NOTE: Throughout this manual, both the LCR.iQ and MASTERLOAD.iQ are
referred to as “Register” (unless otherwise specifically referenced by name).
LCR.iQ/MasterLoad.iQ
Product Manual
Congratulations on ownership of the new LCR.iQ or MasterLoad.iQ electronic meter register
and controller. This manual provides the technical details on installation, hardware, setup,
operation, and regulatory information for your register.
The Register calculates, monitors and records volumetric data from bulk flow meters, provides
fluid transfer process customization and automation, ties in critical system sensors and inputs,
and bridges data communication between the operator, the equipment, and the operator’s
back office if necessary.
The Register is specially designed to work with leading bulk fuel meters such as LC and
Avery-Hardoll, but will easily retrofit into existing systems with other flow meter brands.
The Register provides many new features, yet supports backward compatibility with LCR-II
and LCR-600.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
3
Page 4
Adobe PDF Manuals
Download either of the manuals using the links below:
To begin reading the online help, start with the Register Overview.
5
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
4
Page 5
LCR.iQ/MasterLoad.iQ Product Manual
Register Overview
The Register is a microprocessor-based electronic meter register that can be used for
Weights & Measures approved custody transfer actions in mobile or fixed installations. The
Register is a self-contained unit. All operation, setup, and configuration functions can be
carried out using the Register function keys and alphanumeric keypad. No lap pads, laptops,
or other data entry devices are required.
A complete Liquid Controls meter system not only accurately measures product, it also
regulates product flow and removes contaminants in order to produce the optimal conditions
for measurement. Typical systems include an air/vapor eliminator, strainer, meter, register,
and control valve.
Basic Functions
The principle functions of the Register registers include:
·
Weights & Measures custody transfer (product delivery and ticket generation)
·
Metrological data collection
·
Preset deliveries by volume
·
Multiple product selection
·
Multi-point meter calibration
·
Security settings
·
Air and vapor elimination (with proper accessories)
·
Single and dual stage valve control (with proper accessories)
·
Electronic Temperature Volume Compensation (ETVC)
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
5
Page 6
LCR.iQ/MasterLoad.iQ Product Manual
Publication Updates
The most current versions of all Liquid Controls publications are available on our web site,
www.LCmeter.com/resources/technical/manuals. If there are questions about the language or
interpretation of any LC manuals, instructions, or specification sheets, please first contact your
local distributor for help with your inquiry.
For service related issues that require further support from the Liquid Controls Service Team,
please call the number below.
Liquid Controls Corporate Office:
Phone: +1 847 295-1050
Toll-free: 800 458 5262
Address: Liquid Controls LLC, 105 Albrecht Drive, Lake Bluff, IL 60044 USA
Website: www.LCmeter.com
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
6
Page 7
Safety Procedures
BE PREPARED
·
Before using this product, read and understand the instructions.
·
All work must be performed by qualified personnel trained in the proper
application, installation, and maintenance of equipment and/or systems in
accordance with all applicable codes and ordinances.
·
When handling electronic components/boards, always use proper Electrostatic
Discharge (ESD) equipment and follow proper procedures.
·
Make sure that all necessary safety precautions have been taken.
·
Provide for proper ventilation, temperature control, fire prevention, evacuation,
and fire management.
·
Provide easy access to appropriate fire extinguishers for your product.
·
Consult with your local fire department, state, and local codes to ensure
adequate preparation.
·
Read this manual and all the literature provided in your owner’s packet.
·
Save these instructions for future reference.
·
Failure to follow the instructions in this publication could result in, personal
injury, or death from fire and/or explosion, property damage, or other hazards
that may be associated with this type of equipment.
SAFELY EVACUATE PIPING SYSTEM
Before disassembly of any meter or accessory component: ALL INTERNAL
PRESSURES MUST BE RELIEVED AND ALL LIQUID DRAINED FROM THE
SYSTEM IN ACCORDANCE WITH ALL APPLICABLE PROCEDURES.
·
Pressure must be 0 (zero) psi.
·
Close all liquid and vapor lines between the meter and liquid source.
Failure to follow this warning could result in property damage, personal
injury, or death from fire and/or explosion, or other hazards that may be
associated with this type of equipment.
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
7
Page 8
LCR.iQ/MasterLoad.iQ Product Manual
OBSERVE NATIONAL & LOCAL CODES
Power, input, and output (I/O) wiring must be in accordance with the area
classification for which it is used (Class I, Div 2). For North America, installations
must be per the U. S. National Electrical Code, NFPA 70, or the Canadian
Electrical Code in order to maintain Class I, Division 2 ratings. This may require
using connections or other adaptations in accordance with the requirements of
the authority having jurisdiction.
Peripheral equipment must be suitable for the hazardous location where it is
installed. (L'équipement périphérique doit être adapté à la zone dangereux où il
est installé.)
WARNING: Explosion Hazard
When in hazardous locations, turn power OFF before replacing or wiring
modules. (Lorsque dans des endroits dangereux, coupler le courant avant de
remplacer ou de câbler des modules.)
DO NOT disconnect equipment unless power has been switched OFF or the area
is known to be Non-Hazardous. (NE PAS déconnecter l'équipement san coupler
l'alimentation ou sans s'assurer que la zone est non dangereuse.)
WARNING: Use 3.5 in • lb (0.4 N • m) torque when tightening terminal block
screws.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
8
Page 9
ESD Protection
ESD Precaution
Opening the Registers
Follow this procedure each time you open the Register or approach it with the door open:
Before opening the Register and handling the CPU board, it's important to discharge any
ESD that may have built up on your person. To discharge ESD from your person, touch a
well-grounded point–such as the Register housing, the meter, truck piping, or the bumper.
When the maintenance is complete and the Register door is closed, the CPU board is
protected from ESD by the Register housing which is grounded to the chassis.
LCR.iQ/MasterLoad.iQ Product Manual
Preventing ESD Damage
To prevent electrostatic discharge (ESD) damage to the Register, truck installations must
properly ground the truck seat cushion and the Epson printer chassis. Prolonged exposure to
ESD over weeks, months, or years can corrupt register memory and damage the electronic
components in Register registers (as well as other electrical components in the truck electrical
system).
Adjustable, shock-absorbing seats, if not grounded correctly, generate significant amounts of
ESD. The pivots and hinges of these seats isolate the seat cushion from an electrical ground.
Without proper bonding, static electric charge builds between the seat cushion and the
operator. This electric charge can enter the Register from any point in the truck electrical
system, including register power and printer cabling.
Liquid Controls Grounding Kits
All truck installations of the Register must have grounded seats and printers using the following
kits:
·
Ground Strap Kit (LC Part Number 82185)
·
Epson Printer Ground Wire Kit (LC Part Number 82184)
Properly grounded seats allow static electricity to ‘bleed off’ before it can build up, discharge,
and damage the Register or other electrical components.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
9
Page 10
LCR.iQ/MasterLoad.iQ Product Manual
The Epson Printer Ground Wire Kit is included with each Epson printer cable kit shipment. For
existing installations and previously purchased registers / printers, both ground kits are
available from LC.
Grounding with a Meter Mount or Remote Mount
In an installation where the Register is mounted directly to the meter, the Register housing is
grounded through the meter. If the register is not mounted on the meter, you must ensure the
Register housing is grounded properly.
Alternate grounding methods for remote mounted registers
For installations where grounding the register housing through a mount is not possible, an
external grounding screw hole is available. This hole requires a #8-32 x 1/4” ground screw–
which is supplied with the register (the LC part number for the screw is 08254)–and also a 12
gauge or larger stranded wire connected to a known ground (less than 1 ohm).
Another option is to connect the ground screw 8-32 x 1/4” ground screw (inside the Register
housing) to a 12 gauge or larger stranded wire connected to a known ground (less than 1
ohm).
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
10
Page 11
LCR.iQ/MasterLoad.iQ Product Manual
Specifications
Mechanical
Housing and Keypad
The Register housing and bases are aluminum die castings with chromate protective finishing
and powder coated with high durability, urethane powder. The cover internal hinge design
provides easy access to the internal connections and keeps all moving hinge parts out of the
elements to further prevent corrosion. Weights and Measures features are accessible by
using a seal-able fastener on the side of the cover. There are 11 half-inch NPT ports, on the
back of the Register to provide secure cable connections for a wide range of external devices.
Construction Materials
·
High grade A360 Die Cast Aluminum, enclosure cover, and enclosure base
·
Chromate finish with powder-coat protective coating
·
Tempered glass display window
·
Silicone display glass seal
·
Stainless steel display bracket
·
Silicone door seal
·
Keypad – Membrane Switch with back-lit silicone overlay
·
Stainless steel fasteners/hardware
·
Stainless steel bonded silicone sealing washer
Certified Operational Temperature Rating
·
The Register is certified for normal operation within the temperature range of -40 to 140 °
F (-40 to 60 °C).
Display
·
7 inch heavy duty, high definition TFT/LCD (Thin Film Transistor Liquid Crystal Display)
video display with LED backlight unit.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
11
Page 12
LCR.iQ/MasterLoad.iQ Product Manual
·
800 x 480 pixels (152.4 mm x 91.4 mm)
·
Luminance: 1500 (cd/m2)
·
Display acceptable operation or storage temperature -40 °F to 185 °F (-40 °C to 85 °C).
Weight
·
Approximately 12 lbs (Meter Mount Version, no added accessories)
·
Approximately 11 lbs (Panel Mount Version, no added accessories)
Cable Entry
·
Eleven (11), 1/2" NPT (1/2-14 NPT) threaded ports
Alphanumeric Keypad
The Register alphanumeric keypad is made of petroleum resistant silicone and consists of 12
large alpha-numeric keys, 5 navigation keys, and 5 function keys that relate to the adjacent
display indicators for operator-guided functionality. The keys, when pressed, give the operator
a tactile, positive confirmation of keystrokes. The keypad multi-tap functionality also allows
users to input up to four alpha-numeric characters on a single key.
Electrical
Inputs
Inputs are configurable in the Register to handle a variety of external accessories that provide
data signals in the metering system including pulse input and a variety of external sensors.
Register Input Voltage
·
Voltage – 9 to 28 VDC
·
Current maximum: 5 A maximum
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
12
Page 13
LCR.iQ/MasterLoad.iQ Product Manual
Pulse Input
In order to calculate flow measurements when mounted to a positive displacement meter, the
Register receives a pulse input from a quadrature pulser that is mechanically connected to the
flow meter output shaft (meter mount option only). A pulse input can also come from an
external device such as a Liquid Controls Pulse Output Device (POD) or another externally
mounted pulse generator. If an external LC POD is purchased, these materials are
necessary, but are not supplied with the POD:
·
16-22 AWG 4 conductor Shielded Cable (Consult the POD manual for complete
specifications)
·
Weather Proof flexible conduit or loom
·
½” Conduit connectors or cable glands
RTD Temperature Probe
The Register is equipped with an input for a temperature probe, so the register can read
realtime temperature as well as compensate volume measurements according to the
temperature of the product.
·
4 wire platinum sensor
·
100 Ω resistance at 0 C
·
138.5 Ω resistance at 100 C
Optical Air Eliminator
The Register is equipped to handle an optical air eliminator input:
·
Voltage – 10 to 28 VDC
·
Current – 0.5 Amp maximum
Digital Inputs 1, 2, 3, 4, 5, and 6
·
Active Low, normally pulled high
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
13
Page 14
LCR.iQ/MasterLoad.iQ Product Manual
·
Voltage: 5 to 28 VDC
·
Current: 3 mA maximum sink current
·
Maximum Frequency: 10 kHz
OUTPUTS
The Register is equipped with six digital outputs and four solenoid outputs. These outputs allow
the Register to communicate with meter system accessories such as solenoid- controlled
valves, optical air and vapor eliminators, remote displays, printers, and third-party devices.
Digital Outputs 1, 2, 3, 4, 5, and 6
·
Open drain output, active low to ground, thermally protected
·
Voltage: 5 to 28 VDC
·
Current: 500 mA maximum
Outputs for solenoids 1, 2, 3, and 4
·
Open drain output, active low to ground, thermally protected
·
Voltage: 12 VDC nominal
·
Current: 1 A maximum
·
Voltage: 24 VDC nominal
·
Current: 0.5 A maximum
Pulse Output
·
Voltage peak to peak – 5 to 28 V
·
Frequency maximum – 7500 Hz
Scale Pulse Output
·
Current sinking capability: 150 mA
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
14
Page 15
Electrical Protection
·
5 A fuse on power cable
COMMUNICATIONS
·
RS-232
·
RS-485
·
CAN BUS – Consult the applicable Chassis Builder’s Guide, available from the truck
chassis manufacturer.
·
Ethernet (Gigabit)
·
Bluetooth (wireless)
·
Wi-Fi (wireless)
LCR.iQ/MasterLoad.iQ Product Manual
Printer (Epson Model 295)
·
Voltage – 24 VDC
·
Current – 0.8 Amp maximum
·
Operating Temperature – -22 to 104 ºF (-30 to 40 ºC)
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
15
Page 16
LCR.iQ/MasterLoad.iQ Product Manual
Regulatory & Certifications
The equipment is Listed by UL to applicable US and Canadian standards for use in hazardous
locations under Liquid Controls file E180172.
LCR.iQ Serial Number tag
MASTERLOAD.iQ Serial Number tag
Class I
·
Potentially Explosive Gas/Vapor Atmospheres.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
16
Page 17
LCR.iQ/MasterLoad.iQ Product Manual
Division 2 and Zone II
·
Gases and vapor are not normally present in an explosive concentration but may
accidentally exist during abnormal operations.
Grp C&D and Grp IIB
·
Flammable/explosive Gas groups.
T4
·
ambient temperature. At the rated maximum ambient temperature, the equipment will not
generate temperature higher than 135 °C
·
Safe limits of ambient temperature.
IP66
·
Ingress protection: dust tight and protected against powerful water jetting.
Type 4X
·
The enclosure has been evaluated by UL for outdoor use to provide protection against
water and dust and an increased level of protection against corrosion; and that will be
undamaged by the external formation of ice.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
17
Page 18
Specifications
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
18
Page 19
FCC Compliance
Unique Identifier: LCR.iQ or MasterLoad.iQ
Responsible Party:
Liquid Controls LLC
105 Albrecht Drive
Lake Bluff, IL 60044 USA
www.LCmeter.com
LCR.iQ/MasterLoad.iQ Product Manual
FCC Compliance Statement: This device complies with Part 15 of the FCC Rules. Operation
is subject to the following two conditions: (1) This device may not cause harmful interference,
and (2) this device must accept any interference received, including interference that may
cause undesired operation.
This device contains FCC ID Z64-WL18DBMOD, IC: 451I-WL18DBMOD, and may optionally
contain FCC ID MCQ-XBPS3B, IC: 1846A-XBPS3B (DIGI Module).
This equipment has been tested and found to comply with the limits for a Class B digital
device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable
protection against harmful interference in a residential installation. This equipment generates,
uses, and can radiate radio frequency energy and, if not installed and used in accordance with
the instructions, may cause harmful interference to radio communications. However, there is
no guarantee that interference will not occur in a particular installation. If this equipment does
cause harmful interference to radio or television reception, which can be determined by turning
the equipment off and on, the user is encouraged to try to correct the interference by one or
more of the following measures:
·
Reorient or relocate the receiving antenna.
·
Increase the separation between the equipment and receiver.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
19
Page 20
LCR.iQ/MasterLoad.iQ Product Manual
·
Connect the equipment into an outlet on a circuit different from that to which the receiver
is connected.
·
Consult the dealer or an experienced radio/TV technician for help.
Any changes or modifications to this equipment, not expressly approved by Liquid Controls
could void the user’s authority to operate the equipment.
This device complies with the ISED Canada license-exempt RSS standard(s). Operation is
subject to the following two conditions: (1) This device may not cause harmful interference,
and (2) this device must accept any interference received, including interference that may
cause undesired operation.
Cet appareil est conforme à la norme RSS exempte de licence d'ISED Canada. L'opération
est sous réserve des deux conditions suivantes: (1) Cet appareil ne doit pas causer
d'interférences; et (2) Cet appareil doit accepter toute interference fonctionnement indésirable
de l'appareil CAN ICES-3(B)/NMB-3(B)
This device could automatically discontinue transmission in case of absence of information to
transmit or operational failure. Note that this is not intended to prohibit transmission of control
or signaling information or the use of repetitive codes where required by the technology.
The device for operation in the band 5150-5250 MHz is only for indoor use to reduce the
potential for harmful interference to co-channel mobile satellite systems.
High power radars are allocated primary users (i.e. priority users) of the bands 52505350MHz and 5650-5850MHz and that these radars could cause interference and or damage
to the Wi-Fi transceiver.
This equipment complies with the FCC/IC radiation exposure limits set forth for an uncontrolled
environment.
Only antennas specified by Liquid Controls shall be used with this equipment.
The antenna for this equipment shall be installed and operated to maintain a separation
distance of 20 cm or greater between the antenna and any person.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
20
Page 21
LCR.iQ/MasterLoad.iQ Product Manual
The antenna for this equipment shall not be co-located with or operated in conjunction with any
other antenna or transmitter. The antennas shall be installed and operated to maintain a
separation distance of 20 cm or greater between any other radiating antenna.
The FCC ID and IC can also be viewed on the Register by pressing <Main Menu> then
<Diagnostics> then <About>.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
21
Page 22
Dimensions - Panel Mount
FRONT VIEW
LCR.iQ/MasterLoad.iQ Product Manual
BACK VIEW
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
22
Page 23
SIDE VIEW
LCR.iQ/MasterLoad.iQ Product Manual
TOP VIEW
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
23
Page 24
Dimensions - Meter Mount
Front View
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
24
Page 25
Side view
Top View
LCR.iQ/MasterLoad.iQ Product Manual
Bottom View
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
25
Page 26
LCR.iQ/MasterLoad.iQ Product Manual
Check Each Shipment
Before installation, check your shipment against the packing list and ensure that no parts are
missing. The packing list is inside the red information packet along with the Installation and
Operation Manuals.
Installation
If the Register was ordered as part of a metering system, it may arrive mounted on the meter
and pre-wired to peripheral equipment such as an ETVC probe, air eliminator, and valve.
Installation overview for Register ordered with meter system:
1. Ground truck seat cushion. See Ground Strap Kit.
30
2. Install meter system onto truck or fixed installation. Refer to the Meter manual.
3. Run the data and power Cables from the Register to the truck cab or power supply. See
Routing Data and Power Cables.
43
4. Connect any additional components to the Register board.
5. Mount printer and connect printer data cable. See Printers.
6. Connect the Register and the printer to power supply. See Power Supply.
67
70
7. Setup and calibrate the Register.
If you are replacing an existing register, you must mount the register onto the meter and make
the proper connections
to all of the components.
Installation overview for a Register ordered without a meter system:
1. Ground truck seat cushion. See Ground Strap Kit.
2. Mount the Register to the meter. See Mounting Overview.
30
34
3. Run the Data and Power Cables from the Register to the truck cab or power supply. See
Routing Data and Power Cables.
43
4. Connect all components to the Register CPU board.
5. Mount printer and connect printer data cable. See Printers.
6. Connect the Register and the printer to power supply. See Power Supply.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
67
70
26
Page 27
7. Setup and calibrate the Register.
What this chapter covers
This chapter explains and details the mechanical installation of the Register and the
temperature probe as well as the electrical and data installation of all components that
connect to the Register. For additional installation information, refer to the manuals of the
other components. All manuals are available at www.LCmeter.com.
Installation requirements will vary
Specific installation requirements will vary with the model of the truck, the physical layout of
a fixed installation, the configuration of any existing metering equipment, the options
selected, and the type of fluid being metered.
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
27
Page 28
LCR.iQ/MasterLoad.iQ Product Manual
Wiring Diagram
For better viewing of this diagram, click this link to download a high-resolution PDF image: Full-
size wiring diagram.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
28
Page 29
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
29
Page 30
LCR.iQ/MasterLoad.iQ Product Manual
ESD Precaution
Install the Ground Strap Kit before installing the register.
Grounded Passenger Seats
Some truck seats, typically passenger seats, are not adjustable and do not
require grounding.
Ground Strap Kit
All seat cushions are grounded in a similar manner. The illustrations below detail the following
instructions for grounding three typical types of truck seats.
Follow these steps to ground a truck seat:
1. Identify any adjustable, shock absorbing seat in the truck cab. These seats will typically
have pivot points, hinges, or other mechanical design features that make seat
adjustments possible.
2. Find an existing screw or hole near the back of the seat frame, close to the cab floor. If a
hole or screw does not already exist, drill a 9/32” hole in the seat frame.
3. Attach one end of the ground strap to the seat frame bracket using the lock washer, flat
washer and nut provided.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
30
Page 31
LCR.iQ/MasterLoad.iQ Product Manual
Ensure a Good Ground
Remove any dirt or oxidation from the ground strap contact point. Lock
washers should penetrate any paint to ensure a good electrical connection.
4. Find an existing screw or hole, or drill a 9/32” hole, in the part of the seat frame—above
all pivots and adjustments—that is attached directly to the seat cushion. Make sure that
there are no intervening pivot points, guides, adjustment mechanisms, etc., which could
interfere with the ground path between the seat cushion and the ground strap.
·
If the seat cushion has a wooden base, use a wood screw and washer to attach the
strap lug to the bottom of the seat at a point where the seat fabric is attached to the
wood. There must be good contact between the seat fabric and ground strap lug.
5. Use the wire ties provided with the kit and tie off the strap so that it doesn’t interfere with
the movement of the seat and is clear of traffic areas in the cab.
6. Check the strap for a good ground connection (see below).
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
31
Page 32
LCR.iQ/MasterLoad.iQ Product Manual
Attach Ground Strap
Typical Adjustable Truck Seats
The diagrams below demonstrate how to attach the ground strap to typical truck seats.
Air Cushion Seat - Adjustable for Height
Bench Seats - Adjustable for Distance to the Steering Wheel
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
32
Page 33
LCR.iQ/MasterLoad.iQ Product Manual
Turn off accessories
If the multimeter reads “MΩ” or “KΩ”, typically, one of the
accessories is still on.
Verify good contact
If operator receives a ESD discharge when leaving the
seat, the ground strap is not installed correctly.
Check for a Good Ground
After installing the ground kits, use a multimeter to confirm that the seat and printer are both
grounded properly.
Follow these steps to verify a good ground connection:
1. Turn OFF all accessories, including the dome light, to prevent other currents from
distorting the reading.
2. Take a multimeter and measure the resistance between the brackets the two ground
strap bolts are fastened to. Find a clean spot on the brackets without paint to use as
contact points. Other bolts on the brackets are often suitable.
·
If the resistance is less than 3Ω, the system is grounded adequately.
·
If the resistance is still greater than 3Ω, check for proper metal to metal contact on
both ends of the ground strap. Clean any paint, dirt, or oxidation that may block the
grounding point. If the resistance remains above 3Ω, attach the ground strap to a
different ground point. Repeat the process until the ground resistance is below 3Ω.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
33
Page 34
LCR.iQ/MasterLoad.iQ Product Manual
Mounting Overview
The Register is available in two separate mounting options: meter mount and panel mount.
The Register can be mounted directly onto a flow meter; however, it may also be mounted
away from the meter in a more ergonomic or advantageous position, on a control panel or
control pedestal. If the meter is equipped with an external POD pulser, the Register can be
mounted up to 1000 feet (304 meters) away from the meter (actual distance depends on
pulser specifications and wire type).
·
The meter mount design consists of an enclosure base with a round mounting surface that
mates perfectly with standard LC register adapter bracket or industry standard register
mount and can be mounted in 45° increments.
·
The panel mount design consists of an enclosure base with mounting tabs to allow the
register to be conveniently mounted on a flat panel from the front or rear of the panel for a
very clean and wire-free installation from the operator's point of view.
Meter Mount Housing
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
34
Page 35
Panel Mount Housing
Tips for mounting a Register
·
Leave the cover assembly fastened to the base to protect the internal
components.
·
Ensure that the vertical drive shaft from the meter is attached to the pulser
drive shafts.
·
Before securing the Register to the meter or mounting bracket, ensure that
the counter is visible and the keypad and calibration screw can be easily
operated.
LCR.iQ/MasterLoad.iQ Product Manual
Adapters are available for other PD meters such as Neptune (PNs 81364, 82641, 82642),
FMC Smith (PN 81370), and Brooks/Brodie (PN 81800) meters. Each kit includes installation
instructions.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
35
Page 36
LCR.iQ/MasterLoad.iQ Product Manual
WARNING
Relieving Internal Pressure
All internal pressure must be relieved to zero pressure before disassembly
or inspection of the strainer, vapor eliminator, any valves in the system, the
packing gland, and the front or rear covers.
WARNING: Serious injury or death from fire or explosion could result in
performing maintenance on an improperly depressurized and evacuated
system.
Relieving Internal Pressure Procedure for LPG and NH3 Meters
Follow these steps:
1. Close the belly valve of the supply tank.
2. Close the valve on the vapor return line.
3. Close the manual valve in the supply line on the inlet side of the meter. If
no manual valve exists on the inlet side, consult the truck manufacturer
for procedures to depressurize the system.
4. Slowly open the valve/nozzle at the end of the supply line.
5. After product has bled off, close the valve/nozzle at the end of the
supply line.
6. Slowly crack the fitting on top of the differential valve to relieve product
pressure in the system. Product will drain from the meter system.
7. As product is bleeding from the differential valve, slowly reopen and
close the valve/nozzle on the discharge line. Repeat this step until the
product stops draining from the differential valve and discharge line
valve/nozzle.
8. Leave the discharge line valve/nozzle open while working on the system.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
36
Page 37
LCR.iQ/MasterLoad.iQ Product Manual
APPLY Anti-seize
Always apply anti-seize to all bolt threads to ensure easy removal at a later
date.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
37
Page 38
LCR.iQ/MasterLoad.iQ Product Manual
Mounting the Register
Mounting Bolt Pattern
The Register base housing contains eight bolt holes in an industry standard bolt pattern. This
design allows for horizontal rotation of the housing in 45° increments to conveniently mount the
register in various orientations. The holes are ½" deep and take ¼"-20 screws.
If the installation requires that you fabricate a bracket, refer to the drawing below.
Installing the Register on existing LC meter installations
Remove Existing Registration Equipment
Follow these steps:
1. Depressurize the meter completely. See the Warnings in Mounting Overview.
2. Remove the four bolts on the bottom that fasten the register to the meter.
3. If replacing a mechanical register, remove the adjuster from the meter.
4. If the meter has a Temperature Volume Compensator (TVC), remove it as well.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
34
38
Page 39
LCR.iQ/MasterLoad.iQ Product Manual
Apply Anti-seize
Apply anti-seize to all bolt threads to ensure easy removal at a later date.
Mount the Register
Follow these steps:
1. Place the end of the shaft adapter on the pulser drive shaft located on the bottom of the
register.
2. Place the cotter pin through the hole, and bend open the ends of the cotter pin.
3. Lower the register onto the meter, and insert the shaft adapter onto the hex shaft on the
meter.
4. Securely bolt down the register.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
39
Page 40
Neptune Meters
Remove Existing Registration Equipment
Follow these steps:
LCR.iQ/MasterLoad.iQ Product Manual
1. Depressurize the meter completely. See the Warnings in Mounting Overview.
34
2. Remove the mechanical register from the meter.
3. Leave the star-shaped gear and the two square-head studs.
4. Remove the bellows from the front of the meter.
5. Remove the compensator.
Mount the Register
Follow these steps:
1. Install the drive fork and extension piece (pictured below) on the pulser drive shaft
located on the bottom of the Register.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
40
Page 41
LCR.iQ/MasterLoad.iQ Product Manual
Star Gear and Drive Fork
When the register is lowered onto a Neptune meter, make sure the drive
fork is not pressed against the star gear on the meter. There must be a
small gap between these two parts. To lower the star gear, loosen the set
screw on the side of the star gear. Failure to do so will eventually damage
the internal pulser and/or the meter gear train.
APPLY Anti-seize
Apply anti-seize to all bolt threads to ensure easy removal at a later date.
2. Install the bracket on the meter, and fasten with the bolts provided in the kit.
3. Lower the Register on to the bracket, and securely fasten using the four bolts (¼" x ¾")
provided.
Mount the Register on previously temperature
compensated Neptune meters
Follow these steps:
1. Place the shaft adapter on the pulser drive shaft under the Register.
2. Place the cotter pin through the hole, and bend open the ends of the cotter pin.
3. Pass the other end of the shaft adapter through the flange assembly and the weather
plate.
4. Loosely bolt to register.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
41
Page 42
LCR.iQ/MasterLoad.iQ Product Manual
Installation kits 82641 (E-26 series) & 82642 (E-36 series) are
specifically designed for previously temperature compensated
Neptune meters.
5. Place the drive fork and extension piece on the shaft using two more cotter pins.
6. Bolt the flange to the meter and tighten all bolts.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
42
Page 43
LCR.iQ/MasterLoad.iQ Product Manual
Routing the Data and Power Cables
Data and Power Cable
The Register shipment typically includes a gray 50-foot power cable and a 50-foot black data
cable, pre-wired to terminal blocks on the Register CPU board. On typical truck installations,
the cables must be routed from the back of the truck–where the Register is installed–to the
front of the truck, where the accessory panel is and the printer is typically installed. The black
data cable connects to the printer, typically mounted in the truck cab. The gray power cable
hooks up to a power source. During installation, follow these guidelines and ensure the cables
remain undamaged.
During installation, follow these guidelines and ensure the cables remain undamaged.
Guidelines for routing the data and power cables on the outside of the
truck
·
LC recommends that both cables be run through 1/2" automotive plastic corrugated split
loom or through flexible liquid-tight conduit for protection.
·
Make sure the loom or conduit runs down the inside edge of the trucks frame rail and
fasten every 2' with cable ties.
·
Install rubber grommets to protect the cables where they pass through the cab wall, meter
box, etc.
·
Keep the cables away from heat sources such as the engine exhaust, manifold, exhaust
pipe, mufflers, etc.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
43
Page 44
LCR.iQ/MasterLoad.iQ Product Manual
·
Keep cables away from moving suspension components and other moving truck
components.
·
If the cables are shortened, ensure that you use the proper tool for stripping off the
insulation on the cables.
·
Ensure that all cabling and wiring connections are connected to the proper terminal
locations.
Guidelines for routing the data and power cables inside the cab
·
Before you begin, layout positions for the component and pathways for the cable.
·
Ensure that the printer and the wires will not obstruct other vehicle components.
·
Keep cable pathways away from heavy traffic areas and locations where they may be
vulnerable to damage.
·
Remember to provide plenty of room around the components, so the cables can be easily
connected.
·
Avoid installing the cable where it will be exposed to excessive flexing.
·
Ensure that cables are not pulled too tight in areas that will move. For example, when
wiring cab-over trucks, leave enough slack so the cab can be tilted without damaging the
cable.
·
Ensure cables are not fastened to adjustable seats.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
44
Page 45
LCR.iQ/MasterLoad.iQ Product Manual
ETVC Installation
Electronic Temperature Volume Compensation (ETVC) Installation
When ordered as part of a meter system with a Register, the ETVC kit is typically bolted onto
the strainer and wired to the Register at the factory. ETVC kits can also be ordered and
retrofit onto meter systems already in service. Kits are specified according to meter size and
application and are all installed in the same manner. For meter systems that do not include an
LC supplied Strainer mounting kit, Liquid Controls also offers an ETVC kit for pipe mount.
A conduit kit (PN 81024)–with a 30-inch length of weatherproof flexible conduit–is available
from Liquid Controls to provide protection for the RTD temperature probe wire between the
strainer cover and the Register.
Follow these steps to install the ETVC kit:
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
45
Page 46
LCR.iQ/MasterLoad.iQ Product Manual
1.Depressurize the meter completely. See the Warnings in Mounting Overview.
34
2.Remove the old strainer cover.
3.Clean the strainer basket and replace it into the housing.
4.Lightly coat the new cover gasket (included with the ETVC kit) with lubricant. DO NOT
use the included copper grease.
5.Fit the new cover gasket into the strainer cover groove.
6.Bolt the strainer cover in place. Make sure the weights & measures Thermowell port is
at the top of the cover.
7.Assemble the Thermowell kit.
8.Coat the entire probe length with the copper grease provided. Insert and recoat the
probe 2 or 3 times to provide a uniform coating inside the Thermowell and to ensure
proper heat transfer from the liquid to the probe.
9.Connect the assembled Thermowell to the fitting in the middle of the strainer cover. The
angled fitting at the top of the cover is for weights & measures purposes. See Step 6
above.
10. Connect the conduit to a ½" NPT port on the back of the Register using the elbow
fittings provided with the conduit kit (PN 81024). Be sure to use thread sealant on NPT
threads.
11. Wire the temperature probe to the Register internal board on connector J15.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
46
Page 47
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power
Disconnect the power before working on the CPU board.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
47
Page 48
LCR.iQ/MasterLoad.iQ Product Manual
Compatibility
The Register is also compatible with many other brands and types of valves.
Valves
When ordered as part of a meter system with a Register, Liquid Controls control valves are
bolted onto the meter and wired to the Register at the factory. Electronic control valves can
also be ordered separately and retrofitted onto meter systems already in service. These
valves will need to be piped and wired in the field. For piping instructions, refer to the valve
manual. This manual includes wiring instructions for the valves.
Liquid Controls offers single-stage and two-stage electronic valves. Single stage valves have
one solenoid valve (S1) and two positions—an open position and a closed position. Two-stage
valves have two solenoid valves (S1 & S2) and three positions—open, closed, and dwell flow.
Dwell flow is a low flow rate setting controlled by the S2 solenoid and initiated shortly before
the register reaches a preset value.
This chapter covers:
·
Single-Stage Valves
·
Two-Stage Valves
·
Valve Installation
Single-Stage Valves
The three most common Liquid Controls meter systems with single stage valves include:
·
a block valve with a S1 solenoid-operated valve fitted onto external piping (A2847-11),
·
a block valve (A2843) with a 3-way solenoid
·
and an electro-pnuematic valve with an S1 solenoid
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
48
Page 49
LCR.iQ/MasterLoad.iQ Product Manual
A2847-11 Valve
This single stage control valve has a S1 solenoid operated valve located at the meeting point
of three external pipes: one pipe from the inlet side of the valve, one from the top of the block
valve, and one from the outlet side of the valve. This valve is typically used in refined fuels
applications.
.
A2843 Valve and 3-Way Solenoid
The 3-way solenoid-operated valve—mounted directly to the top center port on the back of the
Register—serves as a S1 solenoid-operated valve. The 3-way solenoid-operated valve is
located at the meeting point of two lines from the vapor eliminator (one for eliminated vapor
and one leading to the vapor return line) and one pipe to the top of the block valve. 3-way
solenoid operated valves are typically specified for products that hold vapor in the line such as
LPG and NH3.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
49
Page 50
LCR.iQ/MasterLoad.iQ Product Manual
A2700 Series Electro-Pneumatic Valve
Pneumatic valves use a S1 solenoid-operated valve, mounted to a pneumatic actuator to open
and close a V-7 valve. These valves are typically used in high viscosity applications, such as
lube oil.
Two-Stage Valves
The three most common Liquid Controls meter systems with two stage valves are:
·
a block valve with a S1 and a S2 solenoid-operated valve fitted onto external piping
(A2848-11)
·
a block valve with a S2 solenoid-operated valve (A2859-11) and a 3-way solenoid on
the Register.
·
and an E-7 valve with a S1 and a S2 solenoid-operated valve
A2848-11 Valve
This two stage control valve has a S1 and a S2 solenoid operated valve. The S1 solenoidoperated valve is located at the meeting point of three bypass pipes: one pipe from the inlet
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
50
Page 51
LCR.iQ/MasterLoad.iQ Product Manual
side of the valve, one from the top of the block valve, and one from the outlet side of the valve.
The S2 solenoid valve is located on a bypass pipe that connects the inlet and outlet sides of
the control valve. It opens while the control valve is closed to supply the dwell flow. This valve
is typically used in refined fuels applications.
A2859-11 Valve and 3-Way Solenoid
A two- stage valve with a S2 solenoid-operated valve and a 3-way solenoid valve attached to
the back of the Register. The 3-way solenoid-operated valve is located at the meeting point of
two pipes from the vapor eliminator (one for eliminated vapor and one leading to the spit tank)
and one pipe to the top of the block valve. The S2 solenoid valve is located on a bypass pipe
that connects the inlet and outlet sides of the control valve. It opens while the control valve is
closed to supply the dwell flow. This configuration is typically specified for products that hold
vapor in the line such as LPG and NH3.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
51
Page 52
LCR.iQ/MasterLoad.iQ Product Manual
E-7 Valves
A two stage valve with a S1 and a S2 solenoid-operated valve. The E-7 valve is fitted with one
external pipe to divert product flow to the closing mechanism. To supply a dwell flow, the E-7
redirects the product around the closed valve using channels molded into its housing. This
valve is typically used in refined fuels applications and has the same dimensions as the V7/K7
valve.
Valve Installation
If you install the valve yourself, refer to the valve installation and operation manual for
mechanical installation. Instructions for wiring Liquid Controls valves to the Register can be
found below.
Materials needed for wiring valves
These materials are necessary, but are not supplied with the valve:
·
16-22 AWG 4 conductor Shielded Cable (Consult the POD manual for complete
specifications)
·
Weather Proof flexible conduit or loom
·
½” Conduit connectors or cable glands
·
PTFE tape or thread sealant
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
52
Page 53
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power
Disconnect the power before working on the CPU board.
Follow these steps to wire valves to the Register:
1. Attach cable glands and/or conduit connectors to the solenoid valve(s) and the Register
port(s). Be sure to use thread sealant on NPT threads.
2. Thread the wires through piece of weatherproof conduit that is cut-to-length from the
solenoid to a Register port.
3. Run the weatherproof conduit between the solenoid operated valve(s) and the Register
housing, pull the wires through the ports, and tighten the connectors.
4. Connect the S1 solenoid-operated valve wires to terminals 23 and 24 on the J3 terminal
block of the Register CPU board.
5. Connect the S2 solenoid-operated valve wires to terminals 17 and 18 on the J13 terminal
block of the Register CPU board.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
53
Page 54
LCR.iQ/MasterLoad.iQ Product Manual
Earth Grounds for Solenoid Valves
The Earth grounds for Terminals 16 & 19 are optional. The solenoid operated valves are
grounded through the component they are mounted on.
Solenoid Operated Valve Cables
The 81527 solenoid operated valve (3-way LPG solenoid) has 3 cables potted into the
housing. All other solenoid operated valves on Liquid Controls valves use cable assembly
81859, which has 2 cables.
Follow this diagram as the guide to wiring a single stage valve for presetting:
Valves with 110VAC Solenoids
In order for the Register to control valves with solenoids on 110 VAC circuits, you must install
a relay switch on the positive leg of the solenoid’s circuit.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
54
Page 55
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power (110VAC)
Turn off all 110VAC circuits before beginning the installation.
Relay switch specifications:
·
Switch: SPST (single pole, single throw)
·
Switch Position: Normally open
·
Contact Rating: Greater than maximum current of solenoid
·
Voltage: +12 VDC
Materials needed for wiring valves with 110 VAC solenoids
These materials are necessary, but are not supplied with the valve:
·
SPST relay switch (1 per solenoid)
·
20 AWG stranded wire (2 per solenoid)
·
Weatherproof flexible conduit, ½" diameter and ½" NPT conduit connectors or cable
glands
·
PTFE tape or pipe sealant
To wire 110 VA C solenoids to the Register
Follow these steps:
1. Turn off all 110 VAC circuits before beginning the installation.
2. Install the specified relay switch(es) onto one leg of the 110 solenoid power supply
circuit.
3. Connect the relay switch on the S1 power supply circuit to terminals 23 and 24 on block
J3.
4. Connect the relay switch on the S2 power supply circuit to terminals 20 and 21 on block
J3.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
55
Page 56
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
56
Page 57
LCR.iQ/MasterLoad.iQ Product Manual
Optical Air and Vapor Eliminators
Optical Air and Vapor Eliminator Installations
When ordered as part of a meter system with a Register, the Liquid Control optical air and
vapor eliminators are bolted onto the strainer and wired to the Register at the factory. Optical
air and vapor eliminators can also be ordered separately and installed onto meter systems
already in service. For mechanical installation instructions, refer to the manual specific to the
optical air and vapor eliminator. Instructions for wiring optical air and vapor eliminators to the
Register are provided below.
Optical Air Eliminator (Refined Fuels)
Optical Vapor Eliminator (LPG and NH3)
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
57
Page 58
LCR.iQ/MasterLoad.iQ Product Manual
Materials needed for wiring valves
These materials are necessary, but are not supplied with the valve:
·
20 AWG stranded wire–3 per solenoid. Unnecessary for 3-way solenoid valves. Only 2 are
necessary for E7 solenoids.
·
Weatherproof flexible conduit, ½" diameter.
·
½" NPT conduit connectors or cable glands.
·
PTFE tape or pipe sealant.
M7 meter system with optical air eliminator
Wire optical air and vapor eliminators to the Register
Follow these steps:
1. Attach cable glands and/or conduit connectors to the S3 solenoid valve, the optical
sensor, and the Register ports.Be sure to use thread sealant on NPT threads.
2. Thread the 20 AWG wires through a piece of weatherproof conduit cut-to-length from the
S3 solenoid to a Register port
3. Run the weatherproof conduit between the S3 solenoid operated valve and the Register
housing. Pull the wires through the ports, and tighten the connectors. Liquid Controls
recommends running the optical sensor wire through weatherproof conduit as well.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
58
Page 59
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power
Disconnect the power before working on the CPU board.
4. Connect the two 20 AWG wires to the S3 solenoid operated valve terminals and to
terminals 17 and 18 on the J2 terminal block of the Register board.
5. Connect the optical sensor wires to terminals 10, 11, and 12 on the J2 terminal block of
the Register board.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
59
Page 60
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
60
Page 61
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power
Disconnect the power before working on the CPU board.
Pulse Output Device
Pulse Output Device (POD) Installation
When ordered as part of a meter system with a Register, the Liquid Controls Pulse Output
Device (POD) is typically installed onto the meter and wired to the Register at the factory. The
POD can also be ordered separately and installed onto meter systems already in service. For
mechanical installation instructions, refer to the POD manual. Instructions for wiring the POD to
the Register are given below.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
61
Page 62
LCR.iQ/MasterLoad.iQ Product Manual
These materials are necessary, but are not supplied with the POD:
·
16-22 AWG 4 conductor Shielded Cable (Consult the POD manual for complete
specifications)
·
Weather Proof flexible conduit or loom
·
½” Conduit connectors or cable glands
·
PTFE tape or thread sealant
Follow these steps to wire a POD to the Register:
1. Go to to Main Menu / Setup Menu / Meter Settings. Make sure Pulser Input Type is set
to Dual Channel.
2. Attach cable glands and/or conduit connectors to the POD and the Register port(s).
Make sure to use thread sealant on NPT threads.
3. Thread the wires through a piece of weatherproof conduit cut-to-length from the POD
port to a Register port.
4. Run the weatherproof conduit between the POD and the Register housing, pull the wires
through the ports, and tighten the connectors.
5. Connect the four POD terminals to four terminals on the J11 terminal block of the
Register CPU board.
·
POD terminal 20 to Register terminal 70
·
POD terminal 21 to Register terminal 68
·
POD terminal 22 to Register terminal 69
·
POD terminal 23 to Register terminal 63
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
62
Page 63
LCR.iQ/MasterLoad.iQ Product Manual
Single Channel Pulse Inputs
The Register is compatible with the many single channel pulse output devices.
To wire a single channel pulse output to the Register:
1. Go to Main Menu / Setup Menu / Meter Settings. Select Pulse Input Type, Single Channel.
2. Connect the three pulser terminals (V out, Channel A, and ground) as follows:
·
Pulser channel A to Register terminal 69
·
Pulser voltage out to Register terminal 70
·
Pulser ground to Register terminal 63
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
When ordered as part of a meter system with a Register, the Liquid Control ∆P transducer is
wired to the Register at the factory. The ∆P transducer can also be ordered separately and
installed onto a meter system already in service. Refer to the ∆P transducer manual for
complete installation instructions. Instructions for wiring the ∆P transducer to the Register can
be found below.
Typically, a ∆P transducer operates together with a shutdown device, such as a valve or a
dead-man.
Follow these steps to wire ∆P Transducer to the Register:
1.Route the ∆P transducer cable through a cable gland in a port on the back of the
Register. Secure the cable gland. LC recommends running the cable through
weatherproof conduit. Make sure to use thread sealant on NPT threads.
2.Connect the four ∆P transducer wires to terminals to the recommended Register
terminals as follows:
·
+VP / Black to terminal 12
·
GND / White (Ground) to 36
·
B / Yellow to terminal 38
·
A / Blue to terminal 37
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
64
Page 65
LCR.iQ/MasterLoad.iQ Product Manual
3.Route a two-wire cable from the shutdown control device through a cable gland in a
port on the back of the Register. Secure the cable gland. Make sure to use thread
sealant on NPT threads. Liquid Controls recommends running the cable through
weatherproof conduit.
4.Connect the two wires from the shutdown control device to terminals 23 (S1) and 24
(+VP).
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
65
Page 66
LCR.iQ/MasterLoad.iQ Product Manual
Current Draw on Shutdown Device
The shutdown device should draw no more than 1 Amp.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
66
Page 67
LCR.iQ/MasterLoad.iQ Product Manual
Disconnect Power
Disconnect the power before working on the CPU board.
Printers
Printer Installation (J1 RS-232)
A Liquid Controls meter system with a Register typically includes an Epson slip printer or roll
printer. The installation is the same for either printer.
See instructions in Routing Data and Power Cables for routing the data cable from the back
43
of the truck to the cab.
To wire a Printer to the Register:
1. Go to to Main Menu / Setup Menu / Register Settings (3/3) - Printer Type. Ensure
proper printer is selected in the drop down selection field.
2. Attach cable glands and/or conduit connectors to the Register port. Make sure to use
thread sealant on NPT threads.
3. Connect the wires to the J13 and J14 terminal blocks of the Register board.
·
GND / Black to terminal 80
·
CTS / Blue to terminal 81
·
RXD / Yellow to terminal 82
·
TXD / Orange to terminal 83
·
RTS / Brown to terminal 84
·
RTS / Red to terminal 92
·
TXD / Violet to terminal 91
·
RXD / Gray to terminal 90
·
CTS / Green to terminal 89
·
GND / White to terminal 88
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
67
Page 68
LCR.iQ/MasterLoad.iQ Product Manual
Routing Data Cables
See the instructions on Routing Data and Power Cables for routing the data cable from
the back of the truck to the cab.
Connecting Power
To connect power to the printer, see Power Supply.
- 82184 -
Epson Printer Ground Wire Kit
#
Description
Part Number
Quantity
1
Ground Wire
84101
1
2
Terminal (.375 ring, 16GA)
71878
1
43
To install the printer:
1. Mount the printer in the truck cab where drivers can easily operate it.
2. Clean the mounting spot and the bottom of the printer with alcohol for the best adhesion.
3. Attach Velcro to the mounting area and the bottom of the printer. Fasten the printer to
the mounting area.
4. Connect the data cable to the RS-232 data port on the back of the printer.
70
Epson Printer Ground Wire Kit Installation
Before connecting power to the Register and the Epson printer, ground the printer to the truck
cab floor. Epson printers sold for truck installations are all grounded in the same manner.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
68
Page 69
LCR.iQ/MasterLoad.iQ Product Manual
Additional Terminal
brackets that are not purchased from Liquid Controls.
Follow these steps to ground an Epson printer:
1. Remove one of the mounting bolts that fasten the printer mounting brackets to the truck
cab floor.
2. Place one end terminal of the ground wire over the mounting bolt and return the bolt to its
original place.
3. At the back of the Epson printer, remove the silver ground screw marked “FG”.
4. Place the other end terminal of the ground wire over the ground screw and return the
screw to its original place.
5. Check the strap for a good ground connection (see page 13).
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
69
Page 70
LCR.iQ/MasterLoad.iQ Product Manual
Power Supply
When you have made all of the data connections and complete installation of all components,
connect the power to the Register and the Epson printer. Before making the power
connections, go through the vehicle system checklist below, and ensure that the electrical
system of the truck meets the minimum requirements for powering the Register and the Epson
printer.
Vehicle System Checklist
·
Clean any corrosion from the battery terminals and battery cable to guarantee a solid,
tight connection.
·
Charge the battery according to manufacturer specifications.
·
Ensure the alternator is large enough to meet the total demands of the truck, including the
Register. The Register requires a minimum of 5 Amps for proper operation. Run the truck
at low idle, with all accessories on (including hose reel). Check the voltage with a
multimeter to confirm that the voltage doesn't drop below 11 Volts.
·
Inspect the electrical equipment on the vehicle to ensure proper installation and operation.
·
Determine whether the vehicle is grounded positively or negatively. Consult Liquid Controls
if the vehicle has a positive ground.
·
Ensure that any radio antennas are installed according to manufacturer specifications to
prevent RF interference.
Connect the Power
All Register shipments typically include a 50-foot gray power cable (100-foot and 300-foot
cables are also available) and a 5 Amp fuse.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
70
Page 71
This is the wiring diagram for the power supply:
Cable routing
Routing Data and Power Cables describes the best practices for routing the gray power
cable to the truck cab accessory panel.
LCR.iQ/MasterLoad.iQ Product Manual
43
50-foot Gray Power Cable
The gray power cable (PN 84512050) is prewired to the Register board at the factory (meter
mount version). It includes two 16AWG wires and a ground drain wire. Splice the 5 Amp fuse
into the red 16AWG wire as close to the power source as possible. Panel mount versions will
include the a loose power cable and must be installed according to the wire diagram.
Epson Printer Power
Power must be supplied to the Epson printer. For supplying power to the printer, a 15-foot
cable with a 12/24VDC converter (825001) is also available. The red wire of this cable must
be spliced into the red wire in the gray power cable on the Register side of the 5 Amp fuse.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
71
Page 72
LCR.iQ/MasterLoad.iQ Product Manual
Follow these steps to connect power to the Register and the Epson printer:
1. Route the gray power cable to the accessory panel. See Routing Data and Power
Cables.
43
2. Splice the red wire from the printer power cable into the red wire of the gray power
cable.
3. Splice the 5 Amp fuse to the red wire. close to the direct power terminal connection in
the accessory panel, and on the power side of the splice made with the printer power
cable.
4. Connect the red wire to the direct power supply terminal in the accessory panel.
5. Connect the black wire of the gray power cable to a reliable DC ground.
6. Connect the black wire of the printer power to a reliable DC ground.
7. Tape the green drain wire of the gray power cable back against the power cable.
Power Check
After the Register has been installed, check to ensure that it powers up correctly. The
Registerdisplay and the printer power light should come on when the truck ignition is turned
either to the ON position or the ACC position. Ensure that the printer power switch is on. If the
Register or the printer does not power up, check the wiring and the connections on the
Register board against the instructions in this manual.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
72
Page 73
LCR.iQ/MasterLoad.iQ Product Manual
IMPORTANT: Before Sealing the Register
After correctly powering up the Register, continue on to the Register Setup and Operation
manual to setup the Register for operation. We recommend that you setup and test the
Register before closing and sealing the unit.
Finalize the Installation
Close and Seal the Unit
After setting up and testing the unit, complete the installation by closing and sealing the
housing. The Register must be environmentally sealed to protect the electronics against the
elements. The Register must also be sealed by a Weights & Measures representative to
guarantee that the register is operating at the proper regulatory standards.
1. Secure the cables behind the Register and the cables in the cab with cable ties.
2. If conduit was used during the installation, fill the conduit end inside the Register with
silicon RTV (provided with shipment, PN 82575). Read and follow the directions of the
Environmental Sealing Guidelines, below.
3. Tighten the four socket head cap screws on the four corners of the cover housing using a
3/16 hex key or bit. Ensure that the gap between the cover and the housing is
completely closed. Ensure that the calibration screw is tightened to approximately 7-lb–
and properly sealed. Read and follow the directions of the Environmental Sealing
Guidelines, below.
4. Seal the cover, base, and calibration screw with a wire/lead seal. See the Weights &
Measures Seals section below.
Environmental Sealing Guidelines
The Register includes sensitive electronic components, including a microprocessor that can be
damaged by the presence of moisture. Therefore, it is essential that all conduit ports, the
cover, and the shaft seals be adequately sealed by the installer to ensure watertight integrity.
The conformal coating on the board mitigates the problem of corrosion due to moisture, but
this measure only protects the board from small amounts of moisture trapped inside when the
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
73
Page 74
LCR.iQ/MasterLoad.iQ Product Manual
Sealing the Register is the Responsibility of the Installer
There is no product warranty coverage for any water or moisture damage to the Register
that results from improper sealing.
lid is closed in humid conditions. It is not adequate for protecting the unit over time if a
continuous leak is present in the enclosure.
1. Conduit Entrances
The Register housing has 11 conduit entrances, all are ½" NPT female threads. Use only ½"
NPT male threaded fittings on the conduit entrances. Thread sealant must be used with NPT
threads. Pressed-in Caplugs or straight (rather than tapered) threads are inadequate for
sealing these entrances. Acceptable fittings include metal or plastic conduit, pipe plugs, or
cable glands.
Apply PTFE-based “pipe dope” to threads, or wind a minimum of two revolutions of PTFE tape
prior to installation. Engage the threads with a minimum of four full turns.When using cable
glands, ensure that the gland is sized properly for the outside diameter of the cable and the
elastometric seal around the cable sheath is compressed onto the cable. Use only one cable
per cable gland, unless the gland accommodates for multiple cables. When using conduit or
Liquid-Tite, ensure that the opposite end is connected to an environmentally sealed device. If
the conduit is not sealed at the other device, fill the interior of the conduit at the Register with a
silicone rubber sealant–such as RTV–to prevent moisture from running down the conduit into
the enclosure.
2. Cover Seals
To seal the Register cover properly, ensure that the O-ring surrounding the cover is fit snug
inside the groove, and securely tighten the cover screws.
3. Shaft Seals
Units with internal pulsers have an O-ring around under the pulser inside the enclosure, and
also a pulse encoder drive shaft that extends through the bottom of the Register housing. If a
drive shaft adapter was attached at installation, ensure the O-ring around the shaft is securely
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
74
Page 75
LCR.iQ/MasterLoad.iQ Product Manual
seated in the counter bore of the casting, covered with the flat washer provided, and held in
place with the cotter pin provided.
Any water or moisture damage to the Register as result of improper sealing will not be
covered under the product warranty. Sealing the Register is the responsibility of the installer.
Weights & Measures Seals
To detect possible intrusions into Weights & Measures approved calibrations on a Register,
retainer holes have been drilled into the side of the enclosure adjacent to the Weights &
Measures Screw. Properly tighten the Weights and Measures screw to approximated 7 lb-in of
torque or the proper visual tightening.
To seal according to Weights & Measures standards, a wire is threaded through the retainer
holes and closed with a lead seal.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
75
Page 76
Spare Parts - External Components
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
76
Page 77
Spare Parts - Internal Components
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
77
Page 78
Spare Parts - Board Components
84352 Interface Board
LCR.iQ/MasterLoad.iQ Product Manual
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
78
Page 79
LCR.iQ/MasterLoad.iQ Product Manual
Appendix A: K-Factor (Pulse/Unit) Chart
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
79
Page 80
LCR.iQ/MasterLoad.iQ Product Manual
TypeName
Description
A
ASCII Character
Contains a one byte ASCII character. The number of characters stored in the
field is Size.
AZ
ASCIIZ String
Contains a NUL terminated string of ASCII characters. The maximum length of
the string is Size-1.
B
Boolean
Contains a Boolean value of TRUE or FALSE.
D
Double Floating
Point
Contains an eight byte floating point number in IEEE-754 format.
F
Floating Point
Contains a four byte floating point number in IEEE-754 format.
LF
LCR Flow Rate
Contains a signed four byte integer in the range -2147483648 to 2147483647
with an implied decimal point defined by the decimals field in the record.
LL
LCR List
Contains a one byte unsigned integer in the range of 0 to 255.
LV
LCR Volume
Contains a signed four byte integer in the range -2147483648 to 2147483647
with an implied decimal point defined by the decimals field in the record.
SB
Signed Byte
Contains a one byte signed integer in the range -128 to 127.
SI
Signed Integer
Contains a signed integer in which the range is operating system dependent. On
16-bit machines, it is a two-byte signed integer in the range -32768 to 32767.
On 32-bit machines, it is a four-byte signed integer in the range -2147483648 to
2147483647.
SL
Signed Long
Contains a four byte signed integer in the range -2147483648 to 2147483647.
SS
Signed Short
Contains a two byte signed integer in the range -32768 to 32767.
ST
Structure
Data element is a structure that varies depending on the structure definition.
UB
Unsigned Byte
Contains a one-byte unsigned integer in the range of 0 to 255.
UI
Unsigned Integer
Contains an unsigned integer in which the range is operating system dependent.
On 16-bit machines, it's a two byte unsigned integer in the range 0 to 65535. On
32-bit machines, it's a four byte unsigned integer in the range 0 to 4294967295.
UL
Unsigned Long
Contains a four byte unsigned integer in the range 0 to 4294967295.
UN
Union
Data element is a union, and the contents vary depending on the union definition.
US
Unsigned Short
Contains a two-byte unsigned integer in the range 0 to 65535.
Appendix B: Data Types
For data types D, F, SI, SL, SS, UI, UL, US, and V, the least significant byte of the data is
stored at the lowest address with each subsequent byte being stored at the next incremented
address. For example, a two byte unsigned short equal to 1,000 and placed at offset 4 in a
message or record would be stored as an E8h at offset 4 and a 03h at offset 5.
Get the latest PDF manual: https://www.lcmeter.com/resources/technical/manuals
Mobile/online version of this manual: https://www.lcmeter.com/manuals
80
Page 81
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.