made before at-
tempting to complete the refrigerant charge. The
compressor must not be started at this time.
Preliminary checks as covered by the checklist on page 12 must be completed.
When these checks have been completed and your McQuay sales representative is notified, he will request a McQuay technician to do the ac­tual startup.
IMPORTANT
If any
unit
out by a McQuay technician the unit warranty
may be voided.
Wiring connections to a unit mounted starter or compressor terminal studs must be made with cop­per lugs and copper wire.
is started before it has been checked
CAUTION:

POWER SUPPLY

Voltage supplied to this unit must be held within the allowable variation of
Nameplate rating = 253V,
balance between phases cannot exceed 3%. A voltage un-
balance of only 3.5% will cause an increase of approximate-
ly 25% in motor winding temperature. It is most important
that the phase voltage unbalance be held to 3% or less.

Power Wiring

tory wired and mounted compressor motor starters (starters
are Star-Delta type open or closed transition as required by
the job specifications), or less starters for use with a free
standing starter.
It is important that the proper phase sequence be main­tained in the power wiring with a phase sequence of l-2-3. The proper motor rotation is clockwise when facing the motor end of the compressor.
When a free standing starter is used which requires field supplied wiring, care must be taken to be sure the right phase sequence is carried through the starter to the compressor
motor terminals.
With the phase sequence l-2-3 and and T6, L2 connected to T2 and T4 and L3 connected to T3
and T5, rotation is correct. See the diagram in the terminal box cover of the compressor motor.
Phase sequence may be determined using a G.E. #546703265 phase sequence meter or equal. Before connec­ting the starter load leads to the compressor terminals, and while checking the field connection wiring, the transition timer
in the starter should be adjusted to make the transition from Star to Delta connection in approximately 6 to 15 seconds
from initial start. This should be rechecked when the com-
pressor is put on the line. The timer should be adjusted to actuate (disconnect Star winding connection and connect
Delta) when the motor has come up to speed and before any
speed reduction occurs.
f
10% of the unit nameplate rating. Example:
minimum allowable voltage =
23OV,
maximum allowable voltage =
-
Less condenser units are available with fac-
207V.
Ll
connected to
Voltage un-
Tl
IMPORTANT:
Do not make final power connections to the starter un-
til wiring has been checked and approved by an
authorized McQuay service representative. Under no circumstances should the compressor be brought up to speed unless proper phase sequence and rotation have been established.
The McQuay startup technician will make this check
as part of the startup procedure.
CONTROL WIRING The unit control circuit is designed for operating on a separate power circuit. When factory mounted and wired, starters are supplied as part of the unit assembly, a 2 KVA control transformer is included and a separate power source to the unit control center is not required.
Where separate free standing starters are used, a
115V160Hz
center is required. This power source can be provided through a control transformer installed in the motor starter. The transformer should have a rating not less than 2 a minimum inrush rating of 12.5 KVA at 80% power factor and 95% secondary voltage. Transformers should have multi­ple taps to provide
For control wire sizing, refer to Table 3 or the National Elec­trical Code, Article 215 and 310.
Either power source should be properly fused with 20 amperes dual element fuses, or with a circuit breaker selected for motor duty. (The oil pump motor is in this control circuit.)
When starters are factory mounted, adequate control power
and circuit protection will be included.
If the control transformer or other power source for the con­trol panel is remote from the unit, conductors must be sized for a maximum voltage drop of 3% (see Table 3). The con­trol circuit ampacity rating is 20 amperes at 115 volts.
or 1
lOV150Hz
*
power source to the unit control
KVA,
10% voltage variation of the transformer.
with
Page 10
/
IM 310
Page 11
CAUTION: The control power disconnect switch
must be tagged to prevent power interruption. It
must remain on at all times to keep oil heaters operative and to prevent refrigerant from ac­cumulating in the oil.
L
The control center on-off switch should be turned to the
OFF position whenever compressor operation is not wanted.
Table 3. Maximum Conductor
*Maximum length is distance conductor will traverse between control power source and the unit control panel. Wire size based on voltage drop not to ex­ceed 3%.
Panel terminal connectors will accommodate wire size up to IO AWG; larger
conductors will require an intermediate junction box.
Length’
CONTROL INTERLOCKS An open section has been provided in the unit control panel
for the installation of interlock contacts (see unit electrical diagram for location). The purpose of the open section is to prevent the compressor from operating until external devices
necessary for the proper operation of the unit are functioning.
The condenser fans (and spray pump if used) must cycle with the unit and the fans must be interlocked in the control circuit to prevent the compressor from operating until the con­denser fans are running. Relay CFR (field supplied) on the
unit electrical diagram identifies the condenser fan interlock relay which must have a set of normally open contacts in-
stalled in series with the MCR coil located in the compressor
motor starter or with the panel mounted protective relay in the control panel. In addition to the CFR relay contacts, the use of a flow or pressure differential switch located in the chilled water piping is recommended. The contacts of this flow switch must be wired in series with the CFR contacts
in the interlock circuit. The volt ampere rating of the CFR coil
must not exceed 25 VA.
NOTE: All interlock contacts must be rated for a minimum of 10 inductive amperes. If an alarm circuit relay is utilized and is connected into the section provided for the alarm cir­cuit in the control panel, it must be rated for 115 volts and
its operating coil should draw not more than 100 volt amperes.

CONTROL CIRCUIT TESTING

After the power and control wiring has been completed, the control circuit should be tested “functionally.” During this testing the compressor must not be started. Power wire connections to the unit mounted starter must not be made or when a remote starter is used the load side wiring from the starter to the compressor motor must be disconnected.
1.
In cases where a separate control voltage source is fur-
nished, it is only necessary to energize the control circuit with the compressor disconnect switch open.
2. The McQuay startup technician will check the setting and operation of all unit safety and operating controls at the time of unit checkout and startup.
3. All field interlock connections should be checked for pro­per operation by stopping each pump in order. The motor control relay (MCR) should de-energize at the same time.
4. Stop the water pump. This also should open the starter circuit.
When all of the checklist items are complete, the services of a McQuay startup technician will be furnished at no charge to start the unit. If the startup time required to place the unit in operation exceeds 24 consecutive normal working hours, or if repeated calls are required through no fault of McQuay, charges for such extended services will be invoiced.
NOTE: THE MOST COMMON PROBLEMS DELAYING STARTUP AND AFFECTING UNIT RELIABILITY ARE:
Compressor motor power supply leads too small. Check with the McQuay sales representative to obtain proper wire size. A 115 volt field supplied relay (CFR) must be used to start and stop condenser fans on most applications. Provisions have been made in the control center for connecting the CFR relay. The relayoperating coil must not have a rating in excess of 25 VA.
CAUTION: Be sure all items on the checklist are com­plete and the unit is ready to be checked out and
started. If the startup technican is required to leave the job and return because owner/contractor items of responsibility are not complete and the unit cannot be started, the excess time and expense will be billed at McQuay’s
standard hourly service rate plus in-
curred expenses.
IM
310 / Page 11
Page 12
PRE-START SYSTEM CHECKLIST
(By Installing Contractor)
DIRECT EXPANSION
Piping complete
Main air system fans operable
Controls - dampers, solenoid valves, variable volume boxes, etc., operable
..................................................
........................................
NOT
APPLICABLE
E
L
...
CHILLED WATER
Piping complete
Water system filled, vented
Pumps installed, (rotation checked) strainers cleaned Controls (3-way, face and bypass dampers, bypass valves, etc.) operable Water system operated and flow balanced to meet unit design requirements
CONDENSER
Condenser flushed, filled and vented (if evaporative type), air cooled coils clean
Pumps installed, (rotation checked) strainers cleaned
Controls (bypass valves, etc.) operable
Water system operated and flow balanced to meet unit requirements
ELECTRICAL
115 volt service completed, but not connected to control panel ‘Power leads connected to starter: load leads run to compressor
ready for connection when service engineer is on hand for startup (Do not connect to starter or compressor terminals) All interlock wiring complete between control panel and complies with specifications Starter complies with specifications Pump starter and interlock wired Cooling tower fans and controls wired Wiring complies with National Electrical Code and local codes
*Condenser pump starting relay (CWR) installed and wired
MISCELLANEOUS
Oil cooler water piping complete. (Units with water cooled oil coolers only)
Relief valve piping complete
Thermometer wells, thermometers, gauges, control wells, controls, etc., installed.
Minimum system load of 25% of machine capacity available for testing and adjusting controls Refrigerant piping system has been evacuated and leak tested Approximately 50% of refrigerant charge has been added to system Additional refrigerant available on jobsite to complete charging system
................................................
............................................
...............................
.......................................
.........................................
.....................................
...........................................
........................
......................
................
................
...................
.......................
..........
.........
..........
..........
........
........
.....
...........
...........
...........
...........
0
q q q
0
0
n
q
q
........
STARTUP DUTIES OF McQUAY
1.
Inspect and check unit; verify all valves in operating position.
2.
Control circuit energized.
3.
Oil heaters operating a minimum of 24 hours and oil hot. (Ap-
proximately 130 to 140F)
Oil level correct.
4. Water flow to condenser correct (if applicable).
5.
6.
Check, set and adjust safety controls.
7.
Check that wire size and type is correct. Phase sequence correct.
8.
NOTES: When all of the checklist items are complete, the services of a McQuay startup technician will be furnished at no charge to start the unit.
If the startup time required to place the unit in operation exceeds 24 consecutive normal working hours, or if repeated calls are required
through no fault to McQuay, charges for such extended services will be invoiced.
NOTE: THE MOST COMMON PROBLEMS DELAYING STARTUP AND AFFECTING UNIT RELIABILITY ARE:
1.
Compressor motor power supply leads too small. Check with the McQuay sales representative to obtain proper wire size.
2.
A 115 volt field supplied relay (CFR) must be used to start and stop condenser fans on most applications. Provisions have been made in the control center for connecting the CFR relay. The relay operating coil must not have a rating in excess of 25 VA.
3.
CAUTION: Be
is required to leave the job and return because owner/contractor items of responsibility are not complete and the unit cannot be started, the excess time and expense will be billed at
sure all items on the checklist are complete and the unit is ready to be checked out and started. If the startup technican
McQuay’s
9.
Check voltage and phase unbalance.
Wiring connections correct.
10.
11.
All wiring connections right and made with copper connectors and lugs.
12.
Check that starter parts move freely and contacts meet evenly.
13.
Motor overloads correct and filled with dashpot oil.
14.
Supervise topping off refrigerant charge.
15.
Start unit; check operation.
16.
Instruct owner personnel.
standard hourly service rate plus incurred expenses.
Loading...