Eagle Electronics A100 User Manual

EAGLE
Installation, Operation and
Maintenance Instructions
Lubrication information is in Section III-A, Item 1b. and Section IV-A.
EAGLE MODEL A100
ANSI PUMPS
TABLE OF CONTENTS
SECTION I—GENERAL
Introduction .................................................................................................................................................................3
I-A Importance of Instructions ........................................................................................................................... 3
I-B Special Warnings .......................................................................................................................................... 3
I-C Receiving Inspection—Shortages................................................................................................................. 3
I-D Preservation and Storage.............................................................................................................................. 3
I-E Handling Techniques.................................................................................................................................... 3
SECTION II—INSTALLATION
II-A Location........................................................................................................................................................ 3
II-B Foundations .................................................................................................................................................. 3
II-C Leveling and Grouting of Baseplate ............................................................................................................. 4
II-D Piping Practices ............................................................................................................................................ 4
II-E Alignment—Preliminary .............................................................................................................................. 4
II-F Stuffing Box .................................................................................................................................................. 5
SECTION III—OPERATION
III-A Startup .......................................................................................................................................................... 5
III-B Operation Checks......................................................................................................................................... 6
III-C Shutdown Procedure .................................................................................................................................... 6
SECTION IV—PREVENTIVE AND CORRECTIVE MAINTENANCE
IV-A Lubrication ................................................................................................................................................... 6
IV-B Stuffing Box.................................................................................................................................................. 6
IV-C Vibration....................................................................................................................................................... 6
IV-D Alignment—Final......................................................................................................................................... 6
IV-E Performance.................................................................................................................................................. 6
SECTION V—DISASSEMBLY AND REASSEMBLY
V-A Disassembly................................................................................................................................................... 7
V-B Inspection and Parts Replacement Guidelines............................................................................................. 7
V-C Reassembly Procedures................................................................................................................................. 7
V-D Additional Details ........................................................................................................................................ 9
SECTION VI—PRODUCT DESCRIPTION
Product Description............................................................................................................. 9,10,11,12,13,14
SECTION VII—TROUBLE SHOOTING
Troubleshooting.......................................................................................................................................... 15
SECTION VIII—ORDERING SPARE PARTS
VIII-A Spare Parts.................................................................................................................................................. 15
VIII-B Instructions for Ordering Spare Parts......................................................................................................... 15
2
SECTION I—GENER AL
LEAVE 3/4" TO11/2" UNDER BEDPLATE FOR GROUT
WEDGES
DAM
WASTE
BEDPLATE
GROUT
LEAVE TOP OF FOUNDATION ROUGH, AND WET BEFORE GROUTING.
CONCRETE FOUNDATION
Introduction
This instruction manual is intended to assist those involved with the installation, operation and maintenance of Eagle Model A100 pumps. It is recommended that this manual be thoroughly reviewed prior to installing or performing any work on the pump or motor.
I-A. Importance of Instructions
The design, material and workmanship incorporated in the construction of Eagle pumps make them capable of giving long, trouble–free service. The life and satisfactory service of any mechanical unit, however, is enhanced and extended by periodic inspection and careful maintenance. This instruction manual was prepared to assist operators in understanding the construction and correct methods of installing, operating, and maintaining these pumps.
Study thoroughly Sections I, II, III, and carefully follow the instructions for installation and operation. Sections IV, V, VI, VII, and VIII are answers to trouble and maintenance questions. Keep this instruction manual handy for reference.
I-B. Special Warnings
Eagle Pump and Compressor will not be liable for any damages or delay caused by failure to comply with the provisions of this instruction manual. This pump is not to be operated at speeds, working pressures, discharge pressures, or temperatures higher than nor used with liquids other than originally intended for, without written permission of Eagle Pump.
Instruction sheets on various components as well as the Instruction Book for the pump are included in the shipment. DO NOT DISCARD!
I-D. Preservation and Storage
Eagle’s normal domestic shipping and storage preparation is suitable for protecting the pump during shipment in covered trucks. It also provides protection during covered storage at the jobsite, and for a short period between installation and start-up. If the pump is to be idle and exposed to the elements for an extended period, either before or after installation, special precautions are required. One approach is to provide special preservatives and wrapping before shipment. However, after installation the protective wrappings will have been removed. Therefore, application of preservatives after installation is considered a good practice.
The driver, coupling, and mechanical seal manufacturers should be contacted for their recommendations on preservation and protection procedures.
I-E. Handling Techniques
Care should be used in moving pumps. Pumps should not be hoisted by eyebolts. These eyebolts are intended for removing the back pull–out assembly for maintenance and inspection. An assembled pump should be hoisted using a sling under suction flange and under rear of bearing frame. Bedplate mounted units should be hoisted using slings under bedplate below both pump and driver.
I-C. Receiving Inspection—Shortages
Care should be taken when unloading pumps. If shipment is not delivered in good order and in accordance with the Bill–of– Lading, note the damage or shortage on both receipt and freight bill. MAKE ANY CLAIMS TO THE TRANSPORTATION COMPANY PROMPTLY.
SECTION II—INSTALLATION
II-A. Location
Pumping unit should be placed as close as practical to the source of supply. Floor space and headroom allotted to the unit must be sufficient for inspection and maintenance. Be sure to allow for crane or hoist service.
II-B. Foundations
1. Grouted—Bedplate mounted units are normally grouted–in on a concrete foundation, which has been poured on a solid footing. This allows a permanent, vibration–absorbing base for the unit. The location and size of foundation bolts are shown on the outline assembly drawings supplied for the unit. Fig. 1 illustrates a typical foundation bolt installation.
2. Flexibly Mounted—Installation and leveling of the optional flexibly mounted bedplate should be carried out in accordance with assembly drawings supplied in the data package for the unit.
Figure 1
3
II-C. Leveling and Grouting of Baseplate Initial Alignment Check
1. Put the unit in place on wedges located at four points as shown in Fig. 2. Some long installations may require additional wedges near center of bedplate.
WEDGES
Figure 2
2. Adjust wedges to level unit (approximately), placing unit between ” and 1” above foundation. Level or plumb suction and discharge flanges. Then, bring the coupling halves into reasonable alignment by adjusting the wedges as needed.
3. Make sure that the baseplate is not distorted and that final accurate coupling alignment can be established within the limits of movement of motor and by shimming motor if necessary.
II-E. Alignment—Preliminary
Alignment of the pump and driver is of extreme importance for trouble–free mechanical operation. Alignment should be obtained by adding or removing shims from under the motor feet. The pump bearing frame foot should never be adjusted to obtain alignment. The proper shimming is installed under the bearing frame foot at the factory on units shipped with bedplates. Changing the pump casing or bearing frame in the field will require a reshimming of the frame foot. The proper number of shims is installed when the pump shaft is level and parallel to the bedplate surface. Proper shimming is achieved by loosening frame foot and tightening casing foot. This should create a gap between the frame foot and bedplate between 0 and .040 inches (1mm). This must be filled with shims and the frame foot retightened. If this procedure is not followed, mechanical problems can result. The final alignment is done after the unit has been run under actual operating conditions. The following are suggested steps for aligning the unit, prior to initial startup.
1. Parallel Alignment: The unit is in parallel misalignment when the shaft axes are parallel, but not concentric. During initial alignment, vertical parallel alignment may be different, due to thermal expansion of the unit at actual operating conditions. The following is a suggested cold setting for motor driven units:
Pumpage Temperature Above Ambient Set Motor Shaft
Ambient .002–.004” low (.05–.10 mm) 100° F. .000–.002” high (.00–.05 mm) 200° F. .004–.006” high (.10–.15 mm) 300° F. .008–.010” high (.20–.25 mm) 400° F. .012–.014” high (.30–.35 mm) 500° F. .016–.018” high (.40–.45 mm)
4. Tighten foundation bolts finger tight. Build dam around foundation and pour grout. Fill to level of grout hole making sure that the areas under the pump and motor feet are filled solid. Allow grout to harden at least 48 hours before further tightening foundation bolts. Tighten pump hold down bolts.
II-D. Piping Practices
Guidelines for piping are given in the “Hydraulic Institute Standards” and should be reviewed prior to pump installation. All piping should be supported independently of, and line up naturally with, the pump flanges. NEVER DRAW PIPING INTO PLACE BY USE OF FORCE AT THE FLANGED CONNECTIONS OF THE PUMP.
Both suction and discharge piping should be as short and direct as possible to minimize friction losses. Foundation, pump and driver hold–down bolts should be tightened prior to connecting suction or discharge piping to the pump.
On units handling corrosives, the piping can be arranged to allow flushing of the pump prior to opening of the unit for servicing. After connecting suction and discharge piping to the pump, rotate pump by hand to be sure that there is no binding.
2. To check the parallel alignment of “spider–insert” couplings, place a straight edge across both hubs at four points, 90° apart (see Fig. 3). To check the parallel alignment of flexible spacer couplings, place a dial indicator on one hub and rotate that hub 360° while taking readings on the outside diameter of the other hub. Alignment occurs when indicator deflection does not exceed .002” T.l.R. (see Fig. 4) of the recommended cold setting in elevation and not more than .002” T.l.R. side to side.
To check angular alignment of a “spider–insert” coupling, use calipers at 90° intervals on the circumference on the outer end of hubs. When caliper measurements are identical, the unit is in angular alignment. The correct gap between the hub and insert will be given in the coupling manufacturer’s instructions supplied for the pump.
To check angular alignment of flexible spacer couplings, place a dial indicator on one shaft hub and rotate the hub 360°. Take readings from the face of the other hub. Alignment is achieved when deflection does not exceed .002” (see Fig. 5).
4
PRIOR TO COUPLING DRIVER TO PUMP, ROTATION OF
OIL LEVEL
OIL LEVEL
SET SCREW
DRIVER SHOULD BE CHECKED! Serious damage can result if pump is rotated in wrong direction. Once motor rotation is checked, connect coupling, following the manufacturer’s instructions. If a coupling guard is furnished with the unit, ensure that it is securely fastened in place.
WEDGES
Figure 3
Figure 4
R O T A T E THIS HUB
Figure 4
SECTION III—OPERATION
III-A. Startup
1. Check List
a. Lubrication—Pump bearings are normally oil lubricated.
(THE BEARINGS ARE NOT LUBRICATED AT THE FACTORY.) These pumps are supplied with an oiler which maintains a constant oil level in the bearing frame. Locate oiler as shown on the outline drawings supplied for the unit. See Fig. 6 for correct adjustment of oiler.
Figure 5
II-F. Stufng Box
1. Packing:
If the pumpage is dirty or hot, it is not suitable to lubricate the packing. An external source must be utilized, unless the bypass is equipped with proper separator, filter, and/or cooling system. This must be piped into the lantern ring connection, also (refer to packing recommendations).
2. Mechanical Seals:
When mechanical seals are supplied, they are installed and adjusted at the factory. They must not run dry or in abrasives. Connect recirculation, flush and/or cooling lines as required, following instructions on the seal print supplied for the unit.
Figure 6
5
Loading...
+ 11 hidden pages