McQuay AEQ-30 Installation Manual

Installation & Maintenance Data IM 502-3
Group: Unit Ventilator Part Number: 106196501 Date: April 2000
Model AED, AEQ AAF-HermanNelson® Classroom Unit Ventilator
©2000 AAF-HermanNelson IM 502-3 (Rev. 4/00)
Wall Sleeve
Receiving Shipment
Before signing the freight bill, be certain that all items have been received and that there is no visible damage. Note any shortages and any damage on all copies of the freight bill. Each Model AEQ unit has been carefully inspected and operated at the factory to verify proper performance. It has been packed in a sturdy carton, was checked by the carrier during loading for shipment, and should arrive in perfect condition. However, if there is damage or any shortages, the purchaser is responsible for filing the necessary claims with the carrier. Concealed damage which was not discovered until after unloading should be reported to the carrier within 15 days after receipt. To help avoid concealed damage, the air conditioners must be shipped, handled and stored right-side up. A formal claim for any shortage or damage must be filed with the carrier within nine (9) months after delivery.
Table 1. (See note below)
UNIT UNIT
MODEL DEPTH WT., LB. HEIGHT WIDTH AEQ-24, AEQ-30 AEQ-36, AEQ-42 AEQ-48, AEQ-54
28 103 31 885 28 84 28 103 31 975 28 96 28 115 31 1075 28 108
AB
Figure A.
A
IMPORTANT:
1. Move only one unit at a time.
2. Do not drop unit.
3. Store in a clean and dry environment.
4. Lift only from designated end.
5. May be stacked maximum of 2 high.
6. To remove unit from skid, follow instructions
under "Uncrating Unit" on page 3.
SHIP WALL SLEEVE
39"
B
See Table 1 for unit weights and dimensions. Forklift type vehicles may be used to unload and move the unit. When using a forklift, it is important that the unit remain banded to its skid and be lifted only from the end designated on the carton. See Figure A. Forks on forklift should be a minimum of 36" long. Move only one unit at a time. Do not drop unit.
Storage
If an air conditioner must be stored prior to installation, find a clean, dry, protected, preferably heated area for storage until the equipment is needed. Keep within the carton during storage or handling.
Preliminary Installation
The location and installation of each Model AEQ unit should be carefully arranged to ensure convenient service access for maintenance and, if necessary, removal of the unit. If the unit has been in storage in an unheated area, care must be taken that the refrigerant circuit has had time to reach proper ambient temperature before attempting operation. The unit consists of two major sections: (1) the unit proper and (2) the wall sleeve. The wall sleeve contains the unit main power disconnect switch located in the wall sleeve junction box. All field connections are made inside the wall sleeve junction box (see page 8). The Model AEQ unit is designed to be installed through an outside wall. Installation will require that the wall sleeve be removed from the unit and installed before the unit is installed. See "Uncrating Unit" section. On many jobs, the louver and wall sleeve are shipped ahead of the unit itself. Installation instructions for these compo­nents are shipped with the individual components, as well as being included in this publication.
Uncrating Unit (Figure A)
The unit should be moved to the location at which it is to be installed before uncrating. Check tagging on unit carton to confirm that the unit is correct for the location. The carton is imprinted with the AAF-HermanNelson trademark which is the "front" or room side of the unit. The end of the carton marked "Truck from this end" should be on the right-hand side when facing the front of the carton.
NOTE: All dimensions are approximate only and are subject to change
without notice. Refer to approved submittal prints for rough-in details and construction purposes and for recommended wall opening size.
Page 2 / IM 502
Wall Opening Preparation
An opening in the outside wall is required to accommodate the wall sleeve and louver. The wall opening must be of sufficient size to allow proper, yet snug, fit of the louver and will depend on the type of wall. If the louver is to be installed in a masonry wall, there should also be a lintel to support the wall above the wall sleeve and louver. The opening should be sleeved to prevent moisture from seeping into the wall interior. Refer to
approved submittal prints for recommended wall opening size.
Remodeling Existing Buildings
If the Model AEQ unit is to be installed in an existing class­room, an opening must be cut in the outside wall to accommo­date the wall sleeve and louver. This is accomplished as follows: First, the outside of the wall is cut with a carborundum or other suitable blade as shown in Figure B. This opening should be slightly larger than the size of the louver supplied with the unit.
Figure B.
The inside wall is then knocked out in the area cut for the wall sleeve as shown in Figure D. If the wall consists of concrete block with brick (or other) veneer, and the louver opening is smaller than the opening the wall sleeve (which is to be recessed), be careful not to knock out more veneer than is necessary.
Figure D.
The completed opening is shown in Figure E. After the open­ing is finished, a lintel must be installed above the opening in masonry walls to support the remaining block and brick.
Next, the inside of the wall is cut as shown in Figure C. If any portion of the wall sleeve is to be recessed into the wall, the opening must be large enough to accommodate the wall sleeve (see Table 1, page 2). It is also possible to have a wall opening smaller than the wall sleeve; in which case, the sleeve will be nonrecessed and all of the unit will remain in the room. Other variations are also possible such as dual louvers, etc.
Figure C.
Figure E.
New Buildings
In new construction, if any portion of the wall sleeve is to be recessed into the wall, the opening must be large enough to accommodate the wall sleeve (see Table 1, page 2). For smaller wall openings the wall sleeve will be nonrecessed and all of the unit will project into the room. In all cases the bottom of the wall opening must be at the same height as the floor line. A lintel must be installed above the opening in masonry walls to support the block and brick.
IM 502 / Page 3
Wall Sleeve Installation
a
a
a
a
a
General — The wall sleeve must be installed before the unit can be placed. The wall sleeve measures 85", 96" or 108"wide by 28" high and may be recessed into the wall up to 11 depth.* Consult the approved AAF-HermanNelson submittal drawings for the job to determine the proper amount of recess,if any, and recommended wall opening size.
The wall sleeve is attached to the unit chassis (weld studs) using 4-nuts and washers, see figure 1.
The AAF-HermanNelson wall sleeve and louver design is based on a "wet sleeve" concept. In brief, this means the design accommodates the penetration of some moisture into the rear section of the wall sleeve with the provision being made for containment and disposal of this moisture to the outdoors.
It is necessary for that portion of the opening between the wall sleeve and the louver to be completely enclosed by the installer to prevent air and water leaks into the building.
Recessed and Nonrecessed Applications
The installing contractor shall do the following:
1. Make sure there is a masonry lintel supporting the wall
above any masonry opening.
2. Frame and seal air- and watertight all openings not enclos-
ed by the wall sleeve.
3. Refer to relevant figures for details of required sealing:
Figure 2 for all applications.
Figures 3 and 4 for recessed wall sleeve applications.
Figures 5 and 6 for nonrecessed wall sleeve applications.
4. Seal watertight both ends and top of wall sleeve to building
at rear flange of wall sleeve.
5. Seal watertight bottom of wall sleeve at rear "D" seal to
building and pitch toward louver bottom channel. Also
fasten cross channel to floor through holes with fasteners
(by others). See Figure 2.
6. The louver must be installed with the drain notches
located at the bottom and the bird screen located on
the unit side. Openings between notches must be free
of mortar or other foreign material for water removal. Refer
to IM 449 for specific details regarding louver installation.
7. Apply rubber stripping or sealant material (by others)
across full length of wall sleeve splitters.
8. If the louver does not butt up against the wall sleeve:
a. Fabricate a horizontal air splitter from galvanized
steel, redwood or some other suitable weather resis­tant material. The width of the air splitters is determined by the width of the wall opening. The depth of the air splitters is determined by the distance between the louver horizontal splitter and the wall sleeve splitters.
b. The horizontal air splitters should have a 1" diameter
drain hole approximately 6" from each end.
c. Install the horizontal air splitters by fastening to the
wall sleeve splitters.
d. Apply rubber stripping or sealant material (by
others) across full length of horizontal air splitters to seal against louver.
9. Permanently seal any remaining air leaks so that, when
finished:
Figure 1.
Chassis
Wall Sleeve
3
8" in
a. There is an airtight separation between the condenser
inlet air, condenser discharge air and the outdoor air inlet;
b. There are no air leaks around the perimeter of the wall
sleeve where it adjoins the wall.
Recessed Applications (See Figures 3 and 4)
The installing contractor shall do the following:
1. Place the wall sleeve into the wall opening and recess it the amount shown on the approved AAF-HermanNelson submittal drawings.
2. Level the wall sleeve horizontally and plumb the wall sleeve vertically.
3. Fasten the wall sleeve securely in place using fasteners through the two knockouts provided on each end.
4. Caulk or seal any space between the wall sleeve and the wall on both the room side and the outdoor side.
Nonrecessed Applications (See Figures 5 and 6)
The installing contractor shall check the following before proceeding:
The wall behind the unit should be smooth and plumb. The seals on the rear of the unit will take up the small ir-
regularities of normal masonry construction.
Furring strips must be installed on irregular walls or walls
with mullions in order to provide a flush surface for the unit to seal against.
Any moldings at the floor/wall line should be omitted
behind the unit.
The installing contractor shall do the following:
1. Apply sealant (by others) to bottom edge at rear of unit top and both end flanges on rear of wall sleeve to provide watertight seal to interior wall of building.
2. Level the wall sleeve horizontally, and plumb the wall sleeve vertically.
3. Fasten the wall sleeve securely in place by: a. Securing it to the floor through the two (2)
holes in the turned out bottom flanges of the wall sleeve at each end, and/or:
b. Securing it to the wall through the two (2)
diameter holes in the turned out vertical flanges of the wall sleeve at each end.
4. a. Panel wall applications should have the wall opening
sleeved to prevent moisture from seeping into the wall interior.
b. If the panel wall is less than 2
should be installed flush to the interior wall and be allowed to extend to the outside as required.
5. Seals on rear of unit must be compressed to provide a watertight seal after installation is complete.
Figure 2. Cross Section Detail of Bottom of
Fasten cross channel to floor thru 1⁄4" holes with appropriate fasteners (by others.) 7 fasteners - AEQ 24, 30 8 fasteners - AEQ 36, 40 9 fasteners - AEQ 44, 48, 54
Wall Sleeve & Intake
A "D" shaped seal is provided at the bottom rear of the Wall Sleeve to provide a watertight seal to the bottom of the unit when installed.
Bottom of Wall Sleeve Cross Channel
1
⁄4" thick, the wall louver
3
⁄8" diameter
3
⁄8"
Seal both ends and top of Wall Sleeve to building, watertight at rear flange.
Bottom channel of Louver
3
⁄16"
Seal watertight bottom of Wall Sleeve at rear "D" seal to building and pitch toward bottom channel of louver as shown.
Page 4 / IM 502
*Unit may also be installed with the full 28" deep cabinet projecting into the room.
IMPORTANT: Opening under Louver must be free of foreign material for water removal.
CAUTION: Sleeves furnished for use with optional heated rear drain will have an electric cord installed along
the length of the wall sleeve splitter. Avoid screw penetration or drilling into this cord when installing the horizontal air splitter. (Model AEQ Only)
Figure 3. Rear View of Recessed Wall Sleeve With Horizontal Air Splitters.
By Others. Wall Sleeve must
be sealed watertight at top and both ends at location shown.
By Others. Seal Horizontal Air Splitters to building at both ends.
By Others. Seal both ends of opening between Wall Sleeve and Louver.
IMPORTANT NOTE: By Others: Attach Horizontal Air Splitters to Wall Sleeve
Splitters as shown. Splitters to have 1" dia. drain hole approx. 6" from each end.
Wall Sleeve Splitter(s) (See Caution Above)
"D" Seal
By Others. Wall Sleeve must be sealed watertight at bottom at location shown. Refer to cross section detail of bottom of Wall Sleeve and Louver. (Figure 2.)
Seal Horizontal Air Splitter(s) to Louver. (By Others)
3
16" Under Intake must be free for water run-off. INTAKE MUST
STAND ON EMBOSSED FEET LOCATED ON BOTTOM.
By Others. Building must be sealed between Wall Sleeve and under Louver for water run-off. Pitch toward Louver.
Condenser discharge
Condenser inlet
Outdoor air inlet
By Others. Louver must be sealed watertight at top and both ends.
Figure 4. Rear View of Recessed Wall Sleeve Without Horizontal Air Splitters.
By Others. Wall Sleeve must
be sealed watertight at top and both ends at location shown.
By Others. Seal Horizontal Air Splitters to building at both ends.
Wall Sleeve Splitter(s) (See Caution Above)
"D" Seal
By Others. Wall Sleeve must be sealed watertight at bottom at location shown. Refer to cross section detail of bottom of Wall Sleeve and Louver. (Figure 2.)
IMPORTANT NOTE: By Others. Seal Louver to Wall Sleeve at top and bot­tom Wall Sleeve Splitters, and ends.
3
16" Under Intake must be free for water run-off. INTAKE MUST
STAND ON EMBOSSED FEET LOCATED ON BOTTOM.
By Others. Building must be sealed between Wall Sleeve and under Louver for water run-off. Pitch toward Louver.
By Others. Louver must be sealed watertight at top and both ends.
IM 502 / Page 5
Loading...
+ 11 hidden pages