GE Industrial Solutions TLE Series 225-500 Installation Guide

Page 1
Critical Power
g
imagination at work
TLES_UL_225-250_S1_UPS_GE_01
TLE Series 225 & 250
TLE Series 400 & 500
GE Consumer & Industrial SA
General Electric Company CH – 6595 Riazzino (Locarno) Switzerland T +41 (0)91 / 850 51 51 F +41 (0)91 / 850 52 52
www.gecriticalpower.com
Installation Guide
Uninterruptible Power Supply
Page 2
Critical Power
Modifications reserved
Page 2/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Model:
TLE Series 225 – 250 - 400 - 500 UL S1
Issued by:
Product Document Department – Riazzino - CH
Approved by:
R & D Department – Riazzino - CH
Date of issue:
10/21/2013
File name:
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010
Revision:
1.0
Identification No.:
1026900
Up-dating
Revision
Concern
Date
COPYRIGHT © 2013 by GE Consumer & Industrial SA
All rights reserved.
The information contained in this publication is intended solely for the purposes indicated.
The present publication and any other documentation supplied with the UPS system is not to be reproduced, either in part or in its entirety, without the prior written consent of GE’s Critical Power.
The illustrations and plans describing the equipment are intended as general reference only and are not necessarily complete in every detail.
The content of this publication may be subject to modification without prior notice.
Page 3
Critical Power
Modifications reserved
Page 3/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Dear Customer,
We thank you for selecting our products and are pleased to count you amongst our very valued customers at GE‟s Critical Power.
We trust that the use of the TLE Series 225 - 500 Uninterruptible Power Supply system, developed and produced to the highest standards of quality, will give you complete satisfaction.
Please read carefully the Installation Guide, which contains all the necessary information and describes all you need to know about the installation of the UPS. Thank you for choosing GE‟s Critical Power !
START-UP AND COMMISSIONING
A GE GLOBAL SERVICES FIELD ENGINEER must perform start-up and commissioning of the UPS.
Please Contact GE. GLOBAL SERVICES at least two weeks prior to schedule start-up and commissioning at 1-800-637-1738, or by E-mail at
pqservice@ge.com .
Distributed in the USA by:
Your service contact:
g
GE Consumer & Industrial SA
General Electric Company
CH – 6595 Riazzino (Locarno)
Switzerland
www.gepowerquality.com
g
GE Digital Energy
Power Quality
2501 Pecan Street
Bonham, TX 75418 T: +1 800-637-1738 F: +1 903-640-0533
E: GEPQSales@ge.com
http://www.gedigitalenergy.com/ups
g
GE Digital Energy
Power Quality
830 West 40th Street
Chicago, IL 60609 24/7 T: 800-637-1738 24/7 T: 773-299-6600
F: 866-765-3595
E: pqservice@ge.com
Page 4
Critical Power
Modifications reserved
Page 4/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Congratulations on your choice of a TLE Series Uninterruptible Power Supply (UPS). It will help eliminate load disturbances due to unexpected power problem.
This manual describes how to prepare the installation site, and it provides weight and dimensions and procedures for moving, installing and connecting the UPS.
Please refer to the User Manual, which describes the function of the UPS module, the purpose and location of the switches, the meaning of the system events related to the front panel indication, and provides procedures for starting and stopping the equipment.
While every care has been taken to ensure the completeness and accuracy of this manual, GE‟s Critical Power assumes no responsibility or liability for any losses or damages resulting from the use of the information contained in this document.
WARNING!
TLE Series 225 250 400 - 500 is a product that needs to be installed by a licensed and knowledgeable contractor.
We recommend that this manual be kept next to the UPS for future references. If any problems are encountered with the procedures contained in this manual, please contact your Service Center before you proceed.
This document shall not be copied or reproduced without the permission of GE‟s Critical Power.
Some of the information contained in this manual may be changed without notice to reflect technical improvements.
Safety instructions
Read the safety instructions contained on the following pages carefully before the installation of the UPS, options and battery system.
Pay attention to the rectangular boxes included in the text: They contain important information and warning concerning electrical connections and personnel safety.
Parallel System version secured with RPA
When included in the text, this symbol refers to operation needed only for RPA Parallel System.
Preface
Page 5
Critical Power
Modifications reserved
Page 5/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Table of content Page
1 IMPORTANT SAFETY INSTRUCTIONS ............................................................................................................................. 6
2 LAYOUT ............................................................................................................................................................................... 9
2.1 LAYOUT TLE SERIES 225 & 250 .............................................................................................................................................................................. 9
2.2 LAYOUT TLE SERIES 400 & 500 ........................................................................................................................................................................... 11
3 ENVIRONMENT ................................................................................................................................................................13
3.1 RECYCLING INSTRUCTIONS.................................................................................................................................................................................. 13
4 INSTALLATION .................................................................................................................................................................14
4.1 TRANSPORT................................................................................................................................................................................................................. 14
4.1.1 Dimensions and weights TLE Series 225 – 500 ........................................................................................................................................................... 15
4.2 DELIVERY ...................................................................................................................................................................................................................... 16
4.3 STORAGE ...................................................................................................................................................................................................................... 16
4.3.1 Storage of the UPS .................................................................................................................................................................................................................... 16
4.3.2 Storage of Battery ..................................................................................................................................................................................................................... 16
4.4 PLACE OF INSTALLATION ...................................................................................................................................................................................... 17
4.4.1 UPS location ................................................................................................................................................................................................................................. 17
4.4.2 Battery location .......................................................................................................................................................................................................................... 21
4.5 VENTILATION AND COOLING ............................................................................................................................................................................... 22
4.6 UNPACKING ................................................................................................................................................................................................................ 23
4.7 ELECTRICAL WIRING ............................................................................................................................................................................................... 25
4.7.1 Utility input connection ........................................................................................................................................................................................................... 25
4.7.2 Input/output over current protection and wire sizing ............................................................................................................................................. 26
4.7.3 Battery over current protection and wire sizing ........................................................................................................................................................ 27
4.7.4 Installation requirements....................................................................................................................................................................................................... 29
4.8 WIRING CONNECTION ............................................................................................................................................................................................ 31
4.8.1 TLE Series 225 & 250 - Power connection with Common Input Utility ........................................................................................................... 34
4.8.2 TLE Series 225 & 250 - Power connection with Dual Input Utility ..................................................................................................................... 35
4.8.3 TLE Series 400 & 500 - Power connection with Common Input Utility ........................................................................................................... 37
4.8.4 TLE Series 400 & 500 - Power connection with Dual Input Utility ..................................................................................................................... 38
4.8.5 Use of TLE Series 225 - 500 in eBoost™ Operation Mode ..................................................................................................................................... 40
4.8.6 Use of TLE Series 225 - 500 as frequency converter ............................................................................................................................................... 41
4.9 RPA PARALLEL SYSTEM CONNECTION ............................................................................................................................................................ 42
4.9.1 Power wiring of parallel units .............................................................................................................................................................................................. 42
4.9.2 Parallel control bus connection .......................................................................................................................................................................................... 43
4.9.3 Control bus cable location .................................................................................................................................................................................................... 45
4.10 EPO COMMAND CONNECTION (EMERGENCY POWER OFF) ................................................................................................................... 47
5 CUSTOMER INTERFACE ..................................................................................................................................................48
5.1 SERIAL PORT J35µP - RS232 (SUB D, FEMALE 9 PIN)................................................................................................................................. 49
5.2 CUSTOMER INTERFACE BOARD .......................................................................................................................................................................... 50
5.2.1 Connector J1 – RJ45 8P8C .................................................................................................................................................................................................... 51
5.2.2 X1 terminal block - Output signals on voltage-free contacts ............................................................................................................................. 51
5.2.3 X1 terminal block - Programmable input free contacts ......................................................................................................................................... 51
5.2.4 X2 terminal block - EPO (Emergency Power Off) ........................................................................................................................................................ 52
5.2.5 X1 terminal block - Gen Set Signalling (GEN ON) ....................................................................................................................................................... 52
5.2.6 X1 terminal block - AUX external Maintenance Bypass ......................................................................................................................................... 53
5.2.7 X1 terminal block - eBoost/IEMi control signal ........................................................................................................................................................... 53
6 NOTES ...............................................................................................................................................................................54
6.1 NOTES FORM .............................................................................................................................................................................................................. 54
Page 6
Critical Power
Modifications reserved
Page 6/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
GENERAL
- Move the UPS in an upright position in its original package to the final destination room. To lift the cabinets, use a forklift or lifting belts with spreader bars.
- Check for sufficient floor and elevator loading capacity.
- Check the integrity of the UPS equipment carefully. If you notice visible damage, do not install or start the UPS. Contact the nearest Service Center immediately.
- WARNING! RISK OF ELECTRICAL SHOCK: Do not remove covers, there are no user serviceable parts inside.
- After switching off takes 5 minutes for the DC capacitors to discharge because a lethally high voltage remains at the terminals of the electrolytic capacitors.
- All maintenance and service work should be performed by qualified service personnel. The UPS contains its own energy source (battery).
- The field-wiring outlets may be electrically live, even when the UPS is disconnected from the utility.
- Dangerous voltages may be present during battery operation.
- The battery must be disconnected during maintenance or service work.
- This UPS contains potentially hazardous voltages.
- Be aware that the inverter can restart automatically after the utility voltage is restored.
- End user must follow applicable regional occupational safety codes/regulations during installation, operation and equipment maintenance. This may require additional field marking or labeling defining appropriate level of PPE (Personal Protection Equipment) to reduce the risk of Arc-flash related injuries. Contact our Technical Support for product specific information.
INSTALLATION
- This UPS must be installed and connected only by trained personnel.
- Verify accurately during Commissioning and Maintenance of the UPS, for the following: Damaged components, squeezed wires and cables, or not correctly inserted plugs.
- After removing the sidewalls of the UPS, make sure that all earth connections when reassembling, are correctly reattached.
- This UPS is intended for use in a controlled indoor environment free of conductive contaminants and protected against animals intrusion.
- WARNING! HIGH EARTH LEAKAGE CURRENT: Earth connection is essential before connecting to AC input!
- Switching OFF the unit does not isolate the UPS from the utility.
- Do not install the UPS in an excessively humid environment or near water.
- Avoid spilling liquids on or dropping any foreign object into the UPS.
- The unit must be placed in a sufficiently ventilated area; the ambient temperature should not exceed 104F (40°C).
- Optimal battery life is obtained if the ambient temperature does not exceed 77°F (25C).
- It is important that air can move freely around and through the unit. Do not block the air vents.
- Avoid locations in direct sunlight or near heat sources.
STORAGE
- Store the UPS in a dry location; storage temperature must be within -13°F (-25°C) to 131°F (+55C).
- The optimal temperature for Battery storage is 68°F (20°C) to 77°F (25°C) and shall never exceed the range -
4°F (-20°C) to 104°F (40°C).
- If the unit is stored for a period exceeding 3 months, the battery must be recharged periodically (time depending on storage temperature).
BATTERY
- The battery-voltage is dangerous for person‟s safety.
- When replacing the battery, use the same cells number, voltage (V), capacity (Ah). All the battery used, shall be of the same manufacturer and date of production.
- Proper disposal or recycling of the battery is required. Refer to your local codes for disposal requirements.
- Never dispose of battery in a fire: they may explode.
- Do not open or mutilate battery: their contents (electrolyte) may be extremely toxic. If exposed to electrolyte, wash immediately with plenty of water.
- Avoid charging in a sealed container.
- Never short-circuit the batteries. When working with batteries, remove watches, rings or other metal objects, and only use insulated tools.
- In case of air shipment, the cables +/- going to the battery fuses/terminals shall be disconnected and isolated.

1 IMPORTANT SAFETY INSTRUCTIONS

SAVE THESE INSTRUCTIONS
This manual contains important instructions for models TLE Series 225 - 500 that should be followed during installation and maintenance of the UPS and battery.
Page 7
Critical Power
Modifications reserved
Page 7/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
EXTERNAL BATTERY MUST BE INSTALLED AND CONNECTED TO THE UPS BY QUALIFIED SERVICE PERSONNEL ONLY. INSTALLATION PERSONNEL MUST READ THIS ENTIRE SECTION BEFORE HANDLING THE UPS AND BATTERY.
DANGER!
Full voltage and current are always present at the battery terminals. The battery used in this system can provide dangerous voltages, extremely high currents and a risk of electric shock. If the terminals are shorted together or to ground they may cause severe injury. You must be extremely careful to avoid electric shock and burns caused by contacting battery terminals or shorting terminals during battery installation. Do not touch uninsulated battery terminals.
A qualified service person, who is familiar with battery systems and required precautions, must install and service the battery. The installation must conform to national and local codes. Keep unauthorized personnel away from the battery.
The qualified service person must take these precautions:
1 Wear protective clothing, such as rubber gloves and boots and protective eye wear
Batteries contain caustic acids and toxic materials and can rupture or leak if mistreated. Remove rings and metal wristwatches or other metal objects and jewelry. Do not carry metal objects in your pockets where the objects can fall into the battery cabinet.
2 Tools must have insulated handles and must be insulated so that they will not short battery
terminals. Do not allow a tool to short between individual or separate battery terminals or to the cabinet or rack. Do not lay tools or metal parts on top of the battery, and do not lay them where they could fall onto the battery or into the cabinet.
3 Install the battery as shown on the drawing provided with the battery.
When connecting cables, never allow a cable to short across a battery’s terminals, the
string of battery, or to the cabinet or rack.
4 Align the cables on the battery terminals so that the cable lug will not contact any part of
the cabinet or rack, even if the battery is moved. Keep the cable away from any sharp metal edges.
5 Install the battery cables in such a way that the UPS or battery cabinet doors cannot pinch them. 6 Do not connect the battery terminal to Ground.
If any battery terminal is inadvertently grounded, remove the source of the ground. Contacting any part of a grounded battery can cause a risk of electric shock.
7 To reduce the risk of fire or electric shock, install the battery in a temperature and humidity
controlled indoor area, free of contaminants.
8 Battery system chassis ground (earth) must be connected to the UPS chassis ground (earth).
If you use conduits, this ground conductor must be routed in the same conduit as the battery conductors.
9 Where conductors may be exposed to physical damage, protect the conductors in
accordance with all applicable codes.
10 If you are replacing the battery or repairing battery connections, shut OFF the UPS and
remove the battery fuses.
Safety instructions when working with battery
Page 8
Critical Power
Modifications reserved
Page 8/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING, if instruction is not followed injury or serious equipment damage may occur!
CAUTION, internal parts have dangerous voltage present. Risk of electric shock!
PE (Earth) – GND (Ground) PROTECTIVE GROUNDING TERMINAL: A terminal which must be connected to earth ground prior to making any other connection to the equipment.
A terminal to which or from which an alternating (sine wave) current or voltage may be applied or supplied.
A terminal to which or from which a direct current or voltage may be applied or supplied.
This symbol indicated the word “phase”.
This symbol indicates the principal on/off switch in the on position.
This symbol indicates the principal on/off switch in the off position.
Safety symbols and warnings
Safety warnings The text of this manual contains some warnings to avoid risk to the persons and to avoid damages to
the UPS system and the supplied critical loads.
The non-observance of the warnings reminding hazardous situations could result in human injury and equipment damages.
Please pay attention to the meaning of the following warnings and symbols.
Throughout this manual the following symbols are defined:
Page 9
Critical Power
Modifications reserved
Page 9/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 2.1-1 TLE Series 225 & 250 - General view
Fig. 2.1-3 Control Panel
Fig. 2.1-4 Connectivity Rack
Fig. 2.1-2 TLE Series 225 & 250 - General view with open doors
Fig. 2.1-5 Manual switches Q1 & Q2
TLES_UL_225-250_S1_UPS_GE_02
TLES_160-400_S1_Customer interface-CI_SNMP_XA_01
SNMP
CI
1 2
EPO
EPO
-
+
J35µP
XA
TLES_UL_225-250_S1_UPS_GE_03
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO
EPO
-
+
Q1
I ON
0 OFF
TLES_UL_225-250_S1_Switch Q1-Q2_01
Q2
I ON
0 OFF

2 LAYOUT

2.1 LAYOUT TLE Series 225 & 250

Page 10
Critical Power
Modifications reserved
Page 10/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
1 Opening for top cable entry (*)
2 Opening for bottom cable entry (*)
3 Bus bars for Utility input and Load output
4 Bus bars for external Battery connection
CI Customer Interface Board (see Fig. 2.1-4)
CR Connectivity Rack
J35µP Serial port RS232 for IMV protocol
Q1 UPS output switch
Q2 Manual Bypass switch
SNMP 3-ph SNMP/WEB plug-in adapter (option - see Fig. 2.1-4)
XA Terminals for EPO connection and 24Vdc for external battery switch
*) Remove this panel or provide means to capture metal filings from cutting conduit entry holes
1
4
3
TLES_UL_225-250_S1_UPS_GE_04
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO
EPO
-
+
XA
CR
J35µP
RPA
Q2Q1
2
Fig. 2.1-6 TLE Series 225 & 250 - General view without protection panels
Page 11
Critical Power
Modifications reserved
Page 11/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 2.2-1 TLE Series 400 & 500 - General view
Fig. 2.2-3 Control panel
Fig. 2.2-4 Connectivity Rack
Fig. 2.2-2 TLE Series 400 & 500 - General view with open doors
Fig. 2.2-5 Manual switches Q1 & Q2
TLES_UL_400-500_S1_UPS_GE_02
TLES_160-400_S1_Customer interface-CI_SNMP_XA_01
SNMP
CI
1 2
EPO
EPO
-
+
J35µP
XA
TLES_UL_400-500_S1_UPS_GE_03
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
TLES_UL_400-500_S1_Switch Q1-Q2_01
Q1
I ON
0 OFF
Q2
I ON
0 OFF

2.2 LAYOUT TLE Series 400 & 500

Page 12
Critical Power
Modifications reserved
Page 12/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
1 Opening for top cable entry (*)
2 Opening for bottom cable entry (*)
3 Bus bars for Utility input and Load output
4 Bus bars for external Battery connection
CI Customer Interface Board (see Fig. 2.1-4)
CR Connectivity Rack
J35µP Serial port RS232 for IMV protocol
Q1 UPS output switch
Q2 Manual Bypass switch
SNMP 3-ph SNMP/WEB plug-in adapter (option - see Fig. 2.2-4)
XA Terminals for EPO connection and 24Vdc for external battery switch
*) Remove this panel or provide means to capture metal filings from cutting conduit entry holes
TLES_UL_400-500_S1_UPS_GE_04
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
1
2
XA
CR
RPA
J35µP
4
Q1
Q2
3
Fig. 2.1-6 TLE Series 400 & 500 - General view without protection panels
Page 13
Critical Power
Modifications reserved
Page 13/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
This product has been designed to respect the environment, using materials and components respecting eco-design rules.
It does not contain CFCs (Carbon Fluor Clorid) or HCFCs (Halogen Carbon Fluor Clorid).
PACKING MATERIAL RECYCLING
GE„s Critical Power, in compliance with environment protection, uses only environmentally friendly material.
UPS packing materials must be recycled in compliance with all applicable regulations.
RECYCLING AT THE END OF SERVICE LIFE !
GE‟s Critical Power, in compliance with environment protection recommends to the User that the UPS equipment, at the end of its service life, must be recovered conforming to the local applicable regulations.
WARNING !
Leads contained in the batteries is a dangerous substance for the environment, therefore it must be correctly recycled by specialized companies!

3 ENVIRONMENT

3.1 RECYCLING INSTRUCTIONS

Page 14
Critical Power
Modifications reserved
Page 14/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
The UPS is packaged on a pallet suitable for handling with a forklift. The UPS must be moved in upright position.
Do not tilt cabinets more than +/- 10° during handling.
Move the UPS in its original package to the final destination site. Do not stack other packages on top: This could damage the UPS.
Forklift
Fig. 4.1-1 Position of the forklift when moving the unpacked UPS
Forklift
The UPS may be lifted with a forklift in upright position.
Take note of the center of gravity marked on the package.
Crane
Fig. 4.1-2 Position of the carrying belts when moving the unpacked UPS
WARNING !
Check for sufficient floor and elevator loading capacity.
Transport UPS only in upright position.
Do not stack other package on top of the UPS.
Crane
If the UPS has to be lifted by crane, use suitable carrying belts taking note of the center of gravity marked on the package.
Take all necessary precautions to avoid damage to the cabinet while hoisting the UPS.
WARNING !
When loading / unloading and when moving the UPS, it is forbidden:
When loading / unloading and when moving the UPS, pay attention to:

4 INSTALLATION

4.1 TRANSPORT

Page 15
Critical Power
Modifications reserved
Page 15/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Dimensions and weights TLE Series 225 & 250
Dimensions (WxDxH):
44.10 x 34.06 x 75.00 inches
1120 x 865 x 1905 mm
Weight:
1323 lbs / 600 kg
Floor loading:
127 lbs/sq.ft / 620 kg/m2
Dimensions and weights TLE Series 400 & 500
Dimensions (WxDxH):
863.78 x 34.06 x 75.00 inches
1620 x 865 x 1905 mm
Weight:
2756 lbs / 1250 kg
Floor loading:
183 lbs/sq.ft / 892 kg/m2
NOTE !
The weight of each single piece is marked outside the package!
34.06"
865mm
44.10"
1120 mm
75.00" 1905mm
TLES_UL_225-250_S1_UPS dimension_GE_01
TLES_UL_400-500_S1_UPS dimension_GE_01
34.06"
865mm
63.78"
1620 mm
75.00" 1905mm

4.1.1 Dimensions and weights TLE Series 225 – 500

Page 16
Critical Power
Modifications reserved
Page 16/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
A damaged UPS must never be installed or connected to Utility or Battery!
The equipment is carefully packed for transport and storage so that it is in a perfect condition when eventually installed.
Never leave an UPS outside the building and do not store the UPS one on top of the other.
We recommend to store the UPS in its original package in a dry, dust-free room, away from chemical substances, and with a temperature range not exceeding -13°F (-25°C) to 131°F (55°C). In case the battery is included please refer to Section 4.3.2.
Recharge stored maintenance free Battery every:
6 months when the storage temperature is 68°F (20°C) 3 months when the storage temperature is 86°F (30°C) 2 months when the storage temperature is 95°F (35°C)

4.2 DELIVERY

When delivered, inspect the package integrity and the physical condition of the cabinets carefully.
In case of any damage sustained during transport, immediately inform the carrier and contact your local Service Center.
A detailed report of the damage is necessary for any insurance claim.

4.3 STORAGE

4.3.1 Storage of the UPS

Some important functions of the UPS, such as the customized functions, are defined by parameters stored in a RAM memory. A small backup Battery located on the Control Unit board supplies the RAM. If the storage time of the UPS exceeds 1 year, these functions should be verified by an authorized Service Center before putting the UPS into operation.

4.3.2 Storage of Battery

When the delivery includes a maintenance free Battery, keep in mind that they are subject to self­discharge and therefore you must recharge the Battery.
The storage time without Battery recharge depends on the temperature of the storage site.
The optimal temperature for Battery storage is 68°F (20°C) to 77°F (25°C) and shall never exceed the range -4°F (-20°C) to 104°F (40°C).
Page 17
Critical Power
Modifications reserved
Page 17/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
UPS installation and connection must be performed by QUALIFIED SERVICE PERSONNEL only. If optional cabinets and accessories are included with the UPS, please refer to those accompanying manuals for installation and operating instructions.
NOTE !
Temperature is very important for valve-regulated batteries (maintenance free). Operation at temperatures higher than 77°F (25°C) will reduce battery life.
Positioning of the UPS TLE Series 225 - 500
Fig. 4.4.1-1 TLE Series 225 - 500 – Positioning of the UPS
The rear panel of the UPS may be mounted flush to a wall or other structure.
Clearance around the front of the unit should be sufficient to enable free passage of personnel with the doors fully open, and to allow sufficient airflow to the door vents.
Check section 110-26(A) of the NEC code for specific requirements.
To guarantee proper cooling air exhaust, the recommended minimum clearance between ceiling and top of the UPS is 20” (500mm).
A single-phase power outlet (120Vac) should be provided near the UPS for connection of power tools, test equipment or connectivity devices. This outlet must be grounded.
TLES_UL_225-500_S1_UPS disposition_GE_01
TLE Series 225 & 250
TLE Series 400 & 500
Min.
20" / 500mm
Min.
20" / 500mm

4.4 PLACE OF INSTALLATION

4.4.1 UPS location

It is important to have a clean, dust-free environment provided with proper ventilation and air­conditioning to keep the ambient temperature within the specified operating range.
The recommended air inlet temperature is from 68°F (20°C) to 77°F (25°C) (max. 104°F / 40°C). Refer to Section 4.5.
Check for sufficient floor load capacity before installing the UPS and the Battery. Refer to Section 4.1.1.
For Battery installation follow the local codes and the recommendation of the battery supplier.
The TLE Series 225 - 500 UPS can radiate radio frequency energy. Although some RFI (Radio Frequency Interference) filtering is inherent to the UPS there is no guarantee that the UPS will not influence sensitive devices such as cameras and monitors that are positioned close by. If interference is expected, the UPS should be moved away from the sensitive equipment.
Page 18
Critical Power
Modifications reserved
Page 18/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
TLE Series 400 & 500 Moving the UPS cabinet
Fig. 4.4.1-2 TLE Series 400 & 500 – Moving the UPS cabinet
TLE Series 400 & 500 is
provided with a base reinforcement support (A) to avoid any damage during transportation of the UPS cabinet.
Fig. 4.4.1-3 TLE Series 400 & 500 Removing the UPS cabinet base reinforcement
WARNING !
It’s MANDATORY REMOVE the base reinforcement (A) after installing the UPS and before the start-up. See Fig. 4.4.1-3.
For any subsequent moving of the UPS cabinet is MANDATORY to re-install the base reinforcement (A).
TLES_UL_400-500_S1_UPS moving_01
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
A
TLES_UL_400-500_S1_UPS moving_01
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
A
Page 19
Critical Power
Modifications reserved
Page 19/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
TLE Series 225 - 500 Openings for input and output cable connections
Fig. 4.4.1-4 TLE Series 225 & 250 – Opening on top of the cabinet for input and output cables connections
Fig. 4.4.1-5 TLE Series 400 & 500 – Opening on top of the cabinet for input and output cables connections
Fig. 4.4.1-6 TLE Series 225 & 250 – Opening on the bottom of the cabinet for input & output cables connections
Fig. 4.4.1-7 TLE Series 400 & 500 – Opening on the bottom of the cabinet for input & output cables connections
TLE Series 225 - 500 openings are provided on the top (*) and the bottom (*) of the UPS for the
connection of input and output cables.
Pay attention to the position of these openings, when choosing the placement of the UPS. These openings are covered with a protective plate.
*) Please remove the plate before drilling any holes.
Utility input Output load Battery
9.85 "
250 mm
44.10"
1120 mm
0.99 "
25 mm
TLES_UL_225-250_S1_UPS view top_01US
FRONTAL SIDE
1 "
29.53 " 750 mm
34.06 " 865 mm
Utility input Output load Battery
10.83 "
275 mm
63.78"
1620 mm
1.38 " 35 mm
TLES_UL_400-500_S1_UPS view top_01US
FRONTAL SIDE
1 "
29.53 " 750 mm
34.06 " 865 mm
FRONTAL SIDE
8.27 "
210 mm
TLES_UL_225-250_S1_UPS view bottom_01US
Utility input
Load output
Battery
29.53 "
750 mm
34.06 " 865 mm
44.10"
1120 mm
0.99 "
25 mm
1.97 " 50 mm
FRONTAL SIDE
9.73 "
247 mm
TLES_UL_400-500_S1_UPS view bottom_01US
Utility input
Load output
Battery
29.10 "
739 mm
34.06 " 865 mm
63.78"
1620 mm
2.05 "
52 mm
2.68 " 68 mm
Page 20
Critical Power
Modifications reserved
Page 20/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fixing of the UPS cabinet TLE Series 225 – 500 on the floor
The UPS cabinet is free standing and normally does not require to be bolted to the floor.
The UPS cabinet can be fixed however to the floor by bolting it with the supporting blocks to the floor.
Fig. 4.4.1.8 Fixing of the UPS cabinet on the floor
Fig. 4.4.1-9 TLE Series 225 & 250 – UPS cabinet floor fixing points
Fig. 4.4.1-10 TLE Series 400 & 500 – UPS cabinet floor fixing points
TLES_UL_225-500_S1_UPS fixing_01
2.13 " / 54 mm
2.37 " / 60 mm
44.10 " / 1120 mm
27.56 " / 700 mm
14.18" / 360mm
Ø 12mm / 0.48"
TLES_160-200_S1_UPS fixing_01
FRONTAL SIDE
29.53 " / 750 mm
34.06 " / 865 mm
2.37 " / 60 mm
TLES_UL_400-500_S1_UPS fixing_02
29.53 " / 750 mm
2.37 " / 60 mm
27.56 " / 700 mm
27.56 " / 700 mm
2.37 " / 60 mm
3.94 " / 100 mm
34.06 " / 865 mm
2.37 " / 60 mm
63.78 " / 1620 mm
2.13 " / 54 mm
Ø 0.48 " / 12mm
FRONTAL SIDE
Page 21
Critical Power
Modifications reserved
Page 21/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.4.1-11 TLE Series 225 & 250
RPA Parallel System disposition
Fig. 4.4.1-12 TLE Series 400 & 500
RPA Parallel System disposition
In case of Parallel System, try to place the UPS modules in sequence of their numbers (marked on the packing).
If the units are positioned “side by side”, the side panels must be mounted on all
units.
WARNING !
Battery installation and connection must be performed by qualified personnel only.
Read all safety instructions before proceeding with the installation (see Section 1). Battery discharging and/or charging activities may cause the emission of
hydrogen gas; therefore, the room requires proper ventilation and fresh air. Comply with the UL1778-CSAC22.2no170.3 UPS safety standard, ANSI/IEEE P1184
Guide for Batteries for Uninterruptible Power Supply Systems and applicable codes and governmental regulations.
TLES_UL_225-250_S1_RPA disposition_GE_01US
UPS
3 - 4 - 5 - 6
UPS 2
UPS 1
TLES_UL_400-500_S1_RPA disposition_GE_01US
UPS
3 - 4 - 5 - 6
UPS 1
UPS 2

4.4.2 Battery location

Batteries require a well-ventilated room with controlled temperature to obtain reliable operation.
The Battery can be installed immediately adjacent to the UPS (left or right side) or remotely from the UPS. If the Battery is installed remotely from the UPS, a wall mounted DC disconnect device must be installed within line-of-site to both the UPS and the Battery.
The optimal room temperature for Battery storage is 68°F (20°C) to 77°F (25°C) and shall never exceed the range -4°F (-20°C) to 104°F (40°C).
The life of valve-regulated batteries will be reduced by 50% for each additional 18°F (10°C) that the battery ambient temperature is above 77°F (25°C).
The Battery System associated with larger UPS is usually either rack mounted or installed in multiple Battery Cabinets.
Installation and assembly must be made according to the local standards and Battery System manufacturer„s recommendations.
The Battery Circuit Breaker or Battery Fuse Box must be mounted as near as possible to the Battery.
Page 22
Critical Power
Modifications reserved
Page 22/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.5-1 Installation on plain floor
Fig. 4.5-2 Installation on raised floor
NOTE !
Do not put anything on the top of the cabinet.
UPS model
Losses
Cooling air flow
VFI
eBoost™ (option)
VFI
PF = 1
PF = 1
PF = 1
TLE Series 225
27845 BTU / hr
8.2 kW
10901 BTU / hr
3.2 kW
1698 CFM
2885 m3/h
TLE Series 250
31856 BTU / hr
9.3 kW
10361 BTU / hr
3.0 kW
1784 CFM
3031 m3/h
TLE Series 400
48038 BTU / hr
14.1 kW
17977 BTU / hr
5.3 kW
2710 CFM
4605 m3/h
TLE Series 500
63712 BTU / hr
18.7 kW
20722 BTU / hr
6.1 kW
3294 CFM
5597 m3/h
NOTE !
Even when eBoost™ Operating Mode option is available, the ventilation and cooling system shall be rated as for operation in VFI mode.

4.5 VENTILATION AND COOLING

The heat produced by the UPS is transferred to the environment by its ventilation.
Air inlets for UPS ventilation are located on the front of the UPS, while air outlets are on top of the cabinet.
A suitable ventilation or cooling system must be installed to extract the heat from the UPS room.
Air filtering systems could be required when the UPS operates in a dirty environment.
In order to prevent overheating of the UPS, the available air intake flow rate must exceed the total air exhaust flow rate requirement of the UPS system. Contact your Dealer or the nearest Service Center for appropriate solutions.
The below table indicates the heat dissipation at full Load at PF = 1 and charged Battery, up to 3280 ft (1000 m) altitude, for cooling air 77°F (25°C) to 86°F (30°C).
Page 23
Critical Power
Modifications reserved
Page 23/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
White color = without any anomaly Red color = anomaly evidence
The package of the TLE Series 400 & 500 is equipped with ShockWatch (indicator for shock), and TiltWatch (indicator for overthrow) on the outside.
These devices indicate an eventual shock or overthrow during transport.
Whenever these devices show a possible anomaly, the UPS shall not be commissioned before consulting a
Service Center.
Fig. 4.6-1 ShockWatch device
Fig. 4.6-2 TiltWatch device
NOTE !
Take care not to damage the UPS when moving by forklift.
A damaged UPS must never be installed or connected to Utility or Battery!
In case of any damage sustained during the transport, immediately inform the shipping agent!
A detailed report of the damage is necessary for any indemnity claim.

4.6 UNPACKING

Move the equipment in it‟s original packing, carton box or wooden case, until the place of installation
and remove the packing and the transport sockets only just before installing the UPS. Be aware of the heavy weight of the UPS, pay attention when moving the UPS cabinet.
Included in the delivery you can find the following parts:
An accessories bag. Air inlet grids, which must be mounted on the bottom of the cabinet UPS with the screws included. Control Bus cables for inter-connecting the UPS modules (only For the RPA system).
The documentation includes the User Manual” and the “UPS Safety Rules”.
Page 24
Critical Power
Modifications reserved
Page 24/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.6-3 P1 – Power Interface board
WARNING !
Cable with the sensor installation and connection must be performed by QUALIFIED SERVICE PERSONNEL only.
PACKING MATERIAL RECYCLING
GE‟s Critical Power, in compliance with environment protection, use only environmentally friendly material.
UPS packing materials must be recycled in compliance with all applicable regulations.
TLES_UL_225-500_S1_UPS-P1_Power interface_01
P1 - Power Interface
J12
P1
Q1
I ON
0 OFF
Q2
I ON
0 OFF
P1
In addition you can find a cable (standard length: 5m) with the thermal protection sensor. This is to compensate the battery charge voltage (only for type VRLA without maintenance) based on the working temperature. The sensor must be mounted in the battery cabinet while plug J12 must be connected to "P1-Power Interface".
When the sensor is disconnected, the floating voltage is calibrated for temperature = 68°F (20°C).
If the battery cabinet is not mounted side by side of the UPS, the cable connecting the temperature sensor to the UPS should be run in a protective conduit.
Page 25
Critical Power
Modifications reserved
Page 25/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING !
UPS installation and connection must be performed by QUALIFIED SERVICE PERSONNEL only.
It is the responsibility of the installation technician to ensure that all local and national electric codes are adhered to.
Refer to the “Safety prescriptions - Installation” described on Section 1.
NOTE !
Ensure that the AC and DC external isolators are OFF and locked out to prevent their inadvertent operation. Do not apply power to the equipment prior to the commissioning by a QUALIFIED SERVICE ENGINEER. Before any other input connection, connect and check the grounding wire.
Common Input Utility Rectifier & Bypass
Fig. 4.7.1-1 Common Input Utility Rectifier & Bypass (option)
The same power source is to be used for both Bypass Supply and Rectifier Input (input F3).
Bear in mind that when the Utility fuses are opened there is a supply failure to the Rectifier as well as to the Bypass and Manual Bypass switch.
In this case, the interconnection links BR1, BR2 and BR3 on the input terminals or bus bars MUST REMAIN CONNECTED.
Dual Input Utility Configuration Rectifier & Bypass (option)
Fig. 4.7.1-2 Dual Input Utility Rectifier & Bypass
The Bypass and Rectifier use different power sources (F1 and F2 inputs).
In this case, when the Rectifier-input fuses are opened, the Automatic Bypass and the Manual Bypass are supplied by the other connection.
Always verify that the received UPS is as per the configuration ordered. While installing UPS dual source, the interconnection links BR1, BR2 and BR3 MUST BE REMOVED. See Fig. 4.8.2-2 & 4.8.4-2.

4.7 ELECTRICAL WIRING

4.7.1 Utility input connection

The UPS has available input terminations for the Rectifier and Bypass. The unit may be powered from a Common Input source or Dual Input sources if desired.
Page 26
Critical Power
Modifications reserved
Page 26/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
If you use ELCB breaker (Earth Limiting Circuit Breaker) to protect the input connections, consider the high leakage current generated by the noise suppression capacitors.
If these ELCB breakers are strictly necessary, we suggest using the largest type suitable for non-linear current and for delayed operations.
NOTE !
The delivery and installation of fuses and input/output connections of the UPS are at
the customer’s expense, unless agreed otherwise.

4.7.2 Input/output over current protection and wire sizing

The cabling of the UPS system has to be sized according to the UPS power rating. Sizing of circuit Breakers, Fuses and cables for Input Utility, output load and Battery must meet the requirements of local and national electrical codes.
Before connecting the UPS, verify that the Utility Voltage and Frequency, the Output Load Voltage and Frequency and Battery Data (cells number, floating voltage, autonomy) are according to the required data.
The protection of the UPS utility input must be exclusively with 3 pole breakers. Disconnection of the Neutral is not permitted. The UPS needs the connection of the Neutral to the input, to guarantee the function in TN mode (Neutral-Earth).
Caution when using Four-Pole Circuit Breakers as protection to the UPS Load. A potential problem exists for situations with non-linear Loads, causing the Neutral Current to be higher than the Phase Current.
Avoid to run the input cables in parallel with the output cables to prevent them from noise induction.
The Three-Phase Utility Power supply must be symmetrical with respect to Ground (wye-connected and grounded solidly), due to the existence of voltage surge protection devices inside the UPS.
The connection of the Battery to the UPS must be protected with fuses or similar devices according to technical specifications and in accordance with local standards.
To ensure the circuit selectivity in case of Short- Circuit in the Load equipment, special care must be taken in choosing the Fuse or Circuit Breaker ratings installed in the output distribution circuits.
Due to the relatively low short-circuit capability of the UPS Inverter, a short-circuit in the Load will cause an immediate transfer to Utility. The largest fuse in the output distribution should be at least 1.6 time smaller than the Fuses supplying the Bypass line.
If circuit selectivity is required while the Load is fed from the Inverter (Bypass Utility not available), the Largest Fuse or Circuit Breaker should be rated at no more than 20% of the UPS Output Current Rating.
Page 27
Critical Power
Modifications reserved
Page 27/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
Please read the safety precautions at the front of this guide carefully, and
thoroughly review the battery manufacturers installation and maintenance manual before connecting the batteries to the UPS.
The remote rack mounted batteries are to be used then DC over current
protection must be provided by others.
Choose an appropriate DC fuse or circuit breaker using the current data in the
chart below.
Minimum battery cable requirement is based on the current data below. The maximum available fault current from the battery supply is: 20kA. The minimum breaker voltage rating is 540V
The AC values below are current ratings per phase.
These maximum and nominal ratings should be considered when choosing the appropriate AC
over current protection device.
NEC (National Electric Code) Section 210-20 (A) rules must be applied.
DC current rating is the nominal battery discharge current which the UPS allows.
(See Fig. 4.7.1-1 and 4.7.1.2)
UPS rating
AC Input Rectifier
AC Input Bypass
AC Input
DC Input
F1
F2
F3
F4
Nom.
Max.
Nom.
Max.
TLE Series 225
285 A
310 A
271 A
285 A
310 A
545 A
TLE Series 250
315 A
345 A
301 A
315 A
345 A
605 A
TLE Series 400
504 A
555 A
481 A
504 A
569 A
968 A
TLE Series 500
630 A
690 A
601 A
630 A
690 A
1210 A
Size of Branch Circuit Over Current Protection - All Models: - "CAUTION - To reduce the risk of fire,
only connect UPS to a circuit provided with (see below) maximum amperes branch circuit over
current protection in accordance with the NEC (National Electric Code), NSI / NFPA 70
UPS rating
F1 - AC Input Rectifier
F2 -AC Input Bypass
F3 - AC Input
F4 - DC Input
80% Rated
100% Rated
80% Rated
100% Rated
80% Rated
100% Rated
80% Rated
100% Rated
TLE Series 225
450 A
350 A
350 A
300 A
450 A
350 A
600 A
600 A
TLE Series 250
450 A
350 A
400 A
350 A
450 A
350 A
600 A
600 A
TLE Series 400
700 A
600 A
700 A
500 A
700 A
600 A
1000 A
1000 A
TLE Series 500
1000 A
700 A
800 A
700 A
1000 A
700 A
1200 A
1200 A
WIRING Wire sizing according to NEC Section 210-20 (A) Table 310-16 Use 167°F (75°C) copper or aluminum wire
Wiring requirements: AC INPUT RECTIFIER: 3-Phase, 4 wire plus Ground AC INPUT BYPASS: 3-Phase, 4 wire plus Ground AC OUTPUT: 3-Phase, 4 wire plus Ground DC INPUT: 2 wire (positive and negative) plus Ground
Maximum recommended cable size
UPS rating
Rectifier Input
Bypass Input
DC Input
AC Output
GND
TLE Series 225 TLE Series 250
2 x 600 kcmil
2 x 500 kcmil
2 x 600 kcmil
2 x 500 kcmil
1 x 400 kcmil
TLE Series 400 TLE Series 500
4 x 600 kcmil
4 x 500 kcmil
4 x 750 kcmil
4 x 500 kcmil
2 x 400 kcmil

4.7.3 Battery over current protection and wire sizing

Page 28
Critical Power
Modifications reserved
Page 28/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Temperature Rating of Conductor (See table 310-13)
Size
140°F (60°C)
167°F (75°C)
194°F (90°C)
140°F (60°C)
167°F (75°C)
194°F (90°C)
AWG
or
kcmil
Types
TW, UF
Types
FEPW, RH, RHW,
THHW, THW,
THWN, XHHW,
USE, ZW
Types
TBS, SA, SIS, FEP,
FEPB, MI, RHH, RHW-2, THHN,
THHW, THW-2,
THWN-2, USE-2,
XHH, XHHW,
XHHW-2,ZW-2
Types
TW, UF
Types
RH, RHW,
THHW,
THW, THWN,
XHHW, USE
Types
TBS, SA, SIS,
THHN, THHW,
THW-2, THWN-2, RHH, RHW-2, USE-2,
XHH, XHHW,
XHHW-2,
ZW-2
COPPER
ALUMINUM or COPPER-CLAD ALUMINUM
18
---
---
14
---
---
---
16
---
---
18
---
---
---
14
20
20
25
---
---
---
12
25
25
30
20
20
25
10
30
35
40
25
30
35
8
40
50
55
30
40
45
6
55
65
75
40
50
60
4
70
85
95
55
65
75
3
85
100
110
65
75
85
2
95
115
130
75
90
100
1
110
130
150
85
100
115
1/0
125
150
170
100
120
135
2/0
145
175
195
115
135
150
3/0
165
200
225
130
155
175
4/0
195
230
260
150
180
205
250
215
255
290
170
205
230
300
240
285
320
190
230
255
350
260
310
350
210
250
280
400
280
335
380
225
270
305
500
320
380
430
260
310
350
600
355
420
475
285
340
385
700
385
460
520
310
375
420
750
400
475
535
320
385
435
800
410
490
555
330
395
450
900
435
520
585
355
425
480
1000
455
545
615
375
445
500
1250
495
590
665
405
485
545
1500
520
625
705
435
520
585
1750
545
650
735
455
545
615
2000
560
665
750
470
560
630
CORRECTION FACTORS
Ambient
Temperature
For ambient temperatures other than 86°F (30°C), multiply the allowable ampacities shown above by the
appropriate factor below
70 – 77°F (21 – 25°C)
1.08
1.05
1.04
1.08
1.05
1.04
79 – 86°F (26 - 30°C)
1.00
1.00
1.00
1.00
1.00
1.00
88 – 95°F (31 - 35°C)
0.91
0.94
0.96
0.91
0.94
0.96
97 – 104°F (36 - 40°C)
0.82
0.88
0.91
0.82
0.88
0.91
106 – 113°F (41 - 45°C)
0.71
0.82
0.87
0.71
0.82
0.87
115 – 122°F (46 - 50°C)
0.58
0.75
0.82
0.58
0.75
0.82
124 – 131°F (51 - 55°C)
0.41
0.67
0.76
0.41
0.67
0.76
NEC SECTION 210-20 (A)
Table 310-16. Allowable Ampacities of Insulated Conductors Rated O Through 2000 Volts, 140°F Trough 194°F (60°C Trough 90°C) Not More than Three Current-Carrying Conductors in Raceway, Cable, or Earth (Directly Buried), Based on Ambient Temperature of 86°F (30°C).
Page 29
Critical Power
Modifications reserved
Page 29/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Single UPS with Common Input Utility for Rectifier & Bypass
Single UPS with Dual Input Utility for Rectifier & Bypass
UPS Parallel System with Common Input Utility Rectifier & Bypass

4.7.4 Installation requirements

Typical examples for the connection of the TLE Series 225 - 500.
Page 30
Critical Power
Modifications reserved
Page 30/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
UPS Parallel System with Dual Input Utility for Rectifier & Bypass
Page 31
Critical Power
Modifications reserved
Page 31/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING !
UPS installation and connection must be performed by QUALIFIED SERVICE PERSONNEL only. Refer to the “Safety prescriptions - Installation” described on Chapter 1.
In case of UPS equipped with options or customized parts not covered by this manual, please consult the appropriate technical documentation before proceeding with electrical connections.
TLE Series 225 & 250 Access to the bus bars for the cable connections
Fig. 4.8-1 TLE Series 225 & 250 - Access to connection bus bars
To access Input, Output and Battery connections proceed as
follows:
Remove the front protection
panel A.
Bottom entry cables: remove
the plate B.
Top entry cables: remove the
plate C.
NOTE !
For UPS correct operation, the input utility phase rotation must be clock­wise.
A
B
Utility mains / Battery / Output load
Bottom entry cables
TLES_UL_225-250_S1_UPS connection_01US
Utility mains / Battery / Output load
Top entry cables
!
Please remove the plate (B) before drilling any wholes
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO EPO
-
+
C

4.8 WIRING CONNECTION

Carefully read the following recommendations before proceeding:
Ensure that the AC and DC external isolators are Off, and prevent their inadverted operation. Do not close any external isolators prior to the commissioning of the equipment. The input/output cables must be connected in clockwise phase rotation for both Bypass and
Rectifier Input Bars if separate, taking care to avoid risk of short circuit between different poles.
The grounding and neutral connection of the electrical system must be in accordance with local
regulations.
In case of additional cabinets containing batteries, input/ output transformers, etc, their ground
terminals must be connected to the UPS main ground terminal.
Once the power cables have been connected, re-install the internal safety shields and close the
cabinets by re-installing all external panels.
Page 32
Critical Power
Modifications reserved
Page 32/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
TLE Series 400 & 500 Access to the bus bars for the cable connections
Fig. 4.8-2 TLE Series 400 & 500 - Access to connection bus bars
To access Input, Output and Battery connections proceed as follows:
Remove the front protection panel A. Bottom entry cables: remove the plate B. Top entry cables: remove the plate C.
NOTE !
For UPS correct operation, the input utility phase rotation must be clock-wise.
CAUTION !
Panel “A, B and C” should never be removed or replaced with power applied to the UPS.
These panels are in close proximity to 480V live buss bars.
Always disconnect the rectifier, bypass, load and battery sources from the UPS before removing or replacing these panels. If not serious injury or death could occur!
Q1
I ON
0 OFF
A
B
C
Utility mains / Battery / Output load
Bottom entry cables
TLES_UL_400-500_S1_UPS connection_01US
12
Q2
I ON
0 OFF
EPO
EPO
-
+
Utility mains / Battery / Output load
Top entry cables
!
Please remove the plate (B) before drilling any wholes
!
It's MANDATORY REMOVE the base reinforcement (C) See Chapter 4.4.1
D
Page 33
Critical Power
Modifications reserved
Page 33/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
TLE Series 400 & 500 Connection bus bars configuration for the top cable entry or bottom cable entry
The configuration of the TLE Series 400 & 500 is with top cable entry as standard (see Fig. 4.8-3). It is possible to configure the bus bars with bottom cable entry (see Fig. 4.8-4).
Fig. 4.8-3 TLE Series 400 & 500 - Configuration bus bars with top cable entry (standard)
Fig. 4.8-4 TLE Series 400 & 500 - Configuration bus bars with bottom cable entry
Q2
Q1
TLES_UL_400-500_S1_UPS connection_Top_01US
Utility mains / Battery Output load
Position of the cover protection for
cables input from the bottom of the UPS
+
-
PE
L3-1
L2-1
L1-1
N
Utility Neutral Load Neutral
Load
1
Rectifier &
Bypass
Utility
BR2
BR3
BR1
PE
PE Input Utility & PE Load (Use for top entry cables)
L3
L2
L1
PE
PE Input Utility PE Load
Attention: Use only as additional PE
Q2
Q1
TLES_UL_400-500_S1_UPS connection_Bottom_01US
Position of the cover protection for
cables input from the bottom of the UPS
Utility mains / Battery Output load
+
-
L3
L2
PE
L3-1
L2-1
L1-1
(use for bottom entry cables)
PE Input Utility & PE Load
N
Utility Neutral Load Neutral
Load
L1
1
Rectifier &
Bypass
Utility
BR2
BR3
BR1
PE
Load
(L3 - L2 - L1)
1 - Rectifier & Bypass Utility
(L3-1 - L2-1 - L1-1)
(use for top entry cables)
PE Input Utility & PE Load
PE
PE Input Utility PE Load
Attention:
Use only as additional PE
Page 34
Critical Power
Modifications reserved
Page 34/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.8.3-1 TLE Series 225 & 250 - Power connections Common Input Utility
Common Input Utility - Rectifier / Bypass
L1-1
Rectifier + Bypass Phase A (L1)
L2-1
Rectifier + Bypass Phase B (L2)
N
Neutral
L3-1
Rectifier + Bypass Phase C (L3)
PE
Ground
NOTE !
The interconnection links BR1, BR2 and BR3 (option) on the input bus bars MUST REMAIN CONNECTED.
Output Load
L1
Load phase A (L1)
L2
Load phase B (L2)
L3
Load phase L3
N
Neutral
Ground
External Battery connection
+
Positive pole of the battery
UPS PARALLELED ON THE SAME BATTERY:
This configuration is not possible for UPS Parallel System TLE Series 225 & 250.
Before closing the “External Battery Fuses”, verify for correct polarity of the battery connection.
-
Negative pole of the battery
PE
Battery cabinet ground
NOTE !
To meet standards concerning electromagnetic compliance, the connection between the UPS and external Battery must be done by using a shielded cable or suitable shielded (steel) conduit! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. If the UPS is equipped with an input bypass transformer, the secondary of the transformer must be wye-configured with neutral solidly grounded.
+
-
Typical installation
using common NEMA
two hole lugs
PE
TLES_UL_225-250_S1_UPS connection common_01US
1
Rectifier & Bypass
Utility
L1-1
N
Utility Neutral Load Neutral
Load
L1
L2-1
L2
L3-1
L3
INTERCONNECTIONS LINKS BR1, BR2 and BR3 MUST REMAIN CONNECTED
!

4.8.1 TLE Series 225 & 250 - Power connection with Common Input Utility

Power connection cables are connected to bus bars using M10 bolts. The bolts of the connection cables must be tightened with a torque wrench at 355 Lb-in / 40 Nm.
Page 35
Critical Power
Modifications reserved
Page 35/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
Neutral of Rectifier input and Neutral of Bypass input must be coming from the same input bar.
Fig. 4.8.2-1 TLE Series 225 & 250 - Power connections with Dual Input Utility
Dual Input Utility - Rectifier / Bypass
L1-1
Rectifier phase A (L1)
L1-2
Bypass phase A (L1)
L2-1
Rectifier phase B (L2)
L2-2
Bypass phase B (L2)
L3-1
Rectifier phase C (L3)
L3-2
Bypass phase C (L3)
PE
Ground
N
Neutral
NOTE !
The interconnection links BR1, BR2 and BR3 (option) on the input bus bars MUST BE REMOVED (see Fig. 4.8.4-2).
Output Load
L1
Load phase A (L1)
L2
Load phase B (L2)
L3
Load phase L3
N
Neutral
Ground
External Battery connection
+
Positive pole of the battery
UPS PARALLELED ON THE SAME BATTERY:
This configuration is not possible for UPS Parallel System TLE Series 225 & 250.
Before closing the “External Battery Fuses”, verify for correct polarity of the battery connection.
-
Negative pole of the battery
PE
Battery cabinet ground
NOTE !
To meet standards concerning electromagnetic compliance, the connection between the UPS and external Battery must be done by using a shielded cable or suitable shielded (steel) conduit! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. If the UPS is equipped with an input bypass transformer, the secondary of the transformer must be wye-configured with neutral solidly grounded.
+
-
Typical installation
using common NEMA
two hole lugs
PE
TLES_UL_225-250_S1_UPS connection_01US
1
Rectifier
Utility
L1-1
N
Utility Neutral Load Neutral
2
Bypass
Utility
L1-2
Load
L1
L2-1
L2-2
L2
L3-1
L3-2
L3
INTERCONNECTIONS LINKS BR1, BR2 and BR3 MUST BE REMOVED (see Fig. 4.8.2-2)
!

4.8.2 TLE Series 225 & 250 - Power connection with Dual Input Utility

Power connection cables are connected to bus bars using M10 bolts. The bolts of the connection cables must be tightened with a torque wrench at 355 Lb-in / 40 Nm.
Page 36
Critical Power
Modifications reserved
Page 36/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Installation notices in case of power connection with Dual Input Utility
Fig. 4.8.2-2 TLE Series 225 & 250 - Interconnection links BR1, BR2 and BR3
NOTE !
For separate Bypass and Rectifier input configuration, the interconnection links BR1, BR2 and BR3 MUST BE REMOVED (see Fig. 4.8.2-2).
Q1
Q2
TLES_UL_225-250_S1_UPS BR1-2-3_01US
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO
EPO
-
+
36
BR1 (3x20x1mm / L=220mm)
36
37
BR2 (3x20x1mm / L=220mm)
37
38
BR3 (3x20x1mm / L=220mm)
38
BR1
BR3
BR1, BR2 and BR3 MUST BE REMOVED
!
BR2
Page 37
Critical Power
Modifications reserved
Page 37/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.8.3-1 TLE Series 225 & 250 - Power connections Common Input Utility
Common Input Utility - Rectifier / Bypass
L1-1
Rectifier + Bypass Phase A (L1)
L2-1
Rectifier + Bypass Phase B (L2)
N
Neutral
L3-1
Rectifier + Bypass Phase C (L3)
PE
Ground
NOTE !
The interconnection links BR1, BR2 and BR3 (option) on the input bus bars MUST REMAIN CONNECTED (see Fig. 4.8.3-2).
Output Load
L1
Load phase A (L1)
L2
Load phase B (L2)
L3
Load phase L3
N
Neutral
Ground
External Battery connection
+
Positive pole of the battery
UPS PARALLELED ON THE SAME BATTERY:
This configuration is not possible for UPS Parallel System TLE Series 225 & 250.
Before closing the External Battery Fuses”, verify for correct polarity of the battery connection.
-
Negative pole of the battery
PE
Battery cabinet ground
NOTE !
To meet standards concerning electromagnetic compliance, the connection between the UPS and external Battery must be done by using a shielded cable or suitable shielded (steel) conduit! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. If the UPS is equipped with an input bypass transformer, the secondary of the transformer must be wye-configured with neutral solidly grounded.
INTERCONNECTIONS LINKS
BR1, BR2 and BR3
MUST REMAIN CONNECTED
Q2
Q1
TLES_UL_400-500_S1_UPS connection common_Top_01US
+
-
PE
PE
N
Utility Neutral Load Neutral
Typical installation
using common NEMA
two hole lugs
Load
Typical installation using
common NEMA two hole lugs
PE
PE
(Use for top entry cables)
L3
L2
L1
L3-1
L2-1
L1-1
1
Rectifier &
Bypass
Utility
BR2
BR3
BR1
(Use for bottom entry cables)
PE
Attention: Use only as additional PE
!
Position of the cover protection
with top cable entry
Position of the cover protection with bottom cable entry

4.8.3 TLE Series 400 & 500 - Power connection with Common Input Utility

Power connection cables are connected to bus bars using M10 bolts. The bolts of the connection cables must be tightened with a torque wrench at 355 Lb-in / 40 Nm.
Page 38
Critical Power
Modifications reserved
Page 38/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
Neutral of Rectifier input and Neutral of Bypass input must be coming from the same input bar.
Fig. 4.8.4-1 TLE Series 400 & 500 - Power connections with Dual Input Utility
Dual Input Utility - Rectifier / Bypass
L1-1
Rectifier phase A (L1)
L1-2
Bypass phase A (L1)
L2-1
Rectifier phase B (L2)
L2-2
Bypass phase B (L2)
L3-1
Rectifier phase C (L3)
L3-2
Bypass phase C (L3)
PE
Ground
N
Neutral
NOTE !
The interconnection links BR1, BR2 and BR3 (option) on the input bus bars MUST BE REMOVED (see Fig. 4.8.4-2).
Output Load
L1
Load phase A (L1)
L2
Load phase B (L2)
L3
Load phase L3
N
Neutral
Ground
External Battery connection
+
Positive pole of the battery
UPS PARALLELED ON THE SAME BATTERY:
This configuration is not possible for UPS Parallel System TLE Series 400 & 500.
Before closing the External Battery Fuses”, verify for correct polarity of the battery connection.
-
Negative pole of the battery
PE
Battery cabinet ground
NOTE !
To meet standards concerning electromagnetic compliance, the connection between the UPS and external Battery must be done by using a shielded cable or suitable shielded (steel) conduit! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. If the UPS is equipped with an input bypass transformer, the secondary of the transformer must be wye-configured with neutral solidly grounded.
+
-
PE
L3-1
L1-2
L2-2
(use for bottom cable entry)
PE
N
Utility Neutral Load Neutral
Typical installation
using common NEMA
two hole lugs
L3-2
Load
BR1, BR2 and BR3 MUST BE REMOVED (see Fig. 5.8.2-1)
!
2 - Bypass Utility
1
Rectifier
Utility
Typical installation using
common NEMA two hole lugs
PE
PE
(use for top cable entry)
L3
L2
L1
Q2
Q1
TLES_UL_400-500_S1_UPS connection_01US
L2-1
L1-1
Position of the cover protection
with top cable entry
PE
Attention:
Use only as additional PE
Position of the cover protection with bottom cable entry

4.8.4 TLE Series 400 & 500 - Power connection with Dual Input Utility

Power connection cables are connected to bus bars using M10 bolts. The bolts of the connection cables must be tightened with a torque wrench at 355 Lb-in / 40 Nm.
Page 39
Critical Power
Modifications reserved
Page 39/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Installation notices in case of power connection with Dual Input Utility
Fig. 4.8.4-2 TLE Series 400 & 500 - Interconnection links BR1, BR2 and BR3
NOTE !
For separate Bypass and Rectifier input configuration, the interconnection links BR1, BR2 and BR3 MUST BE REMOVED (see Fig. 4.8.4-2).
+
-
PE
L3-1
L1-2
L2-2
(with bottom cable entry)
PE
N
Utility Neutral Load Neutral
L3-2
Load
2 - Bypass Utility
1
Rectifier
Utility
PE
PE
(with top cable entry)
L3
L2
L1
Q2
Q1
TLES_UL_400-500_S1_UPS BR1-2-3_01US
L2-1
L1-1
BR1, BR2 and BR3 MUST BE REMOVED
!
BR1
BR2
BR3
PE
Attention: Use only as additional PE
36
37
38
38
37
36
Page 40
Critical Power
Modifications reserved
Page 40/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
For systems intended to be operated in eBoost™ Operation Mode, the installation shall be protected with suitable surge protection devices (SPDs) on the AC bus feeding the UPSs.
Please contact your Service Center for more information.
NOTE !
In eBoostTM Operation Mode the inverter output filter is placed in parallel with the load, and combined with the load current it contributes to the UPS input characteristic.
As the inverter output filter exhibits a predominantly capacitive characteristic, it may provide some degree of reactive power compensation when combined with lagging power factor loads.
Conversely, depending on the load type and level, the UPS input characteristic may exhibit a leading power factor in eBoostTM Operation Mode.
Please contact your Service Center for more information.
NOTE !
If an emergency generator set supplies the UPS in case of Utility Failure, and the system is intended to be operated in eBoost™ Operation Mode, eBoost operation shall be prevented during generator operation.
This can be accomplished by either installing a “GENERATOR ON” signal (refer to Section 5.2.5) or an “eBoost/IEMi CONTROL” signal (refer to Section 5.2.7).
Please contact your Service Center for more information.

4.8.5 Use of TLE Series 225 - 500 in eBoost™ Operation Mode

Page 41
Critical Power
Modifications reserved
Page 41/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
The UPS needs the connection of the Neutral at the input Bus Bars.
Fig. 4.8.6-1 TLE Series 225 - 500 - Switch Q2 – Manual Bypass
When the UPS is used as a frequency converter, the circuit breaker Q2 - Manual Bypass operating handle should be removed to avoid any accidental closure. See Fig. 4.8.4-1.
In order to avoid improper operation, only the Rectifier input should be powered (L1-1, L2-1 and L3-1
/ Fig. 4.8.2-1 & 4.8.4.1), therefore the interconnection links BR1, BR2 and BR3, on the input bus bars, MUST BE REMOVED. See Fig. 4.8.2-2 and 4.8.4-2.
Special care must be taken in choosing the fuse ratings installed in the output distribution (max. 20% of the UPS rated current).
Avoid high inrush current due to transformer magnetization or motor starting.
NOTE !
At site only a QUALIFIED SERVICE ENGINEER may change a unit, initially delivered as a frequency converter, into a normally operating “standard” UPS.
Q2
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
-
+
I ON
0 OFF
TLES_UL_400-500_S1_UPS-Switch Q2_01
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
-
+
I ON
O OFF

4.8.6 Use of TLE Series 225 - 500 as frequency converter

When the TLE Series 225 - 500 is utilized for different output frequency compared to the input frequency, the Automatic Bypass and Manual Bypass functions are disabled, therefore the Load cannot
be transferred to Utility in case of overload, short circuit, or inverter failure.
In situations where the UPS needs to be powered down for maintenance purposes, the critical Load must also be powered down during this time.
The UPS cannot be transferred to Manual Bypass, as serious damage to the Load could be the result.
When the set-up parameters of the UPS are set for frequency converter, the eBoost™ Operation Mode is automatically disabled.
Page 42
Critical Power
Modifications reserved
Page 42/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING !
This operation must be performed by trained personnel before the initial start-up (ensure that the UPS installation is completely powered down).
NOTE !
It is strongly recommended that no transformers, automatic circuit breakers or fuses should be inserted between the unit’s output and the Load common bus bars.
However, it is recommended that a disconnection or isolation switch is installed in order to totally isolate a unit if needed.
Fig. 4.9.1-1 Power wiring of RPA Parallel System
1
=
Rectifier
2
=
Inverter
3
=
Automatic Bypass
4
=
Manual Bypass
5
=
Input Utility Distribution
6
=
Unit Output Load
7
=
External Battery MCB
8
=
External Battery
9
=
Common bus bar and Output Load Distribution
=
UPS number 1
=
UPS number 2
=
UPS number 3
=
UPS number 4
=
UPS number 5
=
UPS number 6

4.9 RPA PARALLEL SYSTEM CONNECTION

4.9.1 Power wiring of parallel units

To guarantee good Load sharing between the units of a Parallel System, we recommend that the cable length from the input distribution board (5) to the output distribution board (9) is equal for each unit (a+b = c+d = e+f = g+h = i+l = m+n = o+p = q+r). Tolerance: +/-10%.
The AC input power of the Bypass must be the same for all units of the Parallel System - no phase shift allowed between units.
Verify that power wiring and control wiring run in separate conduits or cable trays. The power wiring requires two separate conduits: one for input and one for output cables.
Page 43
Critical Power
Modifications reserved
Page 43/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
Under no circumstance should the control bus cable connecting J1A - J2A (1/2/3/4/5) and J1B - J2B (1/2/3/4/5) be connected or disconnected after the system has been powered On.
Fig. 4.9.2-1 RPA System - Control bus connection
J2
J1
J2
J1
A
B
J1B/1
J1A/1
J2
J1
J2
J1
A
B
J1B/1
J1A/2÷5
J1A/1
J1B/2÷5
J1A/1 + J1B/1
J2
J1
J2
J1
A
B
J1A/5
J1A/5 + J1B/5
J1A/5
UPS 1
UPS 2/3/4/5
UPS 6
TLES_160-400_S1_RPA-IM0222_01IT

4.9.2 Parallel control bus connection

In case of Parallel System, the communication between the units takes place through the Control Bus Cables.
Each Parallel Unit contains the two boards P13/P14 IM0022 Bus Interface Board (mounted on top of the board P12 IM0196 RPA Board) on which four connectors J1A - J2A and J1B - J2B are allocated. All the parallel units are connected to the same control bus.
This connection allows:
The microprocessors of each unit to communicate with each other. The oscillators of each unit to be locked together. The regulation loops to compare the output current of each unit in order to equally share the Load
current.
For increased reliability, this connection is made with redundant cables. In this way, communication is maintained between units in case one of the control cables should fail or be accidentally damaged or disconnected.
The standard length of the control bus cable between two parallel units is 40 ft / 12m. The maximal overall length of bus connection, between the first and the last unit, should not exceed 295 ft / 90m. Verify that control wiring run in an individual separate steel conduit.
It is important to place the units in sequence of their assigned number. A unit number from 1 to 6 is defined by the setting of parameters and displayed on the panel (1 to 6). This number is also marked inside and outside the packaging.
Page 44
Critical Power
Modifications reserved
Page 44/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.9.2-2 Bus connection on first and last units
Final units, first and last, of a RPA Parallel System
On the two boards P13/P14 – IM0022 Bus Interface Board, of the first and last units of a Parallel System, the switches SW1-1/2/3/4/5/6 MUST BE IN POSITION ON (see Fig. 4.9.2-2).
Fig. 4.9.2-3 Bus connection on intermediate units
Intermediate units of a RPA Parallel System
On the two boards P13/P14 – IM0022 Bus Interface Board, of the intermediate units of a Parallel System, the switches SW1-1/2/3/4/5/6 MUST BE IN POSITION OFF (see Fig. 4.9.2-3).
J2
J1
J2
J1
A
B
J1B/1
J1A/1
1
2
3
SW1
4
5
6
ON
TLES_160-400_S1_RPA-IM0222_02
J2
J1
J2
J1
A
B
J1B/1
J1A/2÷5
J1A/1
J1B/2÷5
1
2
3
4
5
6
ON
SW1
TLES_160-400_S1_RPA-IM0222_03
Page 45
Critical Power
Modifications reserved
Page 45/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING !
This installation must be verified by trained personnel before the initial start-up. ENSURE THAT THE UPS INSTALLATION IS COMPLETELY POWERED DOWN.
Fig. 4.9.3-1 TLE Series 400 & 500
View electronic module on intermediate unit
Fig. 4.9.3-2 TLE Series 400 & 500
View electronic module on intermediate unit
Access to the control bus connection
The communication bus cable connectors are placed on the two boards “P13/P14 – IM0022 Bus Interface Board (see Fig. 4.9.3-1 and 4.9.3-2).
Fig. 4.9.3-3 View electronic module on intermediate unit
Control bus cables connection
Plug the cables J1A – J2A (1/2/3/4/5) and J1B –
J2B (1/2/3/4/5) on the connectors J1A – J2A and J1B – J2B placed on the two boards “P13/P14 – IM0022 – Bus Interface Board”.
Fix the communication bus cables J1A – J2A
(1/2/3/4/5) and J1B – J2B (1/2/3/4/5) with the provided cable clamps “A”.
TLES_UL_225-250_S1_RPA connection_01
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO EPO
-
+
TLES_320-400_S1_RPA connectionE_01
12
EPO
EPO
-
+
0 Off
I ON
0 Off
I ON
Q1
Q2
J2
J1
J2
J1
A
B
J1B/1
J1A/2÷5
J1A/1
J1B/2÷5
-
+
EPO
EPO
TLES_160-400_S1_RPA connection_02

4.9.3 Control bus cable location

Page 46
Critical Power
Modifications reserved
Page 46/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 4.9.3-4 TLE Series 225 & 250 - Control Bus cable routing and connection
Fig. 4.9.3-5 TLE Series 400 & 500 - Control Bus cable routing and connection
Control bus cables routing
Place and fix the cables J1A – J2A (1/2/3/4/5) and J1B – J2B (1/2/3/4/5) inside the UPS cabinets in the position illustrated in the drawing Fig. 4.9.3-4 and 4.9.3-5.
NOTE !
Pay attention when cabling and routing the communication bus cables J1A – J2A (1/2/3/4/5) and J1B J2B (1/2/3/4/5) inside the UPS cabinet.
In case one unit must be removed from the Parallel System, the communication bus cables must be taken out the UPS cabinet WITHOUT DISCONNECTING THEM from the two boards P13/P14 IM0022 Bus Interface Board.
For reliability reasons the cables J1A – J2A (1/2/3/4/5) and J1B – J2B (1/2/3/4/5) connecting the units should be run in separated protected conduits (as indicated in Fig. 4.9.3-3) separated from the power cables.
It is important that the cable J1A – J2A (1/2/3/4/5) must be the same length as cable J1B – J2B (1/2/3/4/5).
WARNING !
Connection and commissioning of an additional UPS to an existing Parallel System must be performed by a service engineer from of your Service Center.
TLES_UL_225-250_S1_RPA connection_03US
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO EPO
-
+
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
EPO
EPO
-
+
J1B/1
J1A/1
UPS 1
J2
J1
J2
J1
A
B
J1B/1
J1A/2÷5
J1A/1
J1B/2÷5
UPS 2/3/4/5
J2
J1
J2
J1
A
B
J1B/1
J1A/1
UPS 1
J1A/2÷5
UPS 3, 4, 5, 6
J1B/2÷5
UPS 2
UPS 3, 4, 5, 6
J1B/2÷5
J1A/2÷5
J2
J1
J2
J1
A
B
J1B/1
J1A/2÷5
J1A/1
J1B/2÷5
UPS 2/3/4/5
J1B/1
J1A/1
J2
J1
J2
J1
A
B
J1B/1
J1A/1
UPS 1
UPS 1
TLES_UL_400-500_S1_RPA connection_03US
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
-
+
UPS 2
Page 47
Critical Power
Modifications reserved
Page 47/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
WARNING !
The connection of an emergency button EPO (Emergency Power Off) must be performed by QUALIFIED SERVICE P E RSONNEL only when the UPS is COMPLETELY POWERED DOWN.
BE AWARE !
The reliability of the system depends on this contact NC (Normally Closed)!
An Emergency button (Normally Closed voltage-free contact) can be connected on terminals XA / EPO-1, EPO-2. Max. rating XA terminals: 2.5mm2.
Fig. 4.10-1 XA terminal block for EPO command connection
When opened, this contact causes the immediate opening of the Contactors K6 and K7 as well as the shut-down of Rectifier, Inverter and Static- Switch.
NOTE !
This procedure could imply a Load shut-down.
NOTE !
To operationalize this function, in case that the UPS was provided with one or more cards “P4 - Customer Interface”, there must be on each card the following:
- Remove the cable short-circuiting terminals X2 / 1, 2 (see Fig. 4.10-2).
- Remove the Jumper JP2 (see Fig. 4.10-2).
Fig. 4.10-2 X2 terminal block and Jumper JP2 on the P4 – Customer Interface Board
In case of a Parallel System press the key “O” (Inverter OFF) on the Control Panel of each unit connected on the Parallel Bus and having its output switch Q1 closed.
SGSE_400-500_S3_Customer interface-XA_01
Customer Interface
1
12
13
14
15
16
17
18
19
20
21
22
2
3
4
5
6
7
8
9
10
11
XA
EPO
EPO
+
-
TLES_UL_400-500_S1_Terminals XA_01
XA
EPO
EPO
+
-
24 Vdc for External (UVR) Battery Breaker
X2
10
9
8
21
19
20
22
11
SGSE_600_S1_Customer interface-X2 EPO_01
SNMP card
14
13
12
2
1
7
6
5
16
15
4
3
18
17
X1
X2
J1
JP2
1 2
8
19 21 2220
10 119
17 181615
7654
12 1413
321
X1
X2
J1
SE_400-500_S1_Customer interface-JP2_01

4.10 EPO COMMAND CONNECTION (EMERGENCY POWER OFF)

When the EPO has been activated, the system must be restored as follows:
Realize the push-button EPO (contact on XA / EPO-1, EPO-2 is closed again). Press the key Inverter OFF on the Control Panel (see User Manual to Section 6.5).
Page 48
Critical Power
Modifications reserved
Page 48/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 5-1 Connectivity rack and Serial port J35µP – RS232
TLE Series 225 - 500 has the following equipment‟s:
- Serial Port J35µP - RS232 (see Section 5.1).
- Connectivity rack ready for the installation of four connectivity boards [max. two boards
“Customer Interface” (see Section 5.2) and max. two boards 3-ph SNMP/WEB Plug-in Adapter” as described in the picture below].
Possible connectivity configurations with TLE Series 225 - 500
Fig. 5-2 Connectivity rack
Slot J2
2nd 3-ph SNMP/WEB plug-in adapter (option)
Slot J3
1st 3-ph SNMP/WEB plug-in adapter (option)
Slot J4
1st Customer Interface board (standard)
Slot J5
2nd Customer Interface board (option)
ATTENTION !
The installation of any option board must be performed by QUALIFIED SERVICE PERSONNEL.
Prior to the installation, connection and cabling of any option board the UPS must be COMPLETELY POWERED DOWN and all the power sources that will be connected to the option board must be DE-ENERGIZED.
Option board shall be connected only to Safety Extra Low Voltage circuits (SELV for IEC-UL-CSA60950-1): voltage up to 30Vac / 42.4Vpk or 60Vdc maximum and galvanically separated from AC Utility supply.
J35µP - RS232
Connectivity rack
TLE Series 225 & 250
1 2
TLES_UL_225-500_S1_UPS connectivity_01
TLE Series 400 & 500
TLES_UL_225-250_S1_UPS connectivity_01
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
-
+
J35µP - RS232
Connectivity rack
Q1
I ON
0 OFF
Q2
I ON
0 OFF
12
-
+
J35µP - RS232
Connectivity rack
SGS_600_S2_Connectivity rack_01
SNMP card
J3
J2
J5
J4
16
15
4
19
18
17
20
9
8
7
6
5
14
13
12
3
2
1
22
11
21
10

5 CUSTOMER INTERFACE

Page 49
Critical Power
Modifications reserved
Page 49/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 5.1-1 Serial Port J35µP – RS232
Serial Port J35µP - RS232 for IMV protocol
Total remote management of the system using software GE
iUPSGuard, GE Data Protection or GE Service Software for system
protection and management of the UPS systems.
Connection of a serial printer
From the display panel it is possible to select printing of measurements, alarms and parameters (see User Manual to Section 6.4 – SETUP / PRINTER).
Fig. 5.1-2 Serial port J35µP connection to PC with RS232 1:1 cable
DB9m – DB9f
The serial port J35µP - RS232 is enabled on all the units of the RPA Parallel System.
Fig. 5.1-3 Connector J1 – RJ45 8P8C
NOTE !
The serial port J35µP - RS232 is enabled also in case the J1-
RJ45 connector of the “P4 ­Customer Interface” (see
Section 5.2.1) is already connected.
TLES_UL_400-500_S1_UPS-J35_01
Q1
12
I ON
0 OFF
Q2
I ON
0 OFF
EPO
EPO
-
+
J35µP - RS232
J35µP - RS232
J1 - RJ45
SGSE_400-500_S3_Customer interface-J1-RJ45_01
20
1
2
3
12
13
14
4
17
15
16
18
19
5
6
7
8
9
21
22
10
11
SNMP card

5.1 SERIAL PORT J35µP - RS232 (SUB D, FEMALE 9 PIN)

Page 50
Critical Power
Modifications reserved
Page 50/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 5.2-1 Customer Interface Board
J1 connector– RJ45 8P8C (see Section 5.2.1)
Pin 5: TX (out)
Pin 6: RX (in)
Pin 4: GND
X1 terminal block – Output signals on voltage free contacts (see Section 5.2.2)
X1 / 1, 2, 3
NO, C, NC
UTILITY FAILURE
(def. Parameter RL=1)
X1 / 4, 5, 6
NO, C, NC
LOAD ON INVERTER
(def. Parameter RL=3)
X1 / 7, 8, 9
NO, C, NC
STOP OPERATION
(def. Parameter RL=5)
X1 / 12, 13, 14
NO, C, NC
LOAD ON UTILITY
(def. Parameter RL=2)
X1 / 15, 16, 17
NO, C, NC
GENERAL ALARM
(def. Parameter RL=4)
X1 / 18, 19, 20
NO, C, NC
BUZZER (acoustic alarm)
(def. Parameter RL=6)
The programmable signals on X1 will be disabled with Q1 open, with the exception of the signals for “16 - MANUAL BYPASS ON and “26 – EMERGENCY
OFF (EPO)”.
X1 terminal block – Input contacts (see Section 5.2.3)
X1 / 10, 21
NO
Programmable
X1 / 11, 22
NO
Programmable / GENERATOR ON
X2 terminal block –EPO -Emergency Power Off connection (see Section 5.2.4)
X2 / 1, 2
NC
EPO (Emergency Power Off)
Note: to enable this function, remove the Jumper JP2 on “P4 – Customer
Interface board (see Section 5.2.4).
NO = Normally Open
C = Common
NC = Normally Closed
Output signals on voltage-free contacts
Programmable functions on input contacts
On terminals X1, 6 of the following 27 signals can be selected from the display, entering with the appropriate password.
Some UPS functions can be activated with parameters when an external Normally Open (NO) contact is closed on:
X1/10, 21 or X1/11, 22
Selectable functions by changing parameters (password required) are:
0 - NO FUNCTION 1 - INVERTER ON 2 - INVERTER OFF 3 – PRINT ALL 4 - STATUS RELAY 5 - GENERATOR ON 6 - EXTERNAL BYPASS 7 - BATTERY FUSES OR EXTERNAL K3
(See Alarm 4104 - Battery Fuses)
8 - eBoost/IEMi CONTROL
Voltage free contacts:
Max. 24Vac / 1A or 60Vdc / 0,5A IEC-UL-CSA 60950-1 (SELV circuit) Min. Signal Level: 5Vdc / 5mA
0- NO SIGNAL
1- BUZZER
2- GENERAL ALARM
3- LOAD ON UTILITY
4- STOP OPERATION
5- LOAD ON INVERTER
6- UTILITY FAILURE
7- DC OVERVOLTAGE
8- LOW BATTERY
9- OVERLOAD
10- OVERTEMPERATURE
11- INVERTER-BYPASS NOT SYNCHR.
12- BYPASS LOCKED
13- BYPASS UTILITY FAILURE
14- RECTIFIER UTILITY FAILURE
15- BATTERY DISCHARGE
16- MANUAL BYPASS ON
17- RECTIFIER ON
18- INVERTER ON
19- BOOST CHARGE
20- BATTERY EARTH FAULT
21- BATTERY FAULT
22- RELAY INPUT 1
23- RELAY INPUT 2
24- RELAY OUTPUT ON
25- RELAY OUTPUT OFF
26- EMERGENCY OFF (EPO)
27- eBoost/IEMi MODE
1 2
8
19 21 2220
10 119
17 181615
7654
12 1413
321
X1
X2
J1
SGSE_400-500_S1_Customer interface_01

5.2 CUSTOMER INTERFACE BOARD

Page 51
Critical Power
Modifications reserved
Page 51/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Fig. 5.2.1-1 Connector J1 – RJ45 8P8C
Total remote management of the system using software GE iUPSGuard, GE Data Protection or GE Service Software for system protection and management of the UPS systems.
Fig. 5.2.1-2 RJ45 –RS232 adaptation cable
TLE Series 225 - 500 is supplied with an adaptation cable for a serial port RS232 / sub DB9 connection.
Fig. 5.2.1-3 Connector J1 to PC with RJ45 –RS232 adaptation cable
The connector J1 – RJ45 is enabled on all the units of the Parallel System.
X1 / 1, 2, 3
(NO, C, NC)
UTILITY FAILURE
(def. Parameter RL=1)
X1 / 4, 5, 6
(NO, C, NC)
LOAD ON INVERTER
(def. Parameter RL=3)
X1 / 7, 8, 9
(NO, C, NC)
STOP OPERATION
(def. Parameter RL=5)
X1 / 12, 13, 14
(NO, C, NC)
LOAD ON UTILITY
(def. Parameter RL=2)
X1 / 15, 16, 17
(NO, C, NC)
GENERAL ALARM
(def. Parameter RL=4)
X1 / 18, 19, 20
(NO, C, NC)
BUZZER (ACOUSTIC ALARM)
(def. Parameter RL=6)
NOTE !
The programmable signals on X1 will be disabled with Q1 open, with the exception of the signals for “16 - MANUAL BYPASS ON and “26 – EMERGENCY ON (EPO).
X1 / 10, 21 User Input 1 (default = Not used) X1 / 11, 22 User Input 2 (default = GENERATOR ON)
J1 - RJ45
SGSE_400-500_S3_Customer interface-J1-RJ45_01
20
1
2
3
12
13
14
4
17
15
16
18
19
5
6
7
8
9
21
22
10
11
SNMP card
6
9
1
5
2 3 4
7 8
CNT_Cable RJ45-RS232_01
8
1
J1 - RJ45
J1 - RS232

5.2.1 Connector J1 – RJ45 8P8C

5.2.2 X1 terminal block - Output signals on voltage-free contacts

The Customer Interface board provides 6 voltage free relay contacts giving some UPS critical alarms and operation mode. These signals are available on terminal blocks X1. Max. rating terminals: 1mm2.
The meaning of the alarms on the free contacts in standard configuration (default) is the following:
In case different alarms or operating status are required, they can be configured on the same terminals via software from the control panel. The configuration can be changed in parameters mode by a trained operator using the appropriate password.

5.2.3 X1 terminal block - Programmable input free contacts

Some programmable UPS functions (indicated in Section 9.2), can be activated by closing an external contact, if connected, on:
Page 52
Critical Power
Modifications reserved
Page 52/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
NOTE !
If an emergency button EPO (Emergency Power Off) is installed, the use of the XA terminals is recommended (see Section 5.10).
Fig. 5.2.4-1 X2 terminals in the P4 – Customer Interface
Fig. 5.2.4-2 Jumper JP2 on the P4 – Customer Interface
NOTE !
To activate the connection of an emergency button EPO (Emergency Power Off) on the terminals XA / EPO-1, EPO-2, performed on each card “P4 – Customer Interface” the following operation:
- Remove the cable short-circuiting terminals X2 / 1, 2 (see Fig. 5.2-4-1).
- Remove the Jumper JP2 (see Fig. 5.2-4-2).
In a Parallel System a separate NO (Normally Open) contact must be connected to each individual unit.
X2
10
9
8
21
19
20
22
11
SGSE_600_S1_Customer interface-X2 EPO_01
SNMP card
14
13
12
2
1
7
6
5
16
15
4
3
18
17
X1
X2
J1
JP2
1 2
8
19 21 2220
10 119
17 181615
7654
12 1413
321
X1
X2
J1
SE_400-500_S1_Customer interface-JP2_01

5.2.4 X2 terminal block - EPO (Emergency Power Off)

5.2.5 X1 terminal block - Gen Set Signalling (GEN ON)

If an emergency generator set supplies the UPS in case of Utility Failure and the generator is considerably unstable in frequency, it should be suitable to install the signal GENERATOR ON on X1 / 11, 22. See Fig. 5.2-1 / X1.
Since the Parameter for of the reading of the Generator function is password protected, call the nearest Service Center for it's activation.
When this contact closes, it changes certain (programmable) functions such as:
Enabling or disabling of synchronization and consequently the Load transfer to generator. Reduction or elimination or delay of Battery recharging during the generator operation.
Additionally, when the GENERATOR ON input contact is closed, the UPS will inhibit eBoost™ Operation Mode and revert to double-conversion operation.
It is advised to contact your Service Center for further details.
Page 53
Critical Power
Modifications reserved
Page 53/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
In a Parallel System, the input on the Customer Interface of each unit must be connected to a separate AUX contact of the External Maintenance Bypass Switch.
When using the “eBoost/IEMi control” function on the programmable user relays of
the Customer Interface X1 terminals in a Parallel System, a separate NO (Normally Open) contact must be connected to each individual unit.

5.2.6 X1 terminal block - AUX external Maintenance Bypass

If the UPS system is equipped with an external Maintenance Bypass Switch, it is possible to connect a NO (Normally Open) voltage-free aux. contact from the External Bypass Switch to the programmable input X1 / 10, 21, making the UPS operate as if the internal switch Q2 has closed.
This function can be activated by changing a dedicated parameter (password required).
When this NO (Normally Open) contact closes, the output Inverter Contactor K7 it is automatically opened and the Load transfer back to Inverter will be inhibited.

5.2.7 X1 terminal block - eBoost/IEMi control signal

The UPS operation in either eBoost or IEMi operating modes can be controlled via an NO (Normally Open)
contact by installing the “eBoost/IEMi CONTROL” signal, routed to the programmable function contacts
(see Section 5.2.3).
When this contact closes, eBoost or IEMi operation mode is inhibited. The Parameter for the activation of such function is password protected. Call the nearest Service Center for its activation.
This function is particularly useful for controlling eBoost or IEMi operation following critical conditions on
either the load side or the input utility, including generator operation when the “GENERATOR ON” signal
has not been installed.
Page 54
Critical Power
Modifications reserved
Page 54/54
GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx
Installation Guide TLE Series 225 - 500 UL S1
Date
Description
Done by

6 NOTES

6.1 NOTES FORM

It is recommended to note in this section Notes, with date and short description all the operations performed on the UPS, as: maintenance, components replacement, abnormal situations, etc.
Loading...