In response to new advancement in condensing boiler design and size, many applications utilize multiple condensing boilers in
addition to the non-condensing boilers. That triggered Laars's design of the M4-LHS. It is intended to manage the two groups of
When Hybrid is selected
as the Boiler Type, the M4-LHS will select the lead group based on the Target temperature switching set point. See "Switch Set
Point" on page 20. The Condensing group of boilers will be the Lead group when the System Temperature is below the System Target
Switching Set Point. However, when the System Temperature rises above the Switching Set Point, the Non-Condensing boiler group
will be the lead group and the Condensing Group will be the lag group.
Basically, the M4-LHS will allow the condensing group of boilers to operate as along as the System sensor is below the Switching Set
Point. See"Switch Set Point" on page 20. During that period, if additional output boilers are needed, the M4-LHS may energize the
Non-Condensing boilers to meet the load depending on the Heavy Load Sequence 2nd Group setting. See"Heavy Load Sequence 2nd
Group" on page 21. When less output is required the M4-LHS will de-energize the lag group of boilers prior to de-energizing the lead
group of boilers.
To eliminate any short-cycling due to rapid changes in the Target Temperature used in the switching, an adjustable Switching Delay
has been incorporated. See"Switch Delay" on page 21.
Each of the condensing and non-condensing groups of boilers can be either modulating or staging. Modulating boilers can be of
4-20mA modulating signal or 0-10V modulating signal. See "Modulating Output Type" on page 23. Staging boilers can be On/Off,
2-Staeg, 3-Stage, or 4-Stage. See "Staging Output Type" on page 22.
For Hybrid settings, See "Boiler Type" on page 19.
To set the Condensing and Non-Condensing boiler types See "HYBRID Modulating Boiler Settings" on page 22.
System
Temp
140°F
120°F
100°F
SWITCH MODE = Target Temperature
SYSTEM
o
o
OD=
F SYS=
F
25
145
A
B
<<A>> B
100% 52%
C
NONCOND
NONCOND
NONCOND
CONDCOND
CONDCOND
NONCOND
D
RUNPROGRAM
B
C
A
S
D
WR
B
C
A
SY
P
/ VLT
CUR / VLT
CU
CUR / VLT
R
m
mAGND
V
mAGND
A
V
GND
LT
LT
L
N
-
-
+
+
+
+
+
5
19
2
15
3
0
18
6
13
910
16
78
1
17
4
11
12
2
14
Target Switch
Set Point
SYSTEM
A
B
C
D
RUNPROGRAM
C
A
B
A
D
WR
SYS
B
C
P
V
T
R
V
U
/
L
CUR
R / VLT
/
CU
C
AGND
mAGND
mAGND
VLT
VLT
m
LN
-
-
+
+
+
+
5
13
9
15
3
19
20
18
6
78
16
10
4
17
11
12
14
1
2
Above the Switch Set Point
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
N
SHUTDOW
N
N
SIO
E
XTE
PROVE
OUTDOOR
SYSTEM
D
TS
TAT
/
/DHW
E
MODUL
TE
MP
TEMP
CUR / VLT
K
A
E
C
TB
/S
AGND
A
V
V
LT
LT
m
m
-485
RS
TO
O
O
O
T
+
+
+
+
2
9
30
28
31
32
26
25
23
22
24
27
21
Non-Condensing are the Lead Group
Condensing are the Lag Group
= 120°F
o
o
OD=
F SYS=
F
25
145
<<A>> B
100% 52%
Below the Switch Set Point
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OWN
S
HUTD
EXTENSION
VE
PRO
M
ST
OUTDOOR
S
E
Y
D
/TSTAT
/DHW
MODULE
T
TEMP
EMP
LT
CUR / VLT
/SETBACK
AGND
A
VLT
m
m
VLT
S
-485
R
O
O
O
O
T
T
++
+
+
+
6
32
23
2
28
29
3031
25
21
22
24
27
Condensing are the Lead Group
Non-Condensing are the Lag Group
M4-LHS Installation and Operation Manual
HT# 059295-00 A
3
MODULATING LOGIC OVERVIEW
The Modulation PID logic is capable of controlling multiple modulating current or voltage boilers. When heat is required, the control
PID activates the lead boiler and starts its purge. See "Purge Delay" on page 31. This is followed by the initiation of its modulation at
the Ignition %. See "Ignition %" on page 40. When additional heat is needed, the control starts to increase the lead boiler modulation
until the Modulation Start % has been reached. See "Modulation Start %" on page 40. Any additional heat requirement starts the lag
boiler purge. While the lag boiler is in purge, the lead boiler resumes its modulation until it reaches full re (100% modulation).
Additional heat requirements triggers the control to increase the lag boiler modulation.
When the M4-LHS PID requires reduced output, it will reduce the modulation of the lag boiler until it reaches its Ignition %. That
shall be followed by the reduction of modulation of the lead boiler until it reaches 40% percent of the Modulation Start %. This shall
trigger the control to turn off the lag boiler. The control will keep reducing the lead boiler modulation until it reaches its Ignition %.
If the Last Stage Hold was activated, the control will hold the lead boiler at the Ignition % until the System Temperature exceeds the
Target Set Point by the Last Stage hold setting. See "Last Stage Hold" on page 32.
For Modulating boilers, See "Boiler Type" on page 19. Also, See "HYBRID Modulating Boiler Settings" on page 22.
HT# 059295-00 A
4
M4-LHS Installation and Operation Manual
OUTDOOR RESET CONCEPT
Outdoor Temperature (in °F)
70 60
50
4020
300 -10
10-20
100
120
110
130
140
150
160
180
170
190
200
210
220
1:31:21:1.5
1:1.25
1:1
1.25:1
1.5:1
2:1
3:1
4:1
Water Temperature (in °F)
Reset Ratio Curves
Reset Ratio is Presented as
Outdoor Temp. : Water Temp. Ratio
1:4
The M4-LHS has multiple operating modes that satisfy most hydronic systems. It
changes the System Set Point based on outdoor temperature (Outdoor Reset). The
M4-LHS varies the temperature of the circulating heating water in response to
changes in the outdoor temperature. The heating water temperature is controlled
through the modulation or sequencing of the stages.
The M4-LHS also controls the system circulating pump with an adjustable Outdoor
Cutoff. When the outdoor temperature is above the Outdoor Cutoff, the pump
is off and no heating water is circulated through the system. When the outdoor
temperature drops below the Outdoor Cutoff, the system pump relay is activated
and the heating water circulates through the system. The temperature of the heating
water is controlled by the Reset Ratio, Water Offset, and changes with Outdoor
Temperature.
Reset Ratio/Outdoor Reset
When a building is being heated, heat escapes through the walls, doors, and windows
to the colder outside air. The colder the outside temperature, the more heat escapes.
If you can input heat into the building at the same rate that it is lost out of the
building, then the building temperatures will remain constant. The Reset Ratio is an
adjustment that lets you achieve this equilibrium between heat input and heat loss.
The starting point for most systems is the 1.00 (OD):1.00 (SYS) (Outdoor
Temperature : Heating Water Temperature) ratio. This means that for every degree
the outdoor temperature drops, the temperature of the heating water increases by one
degree. The starting point of the curves is adjustable, but comes factory selected
at 70°F Outdoor Temperature and 100°F Water Temperature. For example with
a 1.00 (OD):1.00 (SYS) ratio, if the outdoor temperature is 50°F, this means the
temperature has fallen 20° from the starting point of 70°F. Therefore, the heating
water temperature shall increase 20° to 120°F.
Each building has different heat loss characteristics. A very well insulated building
will not lose much heat to the outside air, and may need a Reset Ratio of 2.00
(OD):1.00 (SYS) (Outdoor:Water). This means the outdoor temperature would
have to drop 2° to increase the water temperature 1 degree. On the other hand, a
poorly insulated building with insufcient radiation may need a Reset Ratio of 1.00
(OD):2.00 (SYS). This means that for each degree the outdoor temperature dropped
the water temperature increases by 2°. The M4-LHS has a full range of Reset Ratios
to match any buildings heat loss characteristics.
A heating curve that relies not only on Outdoor Temperature but also on the type
of radiation improves heat comfort. The following are suggested initial settings for
different types of radiation based on average building insulation and heat loss. The
contractor can ne tune these adjustments based on the specic building need.
Fan Coils & Air Handlers1.00 (OD) : 1.00 (SYS)20˚F
M4-LHS Installation and Operation Manual
With a 0° Offset, the
Reset curves begin at
100° Water Temperature.
With a -20° Offset, the
Reset curves begin at
80° Water Temperature.
With a +20° Offset, the
Reset curves begin at
120° Water Temperature.
130
120
110
Water T emp erature
100
70405060
Outdoor Temperature
110
100
90
Water Tem peratur e
80
70405060
Outdoor Temperature
150
140
130
Water Tem per ature
120
90
100
70405060
Outdoor Temperature
1:41:1
4:1
1:4
-20 Offset
1:4
1:1
4:1
1:1
+20 Offset
5
4:1
HT# 059295-00 A
CONTROL LAYOUT
Program Switch to restrict access to
function changes. This switch is
covered with Wiring Enclosure.
LED indicates the
associated relay status.
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
PWR
L
1
to de-energize the equipment before servicing.
SYS
N
2
3
4
A
B
C
D
5
6
7
8
9
10
11
12
The digital display shows the system status, set point,
lead stage <in brackets>, and status of each stage.
To view and adjust settings, press the appropriate buttons.
Buttons function is presented on
Bottom Row of display.
M4-LHS
SYSTEM
A
B
C
D
A
CUR / VLT
GND
13
B
CUR / VLT
mA
VLT
-
+
15
14
CUR / VLT
GND
mA
VLT
GND
-
+
-
+
+
16
18
19
17
HYBRID CONTROL
o
F
OD=35
<<A>> B
100% 50%
STAGE MENU
D
mA
mA
VLT
+
+
+
24
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OUTDOOR
TEMP
T
O
25
26
RUNPROGRAM
C
CUR / VLT
mA
VLT
GND
-
+
+
20
23
21
22
SYS=145
SYSTEM
PROVE
TEMP
/DHW
T
O
28
29
27
O
30
o
F
SHUTDOWN
/TSTAT
/SETBACK
O
31
EXTENSION
MODULE
RS-485
120VAC Power
Four N.O. Boiler startup relay
outputs. Each is wired in series
with each boiler's limit circuit.
When connecting the control Outdoor Air
Sensor and System Sensor, no polarity is
observed. Prove terminals must be connected
for control to operate boilers.
System Output controls
pumps, valves, or other
system components.
Four modulation/staging outputs can be
4-20mA or Voltage. Go to Startup Menu
to determine the type of output for each stage.
Connect Extension panels to add
additional stages using a RJ11 cable(cable
provided with Extension) and RJ45-RJ11
Adaptor (Supplied with control) only or add
X-BAC BACnet Interface Module using RJ45
(cable provided with X-BAC Module)
PART NUMBER # CA009200
HT# 059295-00 A
6
M4-LHS Installation and Operation Manual
EXTENSION LAYOUT
Extension Selection Switch to determine
Stage letters and LED colors.
Ext-A Stages E - J and all LEDs are Green
Ext-B Stages K - P and all LEDs are Red
This switch is covered with the Wiring Enclosure.
LED indicates the
associated relay status.
PWR
L N
1 2
CUS
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
LISTED
99RA
KMOLNP
E
3 4F5 6G7 8H9 10I11 12
FULL MODULATION SEQUENCING EXTENSION
E
G
I
Comm
J
11 12
M4Ext
K
M
O
L
F
N
H
J
P
Power
CAUTION:
More than one disconnect switch may be required
to de-energize the equipment before servicing.
VLTmA
1514
CUR / VLT
GND
16
VLTmAGND
181716
Ext B
CUR / VLT
GND
19
VLTmAGND
212019
Ext A
KMLN
EFGH
CUR / VLT
GND
13
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz, 12VA MAX
Use Copper Conductors Only.
Risk of Electric Shock.
CUR / VLT
VLTmAGND
GND
242322
22
OP
IJ
CUR / VLT
GND
25
VLTmA
2726
CUR / VLT
GND
28
EXTENSION
VLTmAGND
302916
MODULE
RS-485
120VAC Power
outputs. Each is wired in series
with each boiler's limit circuit.
4-20mA or Voltage. Go to the control Startup
Menu to determine the type of output for each stage.
M4-LHS Installation and Operation Manual
Six N.O. Boiler startup relay
Six modulation/staging outputs can be
PART NUMBER # CA004400
Connect to any M4-LHS
and additional Extension panels to add
additional stages using a RJ11 cable only
(cable provided with M4Ext).
HT# 059295-00 A
7
FEATURES
Laars designed the M4-LHS with Hydronic building heating, using both condensing and non-condensing boilers, as the primary purpose.
In addition, the M4-LHS is capable of controlling modulating and staging boilers. With this in mind, many of the M4-LHS features can
be utilized to ease, enhance, and improve your system performance.
Condensing and Non-Condensing Boilers Can be Modulating or Multi-Stage.
The M4-LHS can operate both modulating and staging boilers. Just specify each of the Condensing and Non-Condensing boiler group
type and the M4-LHS activates the groups based on an adjustable set of criteria.
PID Type Logic
The M4-LHS's control algorithms allow it to look at the rate of change in the system. If the system temperature is changing quickly,
the M4-LHS reacts quickly to adjust the modulating stages’ output. If the system temperature changes slowly, the M4-LHS shall make
slow and gradual output adjustments. Therefore, the M4-LHS adapts to specic system requirements and minimizes uctuations around
the set point.
Controls 0-10 V or 4-20 mA modulating Burners
Whenever any of the Condensing or Non-Condensing group type is set to Modulating, the M4-LHS accurately controls the output from
0 to 100% of modulation for each of these different types of motors. Moreover, a single M4-LHS can control multiple modulating burners
each with a different modulating signal.
Controls On/Off, 2-Stage, 3-Stage, or 4-Stage Burners
Whenever one of the Condensing or Non-Condensing group Type is set to Staging, the M4-LHS accurately sequences the stages using
a PID logic.
Digital Display of all System Settings
The M4-LHS's alphanumeric digital display names each system parameter in simple English and shows its precise value. The easy
to follow menu system allows users to quickly make changes to any system setting without having to learn any specialized codes or
keyboard commands.
Automatic Rotation among Stages
Rotating the lead stage of each group promotes even wear. The M4-LHS has three modes of rotation: Manual, Last On, or Time. The
Time rotates the lead stage every selected period from every hour to every 60 days.
Outdoor Reset or Set Point
The M4-LHS has a hydronic outdoor temperature reset function. This allows the M4-LHS to change the set point based on outdoor
temperature. Furthermore, additional settings have been added to ne tune this operation, like Offset, Minimum, and Maximum Water
Temperature and night setback schedule.
System Output
This output can be used to activate a system pump, combustion air damper, or perform any other function that is required when any stage
is active. It energizes whenever the outdoor temperature is below the Outdoor Cutoff setting. A System Prove input checks the status
of components activated by the System output before stages can be activated.
Normal or Parallel Modulation
The M4-LHS can stage modulating boilers as needed. In Normal Modulation, it increases the lead boiler modulation until it reaches
its Modulation Start percent adjustment. Then, the M4-LHS starts the next boiler and so on. Moreover, the M4-LHS offers a parallel
mode that can modulate several boilers together as a single large boiler. This mode is useful when used with condensing boilers as they
run more efcient at lower modulation. Thus, it is better to run several boilers at lower modulation than to run a single boiler at full re.
Add up to 16 Boiler Stages (Optional)
As a stand-alone, the M4-LHS is designed to control four stages. However, it has the capability of expanding its control to two extension
panels each with six boiler stages. Thus, the M4-LHS can control a total of up to 16 boiler stages.
HT# 059295-00 A
8
M4-LHS Installation and Operation Manual
Setback or Day/Night Scheduling
Two Setback modes are available for the M4-LHS:
• The Day/Night Scheduling provides an adjustable time-based schedule for the Setback (only available when Shutdown or Tstat is
selected as the Setback/Shutdown Startup option). See "Shutdown/Tstat/Setback Mode" on page 24.
• The Setback mode uses an external signal to switch the operation of the M4-LHS in and out of setback mode (only available when
Setback is selected as the Setback/Shutdown Startup option).
Remote Set point (EMS 4-20mA)
By connecting the control to the optional 4-20mA EMS Interface (X-SIG), the control shall be capable of accepting a remote set point.
BACnet MS/TP Communication
An optional BACnet Interface Module (X-BAC) (CA009100) can be used to connect the control to a BACnet MSTP network for remote
access.
MAKE SURE YOU HAVE THE RIGHT CONTROL
If you need the M4-LHS to do additional tasks that either are not listed or do not know how to congure them, contact your local
Laars representative.
Setting an Initial Program will ease the conguration of the M4-LHS and will give the opportunity to utilize many of the energy saving
features while giving comfortable heat when needed.
The program should consist of the following:
• Selecting the features that your system can utilize.
• Installation: Install the Control, switches and sensors. See"Installation" on page 10
• Setting the System Startup. See "Startup Settings" on page 19.
• Setting the System Operating Settings. See "Operating Settings" on page 27
• Setting the Stages. See "Modulating Boiler Operating Settings" on page 33. Also, see "Staging Boiler Operating Settings" on page 34
• Adjusting Reset Ratio and Water Offset (In Reset Mode Only). See "Reset Ratio" on page 27
M4-LHS Installation and Operation Manual
HT# 059295-00 A
9
INSTALLATION
Each of the M4-LHS or Extension consists of three primary enclosure components.
• TheEnclosureDisplayModule: contains the control electronic board, display, buttons, LEDs, and electric wiring terminals.
It has two screws to hold it to the base. A program conguration switch, used to adjust the control settings, is placed above the
terminals. This switch is enclosed with the enclosure wiring cover for security. Wiring terminals are of the plug-in type to ease
installation and removal.
• TheEnclosureBase: contains the holes to mount and hold the control against the wall or any at surface. All other enclosure
components mount on the base. The bottom section of the Enclosure Base contains the wiring chamber with knockouts on the
bottom to ease installation.
• TheEnclosureWiringCover: seals the wires from the external environment. It has two screws to hold it the base and a hole to
secure a lock on the wiring enclosure. A plastic web that separates the wiring chamber into high and low volt sections has been
provided.
MOUNTING THE ENCLOSURE
• Select a location near the equipment to be controlled.
• The surface should be at and sufciently wide and strong to hold the M4-LHS or the Extension.
• Keep the control away from extreme heat, cold, or humidity. Ambient operating temperature is from 20 to 120°F.
• Remove the Enclosure Wiring Cover from the control enclosure by removing the two bottom screws.
• Remove the Enclosure Display Module by removing the enclosure middle screws.
• Screw the Enclosure Base to the surface through the upper and lower mounting holes on the back of the enclosure.
• Replace the Enclosure Display Module and replace the enclosure middle screws.
• Do not replace the enclosure wiring cover until all wiring is done.
• When purchasing a padlock for the enclosure, the maximum shank diameter should not exceed ¼"
Enclosure Display Module
Enclosure Wiring CoverEnclosure Base
Hole for optional lock
Mounting Holes
Display Mounting Screws
Wiring Cover
Mounting Screws
HT# 059295-00 A
10
M4-LHS Installation and Operation Manual
INSTALL THE SENSORS
System
Strap-On
Sensor
Shield
Not connected
Plastic
Tie-Wraps
Around Pipe
Strap-On Sensor
Outdoor Sensor
System Sensor Installation
• Only use the System sensor (CA002500 or equivalent) provided with the unit.
• The sensor wires can be extended up to 500' using a shielded 2-conductor cable
(Belden #8760 or equivalent). Do not ground the shield at the sensor but at the
panel using one of the terminals marked with an “O”.
• Do not run sensor wires in conduit with line voltage wiring.
• Install a 3/8"ID 1/2"NPT immersion well.
• If installing the system sensor on the supply, insert the sensor in a well with heat
paste approximately 5' feet past the boiler loop outlet on the common supply
header but before any major takeoffs. The sensor must be located where it sees
the output of all the boiler stages. If a boiler is piped so that the sensor does not
see its output, the M4-LHS will not sequence the boilers correctly.
• The sensor can also be installed on the return to the boilers after all major returns
and before any boiler. However, when setting the reset ratio and the offset, the
user must consider the temperature drop across the building loop.
WARNING
Use only the System and Outdoor Air sensors included with the control. Do
not use boiler sensors as it will cause operational problems.
Outdoor Sensor Installation
• Only use the Laars Outdoor Air Sensor group included with the unit (CA006500).
• Locate the sensor in the shade on the north side of the building. The sensor
should never be in direct sunlight.
• Be sure the location is away from doors, windows, exhaust fans, vents, or other
possible heat sources.
• The sensor should be mounted approximately 10' feet above ground level.
• Adhere the Outdoor Label provided to the back of the sensor base.
• Use the Enclosure Base bottom knockout for the conduit. Use the locknut to hold
the conduit and enclosure base together. Screw the cover to the base.
• If screws are used to afx the enclosure to the wall, make sure to seal around the
sensor and wall except from the bottom.
• The sensor wires can be extended up to 500' using shielded 2-conductor cable
(#18/2). Do not ground the shield at the sensor but at the control using the
terminal marked with an “O”.
• Do not run sensor wires in conduit with line voltage wiring.
Immersion Heating System Sensor
Immersion Well
3/8" ID 1/2" NPT
Shield
Heating System
Sensor
Common Supply Pipe
Sensor Probe
ALERT
If the HSS can not sense the correct water
temperature, the M4-LHS will not provide
comfortable heat levels.
Seal around
sensor and wall
Outdoor Sensor
snap-in location
Mounting
screws
location
Outdoor
drip-hole
Outdoor Label
on back of Sensor
Shield
not connected
ALERT
Determining the proper location of the Outdoor Sensor is very important. The M4-LHS will base
the heat on the outdoor temperature information it receives from this location. If the sensor is in the
sun, or covered with ice, its reading will be different from the actual Outdoor Temperature (OD).
M4-LHS Installation and Operation Manual
Conduit
HT# 059295-00 A
11
WIRING
SYSTEM
A
B
C
D
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
3
4
5
6
7
8
9
10
11
12
13
15
14
17
16
18
20
19
21
24
23
29
25
27
26
28
32
30
31
-
+
+
T
T
O
O
RS-485
mA
GND
VLT
SYS
A
B
C
D
CUR / VLT
A
-
+
+
mA
GND
VLT
-
+
+
mA
GND
VLT
+
+
mA
22
-
GND
VLT
+
mA
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
CUR / VLTBCUR / VLTCCUR / VLT
D
PROVE
/DHW
SHUTDOWN
/SETBACK
FOR ALL CIRCUITS
120VAC, 6A RESISTIVE
OUTPUT RATINGS:
1A PILOT DUTY, 15ATOTAL
115VAC 60Hz , 30VA MAX
INPUT RATINGS:
USE COPPER WIRE,CLASS 1 WIRE ONLY.
CAUTION
: RISK OF ELECTRIC SHOCKMore than one disconnect switch may be requiredto de-energize the equipment before servicing.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
/TSTAT
M4-LHS
HYBRID CONTROL
32
31
RS-485
O
EXTENSION
MODULE
SHUTDOWN
/SETBACK
/TSTAT
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
29
32
30
31
RS-485
O
O
EXTENSION
MODULE
PROVE
/DHW
SHUTDOWN
/SETBACK
/TSTAT
RS-485
EXTENSION
MODULE
• All wiring must enter the enclosure through the bottom knockouts.
• Class 1 voltage wiring must utilize a different knockout and conduit from any Class 2 voltage wiring.
Wiring the Power
(Terminals 1, 2)
• Bring the 120VAC 60Hz power wires through the bottom left knockout of the enclosure.
• Connect the hot line to terminal marked L.
• Connect the neutral line to the terminal marked N.
• Laars recommends installing a surge suppressor on the power source to the M4-LHS.
WARNING
Class 1 voltages must enter the enclosure through a different opening from any Class 2 voltage wiring.
Laars recommends installing a surge suppressor on the power source to the M4-LHS.
Wiring the Sensors
WARNING
Connect the shield at the control terminal end and cut the shield wire at the sensor end.
To avoid operational problems, use only the System and Outdoor Air sensors included with the control.
System Sensor Wiring
(Terminals 27, 28)
• A M4-LHS must be connected to a System Temperature sensor (CA002500 or equivalent) located in the common
header. The sensor must be inserted in a 3/8 ID well using heat paste.
• Temperature sensor wires can be extended up to 500’ by splicing its wires with a shielded 2-conductor cable
(Belden #8760 or equivalent (#18/2)).
• Temperature sensors have no polarity. Connect the two wires from the sensor to the M4-LHS terminals marked
SYSTEM TEMP 27, 28.
• Connect the sensor shield to the circled terminal 28 with one of the sensor wires.
Outdoor Sensor Wiring
(Terminals 25, 26)
• The M4-LHS will vary the system Set Point based on outdoor temperature. In addition, the Outdoor Air Sensor
group (CA006500) is used as an Outdoor Cutoff. The M4-LHS will disable all boilers when the outdoor
temperature is above the adjustable Outdoor Cutoff temperature.
• For an outdoor sensor use the outdoor sensor provided.
• The sensor wires can be extended up to 500’ using shielded 2-conductor cable (Belden #8760 or equivalent (#18/2)).
• Temperature sensors have no polarity. Connect the wires from the outdoor sensor to the M4-LHS terminals marked
• Connect the shield to the circled terminal 26 with one of the sensor wires.
OUTDOOR TEMP - 25, 26.
Wiring the Shutdown, Tstat, or Setback
(Terminals 31, 32)
• The Shutdown will be available when selected as the Shutdown/Tstat/Setback mode from the Startup menu. See
• The Shutdown feature can be used whenever it is desirable to turn off the M4-LHS stage outputs from a remote
• The Tstat option, when selected from the Shutdown/Tstat/Setback startup menu, offer the capability of controlling
• The thermostat will send the M4-LHS a call for heat by shorting terminals 31 and 32.
"Shutdown/Tstat/Setback Mode" on page 24. This will provide the user with an adjustable Day/Night Schedule. See
"Day - Night Schedule" on page 36.
location or another controller (i.e. EMS input).
the operation of the M4-LHS based on a thermostat input. This will provide the user with a adjustable Day/Night
Schedule.
PWR
N
L
1
2
Line
Neutral
120VAC
Power Source
SYSTEM
TEMP
T
O
28
27
System Sensor
OUTDOOR
TEMP
T
O
25
26
Outdoor Sensor
SHUTDOWN
/TSTAT
/SETBACK
O
O
32
30
31
Shutdown,
T-Stat, or
Setback Signal
PROVE
/DHW
O
30
29
Sensor Shield
SYSTEM
TEMP
T
O
28
27
Sensor Shield
HT# 059295-00 A
12
M4-LHS Installation and Operation Manual
• When the Shutdown input is enabled by closing the dry contact, or when the Tstat input is disabled by opening the
RS-485
EXTENSION
MODULE
RS-485
EXTENSION
MODULE
SYSTEM
A
B
C
D
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
7
8
9
10
11
12
13
15
14
17
16
18
20
19
21
24
23
29
25
27
26
28
32
30
31
-
+
+
T
T
O
O
RS-485
mA
GND
VLT
B
C
D
CUR / VLT
A
-
+
+
mA
GND
VLT
-
+
+
mA
GND
VLT
+
+
mA
22
-
GND
VLT
+
mA
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
CUR / VLTBCUR / VLTCCUR / VLT
D
PROVE
/DHW
SHUTDOWN
/SETBACK
FOR ALL CIRCUITS
120VAC, 6A RESISTIVE
OUTPUT RATINGS:
1A PILOT DUTY, 15ATOTAL
115VAC 60Hz , 30VA MAX
INPUT RATINGS:
USE COPPER WIRE,CLASS 1 WIRE ONLY.
CAUTION
: RISK OF ELECTRIC SHOCKMore than one disconnect switch may be requiredto de-energize the equipment before servicing.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
/TSTAT
M4-LHS
HYBRID CONTROL
dry-contact, all active modulating boilers will immediately modulate down to low for the Soft-Off period, then turn
off. All staging boilers will turn off immediately.
• The System Output relay will remain active until the System Run-On Delay expires and then it will turn off.
• When Setback is selected in the Startup, a BMS/EMS or external clock can provide a Setback signal using these
input terminals. See "Shutdown/Tstat/Setback Mode" on page 24. No Day/Night Schedule will be available when
Setback is selected from the Shutdown/Tstat/Setback mode in the Startup menu.
• Bring the two wires from the dry contact to the terminals marked SHUTDOWN/TSTAT/SETBACK- 31,32.
• The signal must be a dry contact only. No voltage can be placed across the SHUTDOWN/TSTAT/SETBACK
terminals.
Wiring the Prove
(Terminals 29, 30)
• The Prove feature checks system component operation and must be selected in the Startup Menu from the Prove/
DHW Sharing menu. See "Prove/Indirect Domestic Hot Water (DHW) Priority" on page 24.
• A typical use of this feature is to check for pump ow or combustion air damper status before ring any boiler.
• If the PROVE input is open on a call for heat, the M4-LHS enables only the System Output. All boiler outputs
will be off when the PROVE input is open.
• A factory-installed jumper provides the System Prove signal. Do not remove the jumper unless it is replaced with
a System Prove signal or these terminals are to be used for DHW call input.
• Bring the two wires from the dry contact to the terminals marked PROVE - 29, 30.
• Prove Input terminals can accept a dry-contact signal only. No voltage can be placed across these terminals.
SHUTDOWN
PROVE
/DHW
O
O
30
29
Prove Signal
/TSTAT
/SETBACK
O
32
31
WARNING
The PROVE input cannot be used as a safety limit. All equipment must have its own
certified limit and safety controls as required by local codes. If Prove is selected in the
startup menu, no boiler stage will start unless Prove terminals are shorted. DO NOT remove
the PROVE jumper supplied unless replacing it with a Prove signal.
Wiring the Indirect Domestic Hot Water (DHW) Call
(Terminals 29, 30)
• DHW can be used to raise system Set Point to the DHW Set Point as well as manage the System Pump according
to the DHW Priority setting. One of the DHW options must be selected from the Prove/DHW Sharing Startup
menu. See "Prove/Indirect Domestic Hot Water (DHW) Priority" on page 24.
• Remove the existing jumper and wire an aquastat or a control to provide dry-contact closure to the DHW Call - 29,
30 terminals.
• DHW Call terminals can accept dry contact signals only. No voltage can be placed across these terminals.
Wiring the System Output
(Terminals 3, 4)
• The SYS output relay will energize and remain constantly energized whenever the outdoor temperature is below
the Outdoor Cutoff.
• When the outdoor temperature rises 2°F above the Outdoor Cutoff, the SYS output will remain energized for the
period set by the System Run-On then de-energize. See "System Run-On" on page 31.
• In addition, the System output will energize during summer DHW calls when DHW No Priority is selected. See
"Prove/Indirect Domestic Hot Water (DHW) Priority" on page 24.
• The SYS output has one Normally Open (N.O.) relay contact rated for (1/8 HP).
• The N.O. contacts are dry contacts only. They do not source any voltage.
• Class 1 voltages must enter the enclosure through a different opening from any Class 2 voltage wiring.
PROVE
/DHW
O
O
30
29
28
Indirect
DHW Signal
SYS
3
4
L
N
System Pump
or Pump Starter
SHUTDOWN
/TSTAT
/SETBACK
O
32
31
A
5
6
M4-LHS Installation and Operation Manual
HT# 059295-00 A
13
Wiring the Boilers
SYSTEM
A
B
C
D
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
9
10
11
12
13
15
14
17
16
18
20
19
21
24
23
29
25
27
26
28
32
30
31
-
+
+
T
T
O
O
RS-485
mA
GND
VLT
C
D
CUR / VLT
A
-
+
+
mA
GND
VLT
-
+
+
mA
GND
VLT
+
+
mA
22
-
GND
VLT
+
mA
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
CUR / VLTBCUR / VLTCCUR / VLT
D
PROVE
/DHW
SHUTDOWN
/SETBACK
FOR ALL CIRCUITS
120VAC, 6A RESISTIVE
OUTPUT RATINGS:
1A PILOT DUTY, 15ATOTAL
115VAC 60Hz , 30VA MAX
INPUT RATINGS:
USE COPPER WIRE,CLASS 1 WIRE ONLY.
CAUTION
: RISK OF ELECTRIC SHOCKMore than one disconnect switch may be requiredto de-energize the equipment before servicing.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
/TSTAT
M4-LHS
HYBRID CONTROL
SYSTEM
A
B
C
D
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
13
15
14
17
16
18
20
19
21
24
23
29
25
27
26
28
32
30
31
-
+
+
T
T
O
O
RS-485
mA
GND
VLT
CUR / VLT
A
-
+
+
mA
GND
VLT
-
+
+
mA
GND
VLT
+
+
mA
22
-
GND
VLT
+
mA
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
CUR / VLTBCUR / VLTCCUR / VLT
D
PROVE
/DHW
SHUTDOWN
/SETBACK
CAUTION
: RISK OF ELECTRIC SHOCKMore than one disconnect switch may be requiredto de-energize the equipment before servicing.
/TSTAT
M4-LHS
HYBRID CONTROL
SYSTEM
A
B
C
D
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
17
18
20
19
21
24
23
29
25
27
26
28
32
30
31
T
T
O
O
RS-485
+
+
mA
VLT
-
+
+
mA
GND
VLT
+
+
mA
22
-
GND
VLT
+
mA
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
CUR / VLTBCUR / VLTCCUR / VLT
D
PROVE
/DHW
SHUTDOWN
/SETBACK
/TSTAT
M4-LHS
HYBRID CONTROL
RUNPROGRAM
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
29
25
27
26
28
32
30
31
T
T
O
O
RS-485
TEMP
OUTDOOR
O
O
TEMP
SYSTEM
EXTENSION
MODULE
PROVE
/DHW
SHUTDOWN
/SETBACK
/TSTAT
HYBRID CONTROL
• When wiring Condensing and Non-Condensing boilers make sure that the Condensing boilers use the rst
stages and the Non-Condensing boilers use the following stages. That is, if the installation had two Condensing
Modulating boilers and two Non-Condensing Staging On/Off boilers, Stage A and B must be used by the
Condensing boilers while Stage C and D must be used by the Non-Condensing boilers.
Wiring Boiler Activation or On/Off Staging Boilers
(A Terminals 5, 6), (B Terminals 7, 8), ...
• Each boiler output has a Normally Open (N.O.) dry-contact relay. They do not source any power.
• Wire the N.O. relay contacts in series with the unit’s limit circuit.
• Note that some modulating boilers may not require the use of these outputs.
A
SYS
5
3
4
Boiler
Boiler Enable
Output
B
678
Wiring Multi-Stage Boilers
(For Staging Boiler Types Only) See Page 19
• Each stage on a multi-stage boiler must use one of the N.O. relays.
• Note that on the display of the M4-LHS each multi-stage boiler will
OD=55oF SYS=142
<<AB>> CD
HI LOW
consist of a multiple letters.
• Each stage output has one Normally Open (N.O.) relay contact that
does not source any power.
STAGE ◄► MENU
Multi-Stage Boiler
WARNING
Class 1 voltages must enter the enclosure through a different opening from any Class 2 voltage wiring.
Wiring to Modulating Boilers
The M4-LHS can modulate any combination of current or voltage boiler signals. See "Modulating Output Type" on
page 23. Some modulating boilers may require the use of the stage output relays in addition to the modulating output.
WARNING
The Modulating Output Type must be set to match the boiler modulating
signal prior to wiring the boiler signal to avoid control or equipment damage.
Wiring the 4-20mA Modulating Boilers
(A Terminals 13, 14), (B Terminals 16, 17),...
• The M4-LHS can operate up to four 4-20 mA modulating motors.
• The Extension can operate up to six 4-20 mA modulating motors.
• The M4-LHS and the Extension sources excitation voltage for the
4-20mA signal.
• Wire the (-) from the boiler modulating motor to the (GND) terminal
on the M4-LHS. That is for boiler A, the modulating (GND) terminal
will be 13.
• Wire the (+) from the boiler modulating motor to the (mA+) terminal
on the M4-LHS. That is for boiler A, the modulating (mA+) terminal
will be 14.
OD=55oF SYS=142
<A> B
80% 50%
STAGE ◄► MENU
Modulating Boiler (Modulating
Boiler Type)
D
o
F
C
8
9
10
11
12
Low
High
2-Stage Boiler
o
F
A
CUR / VLT
mA
VLT
GND
-
+
+
15
13
14
4-20mA
-
Boiler 4-20mA
Modulation Output
Burner
Motor
+
GND
-
16
Wiring Voltage Modulating Boilers
(A Terminals 13, 15), (B Terminals 16, 18),...
• The M4-LHS can operate up to four 0-10V modulating motors.
• The Extension can operate up to six 0-10V modulating motors.
• Wire the (GND) from the boiler modulating motor to the (GND) terminal on the M4-LHS. For boiler D, the
modulating (GND) terminal is be 22.
• Wire the (VLT+) from the boiler modulating motor to the (VLT+)terminal on the M4-LHS. For boiler D, the
modulating (VLT+) terminal is be 23.
HT# 059295-00 A
14
M4-LHS Installation and Operation Manual
C
D
CUR / VLT
mA
mA
mA
VLT
VLT
GND
-
+
+
+
+
+
20
GND
23
21
24
22
Voltage
Burner
Motor
Boiler Voltage
Modulation Output
V+
Connecting to the Extensions and 4-20mA EMS Interface
SYSTEM
A
B
C
D
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
HYBRID CONTROL
RUNPROGRAM
ALERT
To set the Extension to a specific letter, remove the wiring cover and switch the Ext A/Ext B to the
desired letter. DO NOT set both extensions to the same letter to avoid errors.
• The M4-LHS is equipped with a RJ45 socket and a RJ45 to RJ11 Adaptor to connect to extension panels and X-SIG 4-20mA EMS
Interfaces. The Extension is equipped with two RJ11 sockets. It comes packaged with a RJ11 cable to connect to M4-LHS and an
additional Extension. Use the RJ45 to RJ11 Adaptor on the M4-LHS.
• The order in which the control, the extensions, and the interface are wired is not observed.
• Set each Extension to a different letter (EXT-A or EXT-B). The M4-LHS assigns the stage letters based on the extension letter
selected.
• Extension-A operates stages (E - J) and all the LEDs are Green. However, Extension-B operates stages (K - P) and all the LEDs
are Red. .
• Congure the Modulating and Sequencing Output Types after connecting the Extension panels to be able to congure their outputs.
See "Boiler Type" on page 19
• Use the 6-wire RJ11 cable supplied with the extension for proper operation.
M4-LHS
M4-LHS
SYSTEM
OUTPUT RATINGS:
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
1A PILOT DUTY, 15ATOTAL
FOR ALL CIRCUITS
FOR ALL CIRCUITS
INPUT RATINGS:
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
CLASS 1 WIRE ONLY.
ENCLOSEDENERGY
MANAGEMENT
EQUIPMENT
CAUTION: RISK OF ELECTRIC SHOCK
CAUTION: RISK OF ELECTRIC SHOCK
LISTED
More than one disconnect switch may be required
More than one disconnect switch may be required
99RA
to de-energize the equipment before servicing.
to de-energize the equipment before servicing.
D
C
B
A
SYS
PWR
SYS
PWR
L
N
L
N
3
1
2
3
1
2
D
C
B
A
5
8
6
7
9
10
4
11
12
5
6
7
9
8
10
4
11
12
SYSTEM
A
A
B
B
C
C
D
D
B
A
A
B
CUR / VLT
CUR / VLT
CUR / VLT
CUR / VLT
CUR / VLT
CUR / VLT
mA
VLT
mA
VLT
GND
GND
GND
mA
mA
VLT
GND
GND
GND
VLT
-
-
-
-
-
-
+
+
+
+
+
+
+
+
19
15
13
18
16
14
17
19
15
13
18
16
14
17
4-20 mA EMS
4-20mA INPUT
SignalGND
+
2
1
3
EMS/BMS
Temperature
Set PointInput
EMS/BMS Sources
Excitation Voltage
CONDENSING AND NON-CONDENSING
Full Modulation Sequencing Control
o
F
SYS=145oF
OD=35
<<A>> B
100% 50%
STAGE MENU
DO NOTAPPLYANY VOLTAGE
DO NOT APPLY ANY VOLTAGE
RUNPROGRAM
RUNPROGRAM
20
20
C
D
D
C
CUR / VLT
CUR / VLT
mA
mA
VLT
mA
VLT
GND
VLT
mA
mA
mA
GND
VLT
-
-
+
+
+
+
+
+
+
+
+
+
23
22
24
21
23
21
22
24
RJ45 to RJ11
Adaptor
TO INPUTTERMINALS
TO INPUT TERMINALS
SYSTEM
OUTDOOR
SYSTEM
OUTDOOR
TEMP
TEMP
TEMP
TEMP
T
T
O
T
T
O
26
25
27
26
25
27
X SIG
RS485
EXTENSION
CONNECTORS
(-)
(+)
O
O
28
28
PROVE
PROVE
/DHW
/DHW
O
O
30
29
30
29
RJ11
SHUTDOWN
SHUTDOWN/SETBACK
/SETBACK
31
31
M4-Extension A
M4-Ext
FULL MODULATION SEQUENCING EXTENSION
K
F
E
M
H
G
O
J
I
Power
Comm
EXTENSION
EXTENSION
/TSTAT
MODULE
MODULE
RS-485
O
RS-485
O
32
32
PWR
L N
1 2
KMOLNP
E
3 4F5 6G7 8H9 10I11 12
J
13114
Ext A
KMLN
E F G H
CUR / VLT
VLTmA
GND
1716
15
L
N
P
CAUTION:
More than one disconnect switch may be required
to de-energize the equipment before servicing.
Ext B
CUR / VLT
CUR / VLT
GND
VLTmAGND
VLTmAGND
GND
21
201916
232219
18
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz, 12VA MAX
Use Copper Conductors Only.
Risk of Electric Shock.
O P
I J
CUR / VLT
CUR / VLT
VLTmAGND
VLTmA
GND
GND
262522
2928
27
24
CUR / VLT
GND
30
EXTENSION
MODULE
VLTmAGND
RS-485
323116
RJ11
Each Extension Panel or 4-20mA EMS
Interface comes with Connection Cable.
M4-Extension B
M4-Ext
PWR
L N
1 2
KMOLNP
E
3 4F5 6G7 8H9 10I11 12
FULL MODULATION SEQUENCING EXTENSION
K
F
E
M
H
G
O
J
I
Power
Comm
Ext A
KMLN
E F G H
J
CUR / VLT
VLTmA
GND
1716
15
13 14
L
N
P
CAUTION:
More than one disconnect switch may be required
to de-energize the equipment before servicing.
Ext B
CUR / VLT
CUR / VLT
GND
VLTmAGND
VLTmAGND
GND
21
201916
232219
18
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz, 12VA MAX
Use Copper Conductors Only.
Risk of Electric Shock.
O P
I J
CUR / VLT
CUR / VLT
VLTmAGND
VLTmA
GND
GND
262522
2928
27
24
CUR / VLT
GND
30
EXTENSION
MODULE
VLTmAGND
RS-485
323116
RJ11
M4-LHS Installation and Operation Manual
HT# 059295-00 A
15
Connecting to BACnet Interface Module
• The M4-LHS can communicate to BACnet MSTP networks when used the X-BAC BACnet Interface Module (CA009100). The
module must be purchased separately.
• The BACnet Interface Module comes with an RJ45 cable.
• Both the M4-LHS and the BACnet Interface Module are equipped with a RJ45 socket (RS485) to connect to communicate to each
other.
• The Interface BACnet Module must be wired to the BACnet MSTP network using the RS485 terminals A, GND, and B.
• If both an extension panel and the BACnet Interface Module are to be used, connect the RJ11 socket on the BACnet Interface
Module to the extension.
• Set the BACnet parameters. See "BACnet MSTP Communication Menu" on page 26.
X-BAC
BACnet Interface Module
PWR
L
N
1
2
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
SYS
A
B
C
5
3
6
4
7
8
9
10
11
D
12
M4-LHS
A
B
C
D
RUNPROGRAM
A
B
CUR / VLT
GND
-
13
14
C
CUR / VLT
CUR / VLT
mA
VLT
GND
mA
VLT
GND
mA
-
-
+
+
+
+
+
15
16
18
19
17
20
HYBRID CONTROL
D
CUR / VLT
VLT
GND
mA
mA
VLT
-
+
+
+
+
23
21
22
24
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OUTDOOR
SYSTEM
PROVE
TEMP
TEMP
/DHW
T
O
T
O
O
25
26
28
29
27
30
SHUTDOWN
/TSTAT
/SETBACK
31
MSTP
A GND B
1 2 3
B (-)
A (+)
EXTENSION
MODULE
RS-485
O
32
Ground
To BACnet
MSTP
PRODUCT
COMM
RJ45 Cable
RS485
RJ45RJ11
RJ45
RJ45 Communication Cable
Extension
M4Ext
PWR
L N
1 2
KMOLNP
E
3 4F5 6G7 8H9 10I11 12
FULL MODULATION SEQUENCING EXTENSION
K
E
M
G
O
I
Comm
J
13 14
L
F
N
H
J
P
Power
Ext A
KMLN
EFGH
CUR / VLT
CUR / VLT
VLTmA
GND
GND
1716
15
18
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz, 12VA MAX
Use Copper Conductors Only.
CAUTION:
Risk of Electric Shock.
More than one disconnect switch may be required
to de-energize the equipment before servicing.
Ext B
CUR / VLT
GND
VLTmAGND
21
201916
IJ
CUR / VLT
CUR / VLT
VLTmAGND
VLTmAGND
GND
GND
232219
262522
27
24
OP
CUR / VLT
VLTmA
GND
2928
30
VLTmAGND
323116
RJ11
ACTIVATE THE BATTERY
• The battery enables to control to maintain the clock time.
• Unscrew and remove the Enclosure Display Module to reveal the back of the control
CPU Board.
• Remove the plastic strap that covers the battery. The battery holder contacts should be
touching the battery. The control has a coin Lithium battery (CR2032) that is used to
maintain the control's time during power outages. This battery can maintain the clock for
up to a total of 100 days.
EXTENSION
MODULE
RS-485
RJ11 Extension Cable
Battery
ALERT
Do not install the battery unless you plan to keep the control continuously powered. If the
control has no power, the battery will lose its charge in 100 days.
HT# 059295-00 A
16
M4-LHS Installation and Operation Manual
HYBRID STARTUP MENU
-------- SETTINGS ----
Season Winter
System Target 140
<System Settings>
<Maintenance>
<System Startup>
BACK ▲▼ SELECT
-EMS 20ma SETPOINT-
220
F
o
[ ]
BACK ▲▼ SAVE
--- SWITCH DELAY ---
0.5Hour
[ ]
BACK ▲▼ SAVE
Page 21
HEAVY LOAD
-SEQUENCE #2 GROUP-
No
Yes
BACK ▲▼ SAVE
Page 22
CONDENSING
- MODULATING MODE -
Normal
Parallel
BACK ▲▼ SAVE
Page 21
NON-CONDENSING
---- BOILER TYPE ----
Modulating
Staging
BACK ▲▼ SAVE
NON-CONDENSING
-- BOILER NUMBER --
1
[
]
BACK ▲▼ SAVE
Page 24
- SETBCK/SHUTDOWN -
Shutdown/Disable
Tstat/Enable
Setback
BACK ▲▼ SAVE
Shutdown
Page 25
--- BOOST MODE ---
30 Minutes
Disable
BACK ▲▼ SAVE
M4-LHS Installation and Operation Manual
or Tstat
o
F
Page 20Page 21
Page 21
Page 24
Page 25
Setback
-- ARE YOU SURE? --
No
Yes
BACK ▲▼ SAVE
-EMS 4ma SETPOINT -
o
70
F
[ ]
BACK ▲▼ SAVE
--- SWITCH DIFF ---
o
10
F
[ ]
BACK ▲▼ SAVE
CONDENSING
---- BOILER TYPE ----
Modulating
Staging
BACK ▲▼ SAVE
CONDENSING
-- OUTPUT B TYPE --
4-20mA
0-10volt
0-5volt
2-10volt
1-5volt
BACK ▲▼ SAVE
NON-CONDENSING
-- OUTPUT C TYPE --
4-20mA
0-10volt
0-5volt
2-10volt
1-5volt
BACK ▲▼ SAVE
- DHW SETPOINT -
180
F
o
[ ]
BACK ▲▼ SAVE
--- SENSOR FAULT ---
All Off
All On
BACK ▲▼ SAVE
Page 19
--- BOILER TYPE ---
Modulation
Hybrid
Yes
BACK ▲▼ SAVE
Page 19Page 20
--- SENSOR TYPE ---
Reset oF
Reset
o
C
4-20mA EMS
4-20mA EMS
BACK ▲▼ SAVE
Reset
Page 20
- SWITCH SETPOINT -
o
150
[ ]
BACK ▲▼ SAVE
Page 21
CONDENSING
-- BOILER NUMBER --
2
[ ]
BACK ▲▼ SAVE
Page 23
-- OUTPUT A TYPE --
4-20mA
0-10volt
0-5volt
2-10volt
1-5volt
BACK ▲▼ SAVE
Page 22
- MODULATING MODE -
Normal
Parallel
BACK ▲▼ SAVE
Page 24
PROVE/DHW SHARING
Prove
DHW Priority
DHW No Priority
No Priority (Summer)
BACK ▲▼ SAVE
All DHW Options
Page 26
--- BACNET MODE ---
Disable
Enable
BACK ▲▼ SAVE
Modulating
CONDENSING
NON-CONDENSING
F
HT# 059295-00 A
17
MODULATING STARTUP MENU
Page 19
-------- SETTINGS ----
Season Winter
System Target 140
o
F
<System Settings>
<Maintenance>
<System Startup>
BACK ▲▼ SELECT
Page 20
-EMS 4ma SETPOINT -
o
70
F
[ ]
BACK ▲▼ SAVE
-EMS 20ma SETPOINT-
220
F
o
[ ]
BACK ▲▼ SAVE
ALERT
To be able to change the M4-LHS
settings the Program/Run Switch must
be set to Program. The switch is located
under the Enclosure Wiring Cover for
security. The Enclosure Wiring Cover
can be secured using a lock.
-- ARE YOU SURE? --
No
Yes
Yes
BACK ▲▼ SAVE
- EMS INPUT MODE -
Disable
Enable
Enable
BACK ▲▼ SAVE
Disable
Page 23Page 23
Set Point
-- BOILER NUMBER --
2
[ ]
BACK ▲▼ SAVE
Page 24
PROVE/DHW SHARING
Prove
DHW Priority
DHW No Priority
No Priority (Summer)
BACK ▲▼ SAVE
All DHW
Options
Page 24
- DHW SETPOINT -
180
[ ]
BACK ▲▼ SAVE
o
F
--- BOILER TYPE ---
Modulation
Hybrid
BACK ▲▼ SAVE
Page 19
-- SENSOR TYPE --
Reset oF
Reset
o
C
Set Point oF
Set Point oC
BACK ▲▼ SAVE
OUTPUT A TYPE --
4-20mA
0-10volt
0-5volt
2-10volt
1-5volt
BACK ▲▼ SAVE
Page 22
- MODULATING MODE -
Normal
Parallel
BACK ▲▼ SAVE
Page 25
- SETBCK/SHUTDOWN -
Shutdown/Disable
Tstat/Enable
Setback
BACK ▲▼ SAVE
Shutdown
Setback
Page 25
--- SENSOR FAULT ---
All Off
All On
BACK ▲▼ SAVE
Page 26
Page 25
--- BOOST MODE ---
30 Minutes
Disable
BACK ▲▼ SAVE
or Tstat
--- BACNET MODE ---
Disable
Enable
BACK ▲▼ SAVE
HT# 059295-00 A
18
M4-LHS Installation and Operation Manual
STARTUP SETTINGS
SYSTEM
A
B
C
D
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
HYBRID CONTROL
Program Change Switch Setting
To be able to change the M4-LHS settings the Program/Run Switch must be set to Program.
The switch is located under the Enclosure Wiring Cover for security.
Startup Sequence
Button: MENU/<System Startup>
• When powered, the M4-LHS performs a self diagnostics-test.
• On the rst power up, the System Startup screen will appear after the initialization is
complete. If it doesn’t, the M4-LHS has already been congured.
• The System Startup menu sets the main parameters that relate to the heating application.
These settings must be set by the installer.
Boiler Type
Modulation,HybridDefault:Modulation
Button: MENU/<System Startup>/..../Boiler Type
• The same Laars control can operate modulating boilers or a combination of both types.
• The Modulation option will operate a variety of modulating boiler signals.
• The Hybrid option will sequence two groups of boilers, condensing and non-condensing.
Each group could be of a different boiler type (Modulation or Staging). See "Hybrid Logic
Overview" on page 3. Each Multi-Stage boiler will use a single output relay for each stage.
• If BACnet is to be used, each of the Boiler Type modes will have a different set of BACnet
variables. See "Hybrid - Outdoor Reset - BACnet Variable list" on page 44.
(Set Point Options are Not Available with Hybrid Boiler Type)
Button: MENU/<System Startup>/..../Sensor Type
• If Reset °F is selected, all temperatures and settings will be displayed in degrees Fahrenheit
and the control will use Reset Ratios to adjust the system set point.
• If Reset °C is selected, all temperatures and settings will be displayed in degrees Celsius and
the control will use Reset Ratios to adjust the system set point.
• If Set Point °F is selected, all temperatures and settings will be displayed in degrees
Fahrenheit and the control will have an adjustable system set point.
• If Set Point °F is selected, all temperatures and settings will be displayed in degrees Celsius
and the control will have an adjustable system set point.
• The 4-20mA EMS option is only available to the Hybrid Boiler Type option. To use
4-20mA EMS with Modulating Boiler Type, select one of the Set Point options and the EMS
Input Mode menu will follow to offer the 4-20mA EMS option.
• The use of the 4-20mA EMS option requires the purchase of the 4-20mA EMS Interface. It
gives the M4-LHS the capability of accepting a remote 4-20mA signal from a BMS or EMS
system as the target set point.
• If BACnet is to be used, each of the Sensor Type modes will have a different set of BACnet
variables. See "Hybrid - Outdoor Reset - BACnet Variable list" on page 44.
EMS Input Mode
Disable,EnableDefault:Disable
(Available after Set Point with Modulation Boiler Types)
Button: MENU/<System Startup>/..../Boiler Type/Sensor Type / EMS Input Mode
• It allows the M4-LHS to utilize the 4-20mA EMS Interface to accept a remote 4-20mA
signal from a BMS or EMS system as the target set point.
-------- SETTINGS ----
Season Winter
System Target 140
<System Settings>
<Maintenance>
<Histories>
<System Startup>
BACK ▲▼ SELECT
--- BOILER TYPE ---
Modulation
Hybrid
BACK ▲▼ SAVE
Modulating Options
-- SENSOR TYPE --
Reset oF
Reset
Set Point oF
Set Point oC
BACK ▲▼ SAVE
--- SENSOR TYPE ---
Reset oF
Reset
4-20mA EMS
BACK ▲▼ SAVE
- EMS INPUT MODE -
Disable
Enable
BACK ▲▼ SAVE
o
C
Hybrid Options
o
C
RUNPROGRAM
o
F
M4-LHS Installation and Operation Manual
HT# 059295-00 A
19
EMS 4mA and 20mA Set Points
SWITCH MODE = Target Temperature
4mA: can be set from 50°F/ 10°C to 200°F/93°C Default: 70°F/ 21°C
20mA: can be set from 70°F/ 21°C to 220°F/104°C Default: 220°F/ 104°C
Button: MENU/<System Startup>/..../Sensor Type / EMS Input Mode/EMS 4mA Set Point
• With the use of the 4-20mA EMS Interface, the M4-LHS will be able to receive a 4-20mA
signal as a set point from a BMS or an EMS system as the target set point.
• The 4mA and 20mA Set Point menus will follow the selection of the 4-20mA EMS sensor
type option or EMS input Mode.
• There must be at least a 20°F differential between the 4mA and 20mA temperature settings.
• Connect the 4-20mA EMS Control Interface to the M4-LHS RS485 connection.
• Any signal below 2.4mA or above 21.6mA will start an EMS shutdown. The display will
indicate that by displaying the message "Shutdown by EMS".
HYBRID STARTUP SETTINGS
See "Hybrid Logic Overview" on page 3.
System
Temp
140°F
NONCOND
NONCOND
CONDCOND
SYSTEM
o
o
OD=
F SYS=
F
25
145
A
B
<<A>> B
100% 52%
C
D
A
B
A
B
D
SYS
PWR
C
L
T
R
/ V
T
C
U
C
CUR / VL
UR / VL
mAGND
D
mAGND
VL
VLT
GN
T
LN
-
-
+
+
+
+
5
3
9
78
6
10
15
19
13
16
1
4
18
11
2
12
1
17
4
Above the Switch Set Point
DO NOT APPLY ANY VOLTAGE
RUNPROGRAM
TO INPUT TERMINALS
SHUTDOWN
IO
N
N
X
S
TE
E
OUTDOOR
SYSTEM
PROVE
D
C
/TSTAT
/DHW
D
E
UL
MO
TEMP
TEMP
LT
T
R / V
CU
/SETBACK
T
mAGND
mA
V
L
m
L
T
A
V
5
-
48
RS
O
T
O
T
O
O
+
+
+
+
+
26
20
29
28
30
25
23
32
2
1
24
31
2
2
27
Non-Condensing are the Lead Group
Condensing are the Lag Group
-EMS 4ma SETPOINT -
o
70
F
[ ]
BACK ▲▼ SAVE
-EMS 20ma SETPOINT-
220
F
o
[ ]
BACK ▲▼ SAVE
120°F
100°F
NONCOND
NONCOND
Target Switch
Set Point
SYSTEM
o
o
OD=
F SYS=
F
25
145
A
B
<<A>> B
100% 52%
C
D
DO NOT APPLY ANY VOLTAGE
RUNPROGRAM
TO INPUT TERMINALS
TD
H
OWN
U
S
N
EXTENSIO
M
ST
S
E
Y
OUTDOOR
VE
PR
O
C
A
B
D
R
D
SYS
C
A
PW
B
AT
/TS
T
HW
/
D
DU
LE
MO
MP
TE
TEMP
L
L
R / VL
T
T
C
C
T
UR / V
CUR / VLT
CUR / V
U
A
T
CK
/
B
SE
A
mAG
L
m
mAGND
mA
VLT
T
VLT
A
m
V
GND
VLT
ND
GND
RS-4
85
O
T
O
T
O
O
L
N
-
-
-
+
+
+
+
+
+
+
+
+
5
3
1
6
10
13
18
5
26
2
19
20
16
28
789
29
25
30
4
23
1
31
2
3
2
11
12
24
21
17
2
14
27
= 120°F
Below the Switch Set Point
Condensing are the Lead Group
Non-Condensing are the Lag Group
CONDCOND
Switch Set Point
From 0ºF/ -18ºC to 200ºF/ 94ºC Default: 150ºF/ 66ºC
• It is the set point at which the M4-LHS will switch between the Condensing Boiler Group
and Non-Condensing Boiler Group.
• The Condensing Boiler group will be the lead group when the Target Temperature is below
the Target Switch Set Point. However, the Non-Condensing Group will be the lead group
when the Target Temperature is above the Target Switch Set Point.
Switch Differential
Adjustable from 5Fº / 3Cº to 20Fº / 11Cº Default: 10Fº / 6Cº
• The Switch Differential controls the group switching. It allows the Calculated Target to
group over.
• The default value is a good start to avoid oscillation between Condensing and NonCondensing Boiler groups, particularly if no Switch Delay was set. See next setting.
• The Switch Delay is an additional layer of assurance used to reduce the intermittent change
of the lead group.
• To switch the lead group when the temperature is dropping, the sensor temperature must
remain below the Switch Set Point less the Switch Differential for the complete Switch
Delay period before the switching of the lead group.
• I.e., if the Switch Set Point was set to 135ºF, and the Switch Differential was set to 5ºF, then
the Target Temperature must drop below 130ºF for the complete Switch Delay for the lead
group to change from Condensing to Non-Condensing.
• To switch the lead group when the temperature is rising, the Target Temperature must rise
above the Switch Set Point for the complete Switch Delay before the switching of the lead
group could take effect.
--- SWITCH DELAY ---
0.5Hour
[
]
BACK ▲▼ SAVE
Heavy Load Sequence 2nd Group
Yes,NoDefault:No
Button: MENU/<System Startup>/..../Switch Delay/Heavy Load Seq#2 Group
• This option makes the second group of boilers act as a backup in heavy load conditions.
Thus, allowing them to start after all lead group boilers have run at their maximum capacity.
• If the system was designed to operate both groups of boilers in heavy load conditions, then
select Yes.
• Selecting No will only allow the lead group to operate. The secondary group will remain off
even if the system cannot reach the desired set point.
Condensing and Non-Condensing Boiler Type
Modulating,StagingDefault:Modulating
Button: MENU/<System Startup>/..../Heavy Load Seq#2 Group/Condensing Boiler Type
• Select the appropriate boiler type from the list. Each of the types will be followed by a
related additional conguration settings to adjust.
Condensing and Non-Condensing Boiler Number
Adjustablefrom1to15Default:1
Button: MENU/<System Startup>/..../Condensing Boiler Type/ Condensing Boiler Number
• Select the number of condensing boilers. These boilers will occupy the rst letters of the
wiring stages on the M4-LHS starting with Stage-A.
• Then, select the number of non-condensing boilers later in the Startup menu. See "HYBRID
Startup Menu" on page 17.
• Note that, each Multi-Stage boiler requires the use of single output stage relay.
Button: MENU/<System Startup>/..../Condensing Boiler Number/Output A Type
• If either of the Condensing or Non-Condensing Boiler groups was set to Modulating as the
Boiler Type, the M4-LHS will offer the capability of controlling a variety of modulating
signals. Each boiler can be congured to have a different modulating signal.
• The modulating output for each boiler can be congured to 4-20mA operation (Current) or
any of the voltage options. Check the boiler to determine its signal requirements.
• When using the Extension, connect it to the M4-LHS prior to conguring the Output Type.
Otherwise, the M4-LHS might not recognize the Extension stages.
Modulating Mode
Normal,ParallelDefault:Normal
Button: MENU/<System Startup>/..../Output A Type/Condensing Modulating Mode
• Some modulating boilers perform better at higher modulation. For these units, it is
advantageous to run one unit at high modulation than several units at lower modulation. If
the units used are of this type, select Normal. This is the recommended setting for boilers
with low turndown ratios.
• Most condensing boilers run more efciently at lower modulation. If it is more energy
efcient to run several units at lower modulation than one at high. In this case select
Parallel. This is typically used on condensing boilers or boilers with high turndown ratios.
• For best Parallel performance, set the Modulation Start % to be equivalent to the lowest
ring rate of the boiler multiplied by 2. That is, if the lowest ring of the boiler was 20%,
set your Modulation Start% to 40%. See "Modulation Start %" on page 40.
• Set the Lag Delay to 0 for better parallel performance. See "Lag Delay" on page 33.
• During low load conditions, some boilers run more efcient when the lower stages are
energized alone than with the higher stages. For these types of boilers select Lo/Lo/Hi/Hi.
Then, the M4-LHS will sequence the lower stages of all boilers set to Auto before
sequencing the higher stages.
• For the rest of the boiler types, the Lo/Hi/Lo/Hi should allow the staging of the lower stage
of the lead boiler followed by the higher stage of the same boiler. Then when more stages
are needed, it will re the lower stage of the lag boiler followed by the higher stages
NON-CONDENSING
-- OUTPUT TYPE --
On/Off
2-Stage
3-Stage
4-Stage
BACK ▲▼ SAVE
NON-CONDENSING
- STAGING MODE -
LO/HI/LO/HI
LO/LO/HI/HI
BACK ▲▼ SAVE
HT# 059295-00 A
22
M4-LHS Installation and Operation Manual
MODULATING BOILER SETTINGS
Boiler Number
Adjustablefrom1to15Default:1
Button: MENU/<System Startup>/Boiler Type/.../Boiler Number
Button: MENU/<System Startup>/..../Boiler Number/Output A Type
• The M4-LHS will offer the capability of controlling a variety of modulating signals.
Each boiler can be congured to have a different modulating signal. Check the boiler to
determine its signal requirements.
• When using the Extension, connect it to the M4-LHS prior to conguring the Output Type.
Otherwise, the M4-LHS might not recognize the Extension stages.
Modulating Mode
Normal,ParallelDefault:Normal
Button: MENU/<System Startup>/..../Output A Type/Modulating Mode
• Some modulating boilers perform better at higher modulation. For these units, it is
advantageous to run one unit at high modulation than several units at lower modulation. If
the units used are of this type, select Normal. This is the recommended setting for typical
steel and cast iron boilers or boilers with low turndown ratios.
• There are many condensing boilers that run more efciently at lower modulation. If it
is more energy efcient to run several units at lower modulation than one at high, select
Parallel. This is typically used on condensing boilers or boilers with high turndown ratios.
• For best Parallel performance, set the Modulation Start % to be equivalent to the lowest
ring rate of the boiler multiplied by 2. That is, if the lowest ring of the boiler was 20%,
set your Modulation Start% to 40%. See "Modulation Start %" on page 40.
• Set the Lag Delay to 0 for better parallel performance. See "Lag Delay" on page 33.
• This setting determines the functionality of input terminals 29 and 30.
• When Prove is selected, the M4-LHS will not start any boiler unless the Prove terminals are
shorted/closed. However, it will allow the System relay to operate normally.
• There are three DHW Priority options. In all the options, a DHW call will raise the
calculated water temperature to the DHW Set Point (See next setting).
• The Domestic Hot Water Priority option de-energizes the System relay during domestic hot
water calls for a period of one hour. If after the priority period the DHW call did not expire,
the System relay will energize providing heat to the building and the temperature target will
remain at the DHW Set Point. After the DHW call ends, the set point will drop to satisfy the
reset ratio or set point.
• Domestic Hot Water No Priority option allows the System relay to remain energized during
a domestic hot water call (aquastat call on terminals 29 and 30). However, in Summer,
Shutdown, No Tstat call for heat, or when the outdoor temperature is above Outdoor Cutoff,
a DHW call will energize the System relay. After the DHW call terminates, the System relay
will continue to run for the System Run-On period before turning off.
• Domestic Hot Water No Priority (Summer) behaves the same as the DHW No Priority.
The only difference is that in Summer, Shutdown, No Tstat call for heat, or when outdoor
temperature is above Outdoor Cutoff, a DHW call WILL NOT energize the System relay
except for the Run-On delay after the DHW call ends.
• This menu determines the functionality of terminals 31 and 32.
• The M4-LHS has two levels of heat, a Normal/Day and a Setback/Night. The Normal/Day
is good for when buildings are occupied and people are active. The Setback/Night holds a
lower system temperature for night periods or when buildings are unoccupied.
• When Shutdown or Tstat is selected, the Day/Night Schedules will be available in the
operating menu. See next settings. Terminals 31 and 32 will function as a Shutdown (Turn
off boilers when shorted) or as a Tstat (Turn off boilers when opened). However, a call for
indirect DHW will bring the boilers on.
• When Setback is selected, the External Signal option will switch the M4-LHS to Setback
mode when terminals 31 and 32 are shorted. This allows an external device or control to
provide the setback signal. No scheduling or boost menu options will be available with
Setback.
- SETBCK/SHUTDOWN -
Shutdown/Disable
Tstat/Enable
Setback
BACK ▲▼ SAVE
HT# 059295-00 A
24
M4-LHS Installation and Operation Manual
Boost Mode
(Not Available in Setback Mode)
30Minutes,DisabledDefault:Disable
Button: MENU/<System Startup>/..../Boost Mode
• The morning Boost is designed to return the building to comfortable ambient temperatures
after the cooler Night (Setback) period. The control will accomplish this by running
elevated water temperatures (will add Setback setting to calculated water temperature) for
30 minutes before the start of the Day schedule setting. That is, if the normal day set point
at a specic outdoor was 145˚F and the Setback setting was 20˚F, the boost will raise the
system calculated temperature to 165˚F for 30 minutes before the start of the Day Schedule
setting.
• If no Boost is needed, then simply select Disabled from the Boost Menu.
• Boost is only available if Shutdown or Tstat is selected as an option. See previous setting.
--- BOOST MODE ---
30 Minutes
Disable
BACK ▲▼ SAVE
Sensor Fault
AllOff,AllOnDefault:AllOn
Button: MENU/<System Startup>/..../Sensor Fault
• The Sensor Fault will determine the operating status of all output stages that has their Mode
set to Auto when a sensor reads Short or Open.
• When All-Off is selected, the control will turn all boilers Off when the System sensor reads
Short or Open. However, when the Outdoor sensor reads Short or Open, the control will try
to maintain the Minimum Water Temperature.
• When All-On is selected and the Boiler Type was set to other than Hybrid, the control will
turn all boilers On to a 100% when the System sensor reads Short or Open and the outdoor
temperature is below Outdoor Cutoff. However, when the Outdoor sensor reads Short or
Open, the control will try to maintain the Maximum Water Temperature.
• When All-On is selected and the Boiler Type was set to Hybrid, the control will turn all
Non-Condensing boilers On to full re when the System sensor reads Short or Open and the
outdoor temperature is below Outdoor Cutoff. During that time all Condensing boilers will
turn Off. When the Outdoor sensor reads Short or Open, the control will try to maintain the
Maximum Water Temperature.
and adjustments to match the new
SETTING THE CONTROL TO FACTORY DEFAULTS
To Reset the M4-LHS control to its original factory defaults, power down the control.
Hold down the two right most buttons while powering the control back up until the
TOTAL CLEAR STARTED screen appears. The Display will direct you to the Startup
menu to program the control after the defaults are loaded.
--- SENSOR FAULT ---
All Off
All On
BACK ▲▼ SAVE
ALERT
A good practice after performing
any Startup menu modification
is to check all operating settings
settings.
TOTAL CLEAR STARTED
Release buttons
and
Please Wait
NOTE: When resetting the control to original factory defaults all control settings will be
overwritten and will no longer exist.
ALERT
Do not turn off power to control until all Startup settings have been made. Otherwise, the next
power-up will be set to many Startup factory settings that may not fit your application.
M4-LHS Installation and Operation Manual
HT# 059295-00 A
25
BACNET MSTP COMMUNICATION MENU
-------- SETTINGS ----
Season Winter
System Target 140
<System Settings>
<Maintenance>
<System Startup>
BACK ▲▼ SELECT
---- BACNET ID ----
o
F
477000
[ ]
BACK ▲▼ SAVE
When using the M4-LHS in a BACnet MS/TP network, the use of BACnet Interface Module is
required. In addition, each of the Boiler Type and Sensor Type Startup menu option will offer
a different list of BACnet variables. See "Boiler Type" on page 19. See "Sensor Type" on page
19. Also, see "Hybrid - Outdoor Reset - BACnet Variable list" on page 44
• This menu option enables or disables the BACnet MSTP capability. When enabled,
additional BACnet settings shall be available for further customizing.
• Note that if this option was enabled while no BACnet communication is present, the BAcnet
error message will supersede other messages. See "Display Messages" on page 38.
• Each device on the MS/TP network must have a unique address.
• This is the MS/TP address on a RS485 network. Its MS/TP range is 1 though 127.
• The MS/TP address must be provided by the Network Administrator.
BACnet ID
1to4,000,000Default:477,000
Button: MENU/<System Startup>/.... / MSTP Address / BACnet ID
• The BACnet ID is a unique 32 bit number that identies the control within the BACnet
network. No two ID shall be the same even if dealing across networks.
• It must be provided by the BACnet Network Administrator.
- BACNET BAUDRATE -
9600
19200
38400
BACK ▲▼ SAVE
----MS/TP ADDRESS----
64
[ ]
BACK ▲▼ SAVE
---- BACNET ID ----
477000
[ ]
BACK ▲▼ SAVE
HT# 059295-00 A
26
M4-LHS Installation and Operation Manual
OPERATING SETTINGS
SYSTEM
A
B
C
D
DO NOTAPPLYANY VOLTAGE
TO INPUTTERMINALS
HYBRID CONTROL
Outdoor Temperature
WaterTemperature
70405060
130
120
110
100
Outdoor Temperature
WaterTemperature
70405060
110
100
90
80
Outdoor Temperature
Water Temperature
70405060
150
140
130
120
1:4
With a 0° Offset, theReset curves begin at 100° Water Temperature.
With a -20° Offset, theReset curves begin at80° Water Temperature.
With a +20° Offset, theReset curves begin at120° Water Temperature.
1:4
1:41:1
1:1
1:1
4:1
4:1
4:1
90
100
+20 Offset
-20 Offset
Program Change Switch Setting
To be able to change the M4-LHS settings, the Program/Run Switch must be set to Program.
The switch is located under the Enclosure Wiring Cover for security.
Season
Winter,SummerDefault:Winter
Button: MENU/Season
• The M4-LHS will turn all boiler relays off when it is in Summer setting. However, an
indirect DHW call will bring boilers back on when needed. The Message Display Line will
display Summer to show the status.
• In Winter, the M4-LHS will activate the System relay whenever the Outdoor Temperature
(OD) falls below the Outdoor Cutoff setting. The Message Display Line will not show any
season information when in Winter.
• When the heating season is over, it is a good practice to switch the M4-LHS to Summer
setting. This will allow the control to sequence the boilers on an indirect DHW call.
Set Point
Adjustable70ºF-250ºFDefault:70ºF
(Not Available for Hybrid Boiler Types)
Button: MENU/Set Point
• The Set point is the temperature value the M4-LHS will use to control the system.
• The M4-LHS will increase, decrease or hold the modulation of the boilers to maintain the
system temperature around the Set point.
• The system can be expected to uctuate around the set point. The amount of uctuation
depends on the modulation settings and stage Settings.
• If the EMS Input Mode was Enabled, the Set Point will be set by the EMS system and will
be available to be read but not changed on the display. See "EMS Input Mode" on page 19.
• The Reset Ratio determines how the System water temperature (SYS) will vary with
Outdoor Temperature (OD). With any of the ratios, the colder it becomes outside, the hotter
the temperature of the system water. See "Outdoor Reset Concept" on page 5.
• With a 1.00 (OD):4.00 (SYS) ratio, the System water temperature (SYS) will increase
rapidly as the outside temperature falls, hitting the maximum of 240°F at 24°F outside
temperature. With a 4.00 (OD):1.00 (SYS) ratio, the System water temperature (SYS) will
increase slowly as the outside temperature falls. Even at -30°F, the system water will only
be 125°F, and at 24°F outside, the system water will be 112°F. Such a low Reset Ratio
might be used with radiant oor heating applications.
• With most baseboard heating applications, a 1.00 (OD):1.00 (SYS) setting is a good place to
start. With a 1.00 (OD):1.00 (SYS) ratio, for every degree the outside temperature falls, the
system water temperature is increased one degree.
• If required:AdjusttheRESETRATIOincoldweather. If the ambient building
temperatures are too low in cold weather, move the ratio to a higher selection. That is,
if 1.00 (OD):1.00 (SYS) was initially selected, change the selection to 1.00 (OD):1.25
(SYS). If the building temperatures are too warm in cold weather, move the ratio to a lower
selection. That is, if 1.00 (OD):1.00 (SYS) was initially selected, change the selection to
1.25 (OD):1.00 (SYS).
M4-LHS Installation and Operation Manual
RUNPROGRAM
----- SEASON -----
Winter
Summer
BACK ▲▼ SAVE
ALERT
DO NOT turn power off to the
M4-LHS when heating season
is over. If you do so, the battery
will run down and will have to
be replaced. Instead, switch to
Summer.
----- SET POINT -----
[
]
BACK ▲▼ SAVE
-- SYSTEM TARGET --
1.00oOD = 4.00oSys
1.00oOD = 3.00oSys
1.00oOD = 2.00oSys
1.00oOD = 1.50oSys
1.00oOD = 1.25oSys
1.25
o
OD = 1.00oSys
o
OD = 1.00oSys
1.00
1.50oOD = 1.00oSys
2.00oOD = 1.00oSys
3.00oOD = 1.00oSys
4.00oOD = 1.00oSys
BACK ▲▼ SAVE
130
120
110
Water Temperature
100
70405060
Reset Ratio
o
0
F
1:41:1
Warmer
Colder
Outdoor Temperature
4:1
27
HT# 059295-00 A
HYBRID OPERATING MENU
OD= 55oF SYS=143
o
<<A>> B
67% 22%
STAGE ◄► MENU
------- SETBACK -------
o
10
F
[ ]
BACK ▲▼ SAVE
--- PURGE DELAY ---
1.0 min
[ ]
BACK ▲▼ SAVE
-- SYSTEM RUN-ON --
10 min
[ ]
BACK ▲▼ SAVE
-- LEAD ROTATION --
Manual
Time
Last-On
BACK ▲▼ SAVE
-------- SETTINGS ----
Season Winter
F
System Target 140
<System Settings>
o
F
<Maintenance>
----- SEASON -----
Winter
Summer
BACK ▲▼ SAVE
<System Startup>
BACK ▲▼ SELECT
-- SYSTEM TARGET --
1.00oOD = 4.00oSys
1.00oOD = 3.00oSys
1.00oOD = 2.00oSys
1.00oOD = 1.50oSys
----- SETTINGS 1 ----
Setback 10oF
Purge Delay 1.0min
System Run-On 10min
Lead Rotation Time
<More Settings>
BACK ▲▼ SELECT
1.00oOD = 1.25oSys
1.25
o
OD = 1.00oSys
o
OD = 1.00oSys
1.00
1.50oOD = 1.00oSys
2.00oOD = 1.00oSys
3.00oOD = 1.00oSys
4.00oOD = 1.00oSys
BACK ▲▼ SAVE
ALERT
To be able to change the M4-LHS
settings the Program/Run Switch must
be set to Program. The switch is located
under the Enclosure Wiring Cover for
security. The Enclosure Wiring Cover
can be secured using a lock.
------- OFFSET ------
o
+0
F
[ ]
BACK ▲▼ SAVE
- OUTDOOR CUTOFF -
o
65
F
[ ]
BACK ▲ ▼ SAVE
MINIMUM WATER TEMP
o
70
F
[ ]
BACK ▲▼ SAVE
-- STANDBY TIME --
10 min
[ ]
BACK ▲▼ SAVE
LAST STAGE HOLD
[ ]
BACK ▲▼ SAVE
--- LEAD STAGES ---
Cond Lead A
Non-Cond Lead C
BACK ▲▼ SAVE
HT# 059295-00 A
28
5
o
F
----- SETTINGS 2 ----
Standby Time 10min
Last Stg Hold 5
o
F
<Lead Stages>
<Staging Settings>
<Mdlating Settings>
<Day/Night Schdule>
BACK ▲▼ SELECT
DAY/NIGHT SCHEDULE
Set Time **:**
Day Schedule 6:00a
Night Schedule 8:00p
BACK ▲▼ SAVE
MAXIMUM WATER TEMP
200
F
o
[]
BACK ▲▼ SAVE
- STAGE SETTINGS -
Reaction Time 2min
Minimum Runtime 2min
BACK ▲▼ SAVE
MODULATION SETTINGS
Gain +0
Lag Delay 0min
Soft-Off Delay 45sec
BACK ▲▼ SAVE
M4-LHS Installation and Operation Manual
MODULATING OPERATING MENU
-------- SETTINGS ----
OD= 55oF SYS=143
o
<A> B
67% 22%
STAGE ◄► MENU
------- SETBACK -------
o
10
F
[ ]
BACK ▲▼ SAVE
F
Season Winter
System Target 140
<System Settings>
<Maintenance>
<System Startup>
BACK ▲▼ SELECT
----- SETTINGS 1 ----
Setback 10oF
Purge Delay 1.0min
System Run-On 10min
Lead Rotation Time
<More Settings>
BACK ▲▼ SELECT
----- SEASON -----
Winter
o
F
Summer
BACK ▲▼ SAVE
Set Point
----- SET POINT -----
o
0
F
[
]
BACK ▲▼ SAVE
- OUTDOOR CUTOFF -
o
65
F
[ ]
BACK ▲▼ SAVE
--- PURGE DELAY ---
1.0 min
[ ]
BACK ▲▼ SAVE
-- SYSTEM RUN-ON --
settings the Program/Run Switch must
be set to Program. The switch is located
under the Enclosure Wiring Cover for
security. The Enclosure Wiring Cover
10 min
[ ]
BACK ▲▼ SAVE
-- LEAD ROTATION --
Manual
Time
Last-On
BACK ▲▼ SAVE
Last Stg Hold 5
<Lead Stages>
<Mdlating Settings>
<Day/Night Schdule>
• The Offset adjust the starting points of the Reset Ratio curve. This means that, regardless
of the Outdoor Temperature (OD) or the Reset Ratio that has been selected, when the
Offset setting is changed, that change is directly added to or subtracted from the calculated
temperature. For example, if the Set Point was 130°F and the Offset was changed from 0F°
to 10F° (an increase of 10F°), then the Set Point temperature would increase to 140°F.
• The Offset setting does not change the ratio selection. What the Offset does is add or
subtract a constant temperature value. See "Outdoor Reset Concept" on page 5.
• If required: AdjusttheWaterOffsetinmildweather. If the ambient building
temperatures are too warm in mild weather, decrease the offset. If the ambient building
temperatures are too cold in mild weather, increase the Water Offset.
• The rule of thumb for baseboard radiation is to change the offset 4°F for every 1°F you wish
to change the building temperature. In radiant heat applications, change the offset 1F° or
2F° for every 1F° you wish to change the building temperature.
• The control will turn heating off if the outside temperature rises above the Outdoor Cutoff.
This setting shall not affect any indirect DHW requirement.
• The Outdoor Cutoff screen will automatically appear after setting the Offset.
• When the outdoor temperature falls to the adjustable Outdoor Cutoff temperature, the
M4-LHS will operate the boilers to hold the calculated temperature.
• When the outdoor temperature rises to the Outdoor Cutoff plus a 2°F differential, the
M4-LHS will turn all boilers off. The System relay will remain energized for the Run-On
delay then de-energize.
• The Outdoor Cutoff can be set from 20°F to 100°F. In addition, it can be set to ON or OFF.
In the ON position, the System Relay will run regardless of the Outdoor Temperature (OD)
and the burner stages will be active to hold the calculated water temperature. (Note: The
lowest water temperature the M4-LHS will circulate is 70°F. If the Outdoor Cutoff is turned
ON and the Season is set to Winter, the M4-LHS will circulate at least 70°F water even in
the hottest of weather.) In the OFF position, the system pump will always be off and all
Button: MENU/System Target/Offset/Outdoor Cutoff/Minimum Water Temp
• The Minimum Water Temperature must be set to the boiler manufacturer’s specication.
The M4-LHS will calculate the Set Point based on the Outdoor Temperature (OD), the Reset
Ratio, and the Offset value. The M4-LHS will control all boilers to hold either the Set Point
temperature, or the Minimum Water Temperature, whichever is higher.
• The Minimum Water Temperature must be at least 20°F lower than the Maximum
Temperature (See next setting).
• The Setback feature can be used to provide the M4-LHS with a lower temperature Set Point
when less load is required.
• The lower Set Point will appear on the main display indicating this condition.
• For example, if the calculated temperature is 180°F and the Setback is 20°F, then when in
Setback or Night Schedule, the M4-LHS will hold a Set Point of 160°F = 180°F- 20°F. See
"Day - Night Schedule" on page 36.
• A typical use for the Setback is to provide less system temperature to a building during
the Night Schedule or on the weekends when people are asleep or when the building is not
occupied, but heat is still needed.
• The amount of Setback selected is subtracted from the Set Point when a Setback Input
Signal is received or the Night Time schedule setting started.
• If Setback is selected as the Shutdown/Tstat/Setback Mode (See "Shutdown/Tstat/Setback
Mode" on page 24.), the Setback will not be activated unless a Short dry-contact signal is
received on terminals (31 and 32).
• If Shutdown or Tstat is selected as the Shutdown/Tstat/Setback Mode (See "Shutdown/Tstat/
Setback Mode" on page 24.), the Setback will be activated only during the Night Schedule.
----- SETTINGS 1 ----
Setback 0oF
Purge Delay 1.0min
System Run-On 0min
Lead Rotation Time
<More Settings>
BACK ▲▼ SELECT
----- SETTINGS 2 ----
Standby Time 10min
Last Stg Hold 0
<Lead Stages>
<Staging Settings>
<Mdlating Settings>
<Day/Night Schdule>
• Many boilers go through a purge cycle before they are brought on line. When the M4-LHS
activates a boiler, it does not start to calculate its output until the Purge Delay is over. This
allows the boiler to fully come online and begin producing.
• The Purge Delay helps prevent short cycling of any newly activated burner. Once the
burner is activated, it MUST run through the entire Purge Delay period.
• The minimum Purge Delay setting MUST be set to the time required by the boiler
manufacturer. Time entry is in 0.1 of a minute (i.e. 1.5 minute will equal 90 seconds.)
• The Message Display Line will display Purge Delay and the remaining time.
System Run-On
Adjustablefrom0minto360minDefault:10min
Button: MENU/<System Settings>/System run-On
• A common use for the System Run-On is to control a system pump in a heating system.
The extra time helps transfer the boiler residual heat to the heating system.
• The System relay will energize whenever the outdoor temperature is below the Outdoor
Cutoff and the Shutdown is Open or the Tstat is closed. When the Outdoor Temperature
rises 2°F above the Outdoor Cutoff or the control is switched to Summer and after the last
burner relay has de-energized, the System relay will remain energized for the System RunOn period.
M4-LHS Installation and Operation Manual
--- PURGE DELAY ---
1.0 min
[ ]
BACK ▲▼ SAVE
ALERT
Set Purge Delay as per boiler
manufacturer recommendation.
-- SYSTEM RUN-ON --
10 min
[ ]
BACK ▲▼ SAVE
HT# 059295-00 A
31
• The System Run-On time should be set based on the size and type of the boilers and
pumps used. In general, when setting the System Run-On consult the boiler and pump
manufacturers for the best setting.
• When the System relay is in the Run-On period, the Message Display Line will indicate that
• The Lead Boiler is the rst boiler brought on when an output is needed.
• The Lead Boiler can be rotated automatically every specied time period, manually, or
based on Last-On. Time rotation is recommended.
• The Lead Group Lead Boiler is shown in bracket layers on the main display. The Lag
Group lead Boiler is shown in a single bracket. See "Boiler Status" on page 38.
• Only boilers which are set to Auto Mode can be Lead. Therefore, not all the boilers may be
available when manually selecting a new Lead Boiler.
Standby Time
Adjustablefrom1minto60minDefault:10min
Button: MENU/<System Settings>/<More Settings>/Standby Time
• Standby boilers are used for backup or extreme load conditions only. A Standby boiler can
never be a Lead Boiler.
• The Standby Time only applies to boilers set to Standby.
• A boiler can be set to be a Standby boiler using the Stage Menu. See "Mode" on page 39.
• A Standby boiler can only be activated after all the boilers in Auto Mode have run at 100%
modulation for the full Standby Time.
• The full Standby Time must always elapse regardless of what happens to the system
temperature. Therefore, shorter Standby Times will result in smoother set point operation in
extreme conditions. On the other hand, longer Standby Times may prevent a Standby boiler
from ring if the other boilers can eventually meet the load, or if the load decreases.
Button: MENU/<System Settings>/<More Settings>/Last Stg Hold
• The Last Stage Hold prevents short cycling of the Lead Stage during low demand periods.
• In these conditions, the system might require less output than the lowest lead Stage. When
the M4-LHS brings on the Lead Stage, the Set Point is quickly exceeded, and the M4-LHS
turns the Lead Stage off.
• To prolong the run time during this type of condition, use the Last Stage Hold setting to let
the system temperature exceed the Set Point by the number of degrees selected.
• For example, with a Set Point of 160°F and a Last Stage Hold setting of 10°F, the Lead
Stage boiler will de-energize after the Set Point exceeds 170°F (160°F + 10°F).
• In many cases, it is better to overshoot slightly than to short cycle a boiler.
• When Soft-Off is set to other than 0 seconds, the Lead Boiler will need to remain at or
exceed the Last Stage Hold for the Soft-Off period before turning off.
• The Gain adjusts the aggressiveness of the modulating PID logic. It controls how much
modulation is changed when the system temperature is different from the Set Point.
• A Gain of 0 is a good starting point for all systems.
• If during normal load conditions, the system temperature tends to oscillate signicantly,
decrease the Gain by two numbers (for example, from 0 to -2). Wait for at least 15 minutes
before evaluating how the change has affected the system.
• If during normal load conditions the system temperature tends to remain consistently below
the Set Point (or consistently above the Set Point), increase the Gain by two numbers (for
example, from 0 to 2). Wait for at least 15 minutes before evaluating how the change has
• The Lag Delay requires the lead stage to remain at 100% modulation for the full period of
the Lag Delay before the lag stage can be activated. For example, if the Lag Delay was
set to 10 minutes, the Lead Stage must remain at 100% modulation for the full ten minutes
before the lag stage could be activated. The Message Display Line will display Lag Delay and the remaining time.
• The Lag Delay is useful in installations where one unit should usually have enough output
to hold the load unless it fails or load conditions become extreme.
• The Lag Delay overrides the Modulation Start % selected for each stage. Regardless of
that setting, the previous stage must reach and stay at 100% before the lag stage can be
activated.
• The full Lag Delay must elapse regardless of what happens to the system temperature.
Therefore, set the Lag Delay to 0 minutes to achieve smooth operation.
• Note that if Parallel was selected as the Modulation Mode (See "Modulating Logic
Overview" on page 4), this value must be set to 0 minutes to avoid having the lead boiler
going to 100% modulation prior to ring the lag boiler.
• The M4-LHS has two levels of heat. The Day (Normal) level is used when a building is
occupied and people are active.
• The Night (Setback) level is used when a building is not occupied, or when people are
sleeping. This setting reduces the calculated temperature by the Setback setting. See
"Setback" on page 31. If the Day calculated water temperature was 150˚F and the Setback
was 20˚F, the Night Schedule will run at (150˚F - 20˚F) = 130˚F.
• If the Boost feature is being used, it uses the Day Schedule as the Boost ending point. See
"Boost Mode" on page 25. That is, if the Day Schedule is set to start at 6:00AM, the Boost
will start 30 minutes prior to the Day setting at 5:30AM. The M4-LHS will then raise
the calculated water temperature by the Setback amount. Using the previous example,
at 5:30AM the M4-LHS will raise the calculated water to 170˚F = (150˚F + 20˚F) until
6:00AM.
DAY/NIGHT SCHEDULE
Set Time **:**
Day Schedule 6:00a
Night Schedule 8:00p
BACK ▲▼ SAVE
-- DAY SCHEDULE --
6:00 Am
BACK ▲▼ SAVE
Set Time
Button: MENU/<System Settings>/<More Settings>/Set Time
• Adjust the time by selecting Set Time from the menu and then scrolling through the hours
then select Save. If the hours are to be set to PM, scroll through the AM hours to reach the
PM hours. Then, scroll through the minutes then select Save.
ALERT
Remember that the battery is the backup for the Time. If no power is supplied to the M4-LHS and
there was no battery or the battery had no power, time values will be lost and will need to be reset.
MAINTENANCE
Button: MENU/<Maintenance>
The Maintenance menu gives access to sensor and modulating output trimming. In addition,
you'll have access to view the Startup conguration settings.
ALERT
To be able to change the M4-LHS settings the Program/Run Switch must be
set to Program. The switch is located under the Enclosure Wiring Cover for
security. The Enclosure Wiring Cover can be secured using a lock.
Button: MENU/<Maintenance>/System Trim
Button: MENU/<Maintenance>/Outdoor Trim
• The Laars thermistor type sensors are very accurate, and normally require no calibration.
Sometimes it may be desirable to make small adjustments to the displayed value for either
the Outdoor Temperature (OD) or the System Temperature (SYS). The Trim setting is used
to adjust the displayed value.
• Do not use the Trim setting to make the Outdoor Temperature sensor match that reported
on the radio or TV. Outdoor Temperature can vary widely over a broadcast range. Only
trim the outdoor sensor based on an accurate thermometer reading taken where the sensor is
located.
----- SET TIME -----
7:35 Pm
BACK ▲▼ SAVE
----- MAINTENANCE ----
System Trim +0oF
Outdoor Trim 0
<Output Trim>
<Configuration>
BACK ▲▼ SAVE
SYSTEM SENSOR TRIM
[ ]
BACK ▲▼ SAVE
OUTDOOR SENSOR TRIM
[ ]
BACK ▲▼ SAVE
+0
+0
o
F
o
F
o
F
RUNPROGRAM
HT# 059295-00 A
36
M4-LHS Installation and Operation Manual
Output Modulation Trim
(Available for modulating boilers only)
Adjustablefrom-1.0to+1.0Default:0.0
Button: MENU/<Maintenance>/Output Trim
• Each of the modulating stages controlled has a separate Output Trim setting.
• Output Trim acts as an adjustment to a stage output percent to match the burner motor.
• After adjusting the Output Trim, test the operation to make sure the results match your
expectation.
ALERT
DO NOT use the Output Trim for a Stage unless it is absolutely necessary. Test
burner operation and modulation output matching after adjusting the Output Trim.
-- STAGE A TRIM ---
Output Trim +0.0
<Prev Stage>
<Next Stage>
BACK ▲▼ SAVE
Conguration
Button: MENU/<Maintenance>/<Conguration>
• This menu option provides a consolidated view of the M4-LHS's Startup and Stage settings.
PROVE
Bst:30, All On
4-20, 4-20,
BAC=Enable, 19200,2
BACK EXIT
DISPLAY
The M4-LHS display layout provides a variety of information that gives an immediate picture of the operation status. The display
shows two boilers at a time. When extensions are present, the two middle buttons (◄ ►) scroll the screen to view additional boilers.
Moreover, all the information displayed can be viewed in brightly or dimly lit rooms.
• The buttons' functionality changes based on the screen and menu level. The buttons' functionality is displayed on a dark
background on the screen bottom line.
• (◄ ►) Horizontal arrows are to scroll through the available stages.
• (▲ ▼) Vertical arrows are to scroll through the menu functions when in menus or to change settings when in a setting screen.
• The Top line displays the Outdoor and System sensor values.
• The second line displays all messages pertaining to the operation or status. See "Display Messages" on the next page.
• The third line will list the boiler stages. Additional stages can be scrolled to using the two middle buttons. The lead boiler letter
will be bracketed. See "Lead Boiler Rotation" on page 32. The lead boiler in the lead group will have two sets of brackets.
• The fourth line lists each boiler modulation or sequencing status. See "Boiler Status" on the next page.
M4-LHS Installation and Operation Manual
HT# 059295-00 A
37
BOILER STATUS
The M4-LHS boiler status gives immediate access to each boiler stages or modulation.
• --- Boiler is off due to no call for heat.
• <<A>> A is the lead boiler in the lead Hybrid group. See "Lead Stages" on page 32.
• <C> C is the lead boiler in the lag Hybrid group or the lead boiler in Modulating Boiler Type. See "Lead Stages" on page 32.
• C/E Extension panel is NOT communicating back to the M4-LHS. See "Connecting to the Extensions and 4-20mA EMS
Interface" on page 15.
• mON All boiler stages are set to ON.
• mOFF All boiler stages are set to OFF.
Display Modulating Boiler Status
• 97% Boiler is modulating at the indicated percentage.
• m95% Boiler Stage Mode is set to Manual Modulation to the specied percent. See "Mode" on page 39.
• h50% Boiler is in post purge for 30 seconds.
DISPLAY MESSAGES
The M4-LHS display layout reserved the second line for message indications. The following is a list of the most common Message
Display Line information:
• Boost To 170˚F The Boost has started 30 minutes before the Day Schedule setting and the Boost temperature is 170˚F.
See "Boost Mode" on page 25.
• DHW Call (180˚F) There is an indirect DHW call. The M4-LHS will raise the system Set Point to the indicated temperature.
DHW increases calculated temperature to the DHW Set Point. See "Indirect Domestic Hot Water Set
Point" on page 24.
• Holding Until 150˚F The Lead boiler is in Last Stage Hold. This example shows that the lead stage will turn off when system
temperature reaches 150˚F. See "Last Stage Hold" on page 32.
• Interface Module Error There is no communication to the BACnet Module Interface while the BACnet Mode is set to Enable.
See "BACnet Mode" on page 26.
• Lag Delay: 123 The lead boiler is at 100% and the remaining purge time to start the lag boiler in seconds is 123. See "Lag
Delay" on page 33.
• Outdoor Cutoff The outdoor temperature is above the Outdoor Cutoff setting. No boilers will be active for heating. See
"Outdoor Cutoff Temperature" on page 30.
• Prove Failure After boilers have run for some time, Prove signal has ended. All boilers set to Auto or Standby will
de-energize. However, the System relay will remain energized. See "Prove/Indirect Domestic Hot Water
(DHW) Priority" on page 24 and "Wiring the Prove" on page 13.
• Purge Delay: 23 A boiler is in purge cycle and the remaining purge time in seconds is 23. See "Purge Delay" on page 31.
• Setback to: 130˚F The Night Schedule or Setback input is active. Current Setback temperature is 130˚F. See "Setback"
on page 31. See "Day - Night Schedule" on page 36.
• Shutdown Active The Shutdown Terminals are Shorted. No boilers will be active. See "Shutdown/Tstat/Setback Mode" on
page 24. Also See "Wiring the Shutdown, Tstat, or Setback" on page 12.
• Summer The control is set to Summer. No heat is active. See "Season" on page 27.
• Switch in: 00:30 The switch from one group to the other will take place after 30 minutes. See "Switch Delay" on page 21.
• System Run-On: 46 The System relay is ON for the System Run-On Delay. This example shows that it will remain in System
Run-On for an additional 46 seconds before turning off. See "System Run-On" on page 31.
• Tstat Call The Tstat Terminals are Shorted. Boilers will be active. See "Shutdown/Tstat/Setback Mode" on page 24.
• Waiting for Prove The System relay is ON and the prove terminals are open before the lead boiler relay can energize. See
"Prove/Indirect Domestic Hot Water (DHW) Priority" on page 24.
• The Ignition % of a boiler is the lowest percent of modulation that boiler can achieve. That
is for the 4-20mA and 0-10VDC if the Ignition % was set to 20%, the 0-10VDC terminals
will output 2VDC. The 4-20mA terminals will output 7.2mA.
• The 1-10V custom boiler types will use the Ignition % when the boiler is activated. In this
case, the Ignition % will be the level at which the control will output 1VDC.
• During the Soft-Off Delay, the boiler will remain at the Ignition % before turning Off.
- IGNITION POINT -
[ ]
BACK ▲▼ SAVE
Modulation Start %
(Modulating Boilers Only)
Adjustablefrom0%to100%Default:75%
Button: STAGE/Mod Start %
• The Modulation Start determines at what modulation percent the previous boiler (lead
boiler) should be for the lag boiler to be activated.
• For example, if the Modulation Start for Boiler B is set to 50%, then when Boiler A reaches
75% modulation (50% Mod Start % + 25% Ignition % = 75%), Boiler B will be brought on.
• When modulation is decreasing, the lag unit will remain on at the Ignition % modulation until the previous boiler reaches 40% of
lag boiler's Modulation Start, or 2% above the Ignition Point, whichever is higher.
• Using the same example, as the load decreases, Boiler B will modulate down to its Ignition %. Boiler A will then modulate down
to 30% (75% x 40%). Only then will Boiler B turn off.
• If the Lag Delay is set to anything other than 0, the lead boiler must reach 100% modulation before the lag boiler is activated.
However, the Modulation Start % should still be set correctly, because it will be valid when modulation is decreasing. "Lag Delay"
on page 33
• Laars suggests that when Parallel is selected as the Modulation Mode to set the Modulation percent equal to or slightly higher
than double the Ignition %. This way, the lag boiler will only start if the load is large enough for two boilers to run at the lowest
modulation. See "Modulating Logic Overview" on page 4.
[ ]
BACK ▲▼ SAVE
STAGE A
25%
STAGE A
MODULATION START
75%
Copy Settings - Boiler A Only
(Modulating Boilers Only)
Button: STAGE/Copy Settings
• If all the active modulating boilers are to be set to the same Ignition % and Modulation %,
they can be set for Boiler A and then copied to the other modulating boilers.
• It is still required to select the Mode for all other boilers as the Mode is NOT copied.
ALERT
The Mode MUST be set for each boiler. The Copy Settings command will not set the
Mode for the remaining boilers. Only Ignition % and Modulation Start % are copied.
HT# 059295-00 A
40
M4-LHS Installation and Operation Manual
-- COPY SETTINGS -From Stage A to
all other stages
BACK COPY
TROUBLESHOOTING
SENSOR INPUTS
Display shows Sensor OPEN or SHORT
When the display shows sensor OPEN, short the control sensor input terminals. The display
should change to read SHORT. This indicates that the sensor wires are not continuous. If the
display does not SHORT, the M4-LHS may be damaged.
When the display shows sensor SHORT, remove the wires from the sensor terminals. The
display should change to read OPEN. In this case, replace the sensor. Otherwise, if the display
does not show OPEN, the M4-LHS may be damaged.
Display shows an Incorrect Temperature
Remove the wires from the sensor terminals. The display should change to read OPEN. If it
does not, the M4-LHS may be damaged. Take an ohm reading across the detached sensor wires.
The ohm reading should correspond to the Temperature Sensor Chart. If it does not, the sensor
may be damaged.
CONTROL OPERATION
No Heat
• Season- Make sure that the Season is set to Winter. See "Season" on page 27 and "Display
Messages" on page 38.
• Prove- Even though, the system relay may be energized, the M4-LHS will not energize and
stage relays unless the Prove is shorted. See "Display Messages" on page 38 and "Wiring the
Prove" on page 13.
• Shutdown- The M4-LHS will deactivate stage outputs when the Shutdown terminals are
shorted. See "Display Messages" on page 38 and "Wiring the Shutdown, Tstat, or Setback" on
page 12.
• Tstat- The M4-LHS will deactivate stage outputs when the Tstat terminals are open. See
"Display Messages" on page 38 and "Wiring the Shutdown, Tstat, or Setback" on page 12.
• SensorFault- When the Sensor Fault is set to All Off in the startup menu, the System sensor
fault (in all Sensor Type modes) or the Outdoor sensor fault (in Reset mode) will de-energize all
stage relays. See "Display Messages" on page 38 and "Sensor Fault" on page 25.
• SystemorOutdoorSensor- If the System or Outdoor sensor reading was higher that the actual
temperature, the M4-LHS might not bring any stage on. Check "Display shows an Incorrect
Temperature" section.
• OutdoorCutoff- If the Outdoor cutoff was set too low, the building might be allowed to
cool more than is desired. A comfortable setting is between 60°F to 65°F. "Outdoor Cutoff
Temperature" on page 30
Too Much Heat
• IndirectDomesticHotWatercall- The M4-LHS will raise the temperature of the system to the
DHW Set Point on a DHW call, connected to terminals 29 and 30. Check to see if there is a call
for DHW and the length of time it lasts.
• ResetRatioandOffset- If excessive heat occurs only in certain weather conditions, adjust the
Reset Ratio and Offset. See "Outdoor Reset Concept" on page 5. If excessive heat occurs year
round, reduce the Offset.
• BoilerModeSettings- The M4-LHS will only controls boilers their mode is set to Auto or
Standby. Check if any boiler stage is set to Manual or On. See "Mode" on page 39.
• ControlSettings- The Last Stage Hold will allow only the Lead boiler to stay on for an
additional number of degrees. If the setting is too high, and only the Lead boiler is on, the
system can over heat. Reduce the Last Stage Hold setting. See"Last Stage Hold" on page 32.
Temperature Sensor Chart
TEMPERATURE
°F°C
OPEN150000
-30-34117720
-20-2982823
-10-2359076
0-1842683
10-1231215
20-723089
25-419939
30-117264
35214985
40413040
45711374
50109944
55138714
60167653
70215941
80274649
90323667
100382914
110432332
120491879
130541524
140601243
150661021
16071842
17077699
18082583
19088489
20093412
21099349
220104297
230110253
240116217
250121187
SHORT100
Value
(in Ohms)
M4-LHS Installation and Operation Manual
HT# 059295-00 A
41
Too Little Heat
• ResetRatioandOffset- If reduced heat occurs only in certain weather conditions, adjust the
Reset Ratio and Offset (See "Outdoor Reset Concept" on page 5). If reduced heat occurs year
round, increase the Offset.
• SetbackandDay/NightSchedule- If reduced heat occurs only during specic hours, check the
Day/Night Schedule and the Setback values. Then, reduce the Setback setting. See "Setback" on
page 31.
• BoilerModeSettings- The M4-LHS will only control boilers their mode is set to Auto or
Standby. Check if any boiler stage is set to Manual, Off, or Standby. See "Mode" on page 39.
Boilers are Short-Cycling
• LagDelay- Increase the Lag Delay only if modulating boilers tend to short-cycle.
• MinimumRuntime- Increase the Minimum Runtime only if staging boilers tend to short-cycle.
• LastStageHold- Increase the Last Stage Hold only if the lead boiler tends to short-cycle.
System is Overshooting or Undershooting
ModulatingBoilers
• Gain- If when using modulating boilers the system is overshooting reduce the Gain. See "Gain"
on page 33.
• Gain- If when using modulating boilers the system is undershooting increase the Gain.
StagingBoilers
• ReactionTime- If when using staging boilers the system is overshooting increase the Reaction
Time. As the stages will be turning on faster than they are affecting the system. If the system
was undershooting for long periods, reduce the Reaction Time. See "Reaction Time" on page 34.
• MinimumRuntime- If when using staging boilers the system is overshooting reduce the
Minimum Run Time. If the system was undershooting, increase the reaction time as it is turning
off stages quicker than needed. See "Minimum Runtime" on page 34.
Segmentation TypeSupportedWindow Size (MS/TP product limited to 1)
Able to transmit segmented messagesNo
Able to receive segmented messagesNo
Device Address Binding
ProductStatic Binding Supported
M4-LHS BACnet ControlNo
Character Sets
ProductCharacter Sets supported
M4-LHS BACnet ControlANSI X3.4
Baud Rates: 9600, 19200, 38400
M4-LHS Installation and Operation Manual
HT# 059295-00 A
47
PIPING AND WIRING DIAGRAMS
HYBRID PIPING DIAGRAM
M4-LHS
HYBRID CONTROL
SYSTEM
A
B
Two Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
120VAC
B
A
SYS
PWR
L
N
5
3
7
8
6
4
1
2
C
D
DO NOT APPLY ANY VOLTAGE
RUNPROGRAM
TO INPUT TERMINALS
A
C
D
CUR / VLT
mA
GND
VLT
-
+
+
10
9
15
13
12
11
14
OUTDOOR
C
B
D
TEMP
CUR / VLT
CUR / VLT
CUR / VLT
ND
T
mA
mA
VLT
G
GND
mA
mA
VLT
VL
GND
T
-
-
-
+
+
+
+
+
+
+
25
23
20
26
18
16
19
24
22
17
21
Outdoor
Sensor
STARTUP SETTINGS
Boiler Type = Hybrid
SHUTDOWN
EXTENSION
STEM
VE
PRO
SY
/TSTAT
MODULE
W
TEMP
/DH
/SETBACK
485
RS-
O
O
O
O
T
29
32
28
30
31
27
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Modulating Mode = Parallel
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
Boiler 1
Condensing
Modulating
Boiler 2
Condensing
Modulating
Boiler 3
Non-Condensing
On/Off
Boiler 4
Non-Condensing
On/Off
System
Sensor
Building Heating Loop
System:
The M4-LHS operates two modulating boilers and two On/Off Boilers. The boilers are piped in Reverse Return on the
primary loop. The System output is controlling the System Pump.
Laars is aware that each installation is unique. Thus, Laars is not responsible for any installation related to any electrical
or plumbing diagram generated by Laars . The provided illustrations are to demonstrate Laars ’s control operating concept
only.
HT# 059295-00 A
48
M4-LHS Installation and Operation Manual
HYBRID WIRING DIAGRAM
M4-LHS
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
SYSTEM
A
B
C
D
HYBRID CONTROL
Two 4-20mA Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
L
N
L
N
System Pump
PWR
L
1
N
2
B
A
SYS
5
3
678
4
Boiler 1
Boiler 2
{
Modulating
Condensing
Group (Boiler 1 & 2)
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
D
C
9
10
11
12
Boiler 3
Boiler 4
{
4 - 20 mA
Staging
Modulating
Signal Outputs
Non-Condensing
Group (Boiler 3 & 4)
M4-LHS
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
mA
VLT
GND
GND
-
-
+
+
+
15
13
16
14
17
Boiler 1
SYSTEM
A
B
C
D
RUNPROGRAM
VLT
GND
-
+
19
18
Boiler 2
D
mA
mA
mA
VLT
VLT
GND
-
+
+
+
+
+
23
20
21
24
22
HYBRID CONTROL
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OUTDOOR
TEMP
T
25
26
O
SYSTEM
TEMP
T
28
27
Shield
O
PROVE
/DHW
29
Shield
O
30
SHUTDOWN
/SETBACK
31
Prove Jumper
System Sensor
Outdoor Sensor
EXTENSION
/TSTAT
MODULE
RS-485
O
32
Do Not remove
STARTUP SETTINGS
Boiler Type = Hybrid
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Output Type = 4-20ma
Condensing Modulating Mode = Parallel
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
Two Voltage Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
VLT
GND
GND
-
-
+
+
15
13
16
14
Boiler 1
Voltage
Modulating
Signal Outputs
L
N
L
N
System Pump
PWR
L
1
N
2
5
3
678
9
Boiler 1
Boiler 2
{
10
11
12
Boiler 3
{
Boiler 4
4
D
C
B
A
SYS
Staging
Modulating
Condensing
Non-Condensing
Group (Boiler 1 & 2)
Group (Boiler 3 & 4)
M4-LHS Installation and Operation Manual
mA
VLT
GND
+
+
19
18
17
Boiler 2
D
mA
mA
VLT
+
+
+
23
24
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OUTDOOR
TEMP
T
25
26
SHUTDOWN
SYSTEM
PROVE
TEMP
/DHW
/SETBACK
T
O
O
O
30
29
31
28
27
EXTENSION
/TSTAT
MODULE
RS-485
O
32
RUNPROGRAM
mA
VLT
GND
-
-
+
+
20
21
22
STARTUP SETTINGS
Boiler Type = Hybrid
Shield
Shield
Prove Jumper
Do Not remove
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Output Type = Any voltage
Condensing Modulating Mode = Parallel
System Sensor
Outdoor Sensor
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
HT# 059295-00 A
49
MODULATING PIPING DIAGRAM
Outdoor
Sensor
Four Modulating Boilers
120VAC
Boiler 1
Condensing
Modulating
C
B
A
SYS
PWR
L
N
5
6
3
789
4
1
2
Boiler 2
Condensing
Modulating
10
D
12
11
M4-LHS
SYSTEM
A
B
C
D
A
B
CUR / VLT
CUR / VLT
CUR / VLT
GND
mA
mA
VLT
GND
VLT
GND
-
-
-
+
+
+
+
15
13
18
16
19
14
17
RUNPROGRAM
C
GND
mA
VLT
+
+
20
22
21
HYBRID CONTROL
DO NOT APPLY ANY VOLTAGE
OUTDOOR
D
CUR / VLT
T
VL
mA
mA
-
+
+
+
23
24
TO INPUT TERMINALS
TEMP
T
O
25
26
SYSTEM
PROVE
/DHW
TEMP
T
O
O
29
30
28
27
DOWN
SHUT
EXTENSION
/TSTAT
MODULE
CK
BA
/SET
RS-485
O
32
31
Boiler 3
Condensing
Modulating
STARTUP SETTINGS
Boiler Type = Modulation
Boiler Number = 4
Boiler 4
Condensing
Modulating
System
Sensor
Building Heating Loop
System:
The M4-LHS operates four modulating boilers. The boilers are piped in Reverse Return on the primary loop. The System
output is controlling the System Pump.
Laars is aware that each installation is unique. Thus, Laars is not responsible for any installation related to any electrical
or plumbing diagram generated by Laars . The provided illustrations are to demonstrate Laars's control operating concept
only.
HT# 059295-00 A
50
M4-LHS Installation and Operation Manual
PIPING AND WIRING DIAGRAMS
HYBRID PIPING DIAGRAM
M4-LHS
HYBRID CONTROL
SYSTEM
A
B
Two Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
120VAC
B
A
SYS
PWR
L
N
5
3
8
6
7
4
1
2
C
D
DO NOT APPLY ANY VOLTAGE
RUNPROGRAM
TO INPUT TERMINALS
A
C
D
CUR / VLT
mA
VLT
GND
-
+
+
9
10
15
13
12
11
14
OUTDOOR
C
D
B
TEMP
CUR / VLT
CUR / VLT
CUR / VLT
GND
mA
mA
VLT
mA
mA
GND
VLT
VLT
GND
T
-
-
-
+
+
+
+
+
+
+
25
23
20
26
18
16
19
24
22
17
21
Outdoor
Sensor
STARTUP SETTINGS
Boiler Type = Hybrid
SHUTDOWN
EXTENSION
SYSTEM
PROVE
/TSTAT
MODULE
TEMP
/DHW
/SETBACK
RS-485
T
O
O
O
O
32
29
30
28
31
27
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Modulating Mode = Parallel
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
Boiler 1
Condensing
Modulating
Boiler 2
Condensing
Modulating
Boiler 3
Non-Condensing
On/Off
Boiler 4
Non-Condensing
On/Off
System
Sensor
Building Heating Loop
System:
The M4-LHS operates two modulating boilers and two On/Off Boilers. The boilers are piped in Reverse Return on the
primary loop. The System output is controlling the System Pump.
Laars is aware that each installation is unique. Thus, Laars is not responsible for any installation related to any electrical
or plumbing diagram generated by Laars . The provided illustrations are to demonstrate Laars ’s control operating concept
only.
HT# 059295-00 A
48
M4-LHS Installation and Operation Manual
HYBRID WIRING DIAGRAM
M4-LHS
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
SYSTEM
A
B
C
D
HYBRID CONTROL
Two 4-20mA Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
L
N
L
N
System Pump
PWR
L
1
N
2
B
A
SYS
5
3
678
4
Boiler 1
Boiler 2
{
Modulating
Condensing
Group (Boiler 1 & 2)
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
D
C
9
10
11
12
Boiler 3
Boiler 4
{
4 - 20 mA
Staging
Modulating
Signal Outputs
Non-Condensing
Group (Boiler 3 & 4)
M4-LHS
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
VLT
GND
GND
-
-
+
+
15
13
16
14
17
Boiler 1
SYSTEM
A
B
C
D
mA
VLT
GND
+
+
19
18
Boiler 2
RUNPROGRAM
D
mA
mA
mA
VLT
GND
-
-
+
+
+
+
23
20
21
22
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
SYSTEM
PROVE
OUTDOOR
TEMP
TEMP
VLT
+
24
/DHW
T
T
O
O
29
25
28
26
27
Shield
Shield
System Sensor
Outdoor Sensor
HYBRID CONTROL
SHUTDOWN
/TSTAT
/SETBACK
O
O
32
30
31
Prove Jumper
Do Not remove
EXTENSION
MODULE
RS-485
STARTUP SETTINGS
Boiler Type = Hybrid
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Output Type = 4-20ma
Condensing Modulating Mode = Parallel
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
Two Voltage Modulating
Condensing Boilers
and Two On/Off NonCondensing Boilers
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
VLT
GND
GND
-
-
+
+
15
13
16
14
Boiler 1
Voltage
Modulating
Signal Outputs
L
N
L
N
System Pump
PWR
L
1
N
2
5
3
678
9
Boiler 1
Boiler 2
{
10
11
12
Boiler 3
Boiler 4
{
4
D
C
B
A
SYS
Staging
Modulating
Condensing
Non-Condensing
Group (Boiler 1 & 2)
Group (Boiler 3 & 4)
M4-LHS Installation and Operation Manual
mA
VLT
+
+
18
17
Boiler 2
D
mA
mA
VLT
+
+
+
23
24
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
OUTDOOR
TEMP
T
25
26
SHUTDOWN
SYSTEM
PROVE
TEMP
/DHW
/SETBACK
T
O
O
O
30
29
31
28
27
EXTENSION
/TSTAT
MODULE
RS-485
O
32
RUNPROGRAM
mA
VLT
GND
GND
-
-
+
+
19
20
21
22
STARTUP SETTINGS
Boiler Type = Hybrid
Shield
Shield
Prove Jumper
Do Not remove
Condensing Boiler Type = Modulating
Condensing Boiler Number = 2
Condensing Output Type = Any voltage
Condensing Modulating Mode = Parallel
System Sensor
Outdoor Sensor
Non-Condensing Boiler Type = Staging
Non-Condensing Output Type = On/Off
Non-Condensing Boiler Number = 2
HT# 059295-00 A
49
MODULATING PIPING DIAGRAM
Outdoor
Sensor
Four Modulating Boilers
120VAC
Boiler 1
Condensing
Modulating
B
A
SYS
PWR
L
N
5
3
8
6
9
7
4
1
2
Boiler 2
Condensing
Modulating
C
10
D
12
11
M4-LHS
SYSTEM
A
B
C
D
A
B
CUR / VLT
CUR / VLT
CUR / VLT
GND
mA
mA
VLT
GND
VLT
GND
-
-
+
+
+
+
15
13
18
16
19
14
17
RUNPROGRAM
C
mA
VLT
-
+
+
20
21
HYBRID CONTROL
D
CUR / VLT
mA
mA
GND
VLT
-
+
+
+
23
24
22
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
SHUTDOWN
EXTENSION
SYSTEM
PROVE
OUTDOOR
/TSTAT
MODULE
TEMP
TEMP
/DHW
/SETBACK
RS-485
T
O
O
T
O
O
32
29
25
30
28
31
26
27
Boiler 3
Non-Condensing
On/Off
STARTUP SETTINGS
Boiler Type = Modulation
Boiler Number = 4
Boiler 4
Non-Condensing
On/Off
System
Sensor
Building Heating Loop
System:
The M4-LHS operates four modulating boilers. The boilers are piped in Reverse Return on the primary loop. The System
output is controlling the System Pump.
Laars is aware that each installation is unique. Thus, Laars is not responsible for any installation related to any electrical
or plumbing diagram generated by Laars . The provided illustrations are to demonstrate Laars's control operating concept
only.
HT# 059295-00 A
50
M4-LHS Installation and Operation Manual
MODULATING WIRING DIAGRAM
L
N
L
N
System Pump
PWR
L
1
N
2
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
B
A
SYS
5
3
678
4
Boiler 1
Boiler 2
4 Modulating
M4-LHS
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
D
C
9
10
11
12
Boiler 3
Boiler 4
boilers
Activation Signal
SYSTEM
A
B
C
D
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
VLT
GND
GND
-
-
+
+
15
13
16
14
17
Boiler 1
4 - 20 mA
Modulating
Signal Outputs
mA
VLT
GND
+
+
19
18
Boiler 2
RUNPROGRAM
mA
-
+
20
Boiler 3
VLT
+
21
D
mA
mA
GND
-
23
22
+
+
Boiler 4
HYBRID CONTROL
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
SYSTEM
PROVE
OUTDOOR
TEMP
TEMP
VLT
+
24
/DHW
T
T
O
O
29
25
28
26
27
Shield
Shield
System Sensor
Outdoor Sensor
SHUTDOWN
/TSTAT
/SETBACK
O
O
32
30
31
Prove Jumper
Do Not remove
EXTENSION
MODULE
RS-485
Four 4-20mA
Modulating Boilers
STARTUP SETTINGS
Boiler Type = Modulation
Output Type = 4-20ma
Boiler Number = 4
M4-LHS
OUTPUT RATINGS:
120VAC, 6A RESISTIVE
1A PILOT DUTY, 15A TOTAL
FOR ALL CIRCUITS
INPUT RATINGS:
115VAC 60Hz , 30VA MAX
USE COPPER WIRE,
CLASS 1 WIRE ONLY.
ENCLOSED
ENERGY
MANAGEMENT
EQUIPMENT
99RA
SYS
PWR
N
L
3
1
4
2
L
N
A
5
678
Boiler 1
B
Boiler 2
CAUTION
: RISK OF ELECTRIC SHOCK
More than one disconnect switch may be required
to de-energize the equipment before servicing.
D
C
9
10
11
12
Boiler 3
Boiler 4
L
N
System Pump
boilers
4 Modulating
Activation Signal
M4-LHS Installation and Operation Manual
SYSTEM
A
B
C
D
A
CUR / VLT
CUR / VLTBCUR / VLTCCUR / VLT
mA
VLT
GND
GND
-
-
+
+
15
13
16
14
Boiler 1
Modulating
Signal Outputs
mA
VLT
GND
+
+
19
18
17
Boiler 2
Voltage
RUNPROGRAM
D
mA
mA
mA
VLT
GND
-
-
+
+
+
+
23
20
21
22
Boiler 3
Boiler 4
HYBRID CONTROL
DO NOT APPLY ANY VOLTAGE
TO INPUT TERMINALS
SYSTEM
PROVE
OUTDOOR
TEMP
TEMP
VLT
+
24
/DHW
T
T
O
O
29
25
28
26
27
Shield
Shield
System Sensor
Outdoor Sensor
SHUTDOWN
/TSTAT
/SETBACK
O
O
32
30
31
Prove Jumper
Do Not remove
EXTENSION
MODULE
RS-485
Four Voltage
Modulating Boilers
STARTUP SETTINGS
Boiler Type = Modulation
Output Type = Any Voltage