ALL FOUNDATION SPECIFICATIONS SHALL BE CONSTRUED AS RECOMMENDATIONS ONLY.
BECAUSE OF THE MANY VARIABLE CONDITIONS IN AN ACTUAL INSTALLATION, GRAIN
SYSTEMS, INC. ASSUMES NO LIABILITY FOR RESULTS ARISING FROM THE USE OF SUCH
RECOMMENDATIONS.
SITE PREPARATION
Foundation Radius
Spike
Two Feet
2 x 4 Center Stake
Pointed Stake
Foundation Line
Figure #1
1.SELECTING THE PROPER SITE
The selected site should be level, firm, and free from underlying debris. The bin can be installed satisfactorily
on slopes, but as the slope increases, additional labor and materials are required for the foundation. The
concrete foundation surface must be level. If some fill is required, it should be watered and tamped thoroughly
to prevent uneven settling from the weight of the bin. Naturally, the site must allow convenient access for easy
loading and unloading, plus provide additional space for future units. Also, consider the positioning of
handling equipment, availability of electricity, and the placement of fans, heaters, and gas tanks.
2.SCRIBE THE DIAMETER
Having determined the center of the site, drive a small 2 x 4 in the ground to mark the center point of the
foundation. The top of the stake should be the same height as the finished foundation will be. Using one large
spike, nail a straight 2 x 4 (approximately 2 feet longer than the radius of the bin) to the top of the center stake.
This will enable it to swivel. Along the opposite end at a distance given in the foundation layout table, attach
a sharply pointed stake. The swiveling 2 x 4 will act as a compass, enabling you to scribe the correct diameter
of your foundation and later locate the anchor and stiffener bolt locations. (NOTE: Making the 2 x 4 two feet
longer than the radius will allow the 2 x 4 to also be used as a leveling device and for pulling concrete.)
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
1
18' Autoflow
Footing Trench
CIRCULAR FOUNDATION FORM
Carpenter's Level
Figure #2
3.PREPARE THE FOUNDATION
Having scribed the diameter of your foundation, proceed by digging the footing of the foundation. This
consists of a large circular trench dug just inside the foundation line. (Refer to foundation details for necessary
information.) Once the footing has been dug, you are ready to build the forms. It is important that your form
be rigid enough to hold its shape against the poured concrete. Also, the foundation must be flat. Sloped floors
cannot be used in drying bins. A carpenter’s level placed on top of your 2 x 4 will enable you to set the top
of the forms to match the top of the center stake. Check the form work with a transit to ensure a uniform
elevation for the entire foundation.
Grain Systems, Inc. Assumption, Ill.
2
REV. 11-20-96
18' Autoflow
OCTAGONAL FOUNDATION FORM
There are two styles of foundation forms commonly used. The first is the circular form depicted in Figure #2.
The second style can be made of 2" x 8" boards set into a square with corners blocked off to form an octagon.
(See Figure #3 below.) This eight sided form will approximate a circle and can be constructed quite easily.
When the foundation form is completed install reinforcement rods by either welding or wiring in place. Place
2" of compacted sand on the inside level of the foundation. The sand is then covered with a 4 mil plastic
moisture barrier. 6" x 6" wire mesh (2 mats), covering the entire area of the foundation, completes your
preparation of the bin’s foundation. You are now ready to begin pouring concrete.
NOTE: ALL CONCRETE IS TO HAVE A MINIMUM COMPRESSIVE STRENGTH OF 3,000 PSI
@ 28 DAYS.
6" x 6" Wire Mesh
2" x 8" Forms
Footing Trench
Top View
Foundation Line
Figure #3
Grain Systems, Inc. Assumption, Ill.
3
REV. 11-20-96
18' Autoflow
1234567890123456789012345
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1
5
1234567890123456789012345
FROST FREE PAD
NOTES:
Foundation site should be well drained and free of vegetation or debris.
Foundation design is based on a minimum soil bearing capacity of 3,000 lb/ft2. If soil bearing capacity is in
doubt, contact a local soil testing engineer.
Concrete shall have a minimum compressive strength of 3,000 PSI at 28 days.
Requirements for reinforcement do not include overlap.
Lap all circumferential bars 35 bar diameters and stagger all laps in plan 3'-0".
All material used for back fill inside the ring wall should be a clean, well graded, crushed stone or sand-gravel
mixture. Back fill should be placed in 6" lifts and well compacted.
Outside Radius
"N" #6 Bars
Evenly Spaced
1/2" Expansion Joint
6" Max.
1'-6"
1'-0" Min.
#6 Bars @ 12" c/c
Req'd only if "b" is
3" CI.
"b"
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
23456789012345678901234
Well Compacted Fill
Two Layers
6 x 6 - 6/6 Wire Mesh
Vapor Barrier
6"
Greater than 2'-0"
Figure #4
18' Diameter Bin
Ring Number5678
b1'-0"1'-0"1'-0"1'-7"
N2222
Outside Radius9'-9"9'-9"9'-9"9'-9"
Sq. Ft. Mesh 6 x 6 - 6/6500500500500
Length of #6 Bars200200200200
Total Cubic Yd. Concrete8889
Grain Systems, Inc. Assumption, Ill.
4
REV. 11-20-96
18' Autoflow
ANCHOR BOLT LAYOUT
Refer to following diagram for proper bolt layout.
Having poured and leveled the concrete, use the center stake and straight 2" x 4" again to find bolt circle radius
for the outside stiffener bolts. Select a starting point and stretch a pre-measured chord along the imaginary
circle formed by the bolt circle radius. Consider the placement of these bolts so as not to interfere with the
positions of bin doors and transitions.
Work both directions from first anchor bolt location, this will help eliminate possible error in laying out anchor
bolts. On larger bins sight across starting anchor bolt and center pin and place anchor bolt on opposite side
of anchor bolt radius. From this point you can work both directions from both anchor bolts.
Bolt Chord
Bolt Radius
Starting
Point
Work Both
Sight Across
Directions
B-5217 5/8" ANCHOR
BOLT ASSEMBLY
Figure #5
5/8" Anchor Bolt Detail
Bin Diameter
18'9'-3.1/16"12
Bolt Circle
Radius
Number of
Anchors
3"
12"
3"
Bolt Chord
Distance
4'-9.1/2"
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
5
18' Autoflow
HARDWARE/BOLTING REQUIREMENTS
NOTE: Grade 2 bolts are designated with a plain head.
NOTE: Grade 5 bolts are designated by 3 slash marks on the head.
All 5/16" diameter bolts are to be Grade 5 or higher.
NOTE: Grade 8 bolts are designated by 6 slash marks on the head.
NOTE: Grade 8.2 bolts are designated by 6 slash marks on the head in a
sunrise pattern.
All 3/8" diameter bolts are to be Grade 8 or 8.2.
IMPORTANT: Do not tighten bolts to exceed the torque specifications listed below.
TORQUE (ft. lb.)
BOLT SIZEMINIMUMMAXIMUM
5/16" - 181520
3/8" - 163542
7/16" - 146572
1/2" - 1395105
CAUTION: UNDER NO CONDITION SHALL ANY OTHER BOLTS BE SUBSTITUTED FOR
THOSE SUPPLIED BY GRAIN SYSTEMS, INC.
14 gauge and 13 gauge sidewall sheets, use
5/16" X 3/4" bolts and nuts. (S-275)
- Use 5/16" x 1.1/4" (S-277) for attaching floor flashing to the sidewall.
Grain Systems, Inc. Assumption, Ill.
6
REV. 11-20-96
18' Autoflow
REFER TO TOP DRY TANK BOLTING REQUIREMENTS
FOR COMPLETE BOLT USAGE
.950"
.750"
GRADE 5
SIDE VIEW
TOP VIEW
S-275
.3125" x .750" pre-assembled with a steel backed neoprene washer.
This bolt is used to connect horizontal and vertical seams for 13 gage and thinner sidewall sheets to each
other, and to bolt the stiffeners to the sidewall sheets. It is also used in attaching roof panels to the top
sidewall sheet and attaching roof panels and flashing to the center collar.
1.437"
1.250"
GRADE 5
SIDE VIEW
TOP VIEW
S-277
.3125" x 1.250" pre-assembled with a steel backed neoprene washer .
This bolt is primarily used to connect roof panels together where they overlap. It is also used at the bottom
of the flat bottomed bins to attach the base angle to the sidewall sheet. A small number of these are provided
for joints and FC-42076 splice plates for the stiffeners to sidewall connection.
Figure #6
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
7
18' Autoflow
REFER TO TOP DRY TANK BOLTING REQUIREMENTS
FOR COMPLETE BOLT USAGE
1.377"
1.000"
GRADE 8.2
SIDE VIEW
GRADE 8
TOP VIEW
S-7927
.375" x 1.000" hex flanged head without a plastic sealing washer.
This bolt is used to splice the stiffeners together on the flanges. A steel flat washer is used on the nut side of
the connection. They are also used on "c" channel splices and mounting "c" channel to wall bracket.
1.873"
GRADE 8.2
SIDE VIEW
GRADE 8
TOP VIEW
S-7928
.375" x 1.500" hex flanged head without a plastic sealing washer.
This bolt is used to attach the wall bracket to the sidewall and stiffener . A steel flat washer is used on the
nut side of the connection.
Note: The only washers shipped loose with the bins are the steel flat washers. The 5/16" steel flat washer
(S-845) is used where the base angle attaches to the sheet and some are used at the main eave clips. The
3/8" steel flat washers (S-248) are used at the stiffener splices and some are used in the roof rafter splices.
Figure #7
Grain Systems, Inc. Assumption, Ill.
8
REV. 11-20-96
18' Autoflow
LOCATION OF ACCESSORIES
Below is a typical Top Dry bin layout showing suggested locations of Top Dry Accessories. When locating
the manway be sure the outside ladder will not interfere with other accessories below. Roof vents should be
spaced evenly around the roof. (Quantity will vary with individual systems.)
NOTE: The Top Dry system should be provided with a dependable equipment ground.
Aeration Fan &
Transition
Roof Vents
Manual Winch
2 Ring Door
Crop Dryer
Platform
Top Dry
Crop Dryer Unit
Outside Ladder
Access Door
Platform
Manway
Top Dry
Control Center
Unloading Auger
Figure #8
Grain Systems, Inc. Assumption, Ill.
9
REV. 11-20-96
18' Autoflow
VERY IMPORTANT!
DC-1174 (Top Decal)
Top of Sheet
Horizontal seam hole locations
determine top and bottom of sheet.
Sheet shown as viewed from the inside of bin.
Bottom of Sheet
All 4.00" corrugated sidewall sheets must be placed correctly.
Top
All 4.00" corrugated sidewall sheets have a top and bottom!
Failure to observe this will not allow the door to fit properly.
Carefully review the er ection manual and place sidewall sheets as shown.
Grain Systems, Inc. Assumption, Ill.
10
REV. 11-20-96
18' Autoflow
SIDEWALL & STIFFENER GAUGES
Door locations are shown by the underlined sidewall gauges. Actual gauge of the access door sheet located
just below the Top Dry floor is in parentheses.
Top Dry Bin
TDM18-4
TDM18-5
TDM18-6
TDM18-7
Sidewall Gauges
20 20 20 20 (18)
20 20 20 20 20 (18)
20 20 20 20 20 20 (18)
20 20 20 20 20 20 20 (18)
18' Stiffener Layout
Odd Ring
GaugeRingRing
16-T*16-T*
16
16
1
2
3
1
2
3
Even Ring
Gauge
16
16
4
14
5
6
12
7
4
5
14
6
All Top Dry bin stiffeners are mounted on the outside of the bin. See stiffener instructions for stiffener joint
details and stiffener to sidewall attachment.
Figure #9
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
11
18' Autoflow
D
P
L
h
Cod
OUTSIDE STIFFENERS
The XX in the part numbers at the bottom will identify the Stiffener's gauge.
Example: FC-4205714 is a 2-Ring Standard Stiffener 14 Gauge.
1-Ring 18 Ga.FC-420741849 9/1 6"Orange
1-Ring Top 16 Ga.FC-420661641 7/16"Blue
1-Ring Top 18 Ga.FC-420661841 7/16"Orange
SpliceFC-4207610 11/16" ---
art No.
engt
e
85.9/16"
FC-42059XX
1 Ring
12 Ga.
14 Ga.
FC-42065XX
2 Ring Top
16 Ga.
18 Ga.
50.19/32"
FC-42074XX
1 Ring
16 Ga.
18 Ga.
FC-42076
Splice
10 Ga.
41.7/16"
49.9/16"
FC-42066XX
1 Ring Top
16 Ga.
18 Ga.
10.11/16"
93.13/16"
FC-4207216
2 Ring
16 Ga.
Base
Grain Systems, Inc. Assumption, Ill.
FC-42072XX
12
2 Ring
10 Ga.
12 Ga.
14 Ga.
Base
94.27/32"
FC-4206308
2 Ring
8 Ga.
87.15/16"
FC-42073
2 Ring
8 Ga.
Base
Figure #10
88.3/16"
FC-42062
2 Ring
10 Ga.
Transitional
94.19/32"
FC-42057XX
2 Ring
12 Ga.
14 Ga.
94.19/32"
FC-42075XX
2 Ring
16 Ga.
18 Ga.
REV. 11-20-96
93.9/16"
18' Autoflow
TOP STIFFENER STARTING LOCATION
Refer to Figure #11, for proper location of top stiffeners. On the overlap of the stiffeners, and on the splice, use
3/8" x 1" hex bolts, a washer on the nut side connection. Refer to the stiffener layout, Figure #9, for stiffener usage.
All stiffeners are outside the bin wall. Use 5/16" x 3/4" Grade 5 bin bolts with head and neoprene washer to the inside
of the bin wall. Refer to proper charts and illustrations on the previous two pages for proper location of stiffeners and
sidewall sheets.
4.00"
FRONT VIEW
TOP STIFFENER
Figure #11
SIDE VIEW
DETAIL "A"
5/16" X 3/4" BIN
BOLT
(S-275)
BOLT HEAD AND SEAL-
ING WASHER MUST BE
ON THE INSIDE OF THE
BIN.
DETAIL "A"
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
13
18' Autoflow
STIFFENER INSTALLATION & LOCATION
When installing bottom stiffeners, y ou may find that in some cases the stiffener with base plate attached
will not rest on the foundation (due to unlevel concrete, etc.) Shim plates have been furnished and should be
used to fill opening between base plate and concrete.
IMPORTANT: If shim plates are not used where required, the downward pressure of the stiff eners will
not be transferred directly to the foundation, and bin failure could result.
FC-4207516 16 GA.
BLUE
FC-4207518 18 GA.
ORANGE
3/8" DIA. HEX FLANGED
HEAD BOL T (NO
SEALING WASHER)
FC-4207516 16 GA.
BLUE
FC-4207518 18 GA.
ORANGE
USE 3/8" X 1.1/2"
BOL T, NUT AND W ASHER
SPLICE PLATE JOINT
(TOP VIEW)
3/8" DIA. HEX FLANGED
HEAD BOL T (NO
SEALING WASHER)
FC-4206308 8 GA.
YELLOW
FC-42062 10 GA.
PURPLE
FC-42076 SPLICE
OFFSET JOINT CONNECTION
DETAIL
Grain Systems, Inc. Assumption, Ill.
14
Figure #12
REV. 11-20-96
18' Autoflow
BOLTING REQUIREMENTS
2 STIFFENERS PER SIDEWALL SHEET
Sidew allHorizontalVe rticalStiffenerOve rlap
GaugeSeamSeamTo SidewallSeam
17 Thru 205/16" x 3/4"5/16" x 3/4"5/16" x 3/4"5/ 16" x 3/ 4"
[10][42][20][2]
All bolts are standard bin bolts with neoprene washers. For horizontal and vertical seam bolts, the bolt head and
neoprene washers are on the outside of the bin.
Note: For the splice plates FC-42076 use 5/16" x 1.1/4" bolts for the stiffener to sidewall connections.
Standard (17 Gauge Thru 20 Gauge) Sheet Bolting Detail
(Viewed from outside of the bin)
Vertical Seam
Horizontal Seam
Overlap Seam
Stiffener to
Sidewall
Figure #13
Grain Systems, Inc. Assumption, Ill.
REV. 11-20-96
15
18' Autoflow
Even Ring BinsOdd Ring Bins
STIFFENER & SEAM LOCATIONS
Horizontal Seam
Horizontal Seam
Horizontal Seam
Horizontal Seam
Horizontal Seam
Horizontal Seam
2 stiffeners per sidewall sheet
Top Dry stiffener starting location -18' to 36'
4" corrugation stiffener only
Figure #14
Grain Systems, Inc. Assumption, Ill.
16
REV. 11-20-96
Loading...
+ 35 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.