AGF1
WASTE GAS TEMPERATURE SENSOR
PRODUCT DATA
The waste gas temperature sensor AGF1 is suitable for measuring waste gas in the flue gas pipe.#
The measured waste gas temperature can for instance be used for the following functions:
•Monitoring of waste gas temperature
•Determining switching on/off times of the burner
•Determining fuel consumption
•Calculating waste gas loss from the heat generator
•Metering the running time of the burner
In order to find out which of the above functions are possible, consult the instructions of the controller to which the waste gas sensor is connected.
The AGF 1 is designed as a conduit sensor to measure the waste gas temperature.
Temperature measurement
and range of application 0...320 °C
(short-time upper limit 400 °C)
Sensor element |
PT 1000 (1000 Ω at 0 °C) |
|
according to DIN 43 760 |
Construction |
Rod sensor with fitting for |
|
mounting on waste gas pipe |
Dimensions |
Sensor shaft 5 mm |
|
Length 180 mm |
|
Length of terminal cable 1 m |
Max. cable length |
100 m at 1.5 mm² |
The resistance of the waste gas temperature sensor AGF 1 depends on the temperature (according to DIN 43 760):
°C |
0 |
20 |
50 |
100 |
110 |
120 |
130 |
140 |
150 |
160 |
Ω1000 1078 1194 1385 1423 1461 1498 1536 1573 1610
°C 170 180 190 200 210 220 230 250 300 320
Ω1648 1685 1722 1758 1795 1832 1868 1941 2120 2191
EN3R-1104 GE51 R0897
AGF1
1.Loosen locking screw B and pull out the sensor element D from the guiding pipe.
2.Drill a 10 mm Þ hole at the position chosen on the gas pipe. Take care that the hole for the sensor element is near the heat generator (ca. 10 – 40 cm behind supports for the boiler waste gas).
3.Fit the plate C of the waste pipe so that it lies on the pipe.
4.Mark and drill the holes 3.0 mm Þ for the screws supplied.
5.Insert the sensor element into the guiding pipe.
6.Adjustment
The measurement of the waste gas temperature must be carried out in the core of the waste gas stream (hottest zone). Furthermore, it must be ensured that the swirling of waste gas in the pipe has taken place. By inserting the sensor elelment D at various depths and by repeated measuring of the waste gas temperature, the hottest zone will be found. The temperatures can be read in the display on the digital controller (see instructions).
7.When then hottest zone has been found, the sensor shaft is fixed into position by tightening the locking screw B.
There is a three-prong connection in the controller.
The wiring of the temperature sensor has to be in accordance with the overall wiring circuit diagram.
red
RL
AGF 1
|
|
white |
RL |
|||||
|
|
|||||||
|
|
|
|
|
|
|
|
|
Advantage: |
only two cables |
Disadvantage: the cable resistance RL distorts the measurement.
Three cable connection red
A B C D
AGF 1
Advantage:
white
white
the cable resistance is taken into account by the electronic evaluation and there is no distorbtion in the measurement.
Disadvantage: three cables are necessary and all must have the same resistance.
Four cable connection
|
|
red |
|
|
|
|
|
power supply |
|||||||
|
|
|
|
|
+ |
|
|||||||||
|
|
|
|
|
|
|
|
|
|||||||
AGF 1 |
|
red |
|
|
|||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
measurement |
|||||||||
|
|
|
|
|
|
||||||||||
|
|
white |
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
white |
|
|
|
|
|
|
- |
|
|||||
|
|
|
|
|
|
|
|
|
|||||||
|
|
|
|
|
|
|
|
|
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
||||||
Advantage: |
the cable resistance has no bearing on the |
||||||||||||||
|
results due to the electronic compensation |
||||||||||||||
|
(current demand and high ohmic voltage |
||||||||||||||
|
level). The measurement is not distorted and |
||||||||||||||
|
the cables can have different resistances. |
Disadvantage: four cables are necessary
Home and Building Control Products
Honeywell AG
Böblinger Straβ e 17
D-71101 Schönaich
Phone: (49) 7031 63701
Fax: (49) 7031 637493
http://europe.hbc.honeywell.com
Subject to change without notice. Printed in Germany |
Manufacturing location certified to |
EN3R-1104 GE51 R0897