2 Actuator bracket
(5003-0540)
1 Long rod, 17U
(5003-0538)
1 Short rod, 17U
(5003-0541)
1 Long rod, 10U
(5003-0539)
1 Short rod, 10U
(5003-0542)
1 Installation instructions
Part Number 391342-004
April 2007 (Fourth Edition)
Page 2
Hardware contents
g
Identification Quantity Description Picture
A 4 M4 hex lock nut
(0535-0076)
B 18 M5 x 16-mm
screw
(0515-3019)
C 6 M4 x 6-mm
screw
(0515-4500)
D 18 M5 barrel nut
(0590-2318)
E 2 10–24 custom
nut
(A6093-00180)
F 2 M4 x 10-mm flat-
head screw
(0515-4499)
J 3 M4 x 8-mm
screw
(0515-0433)
H 18 M5 cage nut
(353039-002)
Anti-tip stabilizers
The anti-tip stabilizers provide stability and support when
equipment is installed, removed, or accessed within the rack.
Stabilizer kits are available in both 600-mm (23.62-in) and
800-mm (31.50-in) versions. Use the side feet provided with
these kits to stabilize stand-alone racks. If you are stabilizing
racks that are secured together with baying kits, the side feet
are optional on either end of the row.
Single racks with a mounted component exceeding 99.79 kg
(219.99 lb) do not require a stabilizer kit to be installed.
However, when extending a heavy unit for service, a kit is
recommended.
Single racks bolted to the floor or rack rows with four or more
bayed racks do not need a stabilizer kit installed.
Lift and lift handles
WARNING: If you are going to use a lift, be sure to
use a lift that can handle the load of your server. Do
not manually lift the server to install it. If a lift is not
available, use lift handle kit (A6752-04049).
Required tools
• T-20 Torx driver
• T-25 Torx driver
• 8-mm hex-nut driver
Rack warning
WARNING: To reduce the risk of personal injury or
damage to the equipment, be sure that:
• The leveling feet are extended to the floor.
• The full weight of the rack rests on the leveling
feet.
• The stabilizin
a single-rack installation.
• The racks are coupled together in multiple-rack
installations.
• Only one component is extended at a time. A
rack may become unstable if more than one
component is extended for any reason.
1 Product outline
2 Positions for mounting the product (refer to step 8)
3 Positions for mounting the front of the slides (refer to step
3)
Item Reference
1 Product outline
2 Positions for mounting the cable management arm (refer
to step 7)
3 Positions for mounting the rear of the slides (refer to step
3)
NOTE: Single racks with a mounted component
exceeding 99.79 kg (220.99 lb) do not require a
stabilizer kit to be installed. However, when
extending a heavy unit for service, a kit is
recommended.
Single racks bolted to the floor or rack rows with
four or more bayed racks do not need a stabilizer kit
installed.
Page 4
g
g
WARNING: The wei
ht of this product requires a lift
to install. If a lift is not available, go to step 5 for
installation of lift handle panels. If lift handles are
already installed, continue to step 6.
CAUTION: This server must be unpacked in an ESD
safe environment. Observe all ESD safety
precautions before attemptin
this procedure. Failure
to follow ESD safety precautions can result in
damage to the server.
Item Reference
1 Stabilizer anti-tip feet
3. Install the right and left slides into the rack.
5. Install the lift handles, and place the server on the slides.
WARNING: Use the following procedure only if a
lift is not available. This procedure should only be
attempted by two authorized HP service personnel,
as a fully loaded server can weigh up to 99.79 kg
(220 lb). Before attempting this procedure, HP
recommends that you first remove all cell boards and
AC power supplies. Instructions for removing these
components can be found in the "Removal and
replacement" chapter of the service manual. Check
with local safety regulations before attempting to
move the system using the lift handle panels. Failure
to observe these precautions can cause harm to
personnel, or damage to the equipment.
4. Choose one of the following options:
o If you have a lift kit, place the server on the slides,
and then go to step 6.
o If you do not have a lift kit, then go to step 5.
Page 5
Page 6
Secure the slides to the server.
6.
8. Install the bezel front.
7. Install the cable management arm.
a. Attach screws (B) to the left rear column.
b. Slip the cable management arm over the screws (B)
and tighten.
c. Extend the cable management arm to the left rear
side of the product.
9. Install the interlock device.
NOTE: If the rack is bolted to the floor or is used in
a rack configuration with at least four bayed racks,
then the interlock device is not necessary. If two
products are installed and the rack depth is no more
than 717.55 mm (28.25 in), the interlock device
can be installed so that you can remove one product
at a time.
NOTE: The products must be racked adjacent to
each other to use the interlock device.
NOTE: If four products are installed in the rack and
interlock devices are used, then two interlock devices
are needed, with one device connected to the
bottom two products, and the other device
connected to the top two products.
d. Attach the cable management arm to the studs, and
secure it with nuts (E).
Page 7
Installing servers into squarehole racks
1.Attach cage nuts (H) to the front columns.
Item Reference
1 Second product
2 First mounting holes for second product
3 First product
10. Install the rods as shown in the following figure.
Item Reference
1 Product outline
2 Positions for mounting the product (refer to step 9)
3 Positions for mounting the front of the slides (refer to step
4)
Page 8
2.Attach cage nuts (H) to the rear columns.
Item Measurements required for rack
2 476.2 mm (18.75 in)
3 711 to 774.7 mm (28 to 30.5 in)
4. Install the right and left slides into the rack.
NOTE: Single racks with a mounted component
exceeding 99.79 kg (220.99 lb) do not require a
stabilizer kit to be installed. However, when
extending a heavy unit for service, a kit is
recommended.
Single racks bolted to the floor or rack rows with
four or more bayed racks do not need a stabilizer kit
installed.
Item Reference
1 Product outline
2 Positions for mounting the cable management arm (refer
to step 8)
3 Positions for mounting the rear of the slides (refer to step
4)
3. Adjust the slides according to the guidelines in the
following table.
Item Measurements required for rack
1 465 mm (18.31 in)
Page 9
Choose one of the following options:
g
g
5.
o If you have a lift kit, place the server on the slides,
and then go to step 7.
o If you do not have a lift kit, then go to step 6.
WARNING: The wei
ht of this product requires a lift
to install. If a lift is not available, go to step 6 for
installation of lift handle panels. If lift handles are
already installed, continue to step 7.
CAUTION: This server must be unpacked in an ESD
safe environment. Observe all ESD safety
precautions before attemptin
this procedure. Failure
to follow ESD safety precautions can result in
damage to the server.
6. Install the lift handles, and place the server on the slides.
WARNING: Use the following procedure only if a
lift is not available. This procedure should only be
attempted by two authorized HP service personnel,
as a fully loaded server can weigh up to 99.79 kg
(220 lb). Before attempting this procedure, HP
recommends that you first remove all cell boards and
AC power supplies. Instructions for removing these
components can be found in the "Removal and
replacement" chapter of the service manual. Check
with local safety regulations before attempting to
move the system using the lift handle panels. Failure
to observe these precautions can cause harm to
personnel, or damage to the equipment.
Page 10
7. Secure the slides to the server.
8. Install the cable management arm.
a. Attach screws (B) to the left rear column.
b. Slip the cable management arm over the screws (B)
and tighten.
c. Extend the cable management arm to the left rear
side of the product.
d. Attach the cable management arm to the studs, and
secure it with nuts (E).
Page 11
Install the bezel front.
9.
10. Install the interlock device.
NOTE: If the rack is bolted to the floor or is used in
a rack configuration with at least four bayed racks,
then the interlock device is not necessary. If two
products are installed and the rack depth is no more
than 717.55 mm (28.25 in), the interlock device
can be installed so that you can remove one product
at a time.
NOTE: The products must be racked adjacent to
each other to use the interlock device.
NOTE: If four products are installed in the rack and
interlock devices are used, then two interlock devices
are needed, with one device connected to the
bottom two products, and the other device
connected to the top two products.
Item Reference
2 First mounting-holes for second product
3 First product
11. Install the rods as shown in the following figure.
Item Reference
1 Second product
Page 12
Installing SEU into round-hole
racks
NOTE: The SEU can only be used with the rp84XX
and rx86XX server.
1.Attach barrel nuts (D) to the front columns.
Item Reference
1 SEU
2 Server
Item Reference
1 SEU outline
2 Positions for mounting the product (refer to step 6)
3 Positions for mounting the front of the slides (refer to step
3)
4 Server
Page 13
g
2. Attach barrel nuts (D) to the rear columns.
3. Install the right and left slides into the rack. Do not
tighten the outer screws.
Item Reference
1 SEU outline
2 Positions for mounting the cable management arm (refer
to step 7)
3 Positions for mounting the rear of the slides (refer to step
3)
4 Server
4. Remove and discard the center screw, allowing the slide
to lower slightly, and then tighten the outer screws.
5. Place the server on the slides using a lift kit.
WARNING: The wei
ht of this product requires a lift
to install. Do not manually lift the server to install it.
Use a lift that can handle the load of your server.
Page 14
CAUTION: This server must be unpacked in an ESD
g
safe environment. Observe all ESD safety
precautions before attemptin
this procedure. Failure
to follow ESD safety precautions can result in
damage to the server.
6. Insert screws to secure the server to the slides.
NOTE: Use the handles only to adjust the position of
the server while it is on the slides. Do not use the
handles to lift the server.
b. Slip the cable management arm over the screws (B),
and tighten.
c. Extend the cable management arm to the left side of
the product, attach it to the studs, and secure it with
nuts (E).
7. Install the cable management arm.
a. Attach screws (B) to the left rear column.
Page 15
Install the bezel front.
8.
9. Install the interlock device.
NOTE: The interlock device is required for each
rp84XX and rx86XX and SEU pair installed.
NOTE: The products must be racked adjacent to
each other to use the interlock device.
NOTE: If two pairs are installed, two interlock
devices are needed, with one connected to the
bottom pair and the other connected to the top pair.
Item Reference
1 SEU
2 First mounting holes for SEU
3 Server
10. Install the rods.
Page 16
Check the clearance between the short rod and the
11.
bottom actuator bracket. If the clearance is less than 1
mm (0.04 in), then proceed to step 12. If the clearance
is greater than 1 mm (0.04 in), then proceed to step 13.
12. Push the actuator bracket down while tightening the
screw.
Installing SEU into square-hole
racks
1. Attach cage nuts (H) to the front columns.
13. Verify the clearance again. If necessary, readjust, and
then go to step 12.
Item Reference
1 SEU outline
2 Positions for mounting the product (refer to step 9)
3 Positions for mounting the front of the slides (refer to step
4)
4 Server
Page 17
2.Attach cage nuts (H) to the rear columns.
Item Measurements required for rack
2 476.2 mm (18.75 in)
3 711 to 774.7 mm (28 to 30.5 in)
4. Install the right and left slides into the rack. Do not
tighten the outer screws.
NOTE: Single racks with a mounted component
exceeding 99.79 kg (220.99 lb) do not require a
stabilizer kit to be installed. However, when
extending a heavy unit for service, a kit is
recommended.
Single racks bolted to the floor or rack rows with
four or more bayed racks do not need a stabilizer kit
installed.
Item Reference
1 SEU outline
2 Positions for mounting the cable management arm (refer
to step 8)
3 Positions for mounting the rear of the slides (refer to step
4)
4 Server
3. Adjust the slides.
Item Measurements required for rack
1 465 mm (18.31 in)
Page 18
Remove and discard the center screw, allowing the slide
g
g
5.
to lower slightly, and then tighten the outer screws.
6. Place the server on the slides using a lift kit.
WARNING: The wei
ht of this product requires a lift
to install. Do not manually lift the server to install it.
Use a lift that can handle the load of your server.
CAUTION: This server must be unpacked in an ESD
safe environment. Observe all ESD safety
precautions before attemptin
this procedure. Failure
to follow ESD safety precautions can result in
damage to the server.
7. Insert screws to secure the server to the slides.
8. Install the cable management arm.
a. Attach screws (B) to the left rear column.
b. Slip the cable management arm over the screws (B),
and tighten.
c. Extend the cable management arm to the left rear
side of the product.
d. Attach the cable management arm to the studs, and
secure it with nuts (E).
Page 19
Install the bezel front.
9.
11. Install the rods.
10. Install the long and short rod.
Item Reference
1 SEU box
2 First mounting holes for SEU
3 Server
12. Check the clearance between the short rod and the
bottom actuator bracket. If the clearance is less than 1
mm (0.04 in), then proceed to step 13. If the clearance
is greater than 1 mm (0.04 in), then proceed to step 14.
Page 20
Push the actuator bracket down while tightening the
13.
screw.
14. Verify the clearance again. If necessary, readjust, and
then go to step 13.