Installation Tools ……………………………………
Space Requirements …………………………………
Installation Modes ……………………………………
Installation Procedure ………………………………
Components Delivered with the RRU ……………
Installing the RRU on a Metal Pole ………………..
Installing the RRU on a U-Steel ……………………
Installing the RRU on an Angle Steel ……………
Installing the RRU on Wall …………………………
Installing the RRU Cables …………………………
2
3
4
6
6
7
11
11
12
14
RRU Hardware Installation Checklist ……………
Powering On the RRU ………………………………
Appendix………………………………………………
Change History …………………………………...…
(21mm~21mm) for pole installation
(17mm~17mm) for wall installation
Measuring tape
Installation Options
On a metal pole
On a U-steel
On an angle steel
On a wall
The following figure describes the specificati ons for the metal pole, angle steel, a nd U-steel where the RRU is
installed.
60 mm [2.4 in.] to 114 mm [4.5 in.]
80mm
~
63mm
50 mm [2 in.] to 100 mm [3.9 in.]
30 mm [1.2 in.] to 50 mm [2.0 in.]
RRU
Metal pole
63 mm [2.5 in.] to 75 mm [3 in.]
63 mm [2.5 in.] to 75 mm [3 in.]
Angle steelU-steel
The angle between
the vertical and the
angle steel or U-
Angle steel
or U-steel
≤10°
steel or angle steel
where the RRU is
installed must be
less than or equal
to 10 degree.
The brackets cannot be
combined when the RRUs
are installed on the wall.
z A maximum of two RRUs can be installed on a metal pole with a diameter of 60 mm [2.4 in.] to 75 mm [3 in.] ,
and the installation mode must be standard mode. Three or more RRUs must be installed on a metal pole with
a diameter of 76 mm [3 in.] to 114 mm [4.5 in.] in a centralized way.
z It is recommended that only one RRU be installed on a U-st eel or an angl e st eel .
z When installed on a tower, one RRU can be installed only in standard mode or reverse mode rather than
side-mounted. Two RRUs cannot be installed in back-to-back mode.
3
Dimensions and Installation Clearance
Dimensions of the RRU
a
≥3
b
381 mm [15.0 in.]
Recommended Clearance for a
Single RRU
≥300 mm [11.8 in.]
0
0
m
m
[
1
1
.
8
i
n
.
]
170 mm [6.7 in.]
485 mm [19.1 in.]
Minimum Clearance for a Single
c
RRU
1
0
0
m
m
[3
.9
200 mm [7.9 in.]
i
n
.
]
≥
]
.
n
i
5
.
≥
1
3
[
m
m
0
0
8
≥500 mm [19.7 in.]
≥
Recommended Clearance for
d
Multiple Centralized RRUs
≥300 mm [11.8 in.]
]
.
n
i
7
.
9
1
[
m
m
0
0
5
]
.
n
i
6
.
3
2
[
6
0
0
m
m
[
2
3
.
6
i
n
.
]
e
]
.
n
i
7
.
9
1
[
m
m
0
0
5
≥
≥
8
0
0
m
m
[
3
1
.
5
i
n
m
0
0
3
.
]
m
m
0
0
6
300 mm [11.8 in.]
Minimum Clearance for Multiple
Centralized RRUs
200 mm [7.9 in.]
]
.
n
i
8
.
1
1
[
m
4
0
0
m
m
[1
5
.
7
i
n
.
]
]
.
n
i
8
.
1
1
[
m
m
0
0
3
6
0
0
m
m
[
2
3
.
6
i
n
.
]
≥500 mm [19.7 in.]
300 mm [11.8 in.]
4
Dimensions and Installation Clearance
Recommended Horizontal Spacing for
fg
Two RRUs Installed in Parallel
≥300 mm
[11.8 in.]
≥600 mm
[23.6 in.]
≥600 mm
[23.6 in.]
Recommended Vertical Spacing for
h
Two RRUs Installed in Parallel
Minimum Horizontal Spacing for Two
RRUs Installed in Parallel
100 mm
[3.9 in.]
400 mm
[15.7 in.]
Minimum Vertical Spacing for Two
i
RRUs Installed in Parallel
400 mm
[15.7 in.]
≥300 mm [11.8 in.]
≥500 mm [19.7 in.]
200 mm [7.9 in.]
300 mm [11.8 in.]
≥500 mm [19.7 in.]
300 mm [11.8 in.]
5
Installation Procedure
Start
Prepare the
installation
Install the RRU on a
metal pole
Install the RRU on a
U-steel
Install the RRU
Checking the RRU
Hardware Installation
Power on the RRU
Preparing the Installation
Install the RRU on an
angle steel
cables
End
Install the RRU on a
wall
Auxiliary bracket
Dual-nut bolt
Main bracket
Main and auxiliary brackets for the RRU
6
Cover plate
FrontBack
Attachment plate
Installing the RRU on a Metal Pole
a
Installing a Single RRU on a Metal Pole
1. Install the main bracket.
When installing the
main bracket,
ensure that the
contact piece on
the bracket is fixed.
1200 mm [47.2 in.]~
1600 mm [63 in.]
You may fit one end of the auxiliary bracket on one dual-nut bolt assembly and then the other end on the
other dual-nut bolt assembly during the installation.
2. Use an adjustable wrench to tighten the nut until the fastening torque is 40 N·m [354
lbf•in.]. In this way, the main and auxiliary brackets are secured on the pole.
40 N•m
[354 lbf•in.]
Fasten the two dual-nut bolt assemblies
alternatively. After the brackets are secure,
use a tape to measure the spacing between
the main bracket and the auxiliary bracket at
the two sides and ensure that the spacing is
the same.
3. Install the RRU on the main bracket. When you hear click sound, you can infer that
the RRU is in position.
z The weight-bearing capacity of the RF
ports at the bottom of th e RRU is low. Do
not place the RRU at its bott om.
z During the operation, place the foam
pad or cardboard under the RRU to
prevent any damage to the housing of
the RRU.
7
Installing the RRU on a Metal Pole
Installing Two RRUs Back-To-Back on a Metal Pole
b
1. Install an RRU. For details, see page 7
Installing a Single RRU on a Metal Pole.
3. Reinstall the attachment plate and cover plate on the second RRU by interchanging
their positions.
2. Install the main fixture for another RRU.
4. Install the second RRU on the main bracket.
Ensure that the cabling
cavities of the two RRUs
face the same direction
when installing the RRUs.
M6X16
4.8 N•m
[42.5 lbf•in.]
In reverse mode
In standard mode
8
Cabling cavity
Installing the RRU on a Metal Pole
Installing Multiple RRUs in Centralized Mode
c
1. Install the main fixture and the auxiliary fixture. For details, see page 7
Installing a Single RRU in Ordinary Mode.
2. Relocate the attachment plate.
4. Install the second main fixture.3. Fit the tabs on the attachment plate of the
RRU into the anchor slots on the main fixture.
M6X16
4.8 N•m
[42.5 lbf•in.]
5. Fit the tabs on the attachment plate of
the second RRU into the anchor slots on
the second main fixture.
6. Install the third RRU.
9
Installing the RRU on a Metal Pole
Installing Multiple RRUs in Centralized Mode
c
7. Install the fourth main fixture.
8. Fit the tabs on the attachment plate of
the fourth RRU into the anchor slots on
the fourth main fixture.
9. Four RRUs installed in centralized mode.10. Six RRUs installed in centralized mode.
10
Installing the RRU on a U-Steel
U-steel
Plan view
z The procedure for installing the RRU on a U-steel is the same as t hat for installing the RRU on a metal pole.
z It is recommended that only one RRU be installed on a U-steel.
Installing the RRU on an Angle Steel
Plan view
Angle steel
z The procedure for installing t he RRU o n an a ngl e st eel is th e sam e as tha t f or i nst allin g t h e RRU on a met a l
pole.
z It is recommended that only one RRU be installed on an angle steel.
11
Installing the RRU on a Wall
1. Place the auxiliary bracket at the installation position. Use a level to check that the
auxiliary bracket is placed horizontally. Then, mark the anchor points by using a
marking pen.
≥650 mm
[25.6 in.]
Level
1200 mm [47.2 in.]
to 1600 mm [63.0 in.]
≥650 mm
[25.6 in.]
126.5 mm
[5 in.]
128 mm
[5 in.]
126.5 mm
[5 in.]
RRU
z It is recommended that the auxiliary bracket be 1,200 mm [47.2 in.] to 1,600 mm [63.0 in.] above the ground.
z The RRUs cannot installed on a wall in centralized mode. Therefore, expansion bolt assemblies should be
prepared for each RRU.
2. Drill holes at the anchor points and then install the expansion bolt assemblies.
Do not hammer the bolt entirely into the
wall. Instead, leave 20 mm to 30 mm of
the bolt outside the wall.
20 mm [0.8 in.]
to 30mm [1.2 in.]
55 mm [2.2 in.]
to 60mm [2.4 in.]
Ø14
90°
After the expansion bolt is removed,
dispose of the plastic tube.
When the RRU is installed on a wall, the requirements are as follows:
z For one RRU, the wall has a weight-bearing capacity of 96 kg [211.7 lb].
z The fastening torque of the expansion bolt reaches 30 N•m [265.5 lbf•in.] the expansion bolt works properly,
and no damages such as cracks are on the wall.
12
Installing the RRU on a Wall
3. Fit the auxiliary bracket on the expansion
bolts downward, and then tighten the bolts by
using a combination wrench 17 mm [0.7 in.].
M10
30 N•m
[265.5 lbf•in.]
Arrows are upwards
4. Install the main bracket.
5. Install the RRU.
13
Installing the RRU on a Wall
6. Install multiple RRUs.
Recommended Clearance :
≥855 mm
[33.7 in.]
Minimum Clearance:
≥655 mm
[25.8 in.]
≥855 mm
[33.7 in.]
≥655 mm
[25.8 in.]
≥70 mm
[2.8 in.]
≥70 mm
[2.8 in.]
Installing the RRU Cables
a
Cable List
RRU Cable Connections
Connector to…Connector TypeCable
Grounding bolt on the RRUOT terminal (M6)PGND cable
2
(16 mm
(North American standard:
3.3 mm
European standard:
4 mm
)
DIN male connectorRRU RF jumper
DC RRU power cable
2
2
)
CPRI optical cableThe connectors labeled 1A and 1B are connected to the optical
Two OT terminals
(M4)
DLC connector
DLC connector
Nearest grounding barOT terminal
Ports labeled ANT_TX/RXA and ANT_TX/RXB on the RRU
(Only the ANT_TX/RXA port supports the OOK signal).
Feeder or antennaDIN male connector
The blue OT terminal is connected to socket labeled NEG(-)0 in the
RRU cabling cavity. And the black OT terminal is connected to
socket labeled RTN(+)0.
External power supplyBare wire
module on the port labeled CPRI_W on the RRU
The connectors labeled 2A and 2B are connected to port labeled
CPRI0 to CPRI5 on the LBBP board of the BBU.
between the RRU and the
RCU
AISG extended cable
between the RRU and the
RCU
Standard AISG female connector
Port labeled RET/MON on the RRUWaterproof DB9 connectorAISG multi-wire cable
Standard AISG male connector of the AISG extension cable or
RCU
Standard AISG female connector of the AISG multi-wire cableStandard AISG male connector
Standard AISG male connector of the RCUStandard AISG female connector
14
Installing the RRU Cables
a
RRU Cable Connections
Single RRU
z When the length of the AISG multi-wire cable
between the RRU and the RCU is not enough, you
can choose the optional AISG extended cable
between the RRU and the RCU.
z If the coaxial cable is used for the RET antenna
when the STMA or Smart Bias-Tee (SBT) is used,
the OOK signals are required. Therefore, the port for
the RET antenna needs to use the ANT_TX/RXA
port.
PGND cable
RRU RF jumper
DC RRU power
cable
CPRI optical cable
AISG multi-wire cable between
the RRU and the RCU
AISG extended cable between
the RRU and the RCU
External power
system
BBU
RCU
Start
Install PGND cable
Install RRU RF
jumper
Antenna
Install feeder
(optional)
Install DC RRU
power cable
Install CPRI optical cable
Install AISG multi-wire
cable between the RRU
and the RCU (optional)
Install AISG extended
cable between the RRU
and the RCU (optional)
End
Multiple RRUs
PGND cable
RRU RF jumper
DC RRU power
cable
CPRI optical cable
AISG multi-wire cable
between the RRU and
the RCU
AISG extended cable
between the RRU and
the RCU
Antenna
Antenna
External power
system
Antenna
For detail information of the cable, see Cable List on Page 14.
15
Installing the RRU Cables
Opening the Cover Plate
bc
of the RRU Cabling Cavity
M4
Cover plate of the
cabling cavity
Cabling cavity
Label for preparing
the power cable
dCable Connections on the RRU
Cabling Cavity of the RRU
Cable troughs for
power cables
Cable troughs for
optical cables
Cable troughs for
power cables
cable clip
Waterproofing filler
z Before connecting a power cable,
ensure that other end of the power cable
not connected to any power supply.
z Use the DC RRU power cable clip t o
press the shielding layer tightly and
ensure that the lower part of the
shielding layer does not exceed the
position shown in the preceding figure.
z Ground the shielding layer at the
other end of the power cable.
z Do not remove the dustproof cap from
the idle antenna port, and use the
waterproof tape to wrap the joint.
z For details on how to add OT
terminals to the DC RRU power cable of
the RRU, see page 22 " Adding OT
Terminals by Using a Wire Stripper."
z When wrapping the waterproof tape,
apply even force to extend the tape until
the width of the tape is 1/2 of the
original width.
z Wrap the joint spirally upward,
downward, and then upward again. In
other words, the joint is wrapped by
three layers of the tape. Ensure that the
two immediate layers overlap with each
other about half the width of the tape.
For details, see page 24 “Waterproofing
Outdoor Cables.”
z Install the optical module before
installing the optical cables. For details,
see page 25 “Installing the Optical
Module.”
CPRI optical cable
Shielding
layer of the
power cable
DC RRU
power cable
RRU RF
jumper
After the cables
are installed on
the RRU, insert
the waterproofing
fillers into the idle
cable troughs.
First wrap the joint
with the waterproof
tape, and then
wrap the joint with
the PVC insulating
tape.
16
Installing the RRU Cables
e
Closing the Cover Plate of the RRU Cabling Cavity
M4
z The screws on the cover plate should
be tightened until the fastening torque is
1.4 N·m [12.4 lbf•in.].
z Tighten the screws on the cover plate
1.4 N•m
[12.4 lbf•in.]
of the cabling cavity in the sequence
shown in the figure.
f
RRU+APM30H
Grounding the shielding layer
of the power cable:
DC RRU power cable
a
CPRI optical cable
b
RRU1
DC RRU
power
cable
Metal Shielding layer
(25 mm [1 in.])
PGND cable
z The DC RRU power cable is connected to one of the RRU0 to RRU5 terminals of the PDU.
z Strip the jacket of th e DC RRU power cable for a small part, press the exposed shielding layer in the power
cable clip, and then connect the PGND cable on the clip to the nearest grounding bolt on the side of the cabinet.
17
Installing the RRU Cables
g
RRU+BBU Installed Against the Wall
LOAD6
LOAD0
DC RRU power cable
CPRI optical cable
BBU power cable
PGND cable
DCDU panel facing
the side, and the
BBU panel facing
downward
z The DC RRU power cable is connected to one group of the LOAD0 to LOAD5 terminals of the DCDU-03B.
z When the BBU and RRU are installed indoors, the DC RRU power cables need not to be grounded.
RRU+19-Inch Cabinet
h
LOAD0
DC RRU power cable
CPRI optical cable
z At the end of the DC RRU power cable connected to the DCDU-03B, you need to make the shielding
layer of the power cable into an OT terminal, and then connect the OT terminal to the PGND terminal of the
corresponding port on the DCDU-03B. For details about making an OT terminal, see pages 22 and 23.
z The DC RRU power cable is connec t e d t o L OAD 0 to L OAD 5 on th e DCDU-03B.
18
Installing the RRU Cables
RRU+TMC/TMC11H
i
Grounding the shielding layer
of the power cable:
DC RRU power cable
a
CPRI optical cable
b
LOAD0
DC RRU
power
cable
Metal Shielding layer
(25 mm [1 in.])
PGND cable
z At the end of the DC RRU power cable connected to the DCDU-03B, you need to make the shielding layer
of the power cable into an OT terminal, and then connect the OT terminal to the PGND terminal of the
corresponding port on the DCDU-03B. For details about making an OT terminal, see pages 22 and 23.
z The DC RRU power cable is connec t e d t o L OAD 0 to L OAD 5 on th e DCDU-03B.
19
RRU Hardware Installation Checklist
ItemsNo.
1
4
8
9
All self-made PGND cables are copper-based with the proper wire diameters. No breaking device such as switch and
fuse is allowed for the electric connection of the grounding system. No short circuit is allowed. Each terminal on the
grounding bar can be connected with only one wiring terminal of the PGND cable.
The RRU and the installation parts are securely installed.2
The cover plate is securely installed on the cabling cavity of the RRU.3
Waterproof fillers are installed in the idle cable troughs of the cabling cavity of the RRU, and the cover plate of the
cabling cavity is securely installed. In addition, the idle RF ports are covered with waterproof caps and waterproofed.
There are no connectors or joints on the power cable or PGND cable.5
The terminals at both ends of the power cable or PGND cable are securely soldered or crimped.6
The flat washer and the spring washer are well mounted on all OT terminals.7
All the power cables and PGND cables are not short-circuited or reversely connected. In addition, no damaged or
broken parts exist.
The power cable, PGND cable, feeder, optical cable and the E1/T1/FE signal cable are bound separately with a
spacing of larger than 30 mm [1.2 in.] .
The connector of the signal cable is intact, and no damaged or broken parts exist on the cable.10
Labels are correct, legible, and complete on both ends of each cable.11
Powering on the RRU
Start
a
Check
whether the input
voltage of the RRU is
normal?
Yes
Power on the RRU
b
Check
whether the status of
the LEDs on the RRU
is normal?
No
No
Rectify the fault
Rectify the fault
a
Normal input voltage of the
RRU:
If the BBU is supplied with
-48 V DC power, the
external input power
voltage ranges from -57 V
DC to -36 V DC.
b
Normal status of the
LEDs on the RRU:
RUN LED: ON for 1s
and OFF for 1s
ALM LED: OFF
Yes
End
When the RRU is unpacked, it must
be powered on within 24 hours.
20
Appendix
aBinding the RRU and Installation Components
1. Bind the RRU by leading the lifting rope along the low er part of the adaptin g piece and
through the handle, bind the main and auxiliary brackets with the lifting rope, and then
bind the steering rope with the handle of the RRU, as shown in the following fig ures.
Lifting rope
Steering rope
Lower part of the
adapting piece
z When lifting the RRU and installation components to the tower,
prevent the RRU from colliding with the tower.
z Lift the RRU to the tower before it is installe d on th e met al p ol e,
angle steel, or U-steel.
2. Lift the RRU and installation components to the tower.
Pulley
A
z Installer A climbs onto the tower. Then, installer
A fixes the pulley to the support of the tower
platform and leads the lifting rope through the
pulley.
Lifting rope
BC
Steering rope
z Installer C uses a lifting rope to bind the RRU
and installation components as shown in the
preceding figure and then ties a knot in the steering
rope at the handle of the RRU.
z Installer B pulls the lifting rope, and at the same
time, installer C pulls the steering rope away from
the tower to prevent the RRU and installation
components from colliding with the tower.
z Installer A holds the RRU and installation
components and untie the ropes.
Do not bind the lifting rope
only on the handle when
lifting the RRU.
21
Appendix
b
Adding OT Terminals by Using a Wire Stripper (Recommended)
Adding the OT terminals to the power cable invo lves adding OT terminals to the RRU
power cable and adding OT terminals to the shielding la yer of the RRU power cable.
Label for preparing
-48V DC power cable
Shielding layer
-48V DC power wire
OT terminals
GND wire
Determine lengths of power cables for
different operations according to the scales on
the inner side of the cover plate of the cabling
cavity.
the power cable
010203040
14mm
8mm
Based on the determined length, remove the
jacket and shielding layer off the power cable.
Remove the jacket from each wire.
Add an OT terminal to each wire.
Strip a 15 mm jacket off the power cable to
reveal the shielding layer o f t he p o wer ca bl e
15mm
The OT terminals must be added to the power cable before the RRU is installed on a metal pole.
22
Appendix
c
Adding OT Terminals to the Shielding Layer of the DC RRU Power Cable
Wrap the PVC
insulating tape
at the joint
where the three
wires meet.
WARNING
Do not damage the shielding layer of the power cable when cutting around the jacket.
Lead the wires
made of the
shielding layers
through heatshrinkable tubes.
OT terminal on
the shielding
layer
23
Appendix
Waterproofing Outdoor Cables
d
z The waterproof tape should be wrapped for an extra length of 20
mm [0.8 in.] away from the connectors at both ends.
z The tapes should be wrapped around the connector from the
lower part to the upper part. When wrapped for another layer, the
tapes may not be cut.
z When wrapping the waterproof tape, apply even force to extend
the tape until the width of the tape is 1/2 of the original width.
z When wrapping the waterproof tape, ensure that the upper layer
of the tape covers at least 50% of the lower layer.
z The insulating tape should be wrapped for an extra length of 20
mm [0.8 in.] away from the connectors at both ends.
z The last layer of the waterproof tape should be wrapped from
the lower part to the upper part to prevent rainwater from
infiltrating into the tape.
1. Wrap three layers of waterproof tape.
Waterproof tape
Insulating tape
2. Wrap three layers of insulating tape.
Tightly pressing the tape
Installing the Optical Module
e
Tightly pressing the tape
tie
tie
Binding cable ties at both
ends of the tape
24
Appendix
f
Pin Assignment of the RRU AISG Extension cable
Pin of the AISG
male connector
InstructionWire TypeWire ColorPin of the AISG
female connector
+12VTwisted pairWhite/blueX2.1X1.1
Blue
DC Return ATwisted pairWhite/orangeX2.7X1.7
Orange
RS485 BTwisted pairWhite/greenX2.3X1.3
RS485 AGreenX2.5X1.5
+24VTwisted pairWhite/brownX2.6X1.6
Brown
25
Change History
This describes the changes in the RRU3203 Installation Guide.
z01 (2010-04-13)
This is the commercial issue.
26
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People’s Republic of China
www.huawei.com
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.