EFCO 5800 User Manual

Page 1
8
Y
Series 5
00
E-wall silicone gasket curtain wall system
Installation instructions
February 2013
330
Page 2
Minimizing Condensation
Note: Please reference EFCO's "Understanding Condensation" brochure which can be obtained through your EFCO representative. Condensation will form on any surface when unfavorable conditions (interiro temperature and relative humidity and exterior temperature) are present. When the formation of extensive condensation is a concern, it is highly recommended that a design professional is utilized to perform an analysis of the shop drawings to recommend the best possible installation methods. Please contact your EFCO representative for information on EFCO's Thermal Analysis Serv ices. Many current installation practices lead to an increase in the possibility of the formation of condensation. Though not all inclusive, the list of examples below illustrates conditions under which condensation is lik ely to occur:
1. Bridging system thermal break with non-thermally broken metal flashing or lintels that are exposed to the exterior
2. System exposure to the cold air cavities
3. Interior relative humidity levels not maintained at recommended levels, see EFCO's
"Understanding Condensation" brochure
4. Inadequate separation between system and surrounding condition at perimeter
5. Product conbinations during the shop drawing stage that result in bridging thermal
breaks of one or all products involved
7/2011
Page 3
SECTION I: GENERAL NOTES AND GUIDELINES
PAGE 1
NOTE:
THESE INSTALLATION INSTRUCTIONS ARE A SUPPLEMENT TO THE APPROVED SHOP DRAWINGS AND MUST BE USED IN CONJUNCTION WITH THOSE DRAWINGS.
1.
HANDLING/STORING/PROTECTING ALUMINUM - The following precautions are recommended to assure early acceptance of your products and workmanship.
A. HANDLE CAREFULLY - Store with adequate separation between com-
ponents so material will not become scratched or rubbed at points of contact. Store off the ground. Protect against weather elements and other construction trades in adjacent areas of the job site.
B. KEEP MATERIAL AWAY FROM WATER, MUD, AND SPRAY - Prevent cement,
plaster, and other materials from coming in contact with and damaging the finish. Do not allow moisture to be trapped between the finished surface and the wrapping material.
C. PROTECT MATERIALS AFTER ERECTION - Wrap or erect screens of plastic
sheeting. Cement, plaster, terrazzo, and other alkaline materials are very harmful to the finish and must be removed with water and mild soap before hardening. Under no circumstances should these materials be allowed to dry or permanent staining will occur.
GENERAL GUIDELINES - The following practices are recommended for all
2.
installations.
A. REVIEW THE APPROVED SHOP DRAWINGS to become thoroughly familiar
with the project.
B. INSTALL ALL FRAMING MATERIALS PLUMB, LEVEL, AND TRUE - Proper
alignment and relationships to benchmarks and column center lines, as established by the architectural drawings and the general contractor, must be maintained.
C. The sequence of erection should be coordinated with the project
superintendent to prevent delays and minimize the risk of material damage. IF PRESET ANCHORS ARE REQUIRED, COORDINATE
WITH THE GENERAL CONTRACTOR AND SUPERVISE THE LOCATION.
9/2000
Page 4
PAGE 2
SECTION I: GENERAL NOTES AND GUIDELINES CONT.
D. Verify that all job site conditions and accompanying substrates
receiving the installation are in accordance with the contract documents. If deviations occur, notification must be given IN WRITING to the general contractor and differences resolved before proceeding further with the installation in the questionable area.
E. Coat all aluminum, to be placed directly in contact with masonry or
dissimilar materials, with a heavy coating of bituminous primer such as zinc chromate.
F. Follow EFCO’s framing installation and glazing instructions.
G. Verify the contents of all material shipments upon arrival. Verify
quantities and correct finishes. NOTIFY EFCO IMMEDIATELY OF ANY DISCREPANCIES OR DAMAGE WHICH MAY HAVE OCCURRED.
H. Throughout these instructions the term SEALANT will appear. For the
purpose of these instructions, sealant is to be defined as follows:
SEALANT - A weather resistant, gunnable, liquid filler which when dry
provides a resilient, flexible air and water seal between similar and dissimilar materials. All sealant must meet FEDERAL SPECIFICATIONS TT-S-001543A, TT-S-00230C, and ASTM C 290.
NOTE:
Do not assume compatibility of materials in a glazing system already exists. Chemical reactions from physical contact of incompatible materials can adversely affect one or all of the glass or glazing materials. It is strongly advised that sealant manufacturers conduct compatibility and adhesion tests in their laboratories using each exact component of the glazing system (i.e., glass product, structural silicone, aluminum with painted or anodized finish, setting blocks, glazing tapes, etc.) and document compatibility or other findings in written test reports. All frame surfaces should be clean, dry, dust free, and frost free. If a primer is required, it must be applied to clean surfaces. All perimeter substrate should be cleaned and properly treated to receive sealant. It is the responsibility of the installer to follow these guidelines.
TOOLS NEEDED:
1. Dead blow hammer, part #HM46
2. Deglazing tool, part #HM47
3. Brush
4. Cutting tool, do not use box or craft knives.
5. Needle nose pliers
6. Metal spatula
7/2003
Page 5
SECTION II: VERTICAL FRAME INSTALLATION
STEP #1 INSTALL VERTICAL MULLIONS AND ANCHORS Prestage necessary tools and materials in the work area. Prepare all head,
sill, and jamb substrates by cleaning and setting all flashings and/or membrane seals as specified by the project shop drawings. Insert the mullion and/or head anchor, as specified by the project shop drawings, into the end of tubular mullions. For splice joints and floor anchors at multispan conditions, refer to steps #2 and #3 on pages 4 and 5.
PAGE 3
Note: When attaching pocket fillers, start at one end and work into place along the remaining length.
PERIMETER WITH CONTINUOUS POCKET FILLER
"F" ANCHOR
MULLION ANCHORS
TOP ANCHOR IS REQUIRED AT HEAD CONNECTION FOR THERMAL MOVEMENT.
MULL ANCHOR AT INTERMEDIATE VERTICAL MULLIONS.
SIZE AND LOCATE ALL BOLTS BASED ON JOB CONDITIONS AND STRUCTURAL REQUIREMENTS.
SEE APPROVED SHOP DRAWINGS FOR DIMENSION.
SHIM UNDER VERTICAL MULLION.
7/2003
Page 6
SECTION II: VERTICAL FRAME INSTALLATION
STEP #2 APPLY MIDSPAN FLOOR ANCHORS Attach the midspan floor anchors to the mullions with temporary alignment
screws. Set the vertical mullion in place, plumb and true. Make permanent attachment of base anchors, head anchors, and midspan floor anchors to the building structure as specified in the approved project shop drawings. After completing permanent anchorage, remove all temporary alignment screws and fasteners. Multiple runs of vertical mullions can be set in advance of erecting the horizontal members if desired, or the horizontals can be filled in as additional mullions are erected.
NOTE: On long runs, check overall frame dimensions at every fifth opening to avoid dimensional build-up.
POSITION THE MULLION PLUMB AND TRUE. PERMANENTLY ATTACH THE ANCHOR TO THE STRUCTURE PER PROJECT SHOP DRAWINGS.
1"
MIN.
TEMPORARY ALIGNMENT SCREW (REMOVE AFTER ANCHORING).
PAGE 4
DEAD LOAD ANCHOR
BOLTED TO STRUCTURE
THE FLOOR SLABS MUST BE WITHIN THE ADJUSTMENT CAPABILITY OF THE ANCHORING
SYSTEM. REFER TO THE PROJECT SHOP DRAWINGS FOR THE ALLOWABLE ADJUSTMENT.
DRILL THROUGH THE MULLION AT THE HOLE LOCATION IN THE CLIP A MINIMUM OF 1" FROM THE BACK OF THE MULLION. COMPLETE THE BOLT CONNECTION PER PROJECT SHOP DRAWINGS.
NOTE: REFER TO PROJECT SHOP DRAWINGS FOR WELDING INSTRUCTIONS. PROTECT THE INSTALLED GLASS AND METAL FROM WELD SPLATTER.
DEAD LOAD ANCHOR
WELDED TO STRUCTURE
WIND LOAD ANCHOR
BOLTED TO STRUCTURE
NOTE: USE 1/16" HORSE­SHOE SHIMS BETWEEN
THE STEEL ANCHORS AND MULLIONS.
FILLET WELD AT BOTH SIDES OF
THE ANCHOR.
WIND LOAD ANCHOR
WELDED TO STRUCTURE
9/2000
Page 7
PAGE 5
SECTION II: VERTICAL FRAME INSTALLATION CONT.
STEP #3 INSTALL VERTICAL SPLICE JOINTS Splice joints should occur at spandrel areas (if possible).
Refer to approved shop drawings for actual locations. Splice sleeves will be shop assembled in the top of the lower mullion. GENERAL NOTE: The following details depicts a splice joint of 1/2".
The required joint width must be determined at the design stage and shown on the approved shop drawings, on a job by job basis. The actual width of this joint depends on the expected amount of thermal movement plus the expected movement of the building structure.
Once a final check of expansion joint placement and mullion position is made, the final match drilling of mullion through anchor holes and sealing of the splice joint may be completed.
1
2
UPPER MULLION
SPLICE SLEEVE
SLEEVE FASTENERS
SHIM UNTIL ALL ANCHORS ARE SET IN PLACE, THEN FACE SEAL WITH AN APPROVED SEALANT.
1/2"
SHIM
3
LOWER MULLION
7/2003
Page 8
SECTION III: HORIZONTAL FRAME INSTALLATION
STEP #1 PLUG ENDS OF PERIMETER HORIZONTALS Prior to horizontal attachment, insert a 2 1/2" piece of backer rod folded to
90 degree into the jamb end of the head and sill horizontals. Seal the ends with silicone to create an end plug. The end plug will act as a back-up for the perimeter seal later.
STEP #2 PERIMETER HORIZONTALS Clean all mating surfaces and apply a thin film of specified sealant
to the factory notched vertical mullion, at the horizontal locations. Attach the appropriate horizontal member to the vertical mullion at the notch with (2) Stalgard , #10-16 x 3/4", PL-PH-SMS, Tek/2, self drilling fasteners through the predrilled holes in the ends of each horizontal. Confirm the mullion center line dimension at each horizontal installation before and after fastening the horizontal into place. Verify the mullion locations at every fifth mullion spacing to avoid dimensional build-up across the opening.
R
PAGE 6
CUT AND FOLD THE BACKER ROD 90 DEG.
Note: Prior to sealing any area, clean the surface with denatured alcohol.
INSERT THE BACKER ROD 1/4" INSIDE THE EXTRUSION.
ONCE THE HORIZONTALS ARE INSTALLED, INSERT BACKER ROD INTO THE HOLE AND SEAL THE HOLE FLUSH WITH SILICONE.
APPLY A THIN LAYER OF SPECIFIED SEALANT TO THE ENTIRE FACE OF THE COPED MULLION. APPLY SEALANT TO THE ENDS OF THE MULLION AT THE PERIMETER HEAD AND SILL HORIZONTAL MEMBERS ONLY.
SEAL OVER THE END AND TOOL FLUSH WITH THE EDGE OF THE EXTRUSION.
7/2003
Page 9
PAGE 7
SECTION III: HORIZONTAL FRAME INSTALLATION CONT.
STEP #3 INTERMEDIATE HORIZONTALS Attach the appropriate horizontal member to the vertical mullion at the notch
with (2) Stalgard, #10-16 x 3/4", PL-PH-SMS, Tek/2, self drilling fasteners through predrilled holes in the ends of each horizontal member. Confirm the mullion center line to center line dimension at each horizontal installation before and after fastening the horizontal in place. Verify the mullion locations at every fifth mullion spacing to avoid dimensional build-up across the opening.
SEALANT IS NOT REQUIRED AT INTERMEDIATE HORIZONTAL TO VERTICAL CONNECTIONS.
9/2000
Page 10
SECTION IV: CONDENSATION WICK INSTALLATION
STEP #1 INSTALL CONDENSATION WICK To install the condensation wick into the horizontal, first cut the wick
approximately 3" longer than the center line dimension of the vertical mullions. Locate the approximate center of the condensation wick and the center of the horizontal. Using the deglazing tool, press about 6" of the condensation wick into the wick pocket, leaving each end free. Using a needle nose pliers, insert about 1 1/2" of each end of the condensation wick into the hole provided in each vertical mullion. Starting at the middle of the horizontal and working toward the verticals, press the remaining condensation wick into the horizontal pocket. Continue this process until all the slack has been removed and the ends extend freely into the vertical mullion cavity.
PAGE 8
INSERT APPROXIMATELY 1 1/2" OF EACH END OF THE CONDENSATION WICK INTO THE HOLE IN THE VERTICAL MULLIONS.
CONDENSATION WICK
Note: To facilitate insertion of the condensation wick into the vertical, burn each end of the wick and insert with needle nose pliers.
HOLE IN MULLION
9/2000
Page 11
SECTION V: GLAZING ADAPTOR INSTALLATION
STEP #1 INSTALL GLAZING ADAPTORS Locate and insert the glazing adaptors for openings that have a glazing
thickness of less than 1". Horizontal adaptors run through and must be inserted first at the top and bottom of each light. Horizontal adaptors are cut shorter than the opening dimension. Locate and insert the adaptor in the center of the space provided, allowing equal distance between each end. The vertical adaptors may now be installed between the horizontal adaptors.
PAGE 9
VERTICAL GLAZING ADAPTOR
HORIZONTAL GLAZING ADAPTOR
HORIZONTAL ADAPTORS RUN THROUGH.
7/2003
Page 12
SECTION VI: INTERIOR GASKET INSTALLATION
STEP #1 INSTALL HORIZONTAL GASKET Cut the specified interior horizontal gasket 1 3/4" longer than the daylight
opening width. Center the gasket on the horizontal member and press straight into the gasket pocket.
STEP #2 INSTALL VERTICAL GASKET Cut the interior vertical gasket 1/8" longer than the daylight opening. Center
the gasket on the vertical opening and press straight into the gasket pocket. Allow the horizontal gasket to run through. Butt the vertical gasket to the horizontal gasket at the open corners. Crowd in any excess gasket.
PAGE 10
VERTICAL GASKET
THE HORIZONTAL GASKET
RUNS THROUGH. THE
VERTICAL GASKET BUTTS TIGHT TO THE HORIZONTAL.
INTERIOR GASKET
9/2000
Page 13
SECTION VII: GLAZING INSTALLATION
STEP #1 INSTALL GLAZING MATERIALS Verify that all gasket retainer pockets are free from dirt and foreign
matter. Place the specified setting blocks and antiwalk blocks as shown in the approved project shop drawings. Set the specified glazing infill into the corresponding opening, ensuring positive bearing on the setting blocks and an equal glass bite at all sides of the infill panel. The typical glass bite should be 9/16" in a 2 1/2" wide system. Push the infill completely back against the interior gaskets.
POSITION THE ANTIWALK BLOCK AT THE CENTER OF THE VERTICAL GLASS OPENING. SILICONE THE
BLOCK INTO POSITION AFTER THE GLASS IS INSTALLED.
PAGE 11
POSITION THE SETTING BLOCK EVEN WITH THE FRONT OF THE MULLION TONGUE.
THE HORIZONTAL SETTING BLOCKS MUST BE POSITIONED AT 1/4 POINTS OR AS SPECIFIED IN THE PROJECT SHOP DRAWINGS.
9/2000
Page 14
SECTION VIII: EXTERIOR GASKET INSTALLATION
STEP #1 TEMPORARY GASKET INSTALLATION Depending on your sequence of installation, you may or may not want to
use temporary glazing retainers to hold the glass in place until the final gasket installation can be achieved. To allow for temporary installation, 12" long gasket retainers can be provided for your use. Temporary retainers should be positioned in the center of any glass edge that is less than 30" long and at quarter points for edges over 30".
STEP #2 PERMANENT GASKET INSTALLATION If, and when, permanent glazing is possible, remove the temporary glazing
retainers and insert permanent gaskets as specified in the following instruc­tions. Depending on weather conditions and considering public safety, it is recommended that the temporary glazing retainers only be used for short periods of time.
PAGE 12
12" LONG TEMPORARY GASKETS SHOULD BE USED FOR SHORT
PERIODS OF TIME ONLY.
TYPICAL GASKET INSTALLATION AT THE TIME OF FINAL GLAZING ASSEMBLY.
NOTE: Temporary retainers are intended for short term temporary applications only, and are not intended to be left unattended or overnight. (TEMPORARY
RETAINERS DO NOT MEET STRUCTURAL REQUIREMENTS AND CAN FAIL UNDER STRUCTURAL LOADS.)
NOTE: Temporary retainers are available from EFCO by request only and are not
included in the cost of the materials for the job.
9/2000
Page 15
PAGE 13
SECTION VIII: EXTERIOR GASKET INSTALLATION CONT.
STEP #3 GASKET INSTALLATION AND INSPECTION Select a formed corner gasket corresponding to the opening in process and
lubricate with the recommended gasket lubricant. Position the gasket to the opening and install the gasket corner darts into the retainer pockets at the top corners of the opening, using a #HM46 dead blow mallet (see illustration "A" on page #14). Care must be taken to strike the gasket flatly, with only as much force as required to set the gasket dart into the retainer pocket, (see below). Repeat the procedure at the bottom corners of the opening (see illustration "B" on page #14). Caution must be used to ensure that the gaskets are not overdriven into the gasket receiving pocket (see the illustrations below for proper installation of the exterior gasket).
NOTE: To facilitate the gasket installation, it is best to wet the gasket and the glass or panel.
YES
NO
GASKET CORRECTLY INSTALLED
NO
GASKET OVER INSTALLED
GASKET UNDER INSTALLED
NOTE: Inspect each gasket after installation. Do not allow the gasket lip to fold under itself. If this occurs, correct the lip placement by using a thin metal spatula or the back edge of a knife to reposition the gasket.
NOTE: The recommended gasket lubricant is: Summer Installation (40 deg. F plus):
Winter Installation (40 deg. F or less):
5% liquid soap and 95% water 5% liquid soap, 10% methylated
spirits, and 85% water
7/2003
Page 16
PAGE 14
SECTION VIII: EXTERIOR GASKET INSTALLATION CONT.
STEP #4 STEP BY STEP GASKET INSTALLATION Align the center of the linear sides of the gasket with the center line of the
opening. Use the #HM46 mallet to engage the gasket dart into the gasket retainer pocket at this half point. See illustration "B" below. Continue to in­stall the gasket by dividing the remaining loose gasket material in half and work it into the gasket retainer pocket. See illustration "C" below. Continue until the entire length of gasket is engaged in the retainer pocket at all sides. See illustration "D".
CENTER
CORNER INSTALLATION
INSTALLATION
C
L
A
C
STEP #5 FINAL GASKET INSPECTION
B
C
L
D
The gasket surface should be smooth when fully installed. Both a visual and "by feel" inspection of the gasket should be made to ensure that the dart is fully engaged in the retainer pocket continuously along the gasket length, including the corners. All corners should be pushed into alignment with other corners at the intersections of the vertical and horizontal members.
9/2000
Page 17
PAGE 15
SECTION VIII: EXTERIOR GASKET INSTALLATION CONT.
BEFORE ADJUSTMENT
INCORRECT
GASKETS DO NOT ALIGN PROPERLY.
AFTER ADJUSTMENT
CORRECT
ALL GASKET CORNERS LINE UP.
NOTE: Feel the gasket surface to ensure it is smooth and flat.
7/2003
Page 18
PAGE 16
SECTION VIII: EXTERIOR GASKET INSTALLATION CONT.
STEP #6 PERIMETER GASKET INSTALLATION At very large openings, a butt joint may be required to facilitate handling
and installation. A butt joint in the perimeter gasket will generally occur at center of daylight opening. Install the gasket at the opening corners per the typical gasket installation. Clean each gasket end. A factory cut end will be provided. Apply a small amount of specified silicone sealant to the full cross section of each end of the gasket to be jointed. Insert 2" to 3" of each gasket dart into the retainer pocket. Push the gasket ends together to engage the wet silicone sealant. The gasket should lay flat across the joint and all residue sealant should be removed from the gasket surface. Install the remainder of the gasket per the typical installation, taking care not to separate the gasket joints. Do not stretch the gaskets to make them fit.
FINISHED SPLICE JOINT
9/2000
Page 19
SECTION IX: PERIMETER SEAL INSTRUCTIONS
STEP #1 PERIMETER SEAL INSTRUCTIONS Insert the specified backer material into the perimeter joint and apply
perimeter sealant continuously to the prepared substrate and previously cleaned surface of the system framing. Professionally tool the sealant joint to verify that a continuous sealant contact is between the frame and substrate. Perimeter seals can be fully applied before or after the system is glazed.
BACKER ROD
SILICONE SEALANT
PAGE 17
JAMB DETAIL
POCKET FILLER
BACKER ROD
SILICONE SEALANT MUST MARRY WITH THE SILICONE GASKET EDGE.
VERTICAL MULLION
HEAD DETAIL
PERIMETER
HORIZONTAL
PERIMETER POCKET FILLER
SEAL
BETWEEN THE SYSTEM AND CONDITION.
SEAL
BETWEEN THE ADAPTOR AND
THE HORIZONTAL. SEAL THE GASKET
POCKET 1/2" FROM THE ENDS TO MATE WITH THE PERIMETER
SEAL.
FRONT VIEW JOINERY DETAIL AT SILL
*Joint detail similar at head.
7/2003
Page 20
SECTION X: DEGLAZING PROCEDURE
STEP #1 GASKET REMOVAL If the glazing must be removed, use the following procedure. Insert the
deglazing tool provided directly between the gasket intersection point, at the corner. Insert the point of the tool directly down until the point hits the back of the vertical gasket retainer pocket. Using a prying motion, rotate the point of the deglazing tool until the curved back portion seats against the gasket retainer pocket. This action will allow the point of the tool to press out against the back of the molded corner dart. Pry the tool toward the face of the glass until the corner dart pops out of the gasket retainer pocket. Using your free hand, hold the gasket back and away from the wall and reposition the tool under the continuous dart. Using the same prying motion, push the tool inward and pull gently outward on the gasket to facilitate removal.
NOTE: Always pull the gasket gently, directly out, and perpendicular to the plane of the wall. Never twist the gasket when pulling it out as this may
cause the material to tear or cut the gasket dart legs.
PAGE 18
A
A
POSITION THE DEGLAZING TOOL UNDER THE DART IN THE CORNER OF THE GASKET. DISENGAGE THE DART PRIOR TO REMOVING THE GASKET.
DEGLAZING TOOL PART #HM47
VIEW A-A
Stalgard is a registered trademark of Textron, Inc.
MOLDED CORNER DART
7/2003
Loading...